WO2002031316A2 - Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing - Google Patents

Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing Download PDF

Info

Publication number
WO2002031316A2
WO2002031316A2 PCT/HR2001/000046 HR0100046W WO0231316A2 WO 2002031316 A2 WO2002031316 A2 WO 2002031316A2 HR 0100046 W HR0100046 W HR 0100046W WO 0231316 A2 WO0231316 A2 WO 0231316A2
Authority
WO
WIPO (PCT)
Prior art keywords
elements
tunnel
assembly
concrete
arc
Prior art date
Application number
PCT/HR2001/000046
Other languages
French (fr)
Other versions
WO2002031316A3 (en
Inventor
Robert Planinc
Marko Planinc
Dubravko Tisovec
Dubravka Bjegovic
Original Assignee
Robert Planinc
Marko Planinc
Dubravko Tisovec
Dubravka Bjegovic
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Robert Planinc, Marko Planinc, Dubravko Tisovec, Dubravka Bjegovic filed Critical Robert Planinc
Priority to EP01976549A priority Critical patent/EP1325212A2/en
Priority to AU2001295817A priority patent/AU2001295817A1/en
Publication of WO2002031316A2 publication Critical patent/WO2002031316A2/en
Publication of WO2002031316A3 publication Critical patent/WO2002031316A3/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Definitions

  • This invention is related to the system for manufacturing tunnel linings by prefabricated arc- formed self-supporting hydro-insulated concrete elements, serving at the same time as a formwork for concrete filling.
  • This invention saves the working time in the tunnel, lowers the amount of jet-concrete needed for the base of hydro-insulated layer and the hydro-insulation itself, as the working phase in the tunnel is not necessary. So in the case of inclusion of a fire protection system, it shall be performed as two-layer element including outer fireproof layer.
  • the application of prefabricated arc-formed self-supporting hydro-insulated concrete elements provides the possibility for decreasing tunnels burrow profiles.
  • the invention is classified and assigned a classification symbol E21D 11/08, 11/18, 11/40.
  • the special technical problem is making of the lining, requiring the making of elements in the geometric form following the plan's curvature of the tunnel axes, since to turn a solid circular bottom between two cylinder's surfaces is impossible.
  • the bottom's surface (13), in the part which closes the lining bellow, is to be made in segments (13.1) which are interconnected by rubber joint (13.2). It enables changing of curvature radius and transforming of circular segment into ellipsoid segment, or performing of lateral sides in two parts respectively, with the possibility of interjecting triangular element. Lowering of elements' dimensions due to concrete's congregation is solved by well-known technological production process of concrete mixture with additives for ranking of concrete.
  • the working platform (1.1, 1.2, 1.3 and 1.4) consists of the central part with the opening for the site vehicles passing tlirough, and the lateral parts (2.1, 2.2). Their purpose is receiving and mounting of the lower lining elements (A and E), and receiving and launching of upper lining elements (B, C and D) on the upper circular grille (IT) with cylinders (1.2 and 1.3) for reception, longitudinal and transversal transportation of prefabricated elements (B, C and D).
  • the symmetric quality of the working platform enables reception, launching and assembling of elements on the left and right side, depending of the situation on the site, as well as assembling of tunnel lining, consisting of three elements in transversal cross-section, and all according to the same details and operations.
  • the description of assembling, the way of attachment and the insurance of stability apply to both systems presented, and supported by the description of articulated drawings.
  • wet process implies injecting concrete mortar or connection mixture respectively into openings reserved for this purpose on the connection surfaces of these elements. After solidification of injected mass the element takes-over the loading. Dry process, applied in this technical solution, requires precise production of elements in the factory, in which process grooves have to be coated by rubber of a corresponding solidity to annul production deficiencies of reinforced concrete elements.
  • a hydro-insulation of the upper surface is made with polymer-cement coating or with any good quality hydro-insulation, or to use impregnability additives in the concrete mixture to prevent penetrating of moisture from dripping water.
  • Rubber proportionally profiled to concrete form is glued on the lateral sides, whose purpose is to serve as fitting element, and especially as a hydro-insulating element.
  • the rubber is fire protected by special permanently elastic lute, which is heat- resistant up to 300°C or by fireproof seals up to 1350°C respectively, and concrete itself is fire protected by two-layers out of which the lower layer is fireproof up to 1350°C.
  • the next step is concreting of arc-bed and space between assembled arc and calotte tunnel, so that the concrete filling completely fulfil the space between tunnel calotte and assembled arc.
  • Concrete filling may be reinforced or non-reinforced, depending on the terms contained in technical documents.
  • Automatic control of working operation is solved by means of remote control of all working operations relating to reception of assembly element, to its trailing to the axes of circular assembly prefabricated automotive grid, and to its mounting into final position. Thereafter the working platform is turned out and transferred on new working position. In new working position on one launching element (2.1) it receives assembly element "E” and “lafef for receiving tube for concrete transportation on the other launching element. Then it performs concreting of interspace between calotte and mounted arc-crown made of prefabricated reinforced concrete elements and after concreting is finished "lafef is taken off. Mounting of the next arc with "E" element, which was used as ballast for smooth concreting until now, may start. Automatic quality of these working operations consists of impossibility of starting activities, which might jeopardise the security of user, and provides for secure and correct performance of activity, which is in process.
  • Figures la and lb show reception of assembly elements "E” and “D” on launching sliders (2J). From this position element "E” is lifted into vertical position and transferred to the axis of assembly grid.
  • Assembly element (E) is brought to final position by shifting and turning of launching slider ( Figures 2a and 2b). Vertical position is secured by adjustable screwed supports (3). Then, concrete formwork is made. At the same time, the lining assembly element (D) is brought to the axes of circular prefabricated grid by the sliding element (2.2). By turning the receiving arm of the slider (2.1) and by horizontal shifts of slider foot (2.2) the element (D) is brought to the launching position. It is fastened by steel line to the winches driven by hydro-motors (18) and over cylinders (1.2 and 1.3) is drawn by steel line (16) into the position onto already mounted element (E). Shifting of the elements into tunnel axes direction is done by the cylinders (1.3).
