WO2015068840A1 - 負荷制御装置及び負荷制御システム - Google Patents

負荷制御装置及び負荷制御システム Download PDF

Info

Publication number
WO2015068840A1
WO2015068840A1 PCT/JP2014/079729 JP2014079729W WO2015068840A1 WO 2015068840 A1 WO2015068840 A1 WO 2015068840A1 JP 2014079729 W JP2014079729 W JP 2014079729W WO 2015068840 A1 WO2015068840 A1 WO 2015068840A1
Authority
WO
WIPO (PCT)
Prior art keywords
control
load
power
bcp
pattern
Prior art date
Application number
PCT/JP2014/079729
Other languages
English (en)
French (fr)
Inventor
永子 久田
康一 下里
孝雄 野坂
謙一 山崎
沙織 町田
木村 浩二
育郎 駒村
朝妻 智裕
Original Assignee
株式会社東芝
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社東芝 filed Critical 株式会社東芝
Priority to EP14860190.9A priority Critical patent/EP3070801A4/en
Priority to US15/035,686 priority patent/US9991720B2/en
Priority to CN201480061356.4A priority patent/CN105981253A/zh
Publication of WO2015068840A1 publication Critical patent/WO2015068840A1/ja

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J4/00Circuit arrangements for mains or distribution networks not specified as ac or dc
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • H02J2310/12The local stationary network supplying a household or a building
    • H02J2310/14The load or loads being home appliances
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/248UPS systems or standby or emergency generators

