WO2006106587A1 - 調達準備システム及び調達準備方法 - Google Patents

調達準備システム及び調達準備方法 Download PDF

Info

Publication number
WO2006106587A1
WO2006106587A1 PCT/JP2005/006352 JP2005006352W WO2006106587A1 WO 2006106587 A1 WO2006106587 A1 WO 2006106587A1 JP 2005006352 W JP2005006352 W JP 2005006352W WO 2006106587 A1 WO2006106587 A1 WO 2006106587A1
Authority
WO
WIPO (PCT)
Prior art keywords
information
parts
procurement
data
building
Prior art date
Application number
PCT/JP2005/006352
Other languages
English (en)
French (fr)
Inventor
Tamio Ishibashi
Original Assignee
Daiwa House Industry Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa House Industry Co., Ltd. filed Critical Daiwa House Industry Co., Ltd.
Priority to PCT/JP2005/006352 priority Critical patent/WO2006106587A1/ja
Priority to CNA2005800493629A priority patent/CN101151628A/zh
Publication of WO2006106587A1 publication Critical patent/WO2006106587A1/ja

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management

Definitions

  • the present invention systematizes a building, and intensively produces and procure parts and components constituting the system, thereby improving the efficiency of a series of processes leading to the completion of the design capability of each building property. At the same time, it is possible to improve the quality of the building and reduce the construction cost, and in particular, pick up the parts necessary for the construction of the building without excess or deficiency, based on the design details of the ordered building.
  • the present invention relates to a procurement preparation system and procurement preparation method for procurement in a timely manner.
  • a building including a house is different from each other in shape and specification in order to correspond to a specific site or user, and has been constructed by one-piece production.
  • single-product production it was necessary to start design from scratch each time an individual building was constructed.
  • each time it was necessary to select the necessary building materials and procure market power. Therefore, each time, there is a problem in that it takes time for design work, construction material selection work and procurement work.
  • Design work, building material selection work, and procurement work require specialized knowledge and experience, and the ability of the person in charge of the work is reflected in the quality of the work. Therefore, if such work is performed from the beginning every time a building is constructed, the quality and price of the building will be affected by the ability of the person in charge. In other words, it is not possible to perform appropriate design and selection of members when such a work is performed by a person with low ability. In addition, it is not possible to select a supplier who can provide building materials at an appropriate price, quality and delivery date. Therefore, there was a problem that the completed building did not meet customer requirements in terms of delivery time and quality, and the cost was within the budget.
  • a systemized building is constructed using parts that have been standardized in advance. Also standard The design rules for how to apply the selected parts to the individual design conditions and design contents are prepared in advance. Accordingly, it is possible to reduce the time and effort required for the design work and the selection of necessary building materials, and it is possible to provide a building with a certain quality regardless of the ability of the person in charge.
  • the present invention provides a specific means necessary for diversifying the specifications of a systemized building and supplying it more efficiently than before.
  • the object is to provide a means that makes it possible to pick up corresponding parts without excess or deficiency and procure them in a timely manner according to the building design.
  • the present invention is necessary for parts information storage means for storing information on procurement of parts and materials used for a building, outline shape information of an ordered building, information on the period of the building, and application of the building
  • Property information storage means for storing property data including rough layout information of parts and members, and receiving property data search information from authorized users, and receiving the property data search information from the property information storage means Acquire property data corresponding to the property data acquisition means, and based on the property data, pick out and aggregate at least a part of the items and quantities of parts and materials required for the construction of the ordered building.
  • Automatic pick-up means for creating pick-up information including extracted information extracted from the parts information storage means based on the picked-up item, and parts to be ordered based on the period information and pick-up information
  • Ordering information automatic creation means for creating ordering information including the item item, quantity, and procurement schedule of the member.
  • procurement information of parts / components is created in advance, and information created in design proposals and implementation designs to customers is stored and used, so that it is possible to use It is possible to automatically calculate the item, quantity, and procurement schedule of the part corresponding to the design content and provide it as ordering information. Therefore, parts corresponding to the design details of the building can be quickly and definitely picked up and ordered and procured on a schedule that can realize the scheduled period.
  • the part information storage means stores procurement cost information of each part 'member
  • the automatic pick-up means includes the procurement cost information in the extracted information. It can also be configured to create pick-up and retrieval information. With this configuration, it is possible to automatically calculate the procurement costs for parts and components in addition to the items, quantities, and procurement schedules for the parts corresponding to the design details of the building for which the order has been received. Therefore, convenience is further improved.
  • the present invention further includes a field designating unit for receiving an input for designating a factory for ordering parts and components of a building, and the component information storage unit includes production cost information and production of each component / member. Schedule information is set for each factory and stored. And means for creating the pick-up information by including production cost information and production schedule information associated with the factory designated by the factory designation means in the extracted information, and the output means comprises the ordering information, It can also be configured to perform processing to send to the factory designated by the factory designation means.
  • the schematic arrangement information may be configured to include sketch data.
  • architecture it is very easy to show the layout of the main parts and materials that make up a building on the floor plan, and the floor plan uses what is generally used for building design and construction. Information creation and management can be simplified.
  • the present invention is based on the fact that regular procurement request information is input, and is based on the rough shape information of the ordered building, the building period information, and the rough arrangement of parts and members necessary for the construction of the building.
  • Part information storage means that stores information related to procurement of parts / materials in advance based on the picked-up items
  • a step of creating ordering information including items, quantities, and procurement schedules of parts and parts to be ordered based on the construction period information of the building and the picked-up information is performed.
  • FIG. 1 is an explanatory diagram showing an overall configuration of a procurement preparation system of the present embodiment.
  • FIG. 2 is a block diagram showing a configuration of a procurement server in the procurement preparation system of the present embodiment.
  • FIG. 3 is a block diagram showing a configuration of a procurement terminal in the procurement preparation system of the present embodiment.
  • FIG. 4 is a block diagram showing a configuration of a property server in the procurement preparation system of the present embodiment.
  • FIG. 5 is a flowchart showing procurement preparation data creation processing.
  • FIG. 6 is an explanatory diagram showing a screen for selecting a transmission destination of procurement preparation data.
  • FIG. 7 is an explanatory diagram showing a screen for inputting login information of a procurement preparation person in charge.
  • FIG. 8 is an explanatory diagram showing a screen for selecting work contents.
  • FIG. 9 is an explanatory diagram showing a screen for entering search information for searching for property data.
  • FIG. 10 is an explanatory diagram showing a basic matter confirmation screen before creating work data.
  • FIG. 11 is an explanatory diagram showing a basic matter confirmation and correction screen after creation of work data.
  • FIG. 12 is an explanatory diagram showing a screen for inputting search information for searching for existing work data.
  • FIG. 13 is an explanatory view showing a display screen of standard picking data.
  • FIG. 14 is an explanatory diagram showing a detailed content display screen of standard picking data.
  • FIG. 15 is an explanatory diagram showing an item addition screen for adding standard picking data.
  • FIG. 16 is an explanatory view showing a display screen of bespoke data.
  • FIG. 1 to 16 show an embodiment of the present invention, and FIG. 1 shows the entire procurement preparation system.
  • Fig. 2 is a block diagram showing the configuration of the procurement server
  • Fig. 3 is a block diagram showing the configuration of the procurement terminal
  • Fig. 4 is a block diagram showing the configuration of the property server
  • Fig. 5 is the procurement data.
  • Flow chart showing the flow of creation processing Fig. 6 shows the screen for selecting the destination of procurement data
  • Fig. 7 shows the screen for entering the login information for the procurement preparation staff
  • Fig. 8 shows the screen for selecting work details
  • Fig. 9 shows Screen for entering search information to search for property data
  • Fig. 10 shows a screen for checking basic items before creating work data
  • Fig. 11 shows a screen for checking and correcting basic items after creating work data
  • Fig. 12 shows searching for existing work data Screen for entering search information to be used
  • Fig. 13 is a screen for displaying standard picking data
  • Fig. 14 is a screen for displaying details of standard picking data
  • Fig. 15 is an item adding screen for adding standard picking data
  • Fig. 16 is the display of bespoke data It is a screen.
  • Buildings such as so-called industrial homes that have standardized the parts that make up the building, processed in advance at the factory, and minimized assembly at the site, are as shown in (1) to (5) below. It can be provided by preparing information and means. First, at the development stage of an industrialized house, (1) part information including specifications, shapes, constituent materials and procurement information of pre-standardized building components, and (2) how these parts are combined Whether a building with a specific shape or specified specifications will be realized! / Prepare design rules.
  • the parts information and the design rules are provided in a state where they can be used as appropriate to the proposed designer who performs the work of reflecting the customer's request on the shape and specifications of the building.
  • it can be provided as a design rule book, plan book, and case book.
  • it can be provided as a database in which component information is registered.
  • the set parts can be registered as items that can be placed on the drawing, and can be provided as CAD software with a function that prohibits placement without following the design rules.
  • it can be provided as CAD software that holds information such as item, position, quantity, etc. of items placed on drawings in the drawing information.
  • the procurement preparation system S of this embodiment corresponds to a part of the procurement preparation system (4) among the above (1) to (5).
  • the data created in the previous process can be used.
  • the data created in the previous process includes parts information including the procurement information of standard parts shown in (1) above. It also includes property data determined based on a meeting between the proposed designer and the customer.
  • the property data includes outline shape information such as the floor plan and elevation of the building, period information such as the start date and completion date, and outline arrangement information of the parts and members constituting the building.
  • the data created in the previous process is acquired, and the necessary parts are calculated based on the layout information, and the picked-up data is created. Also, based on the calculated item, search for and acquire the procurement information on the necessary parts. Based on the picked-up data and procurement information, procurement preparation data including ordering information is created and transmitted to a manufacturing department such as a factory that actually procures parts.
  • Part information including standardized parts procurement information is associated with, for example, a part symbol and registered in the part information database.
  • Information registered in the parts information database is usually prepared at the development stage of industrialized houses, but may be added or changed as appropriate.
  • the outline shape information, period information, and outline layout information are created with orders for individual buildings, and are registered in the property-specific information database as property data.
  • floor plans and elevations based on various design plans are created, and these data are stored individually. After that, the building order is decided and the contract with the customer.
  • the final plan, elevation, etc. are treated as outline shape information and registered in the property-specific information database.
  • the confirmed start date and completion date are treated as construction period information and registered in the property-specific information database.
  • the floor plan, elevation, construction start date, completion date, etc. before confirmation is also registered in the property-specific information database, and confirmation information is given only to the ordered property and confirmed! /, Information You can identify it! /
  • the layout shows the layout and names of the parts and members that make up the building. Therefore, it is possible to pick up parts and parts items (symbols that identify parts and parts) and quantities required for actual building construction from the floor plan.
  • the sketch includes schematic arrangement information of parts and members. It should be noted that the placement and names of parts and members on the plan are easy to use and easy to use, but are not limited to the plan and may be shown in another drawing. In addition, it is not necessary for the rough layout information to be described in all the plans.
  • schematic shape information such as a plan view and an elevation view
  • schematic layout information such as a floor plan that describes the layout and names of parts and members
  • CAD data for example, Registered in the database.
  • the schematic arrangement information may be created as data in a list form.
  • CAD data and list data may be included. In short, it is only necessary to include information on the items and quantities of necessary parts and parts.
  • CAD data and list data can be converted into text data, for example, and transferred to the procurement preparation system of this example.
  • the procurement preparation system S includes a procurement server device 10, a procurement terminal 20, and a property server device 30.
  • the procurement server device 10, the procurement terminal 20, and the property server device 30 are configured to be connectable to each other via a communication line I such as the Internet or a dedicated line network or a LAN.
  • a communication line I such as the Internet or a dedicated line network or a LAN.
  • the parts information database is stored in the storage unit 11 of the procurement server device 10 as described later, and the property-specific information database is stored in the storage unit 31 of the property server device 30.
  • the power database may be stored in one server device.
  • a plurality of property server devices 30 and procurement server devices 10 may be provided.
  • a unified server device that integrates the procurement server device 10 and the property server device 30 is installed at the headquarters, and all terminals in each branch, each sales office, and each factory send and receive information to and from the unified server device.
  • You may comprise.
  • the procurement server device 10 may be installed in a production management center that supervises all factories, and the property server device 30 may be installed in each branch and each sales office. Further, the procurement server device 10 may be installed in each factory, and the property server device 30 may be installed in each branch and each sales office.
  • the procurement server device 10 includes a storage unit 11 in which various data and programs are stored, a communication unit 12 having a modem power as an input / output interface with the communication line I, and a storage unit 11. And a control unit 13 having a CPU for reading out the stored program and performing various processes based on the program.
  • the procurement server device 10 can be constituted by, for example, a personal computer, a workstation, a general-purpose computer, or the like. Further, the procurement server device 10 may be a single computer or may be configured as an information processing device having a plurality of computer powers.
  • the communication line I can be a public line such as a telephone line network or a dedicated communication line.
  • the storage unit 11 stores various programs and data. For example, parts information database and property-specific information using key information such as programs for registering and managing information in the parts information database, design request numbers that identify orders received, and parts symbols that identify parts and parts A program that retrieves and retrieves information from a database
  • the storage unit 11 stores a parts information database.
  • the information registered in the part information database includes the part symbol that can uniquely identify the part, the child part symbol that identifies the child parts and components that make up the part, and the parent part if there is a parent part that contains the part. Includes the parent part symbol to be identified, part material, shape, dimensions, machining data, strength data based on structural calculation, weight, joint data based on part's component assignment, etc.
  • procurement information of each part is registered in the part information database.
  • the procurement information includes, for example, the price, delivery date, supplier name, agency name, etc., if the part is a manufacturer-supplied product.
  • the part is a factory-made work, it includes the materials necessary for production, the suppliers, processing costs, production capacity, etc.
  • the component information database corresponds to the component information storage means of the present invention.
  • the parts information database is stored in the storage unit 11 of the procurement server device 10, and part of the database is stored in an external computer or storage device connected to the procurement server device 10 via the communication line I. As a configuration.
  • the procurement terminal 20 is configured to transmit and receive various data between the procurement server device 10 and the property server device 30 via the communication line I.
  • the person in charge of procurement transmits login information (ID and password), various search information, and various input information from the procurement terminal 20 to the procurement server device 10. Based on this, various data are also transmitted to the procurement terminal 20 for the procurement server device 10 and the procurement server device 10 displays the received data.
  • the procurement terminal 20 includes an input unit 21 for a procurement preparation person to input data, a display unit 22 such as a CRT or LCD panel, and a communication line I. It includes a communication unit 23 that is an output interface such as a modem, a storage unit 24 that stores various data and programs, and a control unit 25 that includes a CPU that controls these units.
  • the procurement terminal 20 is also configured with, for example, a personal computer. Further, instead of a personal computer, a workstation, a general-purpose computer, or the like can be used.
  • the input unit 21 includes a mouse, a keyboard, and the like.
  • the input unit 21 is A data capture device such as an electronic storage medium reader may be provided. With this configuration, electronic data to be transmitted to the procurement server device 10 can be taken into the procurement terminal 20. Further, the procurement terminal 20 may be connected to a printer device for printing documents such as a laser printer!
  • the property server device 30 includes a storage unit 31 in which various data and programs are stored, a communication unit 3 2 having a modem and the like as an input / output interface with the communication line I, and a storage unit 31. And a control unit 33 having a CPU for reading out the program stored in the computer and performing various processes based on the program.
  • the property server device 30 can be configured as an information processing device including a single personal computer, a plurality of personal computers, a workstation, a general-purpose computer, or the like, like the procurement server device 10 described above.
  • the storage unit 31 stores a property-specific information database in which various data relating to the building for which an order has been received is registered.
  • the property-specific information database is a database in which various design data proposed for customers and various data related to orders received are registered with the design request number as key information.
  • the data registered in the property-specific information database is stored in the storage unit 31, and part of the data is stored in the storage server 31 and an external computer or storage device connected to the property server device 30 via the communication line I. It may be configured to be stored in
  • the storage unit 31 stores information in the property-specific information database, manages and searches the registered information, and performs processing between the procurement server device 10 and the procurement terminal 20. Stores a program for data transmission / reception processing.
  • the following information may be registered in the property-specific information database.
  • the owner name, order branch name, design manager name, order date, order price, house product name, etc. can be registered as basic information of the ordered property.
  • specifications such as the layout of wall and structural pillars, structural design data, and the components (equipment, color, material, specifications, product number, etc.) of each part.
  • articles to be installed in buildings for example, grand pianos
  • the usage and necessity of each room Noh soundproof room, home theater, etc.
  • You can also register site information and ground information.
  • This property-specific information database corresponds to the property information storage means of the present invention.
  • the draft data is generated by the CAD system for creating the draft in the pre-procedure for creating the procurement preparation data by the procurement preparation system of this example, and is registered in the property-specific information database.
  • CAD data for floor plans and elevations, bearing wall and structural column layout information, and data such as structural calculation results are based on the proposed design drawings proposed to the customer in the process of creating the floor plan. It is created by input to the CAD system to create the actual design drawing data, and is registered in the property-specific information database.
  • the basic information of the ordered property and the specifications of the components, equipment, etc. of each part are converted into electronic data at the desired time, such as when creating a design proposal to be presented to the customer or at the time of contract.
  • You may register in another information database.
  • all of this information may be converted to electronic data, or some of the information is available in the form of printed documents, etc. You may check the contents by looking at.
  • step SI the procurement preparation person in charge transmits, to the procurement server device 10, factory designation information for designating a factory to which the procurement preparation data is transmitted by a predetermined input.
  • a selection screen as shown in FIG. 6 is displayed on the display unit 22 of the procurement terminal 20. The procurement officer selects a factory from the list and clicks the process start button. Thereby, the input data is transmitted to the procurement server device 10. Then, a login screen shown in FIG.
  • step S2 the procurement preparation officer transmits login information to the procurement server device 10 by a predetermined input. For example, enter your ID and password on the login screen and click the process start button. Thereby, the input data is transmitted to the procurement server device 10.
  • the procurement server device 10 performs user authentication based on the received login information. If the user is authenticated as a legitimate user, that is, a legitimate procurement preparation officer, the process is continued (step S2: Yes), and a menu bar for selecting work is displayed on the display unit 22. The On the other hand, if the authentication is not successful, the process is stopped (step S2: No), and an error message is displayed on the display unit 22.
