CN207878451U - A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation - Google Patents
A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation Download PDFInfo
- Publication number
- CN207878451U CN207878451U CN201820141455.9U CN201820141455U CN207878451U CN 207878451 U CN207878451 U CN 207878451U CN 201820141455 U CN201820141455 U CN 201820141455U CN 207878451 U CN207878451 U CN 207878451U
- Authority
- CN
- China
- Prior art keywords
- ground connection
- grouting
- ground
- wall
- connection wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本实用新型公开了一种采用坑底注浆地连墙控制基坑开挖影响的装置,包括设置在欲施工区域于保护区土体之间的地连墙,地连墙内设有多个测斜管,地连墙的位于欲施工区域的一侧的上部设有多道水平支撑和多个注浆管,多个注浆管在地连墙的长度方向上的位置与多个测斜管的位置一一对应。传统的支撑轴力伺服控制仅仅对开挖面以上的围护结构变形能够起到控制作用,对开挖面以下围护结构的变形缺乏有效控制,本实用新型采用坑底地连墙动态注浆,边开挖边注浆,使地连墙在变形很小的情况下,用注浆提供被动侧平衡压力,实现基坑内被动区的应力控制,从而对每次开挖时坑底围护结构的变形进行有效控制,操作方便,成本低廉。
The utility model discloses a device for controlling the influence of excavation of a foundation pit by adopting a ground connection wall grouted at the bottom of the pit, which comprises a ground connection wall arranged between the area to be constructed and the soil body in the protection area, and a plurality of ground connection walls are arranged in the ground connection wall. Inclinometer pipe, the upper part of the ground connection wall located on one side of the area to be constructed is provided with multiple horizontal supports and multiple grouting pipes, the position of the multiple grouting pipes in the length direction of the ground connection wall is related to the multiple inclinometers The positions of the tubes correspond one-to-one. The traditional servo control of supporting axial force can only control the deformation of the enclosure structure above the excavation surface, and lacks effective control of the deformation of the enclosure structure below the excavation surface. , grouting while excavating, so that the ground connection wall can provide passive side balance pressure with grouting under the condition of small deformation, so as to realize the stress control of the passive area in the foundation pit, so as to ensure the protection structure of the pit bottom during each excavation The deformation is effectively controlled, the operation is convenient and the cost is low.
Description
技术领域technical field
本实用新型涉及基坑工程施工技术领域,尤其涉及一种采用坑底注浆地连墙控制基坑开挖影响的装置。The utility model relates to the technical field of foundation pit engineering construction, in particular to a device for controlling the influence of foundation pit excavation by using a grouting ground connection wall at the bottom of the pit.
背景技术Background technique
随着城市的快速发展,城市地下隧道越来越多地投入运营,加之城市用地紧张,基坑周边的环境条件变得越来越复杂,深大基坑卸荷将对其位移场及周边环境设施带来不利影响,且基坑对周边环境所产生影响的变形控制标准也日益严格。基坑对周边环境的影响变形控制已由对邻近既有建筑物、道路、地下管线、立交桥等的厘米级变形控制要求,发展到对邻近已运营地铁、高铁、机场等的毫米级变形控制要求,尤其深基坑给基坑工程的变形控制理论、方法和技术提出挑战。支撑轴力伺服控制是控制基坑围护结构变形的常用方法,但支撑轴力伺服控制仅对开挖面以上的围护结构变形能够起到控制作用,对开挖面以下围护结构的变形缺乏有效控制。对于带支撑基坑,无论是每步开挖过程中,还是最终开挖完成时,基坑围护结构的最大位移往往是发生在最下一道支撑之下。因此,当隧道等邻近构筑物位于开挖面以下时,支撑轴力伺服控制对基坑底部围护结构的变形缺乏直接有效的控制。With the rapid development of the city, more and more urban underground tunnels are put into operation, coupled with the shortage of urban land, the environmental conditions around the foundation pit become more and more complex, and the unloading of deep and large foundation pits will affect the displacement field and the surrounding environment. The facilities have adverse effects, and the deformation control standards for the impact of foundation pits on the surrounding environment are becoming increasingly stringent. The impact of foundation pits on the surrounding environment and deformation control has been developed from centimeter-level deformation control requirements for adjacent existing buildings, roads, underground pipelines, overpasses, etc., to millimeter-level deformation control requirements for adjacent operating subways, high-speed rail, airports, etc. , especially the deep foundation pit poses challenges to the deformation control theory, method and technology of foundation pit engineering. The servo control of the supporting axial force is a common method to control the deformation of the enclosure structure of the foundation pit, but the servo control of the supporting axial force can only control the deformation of the enclosure structure above the excavation surface, and it can control the deformation of the enclosure structure below the excavation surface. Lack of effective control. For foundation pits with supports, the maximum displacement of the foundation pit enclosure usually occurs under the last support, no matter during each step of excavation or when the final excavation is completed. Therefore, when adjacent structures such as tunnels are located below the excavation surface, the servo control of the supporting axial force lacks direct and effective control over the deformation of the enclosure structure at the bottom of the foundation pit.
