US20120301227A1 - Foundation pile and installing method thereof - Google Patents
Foundation pile and installing method thereof Download PDFInfo
- Publication number
- US20120301227A1 US20120301227A1 US13/270,308 US201113270308A US2012301227A1 US 20120301227 A1 US20120301227 A1 US 20120301227A1 US 201113270308 A US201113270308 A US 201113270308A US 2012301227 A1 US2012301227 A1 US 2012301227A1
- Authority
- US
- United States
- Prior art keywords
- tubular wall
- foundation pile
- partition plate
- top cap
- upper space
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
Definitions
- the invention relates to a foundation pile for a building construction and a method of installing the foundation pile.
- foundation piles are installed under the ground to support building constructions and to transfer the loads thereof to hard bearing strata in the ground.
- foundation piles are used when large or high-storied buildings are constructed and when the underground strength is insufficient because of the presence of soft soil layers.
- a conventional implanting-type foundation pile 1 includes a tubular wall 11 with a top edge 111 .
- the foundation pile 1 is installed as follows: an implanting hole 21 is first drilled in the ground, and concrete slurry 100 is poured into the hole 21 . Subsequently, the tubular wall 11 of the foundation pile 1 is lowered into the hole 21 such that the concrete slurry 100 flows into the tubular wall 11 from the bottom end thereof and fills the tubular wall 11 . As the tubular wall 11 is lowered, part of the concrete slurry 100 flowing into the gap between the hole 21 and the tubular wall 11 combines with the surrounding soil, and flows back into the tubular wall 11 through the top edge 111 . Therefore, an inferior-quality concrete 100 ′ is formed within the tubular wall 11 proximate to the top edge 111 .
- the concrete slurry 100 is consolidated, and the soil surrounding an upper portion of the foundation pile 1 is excavated to protrude the upper portion.
- the inside of the upper portion is then hollowed out from the top edge 111 to a depth of about 2 meters to remove the inferior concrete 100 ′.
- a reinforcing steel rod 23 is threaded through a reinforcing cage 22 , the reinforcing cage 22 is lowered into the tubular wall 11 , and two ends of the reinforcing steel rod 23 are placed on the top edge 111 of the tubular wall 11 to hang the reinforcing steel rod 23 .
- concrete slurry 100 ′′ is filled in the tubular wall 11 to secure the reinforcing steel rod 23 and the reinforcing cage 22 to the tubular wall 11 .
- the aforesaid method of implanting the foundation pile 1 advantageously reduces noises, vibration and air pollution.
- the following disadvantages are encountered in the method:
- inferior concrete 100 ′ is formed in the upper portion of the foundation pile 1 , it is necessary to excavate the surrounding soil to expose the upper portion of the foundation pile 1 and to remove the inferior concrete 100 ′ from the upper portion, thereby consuming time and labor and increasing costs.
- the foundation pile 1 implanted into the hole 21 has inner and outer surfaces to contact against interior and exterior consolidated concrete bodies. Because no concrete part interconnects the interior and exterior concrete bodies, lateral and axial binding forces of the concrete and the foundation pile 1 are low. As a result, when a building structure supported by the foundation pile 1 encounters destructive forces, such as strong wind, earthquake, etc., the reinforcing cage 22 is prone to displace laterally or become loosened. Especially, the resistance of the foundation pile 1 against an axial pulling force is very low.
- An object of the present invention is to provide a foundation pile that can effectively reduce the installation cost and that possesses high transverse and axial bearing forces and high anchoring effect.
- Another object of the present invention is to provide an improved method of installing a foundation pile.
- a foundation pile comprises a tubular wall having top and bottom ends and defining an inner space, a top cap covering the top end of the tubular wall, a partition plate disposed transversely inside the tubular wall below the top cap and dividing the inner space into an upper space between the top cap and the partition plate, and a lower space below the partition plate and opening at the bottom end, two opposite fixing holes extending radially through the tubular wall and communicated with the upper space, and a plurality of pressure release holes extending radially through the tubular wall and communicated with the lower space.
- a method of installing a foundation pile which includes a tubular wall, a top cap covering a top end of the tubular wall, a partition plate disposed inside the tubular wall and dividing the tubular wall into an upper space between the top cap and the partition plate, and a lower space below the partition plate.
- the method comprises: drilling a hole in the ground; pouring a concrete slurry into the hole; lowering the foundation pile into the hole and into the concrete slurry in such a manner that the upper space of the foundation pile is disposed above the surface of the ground; removing the top cap of the foundation pile to open the upper space and placing a reinforcing cage into the upper space; anchoring the reinforcing cage to the tubular wall; and filling concrete slurry in the upper space to secure the fixing member and the reinforcing cage to the tubular wall.
- FIG. 1 is a sectional view illustrating a conventional foundation pile for a building construction
- FIG. 2 illustrates consecutive operating steps employed in a conventional method for installing the foundation pile of FIG. 1 ;
- FIG. 3 is a fragmentary enlarged sectional view illustrating a reinforcing cage of FIG. 2 ;
- FIG. 4 is a fragmentary enlarged sectional view illustrating a final stage of the foundation pile of FIG. 2 ;
- FIG. 5 is a side sectional view illustrating a foundation pile according to a first preferred embodiment of the present invention
- FIG. 6 is a fragmentary enlarged sectional view of the foundation pile of FIG. 5 ;
- FIG. 7 is a flow diagram illustrating a method of installing a foundation pile according to the first preferred embodiment of the present invention.
- FIGS. 8A ⁇ 8F illustrate consecutive operating steps employed in the method of the preferred embodiment
- FIG. 9 is a fragmentary enlarged sectional view for illustrating a reinforcing cage of the first preferred embodiment.
- FIG. 10 is a side sectional view illustrating the second preferred embodiment of a foundation pile according to the present invention.
- a foundation pile 3 according to the first preferred embodiment of the present invention includes a tubular wall 32 ; a top cap 31 covering the top end of the tubular wall 32 ; a partition plate 33 disposed transversely inside the tubular wall 32 below the top cap 31 ; two opposite fixing holes 34 extending radially through the tubular wall 32 ; and a plurality of pressure release holes 35 extending radially through the tubular wall 32 .
- the tubular wall 32 has top and bottom ends and cooperates with the top cap 31 to define an inner space 36 .
- the partition plate 33 divides the inner space 36 into an upper space 361 between the top cap 31 and the partition plate 33 , and a lower space 363 below the partition plate 33 and formed with an opening 362 at the bottom end.
- a distance between the partition plate 33 and the top cap 31 is smaller than a distance between the partition plate 33 and the bottom end. In this embodiment, the distance between the partition plate 33 and the top cap 31 is about 2000 mm.
- the fixing holes 34 are communicated with the upper space 361 , and the pressure release holes 35 are communicated with the lower space 363 .
- pairs of the pressure release holes 35 are formed in the tubular wall 32 at intervals along the axial direction of the tubular wall 32 .
- the pressure release holes 35 in each pair are diametrically opposite to each other.
- a method of installing the foundation pile 3 comprises the following steps; drilling (step 41 ); pouring concrete (step 42 ); lowering the foundation pile (step 43 ); opening the foundation pile (step 44 ); anchoring a reinforcing cage (step 45 ); and filling concrete (step 46 ).
- a hole 21 is drilled in the ground as shown in FIG. 8A .
- concrete slurry 52 is poured into the hole 21 as shown in FIG. 8B .
- the foundation pile 3 is lowered into the hole 51 and into the concrete slurry 52 in such a manner that the upper spade 361 of the foundation pile 3 is disposed above the surface of the ground.
- the concrete slurry 52 flows into the lower space 363 from the opening 362 , and flows outwardly through the pressure release holes 35 , as shown in FIG. 8C .
- the partition plate 33 stops the concrete slurry 52 from flowing into the upper space 361 .
- the pressure release holes 35 discharge the air in the lower space 363 to reduce pressure inside the tubular wall 32 .
- the concrete slurry 52 will not entrain air and water and will not retard the consolidation of the concrete.
- step 44 the top cap 31 of the foundation pile 3 is removed to open the upper space 361 , and a reinforcing cage 53 is placed into the upper space 361 as shown in FIG. 8D .
- step 45 the reinforcing cage 53 is anchored to the tubular wall 32 by extending a fixing member 54 through the reinforcing cage 53 and by inserting two ends of the fixing member 54 into two fixing holes 34 formed in the tubular wall 32 .
- step 46 concrete slurry 52 ′ is filled in the upper space 361 to secure the fixing member 54 and the reinforcing cage 53 to the tubular wall 32 .
- the fixing member 54 used in the step 45 may be a stiffened steel rod, and the concrete slurry 52 used in the step 42 and the concrete slurry 52 ′ used in the step 46 may include expansive cement.
- the excavating step employed in the conventional method (see FIG. 2 ) is not needed in the invention simplifies the installation operations, conventional method, the method of the present invention simplifies the installation operations, saves time and labor, and reduces costs.
- the fixing member 54 is fixed inside the tubular wall by virtue of the two fixing holes 34 , the fixing member 54 together with the reinforcing cage 53 can be embedded in the consolidated concrete body in the tubular wall 32 , thereby improving anchorage of the reinforcing cage 53 to the tubular wall 32 and the concrete. Accordingly, the resistance of the reinforcing cage 53 against an upward axial pulling force can be increased, the lateral binding forces between the reinforcing cage 53 and the foundation pile 3 are increased, and an incidence of loosening the reinforcing cage 53 due to lateral and axial destructive forces can be reduced.
- the second preferred embodiment of this invention is generally identical to the first preferred embodiment, but differs in that the foundation pile 3 further includes two temporary blocking pieces 37 removably plugged into the fixing holes 34 , respectively.
- the blocking pieces 37 prevent the soil surrounding the hole 51 from entering the upper space 361 through the fixing holes 34 so that the concrete slurry 52 ′ filled in the upper space 361 will not be degraded by the surrounding soil.
Abstract
A foundation pile includes a tubular wall, a top cap covering a top end of the tubular wall, a partition plate disposed transversely in the tubular wall below the top cap and dividing an inner space of the tubular wall into upper and lower spaces, two opposite fixing holes extending radially through the tubular wall and communicated with the upper space, and a plurality of pressure release holes extending radially through the tubular wall and communicated with the lower space. The partition plate prevents concrete slurry from flowing into the upper space. The pressure release holes allow the concrete to consolidate therein and to thereby increase transverse binding forces with the foundation pile. A method of installing the foundation pile is also disclosed.
Description
- This application claims priority of Taiwanese Application No. 100118113 filed on May 24, 2011.
- 1. Field of the Invention
- The invention relates to a foundation pile for a building construction and a method of installing the foundation pile.
- 2. Description of the Related Art
- In order to increase safeness and improve stability of building constructions, foundation piles are installed under the ground to support building constructions and to transfer the loads thereof to hard bearing strata in the ground. Especially, foundation piles are used when large or high-storied buildings are constructed and when the underground strength is insufficient because of the presence of soft soil layers.
- Due to an increasing concern about noises, vibrations and air pollution caused during installation of conventional foundation piles, implanting-type foundation piles have become popular in recent years. Referring to
FIG. 1 , a conventional implanting-type foundation pile 1 includes atubular wall 11 with atop edge 111. - Referring to
FIGS. 2-4 , thefoundation pile 1 is installed as follows: animplanting hole 21 is first drilled in the ground, andconcrete slurry 100 is poured into thehole 21. Subsequently, thetubular wall 11 of thefoundation pile 1 is lowered into thehole 21 such that theconcrete slurry 100 flows into thetubular wall 11 from the bottom end thereof and fills thetubular wall 11. As thetubular wall 11 is lowered, part of theconcrete slurry 100 flowing into the gap between thehole 21 and thetubular wall 11 combines with the surrounding soil, and flows back into thetubular wall 11 through thetop edge 111. Therefore, an inferior-quality concrete 100′ is formed within thetubular wall 11 proximate to thetop edge 111. After 14 days, theconcrete slurry 100 is consolidated, and the soil surrounding an upper portion of thefoundation pile 1 is excavated to protrude the upper portion. The inside of the upper portion is then hollowed out from thetop edge 111 to a depth of about 2 meters to remove theinferior concrete 100′. Thereafter, a reinforcingsteel rod 23 is threaded through a reinforcingcage 22, the reinforcingcage 22 is lowered into thetubular wall 11, and two ends of the reinforcingsteel rod 23 are placed on thetop edge 111 of thetubular wall 11 to hang the reinforcingsteel rod 23. Finally,concrete slurry 100″ is filled in thetubular wall 11 to secure the reinforcingsteel rod 23 and the reinforcingcage 22 to thetubular wall 11. - The aforesaid method of implanting the
foundation pile 1 advantageously reduces noises, vibration and air pollution. However, the following disadvantages are encountered in the method: - Because the
inferior concrete 100′ is formed in the upper portion of thefoundation pile 1, it is necessary to excavate the surrounding soil to expose the upper portion of thefoundation pile 1 and to remove theinferior concrete 100′ from the upper portion, thereby consuming time and labor and increasing costs. - Anchorage of the reinforcing
cage 22 to thefoundation pile 1 is insufficient because the reinforcingsteel rod 23 which carries the reinforcingcage 22 merely rests on thetop edge 111 of thetubular wall 11. - The
foundation pile 1 implanted into thehole 21 has inner and outer surfaces to contact against interior and exterior consolidated concrete bodies. Because no concrete part interconnects the interior and exterior concrete bodies, lateral and axial binding forces of the concrete and thefoundation pile 1 are low. As a result, when a building structure supported by thefoundation pile 1 encounters destructive forces, such as strong wind, earthquake, etc., the reinforcingcage 22 is prone to displace laterally or become loosened. Especially, the resistance of thefoundation pile 1 against an axial pulling force is very low. - An object of the present invention is to provide a foundation pile that can effectively reduce the installation cost and that possesses high transverse and axial bearing forces and high anchoring effect.
- Another object of the present invention is to provide an improved method of installing a foundation pile.
- According to one aspect of the present invention, a foundation pile comprises a tubular wall having top and bottom ends and defining an inner space, a top cap covering the top end of the tubular wall, a partition plate disposed transversely inside the tubular wall below the top cap and dividing the inner space into an upper space between the top cap and the partition plate, and a lower space below the partition plate and opening at the bottom end, two opposite fixing holes extending radially through the tubular wall and communicated with the upper space, and a plurality of pressure release holes extending radially through the tubular wall and communicated with the lower space.
- According to another aspect of the invention, a method of installing a foundation pile, which includes a tubular wall, a top cap covering a top end of the tubular wall, a partition plate disposed inside the tubular wall and dividing the tubular wall into an upper space between the top cap and the partition plate, and a lower space below the partition plate. The method comprises: drilling a hole in the ground; pouring a concrete slurry into the hole; lowering the foundation pile into the hole and into the concrete slurry in such a manner that the upper space of the foundation pile is disposed above the surface of the ground; removing the top cap of the foundation pile to open the upper space and placing a reinforcing cage into the upper space; anchoring the reinforcing cage to the tubular wall; and filling concrete slurry in the upper space to secure the fixing member and the reinforcing cage to the tubular wall.
- Other features and advantages of the present invention will become apparent in the following detailed description of the preferred embodiments with reference to the accompanying drawings, of which:
-
FIG. 1 is a sectional view illustrating a conventional foundation pile for a building construction; -
FIG. 2 illustrates consecutive operating steps employed in a conventional method for installing the foundation pile ofFIG. 1 ; -
FIG. 3 is a fragmentary enlarged sectional view illustrating a reinforcing cage ofFIG. 2 ; -
FIG. 4 is a fragmentary enlarged sectional view illustrating a final stage of the foundation pile ofFIG. 2 ; -
FIG. 5 is a side sectional view illustrating a foundation pile according to a first preferred embodiment of the present invention; -
FIG. 6 is a fragmentary enlarged sectional view of the foundation pile ofFIG. 5 ; -
FIG. 7 is a flow diagram illustrating a method of installing a foundation pile according to the first preferred embodiment of the present invention; -
FIGS. 8A˜8F illustrate consecutive operating steps employed in the method of the preferred embodiment; -
FIG. 9 is a fragmentary enlarged sectional view for illustrating a reinforcing cage of the first preferred embodiment; and -
FIG. 10 is a side sectional view illustrating the second preferred embodiment of a foundation pile according to the present invention. - Before the present invention is described in greater detail with reference to the accompanying preferred embodiments, it should be noted herein that like elements are denoted by the same reference numerals throughout the disclosure.
- Referring to
FIGS. 5 and 6 , afoundation pile 3 according to the first preferred embodiment of the present invention includes atubular wall 32; atop cap 31 covering the top end of thetubular wall 32; apartition plate 33 disposed transversely inside thetubular wall 32 below thetop cap 31; twoopposite fixing holes 34 extending radially through thetubular wall 32; and a plurality ofpressure release holes 35 extending radially through thetubular wall 32. - The
tubular wall 32 has top and bottom ends and cooperates with thetop cap 31 to define aninner space 36. Thepartition plate 33 divides theinner space 36 into anupper space 361 between thetop cap 31 and thepartition plate 33, and alower space 363 below thepartition plate 33 and formed with anopening 362 at the bottom end. A distance between thepartition plate 33 and thetop cap 31 is smaller than a distance between thepartition plate 33 and the bottom end. In this embodiment, the distance between thepartition plate 33 and thetop cap 31 is about 2000 mm. - The
fixing holes 34 are communicated with theupper space 361, and thepressure release holes 35 are communicated with thelower space 363. In this embodiment, pairs of thepressure release holes 35 are formed in thetubular wall 32 at intervals along the axial direction of thetubular wall 32. Thepressure release holes 35 in each pair are diametrically opposite to each other. - Referring to
FIGS. 7 , and 8A˜8F, a method of installing thefoundation pile 3 comprises the following steps; drilling (step 41); pouring concrete (step 42); lowering the foundation pile (step 43); opening the foundation pile (step 44); anchoring a reinforcing cage (step 45); and filling concrete (step 46). - In the
step 41, ahole 21 is drilled in the ground as shown inFIG. 8A . In thestep 42,concrete slurry 52 is poured into thehole 21 as shown inFIG. 8B . Instep 43, thefoundation pile 3 is lowered into thehole 51 and into theconcrete slurry 52 in such a manner that theupper spade 361 of thefoundation pile 3 is disposed above the surface of the ground. At this stage, theconcrete slurry 52 flows into thelower space 363 from theopening 362, and flows outwardly through thepressure release holes 35, as shown inFIG. 8C . Thepartition plate 33 stops theconcrete slurry 52 from flowing into theupper space 361. In the meanwhile, the pressure release holes 35 discharge the air in thelower space 363 to reduce pressure inside thetubular wall 32. As such, when theconcrete slurry 52 flows into thetubular wall 32 from theopening 362, theconcrete slurry 52 will not entrain air and water and will not retard the consolidation of the concrete. - In
step 44, thetop cap 31 of thefoundation pile 3 is removed to open theupper space 361, and a reinforcingcage 53 is placed into theupper space 361 as shown inFIG. 8D . Referring toFIGS. 8E and 9 , instep 45, the reinforcingcage 53 is anchored to thetubular wall 32 by extending a fixingmember 54 through the reinforcingcage 53 and by inserting two ends of the fixingmember 54 into two fixingholes 34 formed in thetubular wall 32. Instep 46,concrete slurry 52′ is filled in theupper space 361 to secure the fixingmember 54 and the reinforcingcage 53 to thetubular wall 32. - According to the preferred embodiment, the fixing
member 54 used in thestep 45 may be a stiffened steel rod, and theconcrete slurry 52 used in thestep 42 and theconcrete slurry 52′ used in thestep 46 may include expansive cement. - In the present invention, because the
upper space 361 of thefoundation pile 3 is disposed above the surface of the ground during the lowering of thefoundation pile 3, and because thepartition plate 33 prevents theconcrete slurry 52 from flowing into theupper space 361, the excavating step employed in the conventional method (seeFIG. 2 ) is not needed in the invention simplifies the installation operations, conventional method, the method of the present invention simplifies the installation operations, saves time and labor, and reduces costs. - In addition, since the fixing
member 54 is fixed inside the tubular wall by virtue of the two fixingholes 34, the fixingmember 54 together with the reinforcingcage 53 can be embedded in the consolidated concrete body in thetubular wall 32, thereby improving anchorage of the reinforcingcage 53 to thetubular wall 32 and the concrete. Accordingly, the resistance of the reinforcingcage 53 against an upward axial pulling force can be increased, the lateral binding forces between the reinforcingcage 53 and thefoundation pile 3 are increased, and an incidence of loosening the reinforcingcage 53 due to lateral and axial destructive forces can be reduced. - Furthermore, because the
concrete slurry 52 flows through the pressure release holes 35 from thelower space 363 and is consolidated in the pressure release holes 53, anchorage between the concrete and thefoundation pile 3 is increased, thus improving lateral and axial binding forces between thefoundation pile 3 and the concrete. - Referring to
FIG. 10 , the second preferred embodiment of this invention is generally identical to the first preferred embodiment, but differs in that thefoundation pile 3 further includes twotemporary blocking pieces 37 removably plugged into the fixing holes 34, respectively. During the step of lowering thefoundation pile 43, the blockingpieces 37 prevent the soil surrounding thehole 51 from entering theupper space 361 through the fixing holes 34 so that theconcrete slurry 52′ filled in theupper space 361 will not be degraded by the surrounding soil. - While the present invention has been described in connection with what is considered the most practical and preferred embodiments, it is understood that this invention is not limited to the disclosed embodiments but is intended to cover various arrangements included within the spirit and scope of the broadest interpretation so as to encompass all such modifications and equivalent arrangements.
Claims (8)
1. A foundation pile for a building construction, comprising:
a tubular wall having top and bottom ends and defining an inner space;
a top cap covering said top end of said tubular wall;
a partition plate disposed transversely inside said tubular wall below said top cap and dividing said inner space into an upper space between said top cap and said partition plate, and a lower space below said partition plate and opening at said bottom end;
two opposite fixing holes extending radially through said tubular wall and communicated with said upper space; and
a plurality of pressure release holes extending radially through said tubular wall and communicated with said lower space.
2. The foundation pile of claim 1 , further comprising two blocking pieces removably plugged into said fixing holes, respectively.
3. The foundation pile of claim 1 , wherein a distance between said partition plate and said top cap is smaller than a distance between said partition plate and said bottom end.
4. The foundation pile of claim 3 , wherein a distance between said partition plate and said top cap is about 2000 mm.
5. A method of installing a foundation pile, which includes a tubular wall, a top cap covering a top end of the tubular wall, a partition plate disposed inside the tubular wall and dividing the tubular wall into an upper space between the top cap and the partition plate, and a lower space below said partition plate, the method comprising:
drilling a hole in the ground;
pouring a concrete slurry into the hole;
lowering the foundation pile into the hole and into the concrete slurry in such a manner that the upper space of the foundation pile is disposed above the surface of the ground;
removing the top cap of the foundation pile to open the upper space and placing a reinforcing cage into the upper space;
anchoring the reinforcing cage to the tubular wall; and
filling concrete slurry in the upper space to secure the fixing member and the reinforcing cage to the tubular wall.
6. The method of claim 5 , wherein the step of anchoring includes the step of threading a fixing member through the tubular wall and the reinforcing cage and inserting two ends of the fixing member respectively into two aligned fixing holes formed in the tubular wall.
7. The method of claim 6 , wherein the fixing member is a stiffened steel rod.
8. The method of claim 5 , wherein the concrete slurry includes expansive cement.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
TW100118113A TW201247971A (en) | 2011-05-24 | 2011-05-24 | Building fundamental pile and construction method thereof |
TW100118113 | 2011-05-24 |
Publications (1)
Publication Number | Publication Date |
---|---|
US20120301227A1 true US20120301227A1 (en) | 2012-11-29 |
Family
ID=46836173
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US13/270,308 Abandoned US20120301227A1 (en) | 2011-05-24 | 2011-10-11 | Foundation pile and installing method thereof |
Country Status (3)
Country | Link |
---|---|
US (1) | US20120301227A1 (en) |
JP (1) | JP5202708B2 (en) |
TW (1) | TW201247971A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061335A (en) * | 2013-01-21 | 2013-04-24 | 中国十七冶集团有限公司 | Pile hole dirt preventing cast iron metal cover plate for prestressed concrete tubular pile and mounting method of pile hole dirt preventing cast iron metal cover plate |
US20140112718A1 (en) * | 2012-10-22 | 2014-04-24 | Vitaly Boris Feygin | Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism |
JP2016041893A (en) * | 2014-08-19 | 2016-03-31 | 株式会社Ihi | Pile foundation and pile foundation construction method |
JP2017057637A (en) * | 2015-09-17 | 2017-03-23 | 株式会社トーヨーアサノ | Pile foundation structure, device for burying precast pile and method for constructing pile foundation structure by device for burying precast pile |
CN111705830A (en) * | 2020-05-29 | 2020-09-25 | 中和华丰建设有限责任公司 | Pile foundation and construction method thereof |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104775439B (en) * | 2015-04-20 | 2017-03-15 | 中建南方投资有限公司 | A kind of pattern foundation pit supporting structure sealing integral structure and its construction method |
CN111254826B (en) * | 2020-03-26 | 2021-11-05 | 浙江德林建设有限公司 | Construction method of municipal bridge prefabricated slab |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3611735A (en) * | 1968-10-24 | 1971-10-12 | Tech Inc Const | Method of making concrete bodies |
US5320453A (en) * | 1991-04-11 | 1994-06-14 | Roger Bullivant Of Texas, Inc. | Composite sectional concrete piles |
US6732483B1 (en) * | 2000-10-25 | 2004-05-11 | American Piledriving Equipment, Inc. | Modular plastic pile systems and methods |
US20080008539A1 (en) * | 2006-07-05 | 2008-01-10 | Con-Tech Systems Ltd. | Void form for constructing post-tensioned foundation piles |
US20080304918A1 (en) * | 2003-06-02 | 2008-12-11 | Yurkevich Engineering Bureau Ltd. | Reinforced-concrete column in the soil pit and method of its construction |
US20090074515A1 (en) * | 2004-11-11 | 2009-03-19 | Antonio Procopio | Modular System for the Construction of Overhead Wire Support and/or Supporting Pile foundations |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07150554A (en) * | 1993-11-25 | 1995-06-13 | Shimizu Corp | Steel pipe pile and method for installing it |
JP2001098542A (en) * | 1999-09-29 | 2001-04-10 | Kubota Corp | Soil cement composite taper pile |
JP2001303584A (en) * | 2000-04-20 | 2001-10-31 | Nippon Steel Corp | Structure for connecting head of foundation pile with footing |
JP2004250984A (en) * | 2003-02-20 | 2004-09-09 | Sumitomo Mitsui Construction Co Ltd | Cast-in-place steel pipe reinforced concrete pile |
JP4882492B2 (en) * | 2006-05-02 | 2012-02-22 | 住友金属工業株式会社 | Steel pipe pile structure and its construction method |
JP5274145B2 (en) * | 2008-08-07 | 2013-08-28 | 株式会社フジタ | Cast-in-place pile and its construction method |
-
2011
- 2011-05-24 TW TW100118113A patent/TW201247971A/en unknown
- 2011-10-06 JP JP2011221831A patent/JP5202708B2/en not_active Expired - Fee Related
- 2011-10-11 US US13/270,308 patent/US20120301227A1/en not_active Abandoned
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3611735A (en) * | 1968-10-24 | 1971-10-12 | Tech Inc Const | Method of making concrete bodies |
US5320453A (en) * | 1991-04-11 | 1994-06-14 | Roger Bullivant Of Texas, Inc. | Composite sectional concrete piles |
US6732483B1 (en) * | 2000-10-25 | 2004-05-11 | American Piledriving Equipment, Inc. | Modular plastic pile systems and methods |
US20080304918A1 (en) * | 2003-06-02 | 2008-12-11 | Yurkevich Engineering Bureau Ltd. | Reinforced-concrete column in the soil pit and method of its construction |
US20090074515A1 (en) * | 2004-11-11 | 2009-03-19 | Antonio Procopio | Modular System for the Construction of Overhead Wire Support and/or Supporting Pile foundations |
US20080008539A1 (en) * | 2006-07-05 | 2008-01-10 | Con-Tech Systems Ltd. | Void form for constructing post-tensioned foundation piles |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140112718A1 (en) * | 2012-10-22 | 2014-04-24 | Vitaly Boris Feygin | Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism |
CN103061335A (en) * | 2013-01-21 | 2013-04-24 | 中国十七冶集团有限公司 | Pile hole dirt preventing cast iron metal cover plate for prestressed concrete tubular pile and mounting method of pile hole dirt preventing cast iron metal cover plate |
JP2016041893A (en) * | 2014-08-19 | 2016-03-31 | 株式会社Ihi | Pile foundation and pile foundation construction method |
JP2017057637A (en) * | 2015-09-17 | 2017-03-23 | 株式会社トーヨーアサノ | Pile foundation structure, device for burying precast pile and method for constructing pile foundation structure by device for burying precast pile |
CN111705830A (en) * | 2020-05-29 | 2020-09-25 | 中和华丰建设有限责任公司 | Pile foundation and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP5202708B2 (en) | 2013-06-05 |
JP2012154162A (en) | 2012-08-16 |
TW201247971A (en) | 2012-12-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20120301227A1 (en) | Foundation pile and installing method thereof | |
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
CN101560770B (en) | Novel deep building foundation pit supporting system | |
US7600948B2 (en) | Micropile retaining wall | |
US20220098817A1 (en) | Method for constructing structure | |
JP5882143B2 (en) | Anti-floating pile for underground structures and anti-floating method for underground structures | |
KR100923587B1 (en) | Micro pile construction method using anchorage appratus of micro pile | |
KR101253678B1 (en) | Pile foundation and method for constucting the same | |
KR101195235B1 (en) | Underground structure construction method using composite pile | |
JP5919675B2 (en) | Composite foundation pile and construction method of composite foundation pile | |
KR20120102480A (en) | Phc pile with improved end bearing capacity and piling method of phc pile using the same | |
KR20120030493A (en) | Method of reinforcing existing concrete footing structure using micropile and structure thereof | |
KR100457995B1 (en) | Method and apparatus of large size stiffness passive pile with dewatering and soil reinforcement | |
CN201202114Y (en) | Bearing pile | |
KR102082495B1 (en) | Low part cast in place pile construction method | |
KR101270832B1 (en) | Concrete-Filled Tube Type Rotary File | |
KR101075922B1 (en) | Metal tubing picket with reinforced tip for auger-drilled piling method | |
KR101257905B1 (en) | Method for constructing foundation work | |
JP4809728B2 (en) | manhole | |
KR101375155B1 (en) | Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile | |
CN207828973U (en) | A kind of processing system that building special foundation is reinforced | |
KR20100136900A (en) | Reinforcing method for structure base | |
JP4475116B2 (en) | Vertical shaft structure and its construction method | |
KR20130015032A (en) | The buoyancy protection device of a steel pipe piles and thereof construction method | |
KR200373276Y1 (en) | Steel pipe pile of support structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: DEHAN INTELLECTUAL TECHNOLOGY CO., LTD, TAIWAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:YU, WEI-CHING;HUANG, HAN-TSUNG;LIANG, JEN-CHIEH;AND OTHERS;REEL/FRAME:027040/0396 Effective date: 20110929 |
|
STCB | Information on status: application discontinuation |