WO2014037612A1 - Method and module for the installation of equipment on a ship - Google Patents

Method and module for the installation of equipment on a ship Download PDF

Info

Publication number
WO2014037612A1
WO2014037612A1 PCT/FI2013/050843 FI2013050843W WO2014037612A1 WO 2014037612 A1 WO2014037612 A1 WO 2014037612A1 FI 2013050843 W FI2013050843 W FI 2013050843W WO 2014037612 A1 WO2014037612 A1 WO 2014037612A1
Authority
WO
WIPO (PCT)
Prior art keywords
module
framework
ship
equipment
equipment unit
Prior art date
Application number
PCT/FI2013/050843
Other languages
French (fr)
Inventor
Antti SALOVUORI
Juhani RAINIO
Janne WECKMAN
Original Assignee
Stx Finland Oy
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Stx Finland Oy filed Critical Stx Finland Oy
Priority to JP2015529087A priority Critical patent/JP6214659B2/en
Priority to KR1020157008609A priority patent/KR102061110B1/en
Priority to EP13766122.9A priority patent/EP2892798B1/en
Priority to CN201380045920.9A priority patent/CN104797492B/en
Publication of WO2014037612A1 publication Critical patent/WO2014037612A1/en
Priority to HRP20170140TT priority patent/HRP20170140T1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/02Hulls assembled from prefabricated sub-units
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/20Building or assembling prefabricated vessel modules or parts other than hull blocks, e.g. engine rooms, rudders, propellers, superstructures, berths, holds or tanks

