SU1708752A1 - Self-climbing crane - Google Patents

Self-climbing crane Download PDF

Info

Publication number
SU1708752A1
SU1708752A1 SU894706542A SU4706542A SU1708752A1 SU 1708752 A1 SU1708752 A1 SU 1708752A1 SU 894706542 A SU894706542 A SU 894706542A SU 4706542 A SU4706542 A SU 4706542A SU 1708752 A1 SU1708752 A1 SU 1708752A1
Authority
SU
USSR - Soviet Union
Prior art keywords
formwork
holder
tower
crane
self
Prior art date
Application number
SU894706542A
Other languages
Russian (ru)
Inventor
Владимир Владимирович Кузьмин
Яков Израилевич Водяницкий
Маргарита Николаевна Кузнецова
Original Assignee
Московское Производственное Объединение "Строймаш"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Московское Производственное Объединение "Строймаш" filed Critical Московское Производственное Объединение "Строймаш"
Priority to SU894706542A priority Critical patent/SU1708752A1/en
Application granted granted Critical
Publication of SU1708752A1 publication Critical patent/SU1708752A1/en

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Изобретение относитс  к подъемным устройствам, а именно к самоподъемным башенным кранам, которые используютс  при строительстве монолитных зданий и сооружений повышенной этажности. Цель изобретени  - улучшение эксплуатационных характеристик. Кран содержит башню 1 с верхней частью крана, подвижную обойму 6 и опалубку. Опалубка прикреплена к нижнему торцу подвижной обоймы 6, причем внутренн   стенка опалубки прикреплена tc обойме, а кажда  сторона наруж^ной стенки 10 опалубки, выполнена в виде шарнирно прикрепленных по углам обоймы створок. 1 з.п. ф-лы, 3 ил..yui2(Лс^о00•^ ельэThe invention relates to lifting devices, namely to self-lifting tower cranes, which are used in the construction of monolithic buildings and structures of a higher number of storeys. The purpose of the invention is to improve performance. The crane contains a tower 1 with the upper part of the crane, a movable holder 6 and formwork. The formwork is attached to the lower end of the movable casing 6, the inner wall of the formwork is attached to the tc holder, and each side of the outer wall 10 of the formwork is made in the form of hinged shutters at the corners of the cage. 1 hp f-ly, 3 il..yui2 (Ls ^ o00 • ^ elia

Description

Изобретение относитс  к подъемным устройствам, а именно к башенным самоподъемным кранам; которые используютс  при строительстве монолитных зданий и сооружений повышенной этажности. The invention relates to lifting devices, namely, self-lifting tower cranes; which are used in the construction of monolithic buildings and structures of higher number of floors.

Цель изобретени  - улучшение эксплуатационнь1х характеристик.The purpose of the invention is to improve operational characteristics.

На фиг. 1 изображен самоподъемный башенный кран (привод передвижени  не показан); на фиг. 2 -элемент башни кр.ана с подвижной обоймсй и прикрепленной к ней опалубкой, аксонометри ; на фиг, 3 - Опалубка в разрезе.FIG. 1 shows a self-erecting tower crane (movement drive not shown); in fig. 2-element tower kr.ana with a movable arm and a formwork attached to it, axonometric; Fig, 3 - Formwork in section.

Самоподъемный башенный кран состоит из башни 1, оголовка 2, стрелы 3. консоли 4 и противовеса 5. Подвижна  обойма 6 охватывает башню 1 крана и представл ет собой металлоконструкцию, в верхней части которой имеетс  площадка дл  размещени  привода выдвижени  обоймы б и башни 1, представл ющего собой гидравлическую систему (на чертежах не показана).A self-elevating tower crane consists of a tower 1, a tip 2, an arrow 3. a console 4 and a counterweight 5. A movable holder 6 encloses the tower 1 of a crane and is a metal structure, in the upper part of which there is a platform for accommodating the drive of the holder b and tower 1, a hydraulic system (not shown in the drawings).