目前采用支撑轴力伺服控制对基坑围护结构周边土体的变形纠偏效果往往并不高效、经济,主要存在以下缺陷:At present, the servo control of the supporting axial force is often not effective and economical in correcting the deformation and deviation of the surrounding soil around the foundation pit enclosure structure, and the main defects are as follows:
第一,目前采取支撑轴力伺服控制仅对开挖面以上的围护结构变形能够起到控制作用,对开挖面以下围护结构的变形缺乏有效控制。First, the current servo control of the supporting axial force can only control the deformation of the enclosure structure above the excavation surface, and lacks effective control over the deformation of the enclosure structure below the excavation surface.
第二,在基坑开挖过程中支撑轴力伺服控制难以准确、及时、灵活地对围护结构变形进行控制和压力补偿。Second, it is difficult to accurately, timely and flexibly control and pressure-compensate the deformation of the enclosure structure during the excavation process of the foundation pit by the servo control of the supporting axial force.
因此,研发一种可控制围护结构土体变形同时可在开挖过程中准确、及时、灵活地进行压力补偿的装置是目前市场发展的迫切需求。Therefore, the development of a device that can control the soil deformation of the enclosure structure and can perform pressure compensation accurately, timely and flexibly during the excavation process is an urgent demand for the current market development.
实用新型内容Utility model content
本实用新型采用坑底地连墙动态注浆,实现基坑内底部土地被动区的应力控制,使地连墙在变形很小的情况下,用注浆提供被动侧土体的平衡压力。在埋有地连墙的土体中开挖基坑时,进行分层开挖。开挖之前,在地连墙中埋设测斜管。在基坑开挖过程中,对坑底的预制注浆点处进行注浆,用注浆向基坑底部的被动侧提供平衡压力,边开挖边注浆,通过观测测斜管显示的土体应变来控制基坑底部的变形满足要求。The utility model adopts the dynamic grouting of the ground connection wall at the bottom of the pit to realize the stress control of the ground passive area at the bottom of the foundation pit, so that the ground connection wall can provide the balance pressure of the passive side soil by grouting when the deformation of the ground connection wall is small. When excavating a foundation pit in the soil where the ground connection wall is buried, excavate in layers. Before excavation, the inclinometer pipe is buried in the ground connection wall. During the excavation of the foundation pit, grouting is carried out at the prefabricated grouting point at the bottom of the pit, and the grouting is used to provide balanced pressure to the passive side of the bottom of the foundation pit. The body strain is used to control the deformation of the bottom of the foundation pit to meet the requirements.