Definitions

  • the invention relates to a solution for the delivery and installation of equipment units within the interior of a ship to be installed in shipbuilding. More specifical- ly, the invention relates to a method and module for the installation aboard a ship of pre-assembled equipment units, such as for example air conditioning systems and engine room equipment.
  • the construction of a ship comprises typically a multitude of different operations, such as for example manufacturing ship hull segments, assembling a hull from the segments, as well as several different fitting-out operations dependent on the hull assembling schedule all the way to a completion of the ship.
  • the number of diverse components to be installed in various fitting-out operations is enormous, which is why, as known in the art, these operations have been facilitated and streamlined by coming up with various types of mod- ular solutions for various facilities and applications.
  • Such modules are typically prefabricated and fitted-out separately from the ship hull building process and schedule and are delivered to the shipyard at an appropriate time for the installation aboard a ship.
  • One example of typical modules to be installed in a ship are ship cabins.
  • Modular solutions have also been used in the installation of miscellaneous structurally heavier objects, such as aggregates, machines, equipment and entities made up thereof aboard a ship, for example in ship fan rooms and engine facilities.
  • these structurally heavier projects have resulted in considerable problems from the stand- point of shipbuilding, such as for example a substantial weight of the modular framework, final connections becoming more difficult due to space demanded by the modular framework, maintenance operations becoming more difficult, cramped conditions for the end user, as well as a considerable increase of hot works and installation hours in the process of installing the module in place.
  • the benefits provided in these projects by modularization have actually reversed into additional costs, extra weight, and increased space demand with respect to conventional shipbuilding.
  • the solution according to the present invention provides a capability of eliminating completely or at least mitigating substantially the above-described mod- ularization problems of prior known heavy aggregate and/or equipment entities.
  • the machine, aggregate and/or other type of equipment entity is modularized in such a way that, during the prefabricate of a module, the equipment and machines are attached to the module frame.
  • the module frame is a self-supporting structure, including typically horizontal brace members as well as vertical brace members.
  • the process of moving, especially lifting a module onto a ship comprises removing the lowest section components of a module frame, i.e. components making up the frame bottom, as well as components connecting the frame bottom in vertical direction with the next section or platform or sections or platforms.
  • the lowermost equipment unit of the module has been mounted with a suspension attachment on the highest or next platform of the module frame, whereby, after dismantling the lowest section components of the module frame, the lowermost equipment unit is left hanging from the remaining upper framework of the module.
  • the module frame is constructed in such a way that, after installing the module aboard a ship, the vertically extending frame components of the module frame, including possible diagonal braces, can be removed.
  • the removable frame components of a module according to the invention are also preferably secured in place on the module frame by means of bolts or screws with flange connections, said flange connections being preferably set in a plane inclined relative to the vertical plane of the module.
  • the module frame is preferably constructed in such a way that it extends in a vertical direction to a plurality of ship deck surfaces, the module frame is fitted with machines and equipment included in several different cover structures, and the module structure is formed with lightened horizontal plane structures, which are adapted to settle in flush- ness with ship decks once the module has been installed in place.
  • the module structure according to the invention can also be used in the building of machines and equipment for engine rooms extending to multiple ship decks.
  • the lightened horizontal flat structures of the module are structurally lighter than a conventional ship deck structure, which enables a further reduction in the module weight.
  • a module according to the invention which extends to multiple ship deck surfaces, is fixed in its position preferably in such a way that, during the course of placing a module in its position, the module has its horizontal flat structures set on top of protrusions extending from the ship's structure substantially in flush- ness with decks, and the module has its horizontal flat structures secured to these protrusions.
  • Such anchoring of a module facilitates and expedites fixing the module in place, especially when a module is lowered into its allocated position inside a ship.
  • the lowermost suspended equipment entity of a module according to the invention is preferably secured to a deck structure constituting the bottom of a space allocated for the module, thus enabling at least a partial removal of frame components used in the suspended attachment of the lowermost equipment entity. More specifically, the characterizing features for a method according to the invention are presented in claim 1 , and the characterizing features of a module according to the invention are presented in claim 7.
  • Fig. 1 shows schematically a triple level embodiment of a module according to the invention
  • Fig. 2 shows schematically a double level embodiment of a module according to the invention.
  • Fig. 1 shows schematically a triple level embodiment for a module 1 according to the invention relating to a fan room unit intended for air conditioning equipment and extending in a vertical direction to three ship decks.
  • the module 1 has its framework 2 consisting of three superimposed horizontal flat structures, i.e. a bottom structure 3 and cover structures 4 and 5 for the framework, and upright beams 6 and 7 connecting these horizontal flat structures to each other.
