WO2012091323A2 - 전력 관리 시스템 및 이에 적용되는 전력 분배기 - Google Patents

전력 관리 시스템 및 이에 적용되는 전력 분배기 Download PDF

Info

Publication number
WO2012091323A2
WO2012091323A2 PCT/KR2011/009577 KR2011009577W WO2012091323A2 WO 2012091323 A2 WO2012091323 A2 WO 2012091323A2 KR 2011009577 W KR2011009577 W KR 2011009577W WO 2012091323 A2 WO2012091323 A2 WO 2012091323A2
Authority
WO
WIPO (PCT)
Prior art keywords
power
server
control device
information
power usage
Prior art date
Application number
PCT/KR2011/009577
Other languages
English (en)
French (fr)
Other versions
WO2012091323A3 (ko
Inventor
신준호
송병훈
Original Assignee
전자부품연구원
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 전자부품연구원 filed Critical 전자부품연구원
Publication of WO2012091323A2 publication Critical patent/WO2012091323A2/ko
Publication of WO2012091323A3 publication Critical patent/WO2012091323A3/ko

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/26Power supply means, e.g. regulation thereof
    • G06F1/32Means for saving power
    • G06F1/3203Power management, i.e. event-based initiation of a power-saving mode
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/003Load forecast, e.g. methods or systems for forecasting future load demand
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • H02J3/144Demand-response operation of the power transmission or distribution network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/50The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads
    • H02J2310/56The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads characterised by the condition upon which the selective controlling is based
    • H02J2310/62The condition being non-electrical, e.g. temperature
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Definitions