  • the user information (for example, the name of the person in charge of procurement preparation) specified by this ID is included in the procurement preparation data for the parts and components created and modified in this session. Added as creator information.
  • the procurement preparation person in charge selects work contents and acquires property data of the ordered building property that is the target of the parts procurement work (steps S3 to S4).
  • step S3 the procurement preparation person in charge selects either “create new” or “continue” partition correction from the work selection menu shown in FIG.
  • the display unit 22 displays a menu bar for selecting an operation to be performed by the procurement preparation system S. If the procurement preparation data has not yet been created, and if the property is to create new procurement preparation data and create procurement preparation data, select “Create New”. On the other hand, select “continue” partition correction ”when adding or correcting existing procurement preparation data. It is also possible to select a work by inputting a predetermined command instead of selecting a menu.
  • Step S3 When “Create New” is selected in Step S3, as shown in Fig. 9 (a) to (c), Enter the property data registration date (CADNET transmission date shown in Fig. 9 (a)), owner name, drawing number, etc., search, extract the property data for which procurement preparation data will be created, and enter the desired input Select by means (step S4).
  • the desired property data can be identified from the property data accumulated in the property-specific information database.
  • design request numbers that can uniquely identify each property are assigned to all properties. Therefore, by entering the design request number, the corresponding data can be extracted from the information stored in the property-specific information database. In addition, when the design request number is not available, it is possible to narrow down the target data by inputting various search conditions and specify the corresponding data.
  • step S5 data used to create procurement preparation data is extracted from the specified property data and set as work data.
  • the property data includes rough shape information, construction period information, and rough layout information, but the rough shape information (plan view, elevation view, etc.) is used to pick up parts / members to be used. It is not required for delivery. Therefore, in step S5, basic information such as the owner name and housing product name, construction period information, and rough layout information are extracted from the property data, and set in the work data.
  • the work data is set, as shown in Fig. 11, a more detailed confirmation of basic items' correction screen is presented.
  • step S3 if "continue 'partition correction" is selected in step S3, as shown in Fig. 12 (a) and (b), as the search conditions, the building classification of the property, the procurement preparation data destination factory name Enter the existing work data creation date (date of pick-up form in Fig. 12 (b)), owner name, etc., search, narrow down the relevant data, and select the relevant property.
  • the procurement preparation data already created for the selected property and the procurement preparation data being created are selected and set as work data (step S6).
  • step S7 new work data is created from the property data or selected from existing work data, and the work data that is the current work target is set.
  • the basic items included in the work data are then presented on the basic item confirmation-correction screen shown in FIG. Check the contents here, and manually correct items Make corrections (step S7).
  • the owner name, factory name, and partition person name can be changed.
  • the work data includes “owner name”, “order number”, “product name”, “building classification”, “total area”, “CADNET transmission date”, “partition transmission destination”, “partitioner”. Information such as “fare”, “aggregation cost” and “total amount” is included.
  • Order No.” corresponds to the design request number
  • CADNET transmission date corresponds to the date on which the rough placement information such as the drawing is created and registered in the property-specific information database.
  • the factory name specified in step S1 is set in “partition transmission destination”
  • the procurement preparation person name logged in in step S2 is set in “sales person in charge”.
  • the “fare” and “aggregation cost” can be set according to the designated factory name, for example, by setting different expenses for each factory in advance. “Total amount” is calculated based on the procurement cost of the parts and materials picked up based on this work data.
  • Buttons for selecting items for various information processing operations are displayed on the basic item confirmation 'correction screen shown in Fig. 11. For example, “pick up standard”, “pick up bespoke”, “BMG”, “simple adjustment”, “print editing / send”, and the like.
  • the person in charge of procurement preparation selects a work item by input means such as clicking these buttons (step S8). Each work is described below.
  • “Selecting Standards” is the current work data included in the information included in the rough layout information?
  • information on parts (standard members) set as standard products in advance is picked up, and the work for creating standard pick-up data by summing up quantities by item is performed.
  • the standard pick-up data is created by first performing a rough automatic pick-up based on the data set as work data, and then making fine adjustments such as adding corrections.
  • step S9 a rough automatic pick-up is performed.
  • the items and quantities of parts / members included in the rough layout information included in the work data are extracted and aggregated.
  • the part symbols placed on the drawing are automatically extracted from the CAD data of the sketch as rough layout information included in the work data, and the item and quantity counter To do.
  • the part symbol and quantity data described in the configuration table column on the drawing are automatically extracted.
  • the data aggregated for multiple plans is added up, and the item and quantity of parts used for the entire building are calculated.
  • the list information is included in the rough layout information as described above, just list the list information.
  • the created standard pick-up and data are displayed on the screen shown in FIG.
  • the “symbol” shown in the column indicated by arrow B in FIG. 13 corresponds to the item (part symbol) of the part set as a standard product. In this way, the quantity is calculated for each item.
  • step S10 fine adjustment such as correction and addition is performed on the standard picking data automatically created by the general automatic picking.
  • the correction is performed as follows.
  • the screen shifts to the detailed content display screen for each component shown in Fig. 14.
  • the quantity of parts can be corrected. It is also possible to check the procurement information of parts.
  • the work of picking up the standard and adding a new part to the data is performed, for example, as follows.
  • the “Add Item Search” button is clicked on the screen of FIG. 13, the item addition screen shown in FIG. The surface is displayed. Enter the search information in the enlarged part, narrow down the standard parts that meet the conditions from the parts information database, and display them in the column marked A. The part selected and clicked can be added to the standard picking data.
  • step S11 the standard members after addition and change are totaled. That is, after the addition and correction work is completed, the “total processing display” button on the screen of FIG. At this time, if the part has a child member, the child members are also counted together. In addition, when there is a change in a part for which an accessory or set is set, the quantity is adjusted accordingly. Then, the work data is updated including the collected data.
  • parts can be picked up automatically by using the data created in the previous process almost automatically. In addition, mistakes in picking up and leakage can be prevented. In addition, by picking up the main parts, accessories and sets are adjusted automatically, so that waste can be saved. Therefore, the cost is reduced.
  • “Pick-up by order” picks up information on parts set as bespoke parts (parts made by order) from the information included in the rough layout information from the current work data, and collects quantities by item. Pick up bespoke! ⁇ Create data.
  • parts that do not meet the standards are designed when there is a special circumstance such as a design that cannot be realized without using parts that do not meet the standards, as requested by the customer.
  • the bespoke data can be included in the property data. For example, when creating schematic layout information by writing part layout information on the floor plan, it is also possible to write a part code for a custom-made product that is replaced by a standard product part code.
  • step S12 a roughly ordered part is selected. Specifically, when you click the “Pick up bespoke” button in Figure 11, the item and quantity of the symbol identified as a bespoke part from the CAD data and list information included in the rough layout information, as well as picking up the standard. Aggregate and create bespoke data. Then, the list shown in FIG. 16 is displayed.
  • custom-ordered parts by, for example, a method such as including a special-ordered part-specific symbol not included in the standard part symbol.
  • step S13 confirmation of detailed information, correction and correction of data
  • step S14 tabulation and storage
  • BMG based on the design details of each building, the work of counting the items and quantities of BMG parts created by the program that automatically designs the parts is performed each time (Step S16).
  • BMG is an abbreviation for Building Material Generator.
  • part design rules are programmed.
  • the procurement preparation system By entering the building design details received in the BMG program, the necessary items and quantities of the parts, as well as the parts information such as shape and constituent materials, are generated. Therefore, the rough layout information includes BMG parts item and quantity information.
  • BMG parts are pre-registered in the parts information database.
  • the BMG program is used instead of searching the parts information database.
  • the design information of the building is input to and processed. As a result, necessary part information is generated and acquired each time.
  • step S16 BMG processing
  • step S15 simple adjustment
  • step S15 simple adjustment
  • step S12 to S14 it is not necessary to pick up a special order (steps S12 to S14) if the design content does not require the use of custom parts. Therefore, the standard pick-up data is created at the minimum, and the total pick-up data can be created by adding custom pick-up data, data, and BMG member pick-up data as appropriate.
  • an order list creation process is performed (step S17).
  • the picked-up data is aggregated for each item, and order list data displaying the quantity and amount information for each item is created.
  • amount information in addition to the total amount, the unit price for each part and the order amount subtotal can be attached as appropriate. If there is information on parts manufactured at a specific factory, other order list data including only that information can be automatically created and output.
  • shipping information indicating when it is necessary to ship the aggregated parts to the factory site can be calculated for each part, and the information can be written in the order list.
  • information that indicates when raw materials should be procured can be written, taking into account information regarding the production capacity of the factory and the raw material procurement period.
  • the created order list is output by printing or sending data to the factory (step S18).
  • information on parts to be procured can be easily picked up and passed to the factory.
  • the factory is first designated and the part picking data is created.
  • the part may be picked up without designating the factory first.
  • characteristics such as procurement costs by the factory can be adjusted together after picking up the parts.
  • production is concentrated at one factory, it is not necessary to consider differences in procurement characteristics among factories.
  • parts and members corresponding to the design contents of a building can be quickly and definitely picked up and can be procured according to a schedule capable of realizing a scheduled period. Accordingly, it is possible to appropriately manage the ordering and production management of parts while responding to various types of building specifications, and supply necessary parts to the site with appropriate quality, delivery time, and price.

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

 工業化住宅の開発段階で、建物に使用する部品・部材の情報を部品情報データベースに予め登録し、受注した建物の図面、仕様書、工期、伏図等の情報を物件別情報データベースに予め登録する。伏図には、施工に必要な部品の配置情報が概略記載されているので、伏図データに基づいて、工場に発注すべき部品の品目及び数量を概略自動で拾い出すことができる。また、拾い出しデータに基づき、工場に引き渡す発注リストを概略自動で作成することができる。

Description

調達準備システム及び調達準備方法
技術分野
[0001] 本発明は、建物をシステム化し、このシステムを構成する部品や部材の生産及び調 達を集約的に行い、これにより各建物物件の設計力 竣工に至る一連の工程の効率 化を図ると共に、建物の品質を向上させ、かつ、建設コストの低減を図ることを可能と するもので、特に、受注した建物の設計内容に基づいて、建物の施工に必要な部品 を過不足なく拾い出して適時に調達するための調達準備システム及び調達準備方 法に関する。
背景技術
[0002] 従来、住宅を含む建築物は、固有の敷地や利用者に対応するため、一軒一軒その 形状や仕様が異なるものとされており、一品生産により建設されていた。一品生産で は、個々の建物を建設する際に、その都度、一から設計作業を行う必要があった。ま た、その都度、必要な建築資材を選定し市場力も調達する作業を行う必要があった。 従って、その都度、設計作業と、建築資材の選定作業及び調達作業に手間を要する という問題点があった。
[0003] また、設計作業や建築資材の選定作業及び調達作業は専門知識と経験を要し、 作業担当者の能力が作業内容の良否に反映される。従って、建物を建設する度に 一からこのような作業を行うと、担当者の能力によって建物の品質や価格が左右され ることになる。つまり、能力の低い担当者力このような作業を行った場合には、適切な 設計や部材の選定を行うことができない。また、適切な価格、品質、納期で建築資材 を提供してくれる購買先を選定することができない。従って、完成した建物が、納期 や品質の点で顧客の要求を満足するものになって 、なかったり、費用が予算内にお さまらな 、と 、う問題点があった。
[0004] このような問題点を改善する方法として、 V、わゆる工業ィ匕住宅のように、建物をシス テム化して供給するのが有効な手段である。
システム化された建物は、予め規格化された部品を用いて構成される。また、規格 ィ匕された部品を個別の設計条件や設計内容に対してどのように適用するかという設 計ルールが予め整備されている。従って、設計作業及び必要な建築資材の選定作 業にかかる手間が低減されると共に、担当者の能力に左右されずに一定の品質の建 物を提供することが可能となる。
[0005] また、規格化された部品は、工場で一括して生産され、各現場へ供給される。従つ て、必要な部品の供給を適切な品質、納期、価格で受けることができる。また、現場 工事での作業量を最小限に抑えることができ、現場工期の短縮化が実現される。ま た、現場組立の作業を合理化することが可能である。従って、作業に要する時間及 び人員を計算し易ぐ現場工事での無駄を省くことが可能である。
[0006] このように有利な特徴を備えた工業ィ匕住宅の建設を更に効率的に行うために、設 計力 竣工に至る一連の工程において、各工程に必要な情報を適時に作成して供 給する情報管理手段及び情報加工手段が求められている。特に、施主のより高度な 要望に対応するために建物の仕様を多様化させると、部品の構成が複雑化すると共 に、部品の品種や組み合わせのパターンが格段に増大する。従って、部品の発注管 理及び生産管理が困難になるという問題が生じる。また、施主に提案した設計内容 に対応する部品を過不足なく拾い出す作業が困難になるという問題が生じる。
[0007] 本発明は、上記のような問題に鑑み、システム化された建物の仕様を多様ィ匕し、か つ、従来よりも更に効率的に供給するために必要な具体的手段を提供するものであ つて、特に、建物の設計内容に応じて、対応する部品を過不足なく拾い出し、適時に 調達することを可能とする手段を提供することを目的とする。
発明の開示
[0008] 本発明は、建物に使用する部品 ·部材の調達に関する情報が格納される部品情報 格納手段と、受注した建物の概略形状情報,前記建物のェ期情報,前記建物の施 ェに必要な部品及び部材の概略配置情報,を含む物件データが格納される物件情 報格納手段と、正規の利用者による物件データ検索情報の入力を受け付けて、前記 物件情報格納手段から前記物件データ検索情報に対応する物件データを取得する 物件データ取得手段と、前記物件データに基づ!、て前記受注した建物の施工に必 要な部品'部材の品目及び数量の少なくとも一部を拾い出して集計した集計情報, 拾い出された品目に基づいて前記部品情報格納手段から抽出した抽出情報,を含 む拾い出し情報を作成する自動拾い出し手段と、前記ェ期情報及び前記拾い出し 情報に基づき、発注する部品 ·部材の品目,数量,調達スケジュール,を含む発注情 報を作成する発注情報自動作成手段と、を備えることを特徴とする。
[0009] このように、本発明によれば、建物に使用する部品 ·部材の調達に関する情報を予 め準備しておくことができる。また、正規の利用者は、物件データ検索情報を入力し て、受注した建物の施工に必要な部品及び部材の概略配置情報等を含む物件デー タを取得することができる。そして、前工程において作成された物件データと、予め準 備された部品,部材の調達情報とを利用することにより、受注した建物の設計内容に 対応する部品'部材の品目、数量を算出することができる。また、予め準備された部 品 '部材の調達情報に基づき、受注した建物の工期情報に適応する調達スケジユー ルを算出することができる。更に、算出した品目、数量、調達スケジュールを含む発 注情報を作成することができる。
[0010] つまり、予め部品 ·部材の調達情報を作成しておき、また顧客への設計提案や実施 設計において作成した情報を保存しておき、これらを利用すること〖こより、受注した建 物の設計内容に対応する部品'部材の品目、数量、調達スケジュールを自動で算出 し、発注情報として提供することができる。従って、建物の設計内容に対応する部品 を、迅速にかつ間違いなく拾い出すと共に、予定したェ期を実現可能とするスケジュ ールで発注し調達することができる。
[0011] また、本発明において、前記部品情報格納手段には、各々の部品'部材の調達費 用情報が格納され、前記自動拾い出し手段は、前記抽出情報に前記調達費用情報 を含めて前記拾 、出し情報を作成するように構成することもできる。このように構成す ると、受注した建物の設計内容に対応する部品'部材の品目、数量、調達スケジユー ルに加えて、部品 ·部材の調達費用も自動で算出することができる。従って、利便性 が更に向上される。
[0012] また、本発明は、建物の部品,部材を発注する工場を指定する入力を受け付けるェ 場指定手段をさらに含み、前記部品情報格納手段には、各部品 ·部材の製作費用 情報及び製作スケジュール情報が工場別に設定されて格納され、前記自動拾 ヽ出 し手段は、前記工場指定手段により指定された工場に関連付けられた製作費用情報 及び製作スケジュール情報を前記抽出情報に含めて前記拾い出し情報を作成し、 前記出力手段は、前記発注情報を、前記工場指定手段により指定された工場に送 信する処理を行うように構成することもできる。
このように構成すると、部品を製作する工場が複数ある場合に、発注先とする工場 を選択して指定することができる。また、各工場の製作能力に応じて、予定したェ期 を実現可能とする調達スケジュールを算出することができる。また、各工場の事情に 応じた製作費用を算出することができる。従って、工場による能力のばらつきを補正 することができる。また、工場数を増加させて建設戸数の増大に対応することができる
[0013] また、本発明において、前記概略配置情報には伏図データが含まれるように構成 することもできる。建築において、建物を構成する主要な部品 ·部材の配置は伏図上 にあらわすのが非常に簡便であり、また伏図は建物の設計、施工に一般的に用いら れているものをそのまま利用することができるので、情報の作成及び管理が簡易化さ れる。
[0014] そして、本発明は、正規の調達依頼情報が入力されたことに基づき、受注した建物 の概略形状情報,前記建物のェ期情報,前記建物の施工に必要な部品及び部材 の概略配置情報,を含む物件データを該物件データが格納される物件情報格納手 段から取得する工程と、前記物件データに基づき、受注した建物の施工に必要な部 品,部材の品目及び数量の少なくとも一部を拾い出して集計し、拾い出された品目に 基づいて、部品 ·部材の調達に関する情報を予め格納した部品情報格納手段力 情 報を抽出し、拾い出し情報を作成する工程と、受注した建物の工期情報と、前記拾 い出し情報とに基づき、発注する部品 ·部材の品目,数量,調達スケジュール,を含 む発注情報を作成する工程と、を行うことを特徴とする。
[0015] このように、受注した物件に関する情報を取得する工程と、取得した情報に基づき 発注する部品'部材の品目、数量を集計し、拾い出した品目の調達に関連する情報 を抽出して拾い出し情報を作成する工程と、拾い出し情報と工期情報とに基づき発 注する部品 *部材の品目,数量,調達スケジュール,を含む発注情報を作成するェ 程と、を行うことにより、既存のデータを利用して、迅速にかつ間違いなく拾い出すと 共に、予定した工期を実現可能とするスケジュールで発注し調達することができる。 図面の簡単な説明
[0016] [図 1]本実施形態の調達準備システムの全体構成を示す説明図である。
[図 2]本実施形態の調達準備システムにおける調達サーバの構成を示すブロック図 である。
[図 3]本実施形態の調達準備システムにおける調達用端末の構成を示すブロック図 である。
[図 4]本実施形態の調達準備システムにおける物件サーバの構成を示すブロック図 である。
[図 5]調達準備データ作成処理を示すフローチャートである。
[図 6]調達準備データの送信先を選択する画面を示す説明図である。
[図 7]調達準備担当者のログイン情報を入力する画面を示す説明図である。
[図 8]作業内容を選択する画面を示す説明図である。
[図 9]物件データを検索するための検索情報を入力する画面を示す説明図である。
[図 10]作業データ作成前の基本事項確認画面を示す説明図である。
[図 11]作業データ作成後の基本事項の確認修正画面を示す説明図である。
[図 12]既存作業データを検索するための検索情報を入力する画面を示す説明図で ある。
[図 13]規格拾いデータの表示画面を示す説明図である。
[図 14]規格拾いデータの詳細内容表示画面を示す説明図である。
[図 15]規格拾いデータの追加を行うための品目追加画面を示す説明図である。
[図 16]別注拾いデータの表示画面を示す説明図である。
発明を実施するための最良の形態
[0017] 本発明の実施の形態について、図面を参照して説明する。また、以下に説明する 配置、形状等は、本発明を限定するものではなぐ本発明の趣旨に沿って各種改変 することがでさることは勿!^である。
図 1乃至図 16は本発明の一実施形態を示す図で、図 1は調達準備システムの全体 構成を示す説明図、図 2は調達サーバの構成を示すブロック図、図 3は調達用端末 の構成を示すブロック図、図 4は物件サーバの構成を示すブロック図、図 5は調達デ ータ作成処理の流れを示すフローチャート、図 6は調達データの送信先を選択する 画面、図 7は調達準備担当者のログイン情報を入力する画面、図 8は作業内容を選 択する画面、図 9は物件データを検索するための検索情報を入力する画面、図 10は 作業データ作成前の基本事項確認画面、図 11は作業データ作成後の基本事項の 確認修正画面、図 12は既存作業データを検索するための検索情報を入力する画面 、図 13は規格拾いデータの表示画面、図 14は規格拾いデータの詳細内容表示画 面、図 15は規格拾いデータの追加を行うための品目追加画面、図 16は別注拾いデ ータの表示画面である。
[0018] (工業化住宅の提供手段)
建物を構成する部品を規格化し、予め工場で加工し、これにより現場での組み立て を最小限にした、いわゆる工業ィ匕住宅のような建物は、以下の(1)〜(5)のような情 報や手段を準備することにより提供可能となる。まず、工業化住宅の開発段階におい て、(1)予め規格化された建物構成部品の仕様、形状、構成材料、調達情報を含む 部品情報と、(2)これらの部品をどのように組み合わせると所定の形状あるいは所定 の仕様の建物が実現されるかと!/ヽぅ設計ルールと、を準備する。
[0019] 部品情報及び設計ルールは、顧客の要望を建物の形状や仕様に反映させる作業 を行う提案設計者に対し、適宜使用可能な状態で提供される。例えば、設計ルール ブックや、プラン集、事例集として提供することができる。また、部品情報を登録した データベースとして提供することができる。また、設定された部品を図面上に配置可 能なアイテムとして登録し、設計ルールに従わな 、配置を禁止する機能を備える CA Dソフトウェアとして提供することができる。また、図面上に配置されたアイテムの品目 、位置、数量、等の情報を図面情報に含めて保持する CADソフトウェアとして提供す ることがでさる。
[0020] また、規格化された部品や建築材料を適時に建設現場に供給するための具体的 手段を準備する。すなわち、(3)予め規格化された建物構成部品を製作可能な工場 設備と、(4)顧客が要望する設計内容に基づき、この設計内容を実現するために必 要な部品'部材の配置、品目、数量等を算出すると共に、工場設備の製作能力に応 じてェ期を守ることが可能なスケジュールを算出し、算出した情報を工場に受け渡す 調達準備システムと、 (5)調達準備システムカゝら提供された情報に基づき、工場設備 を予め設定された基準に従って稼動させ、必要な部品'部材の製作を行い、適時に 現場に出荷する製造システムと、を備える。
[0021] (調達準備システムの概要)
本実施形態の調達準備システム Sは、上記(1)〜(5)のうち、(4)の調達準備シス テムの一部に相当するものである。
本例の調達準備システム Sでは、前工程で作成されたデータが利用可能とされて いる。前工程で作成されたデータには、上記(1)に示す規格ィ匕部品の調達情報を含 む部品情報が含まれる。また、提案設計者と顧客との打ち合わせに基づいて決定さ れた物件データが含まれる。物件データには、建物の平面図、立面図などの概略形 状情報と、着工日や竣工日などのェ期情報と、建物を構成する部品や部材の概略 配置情報と、が含まれる。
そして、本例の調達準備システム Sでは、前工程で作成されたデータを取得し、主 に概略配置情報から、必要な部品'部材の品目、数量を算出し、拾い出しデータを 作成する。また、算出した品目に基づいて、必要な部品'部材の調達情報を検索し 取得する。そして、拾い出しデータと、調達情報とに基づき、発注情報などを含む調 達準備データを作成し、実際に部品を調達する工場などの製造部門に送信する。
[0022] 前工程におけるデータの作成は、以下のように行われる。
規格化された部品の調達情報を含む部品情報は、例えば、部品記号に関連づけら れ、部品情報データベースに登録されている。部品情報データベースに登録される 情報は、通常は工業化住宅の開発段階で準備されるが、適宜追加、変更されること がある。
また、概略形状情報、ェ期情報、及び概略配置情報は、個々の建物の受注に伴つ て作成され、物件データとして物件別情報データベースに登録される。例えば、受注 前の提案設計段階では、さまざまな設計案に基づく平面図、立面図が作成され、そ れらのデータは個別に保存される。その後、建物の受注が決定して顧客との契約が なされ、設計内容が確定すると、確定した平面図、立面図などが概略形状情報として 扱われ、物件別情報データベースに登録される。また、確定した着工日や竣工日は 工期情報として扱われ、物件別情報データベースに登録される。なお、確定する前 の平面図、立面図、着工日、竣工日等も物件別情報データベースに登録しておき、 受注した物件にのみ確定情報を付与して確定して!/、な 、情報と識別してもよ!/、。
[0023] そして、受注により確定した概略形状情報と、確定した他の設計内容 (例えば、色、 材質、塗装、設備、断熱仕様、等の各部位の仕様や、設定荷重、用途など)に基づき 、実施設計を行う担当者により、各種伏図や設備図などの実際の建物の施工に必要 な図面が作成される。本例では、伏図には、建物を構成する部品や部材の配置及び 名称が記載されている。従って、伏図から実際の建物の施工に必要な部品や部材の 品目(部品や部材を特定する記号)と、数量を拾い出すことができる。すなわち、伏図 には部品や部材の概略配置情報が含まれている。なお、伏図上に部品や部材の配 置及び名称を記載するのが、漏れがなぐ簡便であって利用しやすいが、伏図に限 定されず、別の図面に記載してもよい。また、全ての伏図に概略配置情報が記載さ れていなくてもよい。
[0024] 本例では、平面図、立面図などの概略形状情報と、部品や部材の配置及び名称を 記載した伏図などの概略配置情報は、例えば CADデータとして作成され、物件別情 報データベースに登録されている。また、概略配置情報は、リストのような形式のデー タとして作成されていてもよい。また、 CADデータとリストデータとを含んでいてもよい 。要するに、必要な部品 ·部材の品目及び数量の情報が含まれていればよい。 CAD データ及びリストデータは、例えばテキストデータ等に変換して、本例の調達準備シ ステムに受け渡すことができる。
[0025] (調達準備システムの構成)
まず、調達準備システム Sの全体構成について説明する。
図 1に示すように、調達準備システム Sは、調達サーバ装置 10と、調達用端末 20と 、物件サーバ装置 30とを備えて構成されている。調達サーバ装置 10、調達用端末 2 0、物件サーバ装置 30は、インターネット又は専用回線網、あるいは LAN等の通信 回線 Iを介して互 、に接続可能に構成されて 、る。 [0026] 本例では、部品情報データベースは、後述するように調達サーバ装置 10の記憶部 11に格納され、物件別情報データベースは、物件サーバ装置 30の記憶部 31に格 納される構成とした力 両データベースを一台のサーバ装置に格納するように構成し てもよい。また、物件サーバ装置 30、調達サーバ装置 10を複数設けても良い。
例えば、調達サーバ装置 10と物件サーバ装置 30を一体ィ匕した統一サーバ装置を 本社に設置し、各支店、各営業所、各工場の端末は全て統一サーバ装置との間で 情報を送受信するように構成してもよい。また、調達サーバ装置 10を全工場を統括 する生産管理センターに設置し、物件サーバ装置 30を各支店及び各営業所に設置 してもよい。また、調達サーバ装置 10を各工場にそれぞれ設置し、物件サーバ装置 30を各支店、各営業所にそれぞれ設置してもよい。
[0027] 次に、調達サーバ装置 10の構成について説明する。
図 2に示すように、調達サーバ装置 10は、各種データ及びプログラムが記憶された 記憶部 11と、通信回線 Iとの入出力インターフェースであるモデム等力もなる通信部 1 2と、記憶部 11に格納されたプログラムを読み出してこのプログラムに基づき各種の 処理を行うための CPUを備えた制御部 13と、を有している。
調達サーバ装置 10は、例えば、パーソナルコンピュータ、ワークステーション、汎用 コンピュータなどにより構成することができる。また、調達サーバ装置 10は、単独のコ ンピュータであってもよぐまた、複数のコンピュータ等力もなる情報処理装置として構 成されていてもよい。また、通信回線 Iは、例えば電話回線網等の公衆回線や、専用 通信回線とすることができる。
[0028] 記憶部 11には、各種プログラム及びデータが格納されて 、る。例えば、部品情報 データベースへの情報の登録や管理を行うプログラム、受注した建物を特定する設 計依頼番号や部品 ·部材を特定する部品記号等の各種情報をキー情報として部品 情報データベースや物件別情報データベースから情報を検索し取得するプログラム
、物件データに含まれる情報力 部品や部材の品目及び数量を拾い出して集計する プログラム、拾い出された部品の調達情報に基づき、発注情報などの調達準備デー タを作成するプログラム、作成した調達準備データを外部へ送信する処理を行うプロ グラム、等が格納されている。 [0029] また、記憶部 11には、部品情報データベースが格納されて!、る。部品情報データ ベースに登録される情報は、部品を一意に特定可能な部品記号、部品を構成する子 部品や構成部材を特定する子部品記号、部品を含む親部品がある場合には親部品 を特定する親部品記号、部品の材質、形状、寸法、加工データ、構造計算に基づく 強度データ、重量、部品'部材の割付に基づく接合データ、等を含む。
また、部品情報データベースには、各部品の調達情報が登録されている。調達情 報は、例えば、部品がメーカー供給品である場合には、価格、納期、サプライャ名、 代理店名、等が含まれる。また、部品が工場製作品である場合には、製作に必要な 資材及びその発注先、加工費、製作能力、等が含まれる。
[0030] なお、この部品情報データベースが本発明の部品情報格納手段に相当する。部品 情報データベースは、調達サーバ装置 10の記憶部 11に全て格納される構成とする ほか、一部を調達サーバ装置 10に通信回線 Iを介して接続された外部のコンビユー タまたは記憶装置に格納する構成としてもょ 、。
[0031] 次に、調達用端末 20の構成について説明する。
調達用端末 20は、図 1に示すように、通信回線 Iを介して調達サーバ装置 10及び 物件サーバ装置 30との間で各種データを送受信可能に構成されている。調達準備 担当者は、調達用端末 20から調達サーバ装置 10に、ログイン情報 (ID及びパスヮー ド)や各種検索情報、各種入力情報を送信する。これに基づき、調達サーバ装置 10 力も調達用端末 20に各種データが送信され、調達サーバ装置 10は受信したデータ を表示する。
[0032] 図 3に示すように、調達用端末 20は、調達準備担当者がデータを入力するための 入力部 21と、 CRT, LCDパネル等力 なる表示部 22と、通信回線 Iとの入出力イン ターフェースであるモデム等力 なる通信部 23と、各種データやプログラムが記憶さ れた記憶部 24と、これらを制御する CPUを備えた制御部 25を備えている。この調達 用端末 20は、例えばパーソナルコンピュータ力も構成されている。また、パーソナル コンピュータに代えて、ワークステーション、汎用コンピュータなどにより構成すること ができる。
