SU1257221A1 - Method of mining ore bodies - Google Patents

Method of mining ore bodies Download PDF

Info

Publication number
SU1257221A1
SU1257221A1 SU853891570A SU3891570A SU1257221A1 SU 1257221 A1 SU1257221 A1 SU 1257221A1 SU 853891570 A SU853891570 A SU 853891570A SU 3891570 A SU3891570 A SU 3891570A SU 1257221 A1 SU1257221 A1 SU 1257221A1
Authority
SU
USSR - Soviet Union
Prior art keywords
ore
block
notch
cutting gap
broken
Prior art date
Application number
SU853891570A
Other languages
Russian (ru)
Inventor
Хазби Гитеевич Кабисов
Original Assignee
Северо-Кавказский Ордена Дружбы Народов Горно-Металлургический Институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Северо-Кавказский Ордена Дружбы Народов Горно-Металлургический Институт filed Critical Северо-Кавказский Ордена Дружбы Народов Горно-Металлургический Институт
Priority to SU853891570A priority Critical patent/SU1257221A1/en
Application granted granted Critical
Publication of SU1257221A1 publication Critical patent/SU1257221A1/en

Links

Description

Изобретение относитс  к горной промьппленности, в частности к подземной разработке крутопадающих рудных тел с обрушением руды и пород.The invention relates to the mining industry, in particular to the underground mining of steeply dipping ore bodies with the collapse of ore and rocks.

Цель изобретени  - снижение потерь руды.The purpose of the invention is to reduce the loss of ore.

На чертеже представлен продольно-вертикальный разрез блока с oTod- ражением на нем начального и завершающего этапов работ.The drawing shows a longitudinal-vertical section of the block with oTod-ry on it the initial and final stages of work.

Способ осуществл ют следующим образом .The method is carried out as follows.

Первоначально провод т подготовительные работы, которые начинают с проведени  откаточного штрека , фланговых восстающ к 2 и 3 и подэтаж ных штреков 4-6. После того, как подготовительные работы в блоке закончены , у одного из фланговых восстающих блока по всем подэтажай обу- ривают шпуры или скважины и путем их взрывани  образуют отрезную щель 7. Одновременно с этим на ширину отрезной щели 7 вынимают рудный целик 8 над верхним штреком блока. Весь столб отбитой руды выпускают через дучку 9 в основании блока. При вьтуске руды отрезна  щель 7 заполн етс  обрушенными породами, поступающими с верхнего этажа под действием собственной т жести, В дальнейшем отбойку руды в блоке осуществл ют вертикальными прирезками в следующей последовательности. Прирезку 10 отбивают на нижнем подэтаже прирезки 11 на двух нижних подэтажах блока прирезки 12 на трех нижних и прирезки 13 на четырех подэтажах блока и так далее до образовани  сплош;.;ого столба отбитой руды по всей зЕысоте блока. После каждого очередного взрывани  вьшуск отбитой руды производ т из соответствзж)щих дучек 9 в основании блока.Initially, preparatory work was carried out, which began with a haulage, flanking rebuilding to 2 and 3, and sublevel drifts 4-6. After the preparatory work in the block is completed, holes are drilled in one of the flanking rising blocks of all the sublevels or boreholes and by their blasting they form a cutting slot 7. At the same time, the ore rear sight 8 is pulled out above the upper drift of the block . The entire column of broken ore is released through duchka 9 at the base of the block. In the course of ore extraction, the slit 7 is filled with collapsed rocks coming from the upper floor under the action of own weight. Then, the ore is crushed in the block with vertical cutting in the following sequence. Cut-off 10 is fenced off at the lower substage of cut-off 11 on the two lower substages of cut-up block 12 on the three lower floors and cut-on 13 on four block floors, and so on, to form a solid column of broken ore throughout the whole height of the block. After each successive blasting, the release of broken ore is made from the corresponding ducts 9 at the base of the block.

Дальнейшую отбойку руды в блоке производ т также прирезками одинаковой ширины на всех подэтажах с выемкой над ними части надштрекового це,- лика 8 такой же ширины. Опережение прирезок на нижних подэтажах производ т равными высоте подэтажного штрека, что исключает расположение .откосов как отбитой руды, так и обрушенных пород на почвах подэтажных ,Further cutting of the ore in the block is also carried out by cuttings of the same width on all the sub-floors with a notch of a part of the above-the-back center, face 8 of the same width. Advancement of the cuttings on the lower substages is made equal to the height of the subsurface drift, which excludes the location of the spikes of both broken ore and collapsed rocks on subsurface soils,

ВНИИПИ Заказ 4890/26 Тираж 470VNIIPI Order 4890/26 Circulation 470

Проиэа.-полигр. пр-тие, г. Ужгород, ул. Проектна , 4Pro.p. pr-tie, Uzhgorod, st. Project, 4

штреков и не создает помех дл  бурени  нисход щих шпуров или скважин. П&и выпуске руды за ее истечением из блока наблюдают с подэтажных штре- ков. Шпуры или скважины в отбиваемых прирезках бур т сверху вниз на всех подэтажах, а дл  выемки надштрекового целика 8 над очередными прирезками обуривают веера шпуров с верхнего штрека.drifts and does not interfere with the drilling of downstream bore-holes or wells. O & ore release for its outflow from the block is observed from sublevel drifts. Boreholes or boreholes in the cut-off cut-offs are drilled from top to bottom on all sublevels, and for excavation of the pillar 8 pillar above the next cut-outs, fans of holes are drilled from the upper drift.

После доведени  отбойки руды до прирезок 14 у другого фланга блока отбитую руду вьшускают до опускани  ее верхнего контакта с обругаенны- ми породами до уровн  ншкнего под- этажного штрека 4. Затем отбивают прирезки I5 и руду выпускают до опускани  ее верхнего контакта до второ-- го снизу подэтажного штрека 5. Далее отбивают прирезки 16 и отбитую,руДУ выпускают до уровн  верхнего подэтажного штрека 6. В последнуюю очередь отбивают прирезку 17 и выпускают всю отбитую руду из блока.After the ore blasting is brought up to cuttings 14 at the other flank of the block, the broken ore is released before lowering its upper contact with round rocks to the level of the sub-floor drift 4. Then cut I5 trimming and the ore is released before lowering its upper contact to the second from the bottom of the sublevel drift 5. Next, trimming 16 is fended off and broken off, the ore is released to the level of the upper sublevel drift 6. In the last turn, trimming 17 is fought off and all the broken ore from the block is released.

Claims (1)

Формула изобретени Invention Formula Способ разработки рудных тел., включающий проходку восстающих буровых и откаточных штреков и рудовы- пускных дучек, формирование отрезной щели на фланге блока на всю его высоту , буровзрывную отбойку руды в блоке в зажиме на обрушенныеThe method of developing ore bodies. Including the penetration of the revolving drilling and haulage drifts and the ore formations, the formation of a cutting gap on the flank of the block to its entire height, drilling and blasting of ore in the block in the clamp on the collapsed породы, выемку надштрекового целика над отрезной щелью и выпуск отбитой руды через рудовыпускные дучки в основании блока, отличающий с  тем, что, с снижени  потерь руды, осуществл ют выемку части надштрекового целика над отрезной щелью и заполнение ее обрушенной породой путем выпуска, отбитой руды,,после чего отбойку руды в блоке на обрушенное порода в отрезной щели осуществл ют вертикальными прирезками одинаковой ширины , при этом нижележащие части блока по отношению к вьш ележащим част м отрабатывают с опережениемrock, excavation of the superstructure pillar over the cutting gap and release of broken ore through ore discharge duchki at the base of the block, characterized in that, to reduce ore losses, carry out a portion of the superstructure rear column plow above the cutting gap and fill it with the collapsed rock by releasing broken ore, after which the ore is crushed in the block to the collapsed rock in the cutting slot is carried out by vertical cuttings of the same width, while the lower parts of the block with respect to the lower parts are worked out ahead of time на величину, равную высоте бурового штрека, причем одновременно с выемкой прирезки осуществл ют выемку части надштрекового целика шириной,by an amount equal to the height of the drill drift, and simultaneously with the notch of the notch, a notch of a part of the under-rifle rear sight is carried out, равной ширине прирезки.equal to the width of the trimming. Подписное ,Subscription
SU853891570A 1985-05-07 1985-05-07 Method of mining ore bodies SU1257221A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU853891570A SU1257221A1 (en) 1985-05-07 1985-05-07 Method of mining ore bodies

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU853891570A SU1257221A1 (en) 1985-05-07 1985-05-07 Method of mining ore bodies

Publications (1)

Publication Number Publication Date
SU1257221A1 true SU1257221A1 (en) 1986-09-15

Family

ID=21175772

Family Applications (1)

Application Number Title Priority Date Filing Date
SU853891570A SU1257221A1 (en) 1985-05-07 1985-05-07 Method of mining ore bodies

Country Status (1)

Country Link
SU (1) SU1257221A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2448249C2 (en) * 2010-07-07 2012-04-20 Учреждение Российской академии наук Институт проблем комплексного освоения недр Российской академии наук (УРАН ИПКОН РАН) Underground development method of thick mineral deposits
CN108104818A (en) * 2017-11-27 2018-06-01 西北矿冶研究院 Underground mining method for thick massive ore body
CN108625855A (en) * 2018-06-11 2018-10-09 安徽大昌矿业集团有限公司 Safe and efficient mining methods under a kind of obturation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР S 877022, кл. Е 21 С 41/06, 1980. Агошков М.И. и др. Разработка рудных и нерудных месторождений. М.: Недра, 1983, с. 236-245. *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2448249C2 (en) * 2010-07-07 2012-04-20 Учреждение Российской академии наук Институт проблем комплексного освоения недр Российской академии наук (УРАН ИПКОН РАН) Underground development method of thick mineral deposits
CN108104818A (en) * 2017-11-27 2018-06-01 西北矿冶研究院 Underground mining method for thick massive ore body
CN108625855A (en) * 2018-06-11 2018-10-09 安徽大昌矿业集团有限公司 Safe and efficient mining methods under a kind of obturation

Similar Documents

Publication Publication Date Title
MX2012009756A (en) Underground mining.
US3917346A (en) Method of blasting a subterranean deposit
SU1257221A1 (en) Method of mining ore bodies
RU2115803C1 (en) Method for mining thick steep coal seams in upgrade
RU2123109C1 (en) Method for mining of coal series in marginal zones of opencast
RU2263213C1 (en) Method for thick steeply inclined fire-hazardous bed mining with caving
RU2013549C1 (en) Method for artificial interhorizontal pillar building by mining steep and inclined formations
RU2224890C1 (en) Method for extracting sloping or slanted shock-hazardous layers
RU2010972C1 (en) Method of working interchamber pillar
RU96108488A (en) METHOD FOR DEVELOPING THE COAL FORMATION ENVIRONMENT IN THE EXTRAORDINARY ZONES OF THE CAREER
SU829950A1 (en) Method of working adjacent sloping beds of minerals
SU887809A1 (en) Method of mining sloping and gently sloping coal beds
RU2083833C1 (en) Method for development of steep coal seams with backing worked-out area
SU825962A1 (en) Method of controlling hard-to-cave roofs
SU1028846A1 (en) Method of mining steep ore deposit
RU2168629C1 (en) Method of mining of thick flat coal bed
RU2038476C1 (en) Coal deposit exploitation method
SU720161A1 (en) Method of mining steep sloping ore bodies
SU1157242A1 (en) Method of driving an ascending mine working
SU617601A1 (en) Method of drawing pillars at chamber-and-pillar system of mining minerals
RU2344292C1 (en) Method of development of thick flat-lying coal bed on clots of irregular shape
RU2042815C1 (en) Method for mining steeply dipping and inclined coal seams
SU1666725A1 (en) Method for construction of protective wall made of ore blocks
SU1125373A1 (en) Method of mining unstable ores
RU2039260C1 (en) Method for formation of caving slot in longwall face-to-gate junctions