  • the present invention relates to a power management system and a power divider applied thereto, and more particularly, to a power management system for managing power of servers installed in a server rack and a power divider applied thereto.
  • servers installed in data centers are operated for 24 hours regardless of the service usage time and the amount of access. Therefore, energy saving technology and efficient management technology are required.
  • the present invention has been made to solve the above problems, and an object of the present invention includes a power control device for receiving power usage information from a power splitter and setting a reference power usage of a server rack according to the power usage information.
  • the present invention provides a power management system and a power divider applied thereto.
  • a power management system includes: at least one power divider mounted on at least one server management device to sense power usage information of each server; And a power control device that receives the power usage information from the power divider and sets a reference power usage of the server management equipment according to the power usage information.
  • the power control device may calculate demand prediction data, which is data for predicting power demand for a specific period of time, using the power usage information.
  • the power control apparatus may be configured to set the reference power consumption for each server by using information on importance and usage time of each server.
  • the at least one power divider may detect temperature information of each server, and the power controller may determine whether to supply power to each server according to the temperature information of each server.
  • the power control apparatus may convert the power usage information into carbon emissions.
  • the apparatus may further include a remote control terminal remotely connected to the power control device and receiving and displaying power usage information stored in the power control device.
  • the power divider of the server management equipment is mounted at least one server, the power sensor unit for detecting power usage information of each of the at least one server; A power control unit controlling power of each server of the at least one server; Communication unit for performing wired and wireless communication with the external device; A controller configured to control the detected power usage information to be transmitted to the external device through the communication unit and to control power of each of the at least one server according to a control signal received from the external device; Include.
  • a power management system including a power control device that receives power usage information from a power divider and sets a reference power usage of a server rack according to the power usage information, and a power divider applied thereto This allows the power control device to identify and control the power consumption of each server. Accordingly, the power management system can predict power demand for each server, thereby reducing unnecessary power consumption and efficiently managing power of servers in the data center.
  • FIG. 1 is a diagram illustrating a structure of a power management system according to an embodiment of the present invention
  • FIG. 2 is a block diagram showing a configuration of a power divider 10 according to an embodiment of the present invention
  • FIG. 3 is a block diagram showing a detailed structure of the power control device 30, according to an embodiment of the present invention.
  • FIG. 4 is a block diagram showing the structure of a remote control terminal 60 according to an embodiment of the present invention.
  • FIG. 5 is a flowchart illustrating a process of collecting power-related information and a monitoring process according to an embodiment of the present invention
  • FIG. 6 is a flowchart illustrating a power management process using a remote control terminal according to an embodiment of the present invention.
  • the power management system includes at least one power divider 10, a gateway 20, a power control device 30, a terminal PC 40, an Ethernet / wireless network 50, and a remote control. It includes a terminal 60.
  • the power divider 10 is mounted in at least one server rack to sense power usage information and temperature information of each server.
  • the server rack is a server installation and management equipment in the form of a cabinet in which at least one server is mounted. And, one server rack is equipped with one power divider to supply and distribute power.
  • the power divider 10 detects how much power each of the servers mounted in the server rack generates power usage information for each server.
  • the power usage information includes information on how much power each server consumes (for example, daily, weekly, monthly, and yearly).
  • the power divider 10 senses the temperature of each of the servers mounted in the server rack to generate temperature information for each server.
  • the temperature information records the temperature of each server by time.
  • the power divider 10 transmits the power usage information and the temperature information to the power control device 30 through the gateway 20.
  • the power control device 30 receives the power usage information and temperature information from a power distributor, and calculates and sets a reference power usage of the server rack according to the power usage information and temperature information.
  • the power control device 30 predicts the demand for power usage by using the received power usage information and temperature information, and stores the predicted demand prediction data.
  • the demand forecast data represents a forecast value of power usage for the current period, and can be predicted using exponential smoothing during time series analysis, which is a method of predicting that the trend of past use is continuously reflected in the future. have.
  • Exponential smoothing is a method of increasing the accuracy of prediction by weighting data for the latest period among various periods.
  • the prediction principle applying the exponential smoothing method is as follows.
  • F t is the predicted value of t
  • F t-1 is the predicted value of t-1
  • a t-1 is actual value of t-1
  • a is the exponential smoothing coefficient
  • the power control apparatus 30 may calculate the demand forecast data for the current power usage by using the power usage and the forecast amount of the previous period according to the above formula.
  • the power control device 30 determines the reference power usage for each server using the calculated demand forecast data. In addition, the power control apparatus 30 sets a power usage schedule so as not to exceed the reference power usage set for each server, and predicts the total amount of power to be used in the corresponding period.
  • the power control device 30 receives information on the importance and utilization time zone for each server from the user. Then, the power control device 10 sets the reference power consumption in consideration of the input server importance and utilization time zone. In detail, the power control apparatus 10 sets the reference power usage higher for servers of higher importance than other servers. In addition, the power control apparatus 10 sets a high reference power consumption for a server corresponding to a time zone having a high utilization rate for each time zone. The power control device 30 corrects the set reference power usage by using information on importance and usage time of each server from the user.
  • the power control device 30 stores such server-specific power usage information, temperature information, server-specific demand forecast data, reference power usage, and corrected reference power usage in a database. Then, the power control device 30 schedules the amount of power supplied to each server for each time zone. In addition, the power control apparatus 30 transmits a power control signal for power control of each server to the power divider 10 of each server rack so that the power used by each server is controlled according to the scheduled power amount.
  • the power control device 30 calculates the carbon emissions information for each server by converting the power usage into carbon emissions by using the power usage information of each server. In addition, the power control device 30 stores carbon emission information for each time and server in a database.
  • the power control device 30 may automatically create a management document required by an enterprise or a public office such as a usage plan, a greenhouse gas emission report, and a comprehensive management report based on the information stored in the database, and store it in the database 31.
  • the power control device 30 periodically compares the power usage information and temperature information collected for each server with the reference power usage, and checks whether each server deviates from the reference power usage or safety temperature range. And, if there is a server that is out of the reference power consumption or the safe temperature range, the power control device 30 notifies the remote control terminal 60 to the terminal PC 40 or via the Ethernet / wireless communication network 50 Is displayed.
  • the power control device 30 may graph and display information stored in a database such as power usage information, carbon emission information, temperature information, and power demand prediction data collected through the terminal PC 40 on the screen. Therefore, the user can check the power related information through the graph displayed on the screen.
  • the terminal PC 40 displays information provided from the power control device 30 on a monitor and receives a command for controlling the power control device 30 from a user. That is, the user can check power usage information, carbon emission information, temperature information, power demand prediction data, etc. collected and calculated by the power control device 30 through the terminal PC 40.
  • the remote control terminal 60 is a terminal that communicates with the power control device 30 using an external communication network such as an Ethernet / wireless communication network 50.
  • the remote control terminal 60 receives a user authentication, information search, control command, etc. from the user. Then, the remote control terminal 60 makes a communication packet for the input command and transmits it to the power control device 30.
  • the remote control terminal 60 receives data received from the power control device 30 and displays it in the form of a graph or a table on the screen. Communication between the remote control terminal 60 and the power control device 30 transmits and receives only the value of the actual data required in the xml form. And, the remote control terminal 60 is displayed on the screen by transforming the value of the data into a form suitable for a small screen, thereby improving the readability of the user.
  • the power management system can predict power demand for each server, thereby reducing unnecessary power consumption and efficiently managing power of servers in the data center.
  • the power divider 10 includes a power sensor unit 11, a temperature sensor unit 12, a power control unit 13, a control unit 14, and a communication unit 15.
  • the power sensor unit 11 detects power usage information of each of the at least one server. Specifically, the power sensor unit 11 detects how much power each of the servers mounted in the server rack uses to generate power usage information for each server.
  • the power usage information includes information on how much power each server consumes (for example, daily, weekly, monthly, and yearly).
  • the temperature sensor unit 12 senses temperature information in each server of the at least one server. Specifically, the temperature sensor unit 12 detects the temperature of each of the servers mounted in the server rack to generate temperature information for each server. Here, the temperature information records the temperature of each server by time.
  • the power control unit 13 controls the power of each server of the at least one server under the control of the control unit 14. Specifically, the power control unit 13 controls the power supply amount of each server under the control of the control unit 14 to turn on / off the power.
  • the communication unit 15 performs wired and wireless communication with the power control device 30 through a gateway. In detail, the communication unit 15 transmits the detected power usage information and temperature information to the power control device 30.
  • the controller 14 controls the overall operation of the power divider 10.
  • the controller 14 controls the detected power usage information and temperature information to be transmitted to the power control device 30 through the communication unit 15.
  • the controller 15 controls the power controller 13 to control power of each of the at least one server according to a control signal received from an external device.
  • the controller 14 transmits the detected power usage information and temperature information to the external device, and adjusts the power supply amount of each server according to the control signal input from the external device. Therefore, the power divider 10 having such a structure can control the power supply amount of each server.
  • the power control device 30 includes a database 31, an external communication module 32, a user authentication module 33, a scheduling module 34, a statistical processing module 35, and a graph representation.
  • the power control device 30 may be a structure in which the above-described components are implemented in hardware, or may be a structure implemented in some software form.
  • the power control device 30 when implemented in the form of software, the power control device 30 has a computer-like structure, the user authentication module 33, scheduling module 34, statistical processing module 35, graph representation module 36 ), The carbon amount conversion module 37, and the document processing module 38 are implemented by the power control software to be executed by the CPU, the database 31 is implemented in a storage device such as a hard disk, an external communication module 32 is implemented as a wired or wireless LAN. That is, the function of the power control device 30 can be implemented in any of hardware and software.
  • the database 31 stores the power usage information, the carbon emission information, the temperature information, the power demand prediction data, the carbon emission information, etc. by database for each server and period.
  • the external communication module 32 communicates with the power divider 10, the terminal PC 40, and the remote control terminal 60.
  • the external communication module 32 receives power usage information and temperature information from the power distributor 10.
  • the external communication module 32 transmits power usage information, carbon emission information, temperature information, power demand prediction data, carbon emission information, and the like to the terminal PC 40 and the remote control terminal 60.
  • the external communication module 32 receives a control command for controlling the power control device 30 from the terminal PC 40 and the remote control terminal 60.
  • the user authentication module 33 functions to limit the access range of the database 31 through authentication of the user when the user accesses the power control device 30 from the outside. That is, the user authentication module 33 checks and sets a user's access authority using the user's ID.
  • the statistical processing module 35 calculates demand prediction data according to the received power usage information and temperature information, and sets the reference power usage of the server rack by using the same.
  • the demand forecast data represents the forecast amount of power usage for each server.
  • the reference power usage represents an upper limit of power consumption for each server set based on demand prediction data on power usage of each server and server rack.
  • the statistical processing module 35 predicts the demand for power usage by using the received power usage information and temperature information, and stores the predicted demand prediction data.
  • the demand forecast data represents a forecast value of power usage for the current period, and can be predicted using exponential smoothing during time series analysis, which is a method of predicting that the trend of past use is continuously reflected in the future. have.
  • Exponential smoothing is a method of increasing the accuracy of prediction by weighting data for the latest period among various periods.
  • the prediction principle applying the exponential smoothing method is as follows.
  • F t is the predicted value of t
  • F t-1 is the predicted value of t-1
  • a t-1 is actual value of t-1
  • a is the exponential smoothing coefficient
  • the statistical processing module 33 may calculate the demand forecast data for the current power usage by using the power usage and the forecast amount of the previous period according to the above formula. In addition, the statistical processing module 33 determines the reference power usage for each server using the calculated demand forecast data.
  • the scheduling module 34 sets a power usage schedule so as not to exceed the reference power usage set for each server, and adjusts the total amount of power to be used in the corresponding period. That is, the scheduling module 34 sets a reference power usage and sets an optimal power usage plan so as not to exceed the range.
  • the scheduling module 34 receives information on importance and utilization time zone of each server from the user. Then, the scheduling module 34 sets the reference power usage in consideration of the input server importance and utilization time zone. Specifically, the scheduling module 34 sets the reference power usage higher for servers of higher importance than other servers.
  • the scheduling module 34 sets a high reference power consumption for a server corresponding to a time zone having a high utilization rate for each time zone.
  • the scheduling module 34 corrects the set reference power usage by using information on importance and usage time of each server from the user.
  • the scheduling module 34 stores such server-specific power usage information, temperature information, server-specific demand forecast data, reference power usage, and corrected reference power usage in a database. And, the scheduling module 34 schedules the amount of power supplied to each server for each time zone. In addition, the scheduling module 34 transmits a power control signal for controlling power of each server to the power divider 10 of each server rack so that the power used of each server is controlled according to the scheduled power amount.
  • the carbon amount conversion module 37 calculates the carbon emission information for each server by converting the power consumption into carbon emissions by using the power usage information of each server.
  • the carbon amount conversion module 37 stores the carbon emission information for each time and server in the database 31.
  • the document processing module 38 may automatically create a management document required by an enterprise or a public office, such as a usage plan, a greenhouse gas emission report, and a comprehensive management report, based on the information stored in the database, and store it in the database 31.
  • a management document required by an enterprise or a public office such as a usage plan, a greenhouse gas emission report, and a comprehensive management report, based on the information stored in the database, and store it in the database 31.
  • the alarm module 39 periodically compares the power usage information and temperature information collected for each server with the reference power usage, and checks whether the standard power usage or the safe temperature range is out of each server. And, if there is a server that is out of the reference power consumption or the safe temperature range, the alarm module 39 notifies the remote control terminal 60 to the terminal PC 40 or via the Ethernet / wireless communication network 50. Display.
  • the graph expression module 36 may graph and display information stored in a database such as power usage information, carbon emission information, temperature information, and power demand prediction data collected through the terminal PC 40 on the screen. Therefore, the user can check the power related information through the graph displayed on the screen.
  • the power control device 30 having such a structure can receive power usage information and temperature information of each server from the power divider 10 installed in each server rack, so that the power consumption of each server can be checked and controlled. Will be. Accordingly, the power control device 30 can predict power demand for each server, thereby reducing unnecessary power consumption and efficiently managing power of servers in the data center.
  • the remote control terminal 60 includes an external communication module 61, a command processing module 62, an input module 63, a data processing module 64, a graph processing module 65, and An output module 66.
  • the external communication module 61 communicates with the power control device 30 using an external communication network such as an Ethernet / wireless communication network 50.
  • the input module 63 receives a user authentication, an information search, a control command, and the like from the user.
  • the command processing module 62 then generates a communication packet for these commands. Therefore, the external communication module 61 transmits the communication packet generated by the command processing module 52 to the power control device 30.
  • command processing module 62 classifies the received data for each packet and transmits the received data to the data processing module 64.
  • the data processing module 64 then processes the received data to perform a function appropriate to the processed data.
  • the graph processing module 65 processes the power usage information, the carbon emission information, the temperature information, the power demand prediction data, and the carbon emission information received from the power control device 30 in the form of a graph.
  • the output module 66 outputs the graph generated by the graph processing module to the screen.
  • the remote control terminal 60 remotely controls the power control device 30, and displays various information remotely. Therefore, the user can check the information on the power control device 30 and control the power control device 30 regardless of the place using the remote control terminal 60.
  • FIGS. 5 and 6 is a flowchart illustrating a power-related information collection process and a monitoring process according to an embodiment of the present invention.
  • the power control device 30 requests measurement information from the power distributor 10 (S510).
  • the measurement information indicates power usage information detected by the power sensor.
  • the power divider 10 transmits power usage information, which is measurement information, to the power control device 30 (S515).
  • the power control device 30 processes the usage information that is the received measurement information (S520).
  • the power control device 30 stores the processed measurement information in the database 31 (S525).
  • the power control device 30 requests the equipment status information from the power splitter 10 (S530).
  • the equipment state information here represents temperature information detected by the temperature sensor.
  • the power divider 10 transmits the temperature information, which is the equipment state information, to the power control device 30 (S535).
  • the power control device 30 stores the received equipment state information in the database 31 (S540).
  • the power control device 30 receives power usage information and temperature information of each server from the power distributor 10.
  • the power control device 30 generates various monitoring information using power usage information and temperature information.
  • the monitoring information represents information for monitoring information related to power usage, and represents the above-described demand forecast data, reference power usage, corrected reference power usage, carbon emission information, and scheduling information on power usage.
  • the terminal PC 40 When the monitoring information request command is input by the manager (S550), the terminal PC 40 requests the monitoring information to the power control device 30 (S553). Then, the power control device 30 inquires the monitoring information requested from the database 31 (S556). Then, the database 31 transmits the monitoring information requested for inquiry to the power control device 30 (S560). In addition, the power control device 30 returns the monitoring information received to the terminal PC 40 (S563). Thereafter, the terminal PC 40 displays the monitoring information on the screen in response to the monitoring information request for confirmation of the administrator (S566).
  • the power management system collects various measurement information and equipment status information, generates monitoring information related thereto, and displays it to the manager.
  • FIG. 6 is a flowchart illustrating a power management process using a remote control terminal according to an embodiment of the present invention.
  • the remote control terminal 60 periodically requests power usage, carbon emissions, and temperature information from the power control device 30 through the Ethernet / wireless communication network 50 (S610 and S615). Then, in response to this, the power control device 30 transmits power usage, carbon emissions, and temperature information to the remote control terminal 60 through the Ethernet / wireless communication network 50 (S620 and S625).
  • the power control device 30 transmits the alarm information to the remote control terminal 60 through the Ethernet / wireless communication network 50 (S630, S635). Then, the remote control terminal 60 provides the user with a sound alarm or a message alarm indicating that there is an error in the server (S638).
  • the user confirms that there is an abnormality in the power of the server based on the alarm, and inputs a command for requesting server control using the remote control terminal 60 (S640). Then, the remote control terminal 60 transmits the input server control request to the power control device 30 via the Ethernet / wireless communication network 50 (S642, S644). Then, the power control device 30 generates a control signal corresponding to the input server control request and transmits to the power divider 10 (S646).
  • the power divider 10 controls the power of the server according to the control signal corresponding to the server control request, and notifies the power control device 30 of the result thereof (S650). Then, the power control device 30 transmits the control result to the remote control terminal 60 through the Ethernet / wireless communication network 50 (S653, S656). Then, the remote control terminal 60 is provided to the user by displaying the control result on the screen (S659).
  • the user can check the alarm through the remote control terminal 60, it is possible to control the power of the server using the remote control terminal 60 in accordance with the alarm.
  • the power control device 30 may be any device that controls the use of power by using the information provided from the power divider 10.
  • the power control device 30 may be a computer device such as a workstation, a notebook computer, or may be an independent power control device.
  • the technical idea of the present invention can be applied to a computer-readable recording medium containing a computer program for performing the function of the power control device 30 according to the present embodiment.
  • the technical idea according to various embodiments of the present disclosure may be implemented in the form of computer readable codes recorded on a computer readable recording medium.
  • the computer-readable recording medium can be any data storage device that can be read by a computer and can store data.
  • the computer-readable recording medium may be a ROM, a RAM, a CD-ROM, a magnetic tape, a floppy disk, an optical disk, a hard disk drive, or the like.
  • the computer-readable code or program stored in the computer-readable recording medium may be transmitted through a network connected between the computers.

