WO1999019583A1 PCT/FI1998/000798 FI9800798W WO9919583A1 WO 1999019583 A1 WO1999019583 A1 WO 1999019583A1 FI 9800798 W FI9800798 W FI 9800798W WO 9919583 A1 WO9919583 A1 WO 9919583A1
Authority
WO
WIPO (PCT)
Prior art keywords
lifting device
work station
installer
lightweight prefabricated
lightweight
Prior art date
Application number
PCT/FI1998/000798
Other languages
English (en)
Inventor
Jukka Inkeroinen
Original Assignee
Jukka Inkeroinen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jukka Inkeroinen filed Critical Jukka Inkeroinen
Priority to AT98947587T priority Critical patent/ATE299980T1/de
Priority to EP98947587A priority patent/EP1023510B1/fr
Priority to AU94447/98A priority patent/AU9444798A/en
Priority to DE69830915T priority patent/DE69830915D1/de
Publication of WO1999019583A1 publication Critical patent/WO1999019583A1/fr

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F9/00Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes
    • B66F9/06Devices for lifting or lowering bulky or heavy goods for loading or unloading purposes movable, with their loads, on wheels or the like, e.g. fork-lift trucks
    • B66F9/075Constructional features or details
    • B66F9/12Platforms; Forks; Other load supporting or gripping members
    • B66F9/127Working platforms
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for
    • B66F11/04Lifting devices specially adapted for particular uses not otherwise provided for for movable platforms or cabins, e.g. on vehicles, permitting workmen to place themselves in any desired position for carrying out required operations
    • B66F11/044Working platforms suspended from booms
    • B66F11/046Working platforms suspended from booms of the telescoping type
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1805Ceiling panel lifting devices
    • E04F21/1816Ceiling panel lifting devices fluid pressure-operated

Definitions

  • the object of the invention is a lifting device for installing lightweight prefabricated elements in place at an installation site, which is, for example, a wall, ceiling or the like of a building, the said lifting device comprising an intermediate storage for the lightweight prefabricated elements connected with the lifting device, and a lifting unit provided with at least one gripping means for transferring the lightweight prefabricated elements from t e intermediate storage to the installation site.
  • the elements may vary from heavy load- bearing elements to light wall surface elements or insulation elements. Lifting and transferring heavy elements into place usually requires that the elements have, for example, lifting rings from which they can be suspended on the hook of a crane.
  • Lightweight prefabricated elements on the other hand, can be lifted, for example, by gripping the element's plane surface by means of suction pads. Alternatively, a lightweight prefabricated element can also be lifted by gripping the groove formed on the edge of a tongued and grooved lightweight prefabricated element, or other corresponding groove.
  • the lightweight prefabricated elements commonly used in buildings are the type of wall elements which consist of insulating wool in the middle and thin metal sheets on either side.
  • the surface of the element is so smooth that it can easily be gripped with a suction pad lifter.
  • Lightweight prefabricated elements comprised of insulating wool and metal sheets can, however, also be lifted by means of a lifting device that grips the groove of the tongue and groove seam. This is possible because the metal sheet on the surface of the element is folded over the edge of the element so that it forms a tongue and groove seam on the edge of the lightweight prefabricated element. When the element is lifted, the gripping means is guided into the groove, which it grips.
  • the suction pad lifter can also be used for installing other plane elements used in buildings, such as window elements, window panes, stone finished elements, etc.
  • plane elements used in buildings such as window elements, window panes, stone finished elements, etc.
  • the aim of the present invention is to achieve a lifting device which will further improve the efficiency of installation of lightweight prefabricated elements.
  • known lifting devices there is the problem that although the elements can be conveyed to the installation site, their securing is still difficult.
  • the device relating to the invention It is characteristic of the device relating to the invention that at least one work station is incorporated in the lifting device provided with an intermediate storage, for the installer installing the lightweight element in place.
  • the work station may be a platform or, for example, a hoisting cage.
  • the installer's work station is primarily movable to the vicinity of the installation site of the lightweight prefabricated element. It may, however, be so mobile that it will move a person as required to the intermediate storage unit or even lift a person from the ground to the desired place.
  • the installation device relating to the invention the installation of elements is made substantially more efficient. This is because the device can move one or more installers continuously to the installation site or sites as required. It is also an excellent advantage of the invention that no separate personnel hoists are needed in addition to the device for lifting the lightweight prefabricated element. Work site conditions are indeed often so limited in space that there is no room for several different lifters.
  • Figure 1 shows the lifting device relating to the invention as seen diagonally from the side.
  • Figure 2 shows the lifting device as seen from above.
  • Figure 3 corresponds to Figure 2 and shows the lifting device in another situation.
  • Figure 4 shows the lifting device as seen from the side.
  • Figure 5 shows the lifting device as seen from the side, from another direction.
  • Figure 6 corresponds to Figure 5 and shows the hoisting cages of the lifting device's work stations in another position.
  • Figure 7 corresponds to Figure 1 and shows a second embodiment of the lifting device.
  • Figure 8 corresponds to Figure 1 and shows a third embodiment of the lifting device
  • Figure 9 shows the lifting device of Figure 8 when connected to a crane
  • Figure 10 shows a lifting device suspended on the boom of a crane, as seen from the side.
  • Figure 1 1 shows a lifting device attached to a scissor lift, as seen from the side
  • Figure 12 shows the lifting device of Figure 11 when attached to a forklift truck
  • Figure 13 shows the lifting device when connected to a forklift truck, as seen from the side.
  • Figure 14 shows a fourth embodiment of the invention, as seen from the side,
  • Figure 15 shows the lifting device of Figure 14 when connected to a forklift truck
  • Figure 16 shows the installer's work station unit as seen diagonally from the side
  • Figure 17 corresponds to Figure 16 and shows the work station unit in another position.
  • Figure 18 shows a lifting device attached to a crane boom, as seen from the side
  • Figure 19 shows an embodiment of the lifting device, as seen from the side
  • Figure 20 shows the lifting device when attached to a crane boom, with the device on the ground.
  • Figure 21 shows the lifting device when attached to a crane boom, with the device lifted to installation height, as seen from the side.
  • Figure 22 shows a work station and the feeder device of a work machine, as seen from the side.
  • Figure 23 corresponds to Figure 22 and shows the feeder device in a different position
  • Figure 24 shows the lifting device and the installation of the lightweight prefabricated element in place, as seen from above.
  • Figure 25 corresponds to Figure 24 and shows the next stage in the installation of the lightweight prefabricated element.
  • Figure 1 shows the lifting device 20 relating to the invention for lifting and installing lightweight prefabricated elements in place.
  • the lightweight prefabricated elements 21 are placed on top of each other in the intermediate storage 37 incorporated in the lifting device 20, from which they can be lifted one by one and transferred to the installation site, such as the wall or ceiling of a building.
  • the lifting unit 22 of the lifting device 20 is provided with suction pads 23, which grip the lightweight prefabricated element to be lifted, then transferring it into place.
  • the figure shows that at the moment depicted in the picture, lightweight prefabricated element 21c is being installed on top of the elements 21a and 21b, which are installed on the wall of a building.
  • the frame 24 of the lifting device 20 incorporates supporting legs 64a and 64b, which are lowered down onto the ground when the installers' work stations 26a and 26b are moved further to the sides.
  • the frame of the lifting device 20 furthermore incorporates a telescopic extension part 65, which is used to stabilise the lifting device when the weight of the element 21 to be installed increases.
  • the extension part 65 can also be used, for example, for moving the stairs, as shown in Figure 8.
  • the work stations are personnel hoisting cages 26a and 26b located at the ends of the booms 25a and 25b fixed to the frame 24 of the lifting device 20.
  • the booms 25a and 25b incorporate hydraulic cylinders 27a and 27b, by means of which the position of the hoisting cages can be changed both horizontally and vertically.
  • the personnel hoisting cages 26 can be moved to almost any point to which the booms 25a and 25b reach.
  • the hoisting cages 26 can be moved to the vicinity of the lightweight prefabricated element 21c to be installed, but they may also be lowered or lifted so that the person installing the elements may step into the hoisting cage 26 on the ground and be lifted by the hoisting cage to the desired installation site.
  • Figure 2 shows the lifting device 20 in a situation where the lifting unit 22 is about to grip the topmost lightweight prefabricated element 21 in the intermediate storage of the lifting device 20 by means of the suction pads 23.
  • the personnel hoisting cages 26a and 26b acting as the installer's work stations, are located on the sides of the lifting device so that the installation personnel in them are easily able to secure the lightweight prefabricated element 21c installed on the wall.
  • the vertical pillars 28a and 28b of the wall construction are located in the vicinity of the hoisting cages 26a and 26b, which means that both ends of the lightweight prefabricated element 21c are easily secured to the vertical pillars 28a and 28b, for example by means of screws.
  • FIG 3 shows a situation corresponding to Figure 2, where the lifting device 20 is in the vicinity of the interior corner of a building. It can be seen from the figure that in such a case the personnel hoisting cage 26a can be moved closer to the frame 24 of the lifting device 20. Thus the lifting device 20 is able to move all the way to the corner of the building. If the hoisting cage 26 is suspended by means of the boom 25 shown in Figure 1 , the hoisting cage can easily be moved laterally either into the corner, to the vicinity of the pillar 28a, or away from it.
  • FIG 4 shows a situation where the personnel hoisting cage 26a of one of the work stations has been moved, by means of the boom 25a, momentarily away from the vicinity of the lightweight prefabricated element 21c being installed. This situation corresponds to that shown in Figure 3, where the lifting device 20 is required to come close to the interior corner of the building.
  • the other personnel hoisting cage 26b of the lifting device 20 has been moved to the level of the floor 29.
  • the person installing the elements is able to step into the hoisting cage 26b, which can then be lifted to the desired position in the vicinity of the lightweight prefabricated element 21c being installed.
  • the personnel hoisting cages 26 positioned for installation will also act as hoists for lifting personnel from the ground to the installation site.
  • the other hoisting cage 26a is depicted in a position suitable for the installer to secure the lightweight prefabricated element 21c to be installed.
  • Figure 6 shows that the work stations, that is, personnel hoisting cages 26a and 26b of the lifting device 20 are close to both ends of the lightweight prefabricated element 21c to be installed when lifted up. This means that the installers in the hoisting cages are in a suitable position for securing the lightweight prefabricated element 21c at both ends to the frame of the building, for example by means of screws.
  • Figure 7 shows a second embodiment of the invention, where only one boom 25 has been installed on the frame 24 of the lifting device 20, and at the end of the said boom there is only one work station.
  • This type of structure is advantageous in cases where the lightweight prefabricated elements 21 are installed vertically in a space where the elements do not have to be installed on top of each other.
  • the installer in the personnel hoisting cage 26 secures the top ends of the lightweight prefabricated elements 21c, and the other installer on the ground secures the bottom ends of the lightweight prefabricated elements 21c.
  • FIG 8 shows a third embodiment of the invention, where the lifting device 20 incorporates stairs 30, along which the installer can climb to the landing 31 connected to the boom 25 and move on from there to the work station 26.
  • the lifting device 20 is suspended at the end of the boom of a boom crane or the like.
  • the boom crane itself is not shown in the figure, only its mounting unit 32.
  • FIG 10 shows an embodiment in which the type of lifting device 20 which has no wheels supported on the ground is mounted on the boom 33 of a boom crane.
  • the hoisting cage 26a of the first work station is incorporated in the top part of the frame 24 of the lifting device 20 as shown in Figure 1.
  • the personnel hoisting cage 26b of the second work station is incorporated in the bottom part of the frame 24 of the lifting device 20 so that the bottom ends of the lightweight prefabricated elements to be installed vertically can be secured by means of this hoisting cage 26b.
  • FIG 11 shows the lifting device 20 relating to the invention mounted on a scissor lift 34 provided with wheels.
  • a work station that is, a personnel hoisting cage 26 relating to the invention is also incorporated in the lifting device 20.
  • the figure shows that the installer 35 is about to secure the lightweight prefabricated element 21c to the vertical pillar 28 of the frame of the building.
  • the lifting device 20 is provided with the type of lifting unit 22, which comprises a gripping means 36 that lifts the lightweight prefabricated element 21 by the groove of a tongue and groove seam. This is why in this embodiment the lightweight prefabricated elements 21 in the intermediate storage 37 of the lifting device 20 are in a vertical position adjacent to each other.
  • Figure 12 shows the lifting device 20 shown in Figure 11 , when positioned in the fork of a forklift truck 38.
  • the lifting device 20 with its work station personnel hoisting cage 26 corresponds to the lifting device 20 shown in Figure 11.
  • the lifting device 20 is positioned in the fork of a forklift truck 38, where the lifting device 20 can be lifted to the desired height.
  • the hoisting cage 26 of the installer's 35 work station will then also move to the suitable height for installation.
  • the lifting unit 22 is provided with a gripping means 36 which lifts the lightweight prefabricated element 21 by the groove.
  • the lightweight prefabricated elements 21 located in the intermediate storage 37 of the lifting device 20 are in a horizontal position on top of each other and lean on the vertical frame 24 of the lifting device 20.
  • the gripping means 36 of the lifting unit 22 may press the lightweight prefabricated element against the vertical frame 24 of the lifting device 20 when it grips the topmost lightweight prefabricated element 31.
  • the advantage of this arrangement is that at the stage when the gripping means 36 grips the groove of the lightweight prefabricated element 21 , the lightweight prefabricated element 21 cannot slip and will thus stay in place making it easier to grip the groove.
  • Figure 14 shows a lifting device 20 comprising wheels for moving on the ground.
  • the hydraulic system of the device is operated by an electric motor, which is powered by a cable 39.
  • the installer's 35 work station in this embodiment is a personnel hoisting cage 26 mounted on a hydraulic cylinder 40, which hoisting cage can be lifted to the desired height by means of the hydraulic cylinder.
  • Figure 15 shows a lifting device 20 similar to that shown in Figure 14, but which is, however, mounted on the fork of a forklift truck 38 in this embodiment.
  • the lifting device 20 can thus be lifted to the desired height by means of the forklift truck 38.
  • the personnel hoisting cage 26 mounted on the hydraulic cylinder 40 is also provided with stairs 30.
  • Figure 16 shows an embodiment in which the personnel hoisting cages 26a and 26b of the work stations are connected to the same boom 25, thus forming a separate work station unit 41.
  • This unit can be incorporated, for example, into known lifting devices as an accessory.
  • the mobility of the hoisting cages 26 is not as versatile as in the solution shown in Figure 1 , but it is nevertheless advantageous when a simple accessory solution is required.
  • the work station hoisting cage unit 41 shown in Figure 16 can be incorporated, by means of connecting projections 61 , for example, into the lifting devices 20 shown in Figures 14 and 15 or 20 and 21.
  • the work station unit 41 can be connected to the lifting device 20 by means of the connecting projections 61 for example to a lifting device mounted on the spikes of a forklift truck.
  • This accessory may, however, equally well be mounted on a lifting device mounted on the hook of a crane.
  • the work stations 26 of the work station unit 41 can be moved manually by means of telescopic tubes 63. These may, however, be replaced for example, by hydraulic cylinders.
  • Figure 17 shows the work station unit 41 shown in Figure 16 in another position, where the telescopic tubes 63 are turned around the joints 62 into a vertical position. The distance between the work stations 26 can then be adjusted by means of the telescopic tubes 62.
  • Figure 18 shows a lifting device 20 which is suspended, for example, on the boom of a crane by means of a mounting unit 32. During installation, this mounting unit 32 is locked so as to be rigid, in such a way that the lifting device 20 will not be able to move with respect to the top end of the crane boom. In this way it is ensured that the lifting device 20 remains firmly in place when the lightweight prefabricated element 21c is being secured to the vertical pillar 28 of the frame of the building.
  • the mounting unit 32 can, however, be released to enable the lifting device 20 to turn by means of the joint 42.
  • the lifting device 20 may be allowed to tilt, for example, when the crane boom performs a wide movement in lifting the lifting device 20 off the ground to installation height.
  • the joint 42 is, however, again locked so as to be immobile.
  • Figure 19 shows diagrammatically a lifting device 20, the work station hoisting cage 26 of which is provided with a roof 43 or safety bar, which protects the installer 35 from any objects falling from above.
  • Figure 20 shows a lifting device 20 which is mounted on the boom 33 of a crane 44. Between the boom 33 and the lifting device 20 is a mounting unit 32 which is locked so as to be immobile at the installation stage.
  • the work stations, that is, personnel hoisting cages 26a and 26b belonging to the lifting device 20 are provided with frames 45, which are, for example, booths covered with transparent material. These frames 45 thus protect the installers 35 both from rain and from any falling objects.
  • the frames 45 are obviously open on the side on which the installation work takes place. In this embodiment, the work stations 26a and 26b cannot be lifted with respect to the lifting device 20.
  • the work station personnel hoisting cages 26a and 26b may also be provided with a heating device, and they may comprise a heated accessory box, for example, for gaskets being installed.
  • FIG 21 shows the lifting device 20 shown in Figure 20 when mounted on the boom 33 of a crane 44.
  • the lifting device 20 has been connected by means of a lockable mounting unit 32 to the fixed extension part 46 of the crane boom 33.
  • the mounting unit 32 is locked, the lifting device 20 is like a fixed part of the extension part 46 of the boom 33. This means that the installation work can be carried out while the lifting device 20 remains firmly in place.
  • a work machine feeder device 47 is connected to the work station personnel hoisting cage 26 incorporated in the lifting device relating to the invention.
  • the feeder device 47 comprises a cylinder 48, the piston 49 of which is movable, for example, by a foot pedal 50.
  • the construction may be executed mechanically, pneumatically or hydraulically.
  • reference numeral 51 refers to the tube between the foot pedal 50 and the cylinder 48.
  • the installer 35 does not have to support the work machine, which is a drilling machine 52 in Figure 22.
  • the work machine 52 may, however, equally well be, for example, a power screwdriver.
  • the installer 35 may move the drilling machine 52 supported by the eccentric arm 53 to the desired position and then press the foot pedal 50, in which case the feed motion of the piston 49 also brings about a feed motion of the drilling machine 52.
  • FIG 23 shows the work machine feeder device 47 connected to the work station hoisting cage 26 shown in Figure 2, in a horizontal position.
  • the cylinder 48 of the feeder device 47 is fixed to the hoisting cage 26 by means of a joint 54, which means that the cylinder 48 can be turned from the vertical position shown in Figure 22 to the horizontal position shown in Figure 23.
  • the foot pedal 50 causes the horizontal feed motion of the piston 49 and at the same time of the drilling machine 52.
  • the eccentric arm 53 the drilling machine 52 can be moved to the desired position before the actual drilling feed. It is obvious that the installer's 35 work is speeded up and facilitated substantially, when he does not have to support the heavy drilling machine 52 or power screwdriver in his hands.
  • Figure 24 shows the lifting device 20 and an installation situation where the first stage of installing the lightweight prefabricated element 21c has been carried out.
  • the vertical lightweight prefabricated element 21c supported by the suction pads 23, is placed against the vertical pillars 28a and 28b of the wall of the building.
  • the lifting unit 22 also comprises a joint 59, by means of which the lightweight prefabricated element 21c can be brought to a position parallel with the wall surface.
  • the lifting unit 22 also comprises a slide 60, which moves longitudinally and by means of which the element can be brought into place at the installation site in this direction.
  • Figure 24 shows that there is a gap 55 between the previous, secured lightweight prefabricated element 21b and the lightweight prefabricated element 21c now being installed. This is because the tongues and grooves 56a and 56b of the lightweight prefabricated elements 21b and 21c require that the final installation movement takes place in the direction of the plane of the element, as shown in Figure 25. It is only after this that the tongues and grooves 56a and 56b of the lightweight prefabricated elements 21b and 21c will be placed tightly against each other and thus the joint between the elements 21 b and 21c will be locked in place.
  • Figure 25 shows the securing of the lightweight prefabricated element 21c, after the second stage of the installation of the lightweight prefabricated element 21c, that is, the lateral installation movement, has been carried out.
  • the lateral movement is brought about by means of the slide 58 between the boom 57 and the frame of the lifting device 20.
  • the slide 58 always moves the boom 57 horizontally but the slide 60 at the opposite end of the boom always moves the lightweight prefabricated element longitudinally.
  • this adjusting movement of the vertical lightweight prefabricated element 21c also takes place vertically.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Transportation (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Display Devices Of Pinball Game Machines (AREA)
  • Illuminated Signs And Luminous Advertising (AREA)
  • Cage And Drive Apparatuses For Elevators (AREA)
  • Steroid Compounds (AREA)
  • Saccharide Compounds (AREA)
  • Optical Couplings Of Light Guides (AREA)
  • Led Device Packages (AREA)

Abstract

L'invention concerne un dispositif (20) de levage servant à installer sur place des éléments (21) préfabriqués légers sur une paroi ou un plafond d'un bâtiment. Le dispositif de levage comporte un moyen de stockage (37) intermédiaire pour les éléments préfabriqués légers et une unité (22) de levage équipée d'un dispositif (23, 36) de préhension servant à transférer les éléments préfabriqués légers du moyen de stockage intermédiaire au site d'installation. Selon l'invention, le dispositif de levage pourvu du moyen de stockage intermédiaire incorpore au moins un poste (26) de travail pour l'installateur (35) mettant en place l'élément (21) préfabriqué léger. Lorsqu'il y a deux postes (26a, 26b) de travail, le premier (26a) poste de travail est prévu pour l'installateur (35a) mettant en place la première extrémité de l'élément (21) préfabriqué léger, et le deuxième (26b) poste de travail pour l'installateur (35b) mettant en place l'extrémité opposée de l'élément préfabriqué léger. Dans un mode de réalisation idéal, les postes (26a, 26b) de travail sont connectés à des bras (25a, 25b) rotatifs qui sont montés sur le cadre (24) du dispositif de levage, de sorte que les postes de travail sont mobiles dans les sens vertical et latéral.
PCT/FI1998/000798 1997-10-15 1998-10-14 Dispositif servant a installer des unites de panneaux legers WO1999019583A1 (fr)

Priority Applications (4)

Application Number Priority Date Filing Date Title
AT98947587T ATE299980T1 (de) 1997-10-15 1998-10-14 Vorrichtung zum anbringen von leichten paneeleinheiten
EP98947587A EP1023510B1 (fr) 1997-10-15 1998-10-14 Dispositif servant a installer des unites de panneaux legers
AU94447/98A AU9444798A (en) 1997-10-15 1998-10-14 Device for installing light-weight panel units
DE69830915T DE69830915D1 (de) 1997-10-15 1998-10-14 Vorrichtung zum anbringen von leichten paneeleinheiten

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FI973962 1997-10-15
FI973962A FI108636B (fi) 1997-10-15 1997-10-15 Laite kevytelementtien asentamiseksi

Publications (1)

Publication Number Publication Date
WO1999019583A1 true WO1999019583A1 (fr) 1999-04-22

Family

ID=8549732

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/FI1998/000798 WO1999019583A1 (fr) 1997-10-15 1998-10-14 Dispositif servant a installer des unites de panneaux legers

Country Status (6)

Country Link
EP (1) EP1023510B1 (fr)
AT (1) ATE299980T1 (fr)
AU (1) AU9444798A (fr)
DE (1) DE69830915D1 (fr)
FI (1) FI108636B (fr)
WO (1) WO1999019583A1 (fr)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2358012A (en) * 2000-03-07 2001-07-11 Peter James Compton Positioning & fixing loads such as cladding panels
FR2807420A1 (fr) * 2000-04-11 2001-10-12 Ducrocq Ind Engin automoteur de levage et de manutention, plate-forme d'intervention comprenant un tel engin pourvu d'une nacelle, procede d'utilisation d'un tel engin et d'une telle nacelle
DE10256796A1 (de) * 2002-12-05 2004-06-24 Albert Böcker GmbH & Co KG Mobilkran
FR2888599A1 (fr) * 2005-07-13 2007-01-19 Yves Chevalier Pose-plaques
US7600959B2 (en) 2003-04-30 2009-10-13 Jlg Industries, Inc. Panel installation apparatus and method
US20130004265A1 (en) * 2009-10-21 2013-01-03 Niels Henrik Bagge Adjustment Head for a Hoisting Device
WO2015161349A1 (fr) * 2014-04-24 2015-10-29 Quantum Workhealth Programmes Pty Ltd Dispositif pour soulever et transporter un matériau laminaire
ITUA20162318A1 (it) * 2016-04-05 2017-10-05 Magni Telescopic Handlers S R L Piattaforma aerea
WO2018056906A1 (fr) * 2016-09-23 2018-03-29 Sh Technologies Pte Ltd Système et procédé de construction
WO2019092682A1 (fr) * 2017-11-13 2019-05-16 Nhon Hoa Nguyen Chariot élévateur destiné à la construction de bâtiments
CN115233940A (zh) * 2021-04-23 2022-10-25 广东博智林机器人有限公司 一种建筑设备

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113062611B (zh) * 2021-03-11 2022-08-26 银丰工程有限公司 建筑物外墙保温装饰一体化施工用吊装机

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4884938A (en) * 1986-12-01 1989-12-05 Kawasaki Jukogyo Kabushiki Kaisha Apparatus for handling large-sized articles
EP0393004A1 (fr) * 1989-03-24 1990-10-17 Glaceries De Saint-Roch, S.A. Engin de manutention
DE4237058A1 (de) * 1992-11-03 1994-05-05 Rolf Schoch Fahrbares Arbeitsgerät
US5632590A (en) * 1995-06-30 1997-05-27 Ford Motor Company Method and system for loading panels into shipping containers at a work station and end effector for use therein

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4884938A (en) * 1986-12-01 1989-12-05 Kawasaki Jukogyo Kabushiki Kaisha Apparatus for handling large-sized articles
EP0393004A1 (fr) * 1989-03-24 1990-10-17 Glaceries De Saint-Roch, S.A. Engin de manutention
DE4237058A1 (de) * 1992-11-03 1994-05-05 Rolf Schoch Fahrbares Arbeitsgerät
US5632590A (en) * 1995-06-30 1997-05-27 Ford Motor Company Method and system for loading panels into shipping containers at a work station and end effector for use therein

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2358012B (en) * 2000-03-07 2002-12-04 Peter James Compton Apparatus for positioning a load
GB2358012A (en) * 2000-03-07 2001-07-11 Peter James Compton Positioning & fixing loads such as cladding panels
FR2807420A1 (fr) * 2000-04-11 2001-10-12 Ducrocq Ind Engin automoteur de levage et de manutention, plate-forme d'intervention comprenant un tel engin pourvu d'une nacelle, procede d'utilisation d'un tel engin et d'une telle nacelle
DE10256796A1 (de) * 2002-12-05 2004-06-24 Albert Böcker GmbH & Co KG Mobilkran
DE10256796B4 (de) * 2002-12-05 2006-09-28 Albert Böcker GmbH & Co KG Mobilkran
US7600959B2 (en) 2003-04-30 2009-10-13 Jlg Industries, Inc. Panel installation apparatus and method
FR2888599A1 (fr) * 2005-07-13 2007-01-19 Yves Chevalier Pose-plaques
US9908763B2 (en) * 2009-10-21 2018-03-06 Hh Intellitech Aps Adjustment head for a hoisting device
US20130004265A1 (en) * 2009-10-21 2013-01-03 Niels Henrik Bagge Adjustment Head for a Hoisting Device
US10309116B2 (en) 2014-04-24 2019-06-04 Quantum Workhealth Programmes Pty Ltd Device for lifting and transporting sheet material
CN106536386A (zh) * 2014-04-24 2017-03-22 量子工作健康计划股份有限公司 用于提升和运输片材的装置
WO2015161349A1 (fr) * 2014-04-24 2015-10-29 Quantum Workhealth Programmes Pty Ltd Dispositif pour soulever et transporter un matériau laminaire
ITUA20162318A1 (it) * 2016-04-05 2017-10-05 Magni Telescopic Handlers S R L Piattaforma aerea
WO2018056906A1 (fr) * 2016-09-23 2018-03-29 Sh Technologies Pte Ltd Système et procédé de construction
CN109563715A (zh) * 2016-09-23 2019-04-02 顺富科技私人有限公司 建造系统和方法
US11193287B2 (en) 2016-09-23 2021-12-07 Sh Technologies Pte Ltd Construction system and method
CN109563715B (zh) * 2016-09-23 2022-03-04 顺富科技私人有限公司 建造系统和方法
WO2019092682A1 (fr) * 2017-11-13 2019-05-16 Nhon Hoa Nguyen Chariot élévateur destiné à la construction de bâtiments
CN115233940A (zh) * 2021-04-23 2022-10-25 广东博智林机器人有限公司 一种建筑设备
CN115233940B (zh) * 2021-04-23 2024-05-17 广东博智林机器人有限公司 一种建筑设备

Also Published As

Publication number Publication date
AU9444798A (en) 1999-05-03
FI973962A0 (fi) 1997-10-15
ATE299980T1 (de) 2005-08-15
FI108636B (fi) 2002-02-28
EP1023510B1 (fr) 2005-07-20
FI973962A (fi) 1999-04-16
EP1023510A1 (fr) 2000-08-02
DE69830915D1 (de) 2005-08-25

Similar Documents

Publication Publication Date Title
EP1023510B1 (fr) Dispositif servant a installer des unites de panneaux legers
AU711124B2 (en) Method and device for installing light-weight panel units
US9701520B2 (en) Hoisting platform system
US20050232740A1 (en) Material handling apparatus
JPH0821100A (ja) 揚重装置及び、該装置を用いた構築資材の運搬方法
US11680411B2 (en) System and method of assembling and installing commercial roofing
US20030136611A1 (en) Installing frame for installation of shaft equipment, installing elevator with installing frame and method of installation of shaft equipment
KR100436247B1 (ko) 실내 작업용 이동식 고소 작업대 겸용 전동식 리프트 장치
JP2002364178A (ja) 資材吊り上げ装置
JPH0754491A (ja) 建物の外装カーテンウォール組立装置
JP2954837B2 (ja) 外壁板の取付方法及びこれに使用する見切縁
EP1309762B1 (fr) Construction fournie avec un appareil de déplacement d'une plate-forme le long d'une facade
FI116284B (fi) Laite kevytelementtien asentamiseksi
JP2001354374A (ja) エレベータの昇降路内揚重装置
CN216196496U (zh) 用于钢结构墙面板安装的移动操作平台
EP2911971B1 (fr) Système de plateforme de levage
KR102621157B1 (ko) 곤도라 확장용 발판
KR200356598Y1 (ko) 건축물의 외측에 가설되는 건축자재 인양장치
JPH0730823Y2 (ja) テーブルリフター
JPH06100020B2 (ja) 足場装置
CN113982239A (zh) 钢结构墙面板安装施工方法
GB2061223A (en) Load lifting apparatus
KR960008642Y1 (ko) 방열판넬 설치장치
JPH0886021A (ja) バルコニーの取付構造および取付方法
JPH11159149A (ja) 建築物用荷取りステージ

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AL AM AT AU AZ BA BB BG BR BY CA CH CN CU CZ DE DK EE ES FI GB GE GH GM HR HU ID IL IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MD MG MK MN MW MX NO NZ PL PT RO RU SD SE SG SI SK SL TJ TM TR TT UA UG US UZ VN YU ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW SD SZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE BF BJ CF CG CI CM GA GN GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

NENP Non-entry into the national phase

Ref country code: KR

WWE Wipo information: entry into national phase

Ref document number: 1998947587

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 1998947587

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: CA

WWG Wipo information: grant in national office

Ref document number: 1998947587

Country of ref document: EP