KR101260392B1 - Precast concrete column and beam unit assembling structure being connected in the low bending moment zone - Google Patents

Precast concrete column and beam unit assembling structure being connected in the low bending moment zone Download PDF

Info

Publication number
KR101260392B1
KR101260392B1 KR1020110130375A KR20110130375A KR101260392B1 KR 101260392 B1 KR101260392 B1 KR 101260392B1 KR 1020110130375 A KR1020110130375 A KR 1020110130375A KR 20110130375 A KR20110130375 A KR 20110130375A KR 101260392 B1 KR101260392 B1 KR 101260392B1
Authority
KR
South Korea
Prior art keywords
column
concrete
bracket
beam unit
pillar
Prior art date
Application number
KR1020110130375A
Other languages
Korean (ko)
Inventor
김선국
홍원기
이성호
박선치
Original Assignee
(주)케이에이치하우징솔루션스
경희대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)케이에이치하우징솔루션스, 경희대학교 산학협력단 filed Critical (주)케이에이치하우징솔루션스
Priority to KR1020110130375A priority Critical patent/KR101260392B1/en
Application granted granted Critical
Publication of KR101260392B1 publication Critical patent/KR101260392B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/383Connection of concrete parts using adhesive materials, e.g. mortar or glue
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE: A prefabricated structure of a PC(precast) concrete column and a beam unit is provided to improve structural performance with respect to vertical and horizontal loads and to rapidly perform a task in high-altitude. CONSTITUTION: A PC concrete column and a beam unit joined in a low bending moment zone comprises an upper PC column(UC), a lower PC column(DC), a column re-bar(CB), a bracket member(110), lower bracket concrete(120), joint concrete(200), and a low bending moment joint material. The lower bracket concrete and joint concrete are integrally poured for pre-producing PC columns and beams for one unit or floor. The upper part of the upper PC column and the lower part of the lower PC column are positioned in the low bending moment zone. Both ends of the bracket member are positioned in a beam low bending moment zone(BLM).

Description

저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조{Precast Concrete Column And Beam Unit Assembling Structure Being Connected In The Low Bending Moment Zone}Precast Concrete Column And Beam Unit Assembling Structure Being Connected In The Low Bending Moment Zone}

본 발명은 PC기둥에서 여러 절 또는 여러 층의 PC기둥을 간편하게 현장조립할 수 있는 조립식 구조에 관한 것으로, The present invention relates to a prefabricated structure that can be easily assembled on-site as a PC column of several sections or layers in the PC pillar,

사전 제작된 1절 또는 1개층 PC기둥 및 보유닛에서 기둥(Column)의 연결부는 수평, 수직 하중시 발생하는 저모멘트존(Low Bending Moment Part)에서 조립하고 보(Beam)의 연결부는 수직하중시 발생하는 저모멘트존(Low Bending Moment Part)에서 조립할 수 있도록 하여 설치 전 또는 후로 수직 및 수평하중에 대한 구조적 성능이 우수한 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조에 관한 것이다.
In prefabricated single or single-layer PC columns and beam units, the connection of the columns is assembled in the low bending zone, which occurs during horizontal and vertical loads, and the connection of the beams is applied during vertical loads. The present invention relates to a prefabricated structure of a PC column and beam units connected in a low moment zone having excellent structural performance against vertical and horizontal loads before or after installation by enabling assembly in a low moment zone generated.

근래에는 초고층 건축물의 수요증가 및 건식화 기조에 따라 PC구조(Precast Concrete Structure)의 수요가 늘고 있다. In recent years, the demand for precast concrete structures is increasing due to the increase in the demand for high-rise buildings.

종래의 PC구조는 PC기둥유닛 및 PC보유닛을 사전제작하여 현장에서 조립하여 시공한다. 상기 종래의 PC구조는 PC기둥유닛 상호간의 결합부는 별론으로 하더라도 PC기둥유닛과 PC보유닛의 결합부 시공은 각 유닛사이의 작은 공간에서 철근배근 등의 작업이 기능공의 수작업으로 이루어지므로 기능공의 숙련도에 따라 작업속도 및 품질의 많은 차이를 보이며 안전사고의 위험이 높다. 또한 PC기둥유닛과 PC보유닛의 결합부를 보강하기 위한 그라우팅 또는 콘크리트 타설시 거푸집 작업을 선행하게 되는 데, 이때 상기 결합부의 복잡한 형상으로 인하여 거푸집을 현장에서 일일이 절단 및 제작하여 사용하는 번거로움이 있으며 고공에서 수작업으로 이루어지는 특성상 많은 시간과 주의를 요하게 된다.The conventional PC structure is manufactured by pre-fabricating the PC pillar unit and the PC beam unit in the field. In the conventional PC structure, even though the coupling portions between the PC pillar units are separate, the construction of the coupling portions of the PC pillar units and the PC beam units is performed by the reinforcement of the reinforcement in the small space between the units. According to this, there are many differences in work speed and quality, and the risk of safety accident is high. In addition, when the grouting or concrete pouring to reinforce the coupling portion of the PC column unit and PC beam unit is preceded by the formwork, there is a hassle to cut and form the form in the field due to the complex shape of the coupling portion. It takes a lot of time and attention due to the nature of manual work at high altitude.

철골조의 경우 기둥 및 보 등의 구조체를 철골로 빠르게 먼저 시공하고 철골로 시공된 구조체를 지지대로 삼아 다른 모든 공종이 층별로 독립하여 병행 수행될 수 있다. 따라서 철골조의 슬래브공사를 포함한 구조체공사는 전체공정에서 크리티칼패스(critical path)가 되지 않아 공기를 지연시키지 못한다.In the case of steel frames, structures such as columns and beams can be quickly constructed first with steel frames, and all other types of construction can be performed independently and in parallel by using the structures constructed with steel frames as supports. Therefore, the structural work including the slab construction of steel frame does not become a critical path in the whole process and does not delay the air.

그러나 PC구조의 경우 하부층의 구조체공사(기둥 및 보) 및 슬래브공사 등이 마치기 전에는 상부층의 구조체 공사 등을 수행할 수 없으며 상술한 바와 같이 PC기둥유닛과 PC보유닛의 결합부 시공에 많은 시간이 소요되므로, PC구조의 구조체공사는 전체공정에서 크리티칼패스(critical path)가 되어 공기를 지연시키는 문제점이 지적되어 왔다.However, in the case of the PC structure, it is impossible to perform the structure construction of the upper layer until the structure construction (column and beam) and the slab construction of the lower layer are completed, and as described above, a lot of time is required in the construction of the coupling portion of the PC pillar unit and the PC beam unit. As a result, it has been pointed out that the construction of the PC structure becomes a critical path in the whole process and delays the air.

도 1은 건물의 기둥 및 보 등의 조합으로 이루어진 구조체와 한 구간의 모멘트도를 도시한 것이다. 도 1에 도시된 바와 같이 각층 또는 각절의 기둥에 작용하는 모멘트(파란색 실선)를 살펴보면 보 또는 슬래브 레벨의 상부 지점에 최소모멘트(CLM)가 작용하며 보통 보 또는 슬래브 레벨에서 최대모멘트(HM)가 작용한다. 또한 보에 작용하는 수직하중에 의한 모멘트(빨간색 실선)를 살펴보면 기둥에서 이격된 지점에 최소모멘트(BLM)가 작용하며 보통 보와 기둥의 접합점에서 최대모멘트가 작용하는 고모멘트존(HM)이 형성된다.1 illustrates a structure consisting of a combination of pillars and beams of a building and a moment diagram of a section. As shown in FIG. 1, when the moment (blue solid line) acting on the pillar of each layer or section is examined, the minimum moment (CLM) acts at the upper point of the beam or slab level, and the maximum moment (HM) is usually applied at the beam or slab level. Works. In addition, when looking at the moment due to the vertical load acting on the beam (solid red line), the minimum moment (BLM) is applied at the point spaced apart from the column, and the high moment zone (HM) is formed at the junction between the beam and the column. do.

따라서 이와 같은 종래의 PC구조는 PC기둥이나 PC보의 설치시 연결부의 시공을 어렵게 하고 안전사고의 위험으로 이어진다. 또한 시공 중 예기치 않은 하중으로 인하여 전체 PC구조물에 악영향을 주는 구조적 심각성도 지적되어 왔다. Therefore, such a conventional PC structure makes it difficult to install the connecting portion when installing the PC pillar or PC beam and leads to a risk of safety accident. It has also been pointed out the structural severity that adversely affects the entire PC structure due to unexpected loads during construction.

상술한 종래의 PC구조의 문제점은 모두 기둥부재 및 보부재가 크리티칼패스(critical path)가 되기 때문에 1층, 1절, 보레벨 또는 슬래브레벨 등에 맞추어 단위유닛으로 디자인한 것으로 기둥, 보 연결부의 시공상 편의성 및 구조적 안전성이 간과되고 있다. The problem of the conventional PC structure described above is that the pillar member and the beam member are all critical paths, so that they are designed as a unit unit according to the first floor, section 1, beam level, or slab level. Construction convenience and structural safety have been overlooked.

따라서 도 1에 도시된 바와 같이 PC기둥유닛 및 보유닛의 연결부를 모멘트가 적게 작용하는 저모멘트존(CLM, BLM)에 위치시켜 모든 PC기둥 및 보의 유닛을 지상에서 안전하게 제작한 후 고공으로 양중하여, 단순히 고공에서는 연결 작업만 수행 하도록 함으로써 고공에서의 시공 난이도가 높은 작업을 배제하여 시공성 및 안전성 등을 증가시키고, 좌굴이나 수직 및 수평하중에 대한 구조적 성능이 우수한 PC기둥 및 보 유닛 접합구조의 개발이 시급한 실정이다.
Therefore, as shown in Figure 1, the connection between the PC pillar unit and the beam unit is placed in the low moment zone (CLM, BLM) with less moment acting to securely manufacture all the units of the PC pillar and beam on the ground, and then lifted into the air Therefore, by simply performing the connection work at high altitudes, the construction difficulty in high altitudes is eliminated to increase workability and safety, and the structure of the PC column and beam unit joint structure having excellent structural performance against buckling or vertical and horizontal loads Development is urgent.

본 발명은 상기한 바와 같은 종래의 제반 문제점을 해소하기 위해서 제시되는 것이다. 그 목적은 다음과 같다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned problems of the related art. The purpose is as follows.

첫째, PC기둥 및 보 유닛사이 및 PC기둥 및 보 유닛과 보부재의 연결부를 고모멘트존이 아닌 저모멘트존에 위치시켜 수직 및 수평하중에 대한 구조적 성능이 우수한 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공하고자 한다. First, the PC pillar and beam connected between the PC pillar and beam unit, and the PC pillar and beam unit and beam member in the low moment zone, not the high moment zone, and have excellent structural performance against vertical and horizontal loads. To provide a prefabricated structure of the beam unit.

둘째, 종래 고공에서의 복잡한 작업을 미리 지상에서 포함하여 PC기둥 및 보 유닛으로 PC부재를 제작함으로써 고공에서 시공이 편리하고 빠른 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공하고자 한다. Second, to provide a prefabricated structure of the PC column and beam unit connected in the low-moment zone, which is convenient in construction and fast in high altitude by manufacturing a PC member with a PC column and beam unit including the conventional complex work in the ground in advance. .

셋째, 설치현장에서 간단히 설치할 수 있어 미숙련공도 안전하게 소정의 품질확보가 가능한 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공하고자 한다. Third, it is easy to install at the installation site to provide a prefabricated structure of the PC column and beam unit that is connected in the low moment zone that can secure a certain quality even inexperienced workers.

넷째, 습식작업이 최소화된 건식공법으로 시공되므로 시공성이 개선된 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공하고자 한다.
Fourth, to provide a prefabricated structure of the PC column and beam unit connected in the low moment zone improved construction work because the construction method is minimized wet work.

상기한 기술적 과제를 해결하기 위해 본 발명은 선제작된 1절 또는 1개층의 PC기둥 및 보유닛을 서로 결합하고 상기 PC기둥 및 보유닛에 다른 PC기둥 및 보유닛 및 보부재를 결합하는 구조에서, In order to solve the above technical problem, the present invention combines a prefabricated single or one layer of PC pillar and beam unit with each other, and in the structure of coupling the other PC pillar and beam unit and beam member to the PC pillar and beam unit. ,

상부PC기둥(UC); 상기 상부PC기둥(UC)에서 아래로 이격되어 설치되는 하부PC기둥(DC); 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이에 수직으로 배근되는 다수개의 기둥철근(CB); 상기 상부PC기둥(UC)과 하부PC기둥(DC)의 이격된 공간에 수평으로 삽입 설치되는 브래킷부재(110); 상기 브래킷부재(110)의 하부에 타설되어 설치되는 브래킷하부콘크리트(120); 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이의 이격된 공간과 상기 브래킷하부콘크리트(120) 사이에 타설되는 조인트콘크리트(200); 및, 상기 상부PC기둥(UC)의 상부 또는 상기 하부PC기둥(DC)의 하부 중 어느 하나 이상에 설치되어 다른 PC기둥 및 보유닛과 접합주를 형성하는 저모멘트연결부연결재(CP);를 포함하여 구성되는 PC기둥 및 보유닛으로, Upper PC column (UC); A lower PC column (DC) installed spaced apart from the upper PC column (UC); A plurality of column reinforcement bars (CB) vertically arranged between the upper PC column (UC) and the lower PC column (DC); A bracket member 110 horizontally inserted into the spaced space between the upper PC column UC and the lower PC column DC; A lower bracket concrete 120 which is installed by being poured under the bracket member 110; A joint concrete (200) placed between the spaced space between the upper PC column (UC) and the lower PC column (DC) and the bracket lower concrete 120; And a low moment connector connecting material (CP) installed at any one or more of the upper part of the upper PC column (UC) or the lower part of the lower PC column (DC) to form a joining column with other PC columns and beam units. PC column and beam unit configured by

상기 브래킷하부콘크리트(120)와 조인트콘크리트(200)는 일체로 타설되어 1절 또는 1개층의 상기 PC기둥 및 보유닛이 사전 제작되고, 상기 상부PC기둥(UC)의 상부 및 상기 하부PC기둥(DC)의 하부는 건물 전체에서 기둥에 작용하는 모멘트가 적거나 최소인 기둥 저모멘트존(CLM)에 위치하며 상기 브래킷부재(110)의 양단은 건물 전체에서 보에 작용하는 수직하중에 의한 모멘트가 적거나 최소인 보 저모멘트존(BLM)에 위치하여 다른 PC기둥 및 보유닛 그리고 보부재(B)와의 결합이 모멘트가 적거나 최소인 곳에서 이루어지는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공한다.
The bracket lower concrete 120 and the joint concrete 200 are integrally placed so that the PC pillar and the beam unit of one section or one layer are pre-fabricated, and the upper and lower PC pillars of the upper PC pillar UC ( The lower part of DC) is located in the pillar low moment zone (CLM) where the moment acting on the pillar is small or minimum throughout the building, and both ends of the bracket member 110 have the moment due to the vertical load acting on the beam throughout the building. Located on the small or minimum beam moment zone (BLM), the PC pillar connected to the other PC column, beam unit, and beam member (B) is made in a place where the moment is small or minimal. And a prefabricated structure of the beam unit.

본 발명에 따르면 다음과 같은 효과가 기대된다.According to the present invention, the following effects are expected.

첫째, PC기둥 및 보 유닛사이 및 PC기둥 및 보 유닛과 보부재의 연결부를 고모멘트존이 아닌 저모멘트존에 위치시켜 수직 및 수평하중에 대한 구조적 성능이 우수한 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공한다. First, the PC pillar and beam connected between the PC pillar and beam unit, and the PC pillar and beam unit and beam member in the low moment zone, not the high moment zone, and have excellent structural performance against vertical and horizontal loads. Provides a prefabricated structure of the beam unit.

둘째, 종래 고공에서의 복잡한 작업을 미리 지상에서 포함하여 PC기둥 및 보 유닛으로 PC부재를 제작함으로써 고공에서 시공이 편리하고 빠른 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공한다. Second, by providing a PC member with a PC column and beam unit, including the complex work in the conventional high ground in advance, to provide a prefabricated structure of the PC column and beam unit connected in a low moment zone is convenient and fast construction at high altitude.

셋째, 설치현장에서 간단히 설치할 수 있어 미숙련공도 안전하게 소정의 품질확보가 가능한 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공한다. Third, it can be easily installed at the installation site provides a prefabricated structure of the PC column and beam unit that is connected in the low moment zone that can secure a certain quality even inexperienced workers.

넷째, 습식작업이 최소화된 건식공법으로 시공되므로 시공성이 개선된 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공한다.
Fourth, it provides a prefabricated structure of the PC column and beam unit connected in the low moment zone is improved construction work because the construction method is minimized wet work.

도 1은 건물의 기둥 및 보 등의 조합으로 이루어진 구조체와 한 구간의 모멘트도를 도시한 것이다.
도 2는 본 발명의 PC기둥 및 보유닛의 결합사시도이다.
도 3은 본 발명의 PC기둥 및 보유닛의 다른 실시예의 결합사시도이다.
도 4는 본 발명에 사용되는 브래킷부재의 사시도이다.
도 5는 본 발명에 사용되는 저모멘트연결부연결재가 하부PC기둥과 상부PC기둥 사이를 연결한 모습을 도시한 것이다.
도 6은 본 발명의 PC기둥 및 보유닛의 다른 실시예의 결합사시도이다.
도 7은 본 발명에 사용되는 브래킷부재와 수직보강재 그리고 상하부플레이트의 결합사시도이다.
도 8은 본 발명에 사용되는 브래킷부재와 수직보강재의 결합사시도이다.
도 9는 본 발명의 PC기둥 및 보유닛의 다른 실시예의 결합사시도이다.
도 10은 본 발명에 사용되는 브래킷부재와 임베드플레이트 그리고 스터드볼트의 결합사시도이다.
도 11은 본 발명의 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 도시한 것이다.
도 12는 본 발명의 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조에서 기둥의 연결부를 도시한 것이다.
도 13은 횡력으로 구조체에 작용하는 모멘트를 도시한 것이다.
도 14는 도 13의 부분확대도이다.
도 15는 수직력으로 구조체에 작용하는 모멘트를 도시한 것이다.
도 16은 도 15의 부분확대도이다.
도 17 및 18은 본 발명의 PC기둥 및 보유닛의 다른 실시예의 결합사시도이다.
1 illustrates a structure consisting of a combination of pillars and beams of a building and a moment diagram of a section.
Figure 2 is a combined perspective view of the PC column and beam unit of the present invention.
Figure 3 is a combined perspective view of another embodiment of the PC column and beam unit of the present invention.
Figure 4 is a perspective view of the bracket member used in the present invention.
Figure 5 shows the low moment connecting portion used in the present invention connecting the lower PC column and the upper PC column.
6 is a combined perspective view of another embodiment of the PC column and beam unit of the present invention.
Figure 7 is a perspective view of the combination of the bracket member and the vertical reinforcement and the upper and lower plates used in the present invention.
Figure 8 is a perspective view of the combination of the bracket member and the vertical reinforcement used in the present invention.
9 is a combined perspective view of another embodiment of the PC column and beam unit of the present invention.
10 is a perspective view of the combination of the bracket member and the embed plate and the stud bolt used in the present invention.
Figure 11 shows the prefabricated structure of the PC column and beam unit connected in the low moment zone of the present invention.
Figure 12 shows the connection of the pillar in the prefabricated structure of the PC column and beam unit connected in the low moment zone of the present invention.
13 shows the moment acting on the structure with lateral forces.
14 is a partially enlarged view of FIG. 13.
15 shows the moment acting on the structure with normal force.
FIG. 16 is a partially enlarged view of FIG. 15.
17 and 18 is a perspective view of a combination of another embodiment of the PC column and beam unit of the present invention.

이하 첨부한 도면과 함께 상기와 같은 본 발명의 개념이 바람직하게 구현된 실시예를 통하여 본 발명을 더욱 상세하게 설명한다.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명의 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조는 선제작된 1절 또는 1개층의 PC기둥 및 보유닛을 서로 결합하고 상기 PC기둥 및 보유닛에 다른 PC기둥 및 보유닛 및 보부재를 결합하는 구조에서, The prefabricated structure of the PC column and beam unit connected in the low moment zone of the present invention combines the pre-fabricated one or one layer of the PC column and beam unit with each other, and the PC column and beam unit and the other PC pillar and beam unit and In the structure of joining the beam members,

상부PC기둥(UC); 상기 상부PC기둥(UC)에서 아래로 이격되어 설치되는 하부PC기둥(DC); 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이에 수직으로 배근되는 다수개의 기둥철근(CB); 상기 상부PC기둥(UC)과 하부PC기둥(DC)의 이격된 공간에 수평으로 삽입 설치되는 브래킷부재(110); 상기 브래킷부재(110)의 하부에 타설되어 설치되는 브래킷하부콘크리트(120); 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이의 이격된 공간과 상기 브래킷하부콘크리트(120) 사이에 타설되는 조인트콘크리트(200); 및, 상기 상부PC기둥(UC)의 상부 또는 상기 하부PC기둥(DC)의 하부 중 어느 하나 이상에 설치되어 다른 PC기둥 및 보유닛과 접합주를 형성하는 저모멘트접합부연결재(CP);를 포함하여 구성되는 PC기둥 및 보유닛으로, Upper PC column (UC); A lower PC column (DC) installed spaced apart from the upper PC column (UC); A plurality of column reinforcement bars (CB) vertically arranged between the upper PC column (UC) and the lower PC column (DC); A bracket member 110 horizontally inserted into the spaced space between the upper PC column UC and the lower PC column DC; A lower bracket concrete 120 which is installed by being poured under the bracket member 110; A joint concrete (200) placed between the spaced space between the upper PC column (UC) and the lower PC column (DC) and the bracket lower concrete 120; And a low moment junction connecting member (CP) installed at any one or more of the upper part of the upper PC column (UC) or the lower part of the lower PC column (DC) to form a joining column with other PC columns and beam units. PC column and beam unit configured by

상기 브래킷하부콘크리트(120)와 조인트콘크리트(200)는 일체로 타설되어 1절 또는 1개층의 상기 PC기둥 및 보유닛이 사전 제작되고, 상기 상부PC기둥(UC)의 상부 및 상기 하부PC기둥(DC)의 하부는 건물 전체에서 기둥에 작용하는 모멘트가 적거나 최소인 기둥 저모멘트존(CLM)에 위치하며 상기 브래킷부재(110)의 양단은 건물 전체에서 보에 작용하는 수직하중에 의한 모멘트가 적거나 최소인 보 저모멘트존(BLM)에 위치하여 다른 PC기둥 및 보유닛 그리고 보부재(B)와의 결합이 모멘트가 적거나 최소인 곳에서 이루어지는 것을 특징으로 한다.
The bracket lower concrete 120 and the joint concrete 200 are integrally placed so that the PC pillar and the beam unit of one section or one layer are pre-fabricated, and the upper and lower PC pillars of the upper PC pillar UC ( The lower part of DC) is located in the pillar low moment zone (CLM) where the moment acting on the pillar is small or minimum throughout the building, and both ends of the bracket member 110 have the moment due to the vertical load acting on the beam throughout the building. Located in the small or minimum beam moment zone (BLM) is characterized in that the coupling with the other PC column and beam unit and the beam member (B) is made where the moment is small or minimum.

도 2는 본 발명의 PC기둥 및 보유닛의 결합사시도이고, 도 3 및 6 그리고 9는 본 발명의 PC기둥 및 보유닛의 다른 실시예의 결합사시도이다.Figure 2 is a combined perspective view of the PC column and beam unit of the present invention, Figures 3, 6 and 9 are combined perspective views of another embodiment of the PC column and beam unit of the present invention.

본 발명의 PC기둥 및 보유닛은 도 2에 도시된 바와 같이 크게 상부PC기둥(UC), 하부PC기둥(DC), 기둥철근(CB), 브래킷부재(110), 브래킷하부콘크리트(120), 조인트콘크리트(200) 및 저모멘트연결부연결재(CP)를 포함하여 구성된다.
PC column and beam unit of the present invention as shown in Figure 2, large upper PC column (UC), lower PC column (DC), column reinforcement (CB), bracket member 110, bracket lower concrete 120, It comprises a joint concrete 200 and low moment connection portion connecting member (CP).

상기 상부PC기둥(UC) 및 하부PC기둥(DC)은 통상적으로 제작되는 PC기둥의 구조를 가지며 상호 이격되어 설치된다.The upper PC column (UC) and the lower PC column (DC) has a structure of a PC pillar that is usually manufactured and are spaced apart from each other.

상기 기둥철근(CB)은 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이에 수직으로 다수개가 배근되며 상기 상부PC기둥(UC)과 하부PC기둥(DC) 내부에서 상호연장되어 상부하중을 하부로 전달하는 역할을 한다.
The column reinforcing bars (CB) are vertically arranged between the upper PC column (UC) and the lower PC column (DC) and are extended in the upper PC column (UC) and the lower PC column (DC) to the upper load It serves to deliver the lower part.

도 4는 본 발명에 사용되는 브래킷부재의 사시도이다.Figure 4 is a perspective view of the bracket member used in the present invention.

상기 브래킷부재(110)는 상기 상부PC기둥(UC)과 하부PC기둥(DC)의 이격된 공간에 수평으로 삽입 설치되는 것으로, 종래의 브래킷은 기둥의 외면에서 조금 돌출되어 설치되었으나 본 발명은 길게 연장되어 보 저모멘트존(BLM)에 양단부가 위치하는 것을 특징으로 한다. 또한 상기 브래킷부재(110)는 H형강, T형강, 역T형강 등 기존의 모든 철골을 이용할 수도 있고 소정의 강도만 보장되면 FRP(fiber-reinforced plastic)와 같은 강화프라스틱 등의 소재도 이용할 수 있다.The bracket member 110 is horizontally inserted into the spaced space between the upper PC column (UC) and the lower PC column (DC), the conventional bracket was installed to protrude a little from the outer surface of the pillar, but the present invention is long It is characterized in that both ends are located in the extended moment zone (BLM). In addition, the bracket member 110 may use all existing steel, such as H-shaped steel, T-shaped steel, inverted T-shaped steel, and may also use a material such as reinforced plastic such as FRP (fiber-reinforced plastic) if only a predetermined strength is ensured. .

상기 브래킷하부콘크리트(120)는 상기 브래킷부재(110)의 하부에 타설되어 설치되는 것으로, 통상적으로 상기 브래킷부재(110)와 함께 합성보의 구조를 가진다. The bracket lower concrete 120 is to be installed in the lower portion of the bracket member 110, typically has a structure of a composite beam with the bracket member 110.

그리고 상기 합성보 구조를 가지기 위하여 통상적인 보상부주근(130), 보하부주근(140), 스트럽철근, 스터드볼트 등이 설치될 수 있다.
And in order to have the composite beam structure, a conventional compensation part root 130, the bottom part 140, a stirrup reinforcement, stud bolts and the like can be installed.

상기 조인트콘크리트(200)는 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이의 이격된 공간과 상기 브래킷하부콘크리트(120) 사이에 타설되는 것으로, 도 9에 도시된 바와 같이 상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이의 이격된 공간을 빈틈없이 채울 수도 있고, 도 2에 도시된 바와 같이 상기 조인트콘크리트(200)의 타설높이는 상기 브래킷하부콘크리트(120)와 동일 레벨이 되어, 상기 조인트콘크리트(200) 상부와 상기 상부PC기둥(UC)의 하부 사이 및 상기 브래킷부재(110) 상부에 일체로 슬래브콘크리트가 타설되는 것을 특징으로 할 수 있다.
The joint concrete 200 is to be placed between the spaced space between the upper PC column (UC) and the lower PC column (DC) and the bracket lower concrete 120, the upper PC as shown in FIG. The spaces spaced between the column UC and the lower PC column DC may be filled without gaps, and as shown in FIG. 2, the placing height of the joint concrete 200 is the same level as that of the lower bracket concrete 120. The slab concrete may be cast integrally between the upper portion of the joint concrete 200 and the lower portion of the upper PC pillar UC and the upper portion of the bracket member 110.

종래의 PC구조는 상부PC기둥, 하부PC기둥, PC보를 상호 조립한 후 상기 PC보에서 연장되는 철근을 상부PC기둥과 하부PC기둥 사이로 일일이 수작업으로 배근하여 연결하고, 부재간 상호 결합부위에 본 발명의 조인트콘크리트(200)와 같은 역할을 수행하는 콘크리트를 타설하기 위하여 복잡한 거푸집 작업을 고공에서 수작업으로 수행하고 콘크리트를 타설하였다. 그러나 본 발명은 이같은 종래의 문제점을 해결하기 위하여 모든 복잡하고 위험한 공정을 포함하여 지상에서 PC부재을 제작하는 것을 특징으로 한다.
In the conventional PC structure, after assembling the upper PC column, the lower PC column, and the PC beam to each other, the rebars extending from the PC beam are manually arranged between the upper PC column and the lower PC column and manually connected to each other. In order to pour concrete to perform the same role as the joint concrete 200 of the invention, the complex formwork was performed by hand at high altitude and poured concrete. However, the present invention is characterized by manufacturing a PC member on the ground, including all complicated and dangerous processes in order to solve such a conventional problem.