Abstract

전력 관리 시스템 및 이에 적용되는 전력 분배기가 제공된다. 본 전력 관리 시스템은 전력 분배기로부터 전력 사용량 정보를 수신하고 전력 사용량 정보에 따라 서버 랙의 기준 전력 사용량을 설정하는 전력 관제 장치를 포함한다. 이에 따라, 전력 관제 장치는 서버 각각의 전력 소비량을 확인 및 제어할 수 있게 된다. 그리고, 전력 관리 시스템은 서버별로 전력 수요를 예측할 수 있게 되어, 불필요한 전력 소모를 줄이고 데이터 센터의 서버들의 전력을 효율적으로 관리할 수 있게 된다.

Description

전력 관리 시스템 및 이에 적용되는 전력 분배기
본 발명은 전력 관리 시스템 및 이에 적용되는 전력 분배기에 관한 것으로, 더욱 상세하게는, 서버 랙에 설치된 서버들의 전력을 관리하기 위한 전력 관리 시스템 및 이에 적용되는 전력 분배기에 관한 것이다.
일반적으로 데이터센터에 설치된 서버의 경우에는 서비스의 사용시간 및 접속량과 상관없이 24시간 가동되고 있음에 따라 에너지 절감 기술 및 효율적인 관리 기술이 필요하다.
특히, 데이터센터를 운영하기 위해서는 필수적으로 전력을 대량으로 소모하며 IT 분야의 기술의 발달과 사용자들의 요구가 높아짐에 따라 이용 비용 또한 동시에 급증하고 있는 추세이다. 2006년 미국내 데이터 센터들의 전력소모량은 610억 KWh이며, 그 비용은 45억 달러 수준으로 이는 미국 580만 가정의 전력 사용량과 맞먹는 수준이다. 이런 추세로 2011년에는 1000억 KWh를 소모할것으로 예산 되며 그중 대기 전력이 소모하는 비율을 전체 사용량의 25%이상을 차지 할것으로 예상됨에 따라 효율적인 관리가 그 어느 분야보다 더 필요로 하고 있다.
국내의 경우 데이터 센터의 대부분은 전력량을 모니터링 하고 있다. 하지만, 전력량의 모니터링 방법이 단순히 건물 전체의 총 사용량을 모니터링 하는데 그치고 있는 실정이다. 이에 따라, 더욱 효율적으로 전력량을 모니터링하기 위한 방안의 모색이 요청된다.
본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 본 발명의 목적은, 전력 분배기로부터 전력 사용량 정보를 수신하고 전력 사용량 정보에 따라 서버 랙의 기준 전력 사용량을 설정하는 전력 관제 장치를 포함하는 전력 관리 시스템 및 이에 적용되는 전력 분배기를 제공함에 있다.
상기 목적을 달성하기 위한 본 발명의 일 실시예에 따른, 전력 관리 시스템은, 적어도 하나의 서버 관리 장비에 장착되어 각 서버의 전력 사용량 정보를 감지하는 적어도 하나의 전력 분배기; 및 상기 전력 분배기로부터 상기 전력 사용량 정보를 수신하고, 상기 전력 사용량 정보에 따라 상기 서버 관리 장비의 기준 전력 사용량을 설정하는 전력 관제 장치;를 포함한다.
그리고, 상기 전력 관제 장치는, 상기 전력 사용량 정보를 이용하여, 특정 기간에 대한 전력 수요를 예측한 데이터인 수요 예측 데이터를 산출할 수도 있다.
또한, 상기 전력 관제 장치는, 다음의 수식 Ft = Ft-1 + a(At-1 - Ft-1) (여기에서, Ft 는 t기의 예측값, Ft-1 는 t-1기의 예측값, At-1 는 t-1기의 실제 사용값, a는 지수 평활 계수) 을 이용하여 상기 특정 기간(t기)에 대한 상기 수요 예측 데이터를 산출할 수도 있다.
그리고, 상기 전력 관제 장치는, 서버별 중요도 및 활용 시간대에 대한 정보를 이용하여 상기 서버별 기준 전력 사용량을 설정하는 것을 특징으로 할 수도 있다.
또한, 상기 적어도 하나의 전력 분배기는, 각 서버의 온도 정보를 감지하고, 상기 전력 관제 장치는, 상기 각 서버의 온도 정보에 따라 각 서버의 전력 공급 여부를 결정할 수도 있다.
그리고, 상기 전력 관제 장치는, 상기 전력 사용량 정보를 탄소 배출량으로 환산할 수도 있다.
또한, 상기 전력 관제 장치에 원격으로 접속하고, 상기 전력 관제 장치에 저장된 전력 사용량 정보를 수신하여 디스플레이하는 원격 제어 단말;을 더 포함할 수도 있다.
한편, 본 발명의 일 실시예에 따른, 적어도 하나의 서버가 마운트된 서버 관리 장비의 전력 분배기는, 상기 적어도 하나의 서버 각각의 전력 사용량 정보를 감지하는 전력 센서부; 상기 적어도 하나의 서버 각각의 서버의 전원을 제어하는 전원 제어부; 외부 장치와 유무선 통신을 수행하는 통신부; 상기 감지된 전력 사용량 정보가 상기 통신부를 통해 상기 외부 장치로 전송되도록 제어하고, 상기 외부 장치로부터 수신된 제어신호에 따라 상기 적어도 하나의 서버 각각의 전원을 제어하도록 상기 전원 제어부를 제어하는 제어부;를 포함한다.
본 발명의 다양한 실시예에 따르면, 전력 분배기로부터 전력 사용량 정보를 수신하고 전력 사용량 정보에 따라 서버 랙의 기준 전력 사용량을 설정하는 전력 관제 장치를 포함하는 전력 관리 시스템 및 이에 적용되는 전력 분배기를 제공할 수 있게 되어, 전력 관제 장치는 서버 각각의 전력 소비량을 확인 및 제어할 수 있게 된다. 이에 따라, 전력 관리 시스템은 서버별로 전력 수요를 예측할 수 있게 되어, 불필요한 전력 소모를 줄이고 데이터 센터의 서버들의 전력을 효율적으로 관리할 수 있게 된다.
도 1은 본 발명의 일 실시예에 따른, 전력 관리 시스템의 구조를 도시한 도면,
도 2는 본 발명의 일 실시예에 따른, 전력 분배기(10)의 구성을 도시한 블럭도,
도 3은 본 발명의 일 실시예에 따른, 전력 관제 장치(30)의 상세한 구조를 도시한 블럭도,
도 4는 본 발명의 일 실시예에 따른, 원격 제어 단말(60)의 구조를 도시한 블럭도,
도 5는 본 발명의 일 실시예에 따른, 전력 관련 정보 수집 과정 및 모니터링 과정을 설명하기 위한 흐름도,
도 6은 본 발명의 일 실시예에 따른, 원격 제어 단말을 이용한 전력 관리 과정을 설명하기 위한 흐름도이다.
이하에서는 도면을 참조하여 본 발명을 보다 상세하게 설명한다.
도 1은 본 발명의 일 실시예에 따른, 전력 관리 시스템의 구조를 도시한 도면이다. 도 1에 도시된 바와 같이, 전력 관리 시스템은 적어도 하나의 전력 분배기(10), 게이트웨이(20), 전력 관제 장치(30), 단말 PC(40), 이더넷/무선 통신망(50), 및 원격 제어 단말(60)을 포함한다.
전력 분배기(10)는 적어도 하나의 서버 랙(rack)에 장착되어 각 서버의 전력 사용량 정보 및 온도 정보를 감지한다. 여기에서, 서버 랙은 적어도 하나의 서버가 마운트되는 캐비넷 형태의 서버 설치 및 관리 장비이다. 그리고, 하나의 서버 랙에는 전원을 공급 및 분배하기 위해 전력 분배기가 하나씩 장착된다.
이 때, 전력 분배기(10)는 서버 랙에 마운트된 서버들 각각이 어느 정도의 전력을 사용하는지를 감지하여 각 서버에 대한 전력 사용량 정보를 생성한다. 여기에서, 전력 사용량 정보는 각 서버의 전력을 어느정도 소모하는지에 대한 정보가 기간별(예를 들어, 일별, 주별, 월별, 연간)로 포함되어 있다.
또한, 전력 분배기(10)는 서버 랙에 마운트된 서버들 각각의 온도를 감지하여 각 서버에 대한 온도 정보를 생성한다. 여기에서, 온도 정보는 각 서버의 온도가 시간별로 기록되어 있다.
그리고, 전력 분배기(10)는 게이트웨이(20)를 통해 전력 사용량 정보 및 온도 정보를 전력 관제 장치(30)로 전송한다. 전력 관제 장치(30)는 전력 분배기로부터 상기 전력 사용량 정보 및 온도 정보를 수신하고, 상기 전력 사용량 정보 및 온도 정보에 따라 상기 서버 랙의 기준 전력 사용량을 산출 및 설정한다.
그리고, 전력 관제 장치(30)는 수신된 전력 사용량 정보 및 온도 정보를 이용하여 전력 사용량에 대한 수요를 예측하고, 예측된 수요 예측 데이터를 저장한다. 여기에서, 수요 예측 데이터는 현재 기간에 대한 전력 사용량에 대한 예측값을 나타내며, 과거의 사용의 경향이 장래에도 계속 반영된다는 점을 전제로 예측하는 방법인 시계열 분석 중 지수 평활법을 이용하여 예측될 수 있다. 지수 평활법은 다양한 기간 중 최근 기간에 대한 데이터에 가중치를 두어 예측의 정확도를 높이는 방법에 해당된다. 지수 평활법을 적용한 예측 원리는 아래와 같다.
당기 전력 예측값 = a * 전기 실제 전력 사용값 + (1-a) * 전기 전력 예측값
이와 같은 원리를 수식으로 표현하면 아래와 같다.
Ft = Ft-1 + a(At-1 - Ft-1)
여기에서,
Ft 는 t기의 예측값
Ft-1 는 t-1기의 예측값
At-1 는 t-1기의 실제 사용값
a는 지수 평활 계수
전력관제 장치(30)는 이와같은 수식에 따라, 이전 기간의 전력 사용량 및 예측량을 이용하여 현재의 전력 사용량에 대한 수요 예측 데이터를 산출할 수 있게 된다.
그리고, 전력관제 장치(30)는 산출된 수요 예측 데이터를 이용하여 각 서버에 대한 기준 전력 사용량을 결정하게 된다. 그리고, 전력관제 장치(30)는 각 서버별로 설정된 기준 전력 사용량을 초과하지 않도록 전력 사용 스케줄을 설정하여, 해당 기간에 사용될 총 전력량을 예측하게 된다.
또한, 전력관제 장치(30)는 사용자로부터 각 서버별 중요도 및 활용 시간대에 대한 정보를 입력받는다. 그러면, 전력관제 장치(10)는 입력된 서버별 중요도 및 활용 시간대를 고려하여, 기준 전력 사용량을 설정한다. 구체적으로, 전력 관제 장치(10)는 중요도가 높은 서버에 대해서는 다른 서버들보다 기준 전력 사용량을 높게 설정하게 된다. 또한, 전력 관제 장치(10)는 각 시간대 별로, 활용률이 높은 시간대에 해당되는 서버에 대해 기준 전력 사용량을 높게 설정하게 된다. 전력관제 장치(30)는 사용자로부터 각 서버별 중요도 및 활용 시간대에 대한 정보를 이용하여 설정된 기준 전력 사용량을 보정하게 된다.
그리고, 전력관제 장치(30)는 이와 같은 서버별 전력 사용량 정보, 온도 정보, 서버별 수요 예측 데이터, 기준 전력 사용량 및 보정된 기준 전력 사용량을 데이터베이스에 저장하게 된다. 그리고, 전력 관제 장치(30)는 시간대별로 각 서버에 공급되는 전력량을 스케쥴링하게 된다. 그리고, 전력 관제 장치(30)는 스케쥴링된 전력량에 따라 각 서버의 사용 전력이 제어되도록 각 서버 랙의 전력 분배기(10)에 각 서버의 전력 제어를 위한 전력 제어신호를 전송한다.