Лифтова  шахта 7 обустроена путем ее бетонировани , В стенах шахты 7 выполнены отверсти ч 8, обрамленные листовым металхом .Нз каждом этаже в каждой стенке устраивают по два отверсти  8. К нижнему торцу подвижной обоймы б прикреплена опалубка. Внутренние и наружные стенки 9 и 10 опалубки прикреплены к обойме б. Причем наружные стенки 10 выполнены в виде створок, которые закреплены на углах обоймы б посредством шарниров 11 и расположены на рассто нии от внутренних стенок 9 опалубки. При этом наружна  поверхность 12 обоймы б находитс  в одной плоскости с внутренней поверхностью 13 внутренней стенки 9 опалубки,The elevator shaft 7 is equipped by concreting it. In the walls of the shaft 7 holes 8 are framed with sheet metal. Two holes 8 are arranged in each wall in each wall 8. There is a formwork attached to the lower end of the movable cage b. The inner and outer walls 9 and 10 of the formwork are attached to the holder b. Moreover, the outer walls 10 are made in the form of shutters, which are fixed at the corners of the holder b by means of hinges 11 and located at a distance from the inner walls 9 of the formwork. The outer surface 12 of the yoke b is in the same plane with the inner surface 13 of the inner wall 9 of the formwork,

В верхней части опалубки имеютс  отверсти  14, через которые в нее заливают бетон. Вашн  1 закреплена в шахте 7 посредством элементов 15 фиксации, св зывающих башню и шахту. Створки прикреплены к обойме б посредством рамки и кронштейнов.In the upper part of the formwork there are holes 14 through which concrete is poured into it. Your 1 is fixed in the shaft 7 by means of fixing elements 15 connecting the tower and the shaft. The flaps are attached to the holder b by means of a frame and brackets.

Кран работает следующим образом.Crane works as follows.

Смонтированна  башн  1 крана с прикрепленной к ней подвижной обоймой б с опалубкой устанавливаетс  на фундаменте здани  и крепитс  к нему на анкерных болтах . К верхней секции башни 1 через неповорОтную платформу и опорно-поворотный круг крепитс  верхн   часть крана.The mounted crane tower 1, with a movable yoke with formwork attached to it, is mounted on the foundation of the building and fixed to it by anchor bolts. The upper part of the crane is fastened to the upper section of the tower 1 through a fixed platform and a turntable.

После завершени  монтажа крана начинаетс  обустройство лифтовой шахты 7. Подвижную обойму б с опалубкой опускают до основани  здани  укладывают арматуру. Через отвзрсти  14 в опалубку заливают бетон. При бетонировании стен лифтовой шахты 7 устраивают отверсти  8, обрамленные металлом. На каждом эТаже в каждой стенке устраивают по два отверсти  8 дл  установки в них элементов 15 фиксации.After the installation of the crane is completed, the arrangement of the lift shaft 7 begins. The movable holder b with the formwork is lowered to the base of the building and the reinforcement is laid. Concrete is poured into formwork through 14. When concreting the walls of the elevator shaft 7 arrange holes 8, framed with metal. On each floor in each wall, two openings 8 are arranged to install fixing elements 15 in them.

Через некоторое врем  дл  исключени  схватывани  бетона с внутренней стенкой 9After some time to prevent the concrete from setting to the inner wall 9

опалубки раскрывают створки наружной стенки 10 опалубки, а подвижную обойму б немного поднимают вверх. После окончательного застывани  бетона подвижна  обойма б с опалубкой поднимаетс  и ставитс  на торец ствола лифтовой шахты 7. Далее процесс воздействи  лифтовой шахты повтор етс .formwork open the shutters of the outer wall 10 of the formwork, and the movable holder b slightly raise upwards. After the concrete finally solidifies, the movable holder b with the formwork rises and is placed on the end of the shaft of the elevator shaft 7. Then the process of the influence of the elevator shaft is repeated.

Claims (1)

1. Самоподъемный башенный кран, содержащий элементы дл  взаимодействи  с возводимым зданием, смонтированные на башне, установленную на последней с возможностью перемещени  вдоль нее и фиксации обойму, на которой закреплена опалубка с внутренними и наружными вертикальными стенками, расположенными параллельно соответствующим боковым сторонам обоймы, отличающийс  тем,1. A self-erecting tower crane containing elements for interacting with the building being erected, mounted on a tower, mounted on the latter with the possibility of moving along it and fixing a holder on which the formwork is fixed with internal and external vertical walls arranged parallel to the respective sides of the yoke, differing in , что, с целью улучшени  эксплуатационных характеристик, опалубка своей верхней частью посредством промежуточного элемента прикреплена к нижнему торцу обоймы, причем кажда  наружна  стенка опалубкивключает в себ  две створки, установленные с возможностью поворота в горизонтальной плоскости относительно соответствующих углов опалубки,that, in order to improve performance, the formwork is attached to its lower part by means of an intermediate element to the lower end of the cage, each outer wall of the formwork includes two flaps installed rotatably in a horizontal plane relative to the respective angles of the formwork, 2, Кран по п. 1, о т л и ч а ю щ и и с-  тем,2, Crane according to claim 1, of tl and h a y i and so что промежуточный элемент включает в себ  св занные с обоймой кронштейны и соединенную с ними рамку, расположенную над указанными створками и св занную с ними, а внутренние стенки опалубки расположены под соответствующими сторонами обоймы.that the intermediate member includes brackets and a frame connected to them, located above and connected with said leaves, and the inner walls of the formwork are located under the respective sides of the holder.
SU894706542A 1989-06-19 1989-06-19 Self-climbing crane SU1708752A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU894706542A SU1708752A1 (en) 1989-06-19 1989-06-19 Self-climbing crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU894706542A SU1708752A1 (en) 1989-06-19 1989-06-19 Self-climbing crane

Publications (1)

Publication Number Publication Date
SU1708752A1 true SU1708752A1 (en) 1992-01-30

Family

ID=21454807

Family Applications (1)

Application Number Title Priority Date Filing Date
SU894706542A SU1708752A1 (en) 1989-06-19 1989-06-19 Self-climbing crane

Country Status (1)

Country Link
SU (1) SU1708752A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104909280A (en) * 2015-05-08 2015-09-16 青岛中天斯壮科技有限公司 Wind generator tower self-elevating translation hoist hoisting system
CN105016220A (en) * 2015-06-18 2015-11-04 中国电力科学研究院 Holding rod joint adding device
CN105540460A (en) * 2016-01-28 2016-05-04 国家电网公司 Self-jacking device for jib crane
CN105967085A (en) * 2016-07-13 2016-09-28 国家电网公司 Jacking device
CN115490164A (en) * 2022-09-22 2022-12-20 徐州建机工程机械有限公司 Anti-falling structure and anti-falling method for climbing process of tower crane and tower crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР№ 248939, кл. В 66 С 23/28.1967. *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104909280A (en) * 2015-05-08 2015-09-16 青岛中天斯壮科技有限公司 Wind generator tower self-elevating translation hoist hoisting system
CN105016220A (en) * 2015-06-18 2015-11-04 中国电力科学研究院 Holding rod joint adding device
CN105540460A (en) * 2016-01-28 2016-05-04 国家电网公司 Self-jacking device for jib crane
CN105967085A (en) * 2016-07-13 2016-09-28 国家电网公司 Jacking device
CN115490164A (en) * 2022-09-22 2022-12-20 徐州建机工程机械有限公司 Anti-falling structure and anti-falling method for climbing process of tower crane and tower crane

Similar Documents

Publication Publication Date Title
GB1451611A (en) Building construction
JP2790986B2 (en) Bridge pier construction method and construction method
SU1708752A1 (en) Self-climbing crane
JP4172564B2 (en) How to build tower structures
RU2415231C2 (en) Method to erect building from finished elements
SU552395A1 (en) The method of construction of high-rise buildings
CN215482990U (en) Outer wall inner formwork system of underground structure capable of longitudinally turning surrounding purlin operation
CN211421802U (en) High-rise building construction machinery
JPH0667511U (en) Electric automatic special support lifting device
JP2906050B1 (en) Construction method of tower structure
RU2116414C1 (en) Method for erection of sectional-and-monolithic buildings
SU1682472A1 (en) Strip foundation
JP2888913B2 (en) External wall panel mounting method
RU1773854C (en) Self-hoisting crane
SU1629437A1 (en) Climbing shuttering for construction of walls and roofing
RU2002116423A (en) The method of construction of the bezelless frame of the building by the method of lifting floors
SU1707166A1 (en) Method of construction of many-stored building
RU1832144C (en) Floor formwork
SU1726699A1 (en) Movable formwork
RU2119028C1 (en) Method for erection of building covering by raising procedure
SU1761917A1 (en) Centering for erecting monolith walls of buildings and structures
SU1670067A1 (en) Method of erecting buildings and structures by elevating floors
JP2590671B2 (en) Construction method of steel frame using overhead crane frame
SU672303A1 (en) Method of erecting building and structures
SU1059104A1 (en) Hoistable and shiftable structure for constructing prefabricated vertical structures