  • the process of manufacturing a module 1 according to the invention as shown in Fig. 1 comprises constructing first the bottom structure 3 for the framework 2, on top of which is placed the lowermost air conditioning unit 10.
  • This bottom structure 3 for the framework 2 of the module 1 is preferably made up of just a few horizontally extending beams of pipes, which provide necessary supporting points for lifting the lowermost air conditioning unit 10 along with the rest of the module's framework, as well as framework bracing beams 16 extending horizontally around the edges of the bottom structure of the module's framework.
  • the cover structure 4 is preferably assembled as a single entity with the lowest vertically extending upright beam 6, as well as with the bracing beams 16 extending in a horizontal plane of the bottom structure 3 and connecting the bottom ends of these upright beams to each other, said integral entity being then lifted on top of and around the lowermost air conditioning unit 10 and the underlying bottom structure 3
  • the support structure underneath the lowermost air conditioning unit 10 and in flushness with the bottom structure 3 is connected with the cover structure 4 by means of vertically extending suspension beams 1 1 .
  • the middlemost air conditioning unit 9 On top of the cover structure 4 is mounted the middlemost air conditioning unit 9.
  • the highest cover structure 5 included in the framework 2 of the module 1 as well as the upright beams 7 fixing the same to the module's framework, are installed in place, which is followed by mounting the uppermost air conditioning unit 8 in its position on the highest cover structure.
  • the installations of the air conditioning units 8, 9 and 10 can be finished, as well as the necessary installation of accessories can be finished, as well as the module 1 can be fitted with necessary accessories and components.
  • the middle cover structure 4 and the highest cover structure 5 included in the framework 2 of the module 1 of the invention are provided with necessary plat- forms for working on top of these cover structures.
  • the cover structures 4 and 5 have their edges provided with protrusions 12 and 13 in the form of horizontally extending beam ends.
  • the process of moving a completed prefabricated module 1 onto a ship comprises lifting the module 1 first to a suitable height, such as for example to the height of about 1 ⁇ 4 meter, from lifting lugs 14 of the highest cover platform.
  • a suitable height such as for example to the height of about 1 ⁇ 4 meter
  • the module has its framework 2 stripped of the lowest upright beams 6, as well as of the bracing beams 16 extending horizontally at the bottom edges of these upright beams. Consequently, the lowermost air conditioning unit of the module 1 is set hanging through the intermediary of the suspension beams 1 1 and the remaining bottom structure 3 from the middle cover structure 4 of the module.
  • the module is lifted aboard a ship into a space allocated therefor.
  • the protrusions 12 and 13 extending from the edges of the cover structures 4 and 5 of the module's framework 2 are parked on top of protrusions jutting out of the walls of a space allocated for the module, said wall protrusions being substantially flush with the levels of respective ship deck structures.
  • the protrusions 12 and 13 of the module's framework 2 are welded to the attachment with the protrusions jutting out of the ship's structure and the upright braces 7 are removed from the module's framework.
  • the lowermost air conditioning unit 10 is fixed in place to the ship's deck structure establishing the floor of a space allocated for the module 1 , after which the suspension beams 1 1 are disengaged from the module's framework 2, and the support system left in the bottom structure 3 of the module's framework is removed.
  • the module 1 has been successfully set in its place and connections can be made for manifolds of the air conditioning units 8, 9 and 10 with those of the ship.
  • the attachments of the upright beams 6, 7 and the suspension beams 1 1 to the framework's horizontally extending cover structures 3, 4 and 5 are preferably established by way of inclined flange connections 15 with bolts. Accordingly, the disengagement of the upright beams 6, 7, horizontal beams 16 and suspension beams 1 1 from the rest of the framework 2 is carried out without problems, even if the upright beams were supporting for example loads resulting from tolerances after the installation of a module. Thus, the need for hot works in the process of disengaging the upright beams 6, 7, horizontal beams 16 and suspension beams 1 1 can be preferably eliminated.
  • the cover structures 4 and 5 included in the framework 2 of the module 1 remain as a part of the ship's deck structure.
  • the cover structures 4 and 5 of the module 1 can be read- ily and economically provided with a construction which is lighter than the rest of the ship's deck structures.
  • Fig. 2 shows schematically a double level embodiment for a module 21 of the invention relating to a fan room unit intended for air conditioning equipment and extending in vertical direction to two ship decks.
  • This embodiment visualizes more clearly vertical suspension beams 26, which provide a suspended attachment for an air conditioning unit 25 mounted on top of a floor structure 23 included in a framework 22 of the module 21 and which are separate from vertical upright beams 27 of the module's framework, said upright beams being dismantled from the module's framework at the early stage of moving the module to its destination.
  • the modular solution according to the invention is equally appli- cable in the process of installing on board equipment entities other than air conditioning units, such as for example equipment assemblies for elevators and engine rooms.
  • the modular solution according to the invention is also modifiable in a multitude of ways obvious for a person skilled in the art, within the scope of protection defined in the appended claims.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Cage And Drive Apparatuses For Elevators (AREA)
  • Other Air-Conditioning Systems (AREA)
  • Jib Cranes (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Packaging Of Machine Parts And Wound Products (AREA)
  • Apparatuses And Processes For Manufacturing Resistors (AREA)