Definitions

  • Embodiments of the present invention relate to a load control device and a load control system.
  • BCP control is one such technique.
  • BCP Business Continuity Plan
  • self-generated a private power generator for emergency power supply
  • This is one of the control methods when power is supplied.
  • BCP control is a control for efficiently and maximally using self-generated power, supplying energy to a wide range of loads for a long time, and continuing business.
  • the problem to be solved by the present invention is to provide a load control device and a load control system that can use the generated power more efficiently.
  • the load control device of the embodiment includes a storage unit, a selection unit, and a load control unit.
  • the storage unit can store a plurality of patterns having a plurality of control contents with priorities for a plurality of loads that operate by consuming electric power.
  • the selection unit is configured to select a pattern from the patterns stored in the storage unit.
  • the load control unit is based on the control content of the selected pattern within a range in which the total value of power consumed by the load does not exceed a target power value indicating a value based on power that can be supplied by the generator, The loads are operated in descending order of priority.
  • FIG. 3 is a functional block diagram illustrating a functional configuration of a central control device 400.
  • FIG. It is a figure which shows the specific example of the information which the pattern memory
  • 4 is a flowchart showing a flow of BCP control processing in the load control system 10. It is a figure which shows the characteristic of BCP control in the load control system. It is a figure showing the content of the process of the time of BCP control being started, and the time of level control being performed. It is a figure which shows the specific example in case a BCP control level is not raised on injection conditions.
  • load control device In the load control device and the load control system of the embodiment (hereinafter, the two are collectively referred to simply as “load control device” in the present outline), one or more load control patterns are registered in advance.
  • the load control pattern is information in which a load control content is set for each of a plurality of priorities (BCP control levels).
  • BCP control levels In the load control device, when BCP control is performed, load control according to the load control pattern selected by the operator is executed. Specifically, it is as follows.
  • the control contents are referred to in order from the highest priority.
  • the power consumed when the referenced control content is executed (set power) is compared with the surplus power generated from the home (BCP adjusted power).
  • BCP adjusted power the surplus power generated from the home
  • each load is newly controlled based on the control content.
  • the control based on the control content is not performed. Therefore, it becomes possible to operate in order from the load with the highest priority within the power that can be generated from the house. Therefore, it becomes possible to use the power generated by the house more efficiently.
  • FIG. 1 is a diagram illustrating a system configuration of a load control system 10 according to the embodiment.
  • a communication line for performing monitoring and control is indicated by a broken line
  • a path for supplying power is indicated by a solid line
  • each power system to be controlled is indicated by a one-dot chain line.
  • the load control system 10 of the embodiment is installed for one or a plurality of facilities and buildings.
  • the load control system 10 includes a plurality of power systems 100 (power system 100-1 and power system 100-2), an inter-system bypass circuit breaker 200, a commercial power circuit breaker 300, and a central control device 400.
  • the load control system 10 of the embodiment shown in FIG. 1 includes a power system 100-1 (system 1) and a power system 100-2 (system 2).
  • system 1 power system 1
  • system 100-2 system 2
  • the power system 100 includes a generator 101, a first circuit breaker 102, a second circuit breaker 103, a power panel 104, and a load 105.
  • the generator 101 is a private power generator (self-generated) that generates electric power supplied to the load 105.
  • the first circuit breaker 102 is a circuit breaker for controlling whether or not the electric power generated by the generator 101 is supplied to the power line (bus line) connected to the second circuit breaker 103 and the inter-system bypass circuit breaker 200. is there.
  • the first circuit breaker 102 is configured using a high-pressure circuit breaker such as a vacuum circuit breaker (VCB) or a gas circuit breaker (GCB).
  • the second circuit breaker 103 is a circuit breaker for controlling whether or not the power supplied from the generator 101 via the first circuit breaker 102 is supplied to the power panel 104 and the load 105.
  • the second circuit breaker 103 is configured using a high-pressure circuit breaker such as a vacuum circuit breaker or a gas circuit breaker.
  • the power panel 104 is a device for controlling whether or not power is supplied to each of the one or more loads 105. The operator can control the electric power supplied to the load 105 by operating the power panel 104. The operator's operation may be performed directly or from a remote location.
  • the load 105 is a device that operates by consuming electric power supplied via the power panel 104.
  • the load 105 is, for example, an air conditioner, a heat source facility, an air conditioner, an external air conditioner, a lighting facility, a security facility, a communication facility, a building control facility, an elevator facility, or the like.
  • the load 105 changes its state according to control by a central monitoring device (not shown).
  • a central monitoring device not shown.
  • the load 105 receives control such as power on / off, set temperature, and air volume from the central monitoring apparatus, and operates according to the received control.
  • the load 105 accepts an operation by an operator or a user and operates according to the accepted operation.
  • the number of generators 101, first circuit breakers 102, second circuit breakers 103, power panels 104 and loads 105 provided in the electric power system 100 may be one or plural. Further, other configurations different from the generator 101, the first circuit breaker 102, the second circuit breaker 103, the power panel 104, and the load 105 may be provided for the power system 100.
  • the inter-system bypass circuit breaker 200 is a circuit breaker for interrupting a power line (bus) connecting the plurality of power systems 100.
  • the inter-system bypass circuit breaker 200 is configured using a high-pressure circuit breaker such as a vacuum circuit breaker or a gas circuit breaker, for example.
  • a high-pressure circuit breaker such as a vacuum circuit breaker or a gas circuit breaker, for example.
  • the central controller 400 may open the inter-system bypass circuit breaker 200 as necessary.
  • the commercial power circuit breaker 300 is a circuit breaker for controlling whether or not the power supplied from the commercial power source is supplied to the power line.
  • the commercial power circuit breaker 300 is configured using a high voltage circuit breaker such as a vacuum circuit breaker or a gas circuit breaker.
  • the central control device 400 controls the devices of the plurality of power systems 100 provided in the load control system 10, the inter-system bypass circuit breaker 200, and the commercial power circuit breaker 300.
  • the central control device 400 is configured using an information processing device such as a server device.
  • FIG. 2 is a functional block diagram showing the functional configuration of the central control device 400.
  • the central control device 400 includes an input unit 401, a display unit 402, a pattern control unit 403, a pattern storage unit 404, a communication unit 405, a state monitoring unit 406, a state storage unit 407, a load control unit 408, and a determination unit 409.
  • the pattern control unit 403, the state monitoring unit 406, the load control unit 408, and the determination unit 409 are realized by a CPU (Central Processing Unit) executing a central control program.
  • CPU Central Processing Unit
  • the central control program may be recorded on a computer-readable recording medium.
  • the computer-readable recording medium is, for example, a portable medium such as a flexible disk, a magneto-optical disk, a ROM, a CD-ROM, or a storage device such as a hard disk built in the computer system.
  • the central control program may be transmitted via a telecommunication line.
  • the input unit 401 is configured using an existing input device such as a keyboard, pointing device (mouse, tablet, etc.), button, touch panel, or the like.
  • the input unit 401 is operated by the operator when inputting an operator instruction to the central control device 400.
  • the input unit 401 may be an interface for connecting the input device to the central control device 400. In this case, the input unit 401 inputs an input signal generated in response to an operator input in the input device to the central control device 400.
  • Display unit 402 is an image display device such as a CRT (Cathode Ray Tube) display, a liquid crystal display, or an organic EL (Electro Luminescence) display.
  • the display unit 402 displays text and images.
  • the display unit 402 may be an interface for connecting the image display device to the central control device 400. In this case, the display unit 402 generates a video signal for displaying a text or an image, and outputs the video signal to an image display device connected to the display unit 402.
  • the pattern control unit 403 receives a load control pattern created by the operator in response to an instruction input by the operator operating the input device.
  • the pattern control unit 403 writes the received load control pattern in the pattern storage unit 404.
  • the pattern storage unit 404 is configured using a storage device such as a magnetic hard disk device or a semiconductor storage device.
  • the pattern storage unit 404 stores the load control pattern received by the pattern control unit 403.
  • FIG. 3 is a diagram illustrating a specific example of information stored in the pattern storage unit 404.
  • the pattern storage unit 404 stores the pattern table 41 for each load control pattern. Therefore, the pattern storage unit 404 stores as many pattern tables 41 as the number of load control patterns.
  • One pattern table 41 represents the contents of one load control pattern.
  • a plurality of records 42 are registered in the pattern table 41.
  • the record 42 represents priority order and load control contents.
  • the record 42 has values of number, priority, control target, capacity, exclusion, and total capacity (set power).
  • the number is a number that uniquely indicates a record in one pattern table 41.
  • the priority order represents the priority order (BCP control level) of the load control contents defined in the record 42. The smaller the priority value, the higher the priority, and the higher the priority value, the lower the priority.
  • the control target represents the name of the load 105 to be controlled.
  • capacitance represents the quantity of the electric power consumed by performing the control content defined by the control object.
  • Exclusion is a value indicating whether or not to execute the control content defined in the record 42.
  • the total capacity indicates the total amount of power consumed when all the control contents of the priority order defined in the record 42 (excluding the excluded control contents) are executed.
  • the total capacity of the priority “1” is the total value of the capacity of the number 1 record and the capacity of the number 2 record.
  • the total capacity of the priority “2” has the same value as the capacity of the number 3 record because the number 4 record is set to be excluded.
  • the communication unit 405 is a network interface.
  • the communication unit 405 communicates with, for example, each device of the power system 100 and the inter-system bypass circuit breaker 200.
  • the communication unit 405 receives a value indicating the state of the load 105 (hereinafter referred to as “load state value”) from the load 105 or a sensor (not shown).
  • the communication unit 405 transmits the control signal generated by the load control unit 408 to the first circuit breaker 102, the second circuit breaker 103, the power panel 104, and the load 105 that are controlled by the load control unit 408. .
  • the state monitoring unit 406 monitors the state of each load 105 based on the load state value received by the communication unit 405 during normal control (before a power failure occurs). When the state of the load 105 changes, the state monitoring unit 406 writes the changed load state value in the state storage unit 407. After the power failure occurs, the state monitoring unit 406 does not update the load state value until recovery. Therefore, a load state value representing the state of each load 105 immediately before the power failure occurs is recorded in the state storage unit 407 after the power failure occurs.
