WO2006058962A1 - Method and product in the erection of a building - Google Patents
Method and product in the erection of a building Download PDFInfo
- Publication number
- WO2006058962A1 WO2006058962A1 PCT/FI2005/000523 FI2005000523W WO2006058962A1 WO 2006058962 A1 WO2006058962 A1 WO 2006058962A1 FI 2005000523 W FI2005000523 W FI 2005000523W WO 2006058962 A1 WO2006058962 A1 WO 2006058962A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- beams
- floor
- building
- wall
- external wall
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B1/355—Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the tilting up of whole buildings or sections thereof, e.g. walls, portal frames
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/2616—Hinged connections of wooden members
Definitions
- the present invention relates to a method as disclosed in the preamble of claim 1 and to a product as disclosed in the preamble of claim 8 for use in the erection of a building.
- the method and product of the invention hereinafter referred to by the common designation ⁇ solution of the invention' , are particularly well applicable for use in the erection of a building to be built on a ventilated base floor. According to the invention, it is possible to build the floor, outer wall and roof structures of the building to a given degree of completion before the actual erection of the building.
- the solution of the invention is also usable with other types of base floor solutions.
- prior art building factories make prefabricated elements in a horizontal plane, but in this case the construction work has to be carried out by skilled labor and transporting the large elements to the building site is difficult and expensive. Moreover, mounting the large elements at the building site requires the use of an expensive crane as well as skilled labor.
- prior-art methods such as platform construction, wherein the frame structure of a wall is completed in a horizontal plane and the complete wall frame or part of a wall thus assembled is lifted in a single operation to an upright position to the place where it is to be mounted.
- the object of the present invention is to overcome some of the above-mentioned drawbacks and to create an efficient and workable method and a corresponding product in the erection of a building that are good and safe in respect of working ergonomy.
- a further object is to achieve a fast solution of economical price for the erection of a building.
- the method of the invention is characterized by what is disclosed in the characterization part of claim 1, and the product of the invention is characterized by what is disclosed in the characterization part of claim 8.
- Other embodiments of the invention are characterized by what is disclosed in the other claims.
- the advantages of the solution of the invention include the fact that the building's wall structures together with wind shield boards and other necessary components can be built to completion in a horizontal plane, and thus, as compared to traditional building, the construction work is considerably faster, better and considerably safer in respect of working ergonomy, because the construction work can be carried out without using scaffolding, which often involves very laborious work, and there is no major risk of falling down during construction.
- a further advantage is that the outer surface structures of exterior walls, such as boarding and painting of boards, can be completed safely and very quickly in a horizontal plane. It is also an advantage that the building need not necessarily be provided with construction- time temporary structures, such as bracings, to keep the walls upright.
- Yet another significant advantage is that the construction work in a horizontal plane is carried out directly on the building site and the construction work can be executed without skilled labor.
- the components of the frame structures delivered to the building site have largely been designed to standard dimensions so that they are the right size in both width, length and thickness, the only important detail is determination of the starting point, whereafter e.g. the floor beams and the frame structures of the walls as well as the wall panels and thermal insulation can be mounted directly on the elements to be built, without working them at all, and thus the traditionally required tools are not needed at the building site and the site remains free of construction waste, such as saw dust, plaster board or insulating material waste, produced by the working of materials.
- the standard dimensioning obviates the need to perform on the building site any dimensioning, which otherwise is normally a very rigorous and time-consuming task, because the pre-dimensioned structural components, when mounted on each other according to instructions, automatically bring the structures of the building to their designed dimensions. Furthermore, there is also the advantage that the entire roof structures of the building can, if desirable, be constructed and painted from the ground, which means savings in time and costs while a considerably better working safety in the construction work is achieved than in the traditional building method. A crane is thus only needed to lift off the roof structure completed on site from on top of the external wall elements of the building and to lift the completed roof structure into its position on the external wall elements lifted to an upright position.
- the product to be manufactured one important component of which is hereinafter called a beam pair, has the additional advantage that such beam pairs can be industrially manufactured using a very simple device.
- a beam pair For the manufacture of the product, no heavy industrial infrastructure and no significant investments are needed. If necessary, the beam pair manufacture can be transferred to where raw material is available or a demand exists.
- the rest of the materials required for the structures consists of existing standard construction material.
- the beam pairs of the invention have been so designed that they can be packed in a mutually overlapping manner in a very compact transport package, with no empty space left between beam pairs.
- Fig. 1 presents an oblique side view of a beam pair according to the invention, turned to a partially open position
- Fig. 2 presents an oblique side view of beam pairs mounted side by side with even distances upon the foundation of a house
- Fig. 3 presents an oblique side view of wall element constructed from beam pairs in a horizontal plane and provided with wall boarding on the outer surface, which element has not yet been lifted to an upright position to form an actual wall
- Fig. 4 presents an oblique side view of the wall element of Fig. 3, lifted and locked to an upright position to form a complete wall element
- Fig. 5 presents a wall element with a window opening for a side wall of a building as seen directly from inside the building
- Fig. ⁇ presents a sectional and simplified diagrammatic side view of a wall and floor structure constructed from a beam pair, with a roof structure mounted upon it
- Fig. 7 presents a simplified diagrammatic cross-sectional view of a whole building as seen from the gable-end of the building
- Fig. 8 presents a simplified sectional view of the structure of a gable wall element of a building as seen from the side of the element.
- Fig. 1 presents a beam pair 1 according to the invention, forming an important component, seen in an oblique top view and cut into two parts in the longitudinal direction.
- the beam pair 1 comprises a floor beam 2, which has on its lower surface a supporting batten 3 of a length substantially shorter at both ends than the floor beam 2.
- the supporting batten 3 is attached centrally to the floor beam 2 and is wider than the floor beam 2 so that the supporting battens 3 of two adjacent beam pairs 1 support a floor baseboard 11 to be mounted between the floor beams 2.
- the external wall beam 4 Pivoted by a hinge 6 on the upper surface of the floor beam 2 at a position close to the outer end of the floor beam is an external wall beam 4 having a thickness substantially equal to that of the floor beam 2 and a length so selected that the height of the finished wall will be substantially the same as a wall height according to standard construction.
- the external wall beam 4 consists of at least a wall frame beam 4a and an additional beam 5 attached to the outer surface of the frame beam 4a and having a thickness substantially corresponding to the thickness of the frame beam 4a.
- the upper end of the frame beam 4a of the external wall beam 4 is provided with a rectangular cutout 7 made in the outer surface of the frame beam, whereafter the aforesaid additional beam 5 is fastened to the outer surface of the frame beam 4a.
- the length of the additional beam 5 has been fitted to be longer than the length of the frame beam 4a so that in the longitudinal direction each end of the additional beam 5 extends past the respective end of the frame beam 4a.
- the beam pair 1 in the collapsed position is a combination of four components placed one over the other, of which the two middlemost ones, i.e. the floor beam 2 and the frame beam 4a are hinged together by a hinge 6.
- Fig. 2 presents three truncated beam pairs 1 according to the invention mounted on a foundation, such as a plinth structure, so that the base floor solution of the building is a so-called ventilated base floor.
- a foundation such as a plinth structure
- the plinth structure is not shown in the drawing.
- the beam pairs 1 are placed at predetermined distances, substantially with spacing k-600 between them on the plinth structure in such manner that the floor baseboard 11 can be easily mounted afterwards between the beam pairs 1.
- the floor baseboard 11 has been depicted in Fig. 2 already at this stage of installation to give a better visual perception, it is often easier to mount the baseboards 11 e.g. only after the walls have been erected and the roof structure mounted in place.
- the horizontal distance between beam pairs is determined by means of tie plates 12 and 14, which come ready provided with markings showing the position of the midpoint or one side edge of the floor beam 2 of each beam pair.
- the floor beams 2 can be automatically placed at a correct distance from each other.
- the mounting work is started by placing the beam pair 1 adjacent to the gable end onto the marked point on the plinth structure.
- the tie plates 12 and 14 are fastened by their first ends to the ends of the floor beam 2 of the first beam pair, whereupon the next beam pair is positioned at the markings on the tie plates 12 and 14 secured by its ends to the tie plates 12 and 14.
- a third beam pair is again placed at the next marking on the tie plates 12 and 14 and secured by its ends to the tie plates 12 and 14.
- the position of the pivot of the hinge 6 has been so chosen that the distance from the pivot to the outer edge of the tie plate 12 of the floor beam 2 is substantially at least equal to the width of the frame beam 4a of the external wall beam.
- the lower end 9 of the additional beam 5 comprised in the external wall beam 4 will stop the external wall beam at exactly the right angle, which is substantially a right angle.
- the inner edge of the additional beam 5 of the uplifted external wall beam 4 is thus in the vertical plane substantially in the same line with the outer surface of the tie plate 12 at the outer end 8 of the floor beam 2.
- Fig. 3 presents a finished wall element 20 assembled from beam pairs 1 on the building site and containing beam pairs 1 according to Fig. 2, mutually secured at predetermined distances between them and braced by tie plates 12 and 14.
- the external wall beams 4 of the beam pairs are mutually braced by an overhead cross-bracing beam 13, which is placed in notches 7 made in the outer surface of the frame beams 4a.
- the overhead cross-bracing beam 13 is secured to the external wall beams 4 e.g. by screwing or nailing through the additional beams 5.
- a wind shield board 17 of standard width and length is fastened to the outer surfaces of the additional beams 5.
- the lower edge of the wind shield board 17 ends at the same level as the lower surfaces of the additional beams 5 and its upper edge ends at the same level as the upper surfaces of the additional beams 5.
- the standard width of the wind shield board is substantially exactly the same as the width of the three beam pairs 1 mounted on the foundation and secured to each other. Ventilating strips 15 of a length substantially equal to that of the wind shield board 17 are fastened onto the wind shield board 17 at a position and in an orientation corresponding to the position and orientation of the external wall beams 4 under the wind shield board 17.
- External cladding panels 16 are correspondingly fastened onto the ventilating strips 15, but at this stage the lowest board of the panels is preferably left out to allow the wall elements 20 to be more easily locked in the upright position.
- the boards of the external cladding panel 16 have a length substantially equal to the total width of the three beam pairs 1 mounted on the foundation and fastened to each other.
- the panel boards of the external cladding panel 16 are given a surface treatment, e.g. painted before the wall element 20 is lifted to the upright position.
- a locking screw 10 provided with a washer or equivalent is screwed into the lower end of the ventilating strip 15, which screw is used to lock the uplifted wall element 20 in the upright position.
- a locking screw 10 provided with a washer or equivalent is screwed into the lower end of the ventilating strip 15, which screw is used to lock the uplifted wall element 20 in the upright position.
- substantially all the above-mentioned stages of work explained with reference to Fig. 3 are carried out in a horizontal plane before the completed wall element 20 is lifted to its upright position. It is advantageous to build substantially all the wall elements 20 of the side walls to completion at once before lifting the wall elements to the upright position.
- the bracing beams 18 make the structure sturdier and allow the wall elements to be more easily lifted to the upright position.
- Fig. 3 shows the situation before the mounting
- Fig. 4 the completed wall element 20 has been lifted as a single element to its upright position and secured at a substantially right angle relative to the floor beams 2 by means of locking screws 10.
- Thermal insulation, plastic lining and interior wall paneling of standard width are placed in the spaces between the external wall beams 4, against the wind shield board 17.
- An essential point is that the positioning and dimensioning or the beam pairs 1 have been so adapted as to allow thermal insulation and interior wall panel materials of standard width and length to be mounted on the wall element 20 without substantial working and dimensioning at the building site.
- vertical cladding boards are mounted over the vertical joints between the wall elements 20 to cover the gaps between adjacent external cladding panels 16.
- Fig. 5 presents a wall element 32 with a window opening for a side wall of a building as seen directly from inside the building.
- a window opening 27 is made in the wall element 32 in the area of three or more external wall beams 4.
- the external wall beams 31 below the window opening 27 are fastened to the floor beams 2 in the same way as the normal external wall beams 4 and they end below the window opening 27 to support the lower window beam 30.
- the lower window beam 30 is secured to the external wall beams 4 and 31.
- the external wall beams 28 above the window opening 27 are fastened to the wall element 32 via an overhead cross- bracing beam 13.
- the upper window beam 29 is secured to the external wall beams 4 and 28.
- the wind shield board 17b below the window opening 27 is fastened to the external wall beams 4 and 31 and to the upper window beam 30.
- the wind shield board 17a above the window opening 27 is fastened to the external wall beams 4 and 28 and to the upper window beam 29.
- a tie beam 18 mounted in a horizontal position at the upper end of the wall elements ties the wall element 32 with a window opening to the other wall elements 20.
- Fig. 6 presents a simplified sectional view of a building's side wall constructed from uplifted wall elements 20 and 32, as well as floor structures and roof structures. All the wall elements 20 and 32 of the side wall are secured to each other via a horizontal tie beam 18 at the upper end of the external wall beams so as to form a unitary wall assembly. The roof structure already built to completion is lifted onto the tie beams 18 and secured in its proper place.
- Fig. 7 presents a simplified cross-sectional view the wall structures, floor structures and rafter beams 19 of a building as seen from the gable-end of the building.
- the floor beams 2, which are fastened to the side walls of the building, i.e. to the beam pairs 1, have been made to predetermined dimensions and their length is determined by the length of the external wall beams 4 of the beam pairs 1, this length being consistent with the standard dimensioning.
- the final width of the building is determined according to the length of the middlemost floor beams 21 mounted between the opposite beam pairs 1 placed on different sides of the building. However, this length is so adapted that the width of the building is in exact agreement with the standard spacing of the wall beams.
- the middlemost floor beams 21 are substantially aligned with the outermost floor beams 2 and their lower surfaces are provided with corresponding supporting battens 3, to which the floor baseboards 11 are secured as in the case of the outermost floor beams 2.
- the main parts of the roof structures can be built from the ground.
- the rafters 19 are lifted onto the completed wall elements 20 before lifting the wall elements 20 to the upright position.
- the rafters 19 are placed on the wall elements 20 with spacing k-900.
- spacing k-900 may also be necessary to have a compensating spacing below k-900.
- This compensating spacing can be dimensioned e.g. by the traditional measuring method.
- the work stage can be carried out without using a crane, because the roof rafters need not be lifted to a great height.
- the roof structures can thus be built to completion.
- the surface treatment of the roof structures such as painting of the gables, can be performed from the ground.
- the finished and assembled roof structure is lifted off the wall elements 20 by using e.g. ropes and a crane.
- the wall elements 20 are lifted up about the hinges and locked to the upright position. ' If the tie beams 18 have not yet been fastened to the upper end of the wall elements 20, then they have to be fastened now. ' The tie beams 18 lock the wall elements 20 together as a single assembly. Once the wall elements 20 are in the upright position and the tie beams . have been secured in place, the completed roof structure is lifted by means of a crane onto the tie beams 18 and secured in position.
- tile roofing An exception to building the roof structure from the ground is the mounting of tile roofing, because, due to the heavy ⁇ weight of the material, tile roofing is appropriately mounted by the traditional technique only after the roof structures have been lifted up onto the tie beams 18. Likewise, a large and heavy roof structure is preferably built by the traditional technique, because it may be difficult to lift up a heavy roof structure with a large surface area.
- the floor baseboards 11 can be secured in place e.g. with screws to the supporting battens 3 attached to the floor beams 2.
- the thermal insulation of the floor is mounted on the floor baseboards 11, in the spaces between the floor beams 2, using standard- width thermal insulation material.
- the floor of the building is built on the floor beams 2 using prior-art techniques.
- FIG. 8 illustrates the assembly and erection of the wall elements 20 of the long walls, i.e. side walls of a building on the construction site.
- the end wall elements 24 are built as illustrated in Fig. 8.
- the external wall beams 23 of the end walls of the building which were not yet connected by hinges to the floor beams 2 and 21 in the factory delivery, are fastened to the outermost floor beams 2 and 21, i.e. to the floor beams closest to the end of the building.
- the outermost floor beams 2 and 21 at each end of the building are provided with markings spaced at equal distances showing the positions where the external wall beams 23 are to be mounted and the positions for the hinges 22 to be fastened to the mounting positions.
- hinges 22 spaced at equal distances are mounted on these floor beams 2 and 21 already at the factory, to which hinges the external wall beams 23 of the end walls are secured by their lower parts.
- the end wall elements 24 are constructed in a substantially horizontal plane and erected like the wall elements 20 of the long walls of the building.
- the external wall beams 23 of the uplifted end wall elements 24 are supported on a sole 25 secured onto the foundation, such as a plinth 26, and they are locked in their upright position by means of fastening elements 33, such as nails or screws, from the inner side of the floor beams 2 and 21.
- one wall element 20 can be advantageously constructed e.g. by connecting five or seven external wall beams 4 together by means of an overhead cross-bracing beam 13 and a tie beam 18 before lifting the wall element 20 to the upright position. Also, four, six or more external wall beams can be connected together before the wall elements are lifted to the upright position.
- the paneling 16 forming the external cladding may also be implemented by various vertical paneling methods, in which case the external wall structure is provided with ventilating strips in the horizontal direction as well. In this way, a continuous cladding paneling 16 covering the entire length or the wall is obtained, and no separate cladding boards are needed over the gaps between the wall elements 20 and 24.
- the external cladding can also be made after the erection of the wall elements, in which case it is possible to use longer cladding panels on the wall surface than those described above in the example according to Fig. 3.
- the external cladding can also be made from other materials than paneling boards, e.g. from tiles, ashlars or bricks, or the external cladding may be combination of several materials.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Finishing Walls (AREA)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP05818164A EP1831475A1 (en) | 2004-12-01 | 2005-12-01 | Method and product in the erection of a building |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FI20041555A FI20041555A (fi) | 2004-12-01 | 2004-12-01 | Menetelmä ja tuote rakennuksen pystyttämisessä |
FI20041555 | 2004-12-01 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2006058962A1 true WO2006058962A1 (en) | 2006-06-08 |
Family
ID=33547929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/FI2005/000523 WO2006058962A1 (en) | 2004-12-01 | 2005-12-01 | Method and product in the erection of a building |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP1831475A1 (fi) |
FI (1) | FI20041555A (fi) |
RU (1) | RU2007124600A (fi) |
WO (1) | WO2006058962A1 (fi) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
IT201800004131A1 (it) * | 2018-03-30 | 2019-09-30 | Ve Cam S R L | Metodo per la messa in opera di pannelli prefabbricati sulle travi perimetrali di edifici a struttura metallica, per la formazione delle pareti perimetrali di detti edifici |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2033438A (en) * | 1933-06-13 | 1936-03-10 | Mcferran Robert Bayard | Cabin structure |
GB530634A (en) * | 1939-06-15 | 1940-12-17 | Martin Hunter Briggs | Improvements in or relating to portable buildings |
US4831807A (en) * | 1988-01-28 | 1989-05-23 | Bolt Bernard L | Profile open/fold-up truss |
US5322404A (en) * | 1992-09-11 | 1994-06-21 | Bobby E. Keller | Wall lifting device |
WO1999064688A1 (en) * | 1998-06-09 | 1999-12-16 | I-Lok Multi-Structural International Limited | Prefabricated building systems |
-
2004
- 2004-12-01 FI FI20041555A patent/FI20041555A/fi unknown
-
2005
- 2005-12-01 EP EP05818164A patent/EP1831475A1/en not_active Withdrawn
- 2005-12-01 WO PCT/FI2005/000523 patent/WO2006058962A1/en active Application Filing
- 2005-12-01 RU RU2007124600/03A patent/RU2007124600A/ru unknown
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2033438A (en) * | 1933-06-13 | 1936-03-10 | Mcferran Robert Bayard | Cabin structure |
GB530634A (en) * | 1939-06-15 | 1940-12-17 | Martin Hunter Briggs | Improvements in or relating to portable buildings |
US4831807A (en) * | 1988-01-28 | 1989-05-23 | Bolt Bernard L | Profile open/fold-up truss |
US5322404A (en) * | 1992-09-11 | 1994-06-21 | Bobby E. Keller | Wall lifting device |
WO1999064688A1 (en) * | 1998-06-09 | 1999-12-16 | I-Lok Multi-Structural International Limited | Prefabricated building systems |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
IT201800004131A1 (it) * | 2018-03-30 | 2019-09-30 | Ve Cam S R L | Metodo per la messa in opera di pannelli prefabbricati sulle travi perimetrali di edifici a struttura metallica, per la formazione delle pareti perimetrali di detti edifici |
Also Published As
Publication number | Publication date |
---|---|
RU2007124600A (ru) | 2009-01-10 |
FI20041555A (fi) | 2006-06-02 |
FI20041555A0 (fi) | 2004-12-01 |
EP1831475A1 (en) | 2007-09-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8082718B2 (en) | Bookshelf building panel and method of construction | |
US6067771A (en) | Method and apparatus for manufacturing modular building | |
US20090145075A1 (en) | Timber-framed building structures, and method of constructing same | |
US20100058687A1 (en) | Method of constructing a multi-storey building using prefabricated modular panels | |
US5058343A (en) | Modular log structures and methods of constructing same | |
RU101058U1 (ru) | Каркас дома или другого сооружения на основе профильной клееной балки | |
US2396829A (en) | Building construction | |
SE448558B (sv) | Byggnadskonstruktion samt forfarande for astadkommande derav | |
GB2480994A (en) | Timber I-beams and panels in attic roof structures | |
EP1831475A1 (en) | Method and product in the erection of a building | |
US4073103A (en) | Building structure and method of construction | |
US8561374B2 (en) | Article of manufacture for wood construction | |
CA2639339A1 (en) | Method of constructing a multi-storey building using prefabricated modular panels | |
RU2233367C1 (ru) | Домокомплект сборного каркасно-панельного здания | |
JP3876507B2 (ja) | 小屋組構造およびその施工法 | |
JP2008536030A (ja) | リングビーム構造物と木質梁工法 | |
GB2340531A (en) | Method of manufacturing pre-fabricated building construction elements | |
RU2596167C1 (ru) | Способ строительства с применением деревянной бескаркасной панели | |
JP2688877B2 (ja) | 木造建築物の建築工法 | |
JPH0649905A (ja) | 組立ハウスの施工方法 | |
FI81165C (fi) | Platta av solidpapp foer byggnadsaendamaol. | |
US20120151863A1 (en) | Wooden structural building panels | |
JP4260318B2 (ja) | 屋根構造 | |
AU2011100884A4 (en) | Environ Roof | |
JPH0233808B2 (fi) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AK | Designated states |
Kind code of ref document: A1 Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BW BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE EG ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KM KN KP KR KZ LC LK LR LS LT LU LV LY MA MD MG MK MN MW MX MZ NA NG NI NO NZ OM PG PH PL PT RO RU SC SD SE SG SK SL SM SY TJ TM TN TR TT TZ UA UG US UZ VC VN YU ZA ZM ZW |
|
AL | Designated countries for regional patents |
Kind code of ref document: A1 Designated state(s): BW GH GM KE LS MW MZ NA SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LT LU LV MC NL PL PT RO SE SI SK TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG |
|
121 | Ep: the epo has been informed by wipo that ep was designated in this application | ||
NENP | Non-entry into the national phase |
Ref country code: DE |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2005818164 Country of ref document: EP |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2007124600 Country of ref document: RU |
|
WWP | Wipo information: published in national office |
Ref document number: 2005818164 Country of ref document: EP |