WO2011152512A1 - 給電制御装置 - Google Patents

給電制御装置 Download PDF

Info

Publication number
WO2011152512A1
WO2011152512A1 PCT/JP2011/062758 JP2011062758W WO2011152512A1 WO 2011152512 A1 WO2011152512 A1 WO 2011152512A1 JP 2011062758 W JP2011062758 W JP 2011062758W WO 2011152512 A1 WO2011152512 A1 WO 2011152512A1
Authority
WO
WIPO (PCT)
Prior art keywords
power
unit
amount
power generation
demand
Prior art date
Application number
PCT/JP2011/062758
Other languages
English (en)
French (fr)
Inventor
花房 寛
Original Assignee
三洋電機株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三洋電機株式会社 filed Critical 三洋電機株式会社
Publication of WO2011152512A1 publication Critical patent/WO2011152512A1/ja

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/003Load forecast, e.g. methods or systems for forecasting future load demand
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Definitions

  • the present invention relates to a power supply control device that controls power supply to a load.
  • the contracted electric energy that can be used with an electric power company may be determined based on the maximum demand electric energy per unit time in a predetermined period in a facility or a house.
  • FIG. 6 is a graph showing the daily power purchase amount of a certain user. The horizontal axis represents time, and the vertical axis represents power purchase amount (kW). The amount of power demand is greatest during a certain time of the day, that is, during the daytime when people are active. In the example shown in FIG. 6, the power purchase amount reaches a maximum of about 187 kW around 10 am, and the contract power amount is calculated based on this 187 kW.
  • FIG. 7 is a graph showing the daily power purchase amount of a certain user when a solar cell is used.
  • the horizontal axis represents time, and the vertical axis represents power purchase amount (kW). Since the amount of power demand increases during the daytime, the use of solar cells can suppress an increase in the amount of power purchased with an increase in the amount of power demand.
  • the amount of power generated by generators using natural energy varies greatly depending on the natural state. For example, when a solar cell is used, the amount of power generation varies under the influence of clouds even on a clear day. Therefore, as shown in FIG. 7, when the solar radiation to the solar cell is blocked by the clouds, the amount of power generated by the solar cell decreases, and the amount of power purchased from the power system increases to compensate for this. For this reason, when a generator using natural energy is used, it is difficult to significantly reduce the maximum demand power.
  • the present invention has been made in view of the above-described problems, and an object thereof is to provide a power supply control device that reduces the maximum demand power amount.
  • the power supply control device of the present invention is connected to a power generation unit that generates power using natural energy and a power system, and stores power from at least one of the power generation unit and the power system.
  • a power storage unit that supplies power to a predetermined load; and a control unit that controls power supply to the load; the control unit predicts a power generation amount per unit time by the power generation unit; and A demand power amount prediction unit that predicts the demand power amount per unit time of the load, and compares the power generation amount predicted by the power generation amount prediction unit with the demand power amount predicted by the demand power prediction unit.
  • the power storage unit supplies power to the load.
  • the power supply control device of the present invention is connected to a power generation unit that generates power using natural energy and a power system, stores power from at least one of the power generation unit and the power system, and applies power to a predetermined load.
  • a power storage unit that supplies power and a control unit that controls power supply to the load, and the control unit predicts a power generation amount per unit time by the power generation unit, and a load generation unit per unit time of the load.
  • a demand power amount prediction unit that predicts the demand power amount, and when the demand power amount predicted by the demand power amount prediction unit does not exceed a predetermined threshold value, the load is supplied from the power system to the demand power amount prediction unit.
  • the amount of power demand predicted by exceeds the threshold if the amount of power exceeding the threshold is smaller than the amount of power predicted by the power generation prediction unit, power is supplied from the power system and the power generation unit to the load Power generation Greater when than is characterized by feeding the load from the power system, the power generation unit and power storage unit.
  • the power supply control device of the present invention is a power supply control device that controls power supply to a predetermined load, and a power storage unit that stores power from at least one of a power generation unit that generates power using natural energy and a power system.
  • the controller includes a control unit that controls charging / discharging of the power supply and also controls power supply to the load.
  • the control unit predicts the amount of power generated per unit time by the power generation unit, and the power demand per unit time of the load When the power generation amount is lower than the demand power amount, the power generation amount predicted by the power generation amount prediction unit is compared with the demand power amount predicted by the demand power prediction unit.
  • the electric storage unit is discharged to the load.
  • the power supply control device of the present invention can stably supply the amount of power demanded by the load by the power generation unit and the power storage unit.
  • FIG. 1 is a functional block diagram illustrating functions of the power supply control device 1.
  • the power supply control device 1 is connected to a load 2, a power system 3, and a generator 4.
  • the power supply control device 1 includes a storage unit 5, a storage battery 6, and a control unit 7.
  • the power supply control device 1 controls power supply from the power system 3, the generator 4 and the storage battery 6 to the load 2.
  • the load 2 is a device that consumes electric power installed in a facility or a house, and examples thereof include a refrigerator and an air conditioner used in a house.
  • the generator 4 is a generator that generates power using natural energy, and examples thereof include those using natural energy such as sunlight, wind power, and hydropower.
  • the storage unit 5 stores a predetermined threshold value and a demand power amount prediction table.
  • the predetermined threshold is determined in accordance with the contract power amount that can be used with the electric power company.
  • the demand power amount prediction table associates the past date and time with the demand power amount of the load 2 at that date and time.
  • the storage unit 5 is provided inside the power supply control device 1 in this embodiment, but is provided outside the power supply control device 1 and may be connected by wire or wirelessly.
  • the storage battery 6 is connected to the power system 3 and the generator 4 via the power supply control unit 13 and the charge / discharge control unit 14 and stores the power supplied from the power system 3 and the generator 4.
  • a secondary battery for example, a lithium ion storage battery, a nickel hydride storage battery, or the like
  • the voltage of the storage battery 6 is desired to be lower.
  • the nominal voltage (charging voltage) of the storage battery 6 is selected to be lower than the nominal maximum output operating voltage of the generator 4, and particularly preferably 70% to 90%.
  • the storage battery 6 is stored from the power system 3 in the midnight time zone when the electricity rate is low, and the power generated by the generator 4 and not used for feeding the load 2 is also stored. .
  • the storage battery 6 will be described as always holding a sufficient amount of stored electricity.
  • the control unit 7 determines a power supply path from the power system 3, the generator 4 and the storage battery 6 to the load 2 and controls power supply to the load 2.
  • the control unit 7 includes a power generation amount prediction unit 8, a demand power amount prediction unit 9, a threshold value comparison unit 10, a data comparison unit 11, a power supply path determination unit 12, a power supply control unit 13, and a charge / discharge control unit 14. Including.
  • the power generation amount prediction unit 8 creates power generation amount prediction data in which the power generation amount per unit time after a predetermined time of the generator 4 is predicted.
  • the power generation amount prediction data is data in which the power generation amount of the generator 4 per unit time (for example, 10 minutes) after a predetermined time is predicted based on, for example, video data captured by a satellite. Specifically, when a solar cell is used as the generator 4, the amount of solar radiation to the generator 4 after a predetermined time is estimated by predicting the movement of clouds in the place where the generator 4 is located from satellite image data. Predict the power generation amount of the generator 4. At this time, it is desirable to make a prediction while considering the current power generation amount of the generator 4.
  • the power generation amount prediction unit 8 creates power generation amount prediction data every predetermined time.
  • the demand power amount prediction unit 9 creates demand power amount prediction data in which a demand power amount per unit time (for example, 10 minutes) after a predetermined time of the load 2 is predicted. Specifically, the demand power amount prediction unit 9 acquires the demand power amount prediction table from the storage unit 5, refers to the demand power amount prediction table at the same time and the same time as the time / time to be predicted, and loads 2 Predict the amount of power demand. At this time, it is desirable to make a prediction while taking into account the current power demand of the load 2. The demand power amount prediction unit 9 creates demand power amount prediction data every predetermined time.
  • the threshold value comparison unit 10 determines whether the demand power amount predicted by the demand power amount prediction unit 9 exceeds the contract power amount that can be used with the power company. Specifically, the threshold value comparison unit 10 compares the demand power amount predicted by the demand power amount prediction unit 9 with a predetermined threshold value stored in the storage unit 5. If the threshold comparison unit 10 determines that the predicted demand power amount exceeds the predetermined threshold value, the threshold value comparison unit 10 transmits the result to the data comparison unit 11, and the predicted demand power amount exceeds the predetermined threshold value. If it is determined that there is not, the result is transmitted to the power feeding path determination unit 12.
  • the data comparison unit 11 When the data comparison unit 11 receives a determination result that the predicted demand power amount exceeds a predetermined threshold value from the threshold comparison unit 10, the data comparison unit 11 includes a power amount that exceeds the predetermined threshold value among the predicted demand power amounts (hereinafter, It is determined whether or not the excess power amount exceeds the power generation amount predicted by the power generation amount prediction unit 8. Specifically, the data comparison unit 11 compares the excess power amount with the power generation amount prediction data acquired from the power generation amount prediction unit 8, and transmits the result to the power supply path determination unit 12.
  • the power supply path determination unit 12 determines a power supply path from the power system 3, the generator 4, and the storage battery 6 to the load 2 based on the results received from the threshold comparison unit 10 and the data comparison unit 11.
  • the power supply path determination unit 12 determines the power supply path as the power system 3 when the determination result that the predicted demand power amount does not exceed a predetermined threshold value is received from the threshold comparison unit 10. In addition, when the determination result that the excess power does not exceed the predicted power generation amount is received from the data comparison unit 11, the power supply path determination unit 12 determines the power supply path as the power system 3 and the generator 4. In addition, when the power supply path determination unit 12 receives a determination result that the excess power amount exceeds the predicted power generation amount from the data comparison unit 11, the power supply path determination unit 12 sets the power supply path to the power system 3, the generator 4, and the storage battery 6. decide.
  • the power supply control unit 13 performs switching of the power supply path and control of the power supply amount based on the determination of the power supply path determination unit 12.
  • the charge / discharge control unit 14 controls charging / discharging of the storage battery 6 based on an instruction from the power supply control unit 13.
  • FIG. 2 is a flowchart for explaining the operation of the power supply control device 1.
  • the demand power amount prediction unit 9 refers to the demand power amount prediction table stored in the storage unit 5 to predict the demand power amount per unit time (for example, 10 minutes) after a predetermined time of the load 2.
  • the generated demand power amount prediction data is created (S1).
  • the threshold value comparison unit 10 acquires the demand power amount prediction data from the demand power amount prediction unit 9, and compares the predicted demand power amount with a predetermined threshold value stored in the storage unit 5 (S2). ).
  • the predetermined threshold refers to a contract power amount that can be used with an electric power company.
  • the threshold value comparison unit 10 determines that the predicted power demand is smaller than the predetermined threshold value (No in S2), the threshold value comparison unit 10 transmits the determination result to the power supply path determination unit 12. Based on the determination result of the threshold comparison unit 10, the power supply path determination unit 12 determines the power supply path to the load 2 from the power system 3, and transmits the result to the power supply control unit 13 (S3). The power supply control unit 13 supplies power to the load 2 from the power system 3 based on the result of the power supply path determination unit 12 (S4).
  • the threshold value comparison unit 10 determines that the demand power amount prediction data is larger than the predetermined threshold value (Yes in S2), the threshold value comparison unit 10 transmits the determination result to the data comparison unit 11.
  • the data comparison unit 11 compares the amount of power that has exceeded a predetermined threshold among the predicted amount of power demand (hereinafter referred to as excess power amount) with the predicted amount of power acquired from the power generation amount prediction unit 8 ( S5), and transmits the determination result to the power feeding path determination unit 12.
