Procedure for the manufacture of construction elements consisting of machined pieces, assembled with the help of wedge links and a device for the implementation of this procedure
Download PDF
Info
Publication number
SI22415B
SI22415BSI200700304ASI200700304ASI22415BSI 22415 BSI22415 BSI 22415BSI 200700304 ASI200700304 ASI 200700304ASI 200700304 ASI200700304 ASI 200700304ASI 22415 BSI22415 BSI 22415B
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Grecon Dimter Holzoptimierung Nord Gmbh & Co.KgfiledCriticalGrecon Dimter Holzoptimierung Nord Gmbh & Co.Kg
Publication of SI22415ApublicationCriticalpatent/SI22415A/en
Publication of SI22415BpublicationCriticalpatent/SI22415B/en
B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
B27F—DOVETAILED WORK; TENONS; SLOTTING MACHINES FOR WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES
B27F1/00—Dovetailed work; Tenons; Making tongues or grooves; Groove- and- tongue jointed work; Finger- joints
B27F1/16—Making finger joints, i.e. joints having tapers in the opposite direction to those of dovetail joints
B—PERFORMING OPERATIONS; TRANSPORTING
B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
B27M—WORKING OF WOOD NOT PROVIDED FOR IN SUBCLASSES B27B - B27L; MANUFACTURE OF SPECIFIC WOODEN ARTICLES
B27M3/00—Manufacture or reconditioning of specific semi-finished or finished articles
B27M3/0013—Manufacture or reconditioning of specific semi-finished or finished articles of composite or compound articles
B27M3/002—Manufacture or reconditioning of specific semi-finished or finished articles of composite or compound articles characterised by oblong elements connected at their ends
Landscapes
Engineering & Computer Science
(AREA)
Life Sciences & Earth Sciences
(AREA)
Wood Science & Technology
(AREA)
Forests & Forestry
(AREA)
Manufacturing & Machinery
(AREA)
Mechanical Engineering
(AREA)
Forging
(AREA)
Vehicle Body Suspensions
(AREA)
Abstract
The procedure for the manufacture of longitudinal workpieces assembled with the help of wedge-shaped workpiece links, consists of a workstation (1'') in which the processing unit (14) is adapted for frontal and lateral milling of the current pair of wooden workpieces in the form of panels mutually set apart for the application of glue to such a manufactured wedge linking profile, and for combining both workpieces as well as a profile press (3) attached in the flow- direction (2), which is equipped for batch pressing of a batch of combined workpieces from a profile consisting of several workpieces. By the feeding displacements, which are every time located on both sides of the clamping columns (6, 7) being distributed - looking in the flow direction (2) - before and after the working area of the processing unit (14), such a movement of the joined profile is adapted to the pressing position in the profile press (3) which is designed exclusively as a thrusting movement.
Claims (4)
1 // Patentni zahtevki 1. Postopek za kvazikontinuirano izdelavo gradbenih elementov, ki sestojijo iz obdelovancev, ki so iz lesa, so ploščasti ali paličasti in so čelnostransko sestavljeni s klinastimi spoji, pri čemer se obdelovanci drug za drugim vodijo v delovno postajo (1"), pozicionirajo čelnostransko z medsebojnim razmikom, naravnajo, rezkajo, prevlečejo z lepilom in sestavijo, pri čemer se v delovni postaji (1") obdelovalna enota (14), ki nosi rezkalno orodje in pa razmestitev (31, 32) šob, vertikalno vodi skozi režo med dvema na medsebojni razdalji nasproti ležečima čelnima stranema dveh obdelovancev z namenom izdelave spojnih profilov in pa nanosa lepila na obeh čelnih straneh, in pri čemer se nato gradbeni element, ki sestoji iz več zgolj sestavljenih obdelovancev dokončno izdela v pramenski stiskalnici (3) ob istočasnem stiskanju vseh sestavljenih klinastih spojev.1. A method for the quasicontinuous production of building elements consisting of woodworked workpieces, are planar or rod-shaped, and are sidecuted with wedge joints, wherein the workpieces are run down one after another to the workstation (1 " ) are positioned internally by spacing, adapted, milled, coated with adhesive and assembled, wherein in the work station (1 ") a machining unit (14) which carries a milling tool and a placement (31, 32) of the nozzles, through a slot between the two at a distance from each other opposite the facing ends of the two workpieces for the purpose of producing joint profiles and applying the adhesive on both ends and whereby the building element consisting of several composite workpieces is finally manufactured in the diamond press (3) while simultaneously compressing all composite wedge joints.2. Postopek po zahtevku 1, značilen po tem, da se pramen, ki sestoji iz najmanj dveh, čelnostransko sestavljenih obdelovancev, tekom nadaljnje obdelave transportira zgolj s potisnim gibanjem.Method according to Claim 1, characterized in that the strand consisting of at least two stranded composite workpieces is only transported during a further treatment with a pushing movement.3. Postopek po zahtevku 1 ali 2, značilen po tem, da se za izvedbo postopka rezkanja vsakokratno rezkalno orodje vodi od zgoraj navzdol skozi obdelovanec.The method according to claim 1 or 2, characterized in that the milling tool is carried out from the top down through the workpiece to perform the milling process.4. Naprava za izdelavo gradbenega elementa, ki sestoji iz najmanj dveh obdelovancev, ki sta iz lesa, sta ploščasti ali paličasti in sta sestavljena preko klinastih spojev, z vsaj eno rezkalno napravo (1) obsegajočo delovno postajo (Γ), v kateri je moč vsakokrat dva, čelnostransko z medsebojnim razmikom držana, na ravni podlagi ležeča obdelovanca s pomočjo obdelovalne enote (14), ki je med njima vertikalno gibljiva in je na obeh proč od obdelovanca obrnjenih straneh opremljena z rezkalnimi orodji, obdelati z ozirom na izdelavo spojenih profilov, ki jih je moč sestaviti en v drugega po nanosu lepila, za izvedbo postopka po kateremkoli od zahtevkov od 1 do 3, značilna po tem, daje delovna postaja (1") namenjena in opremljena za en za drugim sledeče rezkanje, nanašanje lepila in sestavljanje z lepilom prevlečenih profilov obdelovancev, da delovni postaji (1") - gledano v smeri (2) prehoda obdelovancev -sledi pramenska stiskalnica (3), namenjena in opremljena za istočasno stiskanje vseh klinastih spojev gradbenih elementov, sestavljenih iz več sestavljenih obdelovancev, in da so vsa gibanja obdelovancev v napravi do končne izdelave gradbenega elementa zasnovana zgolj kot potisna gibanja.An apparatus for the construction of a building element consisting of at least two woodworkers, are planar or rod-shaped and are constituted by means of wedge joints, with at least one milling device (1) comprising a work station (Γ) in which power in each case two, spaced apart with a mutual spacing, on a level basis of a lying workpiece using a processing unit (14) which is vertically movable between them and is equipped with milling tools on both sides of the workpiece facing the workpiece, with respect to the production of coupled profiles, which can be assembled one after the other after application of the adhesive to perform the process according to any one of claims 1 to 3, characterized in that the work station (1 ") is intended and equipped for successive subsequent milling, adhesive application and assembling with adhesive coated workpiece profiles to the work station (1 ") - viewed in the direction of (2) the passage of the workpiece-followed by a strand press (3), designed and equipped for i simultaneous compression of all wedge joints of building elements made up of several composite work pieces, and that all movement of the workpieces in the device until the final construction of the building element is designed only as a pushing movement.
SI200700304A2006-11-242007-11-22Procedure for the manufacture of construction elements consisting of machined pieces, assembled with the help of wedge links and a device for the implementation of this procedure
SI22415B
(en)
Procedure for the manufacture of construction elements consisting of machined pieces, assembled with the help of wedge links and a device for the implementation of this procedure
Procedure for the manufacture of construction elements consisting of machined pieces, assembled with the help of wedge links and a device for the implementation of this procedure
ENERGY- SPACE- AND COST-SAVING METHOD FOR THE PRODUCTION OF ENDLESS WOODS THROUGH WEDGE-JOINTING TO GLUE-PLATED WOODEN CARRIERS AND OTHER WOODEN PRODUCTS THAT, TOO WELL, TOO WELL, TOO WELL
Dovetail joint gluing device for horizontal and vertical dovetailing has dovetailing machine working synchronously with connected longitudinal gluing machine