Abstract

A method for the installation of equipment (8, 9, 10, 25) aboard a ship, said method comprising constructing first a framework (2, 22) for a module (1, 21 ) for mounting thereon the machines and devices of an equipment unit, and said method comprising moving a prefabricated module aboard a ship into a space allocated for the module, whereby, as the prefabricated module (1, 21 ) is being delivered onto a ship, the module framework (2, 22) has its lowest section components (6, 16, 27) dismantled for setting a lowermost equipment unit (10, 25) of the module in suspension from a remaining framework of the module, and that the placing and securing of a module aboard a ship is followed by removing at least some of vertically extending components (7, 1 1, 26) of the module framework. The invention relates also to such a module (1, 21 ).

Description

Method and module for the installation of equipment on a ship
The invention relates to a solution for the delivery and installation of equipment units within the interior of a ship to be installed in shipbuilding. More specifical- ly, the invention relates to a method and module for the installation aboard a ship of pre-assembled equipment units, such as for example air conditioning systems and engine room equipment.
The construction of a ship comprises typically a multitude of different operations, such as for example manufacturing ship hull segments, assembling a hull from the segments, as well as several different fitting-out operations dependent on the hull assembling schedule all the way to a completion of the ship. The number of diverse components to be installed in various fitting-out operations is enormous, which is why, as known in the art, these operations have been facilitated and streamlined by coming up with various types of mod- ular solutions for various facilities and applications. Such modules are typically prefabricated and fitted-out separately from the ship hull building process and schedule and are delivered to the shipyard at an appropriate time for the installation aboard a ship. One example of typical modules to be installed in a ship are ship cabins. Modular solutions have also been used in the installation of miscellaneous structurally heavier objects, such as aggregates, machines, equipment and entities made up thereof aboard a ship, for example in ship fan rooms and engine facilities. Regarding the utilization of a modular structure, however, these structurally heavier projects have resulted in considerable problems from the stand- point of shipbuilding, such as for example a substantial weight of the modular framework, final connections becoming more difficult due to space demanded by the modular framework, maintenance operations becoming more difficult, cramped conditions for the end user, as well as a considerable increase of hot works and installation hours in the process of installing the module in place. Hence, the benefits provided in these projects by modularization have actually reversed into additional costs, extra weight, and increased space demand with respect to conventional shipbuilding. These drawbacks are the reason why there has been hardly any use of modularization in these projects since early experiments. In particular, the modularization of such aggregates and equipment entities is problematic in application projects, in which the module of an aggregate and/or equipment entity extends in a vertical direction over two or more superimposed decks, which is typically the case e.g. with air conditioning units to be installed in ship fan rooms. A similar situation may also occur in the case of a ship's so- called engine shaft. Thus, said modularization problems of such projects become multiplied.
The solution according to the present invention provides a capability of eliminating completely or at least mitigating substantially the above-described mod- ularization problems of prior known heavy aggregate and/or equipment entities.
In a solution according to the invention, the machine, aggregate and/or other type of equipment entity is modularized in such a way that, during the prefabricate of a module, the equipment and machines are attached to the module frame. At this prefabrication stage, the module frame is a self-supporting structure, including typically horizontal brace members as well as vertical brace members. The process of moving, especially lifting a module onto a ship comprises removing the lowest section components of a module frame, i.e. components making up the frame bottom, as well as components connecting the frame bottom in vertical direction with the next section or platform or sections or platforms. During the prefabrication of a module, the lowermost equipment unit of the module has been mounted with a suspension attachment on the highest or next platform of the module frame, whereby, after dismantling the lowest section components of the module frame, the lowermost equipment unit is left hanging from the remaining upper framework of the module. In addition, the module frame is constructed in such a way that, after installing the module aboard a ship, the vertically extending frame components of the module frame, including possible diagonal braces, can be removed.
This enables the space occupied by the module frame in an anchored module to be minimized, thus providing room around a securely installed equipment unit for necessary retrofitting operations as well as equipment maintenance. In addition, by virtue of the removable components of a module frame, it is possible to minimize the extra weight added by the module to a ship's total weight. The removable frame components of a module according to the invention are also preferably secured in place on the module frame by means of bolts or screws with flange connections, said flange connections being preferably set in a plane inclined relative to the vertical plane of the module. This provides a capability of minimizing hot works needed in relation to the installation of a module and disadvantages caused thereby and, in addition, the flange connections set in an inclined plane make it easier to dismantle the removable module frame components from a securely installed module. Removable components are also suitable for re-use in the prefabrication of subsequent similar mod- ules.
In a solution according to the invention, the module frame is preferably constructed in such a way that it extends in a vertical direction to a plurality of ship deck surfaces, the module frame is fitted with machines and equipment included in several different cover structures, and the module structure is formed with lightened horizontal plane structures, which are adapted to settle in flush- ness with ship decks once the module has been installed in place. Hence, the module structure according to the invention can also be used in the building of machines and equipment for engine rooms extending to multiple ship decks. In addition, the lightened horizontal flat structures of the module are structurally lighter than a conventional ship deck structure, which enables a further reduction in the module weight.
A module according to the invention, which extends to multiple ship deck surfaces, is fixed in its position preferably in such a way that, during the course of placing a module in its position, the module has its horizontal flat structures set on top of protrusions extending from the ship's structure substantially in flush- ness with decks, and the module has its horizontal flat structures secured to these protrusions. Such anchoring of a module facilitates and expedites fixing the module in place, especially when a module is lowered into its allocated position inside a ship. The lowermost suspended equipment entity of a module according to the invention is preferably secured to a deck structure constituting the bottom of a space allocated for the module, thus enabling at least a partial removal of frame components used in the suspended attachment of the lowermost equipment entity. More specifically, the characterizing features for a method according to the invention are presented in claim 1 , and the characterizing features of a module according to the invention are presented in claim 7.
The invention will now be described in more detail by way of example with ref- erence to the accompanying figures, in which
Fig. 1 shows schematically a triple level embodiment of a module according to the invention, and
Fig. 2 shows schematically a double level embodiment of a module according to the invention. Fig. 1 shows schematically a triple level embodiment for a module 1 according to the invention relating to a fan room unit intended for air conditioning equipment and extending in a vertical direction to three ship decks.
The module 1 has its framework 2 consisting of three superimposed horizontal flat structures, i.e. a bottom structure 3 and cover structures 4 and 5 for the framework, and upright beams 6 and 7 connecting these horizontal flat structures to each other. On top of each horizontal flat structure 3, 4 and 5 is mounted a respective air conditioning unit 8, 9 and 10.
The process of manufacturing a module 1 according to the invention as shown in Fig. 1 comprises constructing first the bottom structure 3 for the framework 2, on top of which is placed the lowermost air conditioning unit 10. This bottom structure 3 for the framework 2 of the module 1 is preferably made up of just a few horizontally extending beams of pipes, which provide necessary supporting points for lifting the lowermost air conditioning unit 10 along with the rest of the module's framework, as well as framework bracing beams 16 extending horizontally around the edges of the bottom structure of the module's framework.
This is followed by installing in place the next cover structure 4 included in the framework 2 of the module 1 . The cover structure 4 is preferably assembled as a single entity with the lowest vertically extending upright beam 6, as well as with the bracing beams 16 extending in a horizontal plane of the bottom structure 3 and connecting the bottom ends of these upright beams to each other, said integral entity being then lifted on top of and around the lowermost air conditioning unit 10 and the underlying bottom structure 3
Once the cover structure 4 included in the framework 2 of the module 1 , and its support structure along with its upright beams 6, as well as its bracing beams 16 extending at floor level, are in position, the support structure underneath the lowermost air conditioning unit 10 and in flushness with the bottom structure 3 is connected with the cover structure 4 by means of vertically extending suspension beams 1 1 . In addition, on top of the cover structure 4 is mounted the middlemost air conditioning unit 9. Next, the highest cover structure 5 included in the framework 2 of the module 1 , as well as the upright beams 7 fixing the same to the module's framework, are installed in place, which is followed by mounting the uppermost air conditioning unit 8 in its position on the highest cover structure.
Once the framework 2 of the module 1 is completed, the installations of the air conditioning units 8, 9 and 10 can be finished, as well as the necessary installation of accessories can be finished, as well as the module 1 can be fitted with necessary accessories and components.
The middle cover structure 4 and the highest cover structure 5 included in the framework 2 of the module 1 of the invention are provided with necessary plat- forms for working on top of these cover structures. In addition, the cover structures 4 and 5 have their edges provided with protrusions 12 and 13 in the form of horizontally extending beam ends.
The process of moving a completed prefabricated module 1 onto a ship comprises lifting the module 1 first to a suitable height, such as for example to the height of about ¼ meter, from lifting lugs 14 of the highest cover platform. When the module 1 is hanging in the air, the module has its framework 2 stripped of the lowest upright beams 6, as well as of the bracing beams 16 extending horizontally at the bottom edges of these upright beams. Consequently, the lowermost air conditioning unit of the module 1 is set hanging through the intermediary of the suspension beams 1 1 and the remaining bottom structure 3 from the middle cover structure 4 of the module.
Once the framework 2 of the module 1 has its lowest supporting structure removed, the module is lifted aboard a ship into a space allocated therefor. In the latter stages of lifting the module into its place, the protrusions 12 and 13 extending from the edges of the cover structures 4 and 5 of the module's framework 2 are parked on top of protrusions jutting out of the walls of a space allocated for the module, said wall protrusions being substantially flush with the levels of respective ship deck structures.
Once the module 1 is in its position on board in a space allocated therefor, the protrusions 12 and 13 of the module's framework 2 are welded to the attachment with the protrusions jutting out of the ship's structure and the upright braces 7 are removed from the module's framework. In addition, the lowermost air conditioning unit 10 is fixed in place to the ship's deck structure establishing the floor of a space allocated for the module 1 , after which the suspension beams 1 1 are disengaged from the module's framework 2, and the support system left in the bottom structure 3 of the module's framework is removed.
Hence, the module 1 has been successfully set in its place and connections can be made for manifolds of the air conditioning units 8, 9 and 10 with those of the ship.
In the framework 2 of the module 1 according to the invention, the attachments of the upright beams 6, 7 and the suspension beams 1 1 to the framework's horizontally extending cover structures 3, 4 and 5 are preferably established by way of inclined flange connections 15 with bolts. Accordingly, the disengagement of the upright beams 6, 7, horizontal beams 16 and suspension beams 1 1 from the rest of the framework 2 is carried out without problems, even if the upright beams were supporting for example loads resulting from tolerances after the installation of a module. Thus, the need for hot works in the process of disengaging the upright beams 6, 7, horizontal beams 16 and suspension beams 1 1 can be preferably eliminated.
In the embodiment of Fig. 1 , the cover structures 4 and 5 included in the framework 2 of the module 1 remain as a part of the ship's deck structure. With such modularization, the cover structures 4 and 5 of the module 1 can be read- ily and economically provided with a construction which is lighter than the rest of the ship's deck structures.
Fig. 2 shows schematically a double level embodiment for a module 21 of the invention relating to a fan room unit intended for air conditioning equipment and extending in vertical direction to two ship decks. This embodiment visualizes more clearly vertical suspension beams 26, which provide a suspended attachment for an air conditioning unit 25 mounted on top of a floor structure 23 included in a framework 22 of the module 21 and which are separate from vertical upright beams 27 of the module's framework, said upright beams being dismantled from the module's framework at the early stage of moving the module to its destination.
Regarding the embodiments according to the invention as shown in the figures and discussed above, it should be noted that the invention is by no means limited thereby. The modular solution according to the invention is equally appli- cable in the process of installing on board equipment entities other than air conditioning units, such as for example equipment assemblies for elevators and engine rooms. The modular solution according to the invention is also modifiable in a multitude of ways obvious for a person skilled in the art, within the scope of protection defined in the appended claims.

Claims

Claims
1 . A method for the installation of equipment units (8, 9, 10, 25) aboard a ship, said method comprising constructing first a framework (2, 22) for a module (1 , 21 ) for mounting thereon the machines and devices of an equipment unit, and said method comprising moving a prefabricated module aboard a ship into a space allocated for the module, characterized in that, as the prefabricated module (1 , 21 ) is being delivered onto a ship, the module framework (2, 22) has its lowest section components (6, 16, 27) dismantled for setting a lowermost equipment unit (10, 25) of the module in suspension from a remain- ing framework of the module, and in that the placing and securing of a module aboard a ship is followed by removing at least some of vertically extending components (7, 1 1 , 26) of the module framework.
2. A method according to claim 1 , characterized in that the framework (2, 22) of the module (1 , 21 ) is constructed to extend in vertical direction to a plu- rality of ship deck platforms, the module is fitted with the equipment units (8, 9, 10, 25) of several different deck platforms, and the module's framework is formed with lightened cover structures (4, 5, 24), which cover structures settle in flushness with the ship decks once the module has been set in its position.
3. A method according to claim 2, characterized in that the cover structures (4, 5, 24) of the fixedly mounted module (1 , 21 ) are secured to a ship's structure substantially in line with the ship decks by way of protrusions extending out of the ship's hull structure.
4. A method according to any of claims 1 -3, characterized in that the lowermost suspended equipment unit (10, 25) of the module (1 , 21 ) is secured to a ship deck structure, and a module framework (3, 1 1 , 23, 26), which enabled the suspension of the lowermost equipment unit of the module, is removed at least partially.
5. A method according to any of claims 1 -4, characterized in that the components (6, 7, 1 1 ,16, 26, 27) to be dismantled from the framework (2, 22) of the module (1 , 21 ) are attached to the module framework with bolt connections, preferably by way of inclined flange connections (15).
6. A method according to any of claims 1 -5, characterized in that the components (3, 6, 7, 1 1 , 16, 23, 26, 27) dismantled from the framework (2, 22) of the module (1 , 21 ) are reused in the frameworks of new modules.
7. A module (1 , 21 ) for the installation of equipment (8, 9, 10, 25) aboard a ship, said module comprising a framework (2, 22) with the machines and devices of an equipment unit attached to said framework of the module, characterized in that the framework (2, 22) of the module (1 , 21 ) comprises a lowest framework section (6, 16, 27) to be removed before setting the module in place, a suspension attachment (1 1 , 26) of the lowermost equipment unit (10, 25) to a top or next cover surface (4, 24) of the module framework, and vertically extending components (7, 1 1 , 26) of the module framework to be removed at least partially after setting the module in place.
8. A module (1 , 21 ) according to claim 7, characterized in that the module (1 , 21 ) has its framework (2, 22) extending in vertical direction to a plurality of ship deck surfaces (4, 5, 24), the module is fitted with the equipment (8, 9, 10, 25) for several different deck surfaces, and the module framework comprises lightened cover structures, said cover structures being adapted to settle in flushness with the ship decks once the module has been set in place.
9. A module (1 ,21 ) according to claim 8, characterized in that the module (1 , 21 ) has its cover structures (4, 5, 24) adapted to be supported by a ship's structure on protrusions extending from the ship's hull structure substantially in alignment with the ship decks.
10. A module (1 , 21 ) according to any of claims 7-9, characterized in that a section (3, 1 1 , 23, 26) of the module framework (2, 22), which has enabled a suspended attachment for the lowermost equipment unit (10, 25) of the module (21 ), is adapted to be at least partially removable after the lowermost equipment unit is secured in place to the ship's structure.
1 1 . A module (1 , 21 ) according to any of claims 7-10, characterized in that the components (3, 6, 7, 1 1 , 16, 23, 26, 27) to be removed from the framework (2, 22) of the module (1 , 21 ) are attached to the framework with bolt connections, preferably by way of inclined flange connections (15).
PCT/FI2013/050843 2012-09-04 2013-09-03 Method and module for the installation of equipment on a ship WO2014037612A1 (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
JP2015529087A JP6214659B2 (en) 2012-09-04 2013-09-03 Method and module for installing equipment on a ship
KR1020157008609A KR102061110B1 (en) 2012-09-04 2013-09-03 Method and module for the installation of equipment on a ship
EP13766122.9A EP2892798B1 (en) 2012-09-04 2013-09-03 Method and module for the installation of equipment on a ship
CN201380045920.9A CN104797492B (en) 2012-09-04 2013-09-03 Equipment fitting-out method and module
HRP20170140TT HRP20170140T1 (en) 2012-09-04 2017-01-27 Method and module for the installation of equipment on a ship

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FI20125912A FI124115B (en) 2012-09-04 2012-09-04 A method and module for installing equipment on a ship
FI20125912 2012-09-04

Publications (1)

Publication Number Publication Date
WO2014037612A1 true WO2014037612A1 (en) 2014-03-13

Family

ID=49230804

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/FI2013/050843 WO2014037612A1 (en) 2012-09-04 2013-09-03 Method and module for the installation of equipment on a ship

Country Status (8)

Country Link
EP (1) EP2892798B1 (en)
JP (1) JP6214659B2 (en)
KR (1) KR102061110B1 (en)
CN (1) CN104797492B (en)
FI (1) FI124115B (en)
HR (1) HRP20170140T1 (en)
PL (1) PL2892798T3 (en)
WO (1) WO2014037612A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102631760B1 (en) * 2018-12-03 2024-01-31 닛키 글로벌 가부시키가이샤 Method for manufacturing floating body equipment equipped with natural gas liquefaction device
CN113602447A (en) * 2021-08-11 2021-11-05 上海外高桥造船有限公司 Centralized control room unit modular construction and assembly method and ship