  • the state storage unit 407 is configured using a storage device such as a magnetic hard disk device or a semiconductor storage device.
  • the state storage unit 407 stores the load state value written by the state monitoring unit 406.
  • FIG. 4 is a diagram illustrating a specific example of information stored in the state storage unit 407.
  • the state storage unit 407 stores a state information table 71.
  • a plurality of records 72 are registered in the state information table 71.
  • the record 72 has each value of load ID and load state value.
  • the load ID is identification information that uniquely indicates the load 105.
  • the load state value is information representing the state of the load 105 indicated by the load ID of the record 72.
  • the load control unit 408 controls the load 105 based on the load control pattern stored in the pattern storage unit 404 and the determination result by the determination unit 409. For example, the load control unit 408 determines the control content of each load 105 based on the load control pattern, and generates a control signal representing the determined control content. Then, the load control unit 408 transmits a control signal to each load 105 via the communication unit 405.
  • the load control unit 408 may control each load 105 according to the load state value of each load 105 registered in the state information table 71. For example, the load control unit 408 executes control only for the load 105 registered in the state information table 71 as being under control execution among the load control contents defined in the load control pattern. In addition, the load control unit 408 controls the load 105 so that each load 105 does not accept control by another device such as a central monitoring device during the period after the power failure and until recovery (during execution of BCP control). . By such control, the control by the load control unit 408 is disturbed by the control by another device (for example, control with low priority is executed, or the current generated power exceeds the BCP target power). Can be deterred.
  • the determination unit 409 determines whether or not to execute control content with a lower priority. The determination unit 409 outputs the determination result to the load control unit 408.
  • the processing executed by the load control unit 408 includes processing for determining whether or not to start BCP control and processing for determining a system to be excluded from BCP control. Hereinafter, each processing will be described.
  • a condition (control condition) for starting the BCP control is set in advance.
  • the load control unit 408 determines whether the control condition is satisfied.
  • the load control unit 408 starts the BCP control when it is determined that the control condition is satisfied.
  • control conditions the following conditions may be set for each power system 100, for example.
  • the generator 101 is in operation, and the power system 100 is a self-generated power transmission system. -At least one generator 101 that satisfies the operable condition belongs to the power system 100. -An instruction to start BCP control has been executed manually by the operator.
  • a plurality of conditions for indicating that the generator 101 is operating normally without any doubt may be set.
  • a plurality of indices that indicate the state of the generator 101 and a plurality of indices that indicate whether or not the generator 101 has failed may be set as the operable condition.
  • the generator 101 having a condition that does not satisfy at least one of the plurality of conditions set as the operable condition may be determined not to satisfy the operable condition.
  • the load control unit 408 interrupts the BCP control of the power system 100 in which the control condition is not satisfied, when the power system 100 in which the control condition is not satisfied is present while the BCP control is being performed. .
  • the load control unit 408 executes only the control content with the priority “0” in the power system 100 in which the control condition is not satisfied, and executes the control content with the priority lower than “1” and “1”. To stop. Then, the load control unit 408 notifies the operator and the user that the control condition is not satisfied. Note that the set value output need not be controlled. Even if the power system 100 once the control condition is not satisfied, the load control unit 408 does not resume the BCP control for the power system 100 even if the control condition is satisfied later.
  • FIG. 5 is a flowchart showing the flow of BCP control processing in the load control system 10.
  • the BCP control process includes a process mainly performed by an apparatus other than the central control apparatus 400 or an operator. Such processing is represented by a broken-line rectangle in FIG.
  • step S101 The operator of the load control system 10 registers a load control pattern (BCP pattern) in the central control device 400 in advance (step S101).
  • BCP pattern load control pattern
  • step S102 When a power failure occurs in the commercial power source due to the occurrence of a disaster or the like (step S102), all the facilities in the building (full load 105) that are controlled by the load control system 10 are stopped (step S103). Thereafter, the generator 101 of each power system 100 is activated in response to the occurrence of a power failure in the commercial power supply (step S104).
  • the operator confirms the safety of the load 105 installed in the building that is controlled by the load control system 10 (step S105). For example, the operator confirms whether there is no problem even if each load 105 is activated according to a manual set in advance for an accident such as a disaster occurrence (whether a failure has occurred).
  • a load 105 that should not be activated hereinafter referred to as “failure load”
  • the operator performs an operation for excluding the failure load from the control target of the load control system 10.
  • the central controller 400 sets a value of “exclusion” in the record 42 representing the fault load in the pattern table 41 (step S106).
  • step S102 After the occurrence of a power failure (step S102), the operator starts the generator 101 (step S104), confirms the safety of each load 105 in the building (step S105), and excludes fault loads as necessary. (Step S106), the central controller 400 is instructed to start BCP control. At this time, the operator selects one load control pattern from among a plurality of load control patterns registered in advance with respect to the central controller 400. The operator then instructs the central controller 400 on the selected load control pattern. In response to an instruction from the operator, the central controller 400 starts BCP control based on the selected load control pattern (step S107). And each load 105 with which the load control system 10 is equipped operate
  • the power supply to the load 105 depends on the power failure operation pattern on the power receiving / transforming equipment side until the generator 101 is started and the first circuit breaker 102 is turned on again after each second circuit breaker 103 is opened due to a power failure. To do.
  • This power failure operation pattern includes manual start-up by manual operation.
  • the load 105 has not been issued with an abnormal alarm in the central monitoring device or the like, it may be determined that the operation is impossible due to the operator's confirmation work at the site. For this reason, it is desirable to perform an operation for confirming the state of the load 105 on site before the BCP start operation (step S107) is performed.
  • BCP control may be started before some or all of the loads 105 are operated, or BCP control may be started after all of the loads 105 are operated.
  • step S109 processing (steps S109 to S113) from when BCP control is started until it is restored.
  • step S109 the generator 101 is stopped in accordance with the restoration (recovery) of the commercial power supply (step S110).
  • step S110 the 1st circuit breaker 102 is open
  • the operator instructs the central controller 400 to end the BCP control.
  • the central controller 400 ends the BCP control (step S112).
  • the operator performs an operation of restoring the load 105 to a normal operation by operating the load 105 of the field equipment and the central monitoring device (step S113).
  • the central monitoring device is a device that controls one or a plurality of loads 105.
  • the power recovery operation is conditioned by the field equipment and the central monitoring device, and a series of processes related to the BCP control is completed.
  • FIG. 6 is a diagram showing characteristics of BCP control in the load control system 10.
  • the horizontal axis represents time. No power failure has occurred in the commercial power supply until time t1. Therefore, each load 105 in the load control system 10 is operated using electric power supplied from a commercial power source. During this time, the load control system 10 performs normal control.
  • a power failure occurs at the commercial power source at time t1 (FIG. 5: S102).
  • the load control system 10 performs power failure control. Specifically, first, all the facilities (total load 105) in the building which are controlled by the load control system 10 are stopped (FIG. 5: S103). Thereafter, at time t2, the generator 101 is activated, and power can be supplied by the generator 101 (FIG. 5: S104). Further, the operator confirms the safety of the load 105 and excludes the trouble load as necessary (FIG. 5: S105, S106). When the above operation is completed, the power failure control ends at time t3.
  • BCP control is started at time t4 (FIG. 5: S107).
  • BCP control is started, power is first supplied to the emergency disaster prevention load.
  • the emergency disaster prevention load represents the electric power required for the load 105 that needs to be operated with the highest priority in preparation for an emergency out of the loads 105 installed in the building to be controlled by the load control system 10. .
  • the priority order of the emergency disaster prevention load is represented by “0” indicating that the priority is the highest.
  • the central controller 400 determines whether or not to execute the control content with the priority “1”.
  • the central controller 400 compares the power consumed when the control content with the priority “1” is executed (set power) and the surplus power (BCP adjusted power) of the generator 101.
  • the central controller 400 starts control of each load based on the control content with the priority “1”.
  • the central control device 400 performs determination processing in order of priority “2”, “3”,..., And sequentially executes the control contents with priority “19”.
  • the central controller 400 determines whether or not to execute the control content with the priority “20”.
  • the power (set power) consumed when the control content with the priority “20” is executed is higher than the surplus power (BCP adjusted power) of the generator 101. That is, the power consumed when all the control contents from the priority “1” to “20” are executed is higher than the target power (BCP target power) that can be supplied by the generator 101. Therefore, the central controller 400 does not execute the control content with the priority “20”.
  • the commercial power supply recovers (FIG. 5: S109).
  • the generator 101 stops at time t8 (FIG. 5: S110).
  • the central controller 400 opens all the circuit breakers (the circuit breaker connected to the power line of the commercial power supply, the circuit breaker connected to the power line of the generator 101), thereby opening all the loads 105.
  • the power supply to is stopped. With the stop of the power supply, all the loads 105 are stopped (FIG. 5: S111).
  • the operator instructs the central controller 400 to end the BCP control.
  • the central control device 400 sets the priority of the control content to “0”, and the BCP control ends at time t10 (FIG. 5: S112).
  • power recovery control is started at time t11.
  • the operator operates the load 105 of the field equipment and the central monitoring device to restore the load 105 to the normal operation (FIG. 5: S113).
  • each load 105 in the load control system 10 operates normally using power supplied by a commercial power source.
  • FIG. 7 is a diagram showing the contents of processing at the time when the BCP control is started and when the level control is executed. First, each value shown in FIG. 7 will be described.
  • the power that can be generated is the total amount of power that can be generated by the generator 101 that satisfies the control conditions for each system.
  • the power that can be generated is set by the operator. For example, when four generators 101 operate in one system, the power that can be generated by the system is the total value of the power that can be generated by the four generators 101.
  • the currently generated power indicated by a dotted line is the total amount of power generated by the generator 101 that satisfies the control conditions for each system. For example, when four generators 101 are operating in one system, the current generated power of the system is the total value of the generated power of the four generators 101.
  • Currently generated power varies depending on the control content (operation, stop, etc.) of the load 105. In other words, the generated power is the total amount of power supplied to the load 105 (consumed by the load 105) for each system.
  • the BCP target power represents a target value of power that can be supplied by the generator 101.
  • the BCP target power is calculated by the following formula, for example.
  • BCP target power (gW-elW) x dfr / 100)) x ((100-lvr) / 100) (Equation 1)
  • gW represents the power that can be generated
  • elW represents the capacity of the emergency disaster prevention load
  • lvr represents the instantaneous drop rate when the load is started
  • dfr represents the demand rate during BCP control.
  • the input upper limit power is calculated based on the input upper limit power ratio (%) and the BCP target power.
  • the input upper limit power is set according to the number of registered BCP control levels and the total capacity (set power) of each BCP control level. Specifically, the input upper limit power is set in a range that does not exceed the BCP target power when the BCP control level is increased by one (when control with a lower priority is executed).
  • the input upper limit power ratio may be set by an operator.
  • the BCP adjustment power represents power that can be supplied to the load 105 (adjustment power).
  • the BCP adjustment power is calculated by the following formula.
  • BCP adjustment power BCP target power-current generated power (Equation 3)
  • the level setting power is a total value (total capacity) of the load 105 at each BCP control level (for example, 1 to 20) of the BCP control pattern selected by the operator.
  • Level n set power (n is an integer of 0 or more) is a total value of the capacity of the load 105 at the BCP control level n.
  • BCP control is started.
  • the BCP control level when the BCP control is started is “0”. That is, when the BCP control is started, the load control is executed so that only the emergency disaster prevention load operates. Thereafter, the BCP control level is set according to the control cycle (for example, 1 minute) so that the BCP control level is located between the BCP target power and the input upper limit power based on the control pattern selected at the time of starting the BCP control. It is changed repeatedly.
  • the central controller 400 controls the BCP control one higher. Run the level. In this case, the central control device 400 starts control of the load 105 according to the control target of the newly executed BCP control level. The central controller 400 increases the BCP control level one by one within the control cycle.
  • FIG. 8 is a diagram showing a specific example in the case where the BCP control level is not raised under the input conditions.
  • the central controller 400 determines that the BCP control level Do not raise.
  • FIG. 9 is a diagram showing a specific example of the blocking condition.
  • the central controller 400 lowers the BCP control level.
  • the central controller 400 does not lower the BCP control level one by one, but lowers the current generated power at a time to the BCP control level at which the generated power is lower than the BCP target power.
  • the BCP control level for m is lowered at a time. If the control condition is not satisfied, the central controller 400 lowers the BCP control level to “0” at once.
  • the central controller 400 When a load control different from the currently executed load control pattern (hereinafter referred to as “user control”) is executed by an operator or user operation, the central controller 400 is consumed by the user control.
  • the current power generation including the capacity of the power to be calculated is calculated.
  • the central controller 400 reduces the current generated power to be equal to or lower than the BCP target power by stopping other controls while continuing the user control. Specifically, it is as follows.
  • the central control device 400 When the central control device 400 lowers the BCP control level as shown in FIG. 9, the control contents of the BCP control level (the BCP control levels n to (nm) in FIG. 9) are stopped. It is determined whether or not the same control as the user control is included in the control target set in (1). If it is included, the current generated power in a state in which execution of the same control as the user control is maintained is estimated. When the estimated value of the current generated power is lower than the BCP target power, the central controller 400 reduces the BCP control level to (nm). On the other hand, when the estimated value of the current generated power is higher than the BCP target power, central controller 400 estimates the current generated power when the BCP control level is lowered to (n ⁇ (m + 1)). The central control device 400 repeats such processing to reduce the current generated power to be equal to or less than the BCP target power while maintaining execution of user control.
  • FIG. 10 is a diagram illustrating a specific example of the BCP control screen displayed on the display unit 402.
  • the BCP control screen is a screen that displays the set power of each priority order of the load control pattern set on this screen, the control status, and the like.
  • the BCP control state display area 501 is an area for displaying the BCP control state.
  • the BCP control state display area 501 displays values of each item of BCP control condition establishment, during BCP control, power that can be generated, BCP target power, input upper limit power, current generated power, BCP adjustment power, and BCP and subsequent requests. .
  • the satisfaction of the BCP control condition indicates whether or not the BCP control condition is satisfied. If it is established, a circle is displayed, and if it is not established, a cross is displayed. During BCP control, it indicates whether or not BCP control is being performed. A circle is displayed when the BCP control is being performed, and a cross is displayed when the BCP control is not being performed.
  • the BCP control pattern represents the current in-control pattern.
  • the power that can be generated represents the total value of the power generated by the normal generator 101 that satisfies the operable condition.
  • the BCP target power displays the BCP target power that can be supplied by the generator 101.
  • the input upper limit power indicates the input upper limit power calculated by the input upper limit ratio registered in the generator setting with respect to the target power.
  • Current generated power displays current generated power (current generated power).
  • the BCP adjustment power displays a value obtained by subtracting the current generated power from the BCP target power.
  • the BCP transfer request displays the result of the transfer command for the equipment at the start and end of control.
  • the level display area 502 displays the BCP control level implemented in each power system 100. For the power system 100 in which the control is suspended because the condition is not satisfied after the BCP control is started, “0” is displayed as the value of the BCP control level, and “suspended” is displayed in the lower part.
  • the pattern set power display area 503 the pattern number, pattern name, and set power of the currently selected BCP control pattern are displayed.
  • the set power for each pattern represents the accumulated capacity.
  • the current BCP control level is any one of 1 to 20, a predetermined symbol (black triangle in the example of FIG. 10) is displayed to the left of the corresponding BCP control level.
  • the control setting button 504 is a button for displaying a control setting dialog.
  • the pattern selection button 505 is a button for displaying a pattern selection dialog.
  • the pattern setting button 506 is a button for displaying a pattern setting dialog.
  • the control condition setting button 507 is a button for displaying a control condition setting dialog.
  • the generator setting button 508 is a button for displaying a generator setting dialog.
  • the CSV saving button 509 is a button for displaying a CSV saving dialog.
  • the print setting button 510 is a button for displaying a print setting dialog.
  • the control mode display area 511 displays the contents of the control currently being performed (eg, normal power failure control, BCP control, power recovery control, etc.).
  • FIG. 11 is a diagram illustrating a specific example of a pattern setting dialog displayed on the display unit 402.
  • the operator can register the contents of each load control pattern.
  • Information registered in the pattern table 41 is displayed in the pattern setting display area 601.
  • items such as a state, a set value, and a change status are displayed in FIG.
  • the level represents a BCP control level number.
  • the load name represents the name of the control target point.
  • As for the state a black circle is displayed when the control target point controls the state (ON / OFF or the like).
  • the set value represents the load type selected at the time of registering the control target point for outputting the set value.
  • the capacity indicates the capacity of the control target point. Exclusion indicates whether the control target point is excluded.
  • As for the change status only the pattern selected during control displays the change status and the control output status.
  • the total represents the total load capacity registered in each BCP control level.
  • the pattern selection area 602 displays the value of the load control pattern currently displayed in the pattern setting display area 601.
  • the operator can change the load control pattern displayed in the pattern setting display area 601 by operating a button displaying “ ⁇ ” or “>”.
  • the new registration button 603 is a button for displaying a pattern information setting dialog.
  • a change button 604 is a button for displaying an information setting dialog for the BCP control level of the selected control target point.
  • the delete button 605 is a button for deleting the registration of the selected control target point.
  • a cancel button 606 is a button for closing the dialog.
  • FIG. 12 is a diagram illustrating a specific example of a pattern selection dialog displayed on the display unit 402.
  • the pattern selection dialog is a display for the operator to select a load control pattern number for each system.
  • the pattern number display area 701 the number of the load control pattern for each system is displayed.
  • the pattern number selection dialog is displayed. The operator can change the number selected in the pattern number selection dialog.
  • the setting button 702 is a button for reflecting the setting and closing the pattern selection dialog.
  • a cancel button 703 is a button for discarding the setting and closing the pattern selection dialog.
  • the control contents are executed in order from the highest priority based on the load control pattern selected according to the situation by the operator. Therefore, it becomes possible to operate in order from the load with the highest priority within the electric power that can be generated by the generator 101 (in-house). Therefore, it becomes possible to use the power generated by the house more efficiently.
  • the load 105 can be excluded from the control target.
  • the power required for the excluded control is not included in the set power, and the BCP control is executed. Therefore, it is possible to divert the power allocated to the load 105 that does not operate normally to control other loads 105 that operate normally, and to use the generated power more efficiently. It becomes possible.
  • the content registered in the control pattern may not be changed while the BCP control is being performed.
  • lighting start / stop, air conditioning start / stop, and air conditioning temperature setting are listed as specific examples of the control target.
  • the specific example of the control target need not be limited to the above-described example.
  • the load 105 is an air conditioner
  • the following information may be set as a control target. Power on or off. Operation type (for example, cooling, heating, dry, air blowing). Air volume (for example, weak, medium, strong). Set temperature (for example, 28 degrees, 30 degrees).
  • the load 105 is a lighting facility, the following information may be set as a control target.
  • the central control device 400 does not necessarily have to be implemented as a single information processing device.
  • a plurality of information processing apparatuses that can communicate with each other may be configured to cooperate to realize the function of the central control apparatus 400.
  • the central control device 400 and the central monitoring device described above may be configured as a single information processing device.
  • the pattern table 41 shown in FIG. 3 is merely an example and may be configured as a table having other values.
  • values such as a state, a set value, and a change status may be registered in the pattern table 41 in addition to the number, priority, control target, capacity, exclusion, and total capacity. It should be noted that the values such as the status value, the set value, and the change status are the same as the values having the same name shown in the screen of FIG.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Stand-By Power Supply Arrangements (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

 より効率的に自家発の発電電力を利用できる負荷制御装置及び負荷制御システムを提供することである。 実施形態の負荷制御装置は、記憶部、選択部及び負荷制御部を備える。記憶部は、電力を消費して動作する複数の負荷に対する、優先順位がつけられた複数の制御内容を有するパターンを複数記憶できる。選択部は、前記記憶部に記憶された前記パターンからパターンを選択するための構成である。負荷制御部は、前記負荷によって消費される電力の合計値が、発電機によって供給可能な電力に基づいた値を示す目標電力値を上回らない範囲で、選択された前記パターンの制御内容に基づき、前記優先順位が高い順に前記負荷を動作させる。

Description

負荷制御装置及び負荷制御システム
 本発明の実施形態は、負荷制御装置及び負荷制御システムに関する。
 従来から、停電時に負荷に対して給電を安定して継続するための技術が提案されている(例えば、特許文献1参照。)。BCP制御は、このような技術の1つである。
 BCP(Business Continuity Plan)制御とは、停電などの原因で電力会社からの電力の供給が停止し、非常用電源供給用の自家用発電機(以下、「自家発」という。)から複数の負荷に対して給電を行う際の制御方法の一つである。BCP制御は、自家発の発電電力を効率かつ最大限に利用し、広範囲の負荷に対して長時間エネルギーを供給し、事業の継続を図るための制御である。
特開平9-285016号公報
 しかしながら、BCP制御では、未だ効率化の余地が残っており、より効率的な電力の運用技術が要求されていた。
 本発明が解決しようとする課題は、より効率的に自家発の発電電力を利用できる負荷制御装置及び負荷制御システムを提供することである。
 実施形態の負荷制御装置は、記憶部、選択部及び負荷制御部を備える。記憶部は、電力を消費して動作する複数の負荷に対する、優先順位がつけられた複数の制御内容を有するパターンを複数記憶できる。選択部は、前記記憶部に記憶された前記パターンからパターンを選択するための構成である。負荷制御部は、前記負荷によって消費される電力の合計値が、発電機によって供給可能な電力に基づいた値を示す目標電力値を上回らない範囲で、選択された前記パターンの制御内容に基づき、前記優先順位が高い順に前記負荷を動作させる。
実施形態の負荷制御システム10のシステム構成を示す図である。 中央制御装置400の機能構成を表す機能ブロック図である。 パターン記憶部404が記憶する情報の具体例を示す図である。 状態記憶部407が記憶する情報の具体例を示す図である。 負荷制御システム10におけるBCP制御の処理の流れを表すフローチャートである。 負荷制御システム10におけるBCP制御の特徴を示す図である。 BCP制御が開始される時点と、レベル制御が実行される時点と、の処理の内容を表す図である。 投入条件においてBCP制御レベルを上げない場合の具体例を示す図である。 遮断条件の具体例を示す図である。 表示部402が表示するBCP制御画面の具体例を示す図である。 表示部402が表示するパターン設定ダイアログの具体例を示す図である。 表示部402が表示するパターン選択ダイアログの具体例を示す図である。
 [概略]
 実施形態の負荷制御装置及び負荷制御システム(以下、本概略においては2つをまとめて単に「負荷制御装置」という。)では、予め1又は複数の負荷制御パターンが登録される。負荷制御パターンは、複数の優先順位(BCP制御レベル)毎に負荷の制御内容が設定された情報である。負荷制御装置では、BCP制御が行われる際に、オペレータによって選択された負荷制御パターンにしたがった負荷制御が実行される。具体的には以下のとおりである。
 負荷制御装置では、高い優先順位の制御内容から順に参照される。参照されている制御内容を実行した際に消費される電力(設定電力)と、自家発の余剰電力(BCP調整電力)とが比較される。自家発の余剰電力よりも、消費される電力の方が小さい場合には、その制御内容に基づいて新たに各負荷が制御される。一方、自家発の余剰電力よりも、消費される電力の方が大きい場合には、その制御内容に基づいた制御が行われない。そのため、自家発が発電可能な電力内で、優先順位の高い負荷から順に稼働させることが可能となる。したがって、より効率的に自家発の発電電力を利用することが可能となる。
 以下、実施形態の負荷制御装置及び負荷制御システムについて詳細に説明する。
 [詳細]
 図1は、実施形態の負荷制御システム10のシステム構成を示す図である。図1において、監視及び制御を行うための通信線を破線で示し、電力を供給する経路を実線で示し、制御対象となる各電力系統を一点鎖線で示す。実施形態の負荷制御システム10は、1又は複数の設備や建物に対して設置される。負荷制御システム10は、複数の電力系統100(電力系統100-1,電力系統100-2)、系統間バイパス用遮断器200、商用電源遮断器300及び中央制御装置400を備える。図1に示される実施形態の負荷制御システム10は、電力系統100-1(系統1)と、電力系統100-2(系統2)とを備える。以下、電力系統100-1及び電力系統100-2に共通する事項について説明する。
 電力系統100は、発電機101、第一遮断器102、第二遮断器103、動力盤104及び負荷105を備える。
 発電機101は、負荷105に対して供給される電力を発電する自家用発電機(自家発)である。
 第一遮断器102は、発電機101によって発電された電力を第二遮断器103及び系統間バイパス用遮断器200に接続された電力線(母線)へ供給するか否か制御するための遮断器である。第一遮断器102は、例えば真空遮断器(Vacuum Circuit Breaker, VCB)や、ガス遮断器(Gas Circuit Breaker, GCB)等の高圧用遮断器を用いて構成される。
 第二遮断器103は、第一遮断器102を介して発電機101から供給される電力を動力盤104及び負荷105に対して供給するか否か制御するための遮断器である。第二遮断器103は、例えば真空遮断器や、ガス遮断器等の高圧用遮断器を用いて構成される。
 動力盤104は、1又は複数の負荷105毎に電力を供給するか否か制御するための装置である。オペレータは、動力盤104を操作することによって、負荷105に供給される電力を制御することが可能である。オペレータの操作は、直接行われてもよいし、遠隔地から行われてもよい。
 負荷105は、動力盤104を介して供給される電力を消費することによって動作する装置である。負荷105は、例えば空調機器、熱源設備、空調機、外調機、照明設備、セキュリティ設備、通信設備、ビル制御設備、エレベーター設備などの機器である。負荷105は、不図示の中央監視装置による制御に応じて状態を変化する。例えば負荷105が空調機である場合、負荷105は、中央監視装置から電源のオン又はオフ、設定温度、風量などの制御を受け付け、受け付けられた制御に応じて動作する。また、負荷105は、オペレータやユーザによる操作を受け付け、受け付けられた操作に応じて動作する。
 電力系統100に設けられる発電機101、第一遮断器102、第二遮断器103、動力盤104及び負荷105の数は、それぞれ1つであってもよいし複数であっても良い。また、電力系統100に対し、発電機101、第一遮断器102、第二遮断器103、動力盤104及び負荷105とは異なる他の構成が設けられてもよい。
 系統間バイパス用遮断器200は、複数の電力系統100を接続する電力線(母線)を遮断するための遮断器である。系統間バイパス用遮断器200は、例えば真空遮断器や、ガス遮断器等の高圧用遮断器を用いて構成される。系統間バイパス用遮断器200は、例えば商用電源による電力供給が行われている場合には、各電力系統100に商用電源による電力が伝わるように閉じる。一方、発電機101による電力供給が行われる場合には、中央制御装置400は、必要に応じて系統間バイパス用遮断器200を開いてもよい。
 商用電源遮断器300は、商用電源から供給される電力を電力線に対して供給するか否か制御するための遮断器である。商用電源遮断器300は、例えば真空遮断器や、ガス遮断器等の高圧用遮断器を用いて構成される。
 中央制御装置400は、負荷制御システム10に設けられた複数の電力系統100の装置、系統間バイパス用遮断器200及び商用電源遮断器300を制御する。中央制御装置400は、例えばサーバ装置などの情報処理装置を用いて構成される。
 図2は、中央制御装置400の機能構成を表す機能ブロック図である。中央制御装置400は、入力部401、表示部402、パターン制御部403、パターン記憶部404、通信部405、状態監視部406、状態記憶部407、負荷制御部408及び判定部409を備える。パターン制御部403、状態監視部406、負荷制御部408及び判定部409は、CPU(Central Processing Unit)が中央制御プログラムを実行することによって実現される。なお、パターン制御部403、状態監視部406、負荷制御部408及び判定部409の全て又は一部は、ASIC(Application Specific Integrated Circuit)やPLD(Programmable Logic Device)やFPGA(Field Programmable Gate Array)等のハードウェアを用いて実現されてもよい。中央制御プログラムは、コンピュータ読み取り可能な記録媒体に記録されてもよい。コンピュータ読み取り可能な記録媒体とは、例えばフレキシブルディスク、光磁気ディスク、ROM、CD-ROM等の可搬媒体、コンピュータシステムに内蔵されるハードディスク等の記憶装置である。中央制御プログラムは、電気通信回線を介して送信されてもよい。
 入力部401は、キーボード、ポインティングデバイス(マウス、タブレット等)、ボタン、タッチパネル等の既存の入力装置を用いて構成される。入力部401は、オペレータの指示を中央制御装置400に入力する際にオペレータによって操作される。入力部401は、入力装置を中央制御装置400に接続するためのインタフェースであっても良い。この場合、入力部401は、入力装置においてオペレータの入力に応じ生成された入力信号を中央制御装置400に入力する。
 表示部402は、CRT(Cathode Ray Tube)ディスプレイ、液晶ディスプレイ、有機EL(Electro Luminescence)ディスプレイ等の画像表示装置である。表示部402は、テキストや画像を表示する。表示部402は、画像表示装置を中央制御装置400に接続するためのインタフェースであっても良い。この場合、表示部402は、テキストや画像を表示するための映像信号を生成し、自身に接続されている画像表示装置に映像信号を出力する。
 パターン制御部403は、オペレータが入力装置を操作して入力した指示に応じて、オペレータによって作成された負荷制御パターンを受け付ける。パターン制御部403は、受け付けた負荷制御パターンをパターン記憶部404に書き込む。
 パターン記憶部404は、磁気ハードディスク装置や半導体記憶装置などの記憶装置を用いて構成される。パターン記憶部404は、パターン制御部403によって受け付けられた負荷制御パターンを記憶する。
 図3は、パターン記憶部404が記憶する情報の具体例を示す図である。パターン記憶部404は、負荷制御パターン毎に、パターンテーブル41を記憶する。そのため、パターン記憶部404は、負荷制御パターンの数だけパターンテーブル41を記憶する。1つのパターンテーブル41は、1つの負荷制御パターンの内容を表す。
 パターンテーブル41には、複数のレコード42が登録されている。レコード42は、優先順位と負荷の制御内容とを表す。レコード42は、ナンバー、優先順位、制御対象、容量、除外、合計容量(設定電力)の各値を有する。
 ナンバーは、1つのパターンテーブル41内で一意にレコードを示す番号である。
 優先順位は、そのレコード42に定義されている負荷の制御内容の優先順位(BCP制御レベル)を表す。優先順位の値は、小さいほど高い優先度を表し、大きいほど低い優先度を表す。
 制御対象は、制御される負荷105の名称を表す。
 容量は、制御対象に定義された制御内容を実行することによって消費する電力の量を表す。
 除外は、そのレコード42に定義されている制御内容を実行するか否かを意味する値である。除外の値として“除外”が設定されている場合、そのレコード42に定義されている制御内容は実行されない。
 合計容量は、そのレコード42に定義されている優先順位の全ての制御内容(除外されている制御内容を除く)を実行した場合に消費する電力の合計量を示す。例えば、優先順位“1”の合計容量は、ナンバー1のレコードの容量と、ナンバー2のレコードの容量との合計値である。例えば、優先順位“2”の合計容量は、ナンバー4のレコードが除外に設定されているため、ナンバー3のレコードの容量と同値である。
 図2に戻って中央制御装置400の説明を続ける。通信部405は、ネットワークインタフェースである。通信部405は、例えば電力系統100の各装置や系統間バイパス用遮断器200と通信する。例えば、通信部405は、負荷105の状態を示す値(以下、「負荷状態値」という。)を、負荷105や不図示のセンサーから受信する。また、通信部405は、負荷制御部408によって生成された制御信号を、負荷制御部408の制御対象となった第一遮断器102、第二遮断器103、動力盤104、負荷105へ送信する。
 状態監視部406は、通常の制御が行われている間(停電が生じる前まで)に通信部405によって受信された負荷状態値に基づいて、各負荷105の状態を監視する。状態監視部406は、負荷105の状態に変化が生じた場合、変化後の負荷状態値を状態記憶部407に書き込む。状態監視部406は、停電が生じた後は、復旧するまでの間は、負荷状態値の更新を行わない。そのため、停電が生じた後の状態記憶部407には、停電が生じる直前の各負荷105の状態を表す負荷状態値が記録されている。
 状態記憶部407は、磁気ハードディスク装置や半導体記憶装置などの記憶装置を用いて構成される。状態記憶部407は、状態監視部406によって書き込まれる負荷状態値を記憶する。
 図4は、状態記憶部407が記憶する情報の具体例を示す図である。状態記憶部407は、状態情報テーブル71を記憶する。
 状態情報テーブル71には、複数のレコード72が登録されている。レコード72は、負荷ID及び負荷状態値の各値を有する。負荷IDは、負荷105を一意に示す識別情報である。負荷状態値は、そのレコード72の負荷IDが示す負荷105の状態を表す情報である。
 図2に戻って中央制御装置400の説明を続ける。負荷制御部408は、パターン記憶部404に記憶されている負荷制御パターンと、判定部409による判定結果と、に基づいて負荷105を制御する。
 例えば、負荷制御部408は、負荷制御パターンに基づいて各負荷105の制御内容を決定し、決定された制御内容を表す制御信号を生成する。そして、負荷制御部408は、通信部405を介して各負荷105に制御信号を送信する。
 負荷制御部408は、状態情報テーブル71に登録されている各負荷105の負荷状態値に応じて、各負荷105を制御してもよい。例えば、負荷制御部408は、負荷制御パターンにおいて定義されている負荷の制御内容のうち、状態情報テーブル71に制御実行中であったことが登録されている負荷105についてのみ、制御を実行する。
 また、負荷制御部408は、停電後であって復旧するまでの間(BCP制御実行中の間)は、各負荷105が中央監視装置等の他の装置による制御を受け付けないように負荷105を制御する。このような制御により、負荷制御部408による制御が、他の装置による制御によって乱されてしまうこと(例えば、優先順位の低い制御が実行されてしまうことや、現在発電電力がBCP目標電力を超えてしまうこと)を抑止できる。
 判定部409は、より低い優先順位の制御内容を実行すべきか否か判定する。判定部409は、判定結果を負荷制御部408に出力する。
 次に、負荷制御部408が実行する処理について詳細に説明する。負荷制御部408が実行する処理には、BCP制御を開始するか否かを判定する処理、BCP制御の対象外にする系統を判定する処理が含まれる。以下、それぞれの処理について説明する。
 まず、BCP制御を開始するか否かを判定する処理について説明する。負荷制御部408には、BCP制御を開始する条件(制御条件)が予め設定されている。負荷制御部408は、制御条件が満たされたか否か判定する。負荷制御部408は、制御条件が満たされたと判定した場合に、BCP制御を開始する。
 制御条件として、例えば電力系統100毎に以下のような条件が設定されてもよい。
・発電機101が運転中であり、且つ、その電力系統100が自家発としての送電系統であること。
・動作可能条件を満たした発電機101が1台以上その電力系統100に属していること。
・オペレータの手動によりBCP制御の開始の指示が実行済みであること。
 発電機101の動作可能条件には、発電機101が正常に、故障の疑いなく動作していることを示すための複数の条件が設定されてもよい。例えば、発電機101の状態を表す複数の指標や、発電機101が故障しているか否かを表す複数の指標が動作可能条件として設定されてもよい。例えば、動作可能条件に設定されている複数の条件のうち、1つでも満たされていない条件が存在する発電機101は、動作可能条件を満たしていないと判定されてもよい。
 次に、BCP制御の対象外にする系統を判定する処理について説明する。負荷制御部408は、BCP制御が実行されている最中に、上記の制御条件が不成立となった電力系統100が存在する場合、制御条件が不成立となった電力系統100のBCP制御を中断する。この場合、負荷制御部408は、制御条件が不成立となった電力系統100において、優先順位“0”の制御内容のみを実行し、優先順位が“1”及び“1”より低い制御内容の実行を停止する。そして、負荷制御部408は、制御条件が不成立となったことをオペレータやユーザに報知する。なお、設定値出力については制御が行われなくてもよい。
 一度制御条件が不成立となった電力系統100が後に制御条件を満たしたとしても、負荷制御部408は、その電力系統100に対してBCP制御を再開しない。
 図5は、負荷制御システム10におけるBCP制御の処理の流れを表すフローチャートである。なお、BCP制御の処理においては、中央制御装置400以外の装置又はオペレータが主体となる処理も含まれている。このような処理については、図5において破線の矩形にて表す。
 まず、BCP制御が開始されるまでの処理(ステップS101~S108)について説明する。
 負荷制御システム10のオペレータは、負荷制御パターン(BCPパターン)を事前に中央制御装置400に対して登録する(ステップS101)。災害の発生などに起因して商用電源において停電が発生すると(ステップS102)、負荷制御システム10の制御対象となっている建物内の全設備(全負荷105)が停止する(ステップS103)。その後、商用電源に停電が発生したことに応じて各電力系統100の発電機101が起動する(ステップS104)。
 オペレータは、負荷制御システム10の制御対象となっている建物内に設置された負荷105について、安全確認を行う(ステップS105)。例えば、オペレータは、災害発生などのアクシデントに対して予め設定されているマニュアルにしたがって、各負荷105を起動させても問題が無いか(障害が生じていないか)について確認作業を行う。起動させるべきではない負荷105(以下、「障害負荷」という。)の存在が確認された場合、オペレータは、障害負荷を負荷制御システム10の制御対象から除外するための操作を行う。この操作に応じて、中央制御装置400は、パターンテーブル41の障害負荷を表すレコード42に、“除外”の値を設定する(ステップS106)。
 オペレータは、停電の発生後(ステップS102)、発電機101が起動し(ステップS104)、建物内の各負荷105の安全が確認され(ステップS105)、必要に応じて障害負荷の除外が行われた後(ステップS106)、中央制御装置400に対してBCP制御の開始を指示する。この際、オペレータは、中央制御装置400に対して予め登録されている複数の負荷制御パターンの中から、1つの負荷制御パターンを選択する。そして、オペレータは、選択された負荷制御パターンを中央制御装置400に対して指示する。オペレータによる指示に応じて、中央制御装置400は、選択された負荷制御パターンに基づいたBCP制御を開始する(ステップS107)。そして、負荷制御システム10に備えられている各負荷105は、中央制御装置400によるBCP制御に応じて動作する(ステップS108)。
 負荷105への電源供給は、停電による各第二遮断器103の開放後、発電機101が起動し各第一遮断器102が再投入されるまでは、受変電設備側の停電動作パターンに依存する。この停電動作パターンには、手動による自家発起動も含まれる。また、中央監視装置等において異常警報が発報していない負荷105であっても、現地におけるオペレータの確認作業により運転不可と判断されることがあり得る。そのため、BCP開始操作(ステップS107)が行われる前に、負荷105の状態を現地にて確認する作業が行われることが望ましい。ただし、一部又は全部の負荷105が稼働する前にBCP制御が開始されてもよいし、全ての負荷105が稼働した後にBCP制御が開始されてもよい。
 次に、BCP制御が開始されてから復旧するまでの処理(ステップS109~S113)について説明する。
 BCP制御が開始された後に、商用電源による電力の供給が復旧すると(ステップS109)、商用電源の復旧(復電)に応じて発電機101が停止する(ステップS110)。その後、第一遮断器102が開放され、全ての負荷105が停止する(ステップS111)。オペレータは、中央制御装置400に対してBCP制御の終了を指示する。オペレータによる指示に応じて、中央制御装置400は、BCP制御を終了する(ステップS112)。その後、オペレータは、現場設備の負荷105や中央監視装置を操作することによって、負荷105を通常通りの動作に復旧させる作業を行う(ステップS113)。中央監視装置は、1又は複数の負荷105を制御する装置である。この後、現場設備及び中央監視装置によって条件付けされた復電動作となり、BCP制御に関連する一連の処理が終了する。
 図6は、負荷制御システム10におけるBCP制御の特徴を示す図である。図6において、横軸は時間を表す。時刻t1までの間は、商用電源において停電は生じていない。そのため、負荷制御システム10における各負荷105は、商用電源によって供給される電力を用いて動作している。この間は、負荷制御システム10は通常制御を行っている。
 時刻t1に商用電源において停電が生じる(図5:S102)。商用電源において停電が生じると、負荷制御システム10は、停電制御を行う。具体的には、まず、負荷制御システム10の制御対象となっている建物内の全設備(全負荷105)が停止する(図5:S103)。その後、時刻t2において、発電機101が起動し、発電機101による給電が可能な状態になる(図5:S104)。また、オペレータは、負荷105の安全確認を行い、必要に応じて障害負荷を除外する(図5:S105,S106)。以上の作業が完了すると、時刻t3において停電制御が終了する。
 オペレータが中央制御装置400に対してBCP制御の開始を指示すると、時刻t4においてBCP制御が開始される(図5:S107)。BCP制御が開始されると、まず非常用防災負荷に対して電力が供給される。非常用防災負荷とは、負荷制御システム10の制御対象となっている建物内に設置された負荷105のうち、非常時に備えて最優先で稼働させておく必要のある負荷105に要する電力を表す。図6において、非常用防災負荷の優先順位は、優先度が最も高いことを示す“0”で表されている。
 次に、時刻t5において、中央制御装置400は、優先順位が“1”の制御内容を実行するか否か判定する。中央制御装置400は、優先順位が“1”の制御内容を実行した際に消費される電力(設定電力)と、発電機101の余剰電力(BCP調整電力)とを比較する。発電機101の余剰電力よりも消費される電力の方が小さい場合、中央制御装置400は、優先順位が“1”の制御内容に基づいて各負荷の制御を開始する。中央制御装置400は、優先順位“2”、“3”、・・・と順に判定処理を行い、優先順位が“19”の制御内容まで順に実行する。
 次に、時刻t6において、中央制御装置400は、優先順位“20”の制御内容を実行するか否か判定する。優先順位が“20”の制御内容を実行した際に消費される電力(設定電力)は、発電機101の余剰電力(BCP調整電力)よりも高い。すなわち、優先順位“1”から“20”までの制御内容を全て実行した際に消費される電力は、発電機101で供給可能な目標電力(BCP目標電力)よりも高い。そのため、中央制御装置400は、優先順位“20”の制御内容を実行しない。
 時刻t7において、商用電源が復電する(図5:S109)。商用電源の復電に応じて、時刻t8に発電機101が停止する(図5:S110)。その後、時刻t9において、中央制御装置400は、全ての遮断器(商用電源の電力線に接続された遮断器、発電機101の電力線に接続された遮断器)を開放することによって、全ての負荷105に対する電力の供給を停止する。電力の供給の停止に伴い、全ての負荷105が停止する(図5:S111)。
 次に、時刻t9において、オペレータが中央制御装置400に対してBCP制御の終了を指示する。オペレータによる指示に応じて、中央制御装置400は、制御内容の優先順位を“0”に設定し、時刻t10においてBCP制御が終了する(図5:S112)。
 その後、時刻t11に復電制御が開始される。復電制御において、オペレータは、現場設備の負荷105や中央監視装置を操作することによって、負荷105を通常通りの動作に復旧させる作業を行う(図5:S113)。時刻t12以降は、負荷制御システム10における各負荷105は、商用電源によって供給される電力を用いて通常通り動作する。
 図7は、BCP制御が開始される時点と、レベル制御が実行される時点と、の処理の内容を表す図である。まず、図7に示される各値について説明する。
 発電可能電力は、制御条件を満たす発電機101によって発電可能な電力の系統毎の総量である。発電可能電力は、オペレータによって設定される。例えば、1つの系統で4台の発電機101が稼働する場合、その系統の発電可能電力は、4台の発電機101が発電可能な電力の合計値となる。
 点線で示される現在発電電力は、制御条件を満たす発電機101によって発電されている電力の系統毎の総量である。例えば、1つの系統で4台の発電機101が稼働している場合、その系統の現在発電電力は4台の発電機101の発電電力の合計値となる。現在発電電力は、負荷105の制御内容(稼働、停止など)に応じて変化する。いいかえると、現在発電電力は、負荷105に対して供給されている(負荷105によって消費されている)電力の系統毎の総量である。
 BCP目標電力は、発電機101によって供給可能とする電力の目標値を表す。BCP目標電力は、例えば以下の式によって算出される。
 BCP目標電力=(gW-elW)×dfr/100))×((100-lvr)/100)・・・(式1)
 式1において、gWは発電可能電力を示し、elWは非常用防災負荷の容量を示し、lvrは負荷起動時の瞬低率を示し、dfrはBCP制御時の需要率を示す。
 投入上限電力は、投入上限電力比率(%)とBCP目標電力とに基づいて算出される。投入上限電力は、登録されるBCP制御レベルの数と、各BCP制御レベルの合計容量(設定電力)と、に応じて設定される。具体的には、投入上限電力は、BCP制御レベルが1つ上がる場合(1つ低い優先順位の制御が実行される場合)にBCP目標電力を超過しない範囲で設定される。投入上限電力は、例えば以下の式によって算出される。