为了解决上述技术问题,本实用新型提出的一种采用坑底注浆地连墙控制基坑开挖影响的装置,包括设置在欲施工区域于保护区土体之间的地连墙,所述地连墙内设有多个测斜管,多个测斜管沿地连墙的长度按照间距为3~5m均布,所述地连墙的位于欲施工区域的一侧的上部设有多道水平支撑和多个注浆管,注浆管的个数与测斜管的个数相同,多个注浆管在地连墙的长度方向上的位置与多个测斜管的位置一一对应。In order to solve the above-mentioned technical problems, the utility model proposes a device for controlling the influence of foundation pit excavation by using the grouting ground wall at the bottom of the pit, which includes a ground wall arranged between the area to be constructed and the soil in the protection area. A plurality of inclinometer tubes are arranged in the ground connection wall, and the plurality of inclinometer tubes are evenly distributed along the length of the ground connection wall at intervals of 3 to 5 m. The number of grouting tubes is the same as the number of inclinometer tubes, and the positions of multiple grouting tubes in the length direction of the ground connection wall are the same as the positions of multiple inclinometer tubes. correspond.
进一步讲,本实用新型采用坑底注浆地连墙控制基坑开挖影响的装置,其中,所述注浆管的长度与地连墙的高度一致,所述注浆管的直径为100~300mm,所述注浆管选用PVC管。Further speaking, the utility model adopts a device for controlling the impact of foundation pit excavation by grouting the ground connection wall at the bottom of the pit, wherein the length of the grouting pipe is consistent with the height of the ground connection wall, and the diameter of the grouting pipe is 100- 300mm, the grouting pipe is made of PVC pipe.
所述测斜管的长度与地连墙的高度一致。The length of the inclinometer pipe is consistent with the height of the ground connection wall.
与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the utility model are:
(1)本实用新型可实现精细控制:通过控制在预制注浆点的注浆量,及时观察测斜管数值变化,实现对保护区土体变形的精细控制。(1) The utility model can realize fine control: by controlling the amount of grouting at the prefabricated grouting point and observing the value change of the inclinometer tube in time, the fine control of the deformation of the soil in the protected area can be realized.
(2)本实用新型可实现多次注浆:由于在不同深度位置处预留了多个预制注浆点,可在开挖过程中实现准确、及时、灵活地进行压力补偿来控制围护结构的土体变形。(2) The utility model can realize multiple grouting: due to the reservation of multiple prefabricated grouting points at different depths, accurate, timely and flexible pressure compensation can be realized during the excavation process to control the enclosure structure soil deformation.
附图说明Description of drawings
图1是本实用新型中地连墙施工示意图;Fig. 1 is the construction schematic diagram of ground connection wall in the utility model;
图2是基坑开挖后注浆立面示意图;Figure 2 is a schematic diagram of the grouting facade after excavation of the foundation pit;
图3是图2所示基坑开挖后注浆平面示意图;Fig. 3 is a schematic diagram of the grouting plane after excavation of the foundation pit shown in Fig. 2;
图4是下一级基坑开挖后注浆示意图。Fig. 4 is a schematic diagram of grouting after the excavation of the foundation pit of the next stage.
图中:1-欲施工区域,2-保护区土体,3-地连墙,4-测斜管,5-水平支撑,6-注浆管。In the figure: 1-area to be constructed, 2-soil in the protected area, 3-ground connection wall, 4-inclinometer pipe, 5-horizontal support, 6-grouting pipe.
具体实施方式Detailed ways
下面结合附图和具体实施例对本实用新型技术方案作进一步详细描述,所描述的具体实施例仅对本实用新型进行解释说明,并不用以限制本实用新型。The technical scheme of the utility model will be further described in detail below in conjunction with the accompanying drawings and specific embodiments, and the described specific embodiments are only for explaining the utility model, and are not intended to limit the utility model.
如图2和图3所示,本实用新型提出的一种采用坑底注浆地连墙控制基坑开挖影响的装置,包括设置在欲施工区域1于保护区土体2之间的地连墙3,所述地连墙3内设有多个测斜管4,多个测斜管4沿地连墙3的长度按照间距为3~5m均布,如图3所示,所述测斜管4的长度与地连墙3的高度一致。所述地连墙3的位于欲施工区域1的一侧的上部设有多道水平支撑5和多个注浆管6,注浆管6的个数与测斜管4的个数相同,如图3所示,多个注浆管6在地连墙3的长度方向上的位置与多个测斜管4的位置一一对应。如图2所示,所述注浆管6的长度与地连墙3的高度一致,所述注浆管6的直径为100~300mm,所述注浆管6选用PVC管。As shown in Figures 2 and 3, the utility model proposes a device for controlling the influence of excavation of foundation pits by using the grouting ground wall at the bottom of the pit. The connection wall 3, the ground connection wall 3 is provided with a plurality of inclinometer tubes 4, and the plurality of inclinometer tubes 4 are evenly distributed along the length of the ground connection wall 3 at intervals of 3 to 5 m, as shown in Figure 3, the The length of the inclinometer pipe 4 is consistent with the height of the ground connection wall 3 . The upper part of the ground connecting wall 3 on one side of the desired construction area 1 is provided with multiple horizontal supports 5 and a plurality of grouting pipes 6, and the number of the grouting pipes 6 is the same as the number of the inclinometer pipes 4, as As shown in FIG. 3 , the positions of the plurality of grouting pipes 6 in the length direction of the ground connection wall 3 are in one-to-one correspondence with the positions of the plurality of inclinometer pipes 4 . As shown in Figure 2, the length of the grouting pipe 6 is consistent with the height of the ground wall 3, the diameter of the grouting pipe 6 is 100-300mm, and the grouting pipe 6 is made of PVC pipe.
利用本实用新型提出的采用坑底注浆地连墙控制基坑开挖影响的装置进行注浆的方法,包括以下步骤:The method for grouting by using the device proposed by the utility model to control the influence of foundation pit excavation by using the bottom grouting wall to control the excavation of the foundation pit includes the following steps:
步骤一、测量放样后,根据测量放样的结果,开挖沟槽;Step 1. After the measurement and setting out, excavate the trench according to the results of the measurement and setting out;
测量放样包括定位定标控制点和导墙测量,在施工场地利于保护和放样的地方设置地面导线点,根据平面交接桩记录,采用全站仪将控制点引入场地内,放样出地面导线点的平面坐标。根据设计图纸提供的坐标计算出地连墙中心线角点坐标,采用地面导线控制点,用经纬仪实地放样出地连墙角点,并立即作好护桩。Measurement and stakeout includes positioning and calibration control points and guide wall measurement. Ground wire points are set at places on the construction site that are conducive to protection and stakeout. According to the record of plane transfer piles, the total station is used to introduce the control points into the site, and the ground wire points are staked out. plane coordinates. Calculate the corner point coordinates of the center line of the ground connection wall according to the coordinates provided by the design drawings, use the ground wire control points, use the theodolite to stake out the corner points of the ground connection wall on the spot, and immediately prepare the protective piles.
根据放样成果开挖沟槽,浇筑素混凝土底模垫层,绑扎钢筋,支模,最后浇筑导墙混凝土。在地连墙挖槽过程中,采用泥浆护壁保证槽壁的稳定,防止坍方。Excavate trenches according to lofting results, pour plain concrete base form cushion, tie steel bars, set up formwork, and finally pour guide wall concrete. During the excavation process of the ground connection wall, the mud retaining wall is used to ensure the stability of the groove wall and prevent collapse.
开挖沟槽包括:开挖槽段采用机械以“跳孔挖掘法”挖成单元施工槽段。挖槽土方外运。采取一边挖土一边装车外运。槽段质检,合理安排每槽段中各抓作业的顺序和抓数,保证槽壁两个方向的垂直度及装置安装良好,且满足成槽精度3‰的要求。The excavation trench includes: the excavation trench section is dug into a unit construction trench section by mechanical means "jump hole excavation method". Excavation of excavated earthwork. Take the soil while digging and loading it out. The quality inspection of the groove section reasonably arranges the sequence and number of grasping operations in each groove section to ensure the verticality of the two directions of the groove wall and the good installation of the device, and meets the requirement of 3‰ of groove forming accuracy.
清除沉积在槽底部的土碴淤泥,并置换槽内粘度、比重或含沙量过大的泥浆,使全槽泥浆都符合清底后泥浆的质量要求。根据现场情况合理选择吊刷,以保证刷面与接头面紧密接触从而达到清刷效果。Remove the soil silt deposited on the bottom of the tank, and replace the mud with excessive viscosity, specific gravity or sand content in the tank, so that the mud in the whole tank meets the quality requirements of the mud after bottom cleaning. Reasonably select the hanging brush according to the site conditions to ensure that the brush surface is in close contact with the joint surface to achieve the cleaning effect.
步骤二、根据设计要求制作钢筋笼,按照设计要求将多个测斜管4安设在钢筋笼上,采用铝制抽芯铆钉直径4mm连接接头与管体。选取合适的接头水密封型式防止混凝土浇筑时浆液漏入管内堵塞测斜管。将连接好的测斜管预先安装在钢筋笼内。安装位置除保证测斜要求外,应能保证可以安全躲开混凝土输送管底口并能避免振捣器直接撞击,以保护测斜管;必要时可在测斜管外加保护措施如护筋护环在管底和引出结构或地面处2m范围内要加保护钢筒,但保护措施不应对其它方面产生不利影响。定好安装位置的测斜管必须切实固定在钢筋笼上。一般选择较粗的主筋作为固定的依附对象,用软铁丝捆绑;相邻2个捆绑点的间距不宜超过1m。固定时还要使测斜管十字导槽中的一组在钢筋笼就位后处在测斜的±A方向上。Step 2: Make a reinforcement cage according to the design requirements, install a plurality of inclinometer tubes 4 on the reinforcement cage according to the design requirements, and use aluminum blind rivets with a diameter of 4mm to connect the joints and the pipe body. Select the appropriate joint water seal type to prevent the grout from leaking into the pipe and blocking the inclinometer pipe during concrete pouring. The connected inclinometer pipe is pre-installed in the steel cage. In addition to ensuring the requirements of the inclinometer, the installation position should be able to safely avoid the bottom opening of the concrete delivery pipe and avoid the direct impact of the vibrator to protect the inclinometer pipe; if necessary, additional protective measures such as rib protection The ring should be protected by a steel cylinder within 2m of the bottom of the pipe and the lead-out structure or the ground, but the protection measures should not have adverse effects on other aspects. The inclinometer tube with the fixed installation position must be firmly fixed on the steel cage. Generally, the thicker main reinforcement is selected as the fixed attachment object and bound with soft iron wire; the distance between two adjacent binding points should not exceed 1m. When fixing, one group of the cross guide grooves of the inclinometer pipe should be in the ±A direction of the inclinometer after the steel cage is in place.
钢筋笼吊装就位时,应注意保持附于其上的测斜管4基本顺直,避免过大弯曲;并必须在测斜管4内灌注清水以克服浮力和防止护壁泥浆渗入,或防止浇注时水泥浆液渗入。钢筋笼就位后应将测斜管4管口暂时封闭,以防异物进入。When the reinforcement cage is hoisted in place, care should be taken to keep the inclinometer tube 4 attached to it basically straight and avoid excessive bending; and clear water must be poured into the inclinometer tube 4 to overcome buoyancy and prevent wall mud from infiltrating, or to prevent pouring When the cement grout penetrates. After the reinforcement cage is in place, the mouth of the inclinometer tube 4 should be temporarily closed to prevent foreign matter from entering.
步骤三、成墙混凝土浇筑,根据设计要求选择合适的混凝土配比。在钢筋笼入槽4小时内开始浇灌混凝土。在混凝土浇注完成尚未凝固时,打开测斜管4的管口不断检查测斜管4内是否充满清水,必要时进行注水,以保证在混凝土凝固前测斜管4管内清水为满水位。并可以在管口适当用重物加压,帮助克服上浮力。当达到设计注浆量后停止注浆。混凝土凝固后,必须用适当压力的清水洗孔,冲尽测斜管管底的沉积物,使测斜管管中上下全被清水置换,保持全管畅通。混凝土凝固后形成其中设置有一排测斜管4的地连墙3,如图1所示。将测斜管4的管内全部置换为清水;Step 3: Pour the concrete into the wall, and select the appropriate concrete ratio according to the design requirements. Start pouring concrete within 4 hours of the reinforcement cage being placed in the groove. When the concrete pouring is completed and has not yet solidified, open the mouth of the inclinometer tube 4 to constantly check whether the inclinometer tube 4 is full of clear water, and inject water if necessary to ensure that the clear water in the inclinometer tube 4 is full before the concrete solidifies. And it can be properly pressurized with heavy objects at the mouth of the nozzle to help overcome the buoyancy. Stop grouting when the designed grouting volume is reached. After the concrete is solidified, the hole must be washed with water of appropriate pressure to flush out the sediment at the bottom of the inclinometer tube, so that the upper and lower parts of the inclinometer tube are replaced by clean water to keep the whole tube unblocked. After the concrete is solidified, a ground connection wall 3 with a row of inclinometer tubes 4 is formed, as shown in FIG. 1 . All the pipes of the inclinometer pipe 4 are replaced with clear water;
步骤四、沿地连墙3长度方向安设一排与多个测斜管位置一一对应的注浆管6,如图2和图3所示。Step 4: Install a row of grouting pipes 6 corresponding to the positions of the multiple inclinometer pipes along the length direction of the ground connection wall 3, as shown in Fig. 2 and Fig. 3 .
步骤五、基坑开挖,开挖基坑时,向注浆管6内注浆,通过观察测斜管4的数值变化来控制保护区土体变形,以满足土体变形要求。随着基坑开挖深度的加深,在所述地连墙3的位于基坑的一侧的上部增设水平支撑5,如图2和图4所示。同时,清除开挖面以上的注浆管6,根据工程需要继续在开挖面以下注浆,以保证土体变形要求;重复上述操作直至基坑开挖完成。Step 5: Excavation of the foundation pit. When excavating the foundation pit, grout is injected into the grouting pipe 6, and the deformation of the soil in the protected area is controlled by observing the value change of the inclinometer pipe 4 to meet the requirements of soil deformation. As the excavation depth of the foundation pit deepens, a horizontal support 5 is added on the upper part of the ground connection wall 3 on one side of the foundation pit, as shown in FIGS. 2 and 4 . At the same time, remove the grouting pipe 6 above the excavation surface, and continue grouting below the excavation surface according to engineering needs to ensure soil deformation requirements; repeat the above operations until the excavation of the foundation pit is completed.
注浆完成后将水管插至注浆管底,清洗管内残留浆液,以备重复注浆。After the grouting is completed, insert the water pipe to the bottom of the grouting pipe, and clean the residual grout in the pipe for repeated grouting.
传统的支撑轴力伺服控制仅仅对开挖面以上的围护结构变形能够起到控制作用,对开挖面以下围护结构的变形缺乏有效控制,本实用新型可以实现坑底地连墙动态注浆,边开挖边注浆,使地连墙在变形很小的情况下,用注浆提供被动侧平衡压力,实现基坑内被动区的应力控制,从而对每次开挖时坑底围护结构的变形进行有效控制,操作方便,成本低廉。The traditional servo control of supporting axial force can only control the deformation of the enclosure structure above the excavation surface, but lacks effective control over the deformation of the enclosure structure below the excavation surface. Grouting and grouting while excavating, so that the ground connection wall can be used to provide passive side balance pressure with grouting under the condition of small deformation, so as to realize the stress control of the passive area in the foundation pit, so as to protect the bottom of the pit during each excavation The deformation of the structure is effectively controlled, and the operation is convenient and the cost is low.
尽管上面结合附图对本实用新型进行了描述,但是本实用新型并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,而不是限制性的,本领域的普通技术人员在本实用新型的启示下,在不脱离本实用新型宗旨的情况下,还可以做出很多变形,这些均属于本实用新型的保护之内。Although the utility model has been described above in conjunction with the accompanying drawings, the utility model is not limited to the above-mentioned specific embodiments, and the above-mentioned specific embodiments are only illustrative, rather than restrictive. Under the enlightenment of the utility model, many deformations can be made without departing from the purpose of the utility model, and these all belong to the protection of the utility model.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201820141455.9U CN207878451U (en) | 2018-01-25 | 2018-01-25 | A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201820141455.9U CN207878451U (en) | 2018-01-25 | 2018-01-25 | A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN207878451U true CN207878451U (en) | 2018-09-18 |
Family
ID=63508562
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201820141455.9U Active CN207878451U (en) | 2018-01-25 | 2018-01-25 | A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN207878451U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108316283A (en) * | 2018-01-25 | 2018-07-24 | 天津大学 | The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall |
| CN109797750A (en) * | 2019-03-29 | 2019-05-24 | 长安大学 | A kind of system and method obstructing influence of foundation excavation |
| CN116183440A (en) * | 2023-03-10 | 2023-05-30 | 中交第二公路勘察设计研究院有限公司 | A device for testing the rheological properties of foam concrete and its evaluation method |
| CN120174877A (en) * | 2025-05-23 | 2025-06-20 | 上海建工一建集团有限公司 | Precise control method of micro-deformation of deep foundation pit |
-
2018
- 2018-01-25 CN CN201820141455.9U patent/CN207878451U/en active Active
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108316283A (en) * | 2018-01-25 | 2018-07-24 | 天津大学 | The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall |
| CN109797750A (en) * | 2019-03-29 | 2019-05-24 | 长安大学 | A kind of system and method obstructing influence of foundation excavation |
| CN109797750B (en) * | 2019-03-29 | 2024-01-02 | 长安大学 | System and method for blocking foundation pit excavation influence |
| CN116183440A (en) * | 2023-03-10 | 2023-05-30 | 中交第二公路勘察设计研究院有限公司 | A device for testing the rheological properties of foam concrete and its evaluation method |
| CN120174877A (en) * | 2025-05-23 | 2025-06-20 | 上海建工一建集团有限公司 | Precise control method of micro-deformation of deep foundation pit |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112253162B (en) | Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method | |
| CN108442382B (en) | In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method | |
| CN104612162B (en) | A kind of Deep Foundation Pit of Metro Stations excavation construction method | |
| CN108914931B (en) | An assembled vertical shield ring foundation pile and construction method | |
| CN105133627B (en) | Construction under single wall steel sheet-pile cofferdam flowing water state | |
| CN108316283A (en) | The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall | |
| US20140026518A1 (en) | Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts | |
| CN105756091B (en) | A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings | |
| CN207878451U (en) | A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation | |
| CN112663600A (en) | Construction method of cast-in-situ bored pile for water-rich sandy stratum | |
| CN112554198A (en) | Construction method of deep foundation pit protection structure next to high-rise building | |
| CN105570534A (en) | Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method | |
| CN104264683B (en) | Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition | |
| CN116591148A (en) | Construction method of underground diaphragm wall system | |
| CN110055973B (en) | Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method | |
| CN113266392B (en) | A construction method of pipe jacking through existing anchor cable groups | |
| CN114837213A (en) | Tower crane foundation structure and construction method thereof | |
| CN114232602A (en) | Underground continuous pile construction process | |
| CN106758759A (en) | A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed | |
| CN113216215A (en) | Deep groove support reverse construction method in complex environment | |
| CN107299640A (en) | A kind of variable cross-section well shaft type ground continuous wall base and its construction method | |
| CN212104111U (en) | Foundation pit support next to super deep foundation pit of super high-rise subway | |
| CN209941754U (en) | High-voltage power pipe culvert in-situ protection structure | |
| CN210141142U (en) | Underground structure is built in same direction as digging in hole stake secret | |
| CN219158994U (en) | A foundation pit support structure for ultra-deep and large-diameter circular pipe-jacking wells in deep soft soil areas |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |