US3665718A - Method of filling a space under a structural element and structure therefor - Google Patents

Method of filling a space under a structural element and structure therefor Download PDF

Info

Publication number
US3665718A
US3665718A US58775A US3665718DA US3665718A US 3665718 A US3665718 A US 3665718A US 58775 A US58775 A US 58775A US 3665718D A US3665718D A US 3665718DA US 3665718 A US3665718 A US 3665718A
Authority
US
United States
Prior art keywords
structural element
space
water
suspension
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US58775A
Other languages
English (en)
Inventor
Albert Griffioen
Jan Hofmeijer
Paul Cornelis Van Milligen
Jorn Yding Tonnisen
Jacobus Martinus Van Zanten
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Combinatie Westerschelde VOF
Original Assignee
Combinatie Westerschelde VOF
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Combinatie Westerschelde VOF filed Critical Combinatie Westerschelde VOF
Application granted granted Critical
Publication of US3665718A publication Critical patent/US3665718A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/073Tunnels or shuttering therefor assembled from sections individually sunk onto, or laid on, the water-bed, e.g. in a preformed trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/16Jointing caissons to the foundation soil, specially to uneven foundation soil

Definitions

  • ABSTRACT In a known method of filling a space under a structural element with sand, sand and water are supplied into said space through a suspension conduit communicating with a suction dredging installation, rolling on and guided by said structural element, extending above the water level and sucking sand from barges. This suction dredging installation obstructs the shipping and cannot be used at bad weather conditions and/or great depth.
  • the invention provides a method in which the suspension is supplied through a suspension conduit fixed to the structural element, and extending from a junction side of said structural element.
  • the invention relates to a method of laying a foundation for a structural element under water, in which the structural element is supported on a provisional support and a space under the structural element is filled up with foundation material by supplying into the space a suspension of foundation material with water, said structural element being connected with a junction side to another structural element.
  • Such a method is known and is particularly applied for laying a foundation of a tunnel element or a caisson.
  • the suspension is supplied into said space from a side of said structural element through a suspension conduit communicating with a suction dredging installation, rolling on and guided by said structural element, extending above the water level and sucking sand from barges.
  • This suction dredging installation and said barges obstruct the shipping during a period of weeks when carrying out this method.
  • This rolling suction dredging installation cannot be used at bad weather conditions and/or at great depth of said structural element.
  • the invention hasthe object to provide a method of above mentioned kind which does not obstruct shipping above the structural element and which is applicable in bad weather conditions and at great depth.
  • the suspension is supplied through a suspension conduit fixed to said first mentioned structural element, said suspension conduit extending from a junction side of said first mentioned structural element.
  • the invention has the object to provide a structural element particularly adapted for laying a foundation thereunder by applying the method according to the invention.
  • This structural element comprising provisional support means for supporting said structural element on a bed so that a space between said bed and said structural element is formed, is characterized by at least one injection pipe communicating with a suspension conduit and extending under the bottom of said structural element for extending into said space, said suspension conduit extending from a junction side of said structural element, said junction side being adapted for connection with an other structural element.
  • FIG. 1 an elevation of a tunnel during performance of the method according to the invention
  • FIG. 2 on larger scale a section along the line II-II of FIG. 1, and
  • FIG. 3 a detail in longitudinal section along the line III-Ill of FIG. 2.
  • tunnel elements 4a-4e are connected with open ramp elements 5.
  • tunnel element 4a is already laid and sand is already injected under it.
  • the tunnel element 4b is already sunk, is adjusted on provisional supports 6, its junction side 36 being already connected to the tunnel element 4a.
  • Sand is conveyed in a barge 7 and is sucked up from the barge 7 by means of a floating suction dredger installation 8, positioned outside of the navigation channel, said sand being supplied through pressure conduit 9, suspension conduits l and being injected by injection pipes 11, connected to said suspension conduits 10 into space 35 positioned under the tunnel element 4b.
  • vessels 16 that the method according to the invention does not obstruct shipping above the tunnel elements 4);, 4c and 4d.
  • Each injection pipe 11 is mounted swingably in sealing bearings 17 at a spout distance a from the side of tunnel element 4 in the tunnel bottom 18 and communicates through a valve 19 with a suspension conduit 10b running the entire length of the tunnel-element 4b.
  • This suspension conduit 10b has at each of both ends of tunnel element 411 a coupling member 20b provided with a valve 22 and adapted to be connected by means of a flexible conduit 21 to coupling members 20a and 20c of the tunnel elements 40 and 4c.
  • the workers which have to couple said coupling members come through manholes 23 provided in partitions 24.
  • Water suction nozzles 12 for sucking up water positioned in the vicinity of the injection pipe 11 communicate through valves 25 with suction conduits 13 provided with coupling members 26b at each of both ends for connection through valves 28 with flexible conduits 27.
  • Inspection glass 29 is provided for determining whether pure water or water with sand is sucked up. As soon as sand is observed in the inspection glass 29 the injection pipe 11 is shifted with the aid of turn wheel 30 or suspension is supplied through a next injection pipe 11 while water is sucked up through a belonging water suction nozzle 12. After use the injection pipes 11 and water suction nozzles 12 are filled up with water tight curing mortar through mortar injection pipes 31.
  • suspension conduits 10 and water suction conduits 13 are cut off under the valves 19 and 25 and are removed.
  • the provisional supports 6 consist of foot plates 34 and adjustable legs 33 standing on said foot plates 34 and extending through the tunnel bottom 18, the tunnel element 412 supporting on said legs 33 through jacks 32.
  • a method of laying a foundation for a structural element under water in which the structural element is supported on a provisional support and a space under the structural element is filled up with foundation material by supplying into the space a suspension of foundation material with water, said structural element being connected with a junction side to another structural element, characterized in that the suspension is supplied through a suspension conduit fixed to said first mentioned structural element, said suspension conduit extending from a junction side of said first mentioned structural element, the foundation material being supplied into said space by means of at least one injection pipe and water is sucked out of said space by means of at least one water suction nozzle provided in the vicinity of said injection pipe.
  • a method of laying a tunnel or the like beneath a navigation channel without blocking or impeding traffic through the channel which comprises the steps of:
  • Structural element comprising provisional support means for supporting said structural element on a bed so that a space between said bed and said structural element is formed, characterized by at least one injection pipe communicating with a suspension conduit and extending under the bottom of said structural element for extending into said space, said suspension conduit extending from a junction side of said structural element, said junction side being adapted for connection with another structural element, and at least one water suction nozzle provided in the vicinity of said injection pipe.
  • Structural element as claimed in claim 5 characterized by a suspension conduit having a connection member at each of both ends of said structural element.
  • Structural element as claimed in claim 5 characterized by a valve for shutting off said injection pipe and by a valve for shutting off a water suction nozzle provided in the vicinity of said injection pipe.

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Revetment (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Lining And Supports For Tunnels (AREA)
US58775A 1970-03-31 1970-07-28 Method of filling a space under a structural element and structure therefor Expired - Lifetime US3665718A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NL7004556.A NL159746B (nl) 1970-03-31 1970-03-31 Werkwijze voor het onder water funderen van een bouwele- ment, alsmede bouwelement bestemd om te worden gefundeerd met die werkwijze.

Publications (1)

Publication Number Publication Date
US3665718A true US3665718A (en) 1972-05-30

Family

ID=19809719

Family Applications (1)

Application Number Title Priority Date Filing Date
US58775A Expired - Lifetime US3665718A (en) 1970-03-31 1970-07-28 Method of filling a space under a structural element and structure therefor

Country Status (10)

Country Link
US (1) US3665718A (nl)
JP (1) JPS5029564B1 (nl)
BE (1) BE765055A (nl)
CA (1) CA931772A (nl)
CH (1) CH538017A (nl)
DK (1) DK132237C (nl)
FR (1) FR2087844A5 (nl)
GB (1) GB1340905A (nl)
NL (1) NL159746B (nl)
SE (1) SE360413B (nl)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3782127A (en) * 1972-06-12 1974-01-01 K Olsen Method and apparatus for depositing foundations under submerged structures
US3890791A (en) * 1973-04-16 1975-06-24 Ballast Nedam Groep Nv Method of building a tunnel and tunnel built according to said method
US4666346A (en) * 1986-03-24 1987-05-19 Hanna-Beric Systems, Inc. Rotatable fill pipe with collapsible backfill elbow and method of employing same to blind-fill underground voids
CN104129477A (zh) * 2014-07-23 2014-11-05 中交一航局第五工程有限公司 一种半潜驳出运沉箱的封车加固方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL158243B (nl) * 1976-01-05 1978-10-16 Ballast Nedam Groep Nv Werkwijze en inrichting voor het op een onder water gelegen bodem funderen van een bouwwerk.

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR425092A (fr) * 1911-01-21 1911-06-01 Armand Gabriel Considere Fondation sous l'eau
US2191845A (en) * 1936-12-07 1940-02-27 Christiani & Nielsen Depositing of sand under water
FR1111660A (fr) * 1954-09-21 1956-03-02 Cie Ind De Travaux Procédé d'établissement des fondations de machines, en dessous du niveau de l'eau
US3195314A (en) * 1962-02-26 1965-07-20 Degen Wilhelm Foundation method
GB1361178A (en) * 1971-07-13 1974-07-24 Car Mat Co Ltd Emergency escape apparatus

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR425092A (fr) * 1911-01-21 1911-06-01 Armand Gabriel Considere Fondation sous l'eau
US2191845A (en) * 1936-12-07 1940-02-27 Christiani & Nielsen Depositing of sand under water
FR1111660A (fr) * 1954-09-21 1956-03-02 Cie Ind De Travaux Procédé d'établissement des fondations de machines, en dessous du niveau de l'eau
US3195314A (en) * 1962-02-26 1965-07-20 Degen Wilhelm Foundation method
GB1361178A (en) * 1971-07-13 1974-07-24 Car Mat Co Ltd Emergency escape apparatus

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3782127A (en) * 1972-06-12 1974-01-01 K Olsen Method and apparatus for depositing foundations under submerged structures
US3890791A (en) * 1973-04-16 1975-06-24 Ballast Nedam Groep Nv Method of building a tunnel and tunnel built according to said method
US4666346A (en) * 1986-03-24 1987-05-19 Hanna-Beric Systems, Inc. Rotatable fill pipe with collapsible backfill elbow and method of employing same to blind-fill underground voids
CN104129477A (zh) * 2014-07-23 2014-11-05 中交一航局第五工程有限公司 一种半潜驳出运沉箱的封车加固方法
CN104129477B (zh) * 2014-07-23 2017-03-01 中交一航局第五工程有限公司 一种半潜驳出运沉箱的封车加固方法

Also Published As

Publication number Publication date
GB1340905A (en) 1973-12-19
CA931772A (en) 1973-08-14
DK132237C (da) 1976-04-05
NL159746B (nl) 1979-03-15
JPS5029564B1 (nl) 1975-09-25
DE2115209B2 (de) 1976-09-09
DE2115209A1 (de) 1971-10-21
DK132237B (da) 1975-11-10
FR2087844A5 (nl) 1971-12-31
NL7004556A (nl) 1971-10-04
CH538017A (de) 1973-06-15
BE765055A (nl) 1971-09-30
SE360413B (nl) 1973-09-24

Similar Documents

Publication Publication Date Title
CN106120859B (zh) 一种多管段沉管穿越河流的施工方法
CN101315139A (zh) 一种过河管沉管施工工艺
Rasmussen Concrete immersed tunnels—Forty years of experience
JP6640891B2 (ja) 沈埋函の継手箇所のグラウチング方法
US3665718A (en) Method of filling a space under a structural element and structure therefor
US4714379A (en) Pipelay in slurry trench
US4889448A (en) Tunnel construction
CN209603143U (zh) 浮式水下碎石基床连续整平船
CN107587497B (zh) 一种提高吹填平整度的方法
CN216108621U (zh) 一种适用于高水压条件下的沉管结构
GB1367881A (en) Hydraulic engineering installations
US2966778A (en) Caissons for wharf construction and method of installing same
US20020172558A1 (en) Submersible canal bypass
CN109537632B (zh) 一种海底隧道建设方法
CN111691481A (zh) 用于铺设截污干管的沉管法施工工艺
US715768A (en) Method of constructing and laying subaqueous tunnels.
WO1999057376A1 (en) A technique and a device for building protective sea walls or artificial reefs made of modular parts
JPH02128096A (ja) 鋼製沈埋凾およびその設置方法
US1394571A (en) Subaqueous structure and method
JP2001032301A (ja) 海底埋設構造物の構築工法
RU2648766C1 (ru) Автоматизированный способ создания глухой дамбы в размыве берега реки
US1272479A (en) Method of building foundations for subaqueous tunnels.
JP2022144881A (ja) 沈埋トンネルの設置ガイド部材および沈埋トンネルの施工方法
JP3069822B2 (ja) 取水放水管の据付工法
CN113863377A (zh) 一种适用于高水压条件下的沉管结构及其浇筑方法