 投入上限電力=BCP目標電力×投入上限電力比率・・・(式2)
 現在発電電力が投入上限電力より低く、投入条件を満たしていた場合、BCP制御レベルを1つ上げる処理(1つ低い優先順位の制御を実行する処理)が行われる。なお、投入上限電力比率は、オペレータによって設定されてもよい。
 BCP調整電力は、負荷105に供給可能な電力(調整電力)を表す。BCP調整電力は、以下の式によって算出される。
 BCP調整電力=BCP目標電力-現在発電電力・・・(式3)
 レベル設定電力は、オペレータによって選択されたBCP制御パターンの各BCP制御レベル(例えば1~20)における負荷105の容量の合計値(合計容量)である。レベルn設定電力(nは0以上の整数)は、BCP制御レベルnにおける負荷105の容量の合計値である。
 次に、BCP制御の流れについて説明する。
 BCP制御の制御条件が成立すると、BCP制御が開始される。BCP制御が開始された時点のBCP制御レベルは“0”である。すなわち、BCP制御が開始された時点では、非常用防災負荷のみが稼働するように負荷制御が実行される。その後、BCP制御の開始操作時に選択された制御パターンに基づいて、BCP制御レベルがBCP目標電力と投入上限電力との間に位置するように、BCP制御レベルが制御周期(例えば1分)にしたがって繰り返し変更される。
 現在発電電力が投入上限電力より低く、且つ、現在のBCP制御レベルより1つ上のBCP制御レベルの設定電力よりもBCP調整電力の方が高い場合、中央制御装置400は1つ上のBCP制御レベルを実行する。この場合、中央制御装置400は、新たに実行されるBCP制御レベルの制御対象に応じて負荷105の制御を開始する。なお、中央制御装置400は、制御周期内においてBCP制御レベルを1つずつ上げる。
 図8は、投入条件においてBCP制御レベルを上げない場合の具体例を示す図である。現在実行されているBCP制御レベルよりも1つ上のBCP制御レベルの設定電力(図8のレベルn設定電力)が、BCP調整電力を超過している場合、中央制御装置400は、BCP制御レベルを上げない。
 図9は、遮断条件の具体例を示す図である。現在発電電力がBCP目標電力より高くなった場合、中央制御装置400は、BCP制御レベルを下げる。この際、中央制御装置400は、BCP制御レベルを上げる場合とは異なり、1つずつBCP制御レベルを下げるのではなく、現在発電電力がBCP目標電力よりも低くなるBCP制御レベルまで一度に下げる。図9の例では、m分のBCP制御レベルが一度に下げられている。なお、制御条件が不成立になった場合、中央制御装置400はBCP制御レベルを“0”まで一度に下げる。
 また、オペレータ又はユーザの操作によって、現在実行されている負荷制御パターンとは異なる負荷の制御(以下、「ユーザ制御」という。)が実行された場合、中央制御装置400は、ユーザ制御によって消費される電力の容量を含む現在発電電力を算出する。算出された現在発電電力がBCP目標電力よりも高い場合、中央制御装置400は、ユーザ制御を継続したままで、他の制御を停止させることによって、現在発電電力をBCP目標電力以下に下げる。具体的には以下のとおりである。
 中央制御装置400は、図9に示されるようにBCP制御レベルを下げる際に、制御が停止されるBCP制御レベルの制御内容(図9のBCP制御レベルn~(n-m)の各レコード42に設定されている制御対象)にユーザ制御と同一の制御が含まれているか否か判定する。もし含まれている場合には、ユーザ制御と同一の制御の実行を維持した状態における現在発電電力を推定する。現在発電電力の推定値がBCP目標電力よりも低い場合には、中央制御装置400は、BCP制御レベルを(n-m)まで下げる。一方、現在発電電力の推定値がBCP目標電力よりも高い場合には、中央制御装置400は、BCP制御レベルを(n-(m+1))まで下げた場合の現在発電電力を推定する。中央制御装置400は、このような処理を繰り返すことで、ユーザ制御の実行を維持したままで、現在発電電力をBCP目標電力以下に下げる。
 図10は、表示部402が表示するBCP制御画面の具体例を示す図である。BCP制御画面は、この画面において設定される負荷制御パターンの各優先順位の設定電力や、制御状況等を表示する画面である。
 BCP制御状態表示領域501は、BCP制御状態を表示する領域である。BCP制御状態表示領域501には、BCP制御条件成立、BCP制御中、発電可能電力、BCP目標電力、投入上限電力、現在発電電力、BCP調整電力、BCP以降要求の各項目の値が表示される。
 BCP制御条件成立は、BCP制御条件が成立しているか否かを表す。成立している場合には丸印が表示され、成立していない場合はバツ印が表示される。
 BCP制御中は、BCP制御が行なわれているか否かを表す。BCP制御が行われている場合は丸印が表示され、行なわれていない場合はバツ印が表示される。
 BCP制御パターンは、現在の制御中パターンを表す。
 発電可能電力は、動作可能条件を満たしている正常な発電機101の発電電力の合計値を表す。
 BCP目標電力は、発電機101で供給可能とするBCP目標電力を表示する。
 投入上限電力は、目標電力に対し発電機設定で登録された投入上限比率により算出された投入上限電力を表示する。
 現在発電電力は、現在の発電電力(現在発電電力)を表示する。
 BCP調整電力は、BCP目標電力から現在発電電力を引いた値を表示する。
 BCP移行要求は、制御開始時及び終了時の設備に対する移行指令の結果を表示する。
 レベル表示領域502は、各電力系統100において実施されているBCP制御レベルを表示する。BCP制御開始後に条件不成立となったために制御中断している電力系統100については、BCP制御レベルの値として“0”が表示され、下部に“中断”と表示される。
 パターン設定電力表示領域503には、BCP制御パターンの選択中パターンのパターン番号、パターン名称及び設定電力が表示される。各パターンの設定電力は、累積容量を表す。なお、現在のBCP制御レベルが1~20のいずれかである場合、該当するBCP制御レベルの左に所定の記号(図10の例では黒塗りの三角形)が表示される。
 制御設定ボタン504は、制御設定ダイアログを表示するためのボタンである。パターン選択ボタン505は、パターン選択ダイアログを表示するためのボタンである。パターン設定ボタン506は、パターン設定ダイアログを表示するためのボタンである。制御条件設定ボタン507は、制御条件設定ダイアログを表示するためのボタンである。発電機設定ボタン508は、発電機設定ダイアログを表示するためのボタンである。CSV保存ボタン509は、CSV保存ダイアログを表示するためのボタンである。印刷設定ボタン510は、印刷設定ダイアログを表示するためのボタンである。制御モード表示領域511には、現在行われている制御の内容(例えば、通常、停電制御、BCP制御、復電制御など)が表示される。
 図11は、表示部402が表示するパターン設定ダイアログの具体例を示す図である。パターン設定ダイアログの画面では、オペレータは各負荷制御パターンの内容を登録することができる。
 パターン設定表示領域601には、パターンテーブル41に登録されている情報が表示される。なお、図11では、図3に示された項目に加えてさらに、状態、設定値、変更状況などの項目が表示されている。
 レベルは、BCP制御レベルの番号を表す。負荷名称は、制御対象ポイントの名称を表す。状態は、制御対象ポイントが状態(ON/OFFなど)を制御するものである場合に黒塗りの丸が表示される。
 設定値は、設定値出力を行う制御対象ポイント登録時に選択されている負荷種別を表す。負荷種別が温度である場合には黒塗りの正方形が表示され、負荷種別が照度である場合には黒塗りの菱形が表示される。
 容量は、制御対象ポイントの容量を表示する。除外は、制御対象ポイントが除外か否かを表示する。変更状況は、制御中に選択されているパターンのみ変更状況および制御出力状況を表示する。合計は、各BCP制御レベルに登録されている負荷容量の合計を表す。
 パターン選択領域602は、現在パターン設定表示領域601に表示されている負荷制御パターンの値を表示する。オペレータは、“<”や“>”が表示されているボタンを操作することによって、パターン設定表示領域601に表示される負荷制御パターンを変更できる。
 新規登録ボタン603は、パターン情報設定ダイアログを表示するためのボタンである。変更ボタン604は、選択されている制御対象ポイントのBCP制御レベルの情報設定ダイアログを表示するためのボタンである。削除ボタン605は、選択した制御対象ポイントの登録を削除するためのボタンである。キャンセルボタン606は、ダイアログを閉じるためのボタンである。
 図12は、表示部402が表示するパターン選択ダイアログの具体例を示す図である。パターン選択ダイアログは、オペレータが負荷制御パターンの番号を系統毎に選択するための表示である。
 パターン番号表示領域701には、系統毎の負荷制御パターンの番号が表示される。番号が表示されている部分を選択すると、パターン番号選択ダイアログが表示される。オペレータは、パターン番号選択ダイアログにて、選択されている番号を変更できる。
 設定ボタン702は、設定を反映してパターン選択ダイアログを閉じるためのボタンである。キャンセルボタン703は、設定を破棄してパターン選択ダイアログを閉じるためのボタンである。
 以上述べた少なくともひとつの実施形態の負荷制御システムによれば、オペレータによって状況に応じて選択された負荷制御パターンに基づき、優先順位が高い制御内容から順に実行される。そのため、発電機101(自家発)が発電可能な電力内で、優先順位の高い負荷から順に稼働させることが可能となる。したがって、より効率的に自家発の発電電力を利用することが可能となる。
 また、BCP制御が実行されている最中にユーザ制御が発生した場合に、例えユーザ制御が低い優先順位の制御として定義されていたとしても、ユーザ制御を維持したままで他の制御が停止されることによって現在発電電力が調整される。そのため、ユーザが所望する負荷105の制御を維持したままで、自家発の発電電力を効率的に利用することが可能となる。
 また、負荷105に障害が生じた場合、その負荷105を制御対象から除外することが可能である。そして、除外された制御に要する電力は、設定電力に含まれることなく、BCP制御が実行される。そのため、正常に動作しない負荷105に対して割り当てられていた電力を、正常に動作する他の負荷105への制御に転用することが可能であり、自家発の発電電力をより効率的に利用することが可能となる。
 また、BCP制御が実行される際に、停電が生じる前に動作していた負荷105についてのみ制御が実行される。したがって、そもそも動作していなかった負荷105によって自家発の電力が消費されることがない。停電が生じる前に動作していなかった負荷105は、その時点でユーザによって必要とされていない負荷105である可能性が高い。そのため、よりユーザによって必要とされている負荷105に対してのみ自家発の電力を供給し、自家発の発電電力をより効率的に利用することが可能となる。
 <変形例>
 BCP制御が実施されている間は、制御パターンに登録されている内容を変更できないように構成されてもよい。
 上述したレコード42には、制御対象の具体例として照明の発停、空調の発停、空調の温度設定を挙げている。制御対象の具体例は、上述した例に限定される必要は無い。例えば、負荷105が空調機である場合には、制御対象として以下の様な情報が設定されてもよい。電源のオン又はオフ。運転種別(例えば、冷房、暖房、ドライ、送風)。風量(例えば、弱、中、強)。設定温度(例えば、28度、30度)。例えば、負荷105が照明設備である場合には、制御対象として以下の様な情報が設定されてもよい。複数の照明のうち、点灯させる(電源をオンにする)照明の個数又は位置。照度(例えば、低、中、高)。また、空調機や照明設備以外の制御対象が設定されてもよい。
 中央制御装置400は、必ずしも1台の情報処理装置として実装される必要はない。例えば、互いに通信可能な複数台の情報処理装置が連携して中央制御装置400の機能を実現するように構成されてもよい。また、中央制御装置400と、上述した中央監視装置とは、1台の情報処理装置として構成されてもよい。
 図3に示されるパターンテーブル41は、一例にすぎず他の値を有するテーブルとして構成されてもよい。例えば、ナンバー、優先順位、制御対象、容量、除外、合計容量の各値の他に、状態、設定値、変更状況などの値がパターンテーブル41に登録されてもよい。なお、状態値、設定値、変更状況などの各値は、図11の画面に示されている同名の各値を同じである。
 本発明のいくつかの実施形態を説明したが、これらの実施形態は、例として提示したものであり、発明の範囲を限定することは意図していない。これら実施形態は、その他の様々な形態で実施されることが可能であり、発明の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。これら実施形態やその変形は、発明の範囲や要旨に含まれると同様に、特許請求の範囲に記載された発明とその均等の範囲に含まれるものである。
10…負荷制御システム, 100…電力系統, 101…発電機, 102…第一遮断器, 103…第二遮断器, 104…動力盤, 105…負荷, 200…系統間バイパス用遮断器, 300…商用電源遮断器, 400…中央制御装置, 401…入力部, 402…表示部, 403…パターン制御部, 404…パターン記憶部, 405…通信部, 406…状態監視部, 407…状態記憶部, 408…負荷制御部, 409…判定部