또한, 전력 관제 장치(30)는 각 서버의 전력 사용량 정보를 이용하여, 전력 사용량을 탄소 배출량으로 환산하여 시간별 서버별 탄소 배출량 정보를 산출하게 된다. 그리고, 전력 관제 장치(30)는 시간별, 서버별 탄소 배출량 정보를 데이터 베이스에 저장한다.
그리고, 전력 관제 장치(30)는 데이터베이스에 저장된 정보를 바탕으로 사용계획서, 온실가스 배출보고서, 관리종합보고서 등 기업이나 관공서에서 필요한 관리 문서를 자동을 작성하여 데이터 베이스(31)에 저장할 수도 있다.
또한, 전력 관제 장치(30)는 주기적으로 각 서버별로 수집된 전력 사용량 정보 및 온도 정보를 기준 전력 사용량과 비교하여, 각 서버별로 기준 전력 사용량 또는 안전 온도 범위를 벗어나는지를 확인한다. 그리고, 전력 관제 장치(30)는 기준 전력 사용량 또는 안전 온도 범위를 벗어나는 서버가 존재하는 경우, 단말 PC(40)에 또는 이를 이더넷/무선 통신망(50)을 통해 원격 제어 단말(60)에 알림 메시지를 표시한다.
그리고, 전력 관제 장치(30)는 단말 PC(40)를 통해 수집된 전력 사용량 정보, 탄소 배출량 정보, 온도 정보, 전력 수요 예측 데이터 등의 데이터베이스에 저장된 정보를 그래프화하여 화면에 표시할 수도 있다. 따라서, 사용자는 화면에 표시되는 그래프를 통해 전력에 관련된 정보들을 확인할 수 있게 된다.
단말 PC(40)는 전력 관제 장치(30)에서 제공되는 정보를 모니터에 표시하고, 사용자로부터 전력 관제 장치(30)를 제어하기 위한 명령을 입력받는다. 즉, 사용자는 단말 PC(40)를 통해 전력 관제 장치(30)에서 수집 및 산출된 전력 사용량 정보, 탄소 배출량 정보, 온도 정보, 전력 수요 예측 데이터 등을 확인할 수 있게 된다.
원격 제어 단말(60)은 이더넷/무선 통신망(50) 등의 외부 통신망을 사용하여 전력 관제 장치(30)와 통신을 하는 단말이다. 원격 제어 단말(60)은 사용자로부터 사용자 인증, 정보검색, 제어 명령등을 입력받는다. 그러면, 원격 제어 단말(60)은 입력된 명령에 대한 통신 패킷을 만들어 전력 관제 장치(30)로 전송한다.
또한, 원격 제어 단말(60)은 전력 관제 장치(30)로부터 수신되는 데이터를 입력 받아 화면에 그래프 또는 표 형태로 표시한다. 원격 제어 단말(60)과 전력 관제 장치(30) 간의 통신은 xml형태로 필요한 실제 데이터의 값만을 송수신한다. 그리고, 원격 제어 단말(60)은 그 데이터의 값을 소형 화면에 적합한 형태로 변형 시켜 줌으로써 화면에 표시하여, 사용자의 가독성을 높여주게 된다.
이와 같은 전력 관리 시스템에 따르면, 각각의 서버 랙에 설치된 전력 분배기(10)를 이용하여 서버 각각의 전력 사용량 정보 및 온도 정보를 감지할 수 있게 되어, 전력 관제 장치(30)는 서버 각각의 전력 소비량을 확인 및 제어할 수 있게 된다. 이에 따라, 전력 관리 시스템은 서버별로 전력 수요를 예측할 수 있게 되어, 불필요한 전력 소모를 줄이고 데이터 센터의 서버들의 전력을 효율적으로 관리할 수 있게 된다.
도 2는 본 발명의 일 실시예에 따른, 전력 분배기(10)의 구성을 도시한 블럭도이다. 도 2에 도시된 바와 같이, 전력 분배기(10)는 전력 센서부(11), 온도 센서부(12), 전원 제어부(13), 제어부(14), 및 통신부(15)를 포함한다.
전력 센서부(11)는 적어도 하나의 서버 각각의 전력 사용량 정보를 감지한다. 구체적으로, 전력 센서부(11)는 서버 랙에 마운트된 서버들 각각이 어느 정도의 전력을 사용하는지를 감지하여 각 서버에 대한 전력 사용량 정보를 생성한다. 여기에서, 전력 사용량 정보는 각 서버의 전력을 어느정도 소모하는지에 대한 정보가 기간별(예를 들어, 일별, 주별, 월별, 연간)로 포함되어 있다.
그리고, 온도 센서부(12)는 적어도 하나의 서버 각각의 서버 내의 온도 정보를 감지한다. 구체적으로, 온도 센서부(12)는 서버 랙에 마운트된 서버들 각각의 온도를 감지하여 각 서버에 대한 온도 정보를 생성한다. 여기에서, 온도 정보는 각 서버의 온도가 시간별로 기록되어 있다.
전원 제어부(13)는 제어부(14)의 제어에 따라 적어도 하나의 서버 각각의 서버의 전원을 제어한다. 구체적으로, 전원 제어부(13)는 제어부(14)의 제어에 따라, 각 서버의 전력 공급량을 제어하고 전원을 온/오프 하게 된다.
통신부(15)는 게이트웨이를 통해 전력 관제 장치(30)와 유무선 통신을 수행한다. 구체적으로, 통신부(15)는 감지된 전력 사용량 정보 및 온도 정보를 전력 관제 장치(30)로 전송하게 된다.
제어부(14)는 전력 분배기(10)의 동작 전반을 제어한다. 구체적으로, 제어부(14)는 감지된 전력 사용량 정보 및 온도 정보가 통신부(15)를 통해 전력 관제 장치(30)로 전송되도록 제어한다. 그리고, 제어부(15)는 외부 장치로부터 수신된 제어신호에 따라 적어도 하나의 서버 각각의 전원을 제어하도록 전원 제어부(13)를 제어하게 된다.
이와 같이, 제어부(14)는 감지된 전력 사용량 정보와 온도 정보를 외부 기기로 전송하고, 외부 기기에서 입력된 제어신호에 따라 각 서버의 전력 공급량을 조절하게 된다. 따라서, 이와 같은 구조의 전력 분배기(10)는 서버 각각의 전력 공급량을 제어할 수 있게 된다.
도 3은 본 발명의 일 실시예에 따른, 전력 관제 장치(30)의 상세한 구조를 도시한 블럭도이다. 도 3에 도시된 바와 같이, 전력 관제 장치(30)는 데이터 베이스(31), 외부 통신 모듈(32), 사용자 인증 모듈(33), 스케줄링 모듈(34), 통계 처리 모듈(35), 그래프 표현 모듈(36), 탄소량 변환 모듈(37), 및 문서 처리 모듈(38)을 포함한다.
여기에서, 전력 관제 장치(30)는 상술된 구성요소들이 하드웨어로 구현된 구조가 될 수도 있고, 일부 소프트웨어 형태로 구현된 구조가 될 수도 있다. 구체적으로, 소프트웨어 형태로 구현된 경우, 전력 관제 장치(30)는 컴퓨터와 같은 구조를 가지게 되고, 사용자 인증 모듈(33), 스케줄링 모듈(34), 통계 처리 모듈(35), 그래프 표현 모듈(36), 탄소량 변환 모듈(37), 및 문서 처리 모듈(38)은 전력 관제 소프트웨어로 구현되어 CPU에 의해 실행되게 되며, 데이터 베이스(31)는 하드 디스크 등의 저장장치에 구현되며, 외부 통신 모듈(32)은 유무선 랜 등으로 구현되게 된다. 즉, 전력 관제 장치(30)의 기능은 하드웨어 및 소프트웨어 중 어느 것으로도 구현될 수 있게 된다.
데이터 베이스(31)는 전력 사용량 정보, 탄소 배출량 정보, 온도 정보, 전력 수요 예측 데이터, 탄소 배출량 정보 등을 각 서버별, 기간별로 데이터베이스화하여 저장한다.
외부 통신 모듈(32)은 전력 분배기(10), 단말 PC(40) 및 원격 제어 단말(60)과 통신을 수행한다. 구체적으로, 외부 통신 모듈(32)은 전력 분배기(10)로부터 전력 사용량 정보 및 온도 정보를 수신한다. 또한, 외부 통신 모듈(32)은 단말 PC(40) 및 원격 제어 단말(60)로 전력 사용량 정보, 탄소 배출량 정보, 온도 정보, 전력 수요 예측 데이터, 탄소 배출량 정보 등을 전송한다. 그리고, 외부 통신 모듈(32)은 단말 PC(40) 및 원격 제어 단말(60)로부터 전력 관제 장치(30)의 제어를 위한 제어 명령을 입력받는다.
사용자 인증 모듈(33)은 외부에서 사용자가 전력 관제 장치(30)에 접속시 사용자에 대한 인증을 통해 데이터 베이스(31)의 접근 범위를 제한해주는 기능을 한다. 즉, 사용자 인증 모듈(33)은 사용자의 아이디를 이용하여 사용자의 접근 권한을 확인하여 설정하게 된다.
통계처리 모듈(35)은 수신된 전력 사용량 정보 및 온도 정보에 따라 수요 예측 데이터를 산출하고, 이를 이용하여 서버 랙의 기준 전력 사용량을 설정한다. 여기에서, 수요 예측 데이터는 각 서버별 전력 사용의 예측량을 나타낸다. 그리고, 기준 전력 사용량은 각 서버 및 서버랙의 전력 사용에 대한 수요 예측 데이터를 바탕으로 설정된 서버별 전력 사용량의 상한을 나타낸다.
구체적으로, 통계처리 모듈(35)은 수신된 전력 사용량 정보 및 온도 정보를 이용하여 전력 사용량에 대한 수요를 예측하고, 예측된 수요 예측 데이터를 저장한다. 여기에서, 수요 예측 데이터는 현재 기간에 대한 전력 사용량에 대한 예측값을 나타내며, 과거의 사용의 경향이 장래에도 계속 반영된다는 점을 전제로 예측하는 방법인 시계열 분석 중 지수 평활법을 이용하여 예측될 수 있다. 지수 평활법은 다양한 기간 중 최근 기간에 대한 데이터에 가중치를 두어 예측의 정확도를 높이는 방법에 해당된다. 지수 평활법을 적용한 예측 원리는 아래와 같다.
당기 전력 예측값 = a * 전기 실제 전력 사용값 + (1-a) * 전기 전력 예측값
이와 같은 원리를 수식으로 표현하면 아래와 같다.
Ft = Ft-1 + a(At-1 - Ft-1)
여기에서,
Ft 는 t기의 예측값
Ft-1 는 t-1기의 예측값
At-1 는 t-1기의 실제 사용값
a는 지수 평활 계수
통계 처리 모듈(33)은 이와같은 수식에 따라, 이전 기간의 전력 사용량 및 예측량을 이용하여 현재의 전력 사용량에 대한 수요 예측 데이터를 산출할 수 있게 된다. 그리고, 통계 처리 모듈(33)은 산출된 수요 예측 데이터를 이용하여 각 서버에 대한 기준 전력 사용량을 결정하게 된다.
스케줄링 모듈(34)은 각 서버별로 설정된 기준 전력 사용량을 초과하지 않도록 전력 사용 스케줄을 설정하여, 해당 기간에 사용될 총 전력량을 조절하게 된다. 즉, 스케줄링 모듈(34)은 기준 전력 사용량을 정하여 그 범위를 초과하지 않도록 최적의 전력 사용 계획을 설정하게 된다.
그리고, 스케줄링 모듈(34)은 사용자로부터 각 서버별 중요도 및 활용 시간대에 대한 정보를 입력받는다. 그러면, 스케줄링 모듈(34)은 입력된 서버별 중요도 및 활용 시간대를 고려하여, 기준 전력 사용량을 설정한다. 구체적으로, 스케줄링 모듈(34)은 중요도가 높은 서버에 대해서는 다른 서버들보다 기준 전력 사용량을 높게 설정하게 된다.
또한, 스케줄링 모듈(34)은 각 시간대 별로, 활용률이 높은 시간대에 해당되는 서버에 대해 기준 전력 사용량을 높게 설정하게 된다. 스케줄링 모듈(34)은 사용자로부터 각 서버별 중요도 및 활용 시간대에 대한 정보를 이용하여 설정된 기준 전력 사용량을 보정하게 된다.
그리고, 스케줄링 모듈(34)은 이와 같은 서버별 전력 사용량 정보, 온도 정보, 서버별 수요 예측 데이터, 기준 전력 사용량 및 보정된 기준 전력 사용량을 데이터베이스에 저장하게 된다. 그리고, 스케줄링 모듈(34)은 시간대별로 각 서버에 공급되는 전력량을 스케쥴링하게 된다. 그리고, 스케줄링 모듈(34)은 스케쥴링된 전력량에 따라 각 서버의 사용 전력이 제어되도록 각 서버 랙의 전력 분배기(10)에 각 서버의 전력 제어를 위한 전력 제어신호를 전송한다.
탄소량 변환모듈(37)은 각 서버의 전력 사용량 정보를 이용하여, 전력 사용량을 탄소 배출량으로 환산하여 시간별 서버별 탄소 배출량 정보를 산출하게 된다. 그리고, 탄소량 변환모듈(37)은 시간별, 서버별 탄소 배출량 정보를 데이터 베이스(31)에 저장한다.
그리고, 문서 처리 모듈(38)은 데이터베이스에 저장된 정보를 바탕으로 사용계획서, 온실가스 배출보고서, 관리종합보고서 등 기업이나 관공서에서 필요한 관리 문서를 자동을 작성하여 데이터 베이스(31)에 저장할 수도 있다.
또한, 알람 모듈(39)은 주기적으로 각 서버별로 수집된 전력 사용량 정보 및 온도 정보를 기준 전력 사용량과 비교하여, 각 서버별로 기준 전력 사용량 또는 안전 온도 범위를 벗어나는지를 확인한다. 그리고, 알람 모듈(39)은 기준 전력 사용량 또는 안전 온도 범위를 벗어나는 서버가 존재하는 경우, 단말 PC(40)에 또는 이를 이더넷/무선 통신망(50)을 통해 원격 제어 단말(60)에 알림 메시지를 표시한다.
그리고, 그래프 표현모듈(36)은 단말 PC(40)를 통해 수집된 전력 사용량 정보, 탄소 배출량 정보, 온도 정보, 전력 수요 예측 데이터 등의 데이터베이스에 저장된 정보를 그래프화하여 화면에 표시할 수도 있다. 따라서, 사용자는 화면에 표시되는 그래프를 통해 전력에 관련된 정보들을 확인할 수 있게 된다.
이와 같은 구조의 전력 관제 장치(30)는 각각의 서버 랙에 설치된 전력 분배기(10)로부터 서버 각각의 전력 사용량 정보 및 온도 정보를 수신할 수 있게 되어, 서버 각각의 전력 소비량을 확인 및 제어할 수 있게 된다. 이에 따라, 전력 관제 장치(30)는 서버별로 전력 수요를 예측할 수 있게 되어, 불필요한 전력 소모를 줄이고 데이터 센터의 서버들의 전력을 효율적으로 관리할 수 있게 된다.
도 4는 본 발명의 일 실시예에 따른, 원격 제어 단말(60)의 구조를 도시한 블럭도이다. 도 4에 도시된 바와 같이, 원격 제어 단말(60)은 외부 통신 모듈(61), 명령 처리 모듈(62), 입력 모듈(63), 데이터 처리 모듈(64), 그래프 처리 모듈(65), 및 출력 모듈(66)을 포함한다.
외부 통신 모듈(61)은 이더넷/무선 통신망(50) 등의 외부 통신망을 사용하여 전력 관제 장치(30)와 통신을 한다. 입력 모듈(63)은 사용자로부터 사용자 인증, 정보검색, 제어 명령등을 입력받는다. 그러면, 명령 처리 모듈(62)은 이와 같은 명령들에 대한 통신 패킷을 생성한다. 따라서, 외부 통신 모듈(61)은 명령 처리 모듈(52)에 의해 생성된 통신 패킷을 전력 관제 장치(30)로 전송하게 된다.
또한, 명령 처리 모듈(62)은 수신된 데이터를 패킷별로 분류하여 데이터 처리 모듈(64)로 전송한다. 그러면, 데이터 처리 모듈(64)는 수신된 데이터를 처리하여 처리된 데이터에 적합한 기능을 수행하게 된다.
그래프 처리 모듈(65)은 전력 관제 장치(30)로부터 수신된 전력 사용량 정보, 탄소 배출량 정보, 온도 정보, 전력 수요 예측 데이터, 탄소 배출량 정보 등을 그래프 형태로 처리한다. 그리고, 출력 모듈(66)은 상기 그래프 처리 모듈에서 생성된 그래프를 화면에 출력하게 된다.
이와 같이, 원격 제어 단말(60)은 전력 관제 장치(30)를 원격으로 제어하고, 다양한 정보를 원격으로 디스플레이하게 된다. 따라서, 사용자는 원격 제어 단말(60)을 이용하여 장소에 구애받지 않고 전력 관제 장치(30)에 대한 정보를 확인하고 전력 관제 장치(30)를 제어할 수 있게 된다.
이하에서는, 도 5 및 도 6을 참고하여, 전력 관리 시스템의 동작 과정에 대해 설명한다. 도 5는 본 발명의 일 실시예에 따른, 전력 관련 정보 수집 과정 및 모니터링 과정을 설명하기 위한 흐름도이다.
전력 관제 장치(30)는 전력 분배기(10)에 측정 정보를 요청한다(S510). 여기에서 측정 정보는 전력 센서에 의해 감지된 전력 사용량 정보를 나타낸다. 그러면, 전력 분배기(10)는 측정 정보인 전력 사용량 정보를 전력 관제 장치(30)로 전송하게 된다(S515). 그러면, 전력 관제 장치(30)는 수신된 측정 정보인 사용량 정보를 처리한다(S520). 그리고, 전력 관제 장치(30)는 처리된 측정 정보를 데이터 베이스(31)에 저장한다(S525).
또한, 전력 관제 장치(30)는 전력 분배기(10)에 장비 상태 정보를 요청한다(S530). 여기에서 장비 상태 정보는 온도 센서에 의해 감지된 온도 정보를 나타낸다. 그러면, 전력 분배기(10)는 장비 상태 정보인 온도 정보를 전력 관제 장치(30)로 전송하게 된다(S535). 그러면, 전력 관제 장치(30)는 수신된 장비 상태 정보를 데이터 베이스(31)에 저장한다(S540).
이와 같은 과정을 통해 전력 관제 장치(30)는 전력 분배기(10)로부터 각 서버의 전력 사용량 정보 및 온도 정보를 수신하게 된다. 그리고, 전력 관제 장 치(30)는 전력 사용량 정보 및 온도 정보를 이용하여 다양한 모니터링 정보를 생성한다. 여기에서, 모니터링 정보는 전력 사용에 관련된 정보들을 모니터링하기 위한 정보를 나타내는 것으로, 상술한 수요 예측 데이터, 기준 전력 사용량, 보정된 기준 전력 사용량, 탄소 배출량 정보, 전력 사용에 대한 스케쥴링 정보 등을 나타낸다.
관리자에 의해 모니터링 정보 요청 명령이 입력되면(S550), 단말 PC(40)는 전력 관제 장치(30)로 모니터링 정보를 요청하게 된다(S553). 그러면, 전력 관제 장치(30)는 데이터 베이스(31)에서 요청된 모니터링 정보를 조회하게 된다(S556). 그러면, 데이터 베이스(31)는 조회가 요청된 모니터링 정보를 전력 관제 장치(30)로 전송한다(S560). 그리고, 전력 관제 장치(30)는 단말 PC(40)로 수신된 모니터링 정보를 반환하게 된다(S563). 그 후에, 단말 PC(40)는 모니터링 정보 요청에 대한 응답으로, 관리자의 확인을 위해 모니터링 정보를 화면에 표시하게 된다(S566).
이와 같은 과정을 통해, 전력 관리 시스템은 다양한 측정 정보 및 장비 상태 정보를 수집하고, 이에 관련된 모니터링 정보를 생성하여 관리자에게 디스플레이하게 된다.
도 6은 본 발명의 일 실시예에 따른, 원격 제어 단말을 이용한 전력 관리 과정을 설명하기 위한 흐름도이다.
원격 제어 단말(60)은 전력 사용량, 탄소 배출량, 및 온도 정보를 이더넷/무선 통신망(50)을 통해 전력 관제 장치(30)에 주기적으로 요청한다(S610, S615). 그러면, 이에 대한 응답으로 전력 관제 장치(30)는 전력 사용량, 탄소 배출량, 및 온도 정보를 이더넷/무선 통신망(50)을 통해 원격 제어 단말(60)로 전송하게 된다(S620, S625).
또한, 전력 관제 장치(30)는 서버의 전력에 문제가 발생한 경우, 알람 정보를 이더넷/무선 통신망(50)을 통해 원격 제어 단말(60)로 전송한다(S630, S635). 그러면, 원격 제어 단말(60)은 서버에 이상이 있음을 알리는 소리 알람 또는 메시지 알람을 사용자에게 제공하게 된다(S638).
사용자는 알람을 바탕으로 서버의 전력에 이상이 있음을 확인하고, 원격 제어 단말(60)을 이용하여 서버 제어를 요청 명령을 입력한다(S640). 그러면, 원격 제어 단말(60)은 입력된 서버 제어 요청을 이더넷/무선 통신망(50)을 통해 전력 관제 장치(30)에 전송한다(S642, S644). 그러면, 전력 관제 장치(30)는 입력된 서버 제어 요청에 대응되는 제어 신호를 생성하여 전력 분배기(10)로 전송하게 된다(S646).
그러면, 전력 분배기(10)는 서버 제어 요청에 대응되는 제어신호에 따라 서버의 전력을 제어하고, 그에 대한 결과를 전력 관제 장치(30)로 통보해주게 된다(S650). 그러면, 전력 관제 장치(30)는 제어 결과를 이더넷/무선 통신망(50)을 통해 원격 제어 단말(60)로 전송한다(S653, S656). 그러면, 원격 제어 단말(60)은 제어 결과를 화면에 표시함으로써 사용자에게 제공하게 된다(S659).
이와 같이, 사용자는 원격 제어 단말(60)을 통해 알람을 확인할 수 있으며, 알람에 따라 서버의 전력을 원격제어 단말(60)을 이용하여 제어할 수 있게 된다.
한편, 본 실시예에 따른, 전력 관제 장치(30)는 전력 분배기(10)에서 제공되는 정보를 이용하여 전력 사용을 관제하는 장치이면 어느 것이라도 가능하다. 예를 들어, 전력 관제 장치(30)는 워크스테이션, 노트북 등의 컴퓨터 장치이거나 또는 독립적인 전력 관제 장치일 수도 있다.
한편, 본 실시예에 따른 전력 관제 장치(30)의 기능을 수행하게 하는 컴퓨터 프로그램을 수록한 컴퓨터로 읽을 수 있는 기록매체에도 본 발명의 기술적 사상이 적용될 수 있음은 물론이다. 또한, 본 발명의 다양한 실시예에 따른 기술적 사상은 컴퓨터로 읽을 수 있는 기록매체에 기록된 컴퓨터로 읽을 수 있는 코드 형태로 구현될 수도 있다. 컴퓨터로 읽을 수 있는 기록매체는 컴퓨터에 의해 읽을 수 있고 데이터를 저장할 수 있는 어떤 데이터 저장 장치이더라도 가능하다. 예를 들어, 컴퓨터로 읽을 수 있는 기록매체는 ROM, RAM, CD-ROM, 자기 테이프, 플로피 디스크, 광디스크, 하드 디스크 드라이브, 등이 될 수 있음은 물론이다. 또한, 컴퓨터로 읽을 수 있는 기록매체에 저장된 컴퓨터로 읽을 수 있는 코드 또는 프로그램은 컴퓨터간에 연결된 네트워크를 통해 전송될 수도 있다.
또한, 이상에서는 본 발명의 바람직한 실시예에 대하여 도시하고 설명하였지만, 본 발명은 상술한 특정의 실시예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진자에 의해 다양한 변형실시가 가능한 것은 물론이고, 이러한 변형실시들은 본 발명의 기술적 사상이나 전망으로부터 개별적으로 이해되어져서는 안될 것이다.