入力部 21は、マウス、キーボード等から構成されている。また、入力部 21は、スキヤ ナ、電子記憶媒体読取装置等のデータ取込装置を備えていてもよい。このように構 成すると、調達サーバ装置 10に送信する電子データを調達用端末 20に取り込むこ とができる。また、調達用端末 20は、例えばレーザープリンタなど、書類を印刷する ためのプリンタ装置に接続されて 、てもよ!/、。
[0033] 次に、物件サーバ装置 30の構成について説明する。
図 4に示すように、物件サーバ装置 30は、各種データやプログラム等が記憶された 記憶部 31と、通信回線 Iとの入出力インターフェースであるモデム等力もなる通信部 3 2と、記憶部 31に格納されたプログラムを読み出してこのプログラムに基づき各種の 処理を行うための CPUを備えた制御部 33と、を有している。
物件サーバ装置 30は、上記調達サーバ装置 10と同様に、単独又は複数のパーソ ナルコンピュータ、ワークステーション、汎用コンピュータ等からなる情報処理装置とし て構成することができる。
[0034] 記憶部 31には、受注した建物に関する種々のデータが登録された物件別情報デ ータベースが格納されている。物件別情報データベースは、上述したように、顧客に 対して提案された設計案や、受注した建物に関する種々のデータを、設計依頼番号 をキー情報として関連付けて登録したものである。なお、物件別情報データベースに 登録されるデータは、記憶部 31に全て格納される構成とするほか、一部を物件サー バ装置 30に通信回線 Iを介して接続された外部のコンピュータまたは記憶装置に格 納する構成としてもよい。
また、記憶部 31には、物件別情報データベースへの情報の登録、登録された情報 の管理及び検索、等の処理を行うためのプログラムや、調達サーバ装置 10又は調達 用端末 20との間でデータの送受信処理を行うためのプログラムが格納されている。
[0035] 物件別情報データベースには、上述した概略形状情報、工期情報、及び概略配置 情報に加えて、以下のような情報を登録してもよい。例えば、施主名、受注支店名、 設計担当者名、受注日、受注金額、住宅商品名、等を、受注した物件の基本情報と して登録することができる。また、耐カ壁や構造柱の配置、構造設計データ、各部位 の構成部材ゃ設備等の仕様 (色、材質、仕様、品番など)、等を登録することもできる 。また、建物内に設置する物品 (例えばグランドピアノ等)や、各部屋の用途や所要性 能 (防音室、ホームシアター等)を登録することもできる。また、敷地情報や地盤等の 情報を登録することもできる。
なお、この物件別情報データベースが本発明の物件情報格納手段に相当する。
[0036] 伏図データは、上述したように、本例の調達準備システムによる調達準備データ作 成の前工程において、伏図を作成するための CADシステムによって生成され、物件 別情報データベースに登録されている。また、平面図及び立面図の CADデータ、耐 力壁や構造柱の配置情報や、構造計算結果などのデータは、伏図を作成する前ェ 程において、顧客に提案する提案設計図面に基づき、実施設計図面のデータを作 成するための CADシステムへの入力作業によって作成され、物件別情報データべ ースに登録されている。
なお、受注した物件の基本情報や、各部位の構成部材ゃ設備等の仕様は、例えば 、顧客に提示する設計案を作成した時や、契約時等の所望の時期に電子データ化 して物件別情報データベースに登録してもよい。また、これらの情報は、全てが電子 データ化されていてもよいし、一部が印刷された書類等の形態で調達準備担当者の 手元に入手可能とされており、調達準備担当者は書類を見てその内容を確認しても よい。
[0037] (調達準備データ作成処理の流れ)
次に、図 5に示すフローチャートと、図 6〜図 16に示す調達準備システム画面を参 照しながら、本実施形態の調達準備システム Sで行われる調達準備データ作成処理 の流れについて説明する。この調達準備データ作成処理は、例えば、調達サーバ装 置 10の記憶部 11に格納された各種プログラムに基づいて行われる。なお、本明細 書の図中に表示される「仕切」と ヽぅ語は、概ね「調達準備データ作成」を意味するも のである。例えば、図 8に示される「仕切修正」は調達準備データの修正を意味し、図 10に示される「仕切作成」は調達準備データの新規作成を意味し、図 11に示される「 仕切担当者」は調達準備データを作成する調達準備担当者を意味する。
[0038] まず、調達準備担当者は、調達用端末 20にインストールされた調達準備アプリケ ーシヨンを起動させる。そして、調達準備データ送信先、すなわち部品発注先の工場 を選択して、調達サーバ装置 10にログインする処理を行う(ステップ S1〜S2)。 [0039] ステップ SIにおいて、調達準備担当者は、所定の入力により調達準備データを送 信する工場を指定する工場指定情報を調達サーバ装置 10に送信する。例えば、調 達準備システムを起動すると、図 6に示すような選択画面が調達用端末 20の表示部 22に表示される。調達準備担当者は、リストの中から工場を選択し、処理開始ボタン をクリックする。これにより、入力したデータが調達サーバ装置 10に送信される。そし て、表示部 22に、図 7に示すログイン画面が表示される。
[0040] 続いて、ステップ S2において、調達準備担当者は、所定の入力によりログイン情報 を調達サーバ装置 10に送信する。例えば、ログイン画面に ID及びパスワードを入力 し、処理開始ボタンをクリックする。これにより、入力したデータが調達サーバ装置 10 に送信される。調達サーバ装置 10は、受信したログイン情報に基づいてユーザ認証 を行う。そして、正規のユーザ、すなわち正規の調達準備担当者として認証された場 合には処理を継続し (ステップ S2 : Yes)、表示部 22に作業選択を行うためのメ-ュ 一バーが表示される。一方、認証されない場合には処理を中止し (ステップ S2 : No) 、表示部 22にエラーメッセージが表示される。
なお、処理を継続する場合には、このセッションで作成、修正等される部品'部材の 調達準備データには、この IDにより特定されるユーザ情報 (例えば、調達準備担当 者名)が調達準備データ作成者情報として付加される。
[0041] 続いて、調達準備担当者は、作業内容を選択し、また、部品調達作業の対象とする 受注建物物件の物件データを取得する(ステップ S3〜S4)。
ステップ S3において、調達準備担当者は、図 8に示す作業選択メニューから「新規 作成」「継続'仕切修正」のいずれかを選択する。表示部 22には、調達準備システム Sで行う作業を選択するメニューバーが表示される。そして、まだ調達準備データが 作成されて ヽな 、物件にっ ヽて、新たに調達準備データを作成して調達準備データ 作成作業を行う場合には、「新規作成」を選択する。一方、既存の調達準備データの 追加'修正を行う場合には「継続'仕切修正」を選択する。なお、メニューを選択する 力わりに所定のコマンド入力により作業選択を行っても良 、。
[0042] 続、て、作業データを設定する (ステップ S4〜S6)。
ステップ S3において「新規作成」を選択した場合には、図 9 (a)〜(c)に示すように、 物件データの登録日(図 9 (a)に示す CADNET送信日)、施主名、図面番号、等を 入力して検索し、調達準備データ作成の対象とする物件データを抽出し、所望の入 力手段により選択する (ステップ S4)。これにより、物件別情報データベースに蓄積さ れて 、る物件データの中から、所望の物件データを特定することができる。
本例の調達準備システム Sでは、全物件に対して、各々の物件を一意に特定可能 な設計依頼番号が割り振られている。従って、設計依頼番号を入力することにより、 物件別情報データベースに蓄積された情報の中から、該当データを抽出することが できる。また、設計依頼番号が手元にない場合には、種々の検索条件を入力して対 象データを絞り込み、該当データを特定することもできる。
[0043] 次に、図 10に示す画面で基本事項の内容を確認し、「仕切作成」ボタンをクリックす る。すると、特定した物件データから、調達準備データの作成に使用されるデータが 抽出され、作業データとして設定される (ステップ S5)。例えば、本例では、物件デー タには、概略形状情報、工期情報、及び概略配置情報が含まれているが、概略形状 情報(平面図、立面図など)は使用する部品 ·部材の拾い出しには必要とされない。 従って、ステップ S5において、物件データから、施主名や住宅商品名等の基本情報 と、工期情報及び概略配置情報を抽出し、作業データに含めて設定する。作業デー タを設定すると、図 11に示すように、より詳細な基本事項の確認'修正画面が提示さ れる。
[0044] また、ステップ S3において「継続'仕切修正」を選択した場合には、図 12 (a) (b)に 示すように、検索条件として、物件の建物区分、調達準備データ送信先工場名、既 存作業データ作成日(図 12 (b)における拾い出し書作成日)、施主名、等を入力して 検索し、該当データを絞り込み、該当物件を選択する。これにより、選択した物件に っ ヽてすでに作成した調達準備データや、作成途中の調達準備データが選択され 、作業データとして設定される (ステップ S6)。
[0045] このようにして、新たな作業データが物件データから作成され、または既存の作業 データから選択され、現在作業対象とする作業データが設定される。作業データを設 定すると、続いて、作業データに含まれる基本事項が、図 11に示す基本事項確認- 修正画面によって提示される。ここで、内容を確認し、手動で修正可能な項目は適宜 修正を行う (ステップ S 7)。例えば、施主名、工場名、仕切担当者名(調達準備担当 者)は変更することができる。
[0046] 図 11に示すように、作業データには、「施主名」「受注 No」「商品名」「建物区分」「 総面積」「CADNET送信日」「仕切送信先」「仕切担当者」「運賃」「集積費」「合計金 額」などの情報が含まれる。
「受注 No」は、設計依頼番号に相当し、「CADNET送信日」は、この受注物件に っ 、て伏図等の概略配置情報が作成され物件別情報データベースに登録された日 に相当する。また、「仕切送信先」にはステップ S1で指定した工場名が設定され、「仕 切担当者」には、ステップ S2でログインした調達準備担当者名が設定されている。ま た、「運賃」や「集積費」は、例えば工場ごとに異なる費用を予め設定しておき、指定 した工場名に応じて設定することができる。「合計金額」は、この作業データに基づい て拾い出した部品や部材の調達費用が算出される。
[0047] なお、新たに作業データを設定する方法は、上記ステップ S4〜S5以外に、図 11 に示す基本事項確認'修正画面に表示された「複製」ボタンをクリックして行う方法も ある。既存の作業データを選択して、「複製」ボタンをクリックすると、現在作業対象と して設定されている作業データが複製されて保存される。そして、複製した作業デー タの内容について、変更が必要な部分のみ、適宜変更することにより、新たな物件の 調達準備データの作成を行うことができる。このよう〖こすると、わずかしか設計内容が 異ならない複数の受注物件の調達準備データの作成を効率ィ匕することができる。
[0048] 続いて、作業データに基づき、部品 ·部材の拾い出し、発注リストの作成等の各種 情報加工作業を行う (ステップ S8〜S17)。
図 11に示す基本事項確認'修正画面には、各種情報加工作業の項目を選択する ためのボタンが表示されている。例えば、「規格拾い」「別注拾い」「BMG」「簡易調整 」「印刷編集'送信」等である。調達準備担当者は、これらのボタンをクリックする等の 入力手段により、作業項目を選択する (ステップ S8)。以下、各々の作業について説 明する。
[0049] (規格拾い)
「規格拾い」では、現在の作業データのうち、概略配置情報に含まれる情報の中か ら、予め規格品として設定された部品(規格部材)の情報を拾い出し、品目別に数量 を集計して規格拾いデータを作成する作業を行う。規格拾いデータは、本例では、 作業データとして設定されたデータに基づいてまず概略自動拾い出しを行った後、 修正'追加等の微調整を加えることにより作成される。
[0050] まず、ステップ S9において、概略自動拾い出しを行う。すなわち、作業データに含 まれる概略配置情報に含まれる部品 ·部材の品目及び数量を抽出して集計する。例 えば、「規格拾い」ボタンをクリックすると、作業データに含まれる概略配置情報として の伏図の CADデータから、図面上に配置された部品記号を自動で抽出してその品 目と数量魏計する。あるいは、図面上の構成表欄に記載された部品記号と数量の データを自動で抽出する。そして、複数の伏図について集計したデータを合計し、建 物全体として使用される部品'部材の品目と数量を算出する。また、概略配置情報に 上述のようにリスト情報が含まれて 、た場合には、リスト情報を集計するだけでょ 、。 概略自動拾 、出しを行うと、作成された規格拾 、データが図 13に示す画面に表示 される。図 13の矢印 Bで示した欄に示される「記号」は、規格品として設定された部品 の品目(部品記号)に相当する。このように、品目ごとに数量が算出されている。
[0051] 次に、ステップ S10において、概略自動拾い出しにより自動で作成された規格拾い データに対し、修正'追加等の微調整を行う。例えば、修正は以下のように行う。図 1 3の画面で、「記号」の欄に表示された部品記号をダブルクリックすると、図 14に示す 各々の部品の詳細内容表示画面に移行する。この画面で、例えば部品の数量を修 正することができる。また、部品の調達情報等を確認することができる。
また、この画面では、拡大部分に示すような詳細情報が表示される。このように、概 略自動拾い出しを行うと、部品情報データベース力 拾い出された部品の詳細情報 が取得され規格拾いデータに追加される。例えば、図 14に示されるように、部品記号 「AAA— 1A」という部品について、「仕切単価」情報が取得されている。なお、「仕切 単価」は調達価格を意味する。
[0052] また、規格拾 、データに新たに部品を追加する作業は、例えば、以下のように行う 図 13の画面で「品目追加検索」ボタンをクリックすると、図 15に示される品目追加画 面が表示される。拡大した部分に検索情報を入力し、部品情報データベースから、 条件にあった規格部品を絞り込んで Aで示した欄に表示させる。その中から選択して クリックした部品を、規格拾いデータに追加することができる。
[0053] そして、ステップ S 11において、追加'変更後の規格部材の集計を行う。すなわち、 追加'修正作業が終了した後、図 13の画面の「集計処理表示」ボタンをクリックする。 このとき、部品が子部材を備えるものであった場合には、子部材の集計もあわせて行 われる。また、付属品やセット品が設定されている部品に変更があった場合には、そ の数量の調整も合わせて行われる。そして、集計された拾い出しデータを含んで作 業データが更新される。
以上のようにして、部品の拾い出し作業を、前工程で作成されたデータを利用して 大部分自動で行うことにより、大幅に効率ィ匕することができる。また、拾い出しミスや漏 れを防止することができる。また、主要な部品を拾い出すことにより、付属品やセット 品の調整が自動で行われるので、無駄を省くことができる。従って、コストが低減され る。
[0054] (別注拾い)
「別注拾い」では、現在の作業データのうち、概略配置情報に含まれる情報の中か ら、別注品として設定された部品 (別注部品)の情報を拾い出し、品目別に数量を集 計して別注拾!ヽデータを作成する作業を行う。
本例では、顧客の要望により、規格にない部品を使用しなければ実現不可能な設 計内容とされた等の特殊な事情がある場合に、規格にない部品が設計される。そし て、前工程において、すでに別注部材の使用が判明している場合には、別注拾いデ ータを物件データに含めて作成しておくことができる。例えば、伏図に部品配置情報 を記載して概略配置情報を作成する際に、規格品の部品記号でなぐ別注品の部品 記号を記載することもできる。
[0055] 規格拾!、で行った概略自動拾い出しでは、概略配置情報が別注部品を含んで 、 ても、その品目及び数量は集計されないが、以下の手順により、概略配置情報に含 まれる別注部品の品目及び数量のみを拾い出し、別注部品データを作成することが できる。 すなわち、ステップ S12において、別注部品の概略拾い出しを行う。具体的には図 11の「別注拾い」ボタンをクリックすると、規格拾いと同様に、概略配置情報に含まれ る CADデータやリスト情報から、別注部品であると識別された記号の品目と数量を集 計し、別注拾いデータを作成する。そして、図 16に示すリストが表示される。
なお、別注部品の識別は、例えば、規格部品の部品記号には含まれない別注部品 特有の記号を部品記号中に含める等の方法により可能とされる。
そして、規格拾いと同様に、詳細情報の確認、データの修正及び追カ卩 (ステップ S1 3)、集計及び保存 (ステップ S 14)等を行う。
[0056] (簡易調整)
「簡易調整」では、例えば沖縛仕様などのように、形状は同一であって、防鲭性能 だけを高めた部品を調達したい等のように、複数の部品を一括して仕様の異なる部 品に置き換えたい場合に行う処理である。このような機能を有することにより、例えば 、内陸地域で建設したものと同じ形状の建物を沿岸地域で建設する場合に、既存の 拾い出しデータを利用することができ、位置力もデータを作成する必要がない。従つ て、調達準備作業が効率化される。
具体的には、「簡易調整」ボタンをクリックすると、作業データ中の拾い出し '集計さ れた部品の中から、修正が必要な部品だけを自動で抽出し、変更する処理を行う (ス テツプ S15)。具体的には、例えば、「簡易調整」をクリックし、表示された画面で「沖 縛仕様」をクリックすると、拾い出された部品の中からボルトを含む部品だけが抽出さ れ、その部品記号を、より防鲭性の高いボルトを使用する部品の部品記号に置き換 える。それに伴い、各部品に関連付けられた部品情報のうち、修正が必要な情報を、 置き換え後の新たな部品記号に基いて抽出し直し、修正する。例えば、防鲭性能を 高めるために塗装仕様が変更されると、調達価格が変更される。
[0057] (BMG)
「BMG」では、個々の建物の設計内容に基づき、その都度、部品を自動で設計す るプログラムにより作成される BMG部品の品目及び数量を集計する作業を行う(ステ ップ S 16)。 BMGとは、 Building Material Generatorの略語であり、例えば、部 品の設計ルールをプログラム化したものである。本例では、調達準備システムの前ェ 程において、 BMGプログラムに受注した建物の設計内容を入力することにより、必要 な部品の品目及び数量と、形状や構成材料などの部品情報が生成されている。従つ て、概略配置情報には BMG部品の品目及び数量情報が含まれている。つまり、 BM G部品は、部品情報データベースに予め情報が登録されて 、な 、点にぉ 、て規格 部品と異なり、部品情報を取得するためには、部品情報データベースの検索に代え て、 BMGプログラムに建物の設計情報を入力して処理を行う。これにより、必要な部 品情報をその都度生成し、取得する。
[0058] (集計及び出力)
以上の各工程により、必要な拾い出し作業を一通り終えると、各工程で作成された データ^^約して出力することができる。なお、 BMG処理 (ステップ S16)は BMGに 対応しない住宅商品については行う必要がない。また、簡易調整 (ステップ S 15)に ついても、調整を行わない仕様であれば行う必要がない。また、別注拾い (ステップ S 12〜S14)についても、別注部品を全く使用する必要のない設計内容であれば行う 必要がない。従って、最低限作成されるのは規格拾いデータであり、これに、適宜、 別注拾 、データ、 BMG部材の拾い出しデータを加えて合計拾い出しデータを作成 することができる。
[0059] 次に、この合計拾い出しデータを工場に受け渡すための集計及び出力処理を行う まず、発注リスト作成処理を行う(ステップ S17)。すなわち、拾い出したデータを、 品目ごとに集計し、各々の数量と金額情報を表示した発注リストデータを作成する。 金額情報として、全体の合計金額のほかに、部品ごとの単価及び発注金額小計を適 宜添付することができる。なお、特定の工場において製作される部品の情報があれ ば、その情報のみを含む別の発注リストデータを自動で作成して出力することもでき る。
また、ェ期情報に基づいて、集計した部品をいつ工場力 現場へ出荷する必要が あるかを示す出荷情報を、各々の部品について算出し、発注リストにその情報を記載 することもできる。また、更に、工場の生産能力と原材料の調達期間に関する情報を 加味して、原材料をいつ調達すべきかを示す情報を記載することもできる。なお、必 要がなければ合計金額、単価及び発注金額を省略してもよい。製造に必須の情報で はないからである。
続いて、作成した発注リストを印刷又は工場へのデータ送信により出力する (ステツ プ S18)。以上により、調達すべき部品の情報を、容易に漏れなく拾い出し、工場に 受け渡すことができる。
[0060] (改変例 1)
上記実施例は、はじめに工場を指定し、部品の拾い出しデータの作成を行ってい たが、工場を最初に指定せずに部品の拾い出しを行ってもよいのは勿論である。この 場合、工場による調達費用等の特性は、部品の拾い出し後にまとめて調整することも 可能である。また、一工場により集約して生産を行う場合には、工場による調達特性 の差異を考慮する必要がな 、。
[0061] 以上のように、本発明によれば、以下のような効果を奏する。
本発明の調達準備システム及び調達方法によれば、建物の設計内容に対応する 部品ゃ部材を、迅速にかつ間違いなく拾い出すと共に、予定したェ期を実現可能な スケジュールで調達することができる。従って、建物の仕様の多様ィ匕に対応しながら 、部品の発注管理及び生産管理を適切に行い、必要な部品を適切な品質、納期、 価格で過不足なく現場に供給することができる。
また、部品'部材の調達費用も自動で算出することができるので、予算管理が容易 化され、利便性が更に向上される。また、部品を製作する工場が指定可能とされてお り、各工場の製作能力に応じた調達スケジュール及び各工場の事情に応じた製作費 用を算出することができる。従って、工場による能力のばらつきを補正することができ る。

Claims

請求の範囲
[1] 建物に使用する部品,部材の調達に関する情報が格納される部品情報格納手段と 受注した建物の概略形状情報,前記建物のェ期情報,前記建物の施工に必要な 部品及び部材の概略配置情報,を含む物件データが格納される物件情報格納手段 と、
正規の利用者による物件データ検索情報の入力を受け付けて、前記物件情報格 納手段から前記物件データ検索情報に対応する物件データを取得する物件データ 取得手段と、
前記物件データに基づいて前記受注した建物の施工に必要な部品 ·部材の品目 及び数量の少なくとも一部を拾い出して集計した集計情報,拾い出された品目に基 づいて前記部品情報格納手段から抽出した抽出情報,を含む拾い出レ f青報を作成 する自動拾い出し手段と、
前記ェ期情報及び前記拾い出し情報に基づき、発注する部品 ·部材の品目,数量 ,調達スケジュール,を含む発注情報を作成する発注情報自動作成手段と、を備え たことを特徴とする調達準備システム。
[2] 前記部品情報格納手段には、各々の部品'部材の調達費用情報が格納され、 前記自動拾い出し手段は、前記調達費用情報を前記抽出情報に含めて前記拾い 出し情報を作成することを特徴とする請求項 1に記載の調達準備システム。
[3] 建物の部品'部材を発注する工場を指定する入力を受け付ける工場指定手段をさ らに含み、
前記部品情報格納手段には、各部品 ·部材の製作費用情報及び製作スケジユー ル情報が工場別に設定されて格納され、
前記自動拾い出し手段は、前記工場指定手段により指定された工場に関連付けら れた製作費用情報及び製作スケジュール情報を前記抽出情報に含めて前記拾い出 し情報を作成し、
前記出力手段は、前記発注情報を、前記工場指定手段により指定された工場に送 信する処理を行うことを特徴とする請求項 1に記載の調達準備システム。
[4] 前記概略配置情報には伏図データが含まれることを特徴とする請求項 1に記載の 調達準備システム。
[5] 正規の調達依頼情報が入力されたことに基づき、受注した建物の概略形状情報, 前記建物のェ期情報,前記建物の施工に必要な部品及び部材の概略配置情報,を 含む物件データを該物件データが格納される物件情報格納手段力 取得する工程 と、
前記物件データに基づき、受注した建物の施工に必要な部品 ·部材の品目及び数 量の少なくとも一部を拾い出して集計し、拾い出された品目に基づいて、部品'部材 の調達に関する情報を予め格納した部品情報格納手段力 情報を抽出し、拾い出し 情報を作成する工程と、
受注した建物の工期情報と、前記拾い出し情報とに基づき、発注する部品'部材の 品目,数量,調達スケジュール,を含む発注情報を作成する工程と、を行うことを特 徴とする調達準備方法。
PCT/JP2005/006352 2005-03-31 2005-03-31 調達準備システム及び調達準備方法 WO2006106587A1 (ja)

Priority Applications (2)

Application Number Priority Date Filing Date Title
PCT/JP2005/006352 WO2006106587A1 (ja) 2005-03-31 2005-03-31 調達準備システム及び調達準備方法
CNA2005800493629A CN101151628A (zh) 2005-03-31 2005-03-31 采购预备系统和采购预备方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2005/006352 WO2006106587A1 (ja) 2005-03-31 2005-03-31 調達準備システム及び調達準備方法

Publications (1)

Publication Number Publication Date
WO2006106587A1 true WO2006106587A1 (ja) 2006-10-12

Family

ID=37073155

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2005/006352 WO2006106587A1 (ja) 2005-03-31 2005-03-31 調達準備システム及び調達準備方法

Country Status (2)

Country Link
CN (1) CN101151628A (ja)
WO (1) WO2006106587A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3690793A4 (en) * 2017-09-29 2021-09-01 Hitachi Construction Machinery Co., Ltd. COMPONENT PROCUREMENT SYSTEM AND COMPONENT PROCUREMENT PROCEDURE
CN113763066A (zh) * 2020-06-18 2021-12-07 北京京东振世信息技术有限公司 用于分析信息的方法和装置

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103559546A (zh) * 2013-11-26 2014-02-05 武钢集团昆明钢铁股份有限公司 一种利用备件装机量控制采购计划的管理系统与方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001188813A (ja) * 1999-12-28 2001-07-10 Asahi Kasei Corp 住宅資材発注方法およびシステム
JP2001188812A (ja) * 1999-12-28 2001-07-10 Asahi Kasei Corp 工業化注文住宅設計方法およびシステム
JP2001273418A (ja) * 2000-03-24 2001-10-05 Original Engineering Consultants Co Ltd 建設実際原価算出システム
JP2001283050A (ja) * 2000-03-28 2001-10-12 Daiwa House Ind Co Ltd 住宅産業におけるユーザー参加型設計支援システム
JP2002222221A (ja) * 2000-11-24 2002-08-09 Alfa Prime Japan:Kk 住宅情報管理方法、住宅情報管理システム、決済支援方法および決済支援システム
JP2002366607A (ja) * 2001-06-05 2002-12-20 Japan Science & Technology Corp 住宅供給システム
JP2004102929A (ja) * 2002-09-12 2004-04-02 Wood One:Kk 住宅部材生産管理方法および装置

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001188813A (ja) * 1999-12-28 2001-07-10 Asahi Kasei Corp 住宅資材発注方法およびシステム
JP2001188812A (ja) * 1999-12-28 2001-07-10 Asahi Kasei Corp 工業化注文住宅設計方法およびシステム
JP2001273418A (ja) * 2000-03-24 2001-10-05 Original Engineering Consultants Co Ltd 建設実際原価算出システム
JP2001283050A (ja) * 2000-03-28 2001-10-12 Daiwa House Ind Co Ltd 住宅産業におけるユーザー参加型設計支援システム
JP2002222221A (ja) * 2000-11-24 2002-08-09 Alfa Prime Japan:Kk 住宅情報管理方法、住宅情報管理システム、決済支援方法および決済支援システム
JP2002366607A (ja) * 2001-06-05 2002-12-20 Japan Science & Technology Corp 住宅供給システム
JP2004102929A (ja) * 2002-09-12 2004-04-02 Wood One:Kk 住宅部材生産管理方法および装置

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3690793A4 (en) * 2017-09-29 2021-09-01 Hitachi Construction Machinery Co., Ltd. COMPONENT PROCUREMENT SYSTEM AND COMPONENT PROCUREMENT PROCEDURE
US11443081B2 (en) 2017-09-29 2022-09-13 Hitachi Construction Machinery Co., Ltd. Part procurement system and part procurement method
CN113763066A (zh) * 2020-06-18 2021-12-07 北京京东振世信息技术有限公司 用于分析信息的方法和装置
CN113763066B (zh) * 2020-06-18 2023-11-03 北京京东振世信息技术有限公司 用于分析信息的方法和装置

Also Published As

Publication number Publication date
CN101151628A (zh) 2008-03-26

Similar Documents

Publication Publication Date Title
US20050102152A1 (en) Commercial real estate property management system
US20150234377A1 (en) Construction management system
JP2002024495A (ja) スケジュール管理システム
US20070112788A1 (en) Development management system
US11907879B2 (en) System and method for renewable power system interconnection submission processing with the aid of a digital computer
US20030097288A1 (en) Inspection schedule management support system and inspection schedule management support method
US20040064381A1 (en) Method and system for supplying management and maintenance parts
WO2006106587A1 (ja) 調達準備システム及び調達準備方法
CA3038780C (en) System and method for management of web order placement
JP2005100192A (ja) 商品受発注在庫管理システム、及び商品受発注在庫管理装置
JP5004878B2 (ja) 建設関係図面等情報配布システム
JP2002259768A (ja) 印刷物受発注システム
JP2001306718A (ja) コンピュータ及び通信技術を使った情報関連事業を提供する事業システム
CN202276361U (zh) 支持多种访问方式的协同办公系统
KR20140122469A (ko) 통합 업무 지원 서비스 시스템 및 방법
JP2005011106A (ja) 調達管理システム
JP2001117983A (ja) 原価管理装置及び記録媒体
JP2007309034A (ja) 基礎用鉄筋管理システム
JP2005275688A (ja) 生地生産計画管理システム
JP4871409B1 (ja) サインメンテナンスシステムおよびサインメンテナンスシステムを利用したサインメンテナンス方法
JP2011014111A (ja) 物の管理情報と、人の管理情報との相互管理システム
US20050033636A1 (en) Advertisement creation support system and advertisement creation support control method
JP4150495B2 (ja) 協調設計方法及び協調設計システム
JP2004234281A (ja) 住宅リフォーム見積システムおよび住宅リフォーム見積プログラム
JP2005284881A (ja) 業務進捗状況管理システム

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application
WWE Wipo information: entry into national phase

Ref document number: 200580049362.9

Country of ref document: CN

NENP Non-entry into the national phase

Ref country code: DE

WWW Wipo information: withdrawn in national office

Country of ref document: DE

NENP Non-entry into the national phase

Ref country code: RU

WWW Wipo information: withdrawn in national office

Country of ref document: RU

122 Ep: pct application non-entry in european phase

Ref document number: 05727249

Country of ref document: EP

Kind code of ref document: A1

WWW Wipo information: withdrawn in national office

Ref document number: 5727249

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: JP