TWI816527B - Architecture structure and method of constructing the same - Google Patents

Architecture structure and method of constructing the same Download PDF

Info

Publication number
TWI816527B
TWI816527B TW111132045A TW111132045A TWI816527B TW I816527 B TWI816527 B TW I816527B TW 111132045 A TW111132045 A TW 111132045A TW 111132045 A TW111132045 A TW 111132045A TW I816527 B TWI816527 B TW I816527B
Authority
TW
Taiwan
Prior art keywords
plate
floor
height
board
girder
Prior art date
Application number
TW111132045A
Other languages
Chinese (zh)
Other versions
TW202409389A (en
Inventor
尹衍樑
徐坤榮
陳智軒
Original Assignee
潤弘精密工程事業股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 潤弘精密工程事業股份有限公司 filed Critical 潤弘精密工程事業股份有限公司
Priority to TW111132045A priority Critical patent/TWI816527B/en
Application granted granted Critical
Publication of TWI816527B publication Critical patent/TWI816527B/en
Publication of TW202409389A publication Critical patent/TW202409389A/en

Links

Images

Landscapes

  • Devices For Executing Special Programs (AREA)
  • Executing Machine-Instructions (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present application relates to an architecture structure and a method of constructing the same. The method includes the following steps: providing a precast beam extending in a first axial direction; providing a first plate extending upwardly from an outer side of the precast beam; providing a second plate and horizontally fixing it to the upper edge of the first plate, the second plate seving as a bottom formwork for a first floor, and having a first height; providing a third plate and horizontally disposing it on the precast beam and on the opposing side of the first plate, the third plate serving as a bottom formwork for a second floor, and having a second height, the first height being greater than the first height; providing a fourth plate and vertically disposing it on the opposing side of the first plate so that the fourth plate is roughly parallel to the first plate, and the bottom end of the fourth plate is spaced apart from the third plate by a first pre-determined distance so that the precast beam, the first plate, the second plate, the third plate and the fourth plate form a filling space; and pouring concrete into the filling space.

Description

建築結構及其建造方法Building structures and construction methods

本發明係關於一種建築結構及其建造方法,尤其是關於一種包含高低樓地板以及預鑄梁之建築結構及其建造方法。The present invention relates to a building structure and a construction method thereof, in particular to a building structure including high and low floors and ridge beams and a construction method thereof.

RC(鋼筋混凝土)結構可區分為現場澆置混凝土的傳統場鑄工法以及近年發展具有結構品質優異、施工安全迅速、營建成本經濟合理等優點的預鑄工法。預鑄工法係於預鑄廠或工地周邊,以標準化的作業流程及模組化的模具,製作鋼筋結構並澆置混凝土,快速大量生產精密的柱體、梁體、板體等的預鑄構件。藉由精確的搬運管理及組裝作業,將在預鑄廠內或工地周邊生產完成的預鑄構件於工地現場組合。藉此,工地現場中的工作量可以降至最低、減少人力及施工時間,進而有效縮短工期,並確保施工品質。此外,預鑄施工法亦可減少或避免在外牆鷹架上施工,大幅提高了施工安全性。RC (reinforced concrete) structures can be divided into the traditional cast-in-place construction method of pouring concrete on site and the in-situ construction method that has been developed in recent years and has the advantages of excellent structural quality, safe and rapid construction, and economical and reasonable construction costs. The Xuan construction method is based on the Xuan factory or around the construction site. It uses standardized operating procedures and modular molds to make steel structures and pour concrete to quickly mass-produce precision columns, beams, plates, etc. Xuan components. . Through precise handling management and assembly operations, the Xuan components produced in the Xixuan factory or around the construction site are assembled on the construction site. In this way, the workload on the construction site can be minimized, manpower and construction time can be reduced, thereby effectively shortening the construction period and ensuring construction quality. In addition, the construction method can also reduce or avoid construction on the outer wall scaffolding, which greatly improves construction safety.

一種在梁的兩側具有不同高度之樓板的結構,是一種常見的特定建築結構,其施工較一般制式結構為複雜。請參照圖1,習知施作此類結構包含以下所述步驟:在施工現地進行梁結構之鋼筋501配置及綁紮作業,並於鋼筋501周圍設置模板80,以形成如圖1所展示之L形結構。隨後進行灌漿作業,將混凝土灌漿至L形結構之下部分之方形空間中,待其中之混凝土大致凝固後,再繼續將混凝土灌漿至L形結構之上部分之長方形空間中,並待其凝固後拆除灌漿模板80而形成如圖2-3所展示之L形鋼筋混凝土結構50。隨後,於L形鋼筋混凝土結構50之兩側設置水平之底模板及樓板鋼筋90並在其周圍設置灌漿模板以形成灌漿空間,將混凝土灌漿至該灌漿空間中並待其凝固以形成如圖3所展示之在梁的兩側具有不同高度之樓板的結構。A structure with floor slabs of different heights on both sides of the beam is a common specific building structure, and its construction is more complicated than that of a general standard structure. Please refer to Figure 1. It is known that the construction of such a structure includes the following steps: arranging and binding the steel bars 501 of the beam structure at the construction site, and setting the formwork 80 around the steel bars 501 to form an L as shown in Figure 1 shape structure. Then carry out the grouting operation. Grout the concrete into the square space below the L-shaped structure. After the concrete in it has roughly solidified, continue grouting the concrete into the rectangular space above the L-shaped structure and wait until it solidifies. The grouting formwork 80 is removed to form an L-shaped reinforced concrete structure 50 as shown in Figure 2-3. Subsequently, horizontal bottom formwork and floor steel bars 90 are set on both sides of the L-shaped reinforced concrete structure 50 and a grouting formwork is set around it to form a grouting space. Concrete is grouted into the grouting space and waits for it to solidify to form a grouting space as shown in Figure 3 Shown is a structure with floor slabs of different heights on either side of the beam.