  • the element (C) is mounted to the launching slider, and by horizontal shift translation of slider (2.2) and by turning the arm (2.1) it is brought to the launching position. Then fastened by steel line (16) onto winches (18) driven by hydro-motors and over cylinders (1.2 and 1.3) it is drawn by steel line (16) into the position next to already mounted element (D) ( Figures 3a and 3b). It is fastened provisionally to the element (D), and that only when mounting the first arc, the receiving element (9) is released, and lowered to the launching ramp (2.1) to receive the element (B). The same operation is repeated for the assembly element (B).
  • the element (A) ( Figures 4a and 4b) is mounted to the launching slider, and by horizontal shift of slider (2.2) and by turning the arm (2.1) it is brought to the final position (figure 5a and 5b). It comes up to securing of vertical position by adjustable screw supports (3), importing 120 to 150 kN stress force, by necessary protection against radial movements of connecting points of assembly elements by screw anchors (4) only for the first arc. Lateral wedging in the already mounted arc retains the next arcs, and formwork for concrete as lining support is built in. After that the working platform serves as the carrier of the formwork (only for the first arc) for concreting the interspace between the prefabricated lining and tunnel calotte ( Figures 6a and 6b).
  • the working platform After making the first arc, the working platform remains in this position approximately twenty hours, until the outer concrete formwork is removed. After removing the outer concrete formwork and releasing of all supports, the working platform is lowered 90 mm and is put over the four wheels (1.5 and 1.6), two of them being driving wheels (1.5), onto the longitudinal beam (5), which is supported by vertically and horizontally adjustable beds (6). By starting the driving wheels, the working platform is shifted into the new position for assembling of the new arc, which is assembled in the same way as it is described for the first arc. Thereby the new arc is fixed by assembling - disassembling linkage (10) onto the already finished arc by means of the grooves (7) and the protrusions (8) ( Figures 7a and 7b, and Figures 8a and 8b).
  • the cross-section ( Figures 9a, 9b, 9c and 9d) show the system of connecting assembly elements in the tunnel axes direction by means of cone groove (7) and cone protrusion (8) and assembling - disassembling linkage laths (10) ensuring nestling of arcs during concreting of intersections between assembly elements and tunnel calotte.
  • the same cross-section shows the method of supporting and shifting of the working platform from one working position to another.
  • Figures 10a, 10b and 10c show the receiving element (9) with element (11) for receiving steel line and holding system (12) for receiving element onto launching slider (2.1).
  • Figures 11a and lib show three-dimensional assembly element "A" characterised by its lower part being formed for receiving hydraulic cranes and adjustable screw supports (3 and 4) for protection against vertical and horizontal shiftings.
  • the upper part is provided with the characteristic cylindrical rib for wedging the assembly element "B".
  • the lateral regions are provided with the conical grooves (7) on one side and conical protrusions (8) on the other.
  • Figures 12a and 12b show three-dimensional assembly elements "B", “C” and “D”, which are equal mutually, and which are characterised by the fact that the lower part has a cylindrical groove for connecting to assembly element "A”.
  • the upper part is provided with characteristic cylindrical rib for wedging assembly element "C”.
  • the lateral sides are designed with conical grooves (7) on one side, and conical protrusions (8) on the other.
  • Figures 13a and 13b show three-dimensional assembly element "E", which is characterised by the fact that its lower part is formed for receiving hydraulic cranes and adjustable screw supports (3 and 4) for protection against horizontal and vertical shifting.
  • the upper part is provided with characteristic cylindrical groove for wedging assembly element "D”.
  • the lateral sides are provided with conical grooves (7) on one side, and conical protrusions (8) on the other.
  • FIG. 14 shows the system of receiving assembly element "C” and the conducting system for steel line (16), which is manually put on the receiving element (11).
  • the complete assembly (9, 11, "C") is withdrawn by hydro-motor (18) over the cylinders 1.2 and 1.3 toward final position.
  • hydro-motor (18) By passing the lower receiving element (11) over the steel line (17), it is automatically hooked by special hook to the receiving element (11). In this way we have the possibility of moving the assembly element into both directions, which is important during the movement of the assembly element in the tunnel direction, for the wedging of the protrusions (8) to the grooves (7).
  • Figure 15a shows the side view of assembly element
  • Figure 15b shows the drawing of the lining
  • Figure 15c shows the plan of the lining
  • Figure 15d shows the detail of the bottom. All this is for the purpose of better presentation of the system of lower bottom (13) with the solid steel part (13.1), rubber joints (13.2), and adjustable supports (13.3).
  • the lower bottom is brought out of the perpendicular position between the outer (13.4) and inner (13.5) lining by adjustable supports, as in details of the project, so that concrete assembly element, for the part of lining in the curve, has necessary trapezium form in the plan.
  • Figure 16 shows THE SYSTEM OF TUNNEL LINING MADE OF THREE
  • Prefabricated assembly elements are transported and deposited beside the tunnel margin and the working platform.
  • the crane is lifting them to carry them above the launching ramp (2.1), on which they are fixed through receiving element (9) by means of two screws.
  • a launching ramp is pulled into the axis direction of circular working platform by endless transporting chain.
  • Assembly element "E” is mounted by launching ramp to the final position, where it is fixed by adjustable screw supports (3 and 4), and by assembling - disassembling linkages next to the previously positioned element.
  • assembly element "D” is pulled into the axis direction of circular working platform by launching ramp and by means of built in hydraulic cylinders it is brought to the trajectory for drawing it to the site.
  • tube carrier for transporting concrete to the cavity between tunnel calotte and mounted arc made of prefabricated assembly elements.
  • This facilitates and accelerates the manipulation with usually heavy concreting tube, and achieves an ideal concreting of arc, gradually both on one and another side from the heel of the crown towards the top by approx.2/3 width of mounting element, to simply embedding the concrete by vibrating.
  • tube carrier for concrete transport is taken down and the new arc assembling is going to start.
  • Jet-concrete layer thickness is depending on geo-mechanical characteristics of rock and is decreased from approx. 25 cm to approx. 5 cm, • Substitution of monolith part of tunnel lining,
  • the working platform in the manufacturing of tunnel lining made of prefabricated reinforced concrete elements, it can be used, with minor adaptations, for assembling of hall arc-constructions, bridges and inside covering assemblies and the like, in the construction of boats, aircrafts and other constructions with rounded inner surface. With minor structural changes, it can be used as a working platform for maintaining road tunnels and for reconstruction operations requiring constant traffic movement, which is very important for tunnel usage during general maintenance and reconstruction operations.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

This invention is related to the system for construction of tunnel lining by prefabricated arcformed self-supporting hydro-insulated concrete elements. Mounted arc serves as formwork for concrete filling, which may be performed in full cross-section between tunnel arc and tunnel calotte. In case of geo-mechanical reasons to separate covering from the rock, it allows the manufacture of dilatation of necessary width. Saving is related to: Decrease of working time duration for more than 70 %; decrease of jet-concrete quantity; tunnel hydro-insulation; decrease of tunnel burrow profiles. The application of these technical solutions in tunnel construction, provides for the realisation of the following technical-technological characteristics: Elements assembled as arc-unit make final waterproof tunnel lining; two-layer fireproof may be performed, it there is a need; jet-concrete thickness is minimised; fixing points for plate manipulation and mounting are used for attaching ventilation, illumination, signal and other tunnel equipmnt.

Description

TUNNEL LINING MADE OF PREFABRICATED REINFORCED CONCRETE ELEMENTS AND PROCESS FOR ITS MANUFACTURING AND INSTALLING
1. TECHNICAL FIELD TO WHICH THIS INVENTION IS RELATED
This invention is related to the system for manufacturing tunnel linings by prefabricated arc- formed self-supporting hydro-insulated concrete elements, serving at the same time as a formwork for concrete filling. This invention saves the working time in the tunnel, lowers the amount of jet-concrete needed for the base of hydro-insulated layer and the hydro-insulation itself, as the working phase in the tunnel is not necessary. So in the case of inclusion of a fire protection system, it shall be performed as two-layer element including outer fireproof layer. The application of prefabricated arc-formed self-supporting hydro-insulated concrete elements provides the possibility for decreasing tunnels burrow profiles.
According to the International Patent Classification, the invention is classified and assigned a classification symbol E21D 11/08, 11/18, 11/40.
2. TECHNICAL PROBLEM
(for which patent protection is applied for)
The technical problems to be solved by this invention of tunnel lining made of prefabricated arc-formed self-supporting hydro-insulated concrete elements, are: 1. Production of arc-formed elements in the factory,
2. Assembling of elements "under the roof,
3. Interconnection of elements,
4. Hydro-insulating layer of upper sheet and sealing of connections, including a fire protection of concrete, 5. Assembling of circular automotive working platform in the tunnel, and
6. Automation of working operations. 3. STATE OF THE ART
(presentation and analysis of well-known solutions of technical problems defined)
No system of prefabricated tunnel lining has been elaborated in our country thus far, so tunnel lining is performed monolithically by means of sliding linings. First of all, a layer of approx. 20-cm jet-concrete is made and then a hydro-insulation as sliding lining upon it. After that the monolithic tunnel lining is made, as sliding lining, whose progression is dependent on the length of the lining and the time needed for concrete solidification. To my knowledge there is a solution of prefabricated lining only for hydro-technical tunnels and completely circular profile tunnels, but it is completely different from the present invention.
4. DISCLOSURE OF THE ESSENCE OF THE INVENTION (in such a way that the technical problem and its solution may be understood as well as the indication of the technical novelty of the invention in relation to the state of the art)
4.1 Production of arc-formed concrete elements in the factory
The special technical problem is making of the lining, requiring the making of elements in the geometric form following the plan's curvature of the tunnel axes, since to turn a solid circular bottom between two cylinder's surfaces is impossible.
The solution is that the bottom's surface (13), in the part which closes the lining bellow, is to be made in segments (13.1) which are interconnected by rubber joint (13.2). It enables changing of curvature radius and transforming of circular segment into ellipsoid segment, or performing of lateral sides in two parts respectively, with the possibility of interjecting triangular element. Lowering of elements' dimensions due to concrete's congregation is solved by well-known technological production process of concrete mixture with additives for ranking of concrete.
4.2 Assembling of elements "under the roof
Assembling of 5-tons weight elements "under the roof of tunnel, provided that the free space between elements and the wall is only few millimetres, is very difficult technical problem, which we solved by the system of automotive working platform for transversal and circular drawing of elements. The working platform (1.1, 1.2, 1.3 and 1.4) consists of the central part with the opening for the site vehicles passing tlirough, and the lateral parts (2.1, 2.2). Their purpose is receiving and mounting of the lower lining elements (A and E), and receiving and launching of upper lining elements (B, C and D) on the upper circular grille (IT) with cylinders (1.2 and 1.3) for reception, longitudinal and transversal transportation of prefabricated elements (B, C and D). The symmetric quality of the working platform enables reception, launching and assembling of elements on the left and right side, depending of the situation on the site, as well as assembling of tunnel lining, consisting of three elements in transversal cross-section, and all according to the same details and operations. The description of assembling, the way of attachment and the insurance of stability apply to both systems presented, and supported by the description of articulated drawings.
4.3 Interconnection of elements
Interconnection of elements is possible in two basic ways, namely by wet and dry process. Wet process implies injecting concrete mortar or connection mixture respectively into openings reserved for this purpose on the connection surfaces of these elements. After solidification of injected mass the element takes-over the loading. Dry process, applied in this technical solution, requires precise production of elements in the factory, in which process grooves have to be coated by rubber of a corresponding solidity to annul production deficiencies of reinforced concrete elements.
4.4 Prefabricated assembly element as hydro-insulating and fire protection tunnel lining element
After binding and solidification of concrete in the factory warehouse a hydro-insulation of the upper surface is made with polymer-cement coating or with any good quality hydro-insulation, or to use impregnability additives in the concrete mixture to prevent penetrating of moisture from dripping water. Rubber proportionally profiled to concrete form is glued on the lateral sides, whose purpose is to serve as fitting element, and especially as a hydro-insulating element. The rubber is fire protected by special permanently elastic lute, which is heat- resistant up to 300°C or by fireproof seals up to 1350°C respectively, and concrete itself is fire protected by two-layers out of which the lower layer is fireproof up to 1350°C.
4.5 Prefabricated assembly element as a formwork for concrete filling between the tunnel calotte and lining
After longitudinal force is applied to the assembled arc and the arc is reclined on the adjustable screw supports, the next step is concreting of arc-bed and space between assembled arc and calotte tunnel, so that the concrete filling completely fulfil the space between tunnel calotte and assembled arc. Concrete filling may be reinforced or non-reinforced, depending on the terms contained in technical documents.
In the case of necessity, there is a possibility of separating the arc-structure and concrete filling from tunnel calotte by previously covering tunnel calotte by compressible material of the thickness predetermined by the project. Compressible material, beside the dilatation role, has the role of cover lost.
4.6 Assembling of circular automotive working platform in the tunnel