도 5는 본 발명에 사용되는 저모멘트연결부연결재가 하부PC기둥과 상부PC기둥 사이를 연결한 모습을 도시한 것이다.Figure 5 shows the low moment connecting portion used in the present invention connecting the lower PC column and the upper PC column.

상기 저모멘트연결부연결재(CP)는 상기 상부PC기둥(UC)의 상부 또는 상기 하부PC기둥(DC)의 하부 중 어느 하나 이상에 설치되어 다른 PC기둥 및 보유닛과 연결부를 형성하는 것으로, 어떠한 형상 및 구조로든 이용할 수 있으나 도 5(a)의 예를 포함하여 본 발명의 출원인 및 발명자가 출원한 특허발명(출원번호 10-2011-0125079)을 이용하는 것이 바람직하다. 그리고 도 5(b)와 같이 보강차원에서 빈틈을 그라우팅하거나 콘크리트을 타설할 수 있다.
The low moment connecting portion (CP) is installed on any one or more of the upper portion of the upper PC column (UC) or the lower portion of the lower PC column (DC) to form a connection portion with the other PC column and beam unit, any shape And it can be used as a structure, but it is preferable to use the patent invention (Application No. 10-2011-0125079) filed by the applicant and the inventor of the present invention, including the example of Figure 5 (a). And as shown in Figure 5 (b) it can grout the gap in the reinforcement dimension or can be poured concrete.

도 7은 본 발명에 사용되는 브래킷부재와 수직보강재 그리고 상하부플레이트의 결합사시도이고, 도 8은 본 발명에 사용되는 브래킷부재와 수직보강재의 결합사시도이다. 7 is a combined perspective view of the bracket member and the vertical reinforcement and the upper and lower plates used in the present invention, Figure 8 is a combined perspective view of the bracket member and the vertical reinforcement used in the present invention.

본 발명은 상기 상부PC기둥(UC)의 하부 및 상기 하부PC기둥(DC)의 상부 사이에는 수직보강재(300)가 더 포함되는 것을 특징으로 할 수 있다. 상기 수직보강재(300)는 상기 기둥철근(CB)을 보완하여 상부하중을 하부로 전달하는 역할을 한다.The present invention may be characterized in that the vertical reinforcing material 300 is further included between the lower portion of the upper PC column (UC) and the upper portion of the lower PC column (DC). The vertical reinforcing material 300 serves to transfer the upper load to the bottom by complementing the column reinforcement (CB).

또한 상기 수직보강재(300)의 상단에는 도 7 또는 아래 그림과 같이 상부플레이트(310)가 상기 상부PC기둥 하부에 밀착되어 설치되고, 상기 수직보강재(300)의 하단에는 하부플레이트(320)가 상기 하부PC기둥 상부에 밀착되어 설치될 수 있다. In addition, the upper plate 310 is installed on the upper end of the vertical reinforcement 300 in close contact with the lower portion of the upper PC pillar, as shown in Figure 7 or below, the lower plate 320 is the lower end of the vertical reinforcement 300 It can be installed in close contact with the upper PC column.

Figure 112011097253563-pat00001
Figure 112011097253563-pat00001

이때는 도 3 또는 아래 그림에 도시된 바와 같이 상기 조인트콘크리트(200)가 상기 상부플레이트(310)와 하부플레이트(320) 사이의 이격된 공간을 빈틈없이 채울 수도 있고, In this case, as shown in FIG. 3 or the figure below, the joint concrete 200 may fill the space spaced between the upper plate 310 and the lower plate 320 without gaps.

Figure 112011097253563-pat00002

Figure 112011097253563-pat00002

도 6 또는 아래 그림에 도시된 바와 같이 상기 조인트콘크리트(200)의 타설높이는 상기 브래킷하부콘크리트(120)와 동일 레벨이 되어, 상기 조인트콘크리트(200) 상부와 상기 상부플레이트(310)의 하부 사이 및 상기 브래킷부재(110) 상부에 일체로 슬래브콘크리트가 타설되는 것을 특징으로 할 수 있다. As shown in FIG. 6 or below, the placing height of the joint concrete 200 is the same level as that of the bracket lower concrete 120, between the upper part of the joint concrete 200 and the lower part of the upper plate 310; It may be characterized in that the slab concrete is poured integrally on the bracket member 110.

Figure 112011097253563-pat00003
Figure 112011097253563-pat00003

상기 슬래브콘크리트는 도시되지 않았으나 본 발명의 부재를 모두 설치한 한 데크플레이트 등의 슬래브 공사시 타설되는 콘크리트를 말한다.
Although not shown, the slab concrete refers to concrete that is poured during slab construction such as one deck plate provided with all the members of the present invention.

도 10은 본 발명에 사용되는 브래킷부재와 임베드플레이트 그리고 스터드볼트의 결합사시도이다.10 is a perspective view of the combination of the bracket member and the embed plate and the stud bolt used in the present invention.

도 10에 도시된 바와 같이 본 발명은 상기 브래킷부재(110)의 중앙이 끊긴 형태가 되어 끊긴 부분이 상기 조인트콘크리트(200)에 임베드플레이트(EP) 및 스터드볼트(SB)를 통하여 매립되는 것을 특징으로 할 수 있다.
As shown in FIG. 10, the present invention is characterized in that the center of the bracket member 110 is cut off, and the broken portion is embedded in the joint concrete 200 through an embed plate EP and a stud bolt SB. You can do

도 11은 본 발명의 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 도시한 것이고, 도 12는 본 발명의 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조에서 기둥의 연결부를 도시한 것이다. 그리고 도 13은 횡력으로 구조체에 작용하는 모멘트를 도시한 것이고, 도 14는 도 13의 부분확대도이며, 그리고 도 15는 수직력으로 구조체에 작용하는 모멘트를 도시한 것이고, 도 16은 도 15의 부분확대도이다. 11 is a view illustrating a prefabricated structure of a PC pillar and a beam unit connected in the low moment zone of the present invention, and FIG. 12 is a view illustrating a connection portion of a pillar in the prefabricated structure of the PC pillar and the beam unit connected in the low moment zone of the present invention. It is shown. And FIG. 13 shows moments acting on the structure with lateral forces, FIG. 14 is a partially enlarged view of FIG. 13, and FIG. 15 shows moments acting on the structure with vertical forces, and FIG. 16 is part of FIG. 15. It is an enlarged view.

도 11 내지 16에 도시된 바와 같이 본 발명의 가장 큰 특징은 상기 PC기둥 및 보유닛을 사전 제작하고, 상기 상부PC기둥(UC)의 상부 및 상기 하부PC기둥(DC)의 하부는 건물 전체에서 기둥에 작용하는 모멘트가 적거나 최소인 기둥 저모멘트존(CLM)에 위치하며 상기 브래킷부재(110)의 양단은 건물 전체에서 보에 작용하는 수직하중에 의한 모멘트가 적거나 최소인 보 저모멘트존(BLM)에 위치하여 다른 PC기둥 및 보유닛이나 보부재(B)와의 결합이 모멘트가 적거나 최소인 곳에서 이루어진다는 것이다.11 to 16, the biggest feature of the present invention is the pre-fabrication of the PC column and beam unit, the upper part of the upper PC column (UC) and the lower part of the lower PC column (DC) in the entire building Located in the column low moment zone (CLM) with a small or minimal moment acting on the column, and both ends of the bracket member 110 have a minimum or minimum moment of the moment due to the vertical load acting on the beam throughout the building. It is located at (BLM) and the coupling with other PC column and beam unit or beam member (B) is made where the moment is small or minimal.

보상부주근(130) 및 보하부주근(140)과 보부재(B)와의 결합은 도 11의 확대도에 도시된 바와 같이 커플러를 이용하거나 철근의 겹침이음 등 통상적인 방법을 이용한다.
Combination of the compensation peripheral root 130 and the lower peripheral root 140 and the beam member (B) uses a conventional method such as using a coupler or overlapping reinforcing bars as shown in the enlarged view of FIG.

도 17 및 18은 본 발명의 PC기둥 및 보유닛의 다른 실시예의 결합사시도이다.17 and 18 is a perspective view of a combination of another embodiment of the PC column and beam unit of the present invention.

도 17 및 18에 도시된 다른 실시예는 상기 브래킷부재(110)의 상부에 타설되어 설치되는 브래킷상부콘크리트(122); 및, 상기 브래킷상부콘크리트(122)에 매설되는 인장재(T);를 더 포함하되,Another embodiment shown in Figures 17 and 18 is a bracket upper concrete 122 is installed is installed on top of the bracket member 110; And, the tension member (T) is embedded in the upper concrete bracket (122); further comprising,

상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되고 상기 인장재(T)에는 프리텐션(pre-tension) 또는 포스트텐션(post-tension)이 도입되는 것을 특징으로 한다.The bracket upper concrete 122 and the bracket lower concrete 120 are integrally placed and installed, and the tension member T is characterized in that a pre-tension or post-tension is introduced. .

도 17 및 18에 도시된 본 발명의 다른 실시예는 도면에 시스관 및 정착구 등은 도시되지 않았으나 통상적으로 프리텐션(pre-tension) 또는 포스트텐션(post-tension)을 구현하기 위한 수단이 사용된다. In another embodiment of the present invention shown in Figs. 17 and 18, the sheath tube and the anchorage are not shown in the drawings, but means for implementing pre-tension or post-tension are typically used. .

특히 도 18에 도시된 실시예는 상기 브래킷부재(110)가 H형강, T형강 등 일 경우 상부 플렌지에 구멍을 천공하고 상기 구멍에 상기 인장재(T)를 통과시켜 거치한 후 제작할 수 있다. 이때 상기 인장재(T)는 기둥선을 중심으로 완만한 형의 이상적인 인장곡선을 자동적으로 형성하게 된다.
In particular, the embodiment shown in FIG. 18 may be manufactured after drilling a hole in the upper flange and passing the tension member T through the hole when the bracket member 110 is H-shaped steel, T-shaped steel, or the like. At this time, the tension member (T) automatically forms an ideal tensile curve of a gentle type around the pillar line.

또한 본 발명은 도 17 및 18에 도시된 예에서 상기 인장재(T)가 생략된 실시예로써 상기 브래킷부재(110)의 상부에 타설되어 설치되는 브래킷상부콘크리트(122);를 더 포함하되, 상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조를 제공할 수 있다. 이때 도 17 및 18의 예를 포함하여 본 실시예는 후에 타설될 슬래브콘크리트(미도시)와 시공상의 콜드조인트가 발생될 수 있는 데, 이를 대비한 모든 수단을 사용할 수 있으며 한 예로써 상기 브래킷상부콘크리트(122) 내부에서 상기 슬래브콘크리트(미도시) 쪽으로 돌출되어 상기 슬래브콘크리트(미도시)와 맞물리도록 철근 등을 이용한 스터드볼드를 설치할 수 있다.
In addition, the present invention is an embodiment in which the tension member (T) is omitted in the example shown in Figures 17 and 18 bracket upper concrete 122 is installed on the upper portion of the bracket member 110; The bracket upper concrete 122 and the bracket lower concrete 120 may provide a prefabricated structure of the PC column and beam unit connected in the low moment zone, characterized in that the installation is integrally cast. At this time, the present embodiment, including the example of Figure 17 and 18 can be generated later in the slab concrete (not shown) and construction cold joint, all means can be used to prepare for this, as an example the upper part of the bracket A stud bolt using a rebar or the like may be installed to protrude toward the slab concrete (not shown) in the concrete 122 to engage with the slab concrete (not shown).

결론으로 본 발명은 PC기둥 및 보유닛과 보의 양단에 철골(Erection Steel)로 대표되는 브래킷부재(110)를 삽입함으로써 PC의 경우라도 철골시공처럼 횡저항 시스템인 보만 설치하면 슬래브 설치와 관계없이 기둥 및 보 골조를 상부 방향으로 설치할 수 있게 하였다. In conclusion, the present invention, by inserting the bracket member 110 represented by the steel (Erection Steel) on both ends of the PC column and beam unit and beam, even if the PC is installed only the beam of the transverse resistance system like steel construction regardless of the slab installation The column and beam frames can be installed in the up direction.

또한 기존 PC 프레임의 접합부는 시공시 철근만이 시공 수직하중이나 수평하중에 견디도록 되어 있기 때문에 안전상 심각한 문제를 야기할 수 있지만 본 발명에서는 전술한 바와 같이 조립용(Erection)으로 삽입된 철골(Erection Steel)로 대표되는 브래킷부재(110)로 인해 접합부는 철골 접합에 준하는 품질을 얻을 수 있어 시공시 안전성 확보는 물론이고 완성 후에도 철골 접합을 갖는 하이브리드 PC프레임건축물을 구현하는 장점이 있다.
In addition, the joint portion of the existing PC frame can cause serious safety problems because only the reinforcement is constructed to withstand construction vertical load or horizontal load, but in the present invention, the steel frame inserted for assembly as described above (Erection) Due to the bracket member 110 represented by Steel), the joints can obtain a quality comparable to that of the steel frame, thereby securing the safety during construction and implementing the hybrid PC frame building having the steel frame after completion.

본 발명은 상기에서 언급한 바와 같이 바람직한 실시예와 관련하여 설명되었으나, 본 발명의 요지를 벗어남이 없는 범위 내에서 다양한 수정 및 변형이 가능하며, 다양한 분야에서 사용 가능하다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the invention.

따라서 본 발명의 청구범위는 이건 발명의 진정한 범위 내에 속하는 수정 및 변형을 포함한다.
Therefore, the claims of the present invention include modifications and variations that fall within the true scope of the invention.

HM: 고모멘트존
CLM: 기둥 저모멘트존
BLM: 보 저모멘트존
UC: 상부PC기둥
DC: 하부PC기둥
CB: 기둥철근
B: 보부재
CP: 저모멘트연결부연결재
EP: 임베드플레이트
SB: 스터드볼트
T: 인장재
110: 브래킷부재
120: 브래킷하부콘크리트
122: 브래킷상부콘크리트
130: 보상부주근
140: 보하부주근
200: 조인트콘크리트
300: 수직보강재
310: 상부플레이트
320: 하부플레이트
HM: high moment zone
CLM: Column low moment zone
BLM: Beam Moment Zone
UC: Upper PC Column
DC: Lower PC Column
CB: Column Reinforcement
B: beam member
CP: low moment connector
EP: Embed Plate
SB: Stud Bolt
T: tension material
110: bracket member
120: lower bracket concrete
122: concrete on the upper bracket
130: compensation
140: lower back
200: joint concrete
300: vertical reinforcement
310: upper plate
320: lower plate

Claims (12)

선제작된 1절 또는 1개층의 PC기둥 및 보유닛을 서로 결합하고 상기 PC기둥 및 보유닛에 다른 PC기둥 및 보유닛 및 보부재를 결합하는 구조에서,
상부PC기둥(UC);
상기 상부PC기둥(UC)에서 아래로 이격되어 설치되는 하부PC기둥(DC);
상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이에 수직으로 배근되는 다수개의 기둥철근(CB);
상기 상부PC기둥(UC)과 하부PC기둥(DC)의 이격된 공간에 수평으로 삽입 설치되는 브래킷부재(110);
상기 브래킷부재(110)의 하부에 타설되어 설치되는 브래킷하부콘크리트(120);
상기 상부PC기둥(UC)과 하부PC기둥(DC) 사이의 이격된 공간과 상기 브래킷하부콘크리트(120) 사이에 타설되는 조인트콘크리트(200); 및,
상기 상부PC기둥(UC)의 상부 또는 상기 하부PC기둥(DC)의 하부 중 어느 하나 이상에 설치되어 다른 PC기둥 및 보유닛과 접합주를 형성하는 저모멘트연결부연결재(CP);
를 포함하여 구성되는 PC기둥 및 보유닛으로,
상기 브래킷하부콘크리트(120)와 조인트콘크리트(200)는 일체로 타설되어 1절 또는 1개층의 상기 PC기둥 및 보유닛이 사전 제작되고,
상기 상부PC기둥(UC)의 상부 및 상기 하부PC기둥(DC)의 하부는 건물 전체에서 기둥에 작용하는 모멘트가 적거나 최소인 기둥 저모멘트존(CLM)에 위치하며 상기 브래킷부재(110)의 양단은 건물 전체에서 보에 작용하는 수직하중에 의한 모멘트가 적거나 최소인 보 저모멘트존(BLM)에 위치하여 다른 PC기둥 및 보유닛 그리고 보부재(B)와의 결합이 모멘트가 적거나 최소인 곳에서 이루어지는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
In the structure of coupling the pre-fabricated one or one layer of the PC column and beam unit with each other and the other PC column and beam unit and beam member to the PC column and beam unit,
Upper PC column (UC);
A lower PC column (DC) installed spaced apart from the upper PC column (UC);
A plurality of column reinforcement bars (CB) vertically arranged between the upper PC column (UC) and the lower PC column (DC);
A bracket member 110 horizontally inserted into the spaced space between the upper PC column UC and the lower PC column DC;
A lower bracket concrete 120 which is installed by being poured under the bracket member 110;
A joint concrete (200) placed between the spaced space between the upper PC column (UC) and the lower PC column (DC) and the bracket lower concrete 120; And
A low moment connection part connecting member (CP) installed at any one or more of the upper part of the upper PC column (UC) or the lower part of the lower PC column (DC) to form a joining column with other PC columns and beam units;
PC pillar and beam unit configured to include,
The bracket lower concrete 120 and the joint concrete 200 is integrally cast so that the PC column and beam unit of one section or one layer are pre-fabricated,
The upper part of the upper PC column (UC) and the lower part of the lower PC column (DC) is located in the pillar low moment zone (CLM) of the moment or the minimum moment acting on the pillar in the whole building and of the bracket member 110 Both ends are located in the beam moment zone (BLM) where the moment due to the vertical load acting on the beam is small or minimum throughout the building, so that the coupling with other PC columns, beam units, and beam member (B) has a small moment or minimum Prefabricated structure of the PC column and beam unit connected in the low moment zone, characterized in that made in place.
제1항에서,
상기 상부PC기둥(UC)의 하부 및 상기 하부PC기둥(DC)의 상부 사이에는 수직보강재(300)가 더 포함되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
In claim 1,
Prefabricated structure of the PC column and beam unit connected in the low moment zone, characterized in that the vertical reinforcement 300 is further included between the lower portion of the upper PC column (UC) and the upper portion of the lower PC column (DC).
제2항에서,
상기 수직보강재(300)의 상단에는 상부플레이트(310)가 상기 상부PC기둥(UC) 하부에 밀착되어 설치되고, 상기 수직보강재(300)의 하단에는 하부플레이트(320)가 상기 하부PC기둥(DC) 상부에 밀착되어 설치되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
In claim 2,
The upper plate 310 is installed on the upper end of the vertical reinforcement 300 in close contact with the lower upper PC pillar (UC), the lower plate 320 is the lower PC column (DC) at the lower end of the vertical reinforcement 300 Prefabricated structure of the PC column and beam unit connected in the low moment zone, characterized in that is installed in close contact with the top.
제1항 또는 제2항에서,
상기 브래킷부재(110)의 중앙이 끊긴 형태가 되어 끊긴 부분이 상기 조인트콘크리트(200)에 임베드플레이트(EP) 및 스터드볼트(SB)를 통하여 매립되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
3. The method according to claim 1 or 2,
The center of the bracket member 110 is broken form the PC pillar connected in the low moment zone, characterized in that the broken portion is embedded in the joint concrete 200 through the embed plate (EP) and the stud bolt (SB) And a prefabricated structure of the beam unit.
제1항 또는 제2항에서,
상기 조인트콘크리트(200)의 타설높이는 상기 브래킷하부콘크리트(120)와 동일 레벨이 되어, 상기 조인트콘크리트(200) 상부와 상기 상부PC기둥(UC)의 하부 사이 및 상기 브래킷부재(110) 상부에 일체로 슬래브콘크리트가 타설되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
3. The method according to claim 1 or 2,
The pouring height of the joint concrete 200 is the same level as the lower portion of the bracket 120, integral between the upper portion of the joint concrete 200 and the lower portion of the upper PC pillar (UC) and the upper portion of the bracket member 110 Prefabricated structure of the PC column and beam unit connected in the low moment zone, characterized in that the furnace slab concrete is cast.
제3항에서,
상기 조인트콘크리트(200)의 타설높이는 상기 브래킷하부콘크리트(120)와 동일 레벨이 되어, 상기 조인트콘크리트(200) 상부와 상부플레이트(310) 하부 사이 및 상기 브래킷부재(110) 상부에 일체로 슬래브콘크리트가 타설되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
4. The method of claim 3,
The pouring height of the joint concrete 200 is the same level as the lower portion of the bracket 120, the slab concrete integrally between the upper portion of the joint concrete 200 and the lower plate 310 and the upper bracket member 110. Prefabricated structure of the PC column and beam unit connected in the low moment zone, characterized in that the pouring.
제1항 또는 제2항에서,
상기 브래킷부재(110)의 상부에 타설되어 설치되는 브래킷상부콘크리트(122);를 더 포함하되,
상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
3. The method according to claim 1 or 2,
Bracket upper concrete 122 is installed on the top of the bracket member 110;
The bracket upper concrete 122 and the bracket lower concrete 120 is assembled prefabricated structure of the PC pillar and beam unit connected in the low moment zone, characterized in that the installation is integrally installed.
제3항에서,
상기 브래킷부재(110)의 상부에 타설되어 설치되는 브래킷상부콘크리트(122);를 더 포함하되,
상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
4. The method of claim 3,
Bracket upper concrete 122 is installed on the top of the bracket member 110;
The bracket upper concrete 122 and the bracket lower concrete 120 is assembled prefabricated structure of the PC pillar and beam unit connected in the low moment zone, characterized in that the installation is integrally installed.
제4항에서,
상기 브래킷부재(110)의 상부에 타설되어 설치되는 브래킷상부콘크리트(122);를 더 포함하되,
상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
5. The method of claim 4,
Bracket upper concrete 122 is installed on the top of the bracket member 110;
The bracket upper concrete 122 and the bracket lower concrete 120 is assembled prefabricated structure of the PC pillar and beam unit connected in the low moment zone, characterized in that the installation is integrally installed.
제7항에서,
상기 브래킷상부콘크리트(122)에 매설되는 인장재(T);를 더 포함하되,
상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되고 상기 인장재(T)에는 프리텐션(pre-tension) 또는 포스트텐션(post-tension)이 도입되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
In claim 7,
Tensile material (T) is embedded in the upper concrete bracket (122); further comprising,
The bracket upper concrete 122 and the bracket lower concrete 120 is integrally placed and installed, and the tension member T is characterized in that pre-tension or post-tension is introduced. Prefabricated structure of PC column and beam unit connected in low moment zone.
제8항에서,
상기 브래킷상부콘크리트(122)에 매설되는 인장재(T);를 더 포함하되,
상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되고 상기 인장재(T)에는 프리텐션(pre-tension) 또는 포스트텐션(post-tension)이 도입되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
9. The method of claim 8,
Tensile material (T) is embedded in the upper concrete bracket (122); further comprising,
The bracket upper concrete 122 and the bracket lower concrete 120 is integrally placed and installed, and the tension member T is characterized in that pre-tension or post-tension is introduced. Prefabricated structure of PC column and beam unit connected in low moment zone.
제9항에서,
상기 브래킷상부콘크리트(122)에 매설되는 인장재(T);를 더 포함하되,
상기 브래킷상부콘크리트(122)와 상기 브래킷하부콘크리트(120)는 일체로 타설되어 설치되고 상기 인장재(T)에는 프리텐션(pre-tension) 또는 포스트텐션(post-tension)이 도입되는 것을 특징으로 하는 저모멘트존에서 연결되는 PC기둥 및 보유닛의 조립식 구조.
The method of claim 9,
Tensile material (T) is embedded in the upper concrete bracket (122); further comprising,
The bracket upper concrete 122 and the bracket lower concrete 120 is integrally placed and installed, and the tension member T is characterized in that pre-tension or post-tension is introduced. Prefabricated structure of PC column and beam unit connected in low moment zone.
KR1020110130375A 2011-12-07 2011-12-07 Precast concrete column and beam unit assembling structure being connected in the low bending moment zone KR101260392B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110130375A KR101260392B1 (en) 2011-12-07 2011-12-07 Precast concrete column and beam unit assembling structure being connected in the low bending moment zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110130375A KR101260392B1 (en) 2011-12-07 2011-12-07 Precast concrete column and beam unit assembling structure being connected in the low bending moment zone

Publications (1)

Publication Number Publication Date
KR101260392B1 true KR101260392B1 (en) 2013-05-07

Family

ID=48665411

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110130375A KR101260392B1 (en) 2011-12-07 2011-12-07 Precast concrete column and beam unit assembling structure being connected in the low bending moment zone

Country Status (1)

Country Link
KR (1) KR101260392B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2966236A1 (en) 2014-07-07 2016-01-13 Fundacíon Tecnalia Research & Innovation Joining device for precast reinforced concrete columns with a dry joint
EP2966232A1 (en) 2014-07-07 2016-01-13 Fundacíon Tecnalia Research & Innovation Dry joint joining device between columns and beams of precast reinforced concrete
CN109057046A (en) * 2018-07-09 2018-12-21 常州市规划设计院 The assembled integral beam-column node structure and construction method of additional closure connection reinforcing bar

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100452968B1 (en) 2002-01-15 2004-10-15 삼성물산 주식회사 Method of constructing underground building made use of conventional concrete pillar with bored connection part
KR101030419B1 (en) 2010-07-28 2011-04-20 경희대학교 산학협력단 Joint structure of vertical member and horizontal member
KR101228012B1 (en) 2011-08-09 2013-02-14 (주)케이에이치하우징솔루션스 Precast concrete column connecting structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100452968B1 (en) 2002-01-15 2004-10-15 삼성물산 주식회사 Method of constructing underground building made use of conventional concrete pillar with bored connection part
KR101030419B1 (en) 2010-07-28 2011-04-20 경희대학교 산학협력단 Joint structure of vertical member and horizontal member
KR101228012B1 (en) 2011-08-09 2013-02-14 (주)케이에이치하우징솔루션스 Precast concrete column connecting structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2966236A1 (en) 2014-07-07 2016-01-13 Fundacíon Tecnalia Research & Innovation Joining device for precast reinforced concrete columns with a dry joint
EP2966232A1 (en) 2014-07-07 2016-01-13 Fundacíon Tecnalia Research & Innovation Dry joint joining device between columns and beams of precast reinforced concrete
WO2016005632A2 (en) 2014-07-07 2016-01-14 Fundación Tecnalia Research & Innovation Device for connecting pillars and beams prefabricated from reinforced concrete with dry joints
WO2016005631A1 (en) 2014-07-07 2016-01-14 Fundación Tecnalia Research & Innovation Joining device for reinforced concrete prefabricated pillars with a dry joint
CN109057046A (en) * 2018-07-09 2018-12-21 常州市规划设计院 The assembled integral beam-column node structure and construction method of additional closure connection reinforcing bar

Similar Documents

Publication Publication Date Title
US20210087810A1 (en) Precast wall panels and method of erecting a high-rise building using the panels
CN107476476B (en) Combined construction method of long-span steel bar truss floor bearing plate and reinforced concrete beam
CN106836479B (en) Assembled prestressed concrete frame structure
US8074414B2 (en) Precast wall panels and method of erecting a high-rise building using the panels
CN107524234B (en) Connecting beam splitting structure of steel plate concrete shear wall and manufacturing method
CN109339229B (en) Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor
KR101937680B1 (en) Prefabricated Precast Structure and Construction Method Thereof
KR101776129B1 (en) Built-up type precast double structure for slab and wall and double precast wall construction method using the same
KR100770023B1 (en) Connecting structure between cft column and rc slab using shear head
US20180209134A1 (en) Construction arrangement and detachable connection assembly for this construction arrangement
CN113026993B (en) Assembly type combined connecting beam window opening component, structure and manufacturing and construction method
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
CN110805144B (en) Full-assembly type high-rise/super high-rise concrete frame support structure system and construction method thereof
KR101260392B1 (en) Precast concrete column and beam unit assembling structure being connected in the low bending moment zone
CN107447873B (en) Device for connecting prefabricated laminated connecting beam and prefabricated shear wall and installation method
KR100949828B1 (en) Steel beam and hybrid beam of steel concrete for slim floor
CN212453065U (en) Assembled building frame structure member
KR100653283B1 (en) Method for connecting reinforced concrete structures
CN116575317A (en) Connection structure and connection method of capping beam and bridge pier
CN216475803U (en) Novel prefabricated floor slab structure applied to shear wall system
RU2490403C1 (en) Method to increase bearing capacity of jointless monolithic reinforced concrete frame
KR100860592B1 (en) Temporary system for vertical structure using precast concreat block
KR101440560B1 (en) Strucutre of steel-concrete composite borad and construction method thereof
CN209891381U (en) Building structure
RU2197578C2 (en) Structural system of multistory building and process of its erection ( variants )

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160408

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170405

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee