KR101375155B1 - Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile - Google Patents

Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile Download PDF

Info

Publication number
KR101375155B1
KR101375155B1 KR1020120033441A KR20120033441A KR101375155B1 KR 101375155 B1 KR101375155 B1 KR 101375155B1 KR 1020120033441 A KR1020120033441 A KR 1020120033441A KR 20120033441 A KR20120033441 A KR 20120033441A KR 101375155 B1 KR101375155 B1 KR 101375155B1
Authority
KR
South Korea
Prior art keywords
casing
reinforcement
excavation
concrete
pile
Prior art date
Application number
KR1020120033441A
Other languages
Korean (ko)
Other versions
KR20130111010A (en
Inventor
강일형
Original Assignee
주식회사 영신
강일형
(주)영신디엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 영신, 강일형, (주)영신디엔씨 filed Critical 주식회사 영신
Priority to KR1020120033441A priority Critical patent/KR101375155B1/en
Publication of KR20130111010A publication Critical patent/KR20130111010A/en
Application granted granted Critical
Publication of KR101375155B1 publication Critical patent/KR101375155B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 발명의 보강재 관입식 현장 타설 말뚝 시공 공법은 케이싱 외측에 아웃 케이싱을 설치하여 케이싱을 정확한 위치에 견고하게 지지하며, 케이싱 상단에 보강재 지지대를 설치하고, 아웃 케이싱과 보강재 지지대 사이에 볼트로 연결 부재를 체결함으로써, 철골 보강재가 말뚝 선단부 선타설 콘크리트에 안정적으로 관입되어 현장 타설 말뚝의 시공 정도(精度)를 제고할 수 있으며, 구조적 안정성을 확보할 수 있다.The reinforcing material penetration type construction site construction method of the present invention by installing the outer casing outside the casing to firmly support the casing at the correct position, install the reinforcement support on the upper casing, bolted connection member between the out casing and the reinforcement support By fastening, the steel reinforcement can be stably infiltrated into the pile tip pre-casting concrete, thereby improving the construction accuracy of the site-placed pile and ensuring structural stability.

Description

보강재 관입식 현장 타설 말뚝 시공 공법{Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile}Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile}

본 발명은 철골 보강재가 매입(埋入)된 현장 타설 말뚝을 시공함에 있어서, 일단 말뚝의 선단 부에 콘크리트를 타설한 후 보강재 및 케이싱을 지면에 고정한 상태로 양생하고, 선단 부의 양생이 완료되면 케이싱을 인발하고 말뚝의 나머지 부분에 콘크리트를 타설하는 말뚝 시공 공법에 관한 것으로, 좀더 상세하게는 케이싱 외측에 아웃 케이싱을 설치하여 케이싱을 정확한 위치에 견고하게 지지하며, 케이싱 상단에 보강재 지지대를 설치하고, 아웃 케이싱과 보강재 지지대 사이에 볼트로 연결 부재를 체결함으로써, 철골 보강재가 말뚝 선단부 선타설 콘크리트에 안정적으로 관입(貫入)되어 현장 타설 말뚝의 시공 정도(精度)를 제고할 수 있으며, 구조적 안정성을 확보할 수 있는 보강재 관입식 현장 타설 말뚝 시공 공법에 관한 것이다.
The present invention in the construction of the site-placed piles in which steel reinforcement is embedded, once the concrete is poured into the tip of the pile, the reinforcement and the casing is fixed in the state fixed to the ground, the casing is completed when the curing of the end is completed It relates to a pile construction method for drawing concrete and placing concrete in the rest of the pile, more specifically, by installing the outer casing outside the casing to firmly support the casing at the correct position, and to install the reinforcement support on the top of the casing, By fastening the connecting member with bolts between the out casing and the reinforcement support, the steel reinforcement can be reliably penetrated into the pile tip precast concrete to improve the construction accuracy of the site-placement pile and secure structural stability. It is about reinforcement penetration type on-site pile construction method that can be done.

현장 타설 말뚝은 기성(旣成)말뚝과 대비되는 말뚝기초의 일종으로서, 미리 천공된 굴착 공 내부로 콘크리트를 타설한 후 양생하여 구성하게 되며, 기성말뚝과는 달리 지반에 완성된 말뚝 구조체를 타입(打入)하는 공정이 불필요하므로, 항타(杭打)과정에서 유발되는 소음이나 진동을 방지할 수 있다.
On-site casting pile is a kind of pile foundation in contrast with ready-made piles. It is composed by pouring concrete into the pre-drilled excavation ball and curing it. Unlike the ready-made pile, the pile structure is completed on the ground. Since the step of elimination is unnecessary, noise or vibration caused by the driving process can be prevented.

일반적으로 말뚝기초는 선단 지지력과 주면(柱面) 마찰력에 의하여 말뚝 상부 구조물의 하중이나 지하수로 인한 지중구조물의 부압(浮壓)에 저항하게 되므로, 암반층 이상의 굴착 심도를 확보하거나, 암반층이 지나치게 깊은 경우 소정길이 이상의 근입장(根入長)을 확보하여야 한다.
In general, pile foundations are resistant to negative pressures of underground structures due to the load of the upper pile structure and groundwater due to the tip bearing force and the main surface frictional force, thus securing the depth of excavation more than the rock layer or the rock layer being too deep In this case, it is necessary to secure near-term entry length.

또한, 말뚝은 단순히 상부 하중을 지반에 전달하는 구조체로서 거동하는 것 뿐만아니라 그 자체가 일종의 장주(長柱)형 구조물로서 축 방향 압축, 횡 방향 휨 및 좌굴 응력에 저항하여야 하는바, 통상 콘크리트 본체 내부에 보강재로서 철근 또는 철골이 매입된 구조를 가진다.
In addition, the pile not only behaves as a structure that transmits the upper load to the ground, but also itself is a long column-shaped structure that must resist axial compression, transverse bending and buckling stress. Reinforcement or steel frame is embedded as a reinforcement inside.

이러한 철근 또는 철골 및 콘크리트 복합구조는 현장 타설 말뚝에서도 동일하게 적용되어, 현장 타설 말뚝은 일단 굴착 공을 형성한 후 철골 보강재를 굴착 공에 투입한 상태에서 트레미(tremie)를 통하여 말뚝 하부에서 상부로 콘크리트를 타설하는 방식으로 시공된다.
This reinforcement or steel and concrete composite structure is applied in the same way in the cast-in-place pile, the cast-in-place pile is formed once the excavation ball, and then put the steel reinforcement into the excavation ball through the tremie (tremie) from the top of the pile It is constructed by pouring concrete.

즉, 현장 타설 말뚝의 시공을 위한 굴착 공은 토사층에서의 공벽 유지를 위하여 케이싱의 관입과 동시에 굴착 공을 형성하는 방식으로 천공되는데, 일단 계획 심도에 굴착 공이 도달하면 케이싱은 존치한 상태에서 굴착장치를 철수한 후 철골 보강재 및 트레미를 투입하고, 이후 케이싱과 트레미를 서서히 인발 및 인양-해체함과 동시에 콘크리트를 타설하여 말뚝을 구성하게 되는 것이다.
In other words, the excavation ball for the construction of the site-casting pile is drilled by forming the excavation ball at the same time as the penetration of the casing to maintain the wall in the soil layer. Once the excavation ball reaches the planned depth, the casing remains in the excavation device. After withdrawing the steel reinforcement and tremy, and then the casing and tremy will be slowly drawn and lifted-dismantle and at the same time the concrete is to form a pile.

이때 형강(形鋼) 등의 철골 보강재는 하단은 굴착 공 말단부에 접하고 상단은 크레인과 강선으로 연결되어 거치된 상태로 콘크리트가 타설되는데, 트레미의 투입, 인양 및 해체과정은 물론 콘크리트 타설 완료 후 양생과정에서 보강재의 위치나 각도가 변경될 가능성이 매우 크며, 따라서 시공의 정도(精度) 확보가 극히 어려운 문제점이 있었다.
At this time, the steel reinforcement materials, such as section steel, are placed in the state where the lower part is in contact with the end of the excavation ball and the upper part is connected by crane and steel wire, and is mounted. In the curing process, the position or angle of the reinforcement material is very likely to change, and thus, there is a problem that it is extremely difficult to secure the construction accuracy.

이에, 일단 말뚝의 선단 부에 콘크리트를 타설한 후 보강재 및 케이싱을 지면에 고정한 상태로 양생하고, 선단 부의 양생이 완료되면 케이싱을 인발하면서 말뚝의 나머지 부분에 콘크리트를 타설하는 선단부 선타설식 말뚝공법이 개발되어 콘크리트 타설 및 양생 간 보강재의 정 위치 이탈을 어느 정도 해결할 수 있었다.
Therefore, once the concrete is poured on the tip of the pile, the reinforcement and the casing are fixed to the ground, and the curing is completed, and when the curing of the tip is completed, the casing is drawn out and the concrete is poured on the rest of the pile. The development was able to resolve to some extent the deviation of the reinforcement between concrete placement and curing.

이러한 선단 부 선타설식 말뚝공법의 시공과정을 약술하면 다음과 같다.
The construction process of the distal end piling method is as follows.

우선, 케이싱을 관입시킴과 동시에 계획 심도에 이르는 굴착 공을 형성하고, 굴착 공 형성이 완료되면 케이싱을 고정한 상태에서 트레미를 통하여 말뚝 선단 부에 콘크리트를 일부 타설한다.
First, the casing is inserted and at the same time, the excavation ball reaches the planned depth, and when the excavation ball is formed, the concrete is partially poured on the tip of the pile through the trem with the casing fixed.

선단 부 콘크리트 타설이 완료된 직후, 타설된 콘크리트의 양생이 진행되기 전 케이싱 지지대를 신속하게 체결하여 케이싱을 지면에 고정하고, 보강재 지지대를 신속하게 설치한다.
Immediately after the tip concrete is finished, the casing support is fastened to fix the casing to the ground quickly and the reinforcement support is installed quickly.

케이싱 지지대와 보강재 지지대는 케이싱과 보강재를 각각 지면과 케이싱 상단에 고정하는 장치로서, 케이싱 지지대는 지표면에 노출된 케이싱의 상단부에 결합되어 케이싱의 자중을 지면에 분산함으로써, 케이싱의 침하를 방지하는 기능을 수행하며, 보강재 지지대는 케이싱 상단에 결합되는 외곽 부와 보강재 상단부에 체결되는 내부 프레임으로 구성되어 보강재가 케이싱 내에서 정확한 위치를 유지할 수 있도록 지지하는 기능을 수행한다.
The casing support and the reinforcement support are devices for fixing the casing and the reinforcement to the ground and the upper end of the casing respectively. And, the reinforcement support is composed of an outer frame coupled to the upper end of the casing and the inner frame fastened to the upper end of the reinforcement serves to support the reinforcement to maintain the correct position in the casing.

케이싱 지지대의 설치, 케이싱 상단부의 보강재 지지대의 설치가 완료되면, 보강재 지지대를 통과하여 보강재를 굴착 공 내부에 투입하되 보강재의 선단부가 기 타설된 선단 부 콘크리트에 관입되도록 하는데, 이때 콘크리트의 양생이 진행된 상태라면 보강재의 선단 부 콘크리트 내 관입이 어려우므로, 전술한 케이싱 지지대 설치 내지 보강재 지지대 설치공정이 신속하게 완료되어야 한다.
When the installation of the casing support and the installation of the reinforcement support of the upper end of the casing is completed, the reinforcement is introduced into the excavation hole by passing through the reinforcement support, but the tip of the reinforcement is inserted into the concrete of the other end of the reinforcement. If the state is difficult to penetrate the concrete of the front end of the reinforcement, the above-described casing support installation or reinforcement support installation process should be completed quickly.

보강재가 관입된 상태로 선타설 선단 부 콘크리트의 양생이 완료되면, 케이싱 지지대 및 보강재 지지대를 해체한 후, 케이싱을 인발함과 동시에 콘크리트를 타설하여 말뚝을 완성하게 된다.
When curing of the precast concrete at the end of the stiffening material is completed, the casing support and the reinforcement support are dismantled, and the casing is drawn and concrete is poured to complete the pile.

그러나, 종래 현장 타설 말뚝 시공방법은 케이싱이 정확한 위치에 견고하게 지지되지 못하며, 보강재가 정확한 위치에 견고하게 고정되지 못하여, 결과적으로 보강재가 말뚝 선단부 선타설 콘크리트에 안정적으로 관입되지 못하게 됨으로써, 현장 타설 말뚝의 구조적 안정성을 확보하기 어렵고 시공 공정에 많은 시간이 소요되는 문제점이 여전히 남아 있다.
However, in the conventional site-pouring pile construction method, the casing is not firmly supported at the correct position, and the reinforcement is not firmly fixed at the correct position, and as a result, the reinforcement is not stably infiltrated into the pile tip precast concrete, thereby placing There is still a problem that it is difficult to secure the structural stability of the pile and takes a long time in the construction process.

본 발명은 전술한 문제점을 해결하기 위하여 케이싱이 아웃 케이싱에 의해서 정확한 위치에 견고하게 지지되며, 보강재 지지대와 아웃 케이싱을 연결하는 연결부재에 의해서 보강재가 정확한 위치에 고정되고, 견고하게 지지되므로 철골 보강재가 말뚝 선단부 선타설 콘크리트에 안정적으로 관입되어 현장 타설 말뚝의 시공 정도(精度)를 제고할 수 있으며, 구조적 안정성을 확보함은 물론 공정을 간소화하고 공기를 단축할 수 있는 보강재 관입식 현장 타설 말뚝 시공공법을 제공함에 그 목적이 있다.
In order to solve the above problems, the casing is firmly supported at the correct position by the out casing, and the reinforcement is fixed at the correct position by the connecting member connecting the reinforcing member support and the out casing, and is firmly supported so that the steel reinforcement member Stable penetration of the pile tip into the concrete to improve the construction accuracy of the site-placed piles.In addition to securing structural stability, the construction of reinforcement-type site-placed piles that can simplify the process and shorten the air The purpose is to provide a process.

전술한 목적을 달성하기 위하여 본 발명의 보강재 관입식 현장 타설 말뚝 시공 공법은 보강재가 매입되는 현장 타설 말뚝공법으로서, 굴착 공 하측 일부에 콘크리트를 타설하되, 하단에 보강재 선단 일부가 매입된 상태로 양생한 후, 양생이 완료되면 케이싱을 인발하면서 굴착 공의 나머지 부분에 콘크리트를 타설하여 말뚝을 완성하는 현장 타설 말뚝 공법에 있어서, 지중(地中)에 아웃 케이싱을 설치하고, 상기 케이싱을 관입(貫入)시키며, 굴착장치를 굴진하여 굴착 공을 형성하는 단계; 계획 심도에 이르는 굴착 공의 굴착이 완료되면, 지표면에 노출된 케이싱의 외주면 상단부에 케이싱 지지대를 설치하고, 상기 케이싱의 침하를 억제하는 단계; 굴착장치를 굴진하여 계획 심도 이하의 추가 굴착 공을 형성하는 단계; 상기 추가 굴착 공 형성이 완료되면, 상기 굴착장치를 철수하고, 상기 케이싱을 고정시킨 상태에서 트레미를 통하여 말뚝 선단 부에 콘크리트를 일부 타설하는 단계; 상기 케이싱 상단에 보강재 지지대를 설치하고, 상기 아웃 케이싱과 상기 보강재 지지대 사이에 볼트로 연결 부재를 체결하는 단계; 상기 케이싱의 중앙에 위치하도록 보강재를 상기 추가 굴착 공에 투입하여 상기 보강재의 하단부가 상기 추가 굴착 공에 타설된 콘크리트에 관입되는 단계; 상기 보강재 상단부가 상기 보강재 지지대에 의하여 고정된 상태로 추가 굴착 공의 콘크리트를 양생하는 단계; 상기 굴착 공의 콘크리트의 양생이 완료되면, 상기 보강재 지지대, 상기 케이싱 지지대 및 상기 아웃 케이싱을 해체한 후, 상기 케이싱을 인발하면서 트레미를 통하여 굴착 공 내부에 콘크리트를 타설하는 단계; 및 상기 콘크리트를 양생하여 말뚝을 완성하는 단계로 이루어진다.
In order to achieve the above object, the reinforcement immersion-type site-building pile construction method of the present invention is a site-installed pile method in which the reinforcement is embedded, while placing concrete on the lower part of the excavation ball, the reinforcement end portion is buried in the state of curing After the curing is completed, the casing is drawn out and concrete is poured into the remaining portion of the excavation ball to complete the pile.In the field placing pile method, an out casing is installed in the ground and the casing is infiltrated. And drilling the excavation device to form an excavation ball; When the excavation of the excavation ball reaches the depth of the plan is completed, installing a casing support on the upper end of the outer peripheral surface of the casing exposed to the ground surface, and suppressing the settlement of the casing; Drilling an excavator to form additional excavation balls of less than the planned depth; When the additional excavation hole formation is completed, withdrawing the excavation device, and placing part of the concrete at the tip of the pile through the tremy while the casing is fixed; Installing a reinforcing member support on an upper end of the casing, and fastening a connecting member with a bolt between the out casing and the reinforcing member support; Inserting a reinforcing material into the additional drilling hole so as to be located at the center of the casing, and a lower end of the reinforcing material is inserted into the concrete placed in the additional drilling hole; Curing the concrete of the additional excavation ball in a state where the upper end of the reinforcing material is fixed by the reinforcing material supporter; When the curing of the concrete of the excavation ball is completed, after dismantling the reinforcing member support, the casing support and the out casing, placing the concrete inside the excavation ball through the tremy while drawing the casing; And curing the concrete to complete the pile.

상기 아웃 케이싱은 상기 케이싱 외부에 용접하여 상기 케이싱의 움직임을 방지하도록 한다.
The out casing is welded to the outside of the casing to prevent movement of the casing.

이상에서 설명한 바와 같이 본 발명은 케이싱이 아웃 케이싱에 의해서 정확한 위치에 견고하게 지지되며, 보강재 지지대와 아웃 케이싱을 연결하는 연결부재에 의해서 보강재가 정확한 위치에 고정되고, 견고하게 지지되므로 철골 보강재가 말뚝 선단부 선타설 콘크리트에 안정적으로 관입되어 현장 타설 말뚝의 시공 정도(精度)를 제고할 수 있으며, 구조적 안정성을 확보함은 물론 공정을 간소화하고 공기를 단축하며, 자재를 대폭 절감하는 효과를 얻을 수 있다.
As described above, in the present invention, the casing is firmly supported at the correct position by the out casing, and the reinforcement is fixed at the correct position and firmly supported by the connecting member connecting the reinforcing member support and the out casing, so that the steel reinforcement is piled up. It can be stably intruded into the tip-casting concrete to improve the construction accuracy of site-casting piles, and can secure structural stability, simplify the process, shorten the air, and significantly reduce the material. .

도 1은 본 발명의 시공 과정을 보인 설명도
도 2는 본 발명의 시공 과정을 보인 흐름도
도 3은 본 발명에 따른 보강재 관입식 현장 타설 말뚝 시공을 보인 도면
도 4 및 도 5는 케이싱 지지대를 보인 종단면도/평면도
도 6은 아웃 케이싱을 보인 평면도
도 7은 도 6의 A-A선 단면도
도 8은 아웃 케이싱의 변형 예를 보인 평면도
도 9는 케이싱의 상단부에 설치된 보강재 지지대를 보인 사시도
도 10은 연결 부재의 체결구조를 보인 종단면도
도 11은 도 9의 요부 발췌 단면도
1 is an explanatory diagram showing a construction process of the present invention
2 is a flow chart showing the construction process of the present invention
Figure 3 is a view showing the construction of the reinforcement intrusive site pouring pile according to the present invention
4 and 5 are longitudinal cross-sectional / plan views showing the casing support
6 is a plan view showing the out casing
7 is a sectional view taken along the line AA in Fig. 6
8 is a plan view showing a modification of the out casing
9 is a perspective view showing a reinforcement support installed on the upper end of the casing
10 is a longitudinal sectional view showing a fastening structure of the connection member;
11 is a cross-sectional view of the main portion of Figure 9

이하, 첨부 도면을 참조하여 본 발명의 바람직한 실시 예에 따른 보강재 관 입식 현장 타설 말뚝 시공 공법에 대하여 상세하게 설명한다.
Hereinafter, with reference to the accompanying drawings will be described in detail with respect to the reinforcement pipe in situ pile construction method according to an embodiment of the present invention.

도 1은 본 발명의 시공 과정을 보인 설명도, 도 2는 본 발명의 시공 과정을 보인 흐름도, 도 3은 본 발명에 따른 보강재 관입식 현장 타설 말뚝 시공을 보인 도면, 도 4 및 도 5는 케이싱 지지대를 보인 종단면도/평면도, 도 6은 아웃 케이싱을 보인 평면도, 도 7은 도 6의 A-A선 단면도, 도 8은 아웃 케이싱의 변형 예를 보인 평면도, 도 9는 케이싱의 상단부에 설치된 보강재 지지대를 보인 사시도, 도 10은 연결 부재의 체결구조를 보인 종단면도, 및 도 11은 도 9의 요부 발췌 단면도이다.
Figure 1 is an explanatory view showing a construction process of the present invention, Figure 2 is a flow chart showing a construction process of the present invention, Figure 3 is a view showing the construction of the reinforcement penetration type site-placement pile construction according to the present invention, Figures 4 and 5 are 6 is a plan view showing an out casing, FIG. 7 is a sectional view taken along the line AA of FIG. 6, FIG. 8 is a plan view showing a modified example of the out casing, and FIG. 9 is a reinforcement support installed at the upper end of the casing. 10 is a longitudinal sectional view showing the fastening structure of the connecting member, and FIG. 11 is a sectional view of the main portion of FIG.

위 첨부 도면을 참조하면, 본 발명의 바람직한 실시 예에 따른 보강재 관입식 현장 타설 말뚝 시공 공법은 보강재(160)가 매입되는 현장 타설 말뚝공법으로서, 굴착 공 하측 일부에 콘크리트(C)를 타설하되, 하단에 보강재(160) 선단 일부가 매입된 상태로 양생한 후, 양생이 완료되면 케이싱(110)을 인발하면서 굴착 공의 나머지 부분에 콘크리트(C')를 타설하여 말뚝을 완성하는 현장 타설 말뚝 공법에 관한 것이다.
Referring to the accompanying drawings, the reinforcement in-situ site-installed pile construction method according to a preferred embodiment of the present invention as a site-installed pile method in which the reinforcement 160 is embedded, the concrete (C) is poured into a portion of the excavation ball, After curing with a portion of the tip of the reinforcement 160 is embedded at the bottom, after curing is completed, the casing 110 is drawn while placing concrete (C ') on the remaining part of the excavation ball to complete the pile It is about.

본 발명의 바람직한 실시 예에 따른 보강재 관 입식 현장 타설 말뚝공법은 지중(地中)에 아웃 케이싱(120)을 설치하고, 상기 케이싱(110)을 관입(貫入)시키며, 굴착장치(200)를 굴진하여 굴착 공을 형성하는 단계(S 10); 계획 심도에 이르는 굴착 공의 굴착이 완료되면, 지표면(G)에 노출된 케이싱(110)의 외주면 상단부에 케이싱 지지대(130)를 설치하고, 상기 케이싱(110)의 침하를 억제하는 단계(S 20); 굴착장치(200)를 굴진하여 계획 심도 이하의 추가 굴착 공을 형성하는 단계(S 30); 상기 추가 굴착 공 형성이 완료되면, 상기 굴착장치(200)를 철수하고, 상기 케이싱(110)을 고정시킨 상태에서 트레미(T)를 통하여 말뚝 선단 부에 콘크리트(C)를 일부 타설하는 단계(S 40); 상기 케이싱(110) 상단에 보강재 지지대(140)를 설치하고, 상기 아웃 케이싱(120)과 상기 보강재 지지대(140) 사이에 볼트(B)로 연결 부재(150)를 체결하는 단계(S 50); 상기 케이싱(110)의 중앙에 위치하도록 보강재(160)를 상기 추가 굴착 공에 투입하여 상기 보강재(160)의 하단부가 상기 추가 굴착 공에 타설된 콘크리트(C)에 관입되는 단계(S 60); 상기 보강재(160) 상단부가 상기 보강재 지지대(140)에 의하여 고정된 상태로 추가 굴착 공의 콘크리트(C)를 양생하는 단계(S 70); 상기 굴착 공의 콘크리트(C)의 양생이 완료되면, 상기 보강재 지지대(140), 상기 케이싱 지지대(130) 및 상기 아웃 케이싱(120)을 해체한 후, 상기 케이싱(110)을 인발하면서 트레미(T)를 통하여 굴착 공 내부에 콘크리트(C')를 타설하는 단계(S 80); 및 상기 콘크리트(C')를 양생하여 말뚝을 완성하는 단계(S 90);로 이루어진다.
Reinforcement pipe-mounted site-pouring pile method according to a preferred embodiment of the present invention is installed out casing 120 in the ground, the casing 110 is inserted, the excavation apparatus 200 is excavated To form an excavation ball (S 10); When the excavation of the excavation ball reaching the planned depth is completed, installing a casing support 130 on the upper end of the outer peripheral surface of the casing 110 exposed to the ground surface (G), and suppressing the settlement of the casing 110 (S 20 ); Drilling an excavation device 200 to form additional drilling holes having a predetermined depth or less (S 30); When the additional excavation hole formation is completed, withdrawing the excavation device 200, and placing part of the concrete (C) to the pile tip portion through the tremy (T) in a state of fixing the casing 110 ( S 40); Installing a reinforcement supporter 140 on an upper end of the casing 110 and fastening the connecting member 150 with a bolt (B) between the out casing 120 and the reinforcement supporter 140 (S 50); Inserting a reinforcing material (160) into the additional drilling hole so as to be located at the center of the casing (110) so that the lower end of the reinforcing material (160) is introduced into the concrete (C) placed in the additional drilling hole (S 60); Curing the concrete (C) of the additional excavation ball in a state where the upper end of the reinforcement member 160 is fixed by the reinforcement support member 140 (S 70); When the curing of the concrete (C) of the excavation ball is completed, after dismantling the reinforcing member support 140, the casing support 130 and the out casing 120, while pulling out the casing (110) Pouring concrete (C ′) inside the excavation ball through T) (S 80); And curing the concrete (C ′) to complete the pile (S 90).

이하, 본 발명의 바람직한 실시 예에 따른 보강재 관 입식 현장 타설 말뚝공법을 좀더 구체적으로 살펴보면 다음과 같다.
Hereinafter, looking at the reinforcement pipe in situ pile method according to a preferred embodiment of the present invention in more detail.

상기 단계(S 10)에서는, 지중(地中)에 아웃 케이싱(120)을 설치하고, 상기 케이싱(110)을 관입(貫入)시킨다. 그 다음, 굴착장치(200)를 굴진하여 굴착 공을 형성한다. 상기 아웃 케이싱(120)은 상기 케이싱(110) 외부에 밀착 설치하여 상기 케이싱(110)의 움직임을 방지하도록 한다.
In the step S 10, the out casing 120 is installed in the ground, and the casing 110 is inserted therein. Then, the excavation apparatus 200 is excavated to form an excavation ball. The out casing 120 is installed in close contact with the outside of the casing 110 to prevent the movement of the casing 110.

상기 단계(S 20)에서는, 계획 심도에 이르는 굴착 공의 굴착이 완료되면, 지표면(G)에 노출된 케이싱(110)의 외주면 상단부에 케이싱 지지대(130)를 설치하여 상기 케이싱(110)의 침하를 억제하도록 한다.
In the step (S 20), when the excavation of the excavation ball to reach the planned depth is completed, the casing support 130 is installed on the upper end of the outer peripheral surface of the casing 110 exposed to the ground surface (G) to sink the casing 110 To suppress it.

다시 말해, 상기 케이싱 지지대(130)는 지표면에 노출된 아웃 케이싱(120)의 상단부에 결합되어 케이싱(110)의 자중(自重)을 지면(G)에 분산함으로써 케이싱(110)의 침하를 방지하는 기능을 수행한다.
In other words, the casing support 130 is coupled to the upper end of the outer casing 120 exposed to the ground surface to distribute the self-weight of the casing 110 to the ground (G) to prevent settlement of the casing 110 Perform the function.

상기 단계(S 30)에서는, 굴착장치(200)를 굴진하여 계획 심도 이하의 추가 굴착 공을 형성한다.
In the step (S 30), the excavation apparatus 200 is excavated to form additional excavation balls of a predetermined depth or less.

상기 단계(S 40)에서는, 상기 추가 굴착 공의 형성이 완료되면, 상기 굴착장치(200)를 철수하고, 상기 케이싱(110)을 고정시킨 상태에서 트레미(T)를 통하여 말뚝 선단 부에 콘크리트(C)를 일부 타설한다.
In the step (S 40), when the formation of the additional excavation ball is completed, withdraw the excavation device 200, the concrete at the tip of the pile through the tremy (T) in a state of fixing the casing 110 Partially cast (C).

상기 단계(S 50)에서는 상기 케이싱(110) 상단에 보강재 지지대(140)를 설치하고, 상기 아웃 케이싱(120)과 상기 보강재 지지대(140) 사이에 볼트(B)로 연결 부재(150)를 체결한다. 여기서 상기 보강재 지지대(140)는 "ㄴ"형상을 갖는 부재를 사용하고, 상기 연결 부재(150)는 "ㄷ"자 채널구조를 갖는 부재를 사용한다.
In the step (S 50) to install the reinforcement support 140 on the upper casing 110, fastening the connecting member 150 with a bolt (B) between the out casing 120 and the reinforcement support 140. do. Here, the reinforcement supporter 140 uses a member having a "b" shape, and the connection member 150 uses a member having a "c" shaped channel structure.

상기 보강재 지지대(140)는 케이싱(110) 상단에 결합되는 외곽 부분과 보강재(160) 상단부에 체결되는 프레임으로 구성되어, 상기 보강재(160)가 케이싱(110) 내에서 정확한 위치를 유지할 수 있도록 지지하는 기능을 수행한다.
The reinforcement supporter 140 is composed of a frame coupled to the upper end of the casing 110 and the upper end of the reinforcement 160, the support so that the reinforcement 160 can maintain the correct position in the casing 110 It performs the function.

상기 단계(S 60)에서는, 상기 케이싱(110)의 중앙에 위치하도록 보강재(160)를 상기 추가 굴착 공에 투입하여 상기 보강재(160)의 하단부가 상기 추가 굴착 공에 타설된 콘크리트(C)에 관입되도록 한다.
In the step (S 60), the reinforcement 160 is placed in the additional excavation ball so as to be located in the center of the casing 110, the lower end of the reinforcement 160 to the concrete (C) is placed in the additional excavation ball Intrusive.

상기 보강재 지지대(140)의 설치가 완료되면, 보강재 지지대(140)를 통과하여 보강재(160)를 굴착공 내부에 투입하되, 보강재(160)의 선단 부가 기 타설된 선단부 콘크리트(C)에 관입되도록 하는데, 이때 콘크리트의 양생이 진행된 상태라면 보강재(160)의 선단부 콘크리트(C) 내 관입이 어려우므로, 전술한 케이싱 지지대(130) 설치 내지 보강재 지지대(140) 설치공정이 신속하게 완료되어야 한다.
When the installation of the reinforcement supporter 140 is completed, the reinforcement supporter 140 is passed through the reinforcement supporter 140 to be inserted into the excavation hole, so that the tip portion of the reinforcement member 160 is inserted into the other end of the concrete (C). At this time, if the curing of the concrete is in progress, the penetration of the front end of the reinforcement (160) concrete (C) is difficult, the above-described casing support 130 to install the reinforcement support 140 must be completed quickly.

상기 단계(S 70)에서는, 상기 보강재(160) 상단부가 상기 보강재 지지대(140)에 의하여 고정된 상태로 추가 굴착 공의 콘크리트(C)를 일정시간 동안 양생한다.
In the step (S 70), the reinforcement 160 cures the concrete (C) of the additional excavation ball for a predetermined time in a fixed state by the reinforcement support 140.

상기 단계(S 80)에서는, 상기 굴착 공의 콘크리트(C)의 양생이 완료되면, 상기 보강재 지지대(140), 상기 케이싱 지지대(130) 및 상기 아웃 케이싱(120)을 해체한 후, 상기 케이싱(110)을 인발하면서 트레미(T)를 통하여 굴착 공 내부에 콘크리트(C')를 타설한다.
In the step (S 80), when the curing of the concrete (C) of the excavation ball is completed, after dismantling the reinforcement support 140, the casing support 130 and the out casing 120, the casing ( While drawing 110, the concrete (C ') is poured into the excavation ball through the tremy (T).

마지막으로, 상기 단계(S 90)에서는 상기 콘크리트(C')를 양생하여 말뚝을 완성한다.
Finally, the step (S 90) to cure the concrete (C ') to complete the pile.

한편, 도 8은 아웃 케이싱의 변형 예를 보인 도면으로, 아웃 케이싱(120')의 형상을 변형하여 사용할 수도 있다.
8 is a diagram illustrating a modified example of the out casing, and the shape of the out casing 120 'may be modified.

이상에서 설명한 바와 같이 본 발명은 케이싱이 아웃 케이싱에 의해서 정확한 위치에 견고하게 지지되며, 보강재 지지대와 아웃 케이싱을 연결하는 연결부재에 의해서 보강재가 정확한 위치에 고정되고, 견고하게 지지되므로 철골 보강재가 말뚝 선단부 선타설 콘크리트에 안정적으로 관입되어 현장 타설 말뚝의 시공 정도(精度)를 제고할 수 있으며, 구조적 안정성을 확보함은 물론 공정을 간소화하고 공기를 단축하며, 자재를 대폭 절감하는 효과를 얻을 수 있다.
As described above, in the present invention, the casing is firmly supported at the correct position by the out casing, and the reinforcement is fixed at the correct position and firmly supported by the connecting member connecting the reinforcing member support and the out casing, so that the steel reinforcement is piled up. It can be stably intruded into the tip-casting concrete to improve the construction accuracy of site-casting piles, and can secure structural stability, simplify the process, shorten the air, and significantly reduce the material. .

B: 볼트
C,C': 콘크리트
G:지표면
T: 트레미
110: 케이싱
120: 아웃 케이싱
130: 케이싱 지지대
140: 보강재 지지대
150: 연결 부재
160: 보강재
200: 굴착장치
B: Bolt
C, C ': Concrete
G: surface
T: Tremi
110: casing
120: out casing
130: casing support
140: stiffener support
150: connecting member
160: reinforcement
200: excavator

Claims (4)

보강재(160)가 매입되는 현장 타설 말뚝공법으로서, 굴착 공 하측 일부에 콘크리트(C)를 타설하되, 하단에 보강재(160) 선단 일부가 매입된 상태로 양생한 후, 양생이 완료되면 케이싱(110)이 설치된 상태에서 굴착 공의 나머지 부분에 콘크리트(C')를 타설하여 말뚝을 완성하는 현장 타설 말뚝 공법에 있어서,
지중(地中)에 아웃 케이싱(120)을 설치하고, 상기 아웃 케이싱(120)이 케이싱(110) 외부에 밀착하여 상기 케이싱(110)의 움직임을 방지하도록 상기 케이싱(110)을 관입(貫入)시키며, 굴착장치(200)를 굴진하여 굴착 공을 형성하는 단계(S 10);
계획 심도에 이르는 굴착 공의 굴착이 완료되면, 지표면(G)에 노출된 케이싱(110)의 외주면 상단부에 케이싱 지지대(130)를 설치하고, 상기 케이싱 지지대(130)는 아웃 케이싱(120)의 상단부에 결합되어 케이싱(110)의 자중(自重)을 지면(G)에 분산함으로써 케이싱(110)의 침하를 방지하는 단계(S 20);
굴착장치(200)를 굴진하여 계획 심도 이하의 추가 굴착 공을 형성하는 단계(S 30);
상기 추가 굴착 공 형성이 완료되면, 상기 굴착장치(200)를 철수하고, 상기 케이싱(110)을 고정시킨 상태에서 트레미(T)를 통하여 말뚝 선단 부에 콘크리트(C)를 일부 타설하는 단계(S 40);
상기 케이싱(110) 상단에 "ㄴ"형상을 갖는 보강재 지지대(140)를 설치하고, 상기 아웃 케이싱(120)과 상기 보강재 지지대(140) 사이에 볼트(B)로 "ㄷ"자 채널형상의 연결 부재(150)를 체결하는 단계(S 50);
상기 케이싱(110)의 중앙에 위치하도록 보강재(160)를 상기 추가 굴착 공에 투입하여 상기 보강재(160)의 하단부가 상기 추가 굴착 공에 타설된 콘크리트(C)에 관입되는 단계(S 60);
상기 보강재(160) 상단부가 상기 보강재 지지대(140)에 의하여 고정된 상태로 추가 굴착 공의 콘크리트(C)를 양생하는 단계(S 70);
상기 굴착 공의 콘크리트(C)의 양생이 완료되면, 상기 보강재 지지대(140), 상기 케이싱 지지대(130) 및 상기 아웃 케이싱(120)을 해체한 후, 상기 케이싱(110)을 인발하면서 트레미(T)를 통하여 굴착 공 내부에 콘크리트(C')를 타설하는 단계(S 80); 및
상기 콘크리트(C')를 양생하여 말뚝을 완성하는 단계(S 90);로 이루어짐을 특징으로 하는 보강재 관입식 현장 타설 말뚝 시공 공법.
Reinforcement 160 is embedded in the site-pouring pile method, the concrete (C) is placed in the lower part of the excavation ball, the curing of the end portion of the reinforcement 160 is buried at the bottom, after curing, the casing (110) In the site-placement pile construction method to finish the pile by placing concrete (C ') in the remaining portion of the excavation ball with the) installed,
An out casing 120 is installed in the ground, and the out casing 120 is in close contact with the outside of the casing 110 to penetrate the casing 110 to prevent movement of the casing 110. And drilling the excavation device 200 to form an excavation ball (S 10);
When the excavation of the excavation ball reaching the planned depth is completed, the casing support 130 is installed at the upper end of the outer peripheral surface of the casing 110 exposed to the ground surface G, and the casing support 130 is the upper end of the out casing 120. Coupled to the step of dispersing the weight of the casing (110) on the ground (G) to prevent settlement of the casing (110) (S 20);
Drilling an excavation device 200 to form additional drilling holes having a predetermined depth or less (S 30);
When the additional excavation hole formation is completed, withdrawing the excavation device 200, and placing part of the concrete (C) to the pile tip portion through the tremy (T) in a state of fixing the casing 110 ( S 40);
A reinforcing member supporter 140 having a “b” shape is installed on the casing 110, and the “c” shaped channel connection is performed between the out casing 120 and the reinforcing member supporter 140 with a bolt B. Fastening the member 150 (S 50);
Inserting a reinforcing material (160) into the additional drilling hole so as to be located at the center of the casing (110) so that the lower end of the reinforcing material (160) is introduced into the concrete (C) placed in the additional drilling hole (S 60);
Curing the concrete (C) of the additional excavation ball in a state where the upper end of the reinforcement member 160 is fixed by the reinforcement support member 140 (S 70);
When the curing of the concrete (C) of the excavation ball is completed, after dismantling the reinforcing member support 140, the casing support 130 and the out casing 120, while pulling out the casing (110) Pouring concrete (C ′) inside the excavation ball through T) (S 80); And
Step (S 90) to finish the pile by curing the concrete (C '); reinforcement in-situ site casting pile construction method characterized in that consisting of.
삭제delete 삭제delete 삭제delete
KR1020120033441A 2012-03-30 2012-03-30 Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile KR101375155B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120033441A KR101375155B1 (en) 2012-03-30 2012-03-30 Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120033441A KR101375155B1 (en) 2012-03-30 2012-03-30 Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile

Publications (2)

Publication Number Publication Date
KR20130111010A KR20130111010A (en) 2013-10-10
KR101375155B1 true KR101375155B1 (en) 2014-03-17

Family

ID=49632734

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120033441A KR101375155B1 (en) 2012-03-30 2012-03-30 Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile

Country Status (1)

Country Link
KR (1) KR101375155B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102082495B1 (en) * 2017-09-06 2020-02-28 한동덕 Low part cast in place pile construction method
KR102082496B1 (en) * 2017-09-06 2020-02-28 한동덕 Casing separating type cast in place pile construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100657176B1 (en) * 2004-07-08 2006-12-13 석운엔지니어링 주식회사 Extracting casing after lower part curing type cast-in-place pile method
KR100970440B1 (en) * 2009-12-03 2010-07-15 대한기초엔지니어링 주식회사 Beam penetrating after lower part casting type cast-in-place pile method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100657176B1 (en) * 2004-07-08 2006-12-13 석운엔지니어링 주식회사 Extracting casing after lower part curing type cast-in-place pile method
KR100970440B1 (en) * 2009-12-03 2010-07-15 대한기초엔지니어링 주식회사 Beam penetrating after lower part casting type cast-in-place pile method

Also Published As

Publication number Publication date
KR20130111010A (en) 2013-10-10

Similar Documents

Publication Publication Date Title
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR101302743B1 (en) Phc pile and its using the same soil cement wall construction methode
JP2009084919A (en) Ground excavating method
KR101394235B1 (en) Method for constructing complex pile for great soft ground
KR102248187B1 (en) Cast-in-place pile using reinforced grouting and construction method
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR100657176B1 (en) Extracting casing after lower part curing type cast-in-place pile method
JP2010037864A (en) Cast-in-place pile and construction method
KR100970440B1 (en) Beam penetrating after lower part casting type cast-in-place pile method
US20120301227A1 (en) Foundation pile and installing method thereof
KR101341260B1 (en) Method of reinforcing existing concrete footing structure using micropile
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
KR101375155B1 (en) Construction Method of Reinforced Bar Insert Type in-situ Concrete Pile
KR20100124028A (en) Construction method of lower end expanded type cast-in-place piles
KR102247848B1 (en) Cast-in-place pile using Pressurized grouting and construction method
CN108678042A (en) Miniature steel pipe pile for foundation stabilization and the method using its progress foundation stabilization
CN108086307A (en) Compound mini pile is perfused in concrete filled steel tube borehole
JP2016041893A (en) Pile foundation and pile foundation construction method
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
JP6326294B2 (en) Construction method of earth retaining structure
KR102082495B1 (en) Low part cast in place pile construction method
KR102277470B1 (en) Basement Composite Wall Using Retaing Wall And Method for Constructing the Same
JP5036775B2 (en) Construction method of cast-in-place concrete pile or cylindrical ground improvement body
KR20130073336A (en) Pile structure and construction methods

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
X091 Application refused [patent]
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170308

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180312

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190213

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20200212

Year of fee payment: 7