By help of car-crane, lower part of working platform (1.4) is assembled classically as a driving unit (1.4), and upper part of a circular working platform (1.1) has to be unloaded from the truck in one piece and mounted transversally to the tunnel axes alongside already mounted part. By means of hydro-motor, previously mounting assembly elements "E" and "D" on sliders, it is lifted through a console on the height of beds on the part (1.4). Thereafter it is temporary leaned on the tubular working platform, which is trailed under circular carrier, stabilised and already assembled lower part is trailed under the circular carrier by its own drive. Follows screw-joining, then temporary support of light tubular working platform is disassembled and automotive working platform is ready for use.
4.7 Automatic control of working operations
Automatic control of working operation is solved by means of remote control of all working operations relating to reception of assembly element, to its trailing to the axes of circular assembly prefabricated automotive grid, and to its mounting into final position. Thereafter the working platform is turned out and transferred on new working position. In new working position on one launching element (2.1) it receives assembly element "E" and "lafef for receiving tube for concrete transportation on the other launching element. Then it performs concreting of interspace between calotte and mounted arc-crown made of prefabricated reinforced concrete elements and after concreting is finished "lafef is taken off. Mounting of the next arc with "E" element, which was used as ballast for smooth concreting until now, may start. Automatic quality of these working operations consists of impossibility of starting activities, which might jeopardise the security of user, and provides for secure and correct performance of activity, which is in process.
5. DESCRIPTION OF FIGURES
Figures la and lb show reception of assembly elements "E" and "D" on launching sliders (2J). From this position element "E" is lifted into vertical position and transferred to the axis of assembly grid.
Assembly element (E) is brought to final position by shifting and turning of launching slider (Figures 2a and 2b). Vertical position is secured by adjustable screwed supports (3). Then, concrete formwork is made. At the same time, the lining assembly element (D) is brought to the axes of circular prefabricated grid by the sliding element (2.2). By turning the receiving arm of the slider (2.1) and by horizontal shifts of slider foot (2.2) the element (D) is brought to the launching position. It is fastened by steel line to the winches driven by hydro-motors (18) and over cylinders (1.2 and 1.3) is drawn by steel line (16) into the position onto already mounted element (E). Shifting of the elements into tunnel axes direction is done by the cylinders (1.3).
At the same time, the element (C) is mounted to the launching slider, and by horizontal shift translation of slider (2.2) and by turning the arm (2.1) it is brought to the launching position. Then fastened by steel line (16) onto winches (18) driven by hydro-motors and over cylinders (1.2 and 1.3) it is drawn by steel line (16) into the position next to already mounted element (D) (Figures 3a and 3b). It is fastened provisionally to the element (D), and that only when mounting the first arc, the receiving element (9) is released, and lowered to the launching ramp (2.1) to receive the element (B). The same operation is repeated for the assembly element (B). At the same time, the element (A) (Figures 4a and 4b) is mounted to the launching slider, and by horizontal shift of slider (2.2) and by turning the arm (2.1) it is brought to the final position (figure 5a and 5b). It comes up to securing of vertical position by adjustable screw supports (3), importing 120 to 150 kN stress force, by necessary protection against radial movements of connecting points of assembly elements by screw anchors (4) only for the first arc. Lateral wedging in the already mounted arc retains the next arcs, and formwork for concrete as lining support is built in. After that the working platform serves as the carrier of the formwork (only for the first arc) for concreting the interspace between the prefabricated lining and tunnel calotte (Figures 6a and 6b). After making the first arc, the working platform remains in this position approximately twenty hours, until the outer concrete formwork is removed. After removing the outer concrete formwork and releasing of all supports, the working platform is lowered 90 mm and is put over the four wheels (1.5 and 1.6), two of them being driving wheels (1.5), onto the longitudinal beam (5), which is supported by vertically and horizontally adjustable beds (6). By starting the driving wheels, the working platform is shifted into the new position for assembling of the new arc, which is assembled in the same way as it is described for the first arc. Thereby the new arc is fixed by assembling - disassembling linkage (10) onto the already finished arc by means of the grooves (7) and the protrusions (8) (Figures 7a and 7b, and Figures 8a and 8b).
The cross-section (Figures 9a, 9b, 9c and 9d) show the system of connecting assembly elements in the tunnel axes direction by means of cone groove (7) and cone protrusion (8) and assembling - disassembling linkage laths (10) ensuring nestling of arcs during concreting of intersections between assembly elements and tunnel calotte. The same cross-section shows the method of supporting and shifting of the working platform from one working position to another.
Figures 10a, 10b and 10c show the receiving element (9) with element (11) for receiving steel line and holding system (12) for receiving element onto launching slider (2.1).
Figures 11a and lib show three-dimensional assembly element "A" characterised by its lower part being formed for receiving hydraulic cranes and adjustable screw supports (3 and 4) for protection against vertical and horizontal shiftings. The upper part is provided with the characteristic cylindrical rib for wedging the assembly element "B". The lateral regions are provided with the conical grooves (7) on one side and conical protrusions (8) on the other. There are two plastic inserts fixed from the inside, with inner thread for fixing the receiving element (9) for manipulation and assembling. Also there are two plastic inserts with inner thread on every lateral reinforcement of assembly element, for fixing assembling - disassembling linkages (10) made for securing mutual nestling of old and new arc during concreting of interspace between the arc and tunnel calotte. After the assembling is finished, the plastic inserts serve for the suspension of the illumination, signalization, ventilation and the like, to the tunnel lining.
Figures 12a and 12b show three-dimensional assembly elements "B", "C" and "D", which are equal mutually, and which are characterised by the fact that the lower part has a cylindrical groove for connecting to assembly element "A". The upper part is provided with characteristic cylindrical rib for wedging assembly element "C". The lateral sides are designed with conical grooves (7) on one side, and conical protrusions (8) on the other. There are two plastic inserts fixed from the inside, with inner thread for fixing the receiving element (9) for manipulation and assembling. Also there are two plastic inserts with inner thread on every lateral reinforcement of assembly element, for fixing assembling — disassembling linkages (10) provided for securing mutual nestling of old and new arc during concreting of interspace between the arc and tunnel calotte. After the assembling is finished, the plastic inserts serve for suspension of the illumination, signalization, ventilation and the like, to the tunnel lining.
Figures 13a and 13b show three-dimensional assembly element "E", which is characterised by the fact that its lower part is formed for receiving hydraulic cranes and adjustable screw supports (3 and 4) for protection against horizontal and vertical shifting. The upper part is provided with characteristic cylindrical groove for wedging assembly element "D". The lateral sides are provided with conical grooves (7) on one side, and conical protrusions (8) on the other. There are two plastic inserts fixed from the inside, with inner thread for fixing the receiving element (9) for manipulation and assembling.
Also there are two plastic inserts with inner thread on every lateral reinforcement of assembly element, for assembling - disassembling linkages (10) made for securing mutual nestling of old and new arc during concreting of interspace between the tunnel arc and tunnel calotte. After the assembling is finished, the plastic inserts serve for the suspension of the illumination, signalization, ventilation and the like, to the tunnel lining. Figure 14 shows the system of receiving assembly element "C" and the conducting system for steel line (16), which is manually put on the receiving element (11). The complete assembly (9, 11, "C") is withdrawn by hydro-motor (18) over the cylinders 1.2 and 1.3 toward final position. By passing the lower receiving element (11) over the steel line (17), it is automatically hooked by special hook to the receiving element (11). In this way we have the possibility of moving the assembly element into both directions, which is important during the movement of the assembly element in the tunnel direction, for the wedging of the protrusions (8) to the grooves (7).
Figure 15a shows the side view of assembly element, Figure 15b shows the drawing of the lining, Figure 15c shows the plan of the lining, Figure 15d shows the detail of the bottom. All this is for the purpose of better presentation of the system of lower bottom (13) with the solid steel part (13.1), rubber joints (13.2), and adjustable supports (13.3). The lower bottom is brought out of the perpendicular position between the outer (13.4) and inner (13.5) lining by adjustable supports, as in details of the project, so that concrete assembly element, for the part of lining in the curve, has necessary trapezium form in the plan.
Figure 16 shows THE SYSTEM OF TUNNEL LINING MADE OF THREE
PREFABRICATED REINFORCED CONCRETE ELEMENTS shown in the cross-section.
6. DETAILED DESCRIPTION OF AT LEAST ONE WAY FOR CARRYING OUT THE INVENTION
6.1 Production of assembly elements
Production of assembly elements is advisable in closed area equipped by crane of min. 50 kN of loading force, and sufficient space for 50 moulds beneath the crane for production of prefabricated assembly elements, and space for products of three-day production also beneath the crane. Those elements are set up in such a way, that depending on the space available, it enables finishing of lateral sides for gluing rubber tape afterwards. Finishing the upper side by hydro-insulating lining is enabled in intermediate stage by transmission to the warehouse of the factory or on the platform in front of the tunnel. Trapezium formed elements in the plan necessary for carrying out of tunnel lining in the curve, are made by means of adjustable bottom section (13) with rubber joints.
6.2 Assembling of elements in roadway tunnel
Prefabricated assembly elements are transported and deposited beside the tunnel margin and the working platform. The crane is lifting them to carry them above the launching ramp (2.1), on which they are fixed through receiving element (9) by means of two screws. A launching ramp is pulled into the axis direction of circular working platform by endless transporting chain. Assembly element "E" is mounted by launching ramp to the final position, where it is fixed by adjustable screw supports (3 and 4), and by assembling - disassembling linkages next to the previously positioned element. Simultaneously, assembly element "D" is pulled into the axis direction of circular working platform by launching ramp and by means of built in hydraulic cylinders it is brought to the trajectory for drawing it to the site. In this position the upper line (16) is attached to the receiving element (9) and drawing of the element is starting. When the element passed approx. 4 m of trajectory, the lower line (17) is hooked automatically to the receiving element and concrete assembly element "D" is drawn to the final position. Here, by means of lines and cylinders (1.3), it is brought to the final position in transversal and longitudinal sense. Here, it is now attached to the previously assembled arc by assembling - disassembling linkages (10), which are fixed by screws provided with plastic anchors. After fixing the elements to the previously assembled arc, receiving element (9) is separated from assembly element "D", and by means of lines it is drawn back to the launching ramp (2.1). Disassembling of lower line from the receiving element is performed automatically, when the element "D" is passing through the position of element B". The upper line is now manually separated from the receiving element, which is then received automatically on the launching ramp, which then, with the receiving element and by means of endless chain is moved out from circular working platform to get element "C". Element "C" is brought to the place of assembling in the same way as the element "D", and is attached to already existing arc by means of assembling - disassembling linkages, and after that receiving element is released and drawn back to the launching ramp. Then, the element "B" is taken and assembled in the same way next to the element "C" and the existing arc, and it is attached to the existing arc but not with full force. It remains fixed to the upper line (16) until the launching ramp delivers the element "A", which is drawn towards the element "B" and attached by means of assembling - disassembling linkages but not with full force, next to the existing arc. By means of hydraulic cranes set to the heel of the crown and directed to the element "A", the longitudinal force of approx.120 kN is directed to the assembled arc which is thereby undertaking the loading. The heel of the crown is secured in the vertical and horizontal direction by means of adjustable screw supports (3, 4), hydraulic working platforms are taken out and the lining of the heel of the crown is assembled. Then, receiving element is released from elements "A" and "B", circular automotive working platform is taken down to the wheels and driven by its own power out from mounted arc. Then it is fixed to new operating position and has now function of tube carrier for transporting concrete to the cavity between tunnel calotte and mounted arc, made of prefabricated assembly elements. This facilitates and accelerates the manipulation with usually heavy concreting tube, and achieves an ideal concreting of arc, gradually both on one and another side from the heel of the crown towards the top by approx.2/3 width of mounting element, to simply embedding the concrete by vibrating. Immediately after concreting is finished, tube carrier for concrete transport is taken down and the new arc assembling is going to start.
7. WAY OF USING THIS INVENTION
The solution of these technical problems, include the following technical-technological characteristics which are combined in tunnel construction process:
• Elements assembled in arc unit constitute final treatment of tunnel surface, • Waterproof layer is made by hydro-insulated layer on outer surface and rubber seals on lateral surfaces,
• Hydro-insulation on the jet-concrete layer is omitted,
• Jet-concrete layer thickness is depending on geo-mechanical characteristics of rock and is decreased from approx. 25 cm to approx. 5 cm, • Substitution of monolith part of tunnel lining,
• Serves as a formwork for concrete filling,
• In the case of needed of fire-protection, in double-layer it serves as fireproof element for concrete lining protection, • Fixing points for manipulation and mounting of plates are used for ventilation fastening, runnel illumination and other tunnel signalling equipment.
It is important to notice that automotive working platform for circular mounting of prefabricated tunnel lining elements serves also for concreting cavity between tunnel arc and tunnel calotte. This is because it is provided to lead tubes for concrete transportation exactly over circular arc with the same equipment as for assembling reinforced concrete elements, i.e. concrete transporting tube is fixed onto sliding circular element "lafef with the possibility of moving the tube to the tunnel direction.
Apart from using the working platform in the manufacturing of tunnel lining made of prefabricated reinforced concrete elements, it can be used, with minor adaptations, for assembling of hall arc-constructions, bridges and inside covering assemblies and the like, in the construction of boats, aircrafts and other constructions with rounded inner surface. With minor structural changes, it can be used as a working platform for maintaining road tunnels and for reconstruction operations requiring constant traffic movement, which is very important for tunnel usage during general maintenance and reconstruction operations.