Claims (8)

  1. 적어도 하나의 서버 관리 장비에 장착되어 각 서버의 전력 사용량 정보를 감지하는 적어도 하나의 전력 분배기; 및
    상기 전력 분배기로부터 상기 전력 사용량 정보를 수신하고, 상기 전력 사용량 정보에 따라 상기 서버 관리 장비의 기준 전력 사용량을 설정하는 전력 관제 장치;를 포함하는 전력 관리 시스템.
  2. 제1항에 있어서,
    상기 전력 관제 장치는,
    상기 전력 사용량 정보를 이용하여, 특정 기간에 대한 전력 수요를 예측한 데이터인 수요 예측 데이터를 산출하는 것을 특징으로 하는 전력 관리 시스템.
  3. 제2항에 있어서,
    상기 전력 관제 장치는,
    다음의 수식
    Ft = Ft-1 + a(At-1 - Ft-1)
    (여기에서, Ft 는 t기의 예측값, Ft-1 는 t-1기의 예측값, At-1 는 t-1기의 실제 사용값, a는 지수 평활 계수)
    을 이용하여 상기 특정 기간(t기)에 대한 상기 수요 예측 데이터를 산출하는 것을 특징으로 하는 전력 관리 시스템.
  4. 제2항에 있어서,
    상기 전력 관제 장치는,
    서버별 중요도 및 활용 시간대에 대한 정보를 이용하여 상기 서버별 기준 전력 사용량을 설정하는 것을 특징으로 하는 전력 관리 시스템.
  5. 제1항에 있어서,
    상기 적어도 하나의 전력 분배기는,
    각 서버의 온도 정보를 감지하고,
    상기 전력 관제 장치는,
    상기 각 서버의 온도 정보에 따라 각 서버의 전력 공급 여부를 결정하는 것을 특징으로 하는 전력 관리 시스템.
  6. 제1항에 있어서,
    상기 전력 관제 장치는,
    상기 전력 사용량 정보를 탄소 배출량으로 환산하는 것을 특징으로 하는 전력 관리 시스템.
  7. 제1항에 있어서,
    상기 전력 관제 장치에 원격으로 접속하고, 상기 전력 관제 장치에 저장된 전력 사용량 정보를 수신하여 디스플레이하는 원격 제어 단말;을 더 포함하는 것을 특징으로 하는 전력 관리 시스템.
  8. 적어도 하나의 서버가 마운트된 서버 관리 장비의 전력 분배기에 있어서,
    상기 적어도 하나의 서버 각각의 전력 사용량 정보를 감지하는 전력 센서부;
    상기 적어도 하나의 서버 각각의 서버의 전원을 제어하는 전원 제어부;
    외부 장치와 유무선 통신을 수행하는 통신부;
    상기 감지된 전력 사용량 정보가 상기 통신부를 통해 상기 외부 장치로 전송되도록 제어하고, 상기 외부 장치로부터 수신된 제어신호에 따라 상기 적어도 하나의 서버 각각의 전원을 제어하도록 상기 전원 제어부를 제어하는 제어부;를 포함하는 전력 분배기.
PCT/KR2011/009577 2010-12-29 2011-12-13 전력 관리 시스템 및 이에 적용되는 전력 분배기 WO2012091323A2 (ko)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2010-0138312 2010-12-29
KR1020100138312A KR101171145B1 (ko) 2010-12-29 2010-12-29 전력 관리 시스템 및 이에 적용되는 전력 분배기

Publications (2)