  • the power supply path determination unit 12 When the power supply path determination unit 12 receives the determination result that the excess power amount is smaller than the predicted power generation amount from the data comparison unit 11 (No in S5), the power supply path determination unit 12 determines the power supply path to the load 2 as the power system 3 and It determines from the generator 4, and transmits the result to the electric power feeding control part 13 (S6).
  • the power supply control unit 13 supplies power to the load 2 from the power system 3 and the generator 4 based on the result of the power supply path determination unit 12 (S7).
  • the power supply path determination unit 12 determines the power supply path to the load 2 as the power system. 3. It determines from the generator 4 and the storage battery 6, and the result is transmitted to the electric power feeding control part 13 (S8).
  • the power supply control unit 13 supplies power to the load 2 from the power system 3, the generator 4, and the storage battery 6 based on the result of the power supply path determination unit 12 (S9).
  • the power generation amount prediction unit 8 and the demand power amount prediction unit 9 predict the power generation amount and the demand power amount per unit time after a predetermined time every predetermined time. Therefore, the power supply control device 1 repeats the operations S1 to S9 every predetermined time.
  • FIG. 3 is a graph showing the power purchase amount when the control by the power supply control device 1 is performed.
  • FIG. 4 is a graph showing a breakdown of the power supply of the generator 4 and the storage battery 6.
  • the horizontal axis represents time
  • the vertical axis represents power purchase amount (kW).
  • the positive value in the storage battery 6 has shown discharge
  • the negative value has shown charge.
  • the power feeding control device 1 is connected to a power generator 4 that generates power using natural energy and a power system 3, to a storage battery 6 that stores power from the power generator 4 and the power system 3, and to a load 2.
  • the control unit 7 controls the power supply amount of the generator 4.
  • the control unit 7 predicts the power generation amount prediction unit 8 that predicts the power generation amount per unit time of the generator 4 and the demand power amount per unit time of the load 2. When the predicted power generation amount of the generator 4 is lower than the predicted demand power amount of the load 2, the storage battery 6 supplies power to the load 2.
  • the power supply control device 1 since the power generation amount of the generator 4 per unit time is compared with the demand power amount of the load 2 per unit time, if the unit time is set as short as 10 minutes, for example, More reliable control is possible. In other words, the power supply control device 1 can stably supply the demand power amount of the load 2 by the generator 4 and the storage battery 6.
  • the control unit 7 supplies power to the load 2 from the power system 3 and predicts the demand power amount prediction unit 9
  • the demand power amount exceeds the threshold value
  • the power amount exceeding the threshold value is smaller than the power generation amount predicted by the power generation amount prediction unit 8
  • the power generation amount is larger than the power generation amount, power is supplied to the load 2 from the power system 3, the generator 4, and the storage battery 6.
  • the power supply control device 1 can suppress an increase in the amount of power purchased from the power system 3 due to an increase in the demand power amount of the load 2.
  • the power generation amount prediction unit 8 acquires the video data of the place where the generator 4 is located from the satellite and creates the power generation amount prediction data. Thereby, even if there is no external source for generating power generation amount prediction data, the power generation amount of the generator 4 can be predicted only by the power supply control device 1, and the power supply to the load 2 can be appropriately controlled. .
  • the electric power feeding control apparatus 1 As mentioned above, although the structure of the electric power feeding control apparatus 1 has been demonstrated, the electric power feeding control apparatus of this invention is not limited to the structure mentioned above, A various change is possible in the range shown to the claim.
  • the power generation amount prediction unit 8 is configured to acquire the video data of the place where the generator 4 is located from the satellite and create the power generation amount prediction data, but the present invention is limited to this. Absent.
  • the configuration may be such that the movement of clouds within a predetermined time is observed with an image sensor, and the power generation amount prediction data is created based on the observation data.
  • the predetermined time is, for example, one hour.
  • there may be an external source for generating power generation amount prediction data, and the power generation amount prediction data may be acquired from the external source via a wireless or wired communication network. In this case, since it is not necessary to provide the power generation amount prediction unit 8, the number of parts can be reduced, and the entire apparatus can be downsized.
  • the power supply control device 1 is configured to first compare the predicted demand power amount of the load 2 with a predetermined threshold (contract power amount of the power system 3), but the present invention is not limited to this.
  • the power supply control device of the present invention may have a configuration that first compares the predicted demand power amount of the load 2 with the predicted power generation amount of the generator 4. In this case, when it is determined that the predicted demand power amount is larger than the predicted power generation amount, power is further supplied from the storage battery 6 to the load 2. Further, when it is determined that the predicted demand power amount of the load 2 is larger than the predicted power generation amount of the generator 4 and the power storage amount of the storage battery 6, the excess power amount is transferred from the power system 3 to the load 2. Supply power.
  • the power supply control device 1 has a configuration in which the storage battery 6 is provided inside the device, but the present invention is not limited thereto.
  • FIG. 5 is a functional block diagram showing a modification of the power supply control device of the present invention.
  • the storage battery 6 may be provided outside the device. In this case, since the power supply control device does not include the storage battery 6, the entire device can be reduced in size.
  • the demand power amount prediction unit 9 per unit time of the load 2 based on the demand power amount prediction table in which the past date and time and the demand power amount of the load 2 at that date and time are associated.
  • the present invention is not limited to this.
  • a configuration in which the demand power amount prediction unit 9 creates demand power amount prediction data by setting in advance the time and amount of use of the load 2 by the user in advance may be used.
  • the structure which acquires the average demand electric energy prediction data in case the quantity prediction part 9 has the same load 2 from the outside may be sufficient.
  • the power supply control device can be used to control a power supply device using a generator that uses natural energy.
  • 1 power supply control device 2 load, 3 power system, 4 generator, 5 storage unit, 6 storage battery, 7 control unit, 8 power generation amount prediction unit, 9 demand power amount prediction unit, 10 threshold comparison unit, 11 data comparison unit, 12 power supply path / power supply determination unit, 13 power supply control unit, 14 charge / discharge control unit.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

 給電制御装置(1)は、自然エネルギーを利用して発電する発電機(4)と電力系統(3)とに接続されており、発電機(4)および電力系統(3)の少なくとも一方から電力を蓄電するとともに、負荷(2)に対して電力を供給する蓄電池(6)と、負荷(2)への給電を制御する制御部(7)とを備える。制御部(7)は、発電機(4)による単位時間当たりの発電量を予測する発電量予測部(8)と、負荷(2)の単位時間当たりの需要電力量を予測する需要電力量予測部(9)とを含み、発電量予測部(8)により予測した発電量と、需要電力予測部(9)により予測した需要電力量とを比較し、発電量が需要電力量よりも低い場合に、蓄電池(6)から負荷(2)に給電する。

Description

給電制御装置
  本発明は、負荷への給電を制御する給電制御装置に関する。
 電力会社との間における使用可能な契約電力量は、施設や住宅等において、所定の期間における単位時間の最大需要電力量に基づいて決まる場合がある。図6は、あるユーザの1日の電力購入量を示すグラフである。なお、横軸は時間を、縦軸は電力購入量(kW)を示している。需要電力量は1日の内のある一定の時間帯、すなわち人が活動している昼間の時間帯において最も大きくなる。図6に示す例では、午前10時頃に電力購入量が最大の約187kWに達しており、契約電力量はこの187kWに基づいて計算される。
 従来から、この昼間の最大需要電力量を低減するために、太陽電池等の自然エネルギーを利用した発電機を補助的に用いる技術が提案されている。図7は、太陽電池を用いた場合における、あるユーザの1日の電力購入量を示すグラフである。なお、横軸は時間を、縦軸は電力購入量(kW)を示している。需要電力量が大きくなるのは昼間の時間帯であるため、太陽電池を用いることにより、需要電力量の増加に伴う電力購入量の増加を抑制することができる。
 また、昼間の最大需要電力量を低減するために、電力系統からの電力を蓄電可能な蓄電池を用いる技術が提案されている。これは、電気料金の安い深夜時間帯に電力系統から電力を蓄電しておき、需要電力量が大きくなる時間帯に蓄電池から放電することにより、昼間の最大需要電力量を低減するものである。
 しかしながら、自然エネルギーを利用した発電機は、自然の状態により発電量が大きく変動する。例えば、太陽電池を用いた場合には、晴れた日であっても雲の影響を受けて発電量が変動する。そのため、図7に示すように、雲により太陽電池への日射が遮られた場合には、太陽電池による発電量が減少し、それを補うために電力系統からの電力購入量が増加する。そのため、自然エネルギーを利用した発電機を用いた場合には、最大需要電力量を大幅に低減させることは難しい。
 本発明は、上記の問題点に鑑みてなされたものであり、その目的は、最大需要電力量を低減させる給電制御装置を提供することである。
 本発明の給電制御装置は、上記課題を解決するために、自然エネルギーを利用して発電する発電部と電力系統とに接続されており、発電部および電力系統の少なくとも一方から電力を蓄電するとともに、所定の負荷に対して電力を供給する蓄電部と、負荷への給電を制御する制御部とを備え、制御部は、発電部による単位時間当たりの発電量を予測する発電量予測部と、負荷の単位時間当たりの需要電力量を予測する需要電力量予測部とを含み、発電量予測部により予測した発電量と、需要電力予測部により予測した需要電力量とを比較し、発電量が需要電力量よりも低い場合に、蓄電部から前記負荷に給電することを特
徴としている。
 また、本発明の給電制御装置は、自然エネルギーを利用して発電する発電部と電力系統とに接続されており、発電部および電力系統の少なくとも一方から電力を蓄電するとともに、所定の負荷に対して電力を供給する蓄電部と、負荷への給電を制御する制御部とを備え、制御部は、発電部による単位時間当たりの発電量を予測する発電量予測部と、負荷の単位時間当たりの需要電力量を予測する需要電力量予測部とを含み、需要電力量予測部により予測した需要電力量が所定の閾値を超えない場合には、電力系統から負荷に給電し、需要電力量予測部により予測した需要電力量が閾値を超える場合には、閾値を超えた電力
量が、発電量予測部により予測した発電量よりも小さいときは、電力系統および発電部から負荷に給電し、予測した発電量よりも大きいときは、電力系統、発電部および蓄電部から負荷に給電すること特徴としている。
 また、本発明の給電制御装置は、所定の負荷への給電を制御する給電制御装置であって、自然エネルギーを利用して発電する発電部および電力系統の少なくとも一方から電力が蓄電される蓄電部の充放電を制御するとともに、負荷への給電を制御する制御部を備え、制御部は、発電部による単位時間当たりの発電量を予測する発電量予測部と、負荷の単位時間当たりの需要電力量を予測する需要電力量予測部とを含み、発電量予測部により予測した発電量と、需要電力予測部により予測した需要電力量とを比較し、発電量が需要電力量よりも低い場合に、蓄電部より前記負荷に対して放電することを特徴としている。
 本発明の給電制御装置は、負荷の需要電力量を、発電部および蓄電部により安定して賄うことが可能である。
本発明の給電制御装置の機能を示す機能ブロック図である。 給電制御装置の動作を示すフローチャートである。 給電制御装置による制御を行った場合における、あるユーザの1日の電力購入量を示すグラフである。 発電機および蓄電池の電力供給の内訳を示すグラフである。 本発明の給電制御装置の変形例を示す機能ブロック図である。 あるユーザの1日の電力購入量を示すグラフである。 太陽電池を用いた場合における、あるユーザの1日の電力購入量を示すグラフである。
 (給電制御装置1の構成)
 本発明に係る給電制御装置1の構成について、図1を参照して説明する。図1は給電制御装置1の機能を示す機能ブロック図である。
 給電制御装置1は、負荷2と、電力系統3と、発電機4とに接続されている。給電制御装置1は、記憶部5と、蓄電池6と、制御部7とを備える。給電制御装置1は、電力系統3、発電機4および蓄電池6から負荷2への給電を制御するものである。
 負荷2は、施設や住宅等に設置されている電力を消費する機器であり、例えば、住宅で用いられる冷蔵庫やエアコン等が挙げられる。発電機4は、自然エネルギーを利用して発電する発電機であり、例えば、太陽光、風力、水力等の自然エネルギーを利用したものが挙げられる。
 記憶部5には、所定の閾値および需要電力量予測テーブルが記憶されている。所定の閾値は、電力会社との間における使用可能な契約電力量に応じて決定されたものである。需要電力量予測テーブルとは、過去の日時とその日時における負荷2の需要電力量とが関連付けられたものである。なお、記憶部5は、本実施形態では給電制御装置1内部に設けられているが、給電制御装置1の外部に設けられており、有線または無線により接続されていてもよい。
 蓄電池6は、給電制御部13および充放電制御部14を介して電力系統3および発電機4に接続されており、電力系統3および発電機4から供給された電力を蓄電する。蓄電池6としては、自然放電が少なく、充放電効率の高い2次電池(例えば、リチウムイオン蓄電池、ニッケル水素蓄電池等)が用いられる。また、蓄電池6の電圧は高いほど安全設計が重要になることから、蓄電池6の電圧は低いことが望まれる。なお、蓄電池6の公称電圧(充電電圧)は、発電機4の公称最大出力動作電圧よりも低くなるように選択され、特に70%以上90%以下となるように選択されることが望ましい。
 なお、蓄電池6は、電気料金の安い深夜時間帯に電力系統3から蓄電されており、発電機4により発電された電力であって、負荷2への給電に用いられない電力も蓄電されている。本実施形態では、蓄電池6は常に十分な蓄電量を保持しているものとして説明する。
 制御部7は、電力系統3、発電機4および蓄電池6から負荷2への給電経路を決定し、負荷2への給電を制御するものである。制御部7は、発電量予測部8と、需要電力量予測部9と、閾値比較部10と、データ比較部11と、給電経路決定部12と、給電制御部13と、充放電制御部14とを含んでいる。
 発電量予測部8は、発電機4の所定時間後の単位時間当たりの発電量を予測した発電量予測データを作成する。発電量予測データとは、例えば、衛星により撮影した映像データに基づき、所定時間後の単位時間当たり(例えば、10分間)の発電機4の発電量を予測したデータである。具体的には、発電機4として太陽電池を用いた場合は、衛星の映像データから発電機4が位置する場所の雲の動きを予測することにより所定時間後の発電機4への日射量を予測し、発電機4の発電量を予測する。このとき、発電機4の現在の発電量を考慮しながら予測することが望ましい。発電量予測部8は、所定時間毎に発電量予測デ
ータを作成する。
 需要電力量予測部9は、負荷2の所定時間後の単位時間当たり(例えば、10分間)の需要電力量を予測した需要電力量予測データを作成する。具体的には、需要電力量予測部9は、記憶部5から需要電力量予測テーブルを取得し、予測したい時期・時刻と同時期・同時刻の需要電力量予測テーブルを参照して、負荷2の需要電力量を予測する。このとき、負荷2の現在の需要電力量を考慮しながら予測することが望ましい。需要電力量予測部9は、所定時間毎に需要電力量予測データを作成する。
 閾値比較部10は、需要電力量予測部9により予測された需要電力量が、電力会社との間における使用可能な契約電力量を超えるかどうかを判断する。具体的には、閾値比較部10は、需要電力量予測部9により予測された需要電力量と、記憶部5に記憶された所定の閾値とを比較する。そして、閾値比較部10は、予測された需要電力量が所定の閾値を超えると判断した場合には、その結果をデータ比較部11に送信し、予測された需要電力量が所定の閾値を超えないと判断した場合には、その結果を給電経路決定部12に送信する。
 データ比較部11は、予測された需要電力量が所定の閾値を超えるという判断結果を閾値比較部10から受信した場合、予測された需要電力量のうち所定の閾値を超えた電力量(以下、超過電力量)が、発電量予測部8により予測された発電量を超えるかどうかを判断する。具体的には、データ比較部11は、超過電力量と、発電量予測部8から取得した発電量予測データとを比較し、その結果を給電経路決定部12に送信する。
 給電経路決定部12は、閾値比較部10およびデータ比較部11から受信した結果に基づき、電力系統3、発電機4および蓄電池6から負荷2への給電経路を決定する。
 具体的には、給電経路決定部12は、予測された需要電力量が所定の閾値を超えていないという判断結果を閾値比較部10から受信した場合は、給電経路を電力系統3と決定する。また、給電経路決定部12は、超過電力量が予測された発電量を超えていないという判断結果をデータ比較部11から受信した場合は、給電経路を電力系統3および発電機4と決定する。また、給電経路決定部12は、超過電力量が予測された発電量を超えているという判断結果をデータ比較部11から受信した場合は、給電経路を電力系統3、発電機4および蓄電池6と決定する。
 給電制御部13は、給電経路決定部12の決定に基づき、給電経路の切り替えおよび給電量の制御を行う。充放電制御部14は、給電制御部13からの指示に基づき、蓄電池6への充放電を制御する。
 (給電制御装置1の動作)
 次に、給電制御装置1の制御方法について、図2を参照して説明する。図2は、給電制御装置1の動作を説明するためのフローチャートである。
 まず、需要電力量予測部9は、記憶部5に記憶されている需要電力量予測テーブルを参照して、負荷2の所定時間後の単位時間当たり(例えば、10分間)の需要電力量を予測した需要電力量予測データを作成する(S1)。
 次に、閾値比較部10は、需要電力量予測部9から需要電力量予測データを取得するとともに、予測された需要電力量と記憶部5に記憶されている所定の閾値とを比較する(S2)。ここで、所定の閾値とは、電力会社との間における使用可能な契約電力量を指す。
 閾値比較部10は、予測された需要電力量が所定の閾値よりも小さいと判断した場合(S2でNo)、その判断結果を給電経路決定部12に送信する。給電経路決定部12は、閾値比較部10の判断結果に基づき、負荷2への給電経路を電力系統3からと決定し、その結果を給電制御部13に送信する(S3)。給電制御部13は、給電経路決定部12の結果に基づき、電力系統3から負荷2に給電する(S4)。
 また、閾値比較部10は、需要電力量予測データが所定の閾値よりも大きいと判断した場合(S2でYes)、その判断結果をデータ比較部11に送信する。データ比較部11は、予測された需要電力量のうち所定の閾値を超えた分の電力量(以下、超過電力量)と発電量予測部8から取得した予測された発電量とを比較し(S5)、その判断結果を給電経路決定部12に送信する。
 給電経路決定部12は、超過電力量が予測された発電量よりも小さいという判断結果をデータ比較部11から受信した場合には(S5でNo)、負荷2への給電経路を電力系統3および発電機4からと決定し、その結果を給電制御部13に送信する(S6)。給電制御部13は、給電経路決定部12の結果に基づき、電力系統3および発電機4から負荷2に給電する(S7)。
 また、給電経路決定部12は、超過電力量が予測された発電量よりも大きいという判断結果をデータ比較部11から受信した場合には(S5でYes)、負荷2への給電経路を電力系統3、発電機4および蓄電池6からと決定し、その結果を給電制御部13に送信する(S8)。給電制御部13は、給電経路決定部12の結果に基づき、電力系統3、発電機4および蓄電池6から負荷2に給電する(S9)。
 なお、発電量予測部8および需要電力量予測部9は、所定時間毎に所定時間後の単位時間当たりの発電量および需要電力量を予測していく。そのため、給電制御装置1は、所定時間毎にS1~S9の動作を繰り返す。
 (効果)
 以下に、本発明の給電制御装置1の効果について、図3および図4を参照して説明する。図3は、給電制御装置1による制御を行った場合の電力購入量を示すグラフである。図4は、発電機4および蓄電池6の電力供給の内訳を示すグラフである。なお、図3および図4において、横軸は時間を、縦軸は電力購入量(kW)を示している。また、図4において、蓄電池6におけるプラス値は放電を、マイナス値は充電を示している。
 (1)給電制御装置1は、自然エネルギーを利用して発電する発電機4と電力系統3とに接続されており、発電機4および電力系統3から電力を蓄電する蓄電池6と、負荷2への給電を制御する制御部7とを備え、制御部7は、発電機4の単位時間当たりの発電量を予測する発電量予測部8と、負荷2の単位時間当たりの需要電力量を予測する需要電力量予測部9とを含み、予測した発電機4の発電量が予測した負荷2の需要電力量よりも低い場合に、蓄電池6から負荷2に給電する。
 これにより、発電機4の発電量が一時的に低下して、発電機4だけでは負荷2の需要電力を賄うことができない場合でも、蓄電池6から放電することにより発電機4の出力の低下分を補うことができる。給電制御装置1では、単位時間当たりの発電機4の発電量と、単位時間当たりの負荷2の需要電力量とを比較しているため、単位時間を例えば10分のように短く設定すれば、より確実な制御が可能となる。すなわち、給電制御装置1では、負荷2の需要電力量を、発電機4および蓄電池6により安定して賄うことが可能である。
 (2)制御部7は、需要電力量予測部9により予測した需要電力量が所定の閾値を超えない場合には、電力系統3から負荷2に給電し、需要電力量予測部9により予測した需要電力量が閾値を超える場合には、閾値を超えた電力量が、発電量予測部8により予測した発電量よりも小さいときは、電力系統3および発電機4から負荷2に給電し、予測した発電量よりも大きいときは、電力系統3、発電機4および蓄電池6から負荷2に給電する。
 これにより、図3および図4に示すように、負荷2の需要電力量が増加した場合に、電力系統3から所定の閾値(電力会社との間の契約電力量)を超えた量の電力を購入することなく、発電機4および蓄電池6からの電力で賄うことができる。その結果、給電制御装置1では、負荷2の需要電力量の増加に伴う電力系統3からの電力購入量の増加を抑制することができる。
 (3)発電量予測部8は、衛星から発電機4が位置する場所の映像データを取得して発電量予測データを作成する。これにより、発電量予測データを作成する外部ソースがなくとも、給電制御装置1だけで発電機4の発電量を予測することができ、負荷2への給電を適切に制御することが可能である。
 以上のように、給電制御装置1の構成について説明してきたが、本発明の給電制御装置は上述した構成に限定されるものではなく、請求項に示した範囲で種々の変更が可能である。
 (変形例)
 以下に、給電制御装置の変形例及びその効果について説明する。
 (a)給電制御装置1では、発電量予測部8は衛星から発電機4が位置する場所の映像データを取得して発電量予測データを作成する構成であるが、本発明はこれに限られない。例えば、イメージセンサで所定時間内の雲の動きを観測し、観測データに基づいて発電量予測データを作成する構成であってもよい。ここで所定時間とは、例えば1時間である。さらに、発電量予測データを作成する外部ソースがあり、そこから、無線もしくは有線の通信ネットワークを介して発電量予測データを取得する構成であってもかまわない。この場合、発電量予測部8を設ける必要がないため、部品点数を低減することができ、装置全体を小型化することが可能である。
 (b)給電制御装置1では、まず負荷2の予測された需要電力量と所定の閾値(電力系統3の契約電力量)とを比較する構成であるが、本発明はこれに限られない。本発明の給電制御装置は、まず負荷2の予測された需要電力量と発電機4の予測された発電量とを比較する構成であってもよい。この場合、予測された需要電力量が予測された発電量よりも大きいと判断された場合には、さらに蓄電池6から負荷2に給電する。さらに、負荷2の予測された需要電力量が発電機4の予測された発電量および蓄電池6の蓄電量よりも大きいと判断された場合には、超過電力量分を電力系統3から負荷2に給電する。
 このように、電力系統3からの負荷2への電力供給を、発電機4および蓄電池6からの電力供給よりも後にすることにより、電力系統3からの電力購入量を最小限に抑えることが可能である。
 (c)給電制御装置1では、蓄電池6が装置の内部に設けられた構成であるが、本発明はこれに限られない。図5は、本発明の給電制御装置の変形例を示す機能ブロック図である。本発明の給電制御装置では、図5に示すように、蓄電池6が装置の外部に設けられていてもよい。この場合、給電制御装置は蓄電池6を備えていないため、装置全体を小型化することが可能である。
 (d)給電制御装置1では、需要電力量予測部9は、過去の日時とその日時における負荷2の需要電力量とが関連付けられた需要電力量予測テーブルに基づいて、負荷2の単位時間当たりの需要電力量を予測しているが、本発明はこれに限られない。例えば、ユーザが1日の負荷2を利用する時間および利用量を予め設定しておくことにより、需要電力量予測部9が需要電力量予測データを作成する構成であってもよいし、需要電力量予測部9が外部から同一の負荷2を有する場合の平均的な需要電力量予測データを取得する構成であってもよい。
 本発明に係る給電制御装置は、自然エネルギーを利用する発電機を用いる給電装置の制御に利用できる。
 1 給電制御装置、2 負荷、3 電力系統、4 発電機、5 記憶部、6 蓄電池、7 制御部、8 発電量予測部、9 需要電力量予測部、10 閾値比較部、11 データ比較部、12 給電経路・給電量決定部、13 給電制御部、14 充放電制御部。

Claims (9)

  1.  自然エネルギーを利用して発電する発電部と電力系統とに接続されており、前記発電部および前記電力系統の少なくとも一方から電力を蓄電するとともに、所定の負荷に対して電力を供給する蓄電部と、
     前記負荷への給電を制御する制御部とを備え、
     前記制御部は、
     前記発電部による単位時間当たりの発電量を予測する発電量予測部と、
     前記負荷の単位時間当たりの需要電力量を予測する需要電力量予測部とを含み、
     前記発電量予測部により予測した発電量と、前記需要電力予測部により予測した需要電力量とを比較し、発電量が需要電力量よりも低い場合に、前記蓄電部から前記負荷に給電することを特徴とする給電制御装置。
  2.  自然エネルギーを利用して発電する発電部と電力系統とに接続されており、前記発電部および前記電力系統の少なくとも一方から電力を蓄電するとともに、所定の負荷に対して電力を供給する蓄電部と、
     前記負荷への給電を制御する制御部とを備え、
     前記制御部は、
     前記発電部による単位時間当たりの発電量を予測する発電量予測部と、
     前記負荷の単位時間当たりの需要電力量を予測する需要電力量予測部とを含み、
     前記需要電力量予測部により予測した需要電力量が所定の閾値を超えない場合には、前記電力系統から前記負荷に給電し、
     前記需要電力量予測部により予測した需要電力量が前記閾値を超える場合には、前記閾値を超えた電力量が、前記発電量予測部により予測した発電量よりも小さいときは、前記電力系統および前記発電部から前記負荷に給電し、予測した発電量よりも大きいときは、前記電力系統、前記発電部および前記蓄電部から前記負荷に給電すること特徴とする給電制御装置。
  3.  前記発電量予測部は、前記発電部が存在する地点を撮影した映像に基づいて、前記発電部の単位時間当たりの発電量を予測することを特徴とする請求項1または2に記載の給電制御装置。
  4.  前記発電量予測部は、前記発電部による単位時間当たりの発電量を予測した発電量予測データを外部から取得することを特徴とする請求項1または2に記載の給電制御装置。
  5.  前記制御部は、前記需要電力量予測部により予測した需要電力量が前記閾値を超えない場合には、前記発電部で発電した電力を前記蓄電部に蓄電することを特徴とする請求項2に記載の給電制御装置。
  6.  前記発電量予測部および前記需要電力量予測部は、所定時間毎に単位時間当たりの予測を行うことを特徴とする請求項1~5のいずれか1項に記載の給電制御装置。
  7.  前記需要電力量予測部は、前記負荷の過去の日時と需要電力量とを関連付けた需要電力量予測テーブルを参照して、前記負荷の単位時間当たりの需要電力量を予測することを特徴とする請求項1~6のいずれか1項に記載の給電制御装置。
  8.  前記所定の閾値は、電力会社との契約電力量に応じて決定されることを特徴とする請求項2に記載の給電制御装置。
  9.  所定の負荷への給電を制御する給電制御装置であって、
     自然エネルギーを利用して発電する発電部および電力系統の少なくとも一方から電力が蓄電される蓄電部の充放電を制御するとともに、前記負荷への給電を制御する制御部を備え、
     前記制御部は、
     前記発電部による単位時間当たりの発電量を予測する発電量予測部と、
     前記負荷の単位時間当たりの需要電力量を予測する需要電力量予測部とを含み、
     前記発電量予測部により予測した発電量と、前記需要電力予測部により予測した需要電力量とを比較し、発電量が需要電力量よりも低い場合に、前記蓄電部より前記負荷に対して放電することを特徴とする給電制御装置。
PCT/JP2011/062758 2010-06-03 2011-06-03 給電制御装置 WO2011152512A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2010127932A JP2013165534A (ja) 2010-06-03 2010-06-03 給電制御装置
JP2010-127932 2010-06-03

Publications (1)

Publication Number Publication Date
WO2011152512A1 true WO2011152512A1 (ja) 2011-12-08

Family

ID=45066867

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2011/062758 WO2011152512A1 (ja) 2010-06-03 2011-06-03 給電制御装置

Country Status (2)

Country Link
JP (1) JP2013165534A (ja)
WO (1) WO2011152512A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2905867A4 (en) * 2012-10-02 2015-11-18 Panasonic Ip Man Co Ltd ENERGY CONTROL SYSTEM AND SOLAR ENERGY GENERATION SYSTEM
WO2018138710A1 (ja) * 2017-01-26 2018-08-02 株式会社村田製作所 直流給電システム

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015042130A (ja) * 2013-08-23 2015-03-02 中国電力株式会社 電圧調整装置、電圧調整方法
JP5994027B2 (ja) * 2014-01-22 2016-09-21 株式会社日立製作所 電力供給システム及びこれに用いるエネルギーマネジメントシステム
JP6053711B2 (ja) * 2014-02-27 2016-12-27 三菱重工業株式会社 充電設備管理装置、充電設備管理方法、およびプログラム
JP6317431B2 (ja) 2014-04-24 2018-04-25 京セラ株式会社 制御方法および制御装置
KR102223230B1 (ko) * 2018-10-08 2021-03-05 주식회사 시너젠 Amp를 이용한 하이브리드 마이크로 그리드 시스템

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004289918A (ja) * 2003-03-20 2004-10-14 Fujitsu Ltd 電力供給方法
JP2007295680A (ja) * 2006-04-24 2007-11-08 Matsushita Electric Ind Co Ltd 負荷制御装置
JP2008141918A (ja) * 2006-12-05 2008-06-19 Nippon Telegr & Teleph Corp <Ntt> 太陽光発電システム評価装置、方法、およびプログラム
JP2009284586A (ja) * 2008-05-20 2009-12-03 Nippon Telegr & Teleph Corp <Ntt> 電力システムおよびその制御方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004289918A (ja) * 2003-03-20 2004-10-14 Fujitsu Ltd 電力供給方法
JP2007295680A (ja) * 2006-04-24 2007-11-08 Matsushita Electric Ind Co Ltd 負荷制御装置
JP2008141918A (ja) * 2006-12-05 2008-06-19 Nippon Telegr & Teleph Corp <Ntt> 太陽光発電システム評価装置、方法、およびプログラム
JP2009284586A (ja) * 2008-05-20 2009-12-03 Nippon Telegr & Teleph Corp <Ntt> 電力システムおよびその制御方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2905867A4 (en) * 2012-10-02 2015-11-18 Panasonic Ip Man Co Ltd ENERGY CONTROL SYSTEM AND SOLAR ENERGY GENERATION SYSTEM
WO2018138710A1 (ja) * 2017-01-26 2018-08-02 株式会社村田製作所 直流給電システム
US10700540B2 (en) 2017-01-26 2020-06-30 Murata Manufacturing Co., Ltd. DC power supply system

Also Published As

Publication number Publication date
JP2013165534A (ja) 2013-08-22

Similar Documents

Publication Publication Date Title
JP6304008B2 (ja) 電力供給システム
WO2011152512A1 (ja) 給電制御装置
JP4369450B2 (ja) 電力供給システム
JP5466911B2 (ja) 電力供給システム及び電力供給システムの制御装置
US11411400B2 (en) DC power supply system
EP2983265B1 (en) Electric power conversion device, control system, and control method
JP2008154360A (ja) 電力貯蔵装置及びハイブリッド型分散電源システム
US10749346B2 (en) Power management system
JP2011250673A (ja) エネルギーコントローラおよび制御方法
JP2016119728A (ja) 蓄電池の充放電制御装置および蓄電池の充放電制御方法
JP5994027B2 (ja) 電力供給システム及びこれに用いるエネルギーマネジメントシステム
JP5841279B2 (ja) 電力充電供給装置
JP2012200060A (ja) 給電制御システム及び給電制御方法
JP5480343B2 (ja) 直流電源システム
JP2013099207A (ja) 制御装置および制御方法
JP6355017B2 (ja) 電源制御装置及び電源制御方法
JP2017011849A (ja) 定置用蓄電システム
JP2006060984A (ja) 電源装置
JP6468948B2 (ja) 電源システム
WO2019053824A1 (ja) ソーラ発電所用の電力調整装置、発電システム及びソーラ発電所用の電力調整方法
JP2005048207A (ja) 水素製造システム
JP2014168343A (ja) 蓄電システム、蓄電システムの制御装置、蓄電システムの制御方法、及び蓄電システムの制御プログラム
JP2018038229A (ja) 蓄電システム
US10666165B2 (en) Power converting apparatus, power management system, and power converting method
JP6351200B2 (ja) 電力供給システム

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11789913

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 11789913

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: JP