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010076814A1 (en) * 2008-12-29 2010-07-08 Fincantieri Cantieri Navali Italiani S.P.A. Conditioning station for naval application and assembly method thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49116796A (en) * 1973-03-10 1974-11-07
JPS5179492A (en) * 1974-12-28 1976-07-10 Nippon Kokan Kk
JPS6171292A (en) * 1984-09-14 1986-04-12 Nippon Kokan Kk <Nkk> Construction of engine room of vessel
JPS6173500U (en) * 1984-10-22 1986-05-19
CN1046245C (en) * 1990-04-28 1999-11-10 石川岛播磨重工业株式会社 Module frame work for larger structure, method and device for assembling module frame work and coupler for module frame work
CN1948081A (en) * 2006-11-03 2007-04-18 大连船舶重工集团有限公司 Assembly ship building unit element, modularization designing method
CN1948080A (en) * 2006-11-03 2007-04-18 大连船舶重工集团有限公司 Outfitting construction method of boats and ships

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010076814A1 (en) * 2008-12-29 2010-07-08 Fincantieri Cantieri Navali Italiani S.P.A. Conditioning station for naval application and assembly method thereof

Also Published As

Publication number Publication date
FI124115B (en) 2014-03-31
FI20125912A (en) 2014-03-05
JP2015530307A (en) 2015-10-15
CN104797492A (en) 2015-07-22
JP6214659B2 (en) 2017-10-18
EP2892798A1 (en) 2015-07-15
HRP20170140T1 (en) 2017-05-05
KR20150052256A (en) 2015-05-13
KR102061110B1 (en) 2019-12-31
EP2892798B1 (en) 2016-11-09
CN104797492B (en) 2017-03-08
PL2892798T3 (en) 2017-07-31

Similar Documents

Publication Publication Date Title
CN104662290B (en) Supply stand for tower, the tower with supply stand and the method for building supply stand in the inside of tower
CN101844612B (en) Fabricated scaffold and using method thereof
US8769886B2 (en) Building unit with temporary reinforcing members, unit building, and method for constructing unit building
CN103741947A (en) Tube-frame-supporting type hydraulic climbing integral steel platform formwork truss layer construction method
CN105649314A (en) Suspension platform for high and long-span corridor construction
KR20200002831A (en) Hoisting system for installing wind turbines
EP2892798B1 (en) Method and module for the installation of equipment on a ship
CN109132843B (en) The installation method of super-section metal bellows in a kind of vertical shaft
CN106013784A (en) Angle iron frame template and construction method
EP3983627B1 (en) Power plant construction
CN202954553U (en) Full assembly tool type attachment lifting scaffold
CN109057309A (en) A kind of suspended operating platform and its mounting and dismounting method
CN204002841U (en) A kind of outrigger formula mobile formwork for support of tunnel wall pouring construction
EP2692965B1 (en) Module structure and module construction method
CN208763390U (en) A kind of suspended operating platform
JPH09209589A (en) Method of setting product group in building to be constructed
JPH0886037A (en) Plant building, constructing method therefor, and structure for its construction
CN110439264A (en) A kind of monoblock type large-scale composite form system and production method and construction method
CN205421883U (en) Suspension type operation platform
CN219080968U (en) Core section of thick bamboo outer wall and well climbing form and horizontal structure aluminium mould&#39;s combination system
CN110318460B (en) Construction method of inverted-step-shaped special-shaped steel structure
AU2012101066A4 (en) Guide system and method for erecting power transmission line towers
JP5792578B2 (en) Unit conversion method
CN105386593A (en) Hanging-type operation platform and construction method
KR102052680B1 (en) Construction method of standing module for building

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13766122

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2015529087

Country of ref document: JP

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 20157008609

Country of ref document: KR

Kind code of ref document: A

REEP Request for entry into the european phase

Ref document number: 2013766122

Country of ref document: EP

WWE Wipo information: entry into national phase

Ref document number: 2013766122

Country of ref document: EP