Claims (6)

  1.  電力を消費して動作する複数の負荷に対する、優先順位がつけられた複数の制御内容を有するパターンを複数記憶できる記憶部と、
     前記記憶部に記憶された前記パターンからパターンを選択するための選択部と、
     前記負荷によって消費される電力の合計値が、発電機によって供給可能な電力に基づいた値を示す目標電力値を上回らない範囲で、選択された前記パターンの制御内容に基づき、前記優先順位が高い順に前記負荷を動作させる負荷制御部と、
    を有することを特徴とする負荷制御装置。
  2.  前記負荷制御部は、前記合計値が、前記目標電力値を上回る場合は、前記負荷の動作に係る前記制御内容を実行しない、請求項1に記載の負荷制御装置。
  3.  前記負荷制御部は、ユーザ又はオペレータによって開始された前記負荷への制御であるユーザ制御が存在する場合、前記ユーザ制御の優先順位にかかわらず、前記ユーザ制御の実行を維持したままで前記パターンの制御内容に基づく動作の一部を停止することによって、前記合計値が前記目標電力値を上回らないように前記負荷を制御する、請求項1又は2に記載の負荷制御装置。
  4.  前記負荷制御部は、制御の対象とならない負荷が存在する場合、前記合計値が前記目標電力値を上回るか否かの判定を行う際に、前記制御の対象とならない負荷への制御によって消費される電力を含まない前記合計値に基づいて前記判定を行う、請求項1から3のいずれか1項に記載の負荷制御装置。
  5.  前記負荷制御部は、停電が生じた後に前記負荷を制御する場合に、停電が生じる前において制御されていなかった負荷については、前記優先順位にかかわらず制御しない、請求項1から4のいずれか1項に記載の負荷制御装置。
  6.  請求項1から5のいずれか1項に記載の負荷制御装置と、
     前記複数の負荷に対し電力を供給可能な前記発電機と、
    を備える負荷制御システム。
PCT/JP2014/079729 2013-11-11 2014-11-10 負荷制御装置及び負荷制御システム WO2015068840A1 (ja)

Priority Applications (3)

Application Number Priority Date Filing Date Title
EP14860190.9A EP3070801A4 (en) 2013-11-11 2014-11-10 Load control device and load control system
US15/035,686 US9991720B2 (en) 2013-11-11 2014-11-10 Load control apparatus and load control system
CN201480061356.4A CN105981253A (zh) 2013-11-11 2014-11-10 负载控制设备和负载控制系统

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2013232871A JP6319993B2 (ja) 2013-11-11 2013-11-11 負荷制御システム及び中央制御装置
JP2013-232871 2013-11-11

Publications (1)

Publication Number Publication Date
WO2015068840A1 true WO2015068840A1 (ja) 2015-05-14

Family

ID=53041613

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2014/079729 WO2015068840A1 (ja) 2013-11-11 2014-11-10 負荷制御装置及び負荷制御システム

Country Status (5)

Country Link
US (1) US9991720B2 (ja)
EP (1) EP3070801A4 (ja)
JP (1) JP6319993B2 (ja)
CN (1) CN105981253A (ja)
WO (1) WO2015068840A1 (ja)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6772939B2 (ja) * 2017-04-11 2020-10-21 住友金属鉱山株式会社 非常時における設備機器の運転制御システム
JP2019022180A (ja) * 2017-07-21 2019-02-07 アズビル株式会社 監視システム
JP7123586B2 (ja) * 2018-03-16 2022-08-23 株式会社東芝 電力監視システム
JP7115029B2 (ja) * 2018-05-23 2022-08-09 日新電機株式会社 電源システム
CN110311466A (zh) * 2019-07-16 2019-10-08 武汉腾江电气制造有限公司 铁路通信基站双电源系统、控制方法、设备及存储介质
BR112022018142A2 (pt) * 2020-03-17 2022-10-25 Jfe Steel Corp Dispositivo de orientação para selecionar fábrica de segurança, método de orientação para selecionar fábrica de segurança e método de operação de fábrica

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03245743A (ja) * 1990-02-22 1991-11-01 Sony Corp ホームバスシステムの電力制御装置
JPH04317520A (ja) * 1991-04-17 1992-11-09 Toshiba Corp 負荷選択遮断制御装置
JPH06335171A (ja) * 1993-05-18 1994-12-02 Yaskawa Electric Corp 負荷制御方法
JPH09285016A (ja) 1996-04-11 1997-10-31 Nissin Electric Co Ltd 電力設備
JP2007236023A (ja) * 2006-02-27 2007-09-13 Toyota Motor Corp 建物の電力供給システム
US20130270908A1 (en) * 2012-04-17 2013-10-17 Francis X. Wedel Load Shed Control Module For Use With Electrical Generator
JP2013228833A (ja) * 2012-04-25 2013-11-07 Mitsubishi Electric Corp ビル設備監視システム

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3315741B2 (ja) * 1992-12-21 2002-08-19 三菱電機株式会社 デマンド制御装置及びデマンド制御システム
JP3839440B2 (ja) * 2004-03-10 2006-11-01 株式会社エヌ・ティ・ティ・データ エネルギー管理装置、施設監視制御装置、エネルギー管理プログラムおよび施設監視制御プログラム
CA2674372C (en) 2008-07-30 2016-02-09 Gen-Tran Corporation Automatic transfer switch
JP2011083052A (ja) * 2009-10-02 2011-04-21 Panasonic Electric Works Co Ltd 負荷制御システム
US20130187462A1 (en) 2010-06-03 2013-07-25 Briggs & Stratton Corporation Active load management system
US9346464B2 (en) * 2013-02-15 2016-05-24 Vmac Global Technology Inc. Power take-off for engine used in multi-function system and load management of such system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03245743A (ja) * 1990-02-22 1991-11-01 Sony Corp ホームバスシステムの電力制御装置
JPH04317520A (ja) * 1991-04-17 1992-11-09 Toshiba Corp 負荷選択遮断制御装置
JPH06335171A (ja) * 1993-05-18 1994-12-02 Yaskawa Electric Corp 負荷制御方法
JPH09285016A (ja) 1996-04-11 1997-10-31 Nissin Electric Co Ltd 電力設備
JP2007236023A (ja) * 2006-02-27 2007-09-13 Toyota Motor Corp 建物の電力供給システム
US20130270908A1 (en) * 2012-04-17 2013-10-17 Francis X. Wedel Load Shed Control Module For Use With Electrical Generator
JP2013228833A (ja) * 2012-04-25 2013-11-07 Mitsubishi Electric Corp ビル設備監視システム

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of EP3070801A4

Also Published As

Publication number Publication date
JP2015095925A (ja) 2015-05-18
US9991720B2 (en) 2018-06-05
CN105981253A (zh) 2016-09-28
EP3070801A4 (en) 2017-07-26
US20160285275A1 (en) 2016-09-29
EP3070801A1 (en) 2016-09-21
JP6319993B2 (ja) 2018-05-09

Similar Documents

Publication Publication Date Title
WO2015068840A1 (ja) 負荷制御装置及び負荷制御システム
JP4567380B2 (ja) エアコンの中央制御システム及びその動作方法
TWI440276B (zh) 用於產生及控制虛擬電源分配單元之系統及方法
AU2012359824B2 (en) Air conditioner
JPH09135541A (ja) 給電システム
CN103196209A (zh) 一种空调自动切换方法及装置
JP5989436B2 (ja) エネルギー管理システム、エネルギー管理装置、制御方法およびプログラム
JP4179366B2 (ja) 空気調和機
JP2008170047A (ja) 空調機システム、空調機システムの制御方法および集中管理装置
CN103486013B (zh) 一种具有联网功能的空压机控制器及其空压机系统
CN105698342A (zh) 空调器四通阀的故障判定电路、方法及空调器
JP6462411B2 (ja) 負荷制御試験装置、負荷制御試験システム、負荷制御試験方法、及びプログラム
JP6529782B2 (ja) 負荷制御装置、負荷制御システム、負荷制御方法、及びプログラム
JP6435352B2 (ja) 空調管理装置およびその表示制御方法
KR101028094B1 (ko) 비상전원이 구비된 공기조화기 및 그 제어방법
CN114801846A (zh) 一种开闭站控制方法、装置、设备、存储介质及换电站
US9979228B2 (en) Energy management apparatus and method of controlling the same
KR101645244B1 (ko) Plc 네트워크 기반의 원방감시 제어시스템 및 방법
JP7502909B2 (ja) 空調機の管理装置および管理方法
CN109405170A (zh) 用于空调系统的更新方法及装置
KR101598781B1 (ko) 빌딩설비 시스템 및 그 제어방법
JP2020010437A (ja) 制御装置、制御システム、及び制御方法
CN102468689A (zh) 智能化用电管理系统及管理方法
JP2000304336A (ja) 空気調和システム
JP2003329291A (ja) 空気調和システムおよび室外機

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 14860190

Country of ref document: EP

Kind code of ref document: A1

REEP Request for entry into the european phase

Ref document number: 2014860190

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2014860190

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 15035686

Country of ref document: US

NENP Non-entry into the national phase

Ref country code: DE