SU1071755A1 - Method of sinking a mine working with sinking shaft lining - Google Patents

Method of sinking a mine working with sinking shaft lining Download PDF

Info

Publication number
SU1071755A1
SU1071755A1 SU823523655A SU3523655A SU1071755A1 SU 1071755 A1 SU1071755 A1 SU 1071755A1 SU 823523655 A SU823523655 A SU 823523655A SU 3523655 A SU3523655 A SU 3523655A SU 1071755 A1 SU1071755 A1 SU 1071755A1
Authority
SU
USSR - Soviet Union
Prior art keywords
lining
rock
sinking
drilled
support
Prior art date
Application number
SU823523655A
Other languages
Russian (ru)
Inventor
Борис Александрович Гей
Original Assignee
Gej Boris A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gej Boris A filed Critical Gej Boris A
Priority to SU823523655A priority Critical patent/SU1071755A1/en
Application granted granted Critical
Publication of SU1071755A1 publication Critical patent/SU1071755A1/en

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

1. СПОСОБ ПРОХОДКИ ГОРНОЙ ВЫРАБОТКИ ОПУСКНОЙ КРЕПЬЮ, включающий создание сло  глинистого раствора между породой и крепью, отличающийс  тем, что, с целью расширени  области эффективного его применени , на пути погружени  крепи в породе бур т щели, расположенные по периметру крепи, и разбуривают породу в промежутках между щел ми в процессе погружени  крепи. 2.Способ по П.1, отличающийс  тем, что породу между щел ми разбуривают по обе стороны ножевой части крепи до создани  в крепких породах скалываемого зубь ми крепи выступа. 3.Способ по п. 1, отличающийс  тем, что породу в промежутках между щел ми разбуривают одновременно в диаметрально противоположных участках крепи. (Л СП сл1. METHOD OF PORCHING OF THE MINING OPERATING LOWER STRAP, including creating a layer of mud between the rock and lining, characterized in that, in order to expand its effective application area, the lining of the slot, located along the perimeter of the lining, is drilled between the pits during the immersion process. 2. Method according to Claim 1, characterized in that the rock between the cavities is drilled on both sides of the knife part of the lining before the projection is formed in the hard rocks of the shear lining by the teeth. 3. A method according to claim 1, characterized in that the rock between the gaps is drilled simultaneously in the diametrically opposite areas of the support. (L SP CL

Description

Изобретение относитс  к горному делу, а именно к строительству подземных сооружений в сложных гидрогеологических услови х .The invention relates to mining, namely the construction of underground structures in difficult hydrogeological conditions.

Известен способ проходки горных выработок , включающий монтаж бурового оборудовани , устройство форшахты, бурение ствола ступен ми до полного диаметра и погружение крепи в ствол 1.The known method of excavation of mine workings includes the installation of drilling equipment, the installation of a forshakhta, drilling of the barrel in steps to full diameter and immersion of the lining in the barrel 1.

Недостатком известь ого способа  вл ютс  большие трудозатраты.The disadvantage of the lime process is a lot of effort.

Наиболее близким техническим решением к предлагаемому  вл етс  способ проходки горной выработки опускной крепью, включаюш,ий создание сло  глинистого раствора между породой и крепью дл  уменьшени  сил трени  2.The closest technical solution to the present invention is a method of penetrating mining workings with a drop support, including the creation of a layer of mud between the rock and the support to reduce friction 2.

Недостаток этого способа заключаетс  в практической невозможности пересечени  пропластков крепких пород опускной крепью и врезани  последней в крепкие водоупорные породы. Этот недостаток резко сужает область эффективного применени  способа.The disadvantage of this method lies in the practical impossibility of the intersection of the interlayers of hard rock with a drop support and the incision of the hard rocks into strong waterproof rocks. This disadvantage drastically narrows the scope of effective application of the method.

Целью изобретени   вл етс  расширение области эффективного применени  опускной крепи.The aim of the invention is to expand the field of effective use of lowering shields.

Поставленна  цель достигаетс  тем, что согласно способу проходки горной выработки опускной крепью, включающему создание сло  глинистого раствора между породой и крепью, на пути погружени  крепи в породе бур т щели, расположенные по периметру крепи,и разбуривают породу в промежутках между щел ми в процессе погружени  крепи.The goal is achieved by the fact that according to the method of penetration of mine workings with a drop support, which includes creating a layer of mud between the rock and the support, in the path of immersion, the lining in the rock has a drill slot, located along the perimeter of the lining, and rock the gap between the gaps in the diving process lining.

Кроме того, породу между щел ми разбуривают по обе стороны ножевой части крепи до создани  в крепких породах скалываемого зубь ми крепи выступа.In addition, the rock between the holes is drilled on both sides of the knife-side part of the lining until a projection is formed in the strong rocks of the shear teeth.

Кроме того, породу в промежутках между щел ми разбуривают одновременно в диаметрально противоположных участках крепи .In addition, the rock in the gaps between the gaps is drilled simultaneously in the diametrically opposite areas of the lining.

На фиг. 1 показано бурение щелей на пути погружени  опускной крепи; на фиг. 2 разрез А-А на фиг. 1; на фиг. 3 - погружение опускной крепи с одновременным разбуриванием породы в промежутках между щел ми; на фиг. 4 - разрез Б-Б на фиг. 3.FIG. Figure 1 shows the drilling of slots in the way of the drop support; in fig. 2, section A-A in FIG. one; in fig. 3 — sinking of the sinking lining with simultaneous drilling of the rock between the gaps; in fig. 4 shows a section BB in FIG. 3

На пути погружени  крепи в породе бур т щели 1 долотами 2 ударно-канатных станков (рекомендуетс  четыре), расположенных вокруг горнопроходческого копра 3, снабженного поворотной площадкой 4. Последнюю поворачивают возвратно на угол пор дка 100° канатами двухбарабанной лебедки , пропущенными через шкивы на ноге копра и закрепленными на площадке (лебедка и шкивы не показаны). Расположение шкивов 5 и 6 копра и поворотной площадки у оси поворота последней обеспечивает допустимый, до 2°, угол девиации канатов при значительных углах поворотов площадки.On the path of immersion, the lining in the rock is drilled with a slit 1 with chisels 2 shock cable machines (four are recommended) located around the tunnel head 3, equipped with a rotary platform 4. The latter is turned back by an angle of about 100 ° using two-drum winch ropes Copra and fixed on the platform (winch and pulleys not shown). The location of the pulleys 5 and 6 of the copra and the rotary platform at the axis of rotation of the latter provides a permissible, up to 2 °, angle of deviation of the ropes at significant angles of rotation of the platform.

Породу на забое щели разрущают подъемами и сбросами долот 2, перемещаемых по забою поворотами шкивной площадки 4.The rock at the bottom of the gap is destroyed by rises and drops of bits 2, which are moved around the face by the turns of the pulley pad 4.

Стенки щелей поддерживают глинистым раствором. Разбуренную породу выдают на 0 поверхность пульпоэрлифтом по отдельно или совместно с долотами подвещенным колоннам труб.The walls of the cracks support mud. The drilled rock is delivered to the surface by pulpoherlift, separately or together with bits, to the well-known pipe columns.

В форшахте 7 изготавливают опускную крепь 8.In forshahte 7 make lowering support 8.

В бетон крепи заделывают трубы 9 и используют их дл  промывки в процессе погружени  крепи и тампонажа закрепного пространства после погружени .Tubes 9 are embedded in concrete lining and are used for flushing during immersion of the lining and cementing of the fixing space after immersion.

Крепь 8 погружают через наустойчивые и другие породы разбуриванием их в про0 межутках между щел ми по обе стороны ножа крепи до создани  в крепких породах выступа,скалываемого зубь ми ножа усилием гидродомкратов, весом крепи.The support 8 is immersed through pressure-resistant and other rocks by drilling them in the spaces between the slots on either side of the knife lining until a projection is formed in strong rocks, cleaved by the knife teeth with the force of hydraulic jacks and the weight of the support.

Вертикальность погружени  крепи обеспечивают одновременным разбуриванием по5 роды в диаметрально противоположных участках и вертикальностью щелей 1.The verticality of the immersion lining provides simultaneous drilling of rocks in diametrically opposite areas and vertical slots 1.

После погружени  опускной крепи на проектную глубину и тампонажа закрепного пространства осуществл ют выемку 0 породы внутри крепи любым способом л осущетсвл ют дальнейшую проходку ствола , использу  дл  этого копер 3.After immersion of the support roof to the design depth and tamponage of the anchored space, excavation of the rock inside the roof support is carried out in any way; further penetration of the trunk is carried out using a pile driver 3.

Предлагаемое изобретение позволит расширить область эффективного примег нени  способа проходки горной выработки опускной крепью.The present invention will allow to expand the area of effective application of the method of penetration of mine workings with a drop support.

БB

8eight

22

Фиг.FIG.

00

00

mm

IIIIII

I I II I I

фиг. 4FIG. four

Claims (3)

1. СПОСОБ ПРОХОДКИ ГОРНОЙ ВЫРАБОТКИ ОПУСКНОЙ КРЕПЬЮ, включающий создание слоя глинистого раст вора между породой и крепью, отличающийся тем, что, с целью расширения области эффективного его применения, на пути погружения крепи в породе бурят' щели, расположенные по периметру крепи, и разбуривают породу в промежутках между щелями в процессе погружения крепи.1. METHOD FOR MINING THE MINING WITH A DOWNWEAR, including creating a layer of clay solution between the rock and the support, characterized in that, in order to expand the area of its effective application, in the rock immersion the supports in the rock, drill gaps located around the perimeter of the support and drill the rock in the gaps between the cracks in the process of immersion lining. 2. Способ по п.1, отличающийся тем, что породу между щелями разбуривают по обе стороны ножевой части крепи до создания в крепких породах скалываемого зубьями крепи выступа.2. The method according to claim 1, characterized in that the rock between the slits is drilled on both sides of the knife part of the lining until a protrusion is cleaved off by the teeth of the lining in strong rocks. 3. Способ по π. 1, отличающийся тем, что породу в промежутках между щелями разбуривают одновременно в диаметрально противоположных участках крепи.3. The method according to π. 1, characterized in that the rock in the spaces between the slits is drilled simultaneously in diametrically opposite sections of the lining. Фиг. 1FIG. 1
SU823523655A 1982-11-16 1982-11-16 Method of sinking a mine working with sinking shaft lining SU1071755A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823523655A SU1071755A1 (en) 1982-11-16 1982-11-16 Method of sinking a mine working with sinking shaft lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823523655A SU1071755A1 (en) 1982-11-16 1982-11-16 Method of sinking a mine working with sinking shaft lining

Publications (1)

Publication Number Publication Date
SU1071755A1 true SU1071755A1 (en) 1984-02-07

Family

ID=21039770

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823523655A SU1071755A1 (en) 1982-11-16 1982-11-16 Method of sinking a mine working with sinking shaft lining

Country Status (1)

Country Link
SU (1) SU1071755A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661148A (en) * 2012-05-10 2012-09-12 中煤第一建设有限公司 Pneumatic assistance rock turning device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Трупак Н.Г. Специальные способы проведени горных выработок. М., 1964, с. 168-171. 2. Литинский Ю. В. и др. Проходка верхнего участка ствола методом погружени крепи в тиксотропной рубашке. - «Шахтное строительство, 1982, № 1, с. 24-26 (прототип). *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102661148A (en) * 2012-05-10 2012-09-12 中煤第一建设有限公司 Pneumatic assistance rock turning device

Similar Documents

Publication Publication Date Title
US5823276A (en) Diamond-tipped core barrel and method of using same
SU1071755A1 (en) Method of sinking a mine working with sinking shaft lining
CN104989409B (en) A kind of full face tunneling method after vertical shaft light section pore-forming
SU1352067A1 (en) Method of isolating vertical mine workings from subsoil water inflow
JP3948655B2 (en) Construction method of retaining wall and underground structure
Daw et al. Grouting for ground water control in underground mining
RU2098629C1 (en) Method for sinking of shallow mine shafts
SU1133406A1 (en) Shaft-sinking set
JPS5920820B2 (en) Method for creating trenches for underground walls
Haswell Thames Cable Tunnel.
JPS60219321A (en) Pile driving method
JP2004003229A (en) Method for constructing vertical shaft
SU757651A1 (en) Apparatus for tunneling narrow trenches
SU1671866A1 (en) Shaft tunneling method with pre-shaft drifting
RU2001200C1 (en) Method for reinforcement of rock slopes
SU898080A1 (en) Mine shaft sinking method
SU1286774A1 (en) Method of sinking mine shaft
RU94026329A (en) Method for mining of mineral deposits and superstructure for its embodiment
JPS5894598A (en) Level drilling method and drill guide used therein
SU670682A1 (en) Drainage curtain erecting method
SU1448063A1 (en) Method of controlling solid roof in mining bed deposits
RU2160838C2 (en) Method of prevention of earthquakes in potassium rock salt mines
JP2000145354A (en) Deep foundation excavation method in bedrock
SU1252492A1 (en) Method of driving an ascending mine working
RU2152507C1 (en) Method of insulating water-development strata