Claims

C L A I M S
Tunnel lining made of prefabricated reinforced concrete elements, of which supporting assembly elements "A" and "E" are characterised by surfaces parallel to longitudinal axis and arched in radial direction of designed tunnel lining and that:
- their upper surface is designed with decreased weight and with possibility for infixing anchors for reception of elements "A" and "E" and their connection with concrete filling between tunnel calotte and arc made of assembly elements,
- on the lower surface there is a possibility to infix fireproof layer,
- their lower side is designed to provide easy reception of hydraulic working platforms and adjustable screw supports (3, 4) to protect against vertical and horizontal movements, - the upper part is designed with characteristic cylindrical rib or groove respectively for wedging the assembly element "B" or top element "D",
- it is possible to make an assembly element in planar of trapezoidal form, by using adjustable bottom (13),
- that hydro-insulation is made on upper surface and part of lateral surfaces, - that it is at the same time a hydro-insulation element of tunnel lining, preventing water penetration through slashings between assembly elements, and that rubber cloth and serving at the same time as the compensation for minor production deficiencies of elements,
- that on lateral sides conical grooves (7) are designed on one side, and conical protrusions (8) on the other side, serving for mutual wedging of neighbouring arcs,
- that two plastic inserts are built in the lower side, having inner threads for fixing elements (9) for manipulation and assembling, which comprises elements (9), (11) and (12), and two plastic inserts with inner thread on the left and right circular reinforcement to receive elements (10) for mutual attachment of reinforced concrete assembly elements of neighbouring arcs during concreting of the interspace between tunnel calotte and the arc.
. Tunnel lining made of prefabricated strengthened concrete elements, of which lateral and top head assembly elements "B", "C" and "D" according to claim 1, are characterised by the fact that:
- surfaces are parallel to longitudinal axis arched in radius of designed tunnel lining,
- the upper surface is designed with decreased weight and with possibility for infixing the anchors for connection of elements "B", "C" and "E" concrete filling between tunnel calotte and arc made of assembly elements, - on the lower surface there is a possibility to built-in fireproof layer,
- upper and lower layer are designed with characteristic cylindrical rib or cylindrical groove for mutual wedging of assembly elements in line parallel to tunnel axis,
- it is possible to make assembly element, in planar trapezoidal form, by using adjustable bottom (13), - hydro-insulation is provided on the upper surface and part of lateral surfaces, that it is at the same time a hydro-insulation element of tunnel lining,
- lateral sides are coated with canvas rubber,
- water penetration through interspace between assembly elements is prevented, and canvas rubber serves as compensation for minor production deficiencies of elements, - that on lateral sides conical grooves (7) are designed on one side, and conical protrusions
(8) on the other side, serving for mutual wedging of neighbouring arcs,
- that two plastic inserts are built in the lower side, having inner threads for fixing elements (9) for manipulation and assembling, which comprises elements (9), (11) and (12), and two plastic inserts with inner thread on the left and right circular reinforcement to receive elements (10) for mutual attachment of reinforced concrete assembly elements of neighbouring arcs during concreting of the interspace between tunnel calotte and the arc.
3. Tunnel lining made of prefabricated reinforced concrete elements, in which receiving element is represented by positions (9), (11) and (12) for receiving assembly elements "A",
"B", "C", "D" and "E" of tunnel lining to launching slider (2.1, 2.2), characterised by the fact that by their cross-section geometrical form, and rubber supports enable drawing of assembly lining element through a slider (2.1) in a simple way, and prevent movement below and out of given trajectory, that it has special attachments (11 and 12) for trailing and braking steel line with a possibility to turn steel line around assembly element, and automatic hooking and unhooking of lower steel line.
4. Tunnel lining made of prefabricated reinforced concrete elements, in which adjustable screw support (3) and anchor (4) for protection against vertical and horizontal movement according to claims 1-3, is characterised by the fact that it has sliding rubber-steel protection on three sides, serving formwork for monolith concrete of assembled tunnel lining bed so that after solidification of the concrete adjustable screw support may be released and pulled out and be used again during the next supporting or anchoring.
5. Tunnel lining made of prefabricated reinforced concrete elements, in which adjustable bottom of circular lining (13) for producing prefabricated assembling elements of tunnel lining in planar trapezoidal form, according to claims from 1 to 4, characterised by the fact that steel parts of circular bottom (13.1) are interconnected by rubber element (13.2) allowing minimal deformations, so that circular segment is transformed into ellipsoid element, and on each rubber connection point, bottom is received by adjustable support (13.3).
6. Assembling process of prefabricated elements by use of self-automotive working platform for circular assembling of prefabricated tunnel elements, according to claims from 1 to 5, characterised by the fact that it receives prefabricated concrete element by elements (2.1) and (2.2) in free tunnel space next in front of it, and by rotation and longitudinal drawing brings it to the axis of circular support (1.1) and to final position in case of elements "A" and "E", and in the position to launch it to the circular assembling, if it is the case of elements "B", "C" and "D", and elements from the launching part (2.1 and 2.2) through circular trajectory determined by the position of cylinders (1.2 and 1.3), and by means of winch driven by hydro-motor (18), brings to the position from which, by moving in longitudinal direction of tunnel by means of cylinders (1.3) are brought to designed final position, and releasing and moving from finished segment to new working position is performed self-automotively on metal track (5), which is put on vertically and horizontally self-adjustable beds (6), and after bringing the working platform to new working position, it lifts and transfers a steel track to new position for new movement with the possibility for simultaneous working operations for concreting space between tunnel-calotte and arc.
7. Control procedure of inter-depending working operations for circular assembling of prefabricated elements by use of self-automotive working platform, according to claims 1 to 6, characterised by the fact, that:
- all working operations are remote controlled and automated in a way to disable the start of one operation, if the conditions are not met for the security of people and operations already in process,
- it sets to motion and stops the working platform safely and without dynamic strokes - it enables setting to motion, driving and stopping of launching slider without dynamic strokes no matter is it loaded or empty, providing precise delivering of elements to the site
8. Tunnel lining made of prefabricated reinforced concrete elements, its production and assembly process, according to claims 1 to 7, characterised by the fact that it is used for concreting of cavity between arc and tunnel-calotte, because it provides for conduction of tube for concrete transportation, exactly to circular arc, with the same equipment as for assembling the reinforced concrete elements, i.e. the tube for concrete transportation is mounted to circular sliding element ("lafef) with the possibility to move the tube to tumiel direction.
9. Tunnel lining made of prefabricated reinforced concrete elements, its production and assembly process, according to claims 1 to 8, characterised by the fact that it is used, with minor adaptations, for mounting arc-designed constructions of halls, bridges and inner installation coverings etc., for construction of ships, airplains and other areas with rounded inner surfaces
10. Tunnel lining made of prefabricated reinforced concrete elements, its production and assembly process, according to claims 1 to 9, characterised by the fact that it is used as working platform for road-tunnel maintenance and for reparations without stopping the traffic, which is of great importance for tunnel usage and for regular maintenance and reparations.
PCT/HR2001/000046 2000-10-10 2001-10-09 Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing WO2002031316A2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
EP01976549A EP1325212A2 (en) 2000-10-10 2001-10-09 Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing
AU2001295817A AU2001295817A1 (en) 2000-10-10 2001-10-09 Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
HR20000671A HRP20000671A2 (en) 2000-10-10 2000-10-10 Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing
HRP20000671A 2000-10-10

Publications (2)

Publication Number Publication Date
WO2002031316A2 true WO2002031316A2 (en) 2002-04-18
WO2002031316A3 WO2002031316A3 (en) 2002-07-25

Family

ID=10947180

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/HR2001/000046 WO2002031316A2 (en) 2000-10-10 2001-10-09 Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing

Country Status (4)

Country Link
EP (1) EP1325212A2 (en)
AU (1) AU2001295817A1 (en)
HR (1) HRP20000671A2 (en)
WO (1) WO2002031316A2 (en)

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006134408A2 (en) * 2005-06-13 2006-12-21 Robert Planinc Assembly system for prefabricated secondary tunnel lining
FR2900922A1 (en) * 2006-05-11 2007-11-16 Eiffage Tp Soc Par Actions Sim Utilization of fiber added high performance concrete for production or protection of structural elements resistant to extreme temperature conditions
ITRM20080650A1 (en) * 2008-12-04 2010-06-05 Giampaolo Capaldini MODULAR FINISH FOR TUNNELS.
CN102135001A (en) * 2011-03-25 2011-07-27 中铁三局集团有限公司 Device for paving tunnel waterproof boards
CN102477866A (en) * 2010-11-25 2012-05-30 中铁十八局集团有限公司 Formworking jumbo with favorable ventilation performance
CN102606169A (en) * 2012-03-16 2012-07-25 铁道部工程管理中心 Tunnel support method, tunnel support structure and tunnel
US20120233934A1 (en) * 2011-03-15 2012-09-20 James Joseph Drew Formwork for use in the construction of arched structures and a method of constructing arched structures
CN103790599A (en) * 2014-02-24 2014-05-14 甘肃省交通科学研究院有限公司 End die plate of tunnel secondary lining trolley
CN104500102A (en) * 2014-12-26 2015-04-08 山东铁鹰建设工程有限公司 Retractable tunnel lining trolley and rapid movement method thereof
CN105626099A (en) * 2015-12-14 2016-06-01 黄高飞 Tunnel ditch cable trough maintenance trolley
CN106522997A (en) * 2016-11-24 2017-03-22 中铁十四局集团第五工程有限公司 Construction trolley for lagging jack in tunnel and underground construction and construction method
CN106979023A (en) * 2017-05-22 2017-07-25 中铁二局集团有限公司 The adjustable concrete end mould of Tunnel Second Lining width and its adjusting method
CN107975380A (en) * 2017-09-19 2018-05-01 中铁隧道集团二处有限公司 Lining trolley and built-in fitting casting method
CN108516864A (en) * 2018-03-09 2018-09-11 刘占明 A kind of watering curing means for constructing tunnel lining concrete
CN108729937A (en) * 2018-05-23 2018-11-02 向开秀 A kind of constructing tunnel suspension device
CN109296387A (en) * 2018-12-03 2019-02-01 湖南五新隧道智能装备股份有限公司 A kind of trolley top module system
CN109403224A (en) * 2018-11-20 2019-03-01 德州市公路工程总公司 Slab culvert casting top slab truss-like sliding formwork system and construction method
CN109538268A (en) * 2018-11-15 2019-03-29 河南工程学院 What a kind of mine laneway expanded when repairing interim moves suspension device
CN109538247A (en) * 2018-12-28 2019-03-29 江苏建筑职业技术学院 It is a kind of for building the concrete filled steel tube arch of gallery supporting
CN110005452A (en) * 2019-04-29 2019-07-12 中交路桥建设有限公司 A kind of base tunnel supporting arch quick-mount system and installation method
CN111364741A (en) * 2020-04-01 2020-07-03 中交第三航务工程局有限公司南京分公司 Construction process for integrally moving disc buckle type full-hall support
CN111379575A (en) * 2020-05-11 2020-07-07 温州安荷桥科技有限公司 Tunnel lining trolley
CN111441822A (en) * 2020-03-24 2020-07-24 中铁第六勘察设计院集团有限公司 Underwater mining method tunnel reasonable buried depth calculation method
CN112554233A (en) * 2020-12-12 2021-03-26 中国建筑第四工程局有限公司 Truss type formwork and method for efficiently installing and transferring annular opening of oversized wall
CN113006827A (en) * 2021-02-23 2021-06-22 中铁十九局集团第三工程有限公司 Rigid locking foot supporting structure for steel frame of soft rock tunnel
CN113047607A (en) * 2021-03-25 2021-06-29 江西志特新材料股份有限公司 Automatic adjustable and walking formwork system and operation method thereof
CN113417668A (en) * 2021-07-29 2021-09-21 中铁隧道集团一处有限公司 Pouring construction method for high cantilever tunnel side wall
CN116927831A (en) * 2023-09-14 2023-10-24 湖南省通盛工程有限公司 Tunnel arch protection integral dismounting equipment and construction method

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334771A (en) * 2013-07-09 2013-10-02 中铁十四局集团有限公司 Concrete pouring method of side wall and joint of middle plate and vault by means of underground excavation reverse construction method
CN104963701A (en) * 2015-07-20 2015-10-07 舟山市智海技术开发有限公司 Tunnel construction lining quantity confirming device and construction method thereof
CN104963702A (en) * 2015-07-20 2015-10-07 舟山市智海技术开发有限公司 Tunnel construction lining quantity confirming device and construction method thereof
CN104989427A (en) * 2015-07-20 2015-10-21 舟山市智海技术开发有限公司 Tunnel construction lining amount determination device and construction method thereof
CN105569692A (en) * 2016-01-29 2016-05-11 黄高飞 Trolley for welding tunnel waterproof board hanging cloth

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB711282A (en) * 1951-04-24 1954-06-30 W & J R Watson Ltd Improvements in or relating to shuttering for casting concrete
FR1495470A (en) * 1966-05-27 1967-09-22 Formwork for sewer galleries and similar structures
DE3044077A1 (en) * 1980-11-24 1982-06-03 Hochtief Ag Vorm. Gebr. Helfmann, 4300 Essen Tunnel concrete tube membrane tubbing segments - have fibres in concrete forming felt hinges under asymmetrical rock pressure deformation
GB2251203A (en) * 1990-11-21 1992-07-01 Tuyaux Bonna Procedure for fabrication of prefabricated voussoirs
FR2707337A1 (en) * 1993-02-04 1995-01-13 Courtois Jean Marie Device for fitting a half vaulting arch and method for constructing a vaulting arch
FR2756312A1 (en) * 1996-11-28 1998-05-29 Parra Robert Tunnel coffering system, especially for roadway or railway tunnels

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0745799B2 (en) * 1990-02-07 1995-05-17 日本サミコン株式会社 Method and apparatus for installing precast plate for tunnel
JP3659713B2 (en) * 1995-10-31 2005-06-15 石川島播磨重工業株式会社 Segment automatic assembly equipment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB711282A (en) * 1951-04-24 1954-06-30 W & J R Watson Ltd Improvements in or relating to shuttering for casting concrete
FR1495470A (en) * 1966-05-27 1967-09-22 Formwork for sewer galleries and similar structures
DE3044077A1 (en) * 1980-11-24 1982-06-03 Hochtief Ag Vorm. Gebr. Helfmann, 4300 Essen Tunnel concrete tube membrane tubbing segments - have fibres in concrete forming felt hinges under asymmetrical rock pressure deformation
GB2251203A (en) * 1990-11-21 1992-07-01 Tuyaux Bonna Procedure for fabrication of prefabricated voussoirs
FR2707337A1 (en) * 1993-02-04 1995-01-13 Courtois Jean Marie Device for fitting a half vaulting arch and method for constructing a vaulting arch
FR2756312A1 (en) * 1996-11-28 1998-05-29 Parra Robert Tunnel coffering system, especially for roadway or railway tunnels

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 016, no. 010 (M-1199), 13 January 1992 (1992-01-13) & JP 03 233098 A (NIPPON SAMIKON KK), 17 October 1991 (1991-10-17) *
PATENT ABSTRACTS OF JAPAN vol. 1997, no. 09, 30 September 1997 (1997-09-30) & JP 09 125892 A (ISHIKAWAJIMA HARIMA HEAVY IND CO LTD;OKUMURA CORP; OKUMURA MACH CORP), 13 May 1997 (1997-05-13) *

Cited By (37)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006134408A3 (en) * 2005-06-13 2007-02-22 Robert Planinc Assembly system for prefabricated secondary tunnel lining
WO2006134408A2 (en) * 2005-06-13 2006-12-21 Robert Planinc Assembly system for prefabricated secondary tunnel lining
FR2900922A1 (en) * 2006-05-11 2007-11-16 Eiffage Tp Soc Par Actions Sim Utilization of fiber added high performance concrete for production or protection of structural elements resistant to extreme temperature conditions
ITRM20080650A1 (en) * 2008-12-04 2010-06-05 Giampaolo Capaldini MODULAR FINISH FOR TUNNELS.
WO2010064193A1 (en) 2008-12-04 2010-06-10 Giampaolo Capaldini Modular lining for tunnels
CN102477866A (en) * 2010-11-25 2012-05-30 中铁十八局集团有限公司 Formworking jumbo with favorable ventilation performance
US20120233934A1 (en) * 2011-03-15 2012-09-20 James Joseph Drew Formwork for use in the construction of arched structures and a method of constructing arched structures
US9481993B2 (en) * 2011-03-15 2016-11-01 Lock-Block Ltd. Formwork for use in the construction of arched structures and a method of constructing arched structures
CN102135001A (en) * 2011-03-25 2011-07-27 中铁三局集团有限公司 Device for paving tunnel waterproof boards
CN102606169A (en) * 2012-03-16 2012-07-25 铁道部工程管理中心 Tunnel support method, tunnel support structure and tunnel
CN103790599A (en) * 2014-02-24 2014-05-14 甘肃省交通科学研究院有限公司 End die plate of tunnel secondary lining trolley
CN103790599B (en) * 2014-02-24 2016-06-15 甘肃省交通科学研究院有限公司 Tunnel Second Lining chassis end head formwork
CN104500102A (en) * 2014-12-26 2015-04-08 山东铁鹰建设工程有限公司 Retractable tunnel lining trolley and rapid movement method thereof
CN105626099A (en) * 2015-12-14 2016-06-01 黄高飞 Tunnel ditch cable trough maintenance trolley
CN106522997A (en) * 2016-11-24 2017-03-22 中铁十四局集团第五工程有限公司 Construction trolley for lagging jack in tunnel and underground construction and construction method
CN106979023A (en) * 2017-05-22 2017-07-25 中铁二局集团有限公司 The adjustable concrete end mould of Tunnel Second Lining width and its adjusting method
CN107975380B (en) * 2017-09-19 2023-08-29 中铁隧道集团二处有限公司 Lining trolley and embedded part pouring method
CN107975380A (en) * 2017-09-19 2018-05-01 中铁隧道集团二处有限公司 Lining trolley and built-in fitting casting method
CN108516864A (en) * 2018-03-09 2018-09-11 刘占明 A kind of watering curing means for constructing tunnel lining concrete
CN108729937A (en) * 2018-05-23 2018-11-02 向开秀 A kind of constructing tunnel suspension device
CN109538268A (en) * 2018-11-15 2019-03-29 河南工程学院 What a kind of mine laneway expanded when repairing interim moves suspension device
CN109403224A (en) * 2018-11-20 2019-03-01 德州市公路工程总公司 Slab culvert casting top slab truss-like sliding formwork system and construction method
CN109296387A (en) * 2018-12-03 2019-02-01 湖南五新隧道智能装备股份有限公司 A kind of trolley top module system
CN109538247A (en) * 2018-12-28 2019-03-29 江苏建筑职业技术学院 It is a kind of for building the concrete filled steel tube arch of gallery supporting
CN109538247B (en) * 2018-12-28 2024-04-05 江苏建筑职业技术学院 Steel tube concrete arch frame for supporting building corridor
CN110005452A (en) * 2019-04-29 2019-07-12 中交路桥建设有限公司 A kind of base tunnel supporting arch quick-mount system and installation method
CN110005452B (en) * 2019-04-29 2024-02-06 中交路桥建设有限公司 Quick installation system and installation method for pilot tunnel supporting arch centering
CN111441822A (en) * 2020-03-24 2020-07-24 中铁第六勘察设计院集团有限公司 Underwater mining method tunnel reasonable buried depth calculation method
CN111364741A (en) * 2020-04-01 2020-07-03 中交第三航务工程局有限公司南京分公司 Construction process for integrally moving disc buckle type full-hall support
CN111379575A (en) * 2020-05-11 2020-07-07 温州安荷桥科技有限公司 Tunnel lining trolley
CN112554233A (en) * 2020-12-12 2021-03-26 中国建筑第四工程局有限公司 Truss type formwork and method for efficiently installing and transferring annular opening of oversized wall
CN113006827A (en) * 2021-02-23 2021-06-22 中铁十九局集团第三工程有限公司 Rigid locking foot supporting structure for steel frame of soft rock tunnel
CN113047607A (en) * 2021-03-25 2021-06-29 江西志特新材料股份有限公司 Automatic adjustable and walking formwork system and operation method thereof
CN113417668B (en) * 2021-07-29 2023-12-15 中铁隧道集团一处有限公司 Pouring construction method of high cantilever tunnel side wall
CN113417668A (en) * 2021-07-29 2021-09-21 中铁隧道集团一处有限公司 Pouring construction method for high cantilever tunnel side wall
CN116927831A (en) * 2023-09-14 2023-10-24 湖南省通盛工程有限公司 Tunnel arch protection integral dismounting equipment and construction method
CN116927831B (en) * 2023-09-14 2023-12-19 湖南省通盛工程有限公司 Tunnel arch protection integral dismounting equipment and construction method

Also Published As

Publication number Publication date
WO2002031316A3 (en) 2002-07-25
AU2001295817A1 (en) 2002-04-22
HRP20000671A2 (en) 2002-04-30
EP1325212A2 (en) 2003-07-09

Similar Documents

Publication Publication Date Title
EP1325212A2 (en) Tunnel lining made of prefabricated reinforced concrete elements and process for its manufacturing and installing
US20150125215A1 (en) Method for constructing a tunnel course, and structural element for use by the method
EP0363411B1 (en) Bridge deck
US4982538A (en) Concrete panels, concrete decks, parts thereof, and apparatus and methods for their fabrication and use
CN113167072B (en) Building site equipment with climbing form and elevator system
PL190117B1 (en) Modular set of components for construction of railway station platforms
JPH0721209B2 (en) Stadium roof construction method and roof structure
US5218795A (en) Concrete panels, concrete decks, parts thereof, and apparatus and methods for their fabrication and use
CN208280965U (en) Coal mine deep well tunnel smooth surface concrete spraying support structure
CN109537469A (en) Prefabricated box girder cast-in-situ flange supporting formwork and construction method thereof
NO130598B (en)
AU2010214742B2 (en) Expansion joints
WO2006134408A2 (en) Assembly system for prefabricated secondary tunnel lining
CN210256640U (en) Dry dock sequence method full-section integral prefabricated immersed tube template system
CN107100649B (en) Construction process for inclined shaft concrete pouring
CN110184957B (en) Construction method of shed tunnel and steel corrugated plate combined type wind and snow prevention system
RU2296830C1 (en) Method and device for ballastless track construction
LU502559B1 (en) Method for Reconstruction of Existing Single-column Canopy
CN114319145B (en) Bridge erection method using bridge girder erection machine
CN217325000U (en) Middle support bracket system of bridge girder erection machine
KR102411779B1 (en) Embankment reinforcement unit and mettress jig unit for reinforcing embankment and embankment reinforcement method
CN216663850U (en) Pier reinforced structure
CN105863130A (en) External wall panel mounting joint
CN211735121U (en) Concrete bridge deck pavement replacement and repair structure
CN221072313U (en) Beam bracket adapting to different spans

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A2

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ PL PT RO RU SD SE SG SI SK SL TJ TM TR TT TZ UA UG US UZ VN YU ZA ZW

AL Designated countries for regional patents

Kind code of ref document: A2

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
WWE Wipo information: entry into national phase

Ref document number: 2001976549

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 2001976549

Country of ref document: EP

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

NENP Non-entry into the national phase in:

Ref country code: JP

WWW Wipo information: withdrawn in national office

Ref document number: 2001976549

Country of ref document: EP