Publication Number Publication Date
WO2012091323A2 true WO2012091323A2 (ko) 2012-07-05
WO2012091323A3 WO2012091323A3 (ko) 2012-10-04

Family

ID=46383624

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2011/009577 WO2012091323A2 (ko) 2010-12-29 2011-12-13 전력 관리 시스템 및 이에 적용되는 전력 분배기

Country Status (2)

Country Link
KR (1) KR101171145B1 (ko)
WO (1) WO2012091323A2 (ko)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015066048A1 (en) * 2013-10-28 2015-05-07 Virtual Power Systems, Inc. Energy control via power requirement analysis and power source enablement
US10429914B2 (en) 2013-10-28 2019-10-01 Virtual Power Systems, Inc. Multi-level data center using consolidated power control
US10585468B2 (en) 2016-08-18 2020-03-10 Virtual Power Systems, Inc. Datacenter power management using dynamic redundancy
US10747289B2 (en) 2013-10-28 2020-08-18 Virtual Power Systems, Inc. Data center power manipulation
US10969846B2 (en) 2017-05-25 2021-04-06 Virtual Power Systems, Inc. Secure communication initiation and execution for datacenter power control
US11107016B2 (en) 2016-08-18 2021-08-31 Virtual Power Systems, Inc. Augmented power control within a datacenter using predictive modeling
US11126242B2 (en) 2013-10-28 2021-09-21 Virtual Power Systems, Inc. Time varying power management within datacenters
US11216059B2 (en) 2018-03-05 2022-01-04 Virtual Power Systems, Inc. Dynamic tiering of datacenter power for workloads
US11455021B2 (en) 2016-08-18 2022-09-27 Cato Datacenter power management using AC and DC power sources
US11461513B2 (en) 2016-08-18 2022-10-04 Cato Data center power scenario simulation

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101524951B1 (ko) * 2013-12-24 2015-06-01 (주)합동전자산업 디지털 전원분배 모니터링 시스템
KR102160317B1 (ko) * 2015-12-27 2020-09-25 한국전자기술연구원 무선 통신을 통해 효율적인 데이터센터 운영을 지원하는 pdu
KR102363988B1 (ko) 2019-12-23 2022-02-17 (주)아이티공간 서버랙 예지 보전방법
KR102316530B1 (ko) * 2019-12-23 2021-10-22 (주)아이티공간 서버랙의 건전성 지수 검출방법
KR102363987B1 (ko) * 2019-12-23 2022-02-16 (주)아이티공간 사용 안전성이 우수한 스마트 서버랙
KR102334034B1 (ko) * 2021-06-16 2021-12-02 대한민국 서버 이상 진단 감시 장치

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020048333A (ko) * 2002-04-30 2002-06-22 이종수 원격검침을 사용한 멀티 에어컨 검침 시스템
KR20050034414A (ko) * 2003-10-09 2005-04-14 엘지전자 주식회사 에어컨의 중앙제어 시스템
KR20080040454A (ko) * 2006-11-03 2008-05-08 삼성전자주식회사 시스템 에어컨의 전력관리장치 및 그 방법
JP2009159806A (ja) * 2007-12-27 2009-07-16 Semes Co Ltd 遠隔制御電力分配装置及びこれを含む半導体装備の電力分配システム

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020048333A (ko) * 2002-04-30 2002-06-22 이종수 원격검침을 사용한 멀티 에어컨 검침 시스템
KR20050034414A (ko) * 2003-10-09 2005-04-14 엘지전자 주식회사 에어컨의 중앙제어 시스템
KR20080040454A (ko) * 2006-11-03 2008-05-08 삼성전자주식회사 시스템 에어컨의 전력관리장치 및 그 방법
JP2009159806A (ja) * 2007-12-27 2009-07-16 Semes Co Ltd 遠隔制御電力分配装置及びこれを含む半導体装備の電力分配システム

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9800087B2 (en) 2013-10-28 2017-10-24 Virtual Power Systems, Inc. Multi-level data center consolidated power control
US10128684B2 (en) 2013-10-28 2018-11-13 Virtual Power Systems, Inc. Energy control via power requirement analysis and power source enablement
US10429914B2 (en) 2013-10-28 2019-10-01 Virtual Power Systems, Inc. Multi-level data center using consolidated power control
US10747289B2 (en) 2013-10-28 2020-08-18 Virtual Power Systems, Inc. Data center power manipulation
WO2015066048A1 (en) * 2013-10-28 2015-05-07 Virtual Power Systems, Inc. Energy control via power requirement analysis and power source enablement
US11126242B2 (en) 2013-10-28 2021-09-21 Virtual Power Systems, Inc. Time varying power management within datacenters
US11455021B2 (en) 2016-08-18 2022-09-27 Cato Datacenter power management using AC and DC power sources
US10585468B2 (en) 2016-08-18 2020-03-10 Virtual Power Systems, Inc. Datacenter power management using dynamic redundancy
US11107016B2 (en) 2016-08-18 2021-08-31 Virtual Power Systems, Inc. Augmented power control within a datacenter using predictive modeling
US11461513B2 (en) 2016-08-18 2022-10-04 Cato Data center power scenario simulation
US11314304B2 (en) 2016-08-18 2022-04-26 Virtual Power Systems, Inc. Datacenter power management using variable power sources
US10969846B2 (en) 2017-05-25 2021-04-06 Virtual Power Systems, Inc. Secure communication initiation and execution for datacenter power control
US11216059B2 (en) 2018-03-05 2022-01-04 Virtual Power Systems, Inc. Dynamic tiering of datacenter power for workloads

Also Published As

Publication number Publication date
KR20120076244A (ko) 2012-07-09
WO2012091323A3 (ko) 2012-10-04
KR101171145B1 (ko) 2012-08-06

Similar Documents

Publication Publication Date Title
WO2012091323A2 (ko) 전력 관리 시스템 및 이에 적용되는 전력 분배기
WO2019225834A1 (ko) 에너지 저장 장치와 태양광 발전을 이용한 전력 공급 제어 시스템 및 방법
WO2011065733A2 (en) Network system and method of controlling network system
WO2011059132A1 (ko) 분산전원의 전력 거래 시스템 및 거래 방법
US7184905B2 (en) Method and system for monitoring power supplies
WO2015023100A1 (ko) 에너지 정보 제공 장치 및 시스템
WO2018074625A1 (ko) 실시간 모니터링이 가능한 무선원격 검침시스템
BR9600042A (pt) Primeiro computador para uso em conjunto com um segundo microcomputador para controle da operação de uma pluralidade de cargas elétricas nas instalações de um cliente controlador secundário para uso com um controlador mestre sistema para controlar a operação de um dispositivo de carga elétrica monitor para permitir a determinação remota do estado de corrente em um acionador de suprimento de circuito de ramificação elétrica em uma carga elétrica monitor para determinação de parâmetros de consumo de energia eletrica por uma carga eletrica em um circuito de ramificação processo de controle da restaração das cargas de um sistema de distribuição de energia elétrica processo para facilitar a manutenção preventiva em um sistema de distriuição de energia elétrica de um provedor de energia etéricaaparelho sistema para controler a operação de um dispositivo de carga elétrica metodo para fornecer informações sobre o uso de energia elétrica
CN102377179B (zh) 信息处理装置和信息处理方法
CN109255554A (zh) 一种低压配用电监测与管理系统
WO2020111561A1 (ko) 머신러닝 기반 태양광 발전 제어 시스템 및 방법
WO2012060478A1 (ko) 전력제어장치 및 전력제어방법
EP2494736A2 (en) Method of controlling network system
WO2021187739A1 (ko) Ess 충방전 스케쥴 관리장치
JP2007033305A (ja) エネルギー管理システム
WO2019045262A1 (ko) 전력부하 전력소모량 시뮬레이션 장치 및 방법
WO2014104829A1 (ko) 전력 부하 예측 방법 및 이러한 방법을 수행하는 장치
WO2021080169A2 (ko) 건물 에너지 통합 관리 장치 및 그 방법
WO2015147447A1 (ko) 태양광 인버터 진단 시스템 및 그 방법
WO2019132054A1 (ko) 에너지 저장장치를 이용한 최대수요전력 제어 시스템
WO2016018104A1 (en) Method and apparatus for device management based on device power information and pricing schemes
WO2019074173A1 (ko) 단위 가구 피크 전력 수요량 예측 방법 및 시스템
WO2024034758A1 (ko) 원격지에서 태양광 발전시스템의 출력을 제한하는 장치 및 그 방법
WO2020195524A1 (ja) 蓄電制御システムおよび蓄電制御方法
Lu et al. Substation equipment temperature monitoring system design based on self-powered wireless temperature sensors

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11854156

Country of ref document: EP

Kind code of ref document: A2

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 11854156

Country of ref document: EP

Kind code of ref document: A2