然而,前述圖1-3所展示之建築結構之建造方法有諸多缺點。參照圖1,在梁之鋼筋501之周圍設置模板80(例如:鋼模板)需耗費大量人力及時間。此外,在灌漿作業中,僅可先填充L形結構底部方形之部分,以防止混凝土由其未覆蓋之頂表面溢出;待底部方形部分之混凝土大致凝固後,才可繼續進行上部分結構之灌漿。此等待過程將使混凝土澆置作業所需時間增加,進而導致整個施工過程延宕。However, the aforementioned construction method of the building structure shown in Figures 1-3 has many shortcomings. Referring to Figure 1, it requires a lot of manpower and time to set up a formwork 80 (for example, a steel formwork) around the steel bars 501 of the beam. In addition, during the grouting operation, only the square part at the bottom of the L-shaped structure can be filled first to prevent the concrete from overflowing from the uncovered top surface; only after the concrete at the bottom square part is roughly solidified can the grouting of the upper part of the structure continue. . This waiting process will increase the time required for concrete pouring operations, thereby causing delays in the entire construction process.

因此,如何在利用結合場鑄工法以及預鑄工法,並發揮各自的優點以形成在梁的兩側具有不同高度之樓板的結構是業界所長久企盼的。Therefore, how to combine the field casting method and the construction method and bring into play their respective advantages to form a structure with floor slabs of different heights on both sides of the beam is what the industry has been longing for.

緣是,為達上述目的,本發明的一項態樣係關於一種建造一建築結構之方法,包括下列步驟。提供一預鑄梁,其在一第一軸向方向延伸。提供一第一板,其自預鑄梁的一外側向上延伸。提供一第二板,並將其一端水平地固定於於第一板之一上邊緣,第二板作為一第一樓地板之一底模板,並具有一第一高度。提供一第三板,其一端水平地設置於預鑄梁上,並位於第一板之相對側,第三板作為一第二樓地板之一底模板,並具有一第二高度,且第一高度高於該第二高度。提供一第四板,其垂直設置於第一板之相對側,使其與第一板大致平行,且其底端與第三板間隔一第一預定距離;藉此預鑄梁、第一板、第二板、第三板及第四板之間形成一填充空間。將混凝土灌漿至填充空間中待凝固後以形成該建築結構。In order to achieve the above object, one aspect of the present invention relates to a method of constructing a building structure, comprising the following steps. A beam is provided, which extends in a first axial direction. A first plate is provided, extending upward from an outer side of the girder beam. A second board is provided and one end thereof is horizontally fixed to an upper edge of the first board. The second board serves as a bottom formwork of the first floor and has a first height. Provide a third board, one end of which is horizontally disposed on the beam and located on the opposite side of the first board. The third board serves as a bottom formwork for the second floor and has a second height, and the first height is higher than this second height. Provide a fourth plate, which is vertically disposed on the opposite side of the first plate so that it is substantially parallel to the first plate, and its bottom end is spaced from the third plate by a first predetermined distance; whereby the Qixuan beam, the first plate , a filling space is formed between the second board, the third board and the fourth board. Concrete is grouted into the filled space and left to set to form the building structure.

本發明的另一項態樣係關於一種建築結構,其包括一預鑄梁、一第一板、一第一結構、一第一樓地板、一第二樓地板。預鑄梁在一第一軸向方向延伸且具有一頂表面。第一板自預鑄梁的一外側向上延伸。第一結構與第一板之側面及預鑄梁之頂表面相連接。第一樓地板之一端與該第一結構的上部的一第一側相連接。第二樓地板之一端與第一結構的下部的一第二側相連接,且該第一側與第二側為相對側。此外,第一樓地板與第二樓地板具有一高度差H。Another aspect of the present invention relates to a building structure, which includes a beam, a first board, a first structure, a first floor, and a second floor. The Qixuan beam extends in a first axial direction and has a top surface. The first plate extends upward from an outer side of the beam. The first structure is connected to the side of the first plate and the top surface of the beam. One end of the first floor is connected to a first side of the upper portion of the first structure. One end of the second floor is connected to a second side of the lower part of the first structure, and the first side and the second side are opposite sides. In addition, there is a height difference H between the first floor and the second floor.

為更清楚了解本發明的特徵、內容與優點及其所能達成的功效,茲將本發明配合附圖,並以實施例的表達形式詳細說明如下,而其中所使用的圖式,其主旨僅為示意及輔助說明書的用,不應就所附的圖式的比例與配置關係解讀、侷限本發明的申請專利範圍。In order to have a clearer understanding of the characteristics, content, advantages and effects of the present invention, the present invention is described in detail below in conjunction with the accompanying drawings and in the form of embodiments. The drawings used are only for their main purpose. The proportions and arrangement relationships of the attached drawings are for illustration and auxiliary description purposes, and should not be interpreted to limit the patentable scope of the present invention.

請參考圖4,其展示本發明一實施例的施工示意圖一。首先,提供半預鑄梁11,其在一第一軸向方向(垂直紙面之方向)延伸。第一板2在半預鑄梁11的形成過程中即設置於半預鑄梁11的外側113,並在半預鑄梁11形成後,固定至半預鑄梁11並自半預鑄梁11的外側113向上延伸。詳而言之,在上述實施例中,在半預鑄梁11之預鑄過程中將第一板2之一連接部分21設置於半預鑄梁11中之箍筋112的外側1121,且使得第一板2的外表面與預鑄梁之對應外表面大致齊平,並將半預鑄梁11及第一板2之連接部分21一起灌漿,使第一板2之連接部分21埋設於半預鑄梁11中。Please refer to Figure 4, which shows a construction schematic diagram 1 of an embodiment of the present invention. First, a half-clamp beam 11 is provided, which extends in a first axial direction (the direction perpendicular to the paper plane). The first plate 2 is disposed on the outer side 113 of the half beam 11 during the formation process of the half beam 11 , and is fixed to the half beam 11 and removed from the half beam 11 after the half beam 11 is formed. The outer side 113 extends upward. To be more specific, in the above embodiment, during the process of assembling the half-seam beam 11, one of the connecting portions 21 of the first plate 2 is disposed on the outer side 1121 of the stirrups 112 in the half-seam beam 11, and such that The outer surface of the first plate 2 is approximately flush with the corresponding outer surface of the yoke beam, and the half yoke beam 11 and the connecting portion 21 of the first plate 2 are grouted together, so that the connecting portion 21 of the first plate 2 is buried in the half yoke beam. Xixuanliang ranked 11th.

