SU1157242A1 - Method of driving an ascending mine working - Google Patents
Method of driving an ascending mine working Download PDFInfo
- Publication number
- SU1157242A1 SU1157242A1 SU843703684A SU3703684A SU1157242A1 SU 1157242 A1 SU1157242 A1 SU 1157242A1 SU 843703684 A SU843703684 A SU 843703684A SU 3703684 A SU3703684 A SU 3703684A SU 1157242 A1 SU1157242 A1 SU 1157242A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- drilling
- diameter
- annular groove
- rising
- upper horizon
- Prior art date
Links
Landscapes
- Earth Drilling (AREA)
Abstract
СПОСОБ ПРОВЕДЕНИЯ ВОССТАЮЩЕЙ ГОРНОЙ ВЫРАБОТКИ, вкJmчaющий установку буровой машины с опорной плитой на подошву верхнего горизонта , бурение передовой скважины сверху вниз до выхода бурового става в выработку нижнего горизонта , присоединение к буровому ставу расширител с рабочим органом и разбуривание передовой скважины снизу вверх до диаметра восстающего, отличающий с тем, что, с целью повышени безопасности работ при сбойке восстающей выработки с верхним горизонтом, перед установкой буровой машины подошву верхнего горизонта в месте бурени передовой скважины разрыхл ют по кругу диаметром, не меньшим диаметра восстающей выработки, на глубину , не меньшую высоты рабочего органа распмрител , при этом разрыхленный участок перекрывают опорной плитой. (Л 2.Способ по п.1, о т л ичающийс тем, что разс рыхление осуществл ют в объеме кольцевой канавки в виде желоба. 3.Способ по п.1, отличающийс тем, что после разрьпшени породу в кольцевой каел VI навке за пределами восстающей выработки убирают и бетонируют эту часть кольцевой канавки. ND 4 N0METHOD OF RECOVER mining, vkJmchayuschy installation drilling machine to the base plate to the sole upper horizon drilling advanced wells downwards before the drilling rod in the production of subsurface joining the drilling rod dilator with the working body and drilling out the bottom up to a diameter of advanced wells revolted distinguished by the fact that, in order to increase the safety of work when sinking arising development with the upper horizon, before installing the drilling machine, the bottom of the upper horizon in the place of drilling of the advanced well, they loosen in a circle with a diameter not smaller than the diameter of the rising well, to a depth not less than the height of the working tool of the distributor, while the loosened section is overlapped with a support plate. (L 2. Method according to claim 1, about which it is loosened in the volume of the annular groove in the form of a groove. 3. The method according to claim 1, characterized in that after discharging the rock in the annular groove VI outside of the rising production, this part of the annular groove is removed and concreted. ND 4 N0
Description
Изобретение относитс к области горного дела, а более конкретно к проведению восстающих горных выработок механизированным способом , и может быть использовано на горнодобывающих предпри ти х черной и цветной металлургии, химической и угольной промьшшенности. Известен способ бурени восстающего на полное сечение за один проход снизу вверх, который осуществл ют буровыми устройствами Стрела-68 и 1КВ1 (СССР), 36, 60 и 51Р (CUIA) и др. г. Однако данный способ имеет ограниченное применение, так как по конструктивным особенност м оборудовани он приемлем только дл проходки восстающих небольшого сечени . Наиболее близким к изобретению по технической сущности и достигаемому результату вл етс способ про ведени восстающей горной выработки включающий установку буровой машины с опорной плитой на подошву верхнего горизонта, бурение передовой скважины сверху вниз до выхода бурового става в выработку нижнего го ризонта, присоединение к буровому ставу расширител с рабочим органом И разбуривание передовой скважи ны снизу вверх до диаметра восстающего 2. К недостаткам известного способа следует отнести опасность ведени б ровых работ на недобуренном массиве (возможны обвалы) и опускани расширител . Целью изобретени вл етс повышение безопасности работ при сбойке восстающей выработки с верхшсм горизонтом. Указанна цель достигаетс тем, что согласно способу, включающему установку буровой машины с опорной плитой на подошву верхнего горизонта, бурение передовой скважи ны сверху вниз до выхода бурового става в вьфаботку нижнего горизонта гфисоединенйе к буровому ставу расширител с рабочим органом и разбуривание передовой скважины снизу вверх до диаметра восстающего, пере установкой Дуровой машины подошву верхнего горизонта в месте бурени передовой скнажины разрыхл ют по кругу диаметром, не меньшим диамет2 . 2 ра восстающей выработки, на глубину, не меньшую высоты рабочего органа рас1Ш1рител , при этом разрыхленный участок перекрывают опорной плИтой. Разрыхление могут осуществл ть в объеме кольцевой канавки в виде желоба. . После .разрыхлени породу в кольцевой канавке за пределами восстающей выработки убирают и бетонируют эту часть кольцевой канавки. На чертеже изображены схема и оборудование дл проведени восстающей горной вьфаботки. На схеме показаны восстающа выработка 1, проводима диаметром J} между выработками 2 и 3 соответственно верхнего и нижнего горизонтов , передова скважина 4 и кольцева канавка в виде желоба 5 с условным диаметром cJ и глубиной f в объем которого входит оголовок 6 восстающего. На подошве выработки 2 верхнего горизонта установлена бурова машина 7 с опорной плитой 8. К буровой машине посредством бурового става 9 присоединен расширитель 10, высота рабочего органа которого равна . На расширителе установлены шарошки 11. Опорна плита 7 перекрывает кольцевой желоб 5. Способ осуществл етс следуюш 1м образом. При подготовительных работах в буровой камере 2 намечают ось будущей выработки t. Затем около этой оси в радиусе, равном радиусу восстающего, мелкошпуровым .способом производ т рыхление породы в объеме кольцевой канавки в виде желоба 5, глубина t которого не меньше высоты Ъ рабочего органа расширител 10, а условный диаметр с) не меньше диаметра D восстающего. Оголовок 6 будущего восстающего бетонируют, йосло этого на подошву камеры 2 устанавливают буровую машину 7 так, чтобы плита 8 перекрывала разрыхленный участок, т.е. опиралась на невзорванную породу. При этом щпиндель буровой машины должен проходить по оси будущей выработки. 1 или передовой скважины 7. Буровую машину раскрепл ют в камере 2 и осуществл ют бурение передовой скважины, наращива буровой став 9. После выхода бурового ставаThe invention relates to the field of mining, and more specifically to the carrying out of rising mine workings by a mechanized method, and can be used at the mining enterprises of ferrous and non-ferrous metallurgy, chemical and coal industry. There is a known method of drilling the riser on the full section in a single pass from the bottom up, which is carried out by the Strela-68 and 1KB1 (USSR), 36, 60 and 51P drilling devices (CUIA) and others. However, this method has limited application, since design features of the equipment it is acceptable only for the penetration of the rising small section. The closest to the invention to the technical essence and the achieved result is a method of conducting a revolving mine working, including installing a drilling machine with a base plate on the bottom of the upper horizon, drilling an advanced well from top to bottom until the drilling rod leaves the bottom horizon, connecting the extender to the drilling level with the working body And drilling the advanced well from the bottom up to the diameter of the rising 2. The disadvantages of the known method include the danger of maintenance work on unfinished massif (possible collapses) and lowering the expander. The aim of the invention is to improve the safety of operations when sinking of the rising production with the upper horizon. This goal is achieved in that according to the method, including the installation of a drilling machine with a base plate on the bottom of the upper horizon, drilling of the forward well from the bottom to the exit of the drill rod in the lower horizon hydraulically joining the drill rod of the extender with the working body and drilling the forward well from the bottom up to the diameter of the riser, by re-installing the Durov machine, the bottom of the upper horizon at the drilling site of the advanced sknazhina is loosened in a circle with a diameter not less than 2. 2 times of rising production, to a depth not less than the height of the working body of the rider, while the loosened area is covered by the supporting plate. Loosening can occur in the volume of the annular groove in the form of a gutter. . After loosening, the rock in the annular groove outside of the rising production is removed and concreted this part of the annular groove. The drawing shows a diagram and equipment for carrying out a descending mining operation. The diagram shows rising production 1, carried out with a diameter J} between openings 2 and 3, respectively, the upper and lower horizons, the front well 4 and the annular groove in the form of a groove 5 with a nominal diameter cJ and depth f in the volume of which includes the head 6 of the ascendant. A drilling machine 7 with a base plate 8 is installed on the sole of the upper horizon development 2. A reamer 10 is attached to the drilling machine by means of a drilling rod 9, the height of which is equal to the working element. The cutters 11 are mounted on the expander. The support plate 7 overlaps the annular groove 5. The method is carried out in the following 1m manner. During the preparatory work in the drilling chamber 2 outline the axis of the future development of t. Then, around this axis, in a radius equal to the radius of the ascending, the small-hole method looses the rock in the volume of the annular groove in the form of a groove 5, the depth t of which is not less than the height b of the working element of the expander 10, and the nominal diameter c) is not less than the diameter D of the ascending. The head 6 of the future ascendant is concreted, and a drilling machine 7 is installed on the sole of the chamber 2 so that the plate 8 overlaps the loosened area, i.e. relied on unblown rock. In this case, the spindle of the drilling machine should pass along the axis of the future development. 1 or an advanced well 7. The drilling machine is secured in chamber 2 and the advanced well is drilled, increasing the drilling rate 9. After the drilling rod leaves
3131
в камеру нижнего горизонта передовое долото замен ют расгаирителем 10 и, мен направление подачи, осуществл ют разбурнвание передовой скважины Д до нужного диаметра D восстающего.In the lower horizon chamber, the forward chisel is replaced with an emitter 10 and, changing the flow direction, the advanced well D is drilled to the desired diameter D of the ascendant.
Разбуривание передовой скважины производ т ,до тех пор, пока верхн часть расширител не коснетс опорной плиты 8, При этом активна часть (рабочий орган) расширител оказываетс в предварительно разрушенной части 5 восстающего.An advanced well is drilled until the upper part of the reamer touches the base plate 8. In this case, the active part (working organ) of the reamer is in the previously destroyed part 5 of the rebel.
Таким образом вс порода в объеме восстающего разрушена. После этого расширитель фиксируют на опорной плите, а буровую машину демонтируютThus, the entire breed in the volume of the insurgent is destroyed. After that, the expander is fixed on the base plate, and the drilling machine is dismantled
7242-47242-4
Затем опорную плиту вместе с расширителем приподнимают, например, при помощи гидродомкратов, восстающий перекрывают, под расио рис тель подкатывают платформу и перевоз т на новое место.Then, the support plate together with the expander is raised, for example, with the help of hydraulic jacks, the riser is closed, the platform is rolled up under the transport and transported to a new place.
Применение предлагаемого изобретени позволит повысить, безопасность ведени работ за счет исключени The application of the present invention will improve the safety of operations by eliminating
10 буровых работ на целике над восстающим и последующего его обустройства (бетонирование оголовка над пройденным восстающим после взрывани целика), а также повысить говечность бурового става и буровой машины за счет исключени дополнительных спускоподъемных операций.10 drilling rigs on the pillar over the rebel and its subsequent arrangement (concreting the tip over the rebel risen after the rifle has been detonated), as well as to increase the beefiness of the drill rod and the drilling machine by eliminating additional tripping operations.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU843703684A SU1157242A1 (en) | 1984-02-20 | 1984-02-20 | Method of driving an ascending mine working |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU843703684A SU1157242A1 (en) | 1984-02-20 | 1984-02-20 | Method of driving an ascending mine working |
Publications (1)
Publication Number | Publication Date |
---|---|
SU1157242A1 true SU1157242A1 (en) | 1985-05-23 |
Family
ID=21104651
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU843703684A SU1157242A1 (en) | 1984-02-20 | 1984-02-20 | Method of driving an ascending mine working |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU1157242A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114320304A (en) * | 2022-02-11 | 2022-04-12 | 中国水利水电第五工程局有限公司 | Excavation method of large-aperture slag chute open type surge shaft and hoisting construction platform |
-
1984
- 1984-02-20 SU SU843703684A patent/SU1157242A1/en active
Non-Patent Citations (1)
Title |
---|
1. Медведев И.Ф. и др. Механизаци проведений горных выработок в крепких породах. И., Недра, 1982, с. 96-97. 2. Авторское свидетельство СССР № 909186, кл. Е 21 D 3/00, 1980. * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114320304A (en) * | 2022-02-11 | 2022-04-12 | 中国水利水电第五工程局有限公司 | Excavation method of large-aperture slag chute open type surge shaft and hoisting construction platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3379264A (en) | Earth boring machine | |
CA1167872A (en) | Bore hole mining | |
US5232268A (en) | Method of breaking a full face of rock for constructing shafts and tunnels | |
US3917346A (en) | Method of blasting a subterranean deposit | |
US4458947A (en) | Mining method | |
US4069760A (en) | Method for driving a shaft with shaped charges | |
SU1157242A1 (en) | Method of driving an ascending mine working | |
US4906048A (en) | Method of downhole hydraulicking of mineral resources | |
RU2083831C1 (en) | Method for treatment of impact-risky seams in difficult mining and geological conditions | |
RU2315867C2 (en) | Method for thick steeply inclined coal seam excavation | |
SU1257221A1 (en) | Method of mining ore bodies | |
RU2059073C1 (en) | Method for development of mineral deposits | |
RU2039260C1 (en) | Method for formation of caving slot in longwall face-to-gate junctions | |
RU94026329A (en) | Method for mining of mineral deposits and superstructure for its embodiment | |
Stakne | Basic considerations and practical experience with the boring of deep shafts by the raise boring process/Grundsatzüberlegungen und baupraktische Erfahrungen beim Auffahren tiefer Schächte im Raise‐Boring‐Verfahren | |
CA2064625C (en) | Method and apparatus for breaking a full face of rock for constructing mines and tunnels | |
SU1649096A1 (en) | Method of recovery of safety pillar under a hole | |
SU1532687A1 (en) | Method of securing boreholes with nonmetal pipes | |
SU883514A1 (en) | Method for degassing mined space of coal bed | |
US3578808A (en) | Solution mining method and apparatus | |
RU2081324C1 (en) | Method for hydraulic bore-hole mining of minerals | |
SU1344906A1 (en) | Method of driving reserved-dome mine workings | |
SU1456581A1 (en) | Method of recovering mineral from inclined ore bodies | |
SU1564348A1 (en) | Method of excavating pillars on neighbouring ore deposits | |
RU1788258C (en) | Method for mining flat coal seams |