SU912053A3 - Способ сооружени подземной выработки большого сечени - Google Patents

Способ сооружени подземной выработки большого сечени Download PDF

Info

Publication number
SU912053A3
SU912053A3 SU742049661A SU2049661A SU912053A3 SU 912053 A3 SU912053 A3 SU 912053A3 SU 742049661 A SU742049661 A SU 742049661A SU 2049661 A SU2049661 A SU 2049661A SU 912053 A3 SU912053 A3 SU 912053A3
Authority
SU
USSR - Soviet Union
Prior art keywords
tunnels
rock
section
galleries
lining
Prior art date
Application number
SU742049661A
Other languages
English (en)
Inventor
Иеркер Халлениус Торе
Ивар Сагефорс Карл
Original Assignee
за вители
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from SE7310504A external-priority patent/SE375580B/xx
Priority claimed from SE7406572A external-priority patent/SE385491B/xx
Application filed by за вители filed Critical за вители
Application granted granted Critical
Publication of SU912053A3 publication Critical patent/SU912053A3/ru

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lift Valve (AREA)

Description

Изобретение относится к подземному строительству и может быть использовано при сооружении выработок большого поперечного сечения.
Известен способ сооружения подзем- g ных выработок большого сечения, включающий предварительную проходку по периферии выработки системы укрепляющих горный массив штолен с заполнением их несущим материалом, например до бетоном СП.
Недостатком этого способа является большой расход материалов на обделку сооружения, которая должна полностью воспринять все горное давле- де ние.
Известен также способ сооружения подземной выработки большого сечения, включающий предварительное укрепление породного массива за предела- 20 ми ее контура, разработку породы и возведение постоянной обделки [2],
Недостатком известного способа является недостаточная надежность улучшения свойств массива. 25
Цель изобретения - повышение устойчивости массива и надежности крепления выработки.
Поставленная цель достигается тем, что предварительное укрепление породного массива осуществляют путем проходки вокруг проектного сечения будущей выработки системы замкнутых штолен, расположенных в вертикальной плоскости на некотором расстоянии от него, и заполнения их несущим материалом, например бетоном.
При этом целесообразно проходить дополнительно горизонтальные замкнутые штольни, пересекающие вертикальные и образующие вместе с ними плетевидную систему.
Кроме того, обделку выработки большого сечения можно соединить с несущим материалом штолен вспомогательными штольнями или анкерами.
На чертеже изображена подземная . выработка большого сечения, поперечный разрез.
912053 4
До начала сооружения выработки г большого сечения 1 вокруг нее на некотором расстоянии от проектного контура 2 проходят систему замкнутых штолен 3» расположенных в Вертикальной плоскости, и заполняют их несущим материалом, например бетоном. Для дополнительного повышения устойчивости могут быть пройдены горизонтальные замкнутые штольни 4, пересекающие вертикальные и образующие вместе с ними клетевую систему.
Затем известным способом сооружается сама выработка большого сече- , ния и возводится ее обделка, которая может быть соединена с предварительно пройденными замкнутыми штольнями с помощью вспомогательных штолен 5. заполненных несущим материалом, или анкерами.
Таким образом, по предлагаемому способу выработка большого сечения сооружается в предварительно закрепленном массиве, а ее обделка может быть облегчена с учетом того, что основную нагрузку от горного давления воспринимает несущий материал & замкнутых штольнях.

Claims (2)

  1. До начала сооружени  выработки большого сечени  1 вокруг нее на нек тором рассто нии от проектного конту ра 2 проход т систему замкнутых штолен 3 расположенных в вертикальной плоскости, и заполн ют их несущим ма териалом, например бетоном. Дл  дополнительного повышени  устойчивости могут быть пройдены горизонтальные замкнутые штольни k, пересекающие вертикальные и образующие вместе с ними клетевую систему. Затем известным способом сооружаетс  сама выработка большого сечени  и возводитс  ее обделка, котора  может быть соединена с предварительно пройденными замкнутыми штольн ми с помощью вспомогательных штоЛен 5 заполненных несущим материалом, или анкерами. Таким образом, по предлагаемому способу выработка большого сечени  сооружаетс  в предварительно закрепленном массиве, а ее обделка может быть облегчена с учетом того, что основную нагрузку от горного давлени воспринимает несущий материал 6 замкнутых штольн х. Формула изобретени  1. Способ сооружени  подземной вы работки большого сечени , включающий предварительное укрепление породного массива за пределами ее контура, раз 9 34 работку породы и возведение посто нной обделки, отличающийс  тем, что, с целью повышени  устойчивости массива и надежности креплени  выработки, предварительное укрепление породного массива осуществл ют путем проходки вокруг проектного сечени  будущей выработки системы замкнутых штолен, расположенных в верти -i кальной плоскости на некотором рассто нии от него, и заполнени  их несущим материалом, например бетоном. 2.Способ по п. 1, отличающий с   тем, что дополнительно проход т горизонтальные замкнутые штольни, пересекающие вертикальные и образующие вместе сними клетевидную систему. 3.Способ по пп. 1 и 2, о т л ичающийс  тем, что обделку выработки большого сечени  соедин ют с несущим материалом штолен вспомогательными штольн ми,также заполненными несущим материалом, или анкерами . Источники информации, прин тые во внимание при экспертизе 1.Авторское свидетельство СССР № , кл, Е 21 D 1/00, 1969.
  2. 2.Procudings North American Rapeid Excanion-and Tunne ing conference , June 5-7. 1972, Chicago, vol. 1, c. 52, рис. 8 (прототип). Приоритет по признакам: 30.07.73 - по п. 1. 16.05-74 - по п. 2 и 3.
    Йч/
    11
    /e
    %
    H
    «4
    I
    tl
SU742049661A 1973-07-30 1974-07-30 Способ сооружени подземной выработки большого сечени SU912053A3 (ru)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
SE7310504A SE375580B (ru) 1973-07-30 1973-07-30
SE7406572A SE385491B (sv) 1974-05-16 1974-05-16 Metod for utsprengning och forsterkning av bergrum

Publications (1)

Publication Number Publication Date
SU912053A3 true SU912053A3 (ru) 1982-03-07

Family

ID=26656386

Family Applications (1)

Application Number Title Priority Date Filing Date
SU742049661A SU912053A3 (ru) 1973-07-30 1974-07-30 Способ сооружени подземной выработки большого сечени

Country Status (21)

Country Link
US (1) US3996751A (ru)
JP (1) JPS5117805B2 (ru)
AR (1) AR210244A1 (ru)
AT (1) AT343169B (ru)
BR (1) BR7406028D0 (ru)
CA (1) CA1008678A (ru)
CH (1) CH589781A5 (ru)
CS (1) CS171193B2 (ru)
DD (1) DD115936A5 (ru)
DE (1) DE2434200C3 (ru)
EG (1) EG14472A (ru)
ES (1) ES428693A1 (ru)
FI (1) FI58387C (ru)
FR (1) FR2239561B1 (ru)
GB (1) GB1444068A (ru)
HK (1) HK14377A (ru)
IL (1) IL45242A (ru)
NO (1) NO132968C (ru)
PL (1) PL93120B1 (ru)
SU (1) SU912053A3 (ru)
YU (1) YU37009B (ru)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953739A (zh) * 2012-10-26 2013-03-06 中铁二十二局集团第六工程有限公司 一种暗挖地铁车站的双向开洞方法

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4192629A (en) * 1976-12-13 1980-03-11 Hallenius Tore J System for the storage of radioactive material in rock
SE416690B (sv) * 1977-06-30 1981-01-26 Wp System Ab Anleggning for lagring av radioaktivt material i berg
US5000617A (en) * 1987-04-22 1991-03-19 Uwe Eggert Store
SE465171B (sv) * 1989-12-06 1991-08-05 K Svensson Foerfarande foer uttagning av bergrum
AT396710B (de) * 1991-09-04 1993-11-25 Mayreder Kraus & Co Ing Verfahren zum herstellen langgestreckter, grossvolumiger unterirdischer hohlräume
US5746540A (en) * 1994-05-12 1998-05-05 Hindle; David J. Method of isolating a nuclear reactor or other large structures
CN100451295C (zh) * 2007-08-17 2009-01-14 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101655001B (zh) * 2009-06-03 2011-08-10 中国水利水电第七工程局有限公司 水电站地下厂房岩壁梁开挖钢管钻孔样架及施工方法
US8650830B2 (en) 2013-03-08 2014-02-18 John Cogburn Method of basement construction
RU2649193C1 (ru) * 2014-06-13 2018-03-30 Чанцзян Сервей Плэннинг Дизайн Энд Рисерч Ко., Лтд. Схема строительства объединенной группы выработок подземных атомных электростанций в направлении вглубь горы
CN104061007B (zh) * 2014-06-13 2016-06-15 长江勘测规划设计研究有限责任公司 一种地下核反应堆洞室超大跨度穹顶预留中心岩柱施工工艺
JP6280290B2 (ja) * 2014-06-13 2018-02-14 ▲長▼江勘▲測▼▲規▼▲劃▼▲設▼▲計▼研究有限▲責▼任公司 山の縦方向と垂直な地下原子力発電所の原子力アイランド型プラント地下空洞群の建設レイアウト
CN104314583A (zh) * 2014-09-03 2015-01-28 山西煤炭运销集团晋城有限公司 一种煤层巷道过空区的支护方法
CN105888696A (zh) * 2016-06-30 2016-08-24 中铁四局集团第四工程有限公司 大截面隧道的施工方法
CN106246192A (zh) * 2016-08-22 2016-12-21 北京市政路桥股份有限公司 一种隧道基础及底板下的大型溶洞处理及隧道开挖方法
CN106884660A (zh) * 2017-04-28 2017-06-23 中国矿业大学 一种护巷煤柱底角预裂爆破卸压控制巷道变形的方法
CN106979021B (zh) * 2017-05-05 2019-01-11 中铁十二局集团有限公司 大断面黄土隧道开挖及初期支护快速封闭成环方法
CN109653209A (zh) * 2019-01-17 2019-04-19 中交(广州)建设有限公司 城市车站石方开挖施工工艺
CN111005759A (zh) * 2019-12-04 2020-04-14 中交第二公路勘察设计研究院有限公司 一种适用于寒冷地区的超长隧道清污分离排水结构

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US960940A (en) * 1910-02-18 1910-06-07 George W Jackson Art of constructing tunnels in the earth.
FR728858A (fr) * 1931-12-28 1932-07-12 Procédé d'exécution des tunnels ou autres ouvrages souterrains analogues
DE1058535B (de) * 1957-06-29 1959-06-04 Walter Hielmann Dr Ing Verfahren zur Errichtung weitgespannter unterirdischer Raeume, z. B. von Tunneln oder Bunkern
DE1809326C3 (de) * 1968-11-16 1975-04-17 Held & Francke Bauaktiengesellschaft, 8000 Muenchen Verfahren zum Herstellen eines Tunnels oder Stollens

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953739A (zh) * 2012-10-26 2013-03-06 中铁二十二局集团第六工程有限公司 一种暗挖地铁车站的双向开洞方法
CN102953739B (zh) * 2012-10-26 2015-05-06 中铁二十二局集团第六工程有限公司 一种暗挖地铁车站的双向开洞方法

Also Published As

Publication number Publication date
JPS5117805B2 (ru) 1976-06-04
DE2434200A1 (de) 1975-02-20
NO742195L (ru) 1975-02-24
FR2239561A1 (ru) 1975-02-28
BR7406028D0 (pt) 1975-05-06
GB1444068A (en) 1976-07-28
AR210244A1 (es) 1977-07-15
CH589781A5 (ru) 1977-07-15
DE2434200C3 (de) 1978-05-03
EG14472A (en) 1984-03-31
IL45242A0 (en) 1974-10-22
PL93120B1 (ru) 1977-05-30
US3996751A (en) 1976-12-14
CS171193B2 (ru) 1976-10-29
FR2239561B1 (ru) 1976-12-24
FI217274A (ru) 1975-01-31
ATA584074A (de) 1977-09-15
HK14377A (en) 1977-04-01
NO132968B (ru) 1975-11-03
FI58387C (fi) 1981-01-12
YU37009B (en) 1984-08-31
ES428693A1 (es) 1976-09-01
AT343169B (de) 1978-05-10
JPS5071130A (ru) 1975-06-12
CA1008678A (en) 1977-04-19
DD115936A5 (ru) 1975-10-20
FI58387B (fi) 1980-09-30
DE2434200B2 (de) 1977-09-15
YU211374A (en) 1982-02-25
IL45242A (en) 1977-06-30
NO132968C (ru) 1976-02-11

Similar Documents

Publication Publication Date Title
SU912053A3 (ru) Способ сооружени подземной выработки большого сечени
CN102226403B (zh) 地铁大跨度车站主体拱盖法施工方法及车站主体结构
CN105370304B (zh) 高应力强扰动煤层沿空留巷多级加固方法
CN105064397B (zh) 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法
CN102758632A (zh) 岩质地层双初支分层法修建大型地下结构的方法
CN105626083A (zh) 一种通透肋式连拱隧道的施工方法
CN103147760A (zh) 一种底部冒落群赋存条件下大型水平矿柱采矿方法
CN103775095A (zh) 山岭软基隧道超前双导洞及其施工方法
CN104061000B (zh) 触壁下沉通道式隧道中隔墙及其建造方法
CN111022076A (zh) 大跨度地铁隧道二衬拱顶采用分体自行式施工方法
CN112324442A (zh) 大断面隧道的挖掘方法
CN111594168A (zh) 一种岩矸配合成形的伪采空层支护限沉回采方法
CN110552731A (zh) 一种放顶煤回采巷道注浆锚索支护结构及其超前支护方法
CN110284900B (zh) 一种破碎地层超小净距城市隧道支护结构及其跳槽施工工艺
Bekbergenov et al. CURRENT CONDITION AND OUTLOOKS OF SUSTAINABLE DEVELOPMENT OF CHROMITE UNDERGROUND) MIINING, AT LOWER HORIZONS OF MINES OF THE DONSKOY MINING, AND PROCESSING, PLANT
CN105909290A (zh) 一种柱式部分充填开采中控制顶板下沉的装置与方法
SU1017778A1 (ru) Односводчата станци метрополитена глубокого заложени
SU983198A1 (ru) Подпорна стенка и способ ее возведени
CN116291453B (zh) 一种铜铁矿采矿用上向进路充填采矿工艺
SU989083A1 (ru) Способ проходки выработок большого сечени
RU2810978C1 (ru) Способ реконструкции железнодорожного тоннеля
GB1363686A (en) Method for producing undercuttings for buildings
CN213269899U (zh) 一种用于大断面暗挖车站的三层支护结构
CN208364128U (zh) 一种岩溶裂隙隧道衬砌加固装置
RU2026494C1 (ru) Способ проходки горизонтальных горных выработок