US20080028779A1 - Method for controlling electronic expansion valve of air conditioner - Google Patents
Method for controlling electronic expansion valve of air conditioner Download PDFInfo
- Publication number
- US20080028779A1 US20080028779A1 US11/832,216 US83221607A US2008028779A1 US 20080028779 A1 US20080028779 A1 US 20080028779A1 US 83221607 A US83221607 A US 83221607A US 2008028779 A1 US2008028779 A1 US 2008028779A1
- Authority
- US
- United States
- Prior art keywords
- eev
- pulse frequency
- air conditioner
- opening pulse
- indoor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims abstract description 23
- 238000001816 cooling Methods 0.000 claims abstract description 23
- 238000010438 heat treatment Methods 0.000 claims abstract description 20
- 239000003507 refrigerant Substances 0.000 description 25
- 230000004044 response Effects 0.000 description 10
- 238000007796 conventional method Methods 0.000 description 6
- 230000006870 function Effects 0.000 description 6
- 239000007788 liquid Substances 0.000 description 4
- 230000008439 repair process Effects 0.000 description 4
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000012545 processing Methods 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000001704 evaporation Methods 0.000 description 1
- 230000008020 evaporation Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 229920006395 saturated elastomer Polymers 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B41/00—Fluid-circulation arrangements
- F25B41/30—Expansion means; Dispositions thereof
- F25B41/31—Expansion valves
- F25B41/34—Expansion valves with the valve member being actuated by electric means, e.g. by piezoelectric actuators
- F25B41/345—Expansion valves with the valve member being actuated by electric means, e.g. by piezoelectric actuators by solenoids
- F25B41/347—Expansion valves with the valve member being actuated by electric means, e.g. by piezoelectric actuators by solenoids with the valve member being opened and closed cyclically, e.g. with pulse width modulation
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B49/00—Arrangement or mounting of control or safety devices
- F25B49/02—Arrangement or mounting of control or safety devices for compression type machines, plants or systems
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B13/00—Compression machines, plants or systems, with reversible cycle
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2313/00—Compression machines, plants or systems with reversible cycle not otherwise provided for
- F25B2313/027—Compression machines, plants or systems with reversible cycle not otherwise provided for characterised by the reversing means
- F25B2313/02741—Compression machines, plants or systems with reversible cycle not otherwise provided for characterised by the reversing means using one four-way valve
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2500/00—Problems to be solved
- F25B2500/06—Damage
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2500/00—Problems to be solved
- F25B2500/19—Calculation of parameters
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2500/00—Problems to be solved
- F25B2500/26—Problems to be solved characterised by the startup of the refrigeration cycle
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2600/00—Control issues
- F25B2600/25—Control of valves
- F25B2600/2513—Expansion valves
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2700/00—Sensing or detecting of parameters; Sensors therefor
- F25B2700/21—Temperatures
- F25B2700/2104—Temperatures of an indoor room or compartment
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F25—REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
- F25B—REFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
- F25B2700/00—Sensing or detecting of parameters; Sensors therefor
- F25B2700/21—Temperatures
- F25B2700/2106—Temperatures of fresh outdoor air
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B30/00—Energy efficient heating, ventilation or air conditioning [HVAC]
- Y02B30/70—Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating
Definitions
- FIG. 1 a typical air conditioner has a structure illustrated in FIG. 1 .
- the typical air conditioner is largely divided into an outdoor unit 110 and an indoor unit 120 .
- the outdoor unit 110 includes a compressor 111 , a four-way valve 112 , an outdoor heat exchanger 113 , an electronic expansion valve (EEV) 114 , an accumulator 115 and an outdoor fan 116 .
- the indoor unit 120 includes an indoor heat exchanger 121 and an indoor fan 123 .
- a high-temperature and high-pressure gaseous refrigerant compressed in the compressor 111 is introduced, via the four-way valve 112 , into the outdoor heat exchanger 113 that functions as a condenser.
- This high-pressure gaseous refrigerant undergoes heat exchange, through the outdoor heat exchanger 113 , with outdoor air, whose temperature is lower than the refrigerant temperature, to be condensed to a high pressure state.
- the outdoor fan 116 is driven by an outdoor fan motor (not shown), and serves to forcibly ventilate the outdoor air.
- the indoor fan 123 is driven by an indoor fan motor (not shown), and serves to forcibly ventilate the indoor air.
- the refrigerant flow direction at the four-way valve 112 is reversed, so the refrigerant flows in an opposite direction from the refrigerant flow during the cooling operation set forth above.
- the indoor heat exchanger 121 functions as a condenser differently from the cooling operation, warm air is circulated again into the indoor environment by the indoor fan 123 .
- the refrigerant flow during the heating operation of the air conditioner follows the circulation line: for example, “the compressor 111 ⁇ the four-way valve 112 ⁇ the indoor heat exchanger 121 ⁇ the EEV 114 ⁇ the outdoor heat exchanger 113 ⁇ the four-way valve 112 ⁇ the accumulator 115 ⁇ the compressor 111 ”.
- the EEV employed in the air conditioner with the refrigerant circulation line described above offers the functions of converting condensed liquid refrigerant introduced from the outdoor heat exchanger (condenser) into low-temperature and low-pressure liquid refrigerant by throttling, and then sending it to the indoor heat exchanger (evaporator); and adjusting an amount of refrigerant to be circulated.
- a heating mode it provides the like functions of the cooling mode by circulating the refrigerant in the opposite direction of the cooling mode.
- the air conditioner starts running with the EEV being closed. That is, an initial value of the opening level of the EEV is zero pulses/sec. Since the air conditioner starts running at the definite initial value of zero pulses/sec, convenience in control of the opening level of the EEV is secured.
- One of conventional methods to control the opening level of EEV is to let the air conditioner to operate with the EEV being completely closed in the initial phase of a start-up, and then to change the opening level to a reference opening level (reference opening pulse frequency) that is calculated based on an indoor heat load.
- a reference opening level reference opening pulse frequency
- the EEV in the conventional method of controlling the start-up of the air conditioner in the state that the EEV is completely closed in the initial phase of the start-up, the EEV must be opened forcibly by using a separate jig at the time of refrigerant injection or for vacuum work in the production line, which not only complicates work processing but also increases the number of work processes to thereby lower productivity because.
- a trip phenomenon is more likely to occur. That is, when the air conditioner stops momentarily due to a sudden power interruption and restarts its normal operation, sufficient torque of a compressor motor cannot be obtained because there is still a pressure difference, which causes a trip to the motor.
- an object of the present invention to provide a method for controlling an EEV of an air conditioner, which opens the EEV completely at the same time as power is applied, closes the EEV completely in response to an operation start signal, and adaptively controls the opening level of the EEV based on a calculated reference opening pulse frequency (reference opening level).
- an electronic expansion valve in an air conditioner using a compressor, the method including the steps of:
- FIG. 1 shows an overall structural view of a typical air conditioner system
- FIG. 2 illustrates a block diagram of an operation control device of an air conditioner suitable for applying thereto a method for controlling an EEV in the air conditioner in accordance with an embodiment of the present invention
- FIG. 3 is a flowchart illustrating a procedure for adaptively controlling an opening level of the EEV in the air conditioner in accordance with the present invention.
- FIG. 4 depicts a timing chart for explaining a procedure of gradually conducting a start-up control of the EEV in the air conditioner with the elapse of time in accordance with the present invention.
- the present invention controls an opening level of the EEV in the air conditioner in a manner that an EEV of an air conditioner is completely open in response to power-on, completely closed when an operation start signal is inputted, and then controlled adaptively (i.e., in a stepwise manner or gradually) based on a reference opening pulse frequency (reference opening level) calculated on the basis of indoor heat load, etc.
- a reference opening pulse frequency reference opening level
- the indoor temperature sensor 202 is installed at, e.g., a specific position of an indoor unit 120 shown in FIG. 1 , to measure an indoor temperature. The measured indoor temperature is then forwarded to the control block 208 .
- the outdoor temperature sensor 204 is installed at, e.g., a specific position of an outdoor unit 110 shown in FIG. 1 , to measure an outdoor temperature. The measured outdoor temperature is then delivered to the control block 208 .
- the manipulation block 206 has a plurality of manipulation keys that are arranged for allowing a user to input various operation information such as power-on, operation mode (cooling operation mode, heating operation mode, etc.), target temperature, target air volume and the like.
- operation information such as power-on, operation mode (cooling operation mode, heating operation mode, etc.), target temperature, target air volume and the like.
- operation information received from the user is transferred to the control block 208 .
- the control block 208 includes, e.g., a microprocessor and the like, to carry out the overall operation control of the air conditioner, and determines calibration coefficients for the indoor temperature, for the outdoor temperature and for a difference between the indoor temperature and the target temperature.
- a microprocessor and the like to carry out the overall operation control of the air conditioner, and determines calibration coefficients for the indoor temperature, for the outdoor temperature and for a difference between the indoor temperature and the target temperature.
- pre-stored in the form of tables are calibration coefficients for the indoor temperature, for the outdoor temperature and for a difference between the indoor temperature and the target temperature.
- control block 208 calculates the indoor heat load based on a preset cooling capacity, a preset heating capacity, and each of the calibration coefficients determined; and then calculates a reference opening pulse frequency of the EEV in each mode (i.e., reference opening pulse frequencies in the cooling and the heating mode) based on the calculated indoor heat load, the indoor and the outdoor temperature, and a reference operating frequency of a compressor.
- the control block 208 adaptively (in a stepwise manner or gradually) controls the opening level of the EEV on the basis of the calculated reference opening pulse frequency.
- the cooling and the heating capacity are fixed values depending on the capacity of the indoor unit.
- control block 208 completely opens the EEV having been closed at the same time as the power is applied, completely closes the EEV when an operation start signal is inputted by a user (or by an advance setting), and in a stepwise manner or gradually controls the opening level of the EEV based on the calculated reference opening pulse frequency. More details on this procedure will be provided with reference to FIG. 3 later.
- control block 208 carries out its normal functions, i.e., selectively generating any of control signals for driving the indoor fan, the outdoor fan, the compressor and so forth, and providing the same to each corresponding component.
- the EEV driving block 210 controls the opening level of the EEV 114 shown in FIG. 1 , in response to opening level control signals provided from the control block 208 . More concretely, the EEV driving block 210 completely opens the EEV 114 in response to an open control signal from the control block 208 when a power is turned on; completely closes the EEV 114 in response to a close control signal from the control block 208 when an operation start signal is inputted; and in a stepwise manner or gradually increases the opening level of the EEV up to the reference opening level under the control of the control block 208 .
- FIG. 3 is a flowchart illustrating a method for adaptively controlling an opening level of an EEV in an air conditioner in accordance with the present invention.
- step S 306 when a power-on signal is inputted by a user while an air conditioner is on a stand-by mode (stand-by power mode), item, if a power-on signal is inputted from the manipulation block 206 (steps S 302 and S 304 ), the control block 208 generates, in response to the power-on signal, an open control signal for completely opening the EEV 114 shown in FIG. 1 , and sends the generated open control signal to the EEV driving block 210 . In response to this, the EEV driving block 210 generates a driving signal for completely opening the EEV 114 to thereby completely open the EEV 114 (step S 306 ).
- the control block 208 checks whether an operation start signal is inputted (step S 308 ) As a result of the checking, if the operation start signal is inputted, the control block 208 generates a close control signal for completely closing the EEV 114 and sends the generated close control signal to the EEV driving block 210 . In response to this, the EEV driving block 210 generates a driving signal for completely closing the EEV 114 , thereby fully closing the EEV 114 (step S 310 ). At this time, an opening pulse frequency of the EEV 114 is zero pulse/sec (initial value).
- the indoor temperature sensor 202 measures an indoor temperature (indoor air temperature) T ai and provides it to the control block 208
- the outdoor temperature sensor 204 measures an outdoor temperature (outdoor air temperature) T ao and offers it to the control block 208 (step S 312 ).
- control block 208 determines calibration coefficients FT ai for the indoor temperature, FT ao for the outdoor temperature and FdT for a difference dT between the indoor temperature and a target temperature (user set temperature) with reference to tables of calibration coefficients pre-stored in the memory block 209 (step S 314 ).
- each of the calibration coefficients is used for adjusting the reference opening level of the EEV 114 .
- the memory block 209 stores calibration coefficients made in the form of table.
- those calibration coefficients may be defined as shown in Tables 1 to 3.
- Table 1 shows an example list of calibration coefficients for indoor temperatures in both cooling and heating operation modes
- Table 2 represents an example list of calibration coefficients for outdoor temperatures in both cooling and heating operation modes
- Table 3 depicts an example list of calibration coefficients for differences between the indoor temperatures and target temperatures in both cooling and heating operation modes.
- control block 208 calculates indoor cooling/heating load Q by Equation 1 based on the preset cooling capacity Q c , the preset heating capacity Q h , the calibration coefficient FT ai for the indoor temperature, the calibration coefficient FT ao for the outdoor temperature, and the calibration coefficient FdT for the difference between the indoor temperature and the target temperature (step S 316 ).
- the control block 208 calculates a reference opening pulse frequency P b,c of the EEV in a cooling mode and a reference opening pulse frequency P b,h of the EEV in a heating mode by using Equations 2 and 3, respectively, based on the indoor heat load Q obtained from Equation 1, a reference operating frequency F b of the compressor, the indoor temperature T ai , and the outdoor temperature T ao (step S 318 ).
- the indoor and the outdoor temperature are required to be calculated in absolute temperatures. Or, errors may occur in substituting them to Equations 2 and 3 when they are sub-zero temperatures.
- the opening pulse frequency of the EEV in the air conditioner approximately ranges from 70 pulses/sec to 280 pulses/sec. Therefore, during the operation of the air conditioner, the control block 208 calculates the reference opening pulse frequency of the EEV within the range from about 70 pulses/sec to 280 pulses/sec, and adjusts the opening level of the EEV based on the calculated reference opening pulse frequency.
- the reference opening pulse frequency for adjusting the opening level of the EEV is calculated through the above-described procedure.
- the control block 208 gradually controls or in a stepwise manner the opening level of the EEV by using the reference opening pulse frequency.
- the opening level of the EEV can be controlled in a stepwise manner through a four-stage EEV opening pulse control (e.g., four stages having operating pulse frequencies of 0.7 ⁇ P b , 0.8 ⁇ P b , 0.9 ⁇ P b and 1.1 ⁇ P b , respectively, and each stage having a duration of one minute) until it reaches the reference opening pulse frequency P b (step S 320 ).
- the procedure of the invention enters a steady state control after a start-up control of the EEV is performed in four minutes by increasing the opening pulse frequency at every one minute based on the reference opening pulse frequency.
- the start-up control is carried out at a first start-up pulse frequency which is obtained by multiplying the reference opening pulse frequency by 0.7.
- the start-up control is conducted at a second start-up pulse frequency which is obtained by multiplying the reference opening pulse frequency by 0.8.
- the start-up control is performed at a third start-up pulse frequency which is obtained by multiplying the reference opening pulse frequency by 0.9.
- the start-up control is carried out at a fourth start-up pulse frequency which is obtained by multiplying the reference opening pulse frequency by 1.1 (which is a higher opening pulse frequency pulse than the reference opening pulse frequency).
- the reason for setting the opening pulse frequency of the EEV at the fourth stage to be higher than the reference opening pulse frequency P b is to prevent a rapid increase in a discharge pressure of the compressor in case the operating frequency of the compressor reaches its maximum level only after three minutes following the start-up of the compressor in overload or full load condition.
- the EEV is completely open when only a power is turned on, and thus a repair technician can more easily connect a vacuum pump to inject refrigerant, thereby realizing quick after-sales service.
- the EEV automatically opens to full extent to maintain pressure equilibrium. Therefore, a trip phenomenon that may occur due to insufficient torque of a compressor motor caused by difference in pressure can be effectively prevented.
- the start-up of the EEV is controlled by changing in a stepwise manner the opening level of the EEV until it reaches the reference opening pulse frequency through four stages (e.g., 0.7 ⁇ P b , 0.8 ⁇ P b , 0.9 ⁇ P b and 1.1 ⁇ P b ), the embodiment is only for illustrative purposes, and the present invention is not limited thereto. If needed or depending on application, the opening level of the EEV may be classified into and controlled through more than four stages (e.g., five, six, seven, eight stages and so on), and it is apparent that the start-up operation of the EEV can be controlled even more smoothly through the use of the above scheme.
- the opening level of the EEV may be classified into and controlled through more than four stages (e.g., five, six, seven, eight stages and so on), and it is apparent that the start-up operation of the EEV can be controlled even more smoothly through the use of the above scheme.
- the air conditioner is driven evenly for one minute at each of the four stages of the opening level of the EEV, the embodiment is only for illustrative purposes, and the present invention is not limited thereto. It is apparent that the time period can be increased or decreased in consideration of various factors, such as, surrounding environment of the air conditioner. It is also noted that the running time of the air conditioner at each stage can be set differently whenever needed or depending on application.
- calibration coefficients for an indoor temperature, for an outdoor temperature and for a difference in temperature are read out from the pre-stored tables
- the embodiment is only for illustrative purposes, and the present invention is not limited thereto. It is apparent that the calibration coefficients may be calculated in real time mode, instead of being pre-stored in the tables.
- the present invention controls an opening level of an EEV in an air conditioner in a manner that the EEV of the air conditioner is completely open in response to power-on, completely closed when an operation start signal is inputted and then controlled adaptively (in a stepwise manner or gradually) based on a reference opening pulse frequency (a reference opening level) calculated on the basis of indoor heat load, etc.
- a simplified processing in manufacturing procedure associated with refrigerant injection and a quick after-sales service can be realized.
- a trip phenomenon that may occur due to insufficient torque of a compressor motor caused by a difference in pressure in restart-up after stop can be effectively prevented.
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Mechanical Engineering (AREA)
- Thermal Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Air Conditioning Control Device (AREA)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2006-0073556 | 2006-08-04 | ||
KR1020060073556A KR100785979B1 (ko) | 2006-08-04 | 2006-08-04 | 공기 조화기의 전자 팽창 밸브 제어 방법 |
Publications (1)
Publication Number | Publication Date |
---|---|
US20080028779A1 true US20080028779A1 (en) | 2008-02-07 |
Family
ID=38997383
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/832,216 Abandoned US20080028779A1 (en) | 2006-08-04 | 2007-08-01 | Method for controlling electronic expansion valve of air conditioner |
Country Status (5)
Country | Link |
---|---|
US (1) | US20080028779A1 (ko) |
EP (1) | EP2047185A1 (ko) |
KR (1) | KR100785979B1 (ko) |
CN (1) | CN101495824A (ko) |
WO (1) | WO2008016228A1 (ko) |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110232311A1 (en) * | 2010-03-23 | 2011-09-29 | Mitsubishi Electric Corporation | Multi-room air conditioning apparatus |
US20120172724A1 (en) * | 2010-12-31 | 2012-07-05 | Hill Anthony D | Automatic identification of intracardiac devices and structures in an intracardiac echo catheter image |
US20130227984A1 (en) * | 2012-03-05 | 2013-09-05 | Honda Motor Co., Ltd. | Air conditioner for vehicle |
US20140180483A1 (en) * | 2012-12-20 | 2014-06-26 | Automotive Research & Testing Center | Intelligent thermostatic control method and device for an air conditioner blowing cold and hot air |
US8925793B2 (en) | 2012-01-05 | 2015-01-06 | Dunan Microstaq, Inc. | Method for making a solder joint |
US8956884B2 (en) | 2010-01-28 | 2015-02-17 | Dunan Microstaq, Inc. | Process for reconditioning semiconductor surface to facilitate bonding |
US8996141B1 (en) | 2010-08-26 | 2015-03-31 | Dunan Microstaq, Inc. | Adaptive predictive functional controller |
US9006844B2 (en) | 2010-01-28 | 2015-04-14 | Dunan Microstaq, Inc. | Process and structure for high temperature selective fusion bonding |
US20150247661A1 (en) * | 2012-11-21 | 2015-09-03 | Mitsubishi Electric Corporation | Air-conditioning apparatus |
US9140613B2 (en) | 2012-03-16 | 2015-09-22 | Zhejiang Dunan Hetian Metal Co., Ltd. | Superheat sensor |
US9188375B2 (en) | 2013-12-04 | 2015-11-17 | Zhejiang Dunan Hetian Metal Co., Ltd. | Control element and check valve assembly |
US20150362236A1 (en) * | 2013-02-04 | 2015-12-17 | Hangzhou Sanhua Research Institute Co., Ltd. | Electronic expansion valve and control method thereof |
US9261300B2 (en) | 2012-11-12 | 2016-02-16 | Trane International Inc. | Expansion valve control system and method for air conditioning apparatus |
US9702481B2 (en) | 2009-08-17 | 2017-07-11 | Dunan Microstaq, Inc. | Pilot-operated spool valve |
US9835360B2 (en) | 2009-09-30 | 2017-12-05 | Thermo Fisher Scientific (Asheville) Llc | Refrigeration system having a variable speed compressor |
JP2020093599A (ja) * | 2018-12-11 | 2020-06-18 | 本田技研工業株式会社 | 空調装置 |
US11193704B2 (en) * | 2017-08-03 | 2021-12-07 | Gree Electric Appliances (Wuhan) Co., Ltd | Heat pump reversing valve control based on the valve reversing pressure and the system pressure |
US11655991B2 (en) * | 2017-06-29 | 2023-05-23 | Samsung Electronics Co., Ltd. | Air conditioner and method of controlling air conditioner |
Families Citing this family (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103033005B (zh) * | 2011-09-29 | 2016-04-20 | 杭州三花研究院有限公司 | 一种汽车空调系统电子膨胀阀的控制方法 |
CN103033007B (zh) * | 2011-09-29 | 2015-11-18 | 杭州三花研究院有限公司 | 一种汽车空调系统电子膨胀阀的控制方法 |
CN103033006B (zh) * | 2011-09-29 | 2016-03-23 | 杭州三花研究院有限公司 | 一种汽车空调系统电子膨胀阀的控制方法 |
CN103033008B (zh) * | 2011-09-29 | 2016-04-20 | 杭州三花研究院有限公司 | 一种汽车空调系统电子膨胀阀的控制方法 |
CN103411291B (zh) * | 2013-08-30 | 2016-03-09 | 海信(山东)空调有限公司 | 一种膨胀阀喷射控制方法及系统 |
CN104515252A (zh) * | 2013-09-28 | 2015-04-15 | 杭州三花研究院有限公司 | 一种电子膨胀阀的控制方法 |
CN104654529A (zh) * | 2015-02-03 | 2015-05-27 | 深圳麦格米特电气股份有限公司 | 一种变频空调制热运行时电子膨胀阀的控制方法 |
CN104633862B (zh) * | 2015-02-03 | 2018-01-09 | 深圳麦格米特电气股份有限公司 | 一种变频空调制冷运行时电子膨胀阀的控制方法 |
CN105546742B (zh) * | 2015-12-25 | 2018-10-26 | 美的集团武汉制冷设备有限公司 | 空调器和空调器的控制方法及装置 |
CN107631525B (zh) * | 2017-07-31 | 2020-06-02 | 珠海格力电器股份有限公司 | 一种双级压缩机空调系统及其控制方法和装置 |
CN107321488B (zh) * | 2017-08-30 | 2023-07-14 | 四川绿矿环保科技有限公司 | 旋转水阀跳汰机 |
CN111076352B (zh) * | 2019-12-30 | 2021-07-20 | 宁波奥克斯电气股份有限公司 | 多联机电子膨胀阀的控制方法、装置、空调器及存储介质 |
CN111854032B (zh) * | 2020-07-13 | 2021-09-21 | 珠海格力电器股份有限公司 | 电子膨胀阀的控制方法、空调的控制方法和空调器 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5000009A (en) * | 1990-04-23 | 1991-03-19 | American Standard Inc. | Method for controlling an electronic expansion valve in refrigeration system |
US6318101B1 (en) * | 2000-03-15 | 2001-11-20 | Carrier Corporation | Method for controlling an electronic expansion valve based on cooler pinch and discharge superheat |
US6321549B1 (en) * | 2000-04-14 | 2001-11-27 | Carrier Corporation | Electronic expansion valve control system |
US20040098997A1 (en) * | 2002-11-22 | 2004-05-27 | Lg Electronics Inc. | Air conditioner and method for controlling electronic expansion valve of air conditioner |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3676481B2 (ja) * | 1996-03-07 | 2005-07-27 | 三菱電機株式会社 | 空気調和機の電子膨張弁制御装置 |
US6498927B2 (en) * | 2001-03-28 | 2002-12-24 | Gct Semiconductor, Inc. | Automatic gain control method for highly integrated communication receiver |
KR100544673B1 (ko) * | 2002-10-04 | 2006-01-23 | 제일모직주식회사 | 시이트 그레이드 수지 펠렛 제조용 압출기 스크류 |
-
2006
- 2006-08-04 KR KR1020060073556A patent/KR100785979B1/ko active IP Right Grant
-
2007
- 2007-07-16 EP EP07768769A patent/EP2047185A1/en not_active Withdrawn
- 2007-07-16 CN CNA2007800284660A patent/CN101495824A/zh active Pending
- 2007-07-16 WO PCT/KR2007/003440 patent/WO2008016228A1/en active Application Filing
- 2007-08-01 US US11/832,216 patent/US20080028779A1/en not_active Abandoned
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5000009A (en) * | 1990-04-23 | 1991-03-19 | American Standard Inc. | Method for controlling an electronic expansion valve in refrigeration system |
US6318101B1 (en) * | 2000-03-15 | 2001-11-20 | Carrier Corporation | Method for controlling an electronic expansion valve based on cooler pinch and discharge superheat |
US6321549B1 (en) * | 2000-04-14 | 2001-11-27 | Carrier Corporation | Electronic expansion valve control system |
US20040098997A1 (en) * | 2002-11-22 | 2004-05-27 | Lg Electronics Inc. | Air conditioner and method for controlling electronic expansion valve of air conditioner |
Cited By (29)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9702481B2 (en) | 2009-08-17 | 2017-07-11 | Dunan Microstaq, Inc. | Pilot-operated spool valve |
US10845097B2 (en) | 2009-09-30 | 2020-11-24 | Thermo Fisher Scientific (Asheville) Llc | Refrigeration system having a variable speed compressor |
US10816243B2 (en) | 2009-09-30 | 2020-10-27 | Thermo Fisher Scientific (Asheville) Llc | Refrigeration system having a variable speed compressor |
US10072876B2 (en) | 2009-09-30 | 2018-09-11 | Thermo Fisher Scientific (Asheville) Llc | Refrigeration system having a variable speed compressor |
US9835360B2 (en) | 2009-09-30 | 2017-12-05 | Thermo Fisher Scientific (Asheville) Llc | Refrigeration system having a variable speed compressor |
US9006844B2 (en) | 2010-01-28 | 2015-04-14 | Dunan Microstaq, Inc. | Process and structure for high temperature selective fusion bonding |
US8956884B2 (en) | 2010-01-28 | 2015-02-17 | Dunan Microstaq, Inc. | Process for reconditioning semiconductor surface to facilitate bonding |
US20110232311A1 (en) * | 2010-03-23 | 2011-09-29 | Mitsubishi Electric Corporation | Multi-room air conditioning apparatus |
US9032749B2 (en) * | 2010-03-23 | 2015-05-19 | Mitsubishi Electric Corporation | Indoor expansion valve initialization sequence for an air conditioner |
US8996141B1 (en) | 2010-08-26 | 2015-03-31 | Dunan Microstaq, Inc. | Adaptive predictive functional controller |
US20120172724A1 (en) * | 2010-12-31 | 2012-07-05 | Hill Anthony D | Automatic identification of intracardiac devices and structures in an intracardiac echo catheter image |
US8925793B2 (en) | 2012-01-05 | 2015-01-06 | Dunan Microstaq, Inc. | Method for making a solder joint |
US20130227984A1 (en) * | 2012-03-05 | 2013-09-05 | Honda Motor Co., Ltd. | Air conditioner for vehicle |
US9879890B2 (en) * | 2012-03-05 | 2018-01-30 | Honda Motor Co., Ltd. | Air conditioner for vehicle |
US9404815B2 (en) | 2012-03-16 | 2016-08-02 | Zhejiang Dunan Hetian Metal Co., Ltd. | Superheat sensor having external temperature sensor |
US9772235B2 (en) | 2012-03-16 | 2017-09-26 | Zhejiang Dunan Hetian Metal Co., Ltd. | Method of sensing superheat |
US9140613B2 (en) | 2012-03-16 | 2015-09-22 | Zhejiang Dunan Hetian Metal Co., Ltd. | Superheat sensor |
US9261300B2 (en) | 2012-11-12 | 2016-02-16 | Trane International Inc. | Expansion valve control system and method for air conditioning apparatus |
US9863681B2 (en) | 2012-11-12 | 2018-01-09 | Trane International Inc. | Expansion valve control system and method for air conditioning apparatus |
US20150247661A1 (en) * | 2012-11-21 | 2015-09-03 | Mitsubishi Electric Corporation | Air-conditioning apparatus |
US10107537B2 (en) * | 2012-11-21 | 2018-10-23 | Mitsubishi Electric Corporation | Air-conditioning apparatus |
US20140180483A1 (en) * | 2012-12-20 | 2014-06-26 | Automotive Research & Testing Center | Intelligent thermostatic control method and device for an air conditioner blowing cold and hot air |
US9417638B2 (en) * | 2012-12-20 | 2016-08-16 | Automotive Research & Testing Center | Intelligent thermostatic control method and device for an air conditioner blowing cold and hot air |
US20150362236A1 (en) * | 2013-02-04 | 2015-12-17 | Hangzhou Sanhua Research Institute Co., Ltd. | Electronic expansion valve and control method thereof |
US9188375B2 (en) | 2013-12-04 | 2015-11-17 | Zhejiang Dunan Hetian Metal Co., Ltd. | Control element and check valve assembly |
US11655991B2 (en) * | 2017-06-29 | 2023-05-23 | Samsung Electronics Co., Ltd. | Air conditioner and method of controlling air conditioner |
US11193704B2 (en) * | 2017-08-03 | 2021-12-07 | Gree Electric Appliances (Wuhan) Co., Ltd | Heat pump reversing valve control based on the valve reversing pressure and the system pressure |
JP2020093599A (ja) * | 2018-12-11 | 2020-06-18 | 本田技研工業株式会社 | 空調装置 |
JP7015778B2 (ja) | 2018-12-11 | 2022-02-03 | 本田技研工業株式会社 | 空調装置 |
Also Published As
Publication number | Publication date |
---|---|
EP2047185A1 (en) | 2009-04-15 |
CN101495824A (zh) | 2009-07-29 |
WO2008016228A1 (en) | 2008-02-07 |
KR100785979B1 (ko) | 2007-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20080028779A1 (en) | Method for controlling electronic expansion valve of air conditioner | |
US20080028780A1 (en) | Method for controlling start-up operation of air conditioner | |
US7918097B2 (en) | Air conditioning system | |
US7997095B2 (en) | Method of controlling air conditioner cooling load utilizing controlling the opening degree of an expansion valve and/or the number of rotations of an outdoor fan | |
KR100423681B1 (ko) | 냉각기의 핀치 및 배출 과열을 기초로 한 전자 팽창밸브의 제어 방법 | |
CA2030709C (en) | Method for controlling an electronic expansion valve in refrigeration system | |
CN110375418A (zh) | 空调器及其电子膨胀阀控制方法、控制装置和存储介质 | |
EP1942307A2 (en) | Air conditioner and method of determining refrigerant quantity | |
US20090165482A1 (en) | Air conditioning system | |
JP2008510953A (ja) | 圧縮機のローディング制御 | |
CA2812782C (en) | Expansion valve control system and method for air conditioning apparatus | |
WO2021218436A1 (zh) | 变频空调的控制方法 | |
KR20040012046A (ko) | 냉난방 겸용 에어컨의 제상운전 제어방법 | |
KR100791118B1 (ko) | 공기 조화기의 실온 만족 제어 방법 | |
KR20090051479A (ko) | 공기조화기 및 그 제어 방법 | |
US10077929B2 (en) | Movement of electronic expansion valve | |
JP4105413B2 (ja) | マルチ式空気調和機 | |
JP3028008B2 (ja) | 空気調和装置 | |
KR20090069912A (ko) | 공기조화 시스템 | |
KR20090068972A (ko) | 공기조화 시스템 | |
JPH11153366A (ja) | 冷凍装置の起動制御装置 | |
JPH08226732A (ja) | 空気調和機 | |
KR100728344B1 (ko) | 에어컨의 전자팽창밸브 기동제어방법 | |
EP4350241A1 (en) | Air conditioner | |
JP2003329351A (ja) | インバータ冷凍機の運転システム |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: DAEWOO ELECTRONICS CORPORATION, KOREA, REPUBLIC OF Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SONG, KIL HONG;REEL/FRAME:019771/0616 Effective date: 20070805 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |