CN104775439B - A kind of pattern foundation pit supporting structure sealing integral structure and its construction method - Google Patents

A kind of pattern foundation pit supporting structure sealing integral structure and its construction method Download PDF

Info

Publication number
CN104775439B
CN104775439B CN201510185268.1A CN201510185268A CN104775439B CN 104775439 B CN104775439 B CN 104775439B CN 201510185268 A CN201510185268 A CN 201510185268A CN 104775439 B CN104775439 B CN 104775439B
Authority
CN
China
Prior art keywords
concrete
wall
supporting structure
foundation pit
pit supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510185268.1A
Other languages
Chinese (zh)
Other versions
CN104775439A (en
Inventor
邝利军
肖龙鸽
陈举飞
李继超
苏守
苏守一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Infrastructure Co Ltd
Original Assignee
China Construction South Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction South Investment Co Ltd filed Critical China Construction South Investment Co Ltd
Priority to CN201510185268.1A priority Critical patent/CN104775439B/en
Publication of CN104775439A publication Critical patent/CN104775439A/en
Application granted granted Critical
Publication of CN104775439B publication Critical patent/CN104775439B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention discloses a kind of pattern foundation pit supporting structure sealing integral structure and its construction method.The pattern foundation pit supporting structure sealing integral structure includes being arranged at the concrete wall below foundation ditch peripheral ground, is provided with the cylindrical reinforcing steel cage of multiple vertical placements in concrete walls body;The construction method of the pattern foundation pit supporting structure sealing integral structure, it is characterised in that comprise the following steps:Guide groove excavates, lead wall pours, groove section grooving, place steel reinforcement cage and the cast step such as concrete.The present invention not only has the characteristics of rigidity of diaphram wall is big, stagnant water effect is good, it may have Row Piles Supporting Structure steel reinforcement cage lays easily advantage, and technology difficulty is little, and quick construction, quality are easily controlled, and are particularly suited for rich water sand-pebble layer.

Description

A kind of pattern foundation pit supporting structure sealing integral structure and its construction method
Technical field
The present invention relates to the realm of building construction, more particularly to a kind of pattern foundation pit supporting structure sealing integral structure and its construction party Method.
Background technology
With the scale of underground space development increasing, under Complex Hydrogeological Conditions build the underground space by High in water level, permeability is big, and causes the situation of foundation pit supporting construction seepage commonplace, and quality is wayward, also gives underground The progress of main body structure construction causes difficulty.
Conventional vertical support system has campshed, hole-drilling interlocking pile, diaphram wall, cement soil wall etc. at present.Campshed Although watch box system low cost, discontinuous due to stake, will typically increase the measures of preventing water such as water-stop curtain could guarantee system Safe handling, has that many operations, occupied ground and permanent space are big, and stake and the combination of water sealing structure is present always Hidden danger, increases the way of curtain behind campshed, and stake is respectively integrated with curtain, and discontinuity needs Guan Liang between stake and stake Link, when curtain has leakage point behind the stake, be difficult to discover, it is also difficult to repair;Hole-drilling interlocking pile system, easily goes out in construction Existing stake position sideslip and the problem of cutting deformation, once stake position sideslip and deformation, influence whether bitten pile support system supporting and Stagnant water effect;Diaphram wall system supporting is safe and reliable, but amount of reinforcement is big, and places in groove section in constructing bulky Square steel reinforcement cage need to take up an area the big hanging device of big, lifting capacity, while for preventing square steel reinforcement cage deformation from will take two-shipper Lift operating type;Although cement wall support system seriality is preferably, can effective sealing, the intensity of soil cement is very low, The substantial amounts of shaped steel of increase and substantial amounts of anchor pole is generally required using in make up the deficiency of intensity, is not only economically wasted, and Construct below phreatic line substantial amounts of anchor pole, there is also certain potential safety hazard in work progress in itself.
Content of the invention
For overcoming the deficiencies in the prior art, the mesh of the present invention be to provide a kind of pattern foundation pit supporting structure sealing integral structure and its Construction method, its not only have diaphram wall rigidity big, the characteristics of stagnant water effect is good, also have Row Piles Supporting Structure steel reinforcement cage Easily advantage is laid, technology difficulty is little, and quick construction, quality are easily controlled, and are particularly suited for rich water sand-pebble layer, are not required to Individually construction water stop curtain structure is separately set.
For reaching above-mentioned purpose, technical scheme below is present invention employs:
A kind of pattern foundation pit supporting structure sealing integral structure, it include being arranged at the concrete wall below foundation ditch peripheral ground, The cylindrical reinforcing steel cage of multiple vertical placements is provided with concrete walls body.
A kind of construction method of pattern foundation pit supporting structure sealing integral structure, comprises the following steps:
1)Guide groove is excavated in earth's surface;
2)Wall is led groove sidewall casting concrete is led;
3)The earthwork is captured with chute forming machine in guide groove and form cuboid groove section, use mud off in cuboid groove section;
4)After cuboid groove section bottom scarfing cinder, cylindrical reinforcing steel cage is vertically placed in cuboid groove section and is fixed;
5)Cast conduit is transferred in cylindrical reinforcing steel cage, and carries out second clear bottom;
6)Concrete is poured into a mould until concrete liquid level is at the top of cuboid groove section by pouring into a mould conduit;
7)According to step 1)-6)Circulation construction, until form whole pattern foundation pit supporting structure water sealing structures.
Further, for the step 1), levelling of the land and surveying and locating will be first carried out before guide groove excavation, guide groove can use Hand excavation or mechanical equivalent of light excavation, channel widths=cuboid groove section width to be excavated+lead wall width.
Further, for the step 2), wall is led for reinforced concrete structure, first want assembling reinforcement and prop up before pouring Mould, it is highly 1000-1500mm to lead wall, leads wall top surface 50-100mm above ground level;Leading between wall every 1- after the completion of pouring 3m arranges interim wood support.
Further, for the step 4), by mud circulation cleaning bottom, sediment thickness is not more than 5cm, the cylinder Steel reinforcement cage can carry out step 1)-3)Shi Jinhang makes.
Further, for the step 5), 4~10 times for concrete coarse aggregate particle diameter of the cast catheter diameter.
Further, for the step 6), strength grade of concrete is not less than C20.
Beneficial effects of the present invention:(1)It is one that campshed, diaphram wall, water-stop curtain are closed three, makes full use of in groove section Concreting and the overall structure that formed reaches support water stop while the purpose realized;(2)Place by design pitch in groove section Cylindrical reinforcing steel cage, it is to avoid placed required for square steel reinforcement cage in groove section using conventional diaphram wall support system Take up an area the big hanging device of big, lifting capacity, while avoiding the double-machine lifting crane operation that takes for preventing square steel reinforcement cage deformation Mode;(3)Have grooving mechanization degree high using grooving machinery grooving, it is to avoid campshed formula supporting construction pore-forming easily collapses Hole, the impact in pore forming process between adjacent holes;(4)Compared with using support pile+water stop curtain structure form, it is to avoid operation Many, the big problem in occupied ground and permanent space;(5)Compared with hole-drilling interlocking pile, the requirement to concrete performance is relatively low, with When it also avoid because drilling dislocation caused by leakage problems.
Description of the drawings
Fig. 1 is step 1)Floor map;
Fig. 2 is step 1)Generalized section;
Fig. 3 is step 2)Floor map;
Fig. 4 is step 2)Generalized section;
Fig. 5 is step 3)Floor map;
Fig. 6 is step 3)Generalized section;
Fig. 7 is step 4)Floor map;
Fig. 8 is step 4)Generalized section;
Fig. 9 is step 6)Floor map;
Figure 10 is step 6)Generalized section.
In figure:1- concrete walls;2- cylindrical reinforcing steel cages;3- guide grooves;4- leads wall;5- cuboid groove sections;6- mud;7- Concrete;The 8- soil bodys.
Specific embodiment
As shown in figs. 9-10, a kind of pattern foundation pit supporting structure sealing integral structure, including being arranged at below foundation ditch peripheral ground Concrete wall 1, is provided with the cylindrical reinforcing steel cage 2 of multiple vertical placements in concrete wall 1.
As Figure 1-10 shows, a kind of construction method of pattern foundation pit supporting structure sealing integral structure, comprises the following steps:
1)Guide groove 3 is excavated in earth's surface;
2)Wall 4 is led groove sidewall casting concrete is led;
3)The earthwork is captured in guide groove with chute forming machine and forms cuboid groove section 5, use 6 retaining wall of mud in cuboid groove section 5;
4)After the 5 bottom scarfing cinder of cuboid groove section, cylindrical reinforcing steel cage 2 is vertically placed in cuboid groove section 5 and is fixed;
5)Cast conduit is transferred in cylindrical reinforcing steel cage 2, and carries out second clear bottom;
6)Concrete is poured into a mould until concrete liquid level is at the top of cuboid groove section by pouring into a mould conduit;
7)According to step 1)-6)Circulation construction, until form whole pattern foundation pit supporting structure water sealing structures.
For the step 1), levelling of the land and surveying and locating will be first carried out before the excavation of guide groove 3, guide groove can use hand excavation Or mechanical equivalent of light excavation, channel widths=treat box cut section width+lead wall width.
For the step 2), wall 4 is led for reinforced concrete structure, first wants assembling reinforcement formwork before pouring, lead wall high Spend for 1000-1500mm, lead wall top surface 50-100mm above ground level;Being led after the completion of pouring arrange every 1-3m between wall interim Wood support.
For the step 4), by mud circulation cleaning bottom, sediment thickness is not more than 5cm.
For the step 5), 4~10 times for concrete coarse aggregate particle diameter of the cast catheter diameter.
For the step 6), strength grade of concrete is not less than C20.

Claims (3)

1. a kind of construction method of pattern foundation pit supporting structure sealing integral structure, it is characterised in that the pattern foundation pit supporting structure sealing integration Structure includes being arranged at the concrete wall below foundation ditch peripheral ground(1), concrete wall(1)Inside it is interval with multiple vertical The cylindrical reinforcing steel cage of placement(2),
Construction method is comprised the following steps:
1)Guide groove is excavated in earth's surface(3);
2)Wall is led groove sidewall casting concrete is led(4);
3)The earthwork is captured with chute forming machine in guide groove form cuboid groove section(5), cuboid groove section(5)Interior use mud(6)Shield Wall;
4)Cuboid groove section(5)After the scarfing cinder of bottom, in cuboid groove section(5)Interior vertical placement cylindrical reinforcing steel cage(2)And it is fixed;
5)In cylindrical reinforcing steel cage(2)Interior decentralization cast conduit, and carry out second clear bottom;
6)Concrete is poured into a mould until concrete liquid level is at the top of cuboid groove section by pouring into a mould conduit;
7)According to step 1)-6)Circulation construction, until form whole pattern foundation pit supporting structure water sealing structures;For the step 1), guide groove (3)Levelling of the land and surveying and locating will be first carried out before excavation, and guide groove can use hand excavation or mechanical equivalent of light excavation, channel widths=wait out Digging cuboid groove section width+lead wall width;
For the step 2), lead wall(4)For reinforced concrete structure, assembling reinforcement formwork before pouring, is first wanted, lead wall height For 1000-1500mm, wall top surface 50-100mm above ground level is led;Leading after the completion of pouring arrange interim wood every 1-3m between wall Support;
For the step 4), by mud circulation cleaning bottom, sediment thickness is not more than 5cm, and the cylindrical reinforcing steel cage can enter Row step 1)-3)Shi Jinhang makes.
2. the construction method of a kind of pattern foundation pit supporting structure sealing integral structure according to claim 1, it is characterised in that for The step 5), 4~10 times for concrete coarse aggregate particle diameter of the cast catheter diameter.
3. the construction method of a kind of pattern foundation pit supporting structure sealing integral structure according to claim 1, it is characterised in that for The step 6), strength grade of concrete is not less than C20.
CN201510185268.1A 2015-04-20 2015-04-20 A kind of pattern foundation pit supporting structure sealing integral structure and its construction method Active CN104775439B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510185268.1A CN104775439B (en) 2015-04-20 2015-04-20 A kind of pattern foundation pit supporting structure sealing integral structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510185268.1A CN104775439B (en) 2015-04-20 2015-04-20 A kind of pattern foundation pit supporting structure sealing integral structure and its construction method

Publications (2)

Publication Number Publication Date
CN104775439A CN104775439A (en) 2015-07-15
CN104775439B true CN104775439B (en) 2017-03-15

Family

ID=53617179

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510185268.1A Active CN104775439B (en) 2015-04-20 2015-04-20 A kind of pattern foundation pit supporting structure sealing integral structure and its construction method

Country Status (1)

Country Link
CN (1) CN104775439B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105544556A (en) * 2015-12-29 2016-05-04 湖北中南勘察基础工程有限公司 Foundation pit supporting construction technology combining equal-thickness cement-soil diaphragm wall and tubular piles
CN105937218A (en) * 2016-04-27 2016-09-14 中国建筑第五工程局有限公司 Construction method of underground diaphragm wall
CN105970916B (en) * 2016-06-30 2019-05-03 中铁十八局集团第五工程有限公司 A kind of construction method of deep basal pit plain concrete diaphram wall
CN108049393A (en) * 2017-11-24 2018-05-18 中建铁投轨道交通建设有限公司 For the attached building enclosure construction technology in subway station under the conditions of rich water thick sand bed
CN110106888A (en) * 2019-04-02 2019-08-09 刘侨 It is a kind of to exempt from horizontally-supported self-stabilization type foundation pit enclosure support construction construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101343869A (en) * 2008-08-19 2009-01-14 上海建工股份有限公司 Underground continuous wall construction method of city-across pipeline
CN101487261A (en) * 2009-01-21 2009-07-22 浙江中成建工集团有限公司 Profiled bar freezing wall foundation ditch combined enclosure method and its structure
CN102220764A (en) * 2011-04-19 2011-10-19 威海建设集团股份有限公司 Deep foundation pit bracing system and construction method thereof
WO2012149670A1 (en) * 2011-04-30 2012-11-08 安徽省高速公路控股集团有限公司 Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN103469801A (en) * 2013-09-03 2013-12-25 上海建科工程咨询有限公司 Method for constructing foundation pit enclosure structure on basis of prefabricated ground walls
CN103615001A (en) * 2013-11-27 2014-03-05 宁波盛宏建设工程有限公司 Bored pile construction method for reinforcing cage framework layered installation
CN203684233U (en) * 2013-12-27 2014-07-02 中铁大桥局集团第一工程有限公司 Circular support structure for deep foundation pit
CN203878562U (en) * 2014-06-05 2014-10-15 北京住总集团有限责任公司 Underground diaphragm wall corner end blocking structure
WO2015019017A3 (en) * 2013-08-06 2015-04-09 Soletanche Freyssinet Sealing device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1136284A (en) * 1997-07-24 1999-02-09 Shimizu Corp Work execution method for underground continuous wall
TW201247971A (en) * 2011-05-24 2012-12-01 Dehan Intellectual Technology Co Ltd Building fundamental pile and construction method thereof

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101343869A (en) * 2008-08-19 2009-01-14 上海建工股份有限公司 Underground continuous wall construction method of city-across pipeline
CN101487261A (en) * 2009-01-21 2009-07-22 浙江中成建工集团有限公司 Profiled bar freezing wall foundation ditch combined enclosure method and its structure
CN102220764A (en) * 2011-04-19 2011-10-19 威海建设集团股份有限公司 Deep foundation pit bracing system and construction method thereof
WO2012149670A1 (en) * 2011-04-30 2012-11-08 安徽省高速公路控股集团有限公司 Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
WO2015019017A3 (en) * 2013-08-06 2015-04-09 Soletanche Freyssinet Sealing device
CN103469801A (en) * 2013-09-03 2013-12-25 上海建科工程咨询有限公司 Method for constructing foundation pit enclosure structure on basis of prefabricated ground walls
CN103615001A (en) * 2013-11-27 2014-03-05 宁波盛宏建设工程有限公司 Bored pile construction method for reinforcing cage framework layered installation
CN203684233U (en) * 2013-12-27 2014-07-02 中铁大桥局集团第一工程有限公司 Circular support structure for deep foundation pit
CN203878562U (en) * 2014-06-05 2014-10-15 北京住总集团有限责任公司 Underground diaphragm wall corner end blocking structure

Also Published As

Publication number Publication date
CN104775439A (en) 2015-07-15

Similar Documents

Publication Publication Date Title
CN104775439B (en) A kind of pattern foundation pit supporting structure sealing integral structure and its construction method
CN101672041B (en) Top-down construction method of large underground structure outer wall
CN101408025B (en) Pit construction method by using major structure as bearing point
CN106013053B (en) A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson
CN203320532U (en) Protection device of nearby pile foundation close to deep foundation pit
KR101545307B1 (en) Construction method of complex temporary facility with bottom grouting for weak ground
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN103806464B (en) Large-scale high ferro station and subway cross top-down construction method up and down
CN104264663A (en) Hard cutting construction technology for secant piles
CN108316283A (en) The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall
CN209923959U (en) Open caisson structure for dry-process operation of high-groundwater-level soft soil field
CN107059904A (en) A kind of underground pipe gallery ponding well excavation method
CN110424372A (en) Along road interval method in a row remove obstacles after construct diaphram wall construction method
CN207211158U (en) Assembled pile board wall foundation pit supporting construction
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN209585079U (en) The Yield rainfall relation building enclosure of beam is turned under a kind of subway station
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN207878451U (en) A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation
JP6326294B2 (en) Construction method of earth retaining structure
CN216108526U (en) Underground continuous wall structure for foundation pit support
AU2020100004B4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN210421152U (en) Anchor road shoulder retaining wall
CN216615879U (en) Arch ring supporting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200408

Address after: 100000 No. three Li River Road, Beijing, Haidian District, 9

Patentee after: CHINA CONSTRUCTION BASE BACILITIES Co.,Ltd.

Address before: 518022, room 13, building 2105, Zhongjian building, No. 1302 Shennan East Road, Shenzhen, Guangdong, Luohu District

Patentee before: CHINA CONSTRUCTION SOUTH INVESTMENT Co.,Ltd.