在上述實施例中,半預鑄梁11具有自頂部伸出之複數個鋼筋114,該複數個鋼筋114用於與建築結構1位於半預鑄梁11上方之鋼筋綁紮結合(參圖8及圖11),半預鑄梁11的頂表面111係一粗糙的表面,以使得半預鑄梁11上方後續澆置的混凝土可與半預鑄梁11的頂表面緊密的結合。In the above embodiment, the half-joist beam 11 has a plurality of steel bars 114 extending from the top, and the plurality of steel bars 114 are used to bind and combine with the steel bars of the building structure 1 located above the half-joist beam 11 (see Figure 8 and Figure 11), the top surface 111 of the half-rib beam 11 is a rough surface, so that the concrete poured above the half-rib beam 11 can be closely combined with the top surface of the half-rib beam 11 .

請參閱圖5,其為上述實施例的施工示意圖二。施工時,提供第二板3,並將第二板3之一端31水平地固定於第一板2之上邊緣22。第二板3作為第一樓地板12之底模板,並具有第一高度h1。第二板3之第一高度h1係指第二板3至預鑄梁11底表面115之距離Please refer to Figure 5, which is the second construction schematic diagram of the above embodiment. During construction, the second board 3 is provided, and one end 31 of the second board 3 is horizontally fixed to the upper edge 22 of the first board 2 . The second board 3 serves as the bottom formwork of the first floor 12 and has a first height h1. The first height h1 of the second plate 3 refers to the distance from the second plate 3 to the bottom surface 115 of the beam 11

請參照圖5A,其為圖5中A部分之局部放大圖,在上述實施例中,將第二板3之一端31水平地固定於第一板2之上邊緣22的方式包括先將蓋槽鐵6設置於第一板2之上邊緣22,再將第二板3焊接於蓋槽鐵6上。Please refer to Figure 5A, which is a partial enlarged view of part A in Figure 5. In the above embodiment, the method of horizontally fixing one end 31 of the second plate 3 to the upper edge 22 of the first plate 2 includes first covering the groove. The iron 6 is arranged on the upper edge 22 of the first plate 2, and the second plate 3 is welded to the iron 6 of the cover channel.

蓋槽鐵6之設置可使第二板3與第一板2之上邊緣22之接觸由點接觸變成面接觸,使第二板3更穩固地設置於第一板2之上邊緣22。此外,將第二板3焊接至蓋槽鐵6上可防止灌漿時模板直接與混凝土接觸。The arrangement of the cover groove iron 6 can change the contact between the second plate 3 and the upper edge 22 of the first plate 2 from point contact to surface contact, so that the second plate 3 can be more firmly placed on the upper edge 22 of the first plate 2 . In addition, welding the second plate 3 to the cover channel iron 6 prevents direct contact between the formwork and the concrete during grouting.

請參照圖6,其為上述實施例的施工示意圖三。接續上述施工步驟,提供第三板4。將第三板4之一端41水平地設置於半預鑄梁11上,並位於第一板2及第二板3之相對側。第三板4作為第二樓地板13之底模板,並具有第二高度h2。第三板4之第二高度h2係指第三板4至預鑄梁11底表面115之距離。第一高度h1高於第二高度h2。Please refer to Figure 6, which is the third construction schematic diagram of the above embodiment. Continuing the above construction steps, a third plate 4 is provided. One end 41 of the third plate 4 is disposed horizontally on the half beam 11 and located on the opposite side of the first plate 2 and the second plate 3 . The third board 4 serves as the bottom formwork of the second floor floor 13 and has a second height h2. The second height h2 of the third plate 4 refers to the distance from the third plate 4 to the bottom surface 115 of the beam 11 . The first height h1 is higher than the second height h2.

繼續參照圖6,在本實施例中,預鑄梁11之橫截面為矩形且其底邊之長度約為60 cm。第二板3之第一高度h1約為110 cm。第三板4之第二高度h2約為50 cm。此外,參照圖8,第一樓地板12及第二樓地板13之樓地板厚度t約為20 cm。Continuing to refer to FIG. 6 , in this embodiment, the cross section of the beam 11 is rectangular and the length of its base is about 60 cm. The first height h1 of the second plate 3 is approximately 110 cm. The second height h2 of the third plate 4 is approximately 50 cm. In addition, referring to FIG. 8 , the floor thickness t of the first floor floor 12 and the second floor floor 13 is approximately 20 cm.

參照圖8,在其他實施例中,第二板3之第一高度h1、第三板4之第二高度h2、預鑄梁11之厚度及樓地板之厚度t係可實際需求調整,使得第一樓地板12之頂表面與第二樓地板13之頂表面之高度差H(即,樓板高低差)大約為20 cm、40 cm或60 cm。Referring to Figure 8, in other embodiments, the first height h1 of the second plate 3, the second height h2 of the third plate 4, the thickness of the beam 11 and the thickness t of the floor can be adjusted according to actual needs, so that the The height difference H (ie, floor height difference) between the top surface of the first floor floor 12 and the top surface of the second floor floor 13 is approximately 20 cm, 40 cm or 60 cm.

回到圖6,在施工時,設置於第一板2之上邊緣22之第二板3除了模板自重外,尚需乘載樓板混凝土之載重、作業載重及衝擊載重。這些載重之總和(即,總載重W1)除了會對第一板2施加一向下的力之外,還會使第一板2承受一力矩。當此向下之力或力矩超過一臨界值時,將會導致第一板2挫曲(buckling)變形。此外,當第一板2向上延伸在預鑄梁11外之部分越長,第二板3上方之載重對第一板2所產生之力矩會越大,進而增加第一板2挫曲之可能性。Returning to Figure 6, during construction, the second plate 3 disposed on the upper edge 22 of the first plate 2 needs to carry the load of the floor concrete, the operating load and the impact load in addition to the self-weight of the formwork. The sum of these loads (ie, the total load W1) will not only exert a downward force on the first plate 2, but also cause the first plate 2 to bear a moment. When the downward force or moment exceeds a critical value, buckling deformation of the first plate 2 will occur. In addition, the longer the portion of the first plate 2 that extends upward beyond the girder beam 11 is longer, the greater the moment generated by the load above the second plate 3 on the first plate 2 will be, thereby increasing the possibility of buckling of the first plate 2 sex.

為了防止上述第一板2挫曲之問題,上述實施例依據第二板3之預期載重進行結構分析以選擇適合之第一板2之型號及尺寸,並對第一板2進行挫曲檢核,以確保其不會挫曲。舉例而言,減少第一板2向上延伸在預鑄梁外之部分之長度或增加第一板2之厚度皆有助於防止第一板2挫曲。In order to prevent the above-mentioned buckling problem of the first plate 2, the above embodiment performs a structural analysis based on the expected load of the second plate 3 to select a suitable model and size of the first plate 2, and conducts a buckling check on the first plate 2 , to ensure it does not buckle. For example, reducing the length of the portion of the first plate 2 that extends upward beyond the beam or increasing the thickness of the first plate 2 can help prevent buckling of the first plate 2 .

參照圖6,在一實施例中,在第一板2向上延伸在預鑄梁11外之部分之長度為60 cm、第二板之總載重W1為910kgf/m 2且第一板2受力為1,775kgf/m之情況下,選擇VERSA-DEK閉口型40H(鋼板厚度為0.76mm、斷面積為12.62cm 2/m、單位重量為10.40kg/m 2、慣性矩為29.23cm 4/m、正彎矩斷面模數為9.61cm 3/m、負彎矩斷面模數為8.20cm 3/m)作為第一板2不會發生挫曲。 Referring to Figure 6, in one embodiment, the length of the portion of the first plate 2 extending upward outside the beam 11 is 60 cm, the total load W1 of the second plate is 910kgf/ m2 , and the first plate 2 is stressed. In the case of 1,775kgf/m, select VERSA-DEK closed type 40H (steel plate thickness is 0.76mm, cross-sectional area is 12.62cm 2 /m, unit weight is 10.40kg/m 2 , moment of inertia is 29.23cm 4 /m, The positive bending moment section modulus is 9.61cm 3 /m and the negative bending moment section modulus is 8.20cm 3 /m) as the first plate 2 will not buckle.

然而,在上述實施例之參數條件下,若進一步考慮灌漿時第一板2右方之混凝土對其施加之灌漿壓力W2,第一板2將可能會撓曲。此外,灌漿壓力W2對第一板2所造成之側向力將可能進而導致第一板2與預鑄梁11之連接部分21開裂。However, under the parameter conditions of the above embodiment, if the grouting pressure W2 exerted by the concrete on the right side of the first plate 2 during grouting is further considered, the first plate 2 may deflect. In addition, the lateral force caused by the grouting pressure W2 on the first plate 2 may further cause the connection portion 21 between the first plate 2 and the beam 11 to crack.

具體而言,參照圖6,在如上述實施例中之參數條件下,當灌漿高度為0.8公尺時,混凝土施加於第一板之灌漿壓力為1920kgf/m2。在此情況下,第一板2會降伏而撓曲且第一板2之連接部分21與預鑄梁11之混凝土介面有可能會開裂。 Specifically, referring to Figure 6, under the parameter conditions as in the above embodiment, when the grouting height is 0.8 meters, the grouting pressure exerted by concrete on the first plate is 1920kgf/ m2 . In this case, the first plate 2 will yield and deflect, and the concrete interface between the connecting portion 21 of the first plate 2 and the girder beam 11 may crack.

因此,為了防止第一板2挫曲及撓曲,上述實施例對第一板2施加一向右之外力以抵銷上述總載重W1所造成之彎矩及灌漿壓力W2。 Therefore, in order to prevent buckling and deflection of the first plate 2, the above-mentioned embodiment applies an external force to the right on the first plate 2 to offset the bending moment and grouting pressure W2 caused by the above-mentioned total load W1.

請參照圖7,其為上述實施例的施工示意圖四。接續上述施工步驟,提供第四板5。第四板5垂直設置於預鑄梁11上方且位於第一板2之相對側之鋼筋114之外側1141。第四板5與第一板2大致平行且第四板5之底端51與第三板4間隔第一預定距離d1。此外,提供至少一支對拉桿7(圖8展示兩支對拉桿)並將第四板5及第一板2藉由對拉桿7的兩端連接,以使第四板5及第一板2之間保持一第二預定距離d2。 Please refer to Figure 7, which is a construction diagram 4 of the above embodiment. Continuing the above construction steps, a fourth plate 5 is provided. The fourth plate 5 is arranged vertically above the beam 11 and located outside the steel bar 114 on the opposite side of the first plate 2 1141 . The fourth plate 5 is substantially parallel to the first plate 2 and the bottom end 51 of the fourth plate 5 is spaced apart from the third plate 4 by a first predetermined distance d1. In addition, at least one tie rod 7 is provided (Figure 8 shows two tie rods), and the fourth plate 5 and the first plate 2 are connected through the two ends of the tie rod 7, so that the fourth plate 5 and the first plate 2 A second predetermined distance d2 is maintained between them.

為了防止第一板2挫曲及撓曲,在上述實施例之參數條件下,分別於第一板2之離預鑄梁11之頂表面30cm及50cm之位置,以直徑8mm,沿半預鑄梁11之縱向間距50cm之一排對拉桿連接第一板2及第四板5,以使對拉桿兩端拉住第一板2及第四板5。 In order to prevent buckling and deflection of the first plate 2, under the parameter conditions of the above embodiment, at positions 30cm and 50cm away from the top surface of the beam 11 of the first plate 2, with a diameter of 8mm, along the half beam, A row of tie rods with a longitudinal spacing of 50 cm on the beam 11 connects the first plate 2 and the fourth plate 5 so that both ends of the tie rods pull the first plate 2 and the fourth plate 5 .

除了檢核前述第一板2之挫曲及撓曲外,上述實施例尚須檢核第一板2之連接部分21與預鑄梁11之混凝土介面開裂之風險。參照圖7及圖8,在前述實施例參數條件下,為了防止第一板2之連接部分21與預鑄梁11之混凝土介面開裂,第一板2之連接部分21之位於預鑄梁11中之底端23與預鑄梁11之頂表面111之距離(即,錨定長l)需至少大於8.8cm。錨定長l越長,第一板2之連接部分21與預鑄梁11之混凝土介面開裂之風險越小。大於8.8cm之錨定長l範圍可符合實際施工大部分之需求。 In addition to checking the buckling and deflection of the first plate 2 , the above embodiment also needs to check the risk of cracking at the concrete interface between the connecting portion 21 of the first plate 2 and the beam 11 . Referring to Figures 7 and 8, under the parameter conditions of the aforementioned embodiment, in order to prevent the connecting portion 21 of the first plate 2 from cracking at the concrete interface of the Xuan beam 11, the connecting portion 21 of the first plate 2 is located in the Xuan beam 11 The distance between the bottom end 23 and the top surface 111 of the beam 11 (that is, the anchoring length l) needs to be at least greater than 8.8cm. The longer the anchoring length l, the smaller the risk of cracking at the concrete interface between the connecting portion 21 of the first plate 2 and the beam 11. Anchoring length l range greater than 8.8cm can meet most of the needs of actual construction.

此外,為確保第一板2之位於預鑄梁11中之底端23下方之混凝土足以抵抗第一板2所受之力及力矩造成之剪力,還需保護層抗剪力強度之檢核。參照圖8A,其為圖8中B部分之局部放大圖,在第二板3及其所承載之樓板之總載重W1為910kgf/m2之情況下,第一板2會受到一向下且大小為1,775kgf/m之力。當此力所造成之剪力超出一臨界值時,將會導致第一板2之位於預鑄梁11中之底端23下方之混凝土開裂(例如:圖8A所示底端23下方混凝土之45度傾斜之開裂)。在前述參數之條件下,當預鑄梁11之箍筋112外側1121之保護層厚度p至少為4cm時,第一板2之位於預鑄梁11中之底端23下方之混凝土保護層不會開裂。 In addition, in order to ensure that the concrete below the bottom end 23 of the first plate 2 in the beam 11 is sufficient to resist the shear force caused by the force and moment on the first plate 2, the shear strength of the protective layer needs to be checked. . Referring to Figure 8A, which is a partial enlarged view of part B in Figure 8, when the total load W1 of the second plate 3 and the floor it carries is 910kgf/ m2 , the first plate 2 will be subjected to a downward and large force. The force is 1,775kgf/m. When the shear force caused by this force exceeds a critical value, it will cause the concrete below the bottom end 23 of the first plate 2 to crack (for example: 45 of the concrete below the bottom end 23 shown in Figure 8A degree of tilt (cracking). Under the conditions of the aforementioned parameters, when the thickness p of the protective layer on the outside 1121 of the stirrups 112 of the Jiaxuan beam 11 is at least 4cm, the concrete protective layer of the first plate 2 located under the bottom end 23 of the Jiaxuan beam 11 will not cracking.

請參照圖8,其為上述實施例的施工示意圖五。接續上述施工步驟,將混凝土灌漿至預鑄梁11、第一板2、第二板3、第三板4及第四板5形成之填充空間8中。待混凝土凝固後,拆除第二板3、第三板4及第四板5以形成建築結構1。上述施工步驟可根據實際需求調整施工先後順序。本發明上述實施例所提供之方法可免除在施工現場配置L形梁之鋼筋及灌漿模板,亦可省下兩階段灌漿間隔所需之等待時間,可大幅提昇在梁的兩側具有不同高度之樓板的建築結構之建造效率。 Please refer to Figure 8, which is a construction schematic diagram 5 of the above embodiment. Continuing the above construction steps, concrete is grouted into the filling space 8 formed by the beam 11, the first plate 2, the second plate 3, the third plate 4 and the fourth plate 5. After the concrete is solidified, the second plate 3 , the third plate 4 and the fourth plate 5 are removed to form the building structure 1 . The construction sequence of the above construction steps can be adjusted according to actual needs. The method provided by the above embodiments of the present invention can eliminate the need to configure the steel bars and grouting formwork of the L-shaped beam at the construction site, can also save the waiting time required for the two-stage grouting interval, and can greatly improve the construction of L-shaped beams with different heights on both sides. The construction efficiency of the building structure of the floor slab.

在上述實施例中,第一板2、第二板3、第三板4或第四板5可為勁扣版或Deck板。參照圖9,Deck板可為Versa-Dek®之不同型號之Versa-Dek板。Deck板之一側為平坦表面,另一側具有等間距排列之長條突起20,且每個長條突起20具有鳩尾狀之橫截面。施工時,勁扣版或Deck板之具有長條突起20之表面係朝向待灌漿之空間。 In the above embodiment, the first board 2, the second board 3, the third board 4 or the fourth board 5 may be a buckle board or a Deck board. Referring to Figure 9, the Deck board can be a Versa-Dek board of different models of Versa-Dek®. One side of the deck board is a flat surface, and the other side has elongated protrusions 20 arranged at equal intervals, and each long protrusion 20 has a dovetail-shaped cross section. During construction, the surface of the buckle board or deck board with the long protrusions 20 faces the space to be grouted.

參照圖10,其為類似圖4所示之施工示意圖一之另一替代實施例示意圖,其中於半預鑄梁11之預鑄過程中,第一板2並未埋設於半預鑄梁11中一起灌漿,而是先單獨建造半預鑄梁11,再於現地將第一板2附接(例如藉由預先埋設在半預鑄梁11內之螺栓、鉚釘等)至半預鑄梁11之外側113。在此替代之實施例中,第一板2在完成建築結構1之灌漿之後被拆除。Referring to Figure 10, which is a schematic diagram of another alternative embodiment similar to the construction schematic diagram shown in Figure 4, in which the first plate 2 is not buried in the half-tied beam 11 during the construction process. Instead of grouting together, the half-way beam 11 is built separately first, and then the first plate 2 is attached on-site (for example, by bolts, rivets, etc. that are pre-embedded in the half-way beam 11) to the half-way beam 11. Outside 113. In this alternative embodiment, the first panel 2 is removed after completion of grouting of the building structure 1 .

請參閱圖11,其為根據上述實施例所提供之方法所建造之建築結構1示意圖。在本實施例中,建築結構1包括一半預鑄梁11、一第一板2、一第一樓地板12、一第二樓地板13、一第一結構14。半預鑄梁11在第一軸向方向(垂直紙面方向)延伸且具有一頂表面111。第一板2自半預鑄梁11的外側113向上延伸。第一結構14與第一板2之內側面24及半預鑄梁11之頂表面111相連接。第一樓地板12之一端121與第一結構14的上部的第一側141相連接。第二樓地板13之一端131與第一結構14的下部的第二側142相連接,其中第一側141與第二側142為相對側。第一樓地板12與第二樓地板13具有一高度差H。高度差H可為20 cm、40 cm或60 cm。Please refer to Figure 11, which is a schematic diagram of the building structure 1 constructed according to the method provided in the above embodiment. In this embodiment, the building structure 1 includes half of the beams 11 , a first plate 2 , a first floor 12 , a second floor 13 , and a first structure 14 . The half beam 11 extends in the first axial direction (direction perpendicular to the paper surface) and has a top surface 111 . The first plate 2 extends upward from the outer side 113 of the half beam 11 . The first structure 14 is connected to the inner side 24 of the first plate 2 and the top surface 111 of the half-rib beam 11 . One end 121 of the first floor 12 is connected to the first side 141 of the upper part of the first structure 14 . One end 131 of the second floor 13 is connected to the second side 142 of the lower part of the first structure 14 , where the first side 141 and the second side 142 are opposite sides. There is a height difference H between the first floor floor 12 and the second floor floor 13 . The height difference H can be 20 cm, 40 cm or 60 cm.

參照圖11,在本實施例中,半預鑄梁11具有複數個鋼筋114自半預鑄梁11頂表面111伸出,以與半預鑄梁11上方之第一結構14中的鋼筋綁紮結合。此外,第一板2為一勁扣版,且於第一板2之上邊緣22上設置有蓋槽鐵6。Referring to FIG. 11 , in this embodiment, the half-way beam 11 has a plurality of steel bars 114 extending from the top surface 111 of the half-way beam 11 to be tied with the steel bars in the first structure 14 above the half-way beam 11 . In addition, the first plate 2 is a buckle plate, and a cover channel iron 6 is provided on the upper edge 22 of the first plate 2 .

已參考實施例闡述本發明且為理解本發明的特徵的特定應用可個別地及/或以各種組合及/或在各種類型的上實踐。而且,熟習此項技術者將認識到在不背離本發明的範疇的情況下,可對實施例在其應用的任一者中進行各種修改。此外,替代實施例可以不同組成材料、結構及/或空間關係來進行,且儘管如此仍歸屬於本發明的範疇內。鑒於上述情況,本發明應僅限於由本申請案或任何相關申請案發佈的可允許申請專利範圍的範圍。The invention has been described with reference to embodiments and it is understood that specific applications of the features of the invention may be practiced individually and/or in various combinations and/or on various types. Furthermore, those skilled in the art will recognize that various modifications may be made to the embodiments in any of their uses without departing from the scope of the invention. Furthermore, alternative embodiments may be constructed with different constituent materials, structures, and/or spatial relationships and yet remain within the scope of the present invention. In view of the foregoing, the invention shall be limited to the extent of the permissible patent claims issued by this application or any related application.

本文中的用語「一」或「一種」係用以敘述本創作之元件及成分。此術語僅為了敘述方便及給予本創作之基本觀念。此敘述應被理解為包括一種或至少一種,且除非明顯地另有所指,表示單數時亦包括複數。於申請專利範圍中和「包含」一詞一起使用時,該用語「一」可意謂一個或超過一個。此外,本文中的用語「或」其意同「及/或」。The term "a" or "an" used herein is used to describe the elements and components of the invention. This terminology is only for convenience of description and to give the basic concept of this creation. This recitation should be understood to include one or at least one, and the singular also includes the plural unless it is expressly stated otherwise. When used with the word "comprising" in a patent application, the term "a" can mean one or more than one. In addition, the word "or" used in this article has the same meaning as "and/or".

除非另外規定,否則諸如「上方」、「下方」、「向上」、「左邊」、「右邊」、「向下」、「頂」、「底」、「垂直」、「水平」、「側」、「較高」、「下部」、「上部」、「上方」、「下面」等空間描述係關於圖中所展示之方向加以指示。應理解,本文中所使用之空間描述僅出於說明之目的,且本文中所描述之結構之實際實施可以任何相對方向在空間上配置,此限制條件不會改變本創作各實施例之優點。舉例來說,在一些實施例之描述中,提供「在」另一元件「上」之一元件可涵蓋前一元件直接在後一元件上(例如,與後一元件實體接觸)的狀況以及一或多個介入元件位於前一元件與後一元件之間的狀況。Unless otherwise specified, terms such as "above", "below", "up", "left", "right", "down", "top", "bottom", "vertical", "horizontal", "side" Spatial descriptions such as "higher", "lower", "upper", "above", and "below" indicate the direction shown in the figure. It should be understood that the spatial descriptions used herein are for illustrative purposes only, and actual implementations of the structures described herein may be spatially configured in any relative orientation, and this limitation does not alter the advantages of various embodiments of the present invention. For example, in the description of some embodiments, providing that one element is "on" another element may cover situations where the former element is directly on (e.g., in physical contact with) the latter element, as well as when an element is "on" the latter element. Or a situation where multiple intervening components are located between the previous component and the following component.

如本文中所使用,術語「大致」、「實質上」、「實質的」及「約」用以描述及考慮微小之變化。當與事件或情形結合使用時,該等術語可意指事件或情形明確發生之情況以及事件或情形極近似於發生之情況。As used herein, the terms "substantially," "substantially," "substantially," and "approximately" are used to describe and account for minor changes. When used in connection with an event or circumstance, these terms may mean both a definite occurrence of the event or circumstance and a close approximation of the occurrence of the event or circumstance.

1:建築結構1: Building structure

2:第一板2: First board

3:第二板3:Second board

4:第三板4:Third board

5:第四板5:Fourth board

6:蓋槽鐵6: Cover trough iron

7:對拉桿7: Pair the tie rod

8:填充空間8: Fill the space

11:預鑄梁/半預鑄梁11:Haixuanliang/Half Haixuanliang

12:第一樓地板12:First floor floor

13:第二樓地板13: Second floor floor

14:第一結構14:First structure

21:連接部分21:Connection part

22:上邊緣22:Top edge

23:底端23: Bottom

24:內側面24: Medial side

31:端31:end

41:端41:End

20:長條突起20: long protrusion

50:L形鋼筋混凝土結構50: L-shaped reinforced concrete structure

51:底端51: Bottom

80:灌漿模板80: Grout template

90:樓板鋼筋90: Floor steel bars

111:頂表面111:Top surface

112:箍筋112: stirrups

113:外側113:Outside

114:鋼筋114:Rebar

115:底表面115: Bottom surface

121:端121:end

131:端131:End

141:第一側141: First side

142:第二側142: Second side

501:鋼筋501:Rebar

1121:外側1121:Outside

1141:外側1141:Outside

d1:第一預定距離d1: first predetermined distance

d2:第二預定距離d2: second predetermined distance

H:高度差H: Height difference

h1:第一高度h1: first height

h2:第二高度h2: second height

l:錨定長l: anchor length

p:保護層厚度p:Thickness of protective layer

t:樓地板厚度t: floor thickness

W1:總載重W1: total load

W2:灌漿壓力W2: grouting pressure

為更清楚了解本發明及其優點所能達成的功效,茲將本發明配合附圖,並以實施例的表達形式詳細說明如下。 圖1為習知在梁的兩側具有不同高度之樓板的結構之施工示意圖一。 圖2為習知在梁的兩側具有不同高度之樓板的結構之施工示意圖二。 圖3為習知在梁的兩側具有不同高度之樓板的結構之施工示意圖三。 圖4為本發明一實施例之施工示意圖一。 圖5為本發明上述實施例之施工示意圖二。 圖5A為圖5之A部分之局部放大圖。 圖6為本發上述實施例之施工示意圖三。 圖7為本上述實施例之施工示意圖四。 圖8為本上述實施例之施工示意圖五。 圖8A為圖8之B部分之局部放大圖。 圖9為本發明上述實施例中所使用之勁扣版示意圖。 圖10為本發明另一實施例之示意圖。 圖11為本發明上述實施例之橫截面示意圖。 In order to have a clearer understanding of the effects achieved by the present invention and its advantages, the present invention is described in detail below with reference to the accompanying drawings and in the form of embodiments. Figure 1 is a schematic diagram of the construction of a conventional structure with floor slabs of different heights on both sides of the beam. Figure 2 is a schematic diagram 2 of the construction of a conventional structure with floor slabs of different heights on both sides of the beam. Figure 3 is a schematic diagram 3 of the construction of a conventional structure with floor slabs of different heights on both sides of the beam. Figure 4 is a construction schematic diagram 1 of an embodiment of the present invention. Figure 5 is a second construction schematic diagram of the above embodiment of the present invention. FIG. 5A is a partial enlarged view of part A of FIG. 5 . Figure 6 is the third construction schematic diagram of the above embodiment of the present invention. Figure 7 is a construction diagram 4 of the above embodiment. Figure 8 is a construction diagram 5 of the above embodiment. FIG. 8A is a partial enlarged view of part B of FIG. 8 . Figure 9 is a schematic diagram of the buckle plate used in the above embodiment of the present invention. Figure 10 is a schematic diagram of another embodiment of the present invention. Figure 11 is a schematic cross-sectional view of the above embodiment of the present invention.

1:建築結構 1: Building structure

2:第一板 2: First board

5:第四板 5:Fourth board

6:蓋槽鐵 6: Cover trough iron

7:對拉桿 7: Pair the tie rod

8:填充空間 8: Fill the space

11:預鑄梁/半預鑄梁 11:Haixuanliang/Half Haixuanliang

12:第一樓地板 12:First floor floor

13:第二樓地板 13: Second floor floor

14:第一結構 14:First structure

21:連接部分 21:Connection part

22:上邊緣 22:Top edge

23:底端 23: Bottom

24:內側面 24: Medial side

51:底端 51: Bottom

90:樓板鋼筋 90: Floor steel bars

111:頂表面 111:Top surface

112:箍筋 112: stirrups

113:外側 113:Outside

114:鋼筋 114:Rebar

115:底表面 115: Bottom surface

121:端 121:end

131:端 131:end

141:第一側 141: First side

142:第二側 142: Second side

1121:外側 1121:Outside

d1:第一預定距離 d1: first predetermined distance

d2:第二預定距離 d2: second predetermined distance

H:高度差 H: Height difference

Claims (10)

一種建造一建築結構之方法,包括: 提供一預鑄梁,其在一第一軸向方向延伸; 提供一第一板,其自該預鑄梁的一外側向上延伸; 提供一第二板,並將其一端水平地固定於於該第一板之一上邊緣,該第二板作為一第一樓地板之一底模板,並具有一第一高度; 提供一第三板,其一端水平地設置於該預鑄梁上,並位於該第一板之相對側,該第三板作為一第二樓地板之一底模板,並具有一第二高度,其中該第一高度高於該第二高度; 提供一第四板,其垂直設置於該第一之相對側,使其與該第一板大致平行,且其底端與該第三板間隔一第一預定距離; 藉此該預鑄梁、該第一板、該第二板、該第三板及該第四板之間形成一填充空間;且 將混凝土灌漿至該填充空間中待凝固後以形成該建築結構。 A method of constructing a building structure consisting of: Provide a Qixuan beam extending in a first axial direction; Provide a first plate extending upward from an outer side of the girder beam; Provide a second board and fix one end thereof horizontally to an upper edge of the first board. The second board serves as a bottom formwork of a first floor and has a first height; A third board is provided, one end of which is horizontally disposed on the girder and located on the opposite side of the first board. The third board serves as a bottom formwork of a second floor and has a second height, wherein the first height is higher than the second height; Provide a fourth plate, which is vertically disposed on the opposite side of the first plate so that it is substantially parallel to the first plate, and its bottom end is spaced a first predetermined distance from the third plate; Thereby, a filling space is formed between the girder, the first plate, the second plate, the third plate and the fourth plate; and Concrete is grouted into the filled space and allowed to solidify to form the building structure. 如請求項1之方法,其中提供該第一板包括在該預鑄梁之預鑄過程中將該第一板之一連接部分設置於該預鑄梁中之外側並將該預鑄梁及該第一板之該連接部分一起灌漿。The method of claim 1, wherein providing the first plate includes arranging a connecting portion of the first plate on the outside of the center beam and connecting the tie beam and the first The joints of the panels are grouted together. 如請求項1之方法,進一步包括: 提供至少一對拉桿並將該第四板及該第一板經由該對拉桿的兩端連接,以使該第四板及該第一板之間保持一第二預定距離。 The method of claim 1 further includes: At least one pair of tie rods is provided and the fourth plate and the first plate are connected via two ends of the pair of tie rods, so that a second predetermined distance is maintained between the fourth plate and the first plate. 如請求項2之方法,其中在該預鑄梁之預鑄過程中將該第一板之一連接部分設置於該預鑄梁中包括將該第一板設置於該預鑄梁中之箍筋的外側,且使得該第一板的外表面與該預鑄梁之對應外表面大致齊平。The method of claim 2, wherein arranging a connecting portion of the first plate in the yixuan beam during the yoke beam process includes arranging the first plate on the outside of the stirrups in the yixuan beam. , and make the outer surface of the first plate substantially flush with the corresponding outer surface of the Qixuan beam. 如請求項1-3之任一項之方法,其中提供提供該預鑄梁,包括提供一半預鑄梁,其中複數個鋼筋自該半預鑄梁頂部伸出,以與該預鑄梁上方之該建築結構的鋼筋綁紮結合,該半預鑄梁的頂表面係一粗糙的表面。For example, the method of claim 1-3, wherein providing the Kaifeng beam includes providing half of the Kaifeng beam, wherein a plurality of steel bars extend from the top of the half Kaifeng beam to connect with the top of the Kaixuan beam. The steel bars of the building structure are tied together, and the top surface of the half-joist beam has a rough surface. 如請求項4之方法,其中該第一板之該連接部分之位於該預鑄梁中之一底端與該預鑄梁之頂表面之距離至少大於8.8 cm。The method of claim 4, wherein the distance between a bottom end of the connecting portion of the first plate located in the girder and the top surface of the girder is at least greater than 8.8 cm. 如請求項1-3之任一項之方法,其中將該第二板之一端水平地固定於於該第一板之一上邊緣包括:先將一蓋槽鐵設置於該第一板之該上邊緣,再將該第二板焊接於該蓋槽鐵上。The method of any one of claims 1-3, wherein horizontally fixing one end of the second plate to an upper edge of the first plate includes: first setting a cover channel iron on the first plate On the upper edge, the second plate is welded to the cover channel iron. 一種建築結構,其包括: 一預鑄梁,其在一第一軸向方向延伸且具有一頂表面; 一第一板,其自該預鑄梁的一外側向上延伸; 一第一結構,其與該第一板之側面及該預鑄梁之該頂表面相連接; 一第一樓地板,其一端與該第一結構的上部的一第一側相連接;以及 一第二樓地板,其一端與該第一結構的下部的一第二側相連接,該第一側與該第二側為相對側; 其中該第一樓地板與該第二樓地板具有一高度差H。 A building structure consisting of: a girder beam extending in a first axial direction and having a top surface; a first plate extending upward from an outer side of the girder beam; A first structure connected to the side of the first plate and the top surface of the girder; a first floor floor having one end connected to a first side of the upper portion of the first structure; and a second floor, one end of which is connected to a second side of the lower part of the first structure, the first side and the second side being opposite sides; There is a height difference H between the first floor and the second floor. 如請求項8之建築結構,其中該預鑄梁係一半預鑄梁,其中複數個鋼筋自該半預鑄梁頂部伸出,以與該預鑄梁上方之該第一結構中的鋼筋綁紮結合,其中該第一板為一勁扣版且一蓋槽鐵設置於該第一板之一上邊緣上。Such as requesting the building structure of item 8, wherein the Haixuan beam is a half Haixuan beam, in which a plurality of steel bars extend from the top of the half Haixuan beam to be tied with the steel bars in the first structure above the Haixuan beam. , wherein the first plate is a buckle plate and a cover channel iron is provided on an upper edge of the first plate. 如請求項8之建築結構,其中該高度差H為20 cm、40 cm或60 cm。For example, the building structure of claim 8, wherein the height difference H is 20 cm, 40 cm or 60 cm.
TW111132045A 2022-08-25 2022-08-25 Architecture structure and method of constructing the same TWI816527B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW111132045A TWI816527B (en) 2022-08-25 2022-08-25 Architecture structure and method of constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW111132045A TWI816527B (en) 2022-08-25 2022-08-25 Architecture structure and method of constructing the same

Publications (2)

Publication Number Publication Date
TWI816527B true TWI816527B (en) 2023-09-21
TW202409389A TW202409389A (en) 2024-03-01

Family

ID=88966265

Family Applications (1)

Application Number Title Priority Date Filing Date
TW111132045A TWI816527B (en) 2022-08-25 2022-08-25 Architecture structure and method of constructing the same

Country Status (1)

Country Link
TW (1) TWI816527B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN217439000U (en) * 2022-05-20 2022-09-16 上海凯汇建筑设计有限公司 Shear wall head structure
CN217461120U (en) * 2022-05-20 2022-09-20 池州市江口建筑安装工程有限公司 Steel bar truss floor slab height difference connecting structure with detachable bottom die

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN217439000U (en) * 2022-05-20 2022-09-16 上海凯汇建筑设计有限公司 Shear wall head structure
CN217461120U (en) * 2022-05-20 2022-09-20 池州市江口建筑安装工程有限公司 Steel bar truss floor slab height difference connecting structure with detachable bottom die

Also Published As

Publication number Publication date
TW202409389A (en) 2024-03-01

Similar Documents

Publication Publication Date Title
KR101921715B1 (en) Precast concrete panel, manufacturing method of the precast concrete panel and slab construction method using the precast concrete panel
US20190226210A1 (en) Beam-column connection structure and method for forming the same
US10837173B2 (en) Beam-column connection structure and method of making the same
US8549805B2 (en) Grid-type drop-panel structure, and a construction method therefor
KR101030419B1 (en) Joint structure of vertical member and horizontal member
KR101301076B1 (en) Wall structure construction method using precast front wall panel and precast back wall panel
JP6645894B2 (en) Construction method of beam-column joint structure
KR101098693B1 (en) Reinforced Concrete Frame Structure having High Flexibility in Beam-Column Joint
JP7228398B2 (en) Joint structure of CFT column and RC column
JP2010242390A (en) Joining method and structure of column-beam joint part having steel brace
JP7430343B2 (en) Structures and their construction methods
TWI816527B (en) Architecture structure and method of constructing the same
KR101105883B1 (en) Basic mat constructing method of high rise concrete structure
JP5869717B1 (en) Existing concrete structure reinforcement structure
KR101967037B1 (en) the improved steel beam and girder structure for lowering story-height
KR101260392B1 (en) Precast concrete column and beam unit assembling structure being connected in the low bending moment zone
KR101346736B1 (en) Improved Semi-concrete filled tube Column Structure
KR101324884B1 (en) Hybrid building construction method combining dry type and wet type
KR20100101398A (en) Spacer inserted in slab and method using it
EP1416101A1 (en) Composite beam
KR100977275B1 (en) Connecting structure for form-less column and deck beams, and constructing method thereof
KR102244658B1 (en) Method for constructing flat slab structure with drop panel
JP3384785B2 (en) Construction method of damping wall
JPH11158813A (en) Concrete pier constructing method
CN215858481U (en) Anti-seismic concrete floor