US20210310356A1 - Zero-gangue-discharge short-wall face pillar-free mining method - Google Patents
Zero-gangue-discharge short-wall face pillar-free mining method Download PDFInfo
- Publication number
- US20210310356A1 US20210310356A1 US16/319,033 US201816319033A US2021310356A1 US 20210310356 A1 US20210310356 A1 US 20210310356A1 US 201816319033 A US201816319033 A US 201816319033A US 2021310356 A1 US2021310356 A1 US 2021310356A1
- Authority
- US
- United States
- Prior art keywords
- short
- wall face
- mining
- roadway
- gangue
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/005—Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
Definitions
- the present invention relates to a zero-gangue-discharge short-wall face pillar-free mining method, which is especially applicable to zero-gangue-discharge disposal in the mining operation in a mine shaft.
- the purpose of the present invention is to overcome the drawbacks in the prior art, to provide a zero-gangue-discharge short-wall face pillar-free mining method, which is simple but can attain a good effect.
- a short-wall face in an area near the shaft station of a mine shaft according to the actual conditions of the mine shaft, the mining starting position of the short-wall face is 500 m ⁇ 1,000 m away from the shaft station and the short-wall face is mined in a direction away from the shaft station;
- the short-wall face is used to dispose gangues underground, and the short-wall face is in 30 ⁇ 50 m width, in height equal to the height of the coal seam, and in 1,000 m ⁇ 3,000 m length. The entry is in 3 ⁇ 6 m width.
- the short-wall face is mined in a mining sequence of alternating forward mining and backward mining, and the roadway is excavated always by forward excavation.
- FIG. 1 shows forward mining of a short-wall face in the zero-gangue-discharge short-wall face pillar-free mining method according to the present invention
- FIG. 2 shows backward mining of the short-wall face in the zero-gangue-discharge short-wall face pillar-free mining method according to the present invention.
- 1 short-wall face
- 2 entry
- 3 roadway
- 4 open-off cut
- 5 adjacent short-wall face
- 6 adjacent roadway.
- the zero-gangue-discharge short-wall face pillar-free mining method comprises the following steps:
- a short-wall face 1 in an area near the shaft station of a mine shaft according to the actual conditions of the mine shaft, the short-wall face 1 is used to store gangues underground, and is in 30 ⁇ 50 m width, in height equal to the height of the coal seam, and in 1,000 m ⁇ 3,000 m length; the mining starting position of the short-wall face 1 is 500 m ⁇ 1,000 m away from the shaft station, and the short-wall face 1 is mined in a direction away from the shaft station, in a mining sequence of alternating forward mining and backward mining; while excavating the short-wall face 1 always by forward excavation;
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201711290733.3 | 2017-12-08 | ||
| CN201711290733.3A CN108035714A (zh) | 2017-12-08 | 2017-12-08 | 矸石零排放短面无煤柱开采法 |
| PCT/CN2018/087977 WO2019109602A1 (zh) | 2017-12-08 | 2018-05-23 | 矸石零排放短面无煤柱开采法 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20210310356A1 true US20210310356A1 (en) | 2021-10-07 |
Family
ID=62096112
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US16/319,033 Abandoned US20210310356A1 (en) | 2017-12-08 | 2018-05-23 | Zero-gangue-discharge short-wall face pillar-free mining method |
Country Status (5)
| Country | Link |
|---|---|
| US (1) | US20210310356A1 (enExample) |
| JP (1) | JP6684922B2 (enExample) |
| CN (1) | CN108035714A (enExample) |
| AU (1) | AU2018308953A1 (enExample) |
| WO (1) | WO2019109602A1 (enExample) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2024113791A1 (zh) * | 2022-11-30 | 2024-06-06 | 天地(榆林)开采工程技术有限公司 | 一种短壁综采工作面采充分离充填方法 |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108035714A (zh) * | 2017-12-08 | 2018-05-15 | 中国矿业大学 | 矸石零排放短面无煤柱开采法 |
| CN110130899B (zh) * | 2019-07-09 | 2019-11-05 | 北京中矿创新联盟能源环境科学研究院 | 全矿区无煤柱留设无巷道掘进采煤方法 |
| CN110424966B (zh) * | 2019-07-25 | 2020-05-26 | 中国矿业大学 | 一种超高水材料充填工作面矸石泵送留巷无煤柱开采方法 |
| CN111156000A (zh) * | 2020-04-07 | 2020-05-15 | 北京中矿创新联盟能源环境科学研究院 | 薄煤层无煤柱后退式采煤方法 |
Family Cites Families (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3852967A (en) * | 1970-11-04 | 1974-12-10 | Dow Chemical Co | Method of filling subterranean voids with a particulate material |
| CN1483921A (zh) * | 2002-09-18 | 2004-03-24 | 杨新兴 | 洞穴填充式采煤方法 |
| CN1936271B (zh) * | 2006-08-21 | 2011-06-29 | 山东盛泉矿业有限公司 | 煤矿矸石充填无煤柱开采工作面采空区的方法 |
| JP4459966B2 (ja) * | 2007-01-05 | 2010-04-28 | 栄一 鈴木 | 石材の採掘方法 |
| CN102261247B (zh) * | 2011-08-02 | 2013-08-21 | 中国矿业大学 | 一种条带逆向膏体充填的二次采煤方法 |
| CN103410515B (zh) * | 2013-08-23 | 2015-09-16 | 山东科技大学 | 一种三软煤层往复式无煤柱综采方法 |
| CN105089668A (zh) * | 2014-05-19 | 2015-11-25 | 梁捷 | 一种长壁工作面无煤柱开采方法 |
| CN106522948A (zh) * | 2016-11-25 | 2017-03-22 | 山东科技大学 | 一种短壁矸石胶结连采连充采煤法 |
| CN108035714A (zh) * | 2017-12-08 | 2018-05-15 | 中国矿业大学 | 矸石零排放短面无煤柱开采法 |
-
2017
- 2017-12-08 CN CN201711290733.3A patent/CN108035714A/zh active Pending
-
2018
- 2018-05-23 US US16/319,033 patent/US20210310356A1/en not_active Abandoned
- 2018-05-23 JP JP2018555277A patent/JP6684922B2/ja not_active Expired - Fee Related
- 2018-05-23 WO PCT/CN2018/087977 patent/WO2019109602A1/zh not_active Ceased
- 2018-05-23 AU AU2018308953A patent/AU2018308953A1/en not_active Abandoned
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2024113791A1 (zh) * | 2022-11-30 | 2024-06-06 | 天地(榆林)开采工程技术有限公司 | 一种短壁综采工作面采充分离充填方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2020504253A (ja) | 2020-02-06 |
| JP6684922B2 (ja) | 2020-04-22 |
| CN108035714A (zh) | 2018-05-15 |
| WO2019109602A1 (zh) | 2019-06-13 |
| AU2018308953A1 (en) | 2019-06-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2015320268B2 (en) | Mining method | |
| AU2013358812B2 (en) | Solid-filling coal mining method with two pre-excavated tunnels for advancing | |
| AU2018308953A1 (en) | Zero-gangue-discharge short-wall face pillar-free mining method | |
| US5782539A (en) | Wall-to-wall surface mining process | |
| CN107387084B (zh) | 一种沿空留巷减少切顶深度的施工方法 | |
| US4466669A (en) | Method of open cut mining | |
| CN107542465A (zh) | 一种浅埋煤层保水开采方法及其应用 | |
| CN109869150A (zh) | 一种矿山资源分段全采局充开采方法 | |
| CN112502707A (zh) | 一种膏体预充填置换煤柱的全井田无煤柱开采方法 | |
| CN103388478B (zh) | 露天煤矿应用吊斗铲的运输道路形成方法 | |
| Mitra et al. | Surface coal mining methods in Australia | |
| RU2325528C1 (ru) | Способ управления труднообрушаемой кровлей | |
| JP2020506309A (ja) | クリーンで効率的な採炭方法 | |
| CN113738438B (zh) | 一种煤柱回收与矸石充填一体化绿色开采方法 | |
| JP7162687B2 (ja) | ズリ搬送システム、及びトンネル掘削方法 | |
| GB2224053A (en) | Mining method | |
| Matsui et al. | Highwall mining system with backfilling | |
| SU1078070A1 (ru) | Способ рекультивации при открытой разработке месторождений полезных ископаемых | |
| CN103726849B (zh) | 一种露天煤矿坑底境界外薄煤层回采技术 | |
| CN107246264A (zh) | 一种坚硬顶板条件下的簿煤层走向条带充填开采方法 | |
| RU2239066C1 (ru) | Способ разработки и первичной концентрации россыпных месторождений алмазов | |
| Bilim et al. | Fully mechanized excavation system in underground coal mining | |
| Markov et al. | Application and improvement of technologies for underground mining of placer deposits in Yakutia | |
| Matsui et al. | Optimal highwall thick seam mining systems considering the in-situ stress conditions | |
| Mair et al. | 10 Tunnelling methods |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AS | Assignment |
Owner name: CHINA UNIVERSITY OF MINING AND TECHNOLOGY, CHINA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:ZHANG, NONG;XIE, ZHENGZHENG;WEI, QUN;AND OTHERS;REEL/FRAME:048105/0754 Effective date: 20190110 |
|
| AS | Assignment |
Owner name: CHINA UNIVERSITY OF MINING AND TECHNOLOGY, CHINA Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:ZHANG, NONG;XIE, ZHENGZHENG;WEI, QUN;AND OTHERS;REEL/FRAME:048319/0515 Effective date: 20190110 |
|
| STPP | Information on status: patent application and granting procedure in general |
Free format text: NON FINAL ACTION MAILED |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |