RU2518601C2 - Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter - Google Patents

Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter Download PDF

Info

Publication number
RU2518601C2
RU2518601C2 RU2012141074/03A RU2012141074A RU2518601C2 RU 2518601 C2 RU2518601 C2 RU 2518601C2 RU 2012141074/03 A RU2012141074/03 A RU 2012141074/03A RU 2012141074 A RU2012141074 A RU 2012141074A RU 2518601 C2 RU2518601 C2 RU 2518601C2
Authority
RU
Russia
Prior art keywords
lining
lifting
dismantled
hoist
crossbars
Prior art date
Application number
RU2012141074/03A
Other languages
Russian (ru)
Other versions
RU2012141074A (en
Inventor
Борис Михайлович Шевлягин
Вячеслав Моисеевич Фрумкин
Original Assignee
Закрытое Акционерное Общество "Спецжелезобетонстрой"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Закрытое Акционерное Общество "Спецжелезобетонстрой" filed Critical Закрытое Акционерное Общество "Спецжелезобетонстрой"
Priority to RU2012141074/03A priority Critical patent/RU2518601C2/en
Publication of RU2012141074A publication Critical patent/RU2012141074A/en
Application granted granted Critical
Publication of RU2518601C2 publication Critical patent/RU2518601C2/en

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

FIELD: construction.
SUBSTANCE: pipe is constructed in several stages. At the first stage the pipe shaft is concreted with simultaneous section-by-section build-up of a shaft hoist. Upon completion of pipe shaft concreting the blocks of the cargo cage are rested against a shaft hoist, the working site is dismantled, elements of the tent and device for working site lifting, dimensions of which prevent passage of the device in the assembled form via the outlet diameter of the pipe shaft cut, the dismantled elements are lowered in the cargo cage along the shaft hoist. The device for lifting of the working site is lowered along the shaft hoist down, from which angular stands are dismantled with adjacent crossbars and struts, and flexible links to zero elevation, in partially dismantled angular cells of the shaft hoist they install diagonal crossbars for increasing its stiffness; at the bottom the device is fully dismantled. Movement of the self-lifting device is carried out by four specified hoists as ropes are wound or unwound from hoist drums, at the same time to increase weight-lifting capacity of hoists, the rope of each hoist is directed to the assembly block and is returned to the self-lifting device on the frame. The assembly block with its hook with a latch is suspended onto a ring of a double-branch chain sling, each branch of which is fixed on a quick-detachable yoke, installed on the coupling of the shaft hoist stand. A lining site is suspended to the self-lifting device, from which heat insulation, lining works are performed, as well as anti-corrosion protection. When arranging another layer of lining, during lifting of the self-lifting device they restore flexible links and angular stands, and adjacent crossbars and struts under the lining site. When lowering the device, to prepare for arrangement of another layer under the lining site they dismantle angular stands, crossbars, struts and flexible links. After lining the blocks of the cargo cage are fixed on the cut of the pipe shaft. Cells of the shaft hoist are covered by shields installed onto crossbars, from which it is dismantled to zero elevation. Afterwards the self-lifting device is dismantled.
EFFECT: reduced metal intensity, labour intensiveness, higher quality of works and safety of labour, improved labour conditions.
4 cl, 9 dwg

Description

Изобретение относится к области строительства высотных железобетонных промышленных труб с многослойной футеровкой при малом выходном диаметре с применением многоклеточного шахтного подъемника.The invention relates to the field of construction of high-rise reinforced concrete industrial pipes with a multilayer lining with a small output diameter using a multicellular mine hoist.

Известен способ возведения высотных железобетонных труб (Стуканов А. А. Возведение монолитных железобетонных промышленных труб. Изд. 2-е, испр. и доп., Стройиздат, 1973, стр.110, рис.41, стр.128-131, стр.148-149). При этом способе бетонирование ствола трубы осуществляют с помощью шахтного подъемника с подъемным устройством для перемещения рабочей площадки. Доставку бетонной смеси с нулевой отметки производят в ковше грузовой клети шахтного подъемника. Поступившую в раздаточный бункер, закрепленный на подъемном устройстве, бетонную смесь загружают в емкости перемещения, которыми доставляют к месту укладки, выгружают через щель в рабочем настиле в опалубку.There is a method of erecting high-rise reinforced concrete pipes (A. Stukanov A. Erection of monolithic reinforced concrete industrial pipes. Ed. 2nd, rev. And add., Stroyizdat, 1973, p. 110, fig. 41, p. 128-131, p. 148-149). With this method, the concreting of the pipe trunk is carried out using a mine hoist with a lifting device to move the working platform. Concrete mixture is delivered from zero level in the bucket of the cargo stand of a mine hoist. Received into the dispensing hopper, mounted on a lifting device, the concrete mixture is loaded into the movement tanks, which are delivered to the installation site, unloaded through the slot in the working deck into the formwork.

После окончания бетонирования производят теплоизоляционные и футеровочные работы с помощью футеровочной площадки, подвешенной к дополнительному устройству для ее подъема приблизительно тех же габаритов, что и первый. Таким образом, в работе находятся одновременно два устройства.After concreting, heat-insulating and lining work is carried out using a lining pad suspended from an additional device for lifting it of approximately the same dimensions as the first. Thus, two devices are simultaneously in operation.

Известен способ футеровки и теплоизоляции с помощью футеровочной площадки, поднимаемой ручными талями (Стуканов А. А. Возведение монолитных железобетонных промышленных труб. Изд. 2-е, испр. и доп., М. Стройиздат, 1973, стр.63, рис.27).There is a method of lining and thermal insulation using a lining pad lifted by manual hoists (A. A. Stukanov. Construction of monolithic reinforced concrete industrial pipes. Ed. 2-nd, rev. And add., M. Stroyizdat, 1973, p. 63, Fig. 27 )

Недостатком является применение ручного труда при подъеме футеровочной площадки.The disadvantage is the use of manual labor when lifting the lining pad.

Известен способ возведения высотных железобетонных труб, включающий бетонирование ствола трубы с рабочей площадки, перемещаемой устройством для ее подъема по отношению к шахтному подъемнику, транспортирование материалов и бетонной смеси в зону производства работ при одновременном наращивании шахтного подъемника до достижения сооружаемой трубой проектной отметки, после выполнения бетонирования ствола трубы устройство подъема рабочей площадки отсоединяют от шатра, опускают до нулевой отметки, подвешивают к нему футеровочную площадку, с которой выполняют антикоррозионные, футеровочные и теплоизоляционные работы, а устройство для подъема материалов размещают на шатре, который опирают посредством диафрагмы жесткости на шахтный подъемник, или на обрез ствола трубы (SU 1441038 А1, 30.11.1988).A known method of erecting high-rise reinforced concrete pipes, including concreting a pipe trunk from a working platform, moved by a device for lifting it relative to a mine hoist, transporting materials and concrete mix to the work area while building up the mine hoist until the pipe being constructed reaches the design mark, after concreting the barrel of the pipe, the device for lifting the platform is disconnected from the tent, lowered to zero, and the lining area is suspended from it y, which operate anticorrosive lining and heat insulation work and a device for lifting material arranged on the tent, which rests by means of diaphragm stiffness mine hoist or bleed pipe barrel (SU 1441038 A1, 30.11.1988).

Недостатком такого способа является то, что при бетонировании и производстве футеровочных и теплоизоляционных работ используют одно и то же устройство подъема, в то время как при футеровочных и теплоизоляционных работах достаточно грузоподъемности почти в два раза меньше, чем при бетонировании ствола. Устройство для подъема перемещается по шахтному подъемнику постоянного поперечного сечения, что создает препятствие при футеровочных и теплоизоляционных работах в верхней части трубы, где диаметр при футеровке и теплоизоляции уменьшается до критических размеров, являющихся препятствием производству работ.The disadvantage of this method is that when concreting and producing lining and heat-insulating works, the same lifting device is used, while in lining and heat-insulating works, the carrying capacity is almost half as much as when concreting a barrel. The lifting device moves along the shaft lift of constant cross-section, which creates an obstacle during lining and heat-insulating operations in the upper part of the pipe, where the diameter during lining and thermal insulation decreases to critical dimensions, which are an obstacle to the work.

Известен способ строительства жаропрочных высотных железобетонных труб с малым выходным диаметром с большой толщиной теплоизоляции и футеровки из штучных материалов (RU 2405897 С1, 09.09.2009) (Прототип).A known method of construction of heat-resistant high-rise reinforced concrete pipes with a small output diameter with a large thickness of insulation and lining of piece materials (RU 2405897 C1, 09.09.2009) (Prototype).

При этом способе строительство трубы производят в два этапа: на первом этапе бетонируют ствол трубы с рабочей площадки, перемещаемой устройством для ее подъема по шахтному подъемнику при одновременном посекционном его наращивании с установкой гибких связей, бетонную смесь подают в грузовой клети в одной из ячеек шахтного подъемника.With this method, the construction of the pipe is carried out in two stages: at the first stage, the pipe trunk is concreted from the working platform, moved by a device for lifting it along the mine elevator while building it up in sections with flexible connections, the concrete mix is fed into the cargo stand in one of the mine elevator cells .

После окончания бетонирования ствола трубы демонтируют рабочую площадку, опирают блоки грузовой клети на шахтный подъемник, устройство подъема опускают по шахтному подъемнику, демонтируют угловые стойки шахтного подъемника до уровня, на котором диаметр будущей футеровки препятствует проходу футеровочной площадки, дальше продолжают опускать устройство для подъема до нулевой отметки без демонтажа стоек, где его демонтируют. Вместо него монтируют самоподъемное устройство, к которому подвешивают футеровочную площадку, с которой производят теплоизоляционные и футеровочные работы. Футеровочную площадку перемещают самоподъемным устройством по 16-стоечному шахтному подъемнику до отметки уменьшения диаметра футеровки до пределов, препятствующих прохождению шахтного подъемника по 16-стоечной схеме, поэтому с этой отметки переходят на 12-стоечную схему, которая получилась после демонтажа угловых стоек шахтного подъемника после окончания бетонирования ствола трубы.After concreting the trunk, the pipe is dismantled, the cargo stand blocks are supported on the mine hoist, the hoist is lowered along the mine hoist, the angle racks of the mine hoist are dismantled to a level at which the diameter of the future lining prevents passage of the liner, and the device for hoisting continues to lower to zero marks without dismantling racks, where it is dismantled. Instead, a self-lifting device is mounted to which the lining pad is suspended, from which heat-insulating and lining works are carried out. The lining pad is moved by a self-elevating device along the 16-post mine elevator to the point of decreasing the diameter of the lining to the limits that prevent the passage of the mine elevator according to the 16-post scheme, so from this mark they switch to the 12-post scheme, which was obtained after dismantling the corner posts of the elevator after concreting pipe trunk.

Недостатком такого способа является то, что после бетонирования ствола трубы при опускании устройства для подъема рабочей площадки ведут демонтаж угловых стоек не на всю высоту шахтного подъемника и в частично демонтированных угловых ячейках не ставят диагональные ригели, чем уменьшают жесткость и продольную устойчивость шахтного подъемника. После демонтажа устройства для подъема рабочей площадки монтируют самоподъемное устройство с размерами, расположенными со стороны внешних граней шахтного подъемника, равными размерам устройства для подъема рабочей площадки, что сказывается на увеличении габаритных размеров самоподъемного устройства. Футеровочные работы ведут из штучных материалов, например кирпича, ярусами высотой 500 мм, что не дает возможности проводить футеровочные работы из монолитного легкого бетона, например, из монолитного полимеркерамзитобетона.The disadvantage of this method is that after concreting the pipe trunk when lowering the device to raise the working platform, the corner posts are not dismantled not to the entire height of the shaft lift and diagonal crossbars are not placed in the partially dismantled corner cells, which reduces the rigidity and longitudinal stability of the shaft lift. After dismantling the device for lifting the working platform, a self-lifting device is mounted with dimensions located on the side of the external faces of the mine hoist equal to the dimensions of the device for lifting the working platform, which affects the increase in overall dimensions of the self-lifting device. Lining works are carried out from piece materials, for example, bricks, in tiers with a height of 500 mm, which makes it impossible to carry out lining works from monolithic lightweight concrete, for example, from monolithic polymer-ceramic-concrete.

Цель изобретения устранить отмеченные недостатки.The purpose of the invention is to eliminate the noted disadvantages.

Указанную цель достигают тем, что строительство трубы проводят в несколько этапов: на первом этапе бетонируют ствол трубы с одновременным постепенным наращиванием шахтного подъемника. После окончания бетонирования ствола трубы, демонтажа рабочей площадки и элементов шатра, выходящих за габарит выходного диаметра ствола трубы, опускания демонтированных элементов в грузовой клети на нулевую отметку, опирают блоки грузовой клети на шахтный подъемник, а оставшийся облегченный шатер на обрез ствола трубы, поддерживающий необходимый микроклимат внутри трубы и защищающий монтажников и работающее оборудование от атмосферных осадков. Устройство для подъема рабочей площадки опускают по шахтному подъемнику, одновременно демонтируют угловые стойки и примыкающие к ним ригели и раскосы шахтного подъемника, которые опускают в грузовой клети на нулевую отметку, устанавливают диагональные ригели в зоне частично разобранных угловых ячеек шахтного подъемника для увеличения его жесткости и продольной устойчивости. Устройство опускают до нулевой отметки, где его полностью демонтируют. Шахтный подъемник с частично демонтированными угловыми ячейками используют для футеровочных, теплоизоляционных и противокоррозионных работ, для чего на нулевой отметке собирают самоподъемное устройство, охватывающее снаружи многоклеточный шахтный подъемник с демонтированными угловыми стойками и примыкающими к ним ригелями и раскосами, имеющее меньший габаритный диаметр, обеспечивающий проход устройства через наименьшее поперечное сечение ствола трубы и имеющее меньшую грузоподъемность, обеспечивающую подъем полностью нагруженного устройства при необходимой нагрузке, которая значительно меньше нагрузки, требуемой при бетонировании ствола трубы. Перемещение самоподъемного устройства, содержащего каркас с четырьмя лебедками, расположенными параллельно диагональным ригелям по направлению диагональных осей шахтного подъемника, что дает возможность уменьшить габариты самоподъемного устройства; восемь страховочных стропов, идущих параллельно центральным стойкам внешнего контура шахтного подъемника; осуществляют четырьмя упомянутыми лебедками при наматывании или сматывании канатов с барабанов лебедок. Для увеличения грузоподъемности лебедок, канат каждой лебедки направляют на монтажный блок и возвращают к самоподъемному устройству, на котором крепят к специально предназначенному для этого узлу на каркасе, монтажный блок своим крюком с защелкой навешивают на кольцо двухветвевого цепного стропа, каждую ветвь которого закрепляют на быстроразъемном хомуте, установленном на муфте стойки шахтного подъемника. Самоподъемное устройство страхуют восемью одноветвевыми цепными стропами, изменяемой длины, используя такую конструкцию, получают возможность при необходимости менять длину цепного стропа на величину, минимально равную шагу цепи, максимально кратную длине стойки, равную 2500 мм, тем самым создают условия для выполнения футеровки как из штучных материалов с переменным шагом подъема (блоки из пеностекла, прижимная кладка из кирпича), так и из монолитного легкого бетона, например, (монолитного полимеркерамзитобетона) с применением внутренней трубной опалубки и подвесных лесов, подвешенных к футеровочной площадке, с которых ведут установку и переустановку щитов внутренней трубной опалубки или опалубки подобного вида, переустановку щитов производят с постоянным шагом подъема, определяемым высотой яруса бетонирования и высотой щита внутренней опалубки 1250 или 2500 мм; при переустановке щитов применяют два или три одинаковых внутренних щита, установленных друг на друга, при этом нижний используют как опорный для выше расположенных, после бетонирования очередного яруса нижний щит (опорный) снимают и переставляют на верхний, которому передают функции опорного. Верхние щиты образуют с предыдущим слоем футеровки кольцевую щель, в которую укладывают последующий слой монолитной футеровки, перед укладыванием очередного слоя монолитной футеровки верхние щиты раскрепляют специальными бандажами из круглой стали, установленными в зажимы на щитах для получения геометрической неизменяемости кольцевой щели и необходимой толщины монолитной футеровки. При новом положении самоподъемного устройства после его подъема лебедками устанавливают с помощью соединительного звена и крюка ограничителя необходимую длину страховочного стропа и подвешивают его с помощью быстроразъемного хомута к муфте стойки шахтного подъемника, опускают лебедками самоподъемное устройство до момента передачи нагрузки с каната лебедки на страховочный строп, последовательно переставляя быстроразъемные хомуты крепления монтажного блока подвески каната лебедки и установки страховочного каната и соответствующего подъема самоподъемного устройства, перемещают подвешенную к нему футеровочную площадку, с которой производят различного вида футеровочные работы; установку быстроразъемных хомутов крепления двухветвевого цепного стропа и страховочного стропа производят в различных уровнях со смещением по высоте как минимум на половину длины стойки, равную 1250 мм, тем самым устраняют возможность крепления их к одной и той же муфте стойки шахтного подъемника; для сохранения необходимого по технике безопасности зазора между футеровочной площадкой и футеровкой, равного не более 150 мм, по периметру футеровочной площадки устанавливают выдвижные консоли, регулирующие этот зазор, при устройстве очередного слоя футеровки, при подъеме специального устройства восстанавливают гибкие связи и угловые стойки, и примыкающие к ним ригели и раскосы под футеровочной площадкой; при опускании устройства для подготовки производства последующего слоя под футеровочной площадкой демонтируют угловые стойки, ригели, раскосы и гибкие связи; эти работы повторяют при подготовке, проведении и после окончания каждого слоя, количество которых зависит от объема, качества, разнообразия типов футеровки; после выполнения всех слоев футеровки блоки грузовой клети крепят на обрезе ствола трубы, ячейки шахтного подъемника перекрывают установленными на ригели щитами, с которых ведут его демонтаж, опуская демонтируемые элементы в грузовой клети, после чего демонтируют все устройство. Возможен вариант, при котором близкие по назначению и производству работ слои футеровки и совместимые между собой объединяют в один этап, например, блоки из пеностекла и прижимная кладка из кирпича. При обосновании жесткости и продольной устойчивости шахтного подъемника возможен вариант установки диагональных ригелей не на каждом уровне стоек шахтного подъемника.This goal is achieved by the fact that the construction of the pipe is carried out in several stages: at the first stage, the pipe trunk is concreted with a simultaneous gradual build-up of the mine hoist. After concreting the pipe trunk, dismantling the working platform and tent elements that go beyond the size of the output diameter of the pipe trunk, lowering the dismantled elements in the cargo stand to the zero mark, put the blocks of the cargo stand on the shaft lift, and the remaining lightweight tent on the edge of the pipe trunk, supporting the necessary microclimate inside the pipe and protecting installers and operating equipment from precipitation. The device for lifting the working platform is lowered along the mine hoist, at the same time, the corner posts and the crossbars and braces of the mine hoist adjacent to them, which are lowered to the zero mark in the cargo stand, are installed, the diagonal bolts are installed in the area of the partially dismantled corner cells of the mine hoist to increase its rigidity and longitudinal sustainability. The device is lowered to zero, where it is completely dismantled. A mine hoist with partially dismantled corner cells is used for lining, insulation and anti-corrosion work, for which a self-elevating device is assembled at the zero point, covering the outside of a multi-celled mine hoist with dismantled corner racks and adjacent crossbars and braces, having a smaller overall diameter that allows passage of the device through the smallest cross-section of the pipe trunk and having a lower carrying capacity, providing lifting fully loaded device with the required load, which is much less than the load required when concreting the pipe trunk. Moving a self-lifting device containing a frame with four winches located parallel to the diagonal crossbars in the direction of the diagonal axes of the mine hoist, which makes it possible to reduce the dimensions of the self-lifting device; eight safety slings running parallel to the central racks of the outer contour of the mine hoist; carry out the four mentioned winches when winding or winding ropes from the drums of winches. To increase the lifting capacity of the winches, the rope of each winch is sent to the mounting block and returned to the self-lifting device, on which they are attached to a unit specially designed for this purpose, the mounting block is hung with a latch hook on the two-branch chain sling ring, each branch of which is fixed on a quick-detachable clamp mounted on a shaft rack coupling. A self-lifting device is insured with eight single-branch chain slings, of variable length, using this design, it is possible, if necessary, to change the length of the chain sling by an amount minimally equal to the chain pitch, as much as a multiple of the rack length equal to 2500 mm, thereby creating the conditions for lining as piece materials with a variable pitch (blocks of foam glass, clamping brickwork), and of monolithic lightweight concrete, for example, (monolithic polymer-claydite concrete) using internal th tube formwork and suspended scaffolding suspended from the socket to the site from which lead the installation and re-installation of shields the inner tubular casing or casing of this type, reset panels produce a constant lifting step determines the height of concrete tiers and the height of the inner formwork panel 1250 or 2500 mm; when reinstalling the shields, two or three identical internal shields are used, mounted on top of each other, while the lower one is used as a support for the higher ones, after concreting the next tier, the lower shield (support) is removed and rearranged to the upper one, which is transferred to the support function. The upper panels form an annular gap with the previous layer of the lining, into which the next layer of the monolithic lining is laid, before laying the next layer of the monolithic lining, the upper panels are fastened with special round steel bandages installed in the clamps on the panels to obtain the geometric immutability of the annular gap and the required thickness of the monolithic lining. In the new position of the self-lifting device after lifting it, the winches are installed using the connecting link and the limiter hook to the necessary length of the safety line and suspended with a quick-release clamp to the shaft jack of the mine hoist, the self-lifting device is lowered by the winches until the load is transferred from the winch rope to the safety line, rearranging quick-disconnect clamps of fastening of the mounting block of a suspension bracket of a winch rope and installation of a safety rope and accordingly th lifting of the self-lifting device, move the lining pad suspended from it, from which various types of lining work are performed; the installation of quick-release clamps for attaching a two-branch chain sling and a safety sling is carried out at various levels with a height offset of at least half the rack length equal to 1250 mm, thereby eliminating the possibility of attaching them to the same shaft rack coupling; To maintain the necessary safety gap between the lining pad and the lining equal to not more than 150 mm, extendable consoles are installed around the perimeter of the lining pad to regulate this gap, when the next layer of the lining is installed, when lifting a special device, flexible connections and corner posts are restored, and adjacent to them crossbars and braces under the lining pad; when lowering the device to prepare the production of the next layer under the liner, dismantle the corner posts, crossbars, braces and flexible connections; these works are repeated during the preparation, conduct and after the end of each layer, the amount of which depends on the volume, quality, variety of types of lining; after all layers of the lining have been completed, the blocks of the cargo stand are mounted on the edge of the pipe trunk, the cells of the mine hoist are covered with shields installed on the crossbars, from which they are dismantled, lowering the dismantled elements in the cargo stand, after which the entire device is dismantled. A variant is possible in which the layers of the lining, which are close in purpose and work, and are compatible with each other, are combined in one stage, for example, foam glass blocks and brick pressing masonry. When substantiating the rigidity and longitudinal stability of the mine hoist, it is possible to install diagonal crossbars not at each level of the racks of the mine hoist.

Такое техническое решение обеспечивает строительство высотных железобетонных промышленных труб с многослойной футеровкой как из штучных материалов, так и монолитного легкого бетона, например, монолитного полимеркерамзитобетона при малом выходном диаметре, повышает производительность, качество работ и безопасность труда, снижает трудоемкость и металлоемкость конструкции.Such a technical solution ensures the construction of high-rise reinforced concrete industrial pipes with multilayer lining from piece materials and monolithic lightweight concrete, for example, monolithic polymerceramite concrete with a small output diameter, increases productivity, work quality and labor safety, reduces the complexity and metal consumption of the structure.

Способ строительства высотных железобетонных промышленных труб с многослойной футеровкой при малом выходном диаметре поясняется на чертежах.The method of construction of high-rise reinforced concrete industrial pipes with multilayer lining with a small output diameter is illustrated in the drawings.

На фиг.1 показана схема бетонирования ствола трубыFigure 1 shows a concreting diagram of a pipe trunk

На фиг.2 показана общая схема футеровочных работ.Figure 2 shows the General scheme of lining operations.

На фиг.3 показана схема работ по монолитной футеровке.Figure 3 shows the scheme of work on a monolithic lining.

На фиг.4 показан фрагмент монолитной футеровки.Figure 4 shows a fragment of a monolithic lining.

На фиг.5 показано расположение лебедок на самоподъемном устройстве.Figure 5 shows the location of the winches on a self-lifting device.

На фиг.6 показано сечение шахтного подъемника в плане при бетонировании ствола трубы.Figure 6 shows a cross section of a mine elevator in plan when concreting a pipe trunk.

На фиг.7 показано сечение шахтного подъемника в плане после демонтажа угловых стоек, с примыкающими к ним ригелями и раскосами, после окончания бетонирования ствола трубы.Figure 7 shows a cross section of a mine elevator in plan after dismantling the corner posts, with crossbars and braces adjacent to them, after concreting the pipe trunk.

На фиг.8 показано усиление шахтного подъемника диагональными ригелями. после частичного демонтажа угловых ячеек.On Fig shows the reinforcement of the mine hoist with diagonal crossbars. after partial dismantling of the corner cells.

На фиг.9 показана схема установки на стойку шахтного подъемника быстроразъемного хомута, и крепление к нему крюка ограничителя цепного со страховочным цепным стропом регулируемой длины.In Fig.9 shows a diagram of the installation on a rack of a mine hoist quick disconnect collar, and fastening to it a chain limiter hook with a safety chain sling of adjustable length.

На фигурах обозначено: 1 - многоклеточный шахтный подъемник, 2 - ствол трубы, 3 - рабочая площадка, 4 - устройство для подъема рабочей площадки, 5 - блоки грузовой клети, 6 - шатер, 7 - грузовая клеть, 8 - внутренние щиты опалубки, 9 - наружные щиты опалубки, 10 - гибкая связь, 11 - консоль ствола трубы, 12 - стойка, 13 - раскос, 14 - ригель, 15 - самоподъемное устройство, 16 - лебедка перемещения самоподъемного устройства, 17 - канат лебедки, 18 - быстроразъемный хомут, 19 - монтажный блок, 20 - кольцо двухветвевого цепного стропа, 21 - двухветвевой цепной строп, 22 - облегченный шатер, 23 - диагональный ригель, 24 - одноветвевой цепной страховочный строп, 25 - футеровочная площадка, 26 - выдвижная консоль, 27 - теплоизоляционный монолитный легкий полимер-керамзитобетон ствола трубы, 28 - блоки из пеностекла, 29 - прижимная кладка из кислотоупорного кирпича, 30 - специальный бандаж из круглой стали, 31 - верхний внутренний щит, 32 - нижний внутренний щит, 33 - подвесные леса, 34 - каркас самоподъемного устройства, 35 - крюк ограничитель цепной.The figures indicate: 1 - a multicellular shaft lift, 2 - a pipe trunk, 3 - a work platform, 4 - a device for lifting a work platform, 5 - blocks of a cargo stand, 6 - a tent, 7 - a cargo stand, 8 - internal formwork panels, 9 - external formwork panels, 10 - flexible connection, 11 - pipe trunk console, 12 - strut, 13 - brace, 14 - crossbar, 15 - self-lifting device, 16 - winch for moving self-lifting device, 17 - winch rope, 18 - quick-release clamp, 19 - mounting block, 20 - two-branch chain sling ring, 21 - two-branch chain sling, 22 - lightweight w ather, 23 - diagonal crossbar, 24 - single-branch chain safety sling, 25 - lining pad, 26 - extendable console, 27 - heat-insulating monolithic lightweight polymer-expanded clay concrete pipe trunk, 28 - foam glass blocks, 29 - acid-resistant brick pressing masonry, 30 - a special bandage made of round steel, 31 - the upper inner shield, 32 - the lower inner shield, 33 - suspended scaffolding, 34 - the frame of the self-lifting device, 35 - hook limiter chain.

Работы ведут в несколько этапов. С применением шахтного подъемника 1 производят бетонирование ствола 2 трубы с рабочей площадки 3, перемещаемой устройством 4 для ее подъема по отношению к шахтному подъемнику 1 при одновременном его наращивании с установкой гибких связей 10, бетонную смесь подают грузовой клетью 7 канатом, идущим от нее через блок 5 грузовой клети к лебедке, расположенной на нулевой отметке, грузовой блок устанавливают в верхней части шатра 6, бетонную смесь опускают через кольцевую щель в рабочей площадке в кольцевое пространство между внутренними 8 и наружными 9 щитами опалубки.Work is carried out in several stages. Using the mine hoist 1, the barrel 2 of the pipe is concreted from the working platform 3, moved by the device 4 for lifting it with respect to the mine hoist 1 while building it up with the installation of flexible connections 10, the concrete mixture is fed by a cargo cage 7 with a rope going from it through the block 5 of the cargo stand to the winch, located at the zero mark, the cargo block is installed in the upper part of the tent 6, the concrete mixture is lowered through the annular gap in the working platform into the annular space between the inner 8 and the outer E 9 shuttering boards.

На втором этапе после окончания бетонирования ствола 2 демонтируют рабочую площадку 3, элементы шатра 6, устройства для подъема 4, препятствующие прохождению их через выходной диаметр трубы, опуская демонтированные элементы в грузовой клети 7 на нулевую отметку. Опирают блоки 5 грузовой клети на шахтный подъемник 1, а оставшийся облегченный шатер 22 на обрез ствола трубы, создающий необходимый микроклимат внутри ствола трубы и защищающий монтажников и оборудование от атмосферных осадков. Устройство подъема 4 опускают по шахтному подъемнику, демонтируют угловые стойки 12 шахтного подъемника до нулевой отметки. По ходу опускания самоподъемного устройства в частично демонтированных угловых ячейках устанавливают диагональные ригели. Внизу демонтируют устройство подъема 4 полностью.At the second stage, after concreting of the barrel 2, the platform 3 is dismantled, the tent elements 6, lifting devices 4, which prevent them from passing through the pipe outlet diameter, lowering the dismantled elements in the cargo stand 7 to the zero mark. Blocks 5 of the cargo stand are supported on the mine lift 1, and the remaining lightweight tent 22 is cut off the pipe trunk, creating the necessary microclimate inside the pipe trunk and protecting the installers and equipment from atmospheric precipitation. The lifting device 4 is lowered along the mine hoist, the corner posts 12 of the mine hoist are dismantled to zero. In the course of lowering the self-lifting device, diagonal crossbars are installed in the partially dismantled corner cells. Below, dismantle the lifting device 4 completely.

На нулевой отметке собирают самоподъемное устройство 15, охватывающее снаружи многоклеточный шахтный подъемник 1 и имеющий малый габаритный диаметр, обеспечивающий проход устройства через наименьшее сечение ствола трубы.At the zero point, a self-lifting device 15 is assembled, covering the outside of the multicellular shaft lift 1 and having a small overall diameter, allowing the device to pass through the smallest section of the pipe trunk.

Перемещение самоподъемного устройства 15, содержащего каркас 35, с четырьмя лебедками 16, расположенными параллельно диагональным ригелям по направлению диагональных осей шахтного подъемника, восемь страховочных стропов 24, идущих параллельно центральным стойкам внешнего контура шахтного подъемника, осуществляют четырьмя упомянутыми лебедками 16 при наматывании и сматывании каната 17 с барабанов лебедок, при этом, для увеличения грузоподъемности лебедок 16, канат 17 каждой лебедки направляют на монтажный блок 19 и возвращают к самоподъемному устройству 15, на котором крепят к специально предназначенному узлу на каркасе 34, монтажный блок своим крюком с защелкой навешивают на кольцо 20, двухветвевого стропа 17, каждую ветвь которого закрепляют на быстроразъемном хомуте 18, установленном на муфте стойки 12 шахтного подъемника; самоподъемное устройство страхуют восемью одноветвевыми цепными стропами 24. Конструкция стропа позволяет менять его длину на величину, минимально равную шагу цепи, максимально 2500 мм или больше в зависимости от длины примененного стропа.The movement of the self-lifting device 15, containing the frame 35, with four winches 16 located parallel to the diagonal crossbars in the direction of the diagonal axes of the mine hoist, eight safety slings 24 running parallel to the central posts of the outer contour of the mine hoist, are carried out by the four mentioned hoists 16 when winding and winding the rope 17 from the drums of the winches, in this case, to increase the carrying capacity of the winches 16, the rope 17 of each winch is sent to the mounting block 19 and returned to the self-lifting device 15, which is secured to node specially adapted to the frame 34, its mounting unit hook to hang the snap ring 20, dvuhvetvevoj sling 17, each branch of which is fixed on the mounting clamps 18 mounted on the sleeve 12 rack mine hoist; a self-lifting device is insured with eight single-branch chain slings 24. The design of the sling allows you to change its length by an amount minimally equal to the chain pitch, maximum 2500 mm or more, depending on the length of the sling used.

При новом положении самоподъемного устройства 15 после его подъема лебедками 16 устанавливают с помощью крюка ограничителя 35 цепного стропа необходимую длину страховочного одноветвевого цепного стропа 24, опускают лебедками самоподъемное устройство до момента передачи нагрузки с каната 17 лебедки 16 на страховочный строп.With the new position of the self-lifting device 15, after lifting it by the winches 16, using the hook of the limiter 35 of the chain sling, set the necessary length of the safety single-chain chain sling 24, lower the self-lifting device with winches until the load is transferred from the rope 17 of the winch 16 to the safety sling.

К самоподъемному устройству 15 подвешивают футеровочную площадку 25, с которой производят теплоизоляционные и футеровочные работы. Для сохранения необходимого по технике безопасности зазора между футеровочной площадкой и кладкой футеровки, равного не более 150 мм по периметру футеровочной площадки, устанавливают выдвижные консоли 26, регулирующие этот зазор.A lining pad 25 is suspended from a self-lifting device 15, from which heat-insulating and lining works are performed. To maintain the necessary safety gap between the lining pad and the lining of the lining, equal to not more than 150 mm around the perimeter of the lining pad, retractable arms 26 are installed to control this gap.

Самоподъемное устройство страхуют восемью одноветвевыми цепными стропами 24, изменяемой длины, благодоря чему получают возможность при необходимости менять длину цепного стропа на величину, минимально равную шагу цепи, максимально кратную длине стойки, равную 2500 мм, тем самым создают условия для выполнения футеровки как из штучных материалов с переменным шагом подъема (блоки из пеностекла, прижимная кладка из кирпича), так и из монолитного легкого бетона, например, (монолитного полимеркерамзитобетона) с применением внутренней трубной опалубки с внутренними щитами 31,32 и подвесных лесов 33, подвешенных к консоли 25 футеровочной площадки 26, с которых ведут установку и переустановку щитов внутренней трубной опалубки или опалубки подобного вида, переустановку щитов производят с постоянным шагом подъема, определяемым высотой яруса бетонирования и высотой щита внутренней опалубки 1250 или 2500 мм; при переустановке щитов применяют два или три одинаковых внутренних щита, установленных друг на друга, при этом нижний 32 используют как опорный для выше расположенных, после бетонирования очередного яруса нижний щит 32 (опорный) снимают и переставляют на верхний 31, которому передают функции опорного. Верхние щиты образуют с предыдущим слоем футеровки кольцевую щель, в которую укладывают последующий слой монолитной футеровки, перед укладыванием очередного слоя монолитной футеровки верхние щиты раскрепляют специальными бандажами 30 из круглой стали, установленными в зажимы на щитах для получения геометрической неизменяемости кольцевой щели и необходимой толщины монолитной футеровки. При новом положении самоподъемного устройства после его подъема лебедками устанавливают с помощью соединительного звена и крюка ограничителя 35 необходимую длину страховочного стропа и подвешивают его с помощью быстроразъемного хомута 18 к муфте стойки 11 шахтного подъемника, опускают лебедками самоподъемное устройство до момента передачи нагрузки с каната лебедки на страховочный строп, последовательно переставляя быстроразъемные хомуты крепления монтажного блока 19 подвески каната 17 лебедки 16 и установки страховочного каната 24 и соответствующего подъема самоподъемного устройства перемещают подвешенную к нему футеровочную площадку 25, с которой производят различного вида футеровочные работы; установку быстроразъемных хомутов крепления двухветвевого цепного стропа и страховочного стропа производят в различных уровнях со смещением по высоте как минимум на половину длины стойки, равную 1250 мм, тем самым устраняют возможность крепления их к одной и той же муфте стойки шахтного подъемника; для возможности необходимого по технике безопасности зазора между футеровочной площадкой и футеровкой, равного не более 150 мм, по периметру футеровочной площадки устанавливают выдвижные консоли 26, регулирующие этот зазор, при устройстве очередного слоя футеровки, при подъеме специального устройства восстанавливают гибкие связи 10 и угловые стойки 12, и примыкающие к ним ригели 14 и раскосы 13 под футеровочной площадкой 25; при опускании устройства для подготовки проведения последующего слоя под футеровочной площадкой 25 демонтируют угловые стойки 12, ригели 14, раскосы 13 и гибкие связи 10; эти работы повторяют при подготовке, проведении и после окончания каждого слоя, количество которых зависит от объема, качества, разнообразия типов футеровки; после выполнения всех слоев футеровки блоки грузовой клети 5 крепят на обрезе ствола трубы, ячейки шахтного подъемника перекрывают установленными на ригели щитами, с которых ведут его демонтаж, опуская демонтируемые элементы в грузовой клети, после чего демонтируют все устройство. Возможен вариант, при котором близкие по назначению и производству работ слои футеровки и совместимые между собой объединяют в один этап, например, блоки из пеностекла 28 и прижимная кладка из кирпича 29. При обосновании жесткости и продольной устойчивости шахтного подъемника возможен вариант установки диагональных ригелей не на каждом уровне стоек шахтного подъемника.The self-lifting device is insured with eight single-branch chain slings 24, of variable length, due to which they get the opportunity, if necessary, to change the length of the chain sling by an amount that is at least equal to the chain pitch, as much as a multiple of the rack length, equal to 2500 mm, thereby creating conditions for lining as from piece materials with a variable lifting step (foam glass blocks, clamping masonry made of brick), and of monolithic lightweight concrete, for example (monolithic polymer-claydite concrete) using an internal pipe op formwork with internal shields 31.32 and hanging scaffolds 33, suspended from the console 25 of the lining platform 26, from which the shields of the internal pipe formwork or formwork of this kind are installed and reinstalled, the shields are reinstalled with a constant lifting step, determined by the height of the concrete level and the height of the shield inner formwork 1250 or 2500 mm; when reinstalling the shields, two or three identical internal shields are used, installed on top of each other, while the bottom 32 is used as a support for the higher ones, after concreting the next tier, the bottom shield 32 (support) is removed and rearranged to the upper 31, to which the support functions are transferred. The upper panels form an annular gap with the previous layer of the lining, into which the next layer of the monolithic lining is laid, before laying the next layer of the monolithic lining, the upper panels are fastened with special round steel bandages 30 installed in the clamps on the panels to obtain the geometric immutability of the annular gap and the required thickness of the monolithic lining . In the new position of the self-lifting device after lifting it, the winches set the necessary length of the safety line using the connecting link and the limiter hook 35 and hang it with the quick-release clamp 18 to the coupling of the rack 11 of the mine hoist, lower the self-lifting device with the winches until the load is transferred from the winch rope to the safety sling, sequentially rearranging quick-release clamps of fastening of the mounting block 19 of the suspension of the rope 17 of the winch 16 and the installation of the safety rope 24 and sponding jack-lifting device are moved hanging from it lining pad 25, which produce various types of lining works; the installation of quick-release clamps for attaching a two-branch chain sling and a safety sling is carried out at various levels with a height offset of at least half the rack length equal to 1250 mm, thereby eliminating the possibility of attaching them to the same shaft rack coupling; for the possibility of a necessary safety gap between the liner and the liner, equal to not more than 150 mm, extendable consoles 26 are installed around the perimeter of the liner to regulate this gap, when the next layer of the liner is installed, when the special device is lifted, flexible connections 10 and corner posts 12 are restored , and adjacent bolts 14 and braces 13 under the lining pad 25; when lowering the device to prepare the subsequent layer under the lining pad 25, the corner posts 12, the crossbars 14, the braces 13 and the flexible connections 10 are dismantled; these works are repeated during the preparation, conduct and after the end of each layer, the amount of which depends on the volume, quality, variety of types of lining; after all layers of the lining have been completed, the blocks of the cargo stand 5 are mounted on the edge of the pipe trunk, the cells of the mine hoist are covered with shields installed on the crossbars from which they are dismantled, lowering the dismantled elements in the cargo stand, after which the entire device is dismantled. A variant is possible in which the lining layers, which are close in purpose and work, and are compatible with each other, are combined in one stage, for example, foam glass blocks 28 and brick pressing masonry 29. When substantiating the rigidity and longitudinal stability of the mine hoist, it is possible to install diagonal crossbars not on each level of racks of a mine elevator.

Claims (4)

1. Способ строительства высотных железобетонных промышленных труб с многослойной футеровкой при малом выходном диаметре, включающий возведение ствола трубы с применением многоклеточного шахтного подъемника, подъемного устройства, охватывающего шахтный подъемник, и перемещаемой по нему рабочей площадки с опалубкой для бетонирования ствола трубы; бетонирование ствола трубы совмещают с постепенным монтажом шахтного подъемника и установкой гибких связей; подачу бетонной смеси, которую осуществляют грузовой клетью, канат которой через блоки, расположенные на подъемном устройстве рабочей площадки, направляют к лебедке, расположенной на нулевой отметке; работы по многослойной футеровке, включая теплоизоляционные, и по противокоррозионной защите, которые ведут с футеровочной площадки, отличающийся тем, что строительство трубы производят в несколько этапов; на первом этапе бетонируют ствол трубы с одновременным постепенным наращиванием шахтного подъемника; на втором этапе после окончания бетонирования ствола трубы, демонтажа рабочей площадки и элементов шатра, выходящих за габарит выходного диаметра ствола трубы, опускания демонтированных элементов в грузовой клети на нулевую отметку, опирают блоки грузовой клети на шахтный подъемник, а оставшийся облегченный шатер на обрез ствола, поддерживающий необходимый микроклимат внутри ствола трубы и защищающий монтажников и работающее оборудование от атмосферных осадков; устройство для подъема рабочей площадки опускают по шахтному подъемнику, одновременно демонтируют угловые стойки и примыкающие к ним ригели и раскосы шахтного подъемника, которые опускают в грузовой клети на нулевую отметку, устанавливают диагональные ригели в зоне частично разобранных угловых ячеек шахтного подъемника для увеличения его жесткости, устройство опускают до нулевой отметки, где его полностью демонтируют; шахтный подъемник используют для футеровочных, теплоизоляционных и противокоррозионных работ, для чего на нулевой отметке собирают самоподъемное устройство, охватывающее снаружи многоклеточный шахтный подъемник с демонтированными угловыми стойками и примыкающими к ним ригелями и раскосами, имеющее меньший габаритный диаметр, обеспечивающий проход устройства через наименьшее поперечное сечение ствола трубы и имеющее меньшую грузоподъемность, обеспечивающую подъем полностью нагруженного устройства при необходимой нагрузке, которая значительно меньше нагрузки, требуемой при бетонировании ствола трубы; перемещение самоподъемного устройства, содержащего каркас с четырьмя лебедками, расположенными параллельно диагональным ригелям по направлению диагональных осей шахтного подъемника, восемь страховочных стропов, идущих параллельно центральным стойкам внешнего контура шахтного подъемника; осуществляют четырьмя упомянутыми лебедками при наматывании или сматывании канатов с барабанов лебедок, при этом для увеличения грузоподъемности лебедок, канат каждой лебедки направляют на монтажный блок и возвращают к самоподъемному устройству, на котором крепят к специально предназначенному для этого узлу на каркасе, монтажный блок своим крюком с защелкой навешивают на кольцо двухветвевого цепного стропа, каждую ветвь которого закрепляют на быстроразъемном хомуте, установленном на муфте стойки шахтного подъемника; самоподъемное устройство страхуют восемью одноветвевыми цепными стропами, изменяемой длины, используя такую конструкцию, получают возможность при необходимости менять длину цепного стропа на величину, минимально равную шагу цепи, максимально кратную длине стойки, равную 2500 мм, тем самым создают условия для выполнения футеровки как из штучных материалов с переменным шагом подъема (блоки из пеностекла, прижимная кладка из кирпича), так и из монолитного полимеркерамзитобетона с применением внутренней трубной опалубки и подвесных лесов, подвешенных к футеровочной площадке, с которых ведут установку и переустановку щитов внутренней опалубки, соблюдая необходимое расстояние между предыдущим слоем и щитами равным толщине бетонируемого слоя полимеркерамзитобетона, переустановку щитов ведут с постоянным шагом подъема, определяемым высотой щита внутренней опалубки 1250 или 2500 мм; при переустановке щитов применяют два или три одинаковых внутренних щита, установленных друг на друга, при этом нижний используют как опорный для вышерасположенных, после бетонирования очередного яруса нижний щит (опорный) снимают и переставляют на верхний, которому передают функции опорного, в кольцевую щель, образованную верхними щитами с предыдущим слоем футеровки укладывают последующий слой монолитной футеровки, перед укладыванием очередного слоя монолитной футеровки верхние щиты раскрепляют специальными бандажами из круглой стали, установленными в зажимы на щитах для получения геометрической неизменяемости кольцевой щели и необходимой толщины монолитной футеровки, при новом положении самоподъемного устройства после его подъема лебедками устанавливают с помощью соединительного звена и крюка ограничителя необходимую длину страховочного стропа и подвешивают его с помощью быстроразъемного хомута к муфте стойки шахтного подъемника, опускают лебедками самоподъемное устройство до момента передачи нагрузки с каната лебедки на страховочный строп, последовательно переставляя быстроразъемные хомуты крепления монтажного блока подвески каната лебедки и установки страховочного каната и соответствующего подъема самоподъемного устройства перемещают подвешенную к нему футеровочную площадку, с которой производят различного вида футеровочные работы; установку быстроразъемных хомутов крепления двухветвевого цепного стропа и страховочного стропа производят в различных уровнях со смещением по высоте как минимум на половину длины стойки, равную 1250 мм, тем самым устраняют необходимость крепления их к одной и той же муфте стойки шахтного подъемника; для сохранения необходимого по технике безопасности зазора между футеровочной площадкой и футеровкой, равного не более 150 мм, по периметру футеровочной площадки устанавливают выдвижные консоли, регулирующие этот зазор, при устройстве очередного слоя футеровки, при подъеме специального устройства восстанавливают гибкие связи и угловые стойки, и примыкающие к ним ригели и раскосы под футеровочной площадкой; при опускании устройства для подготовки производства последующего слоя под футеровочной площадкой демонтируют угловые стойки, ригели, раскосы и гибкие связи; эти работы повторяют при подготовке, проведении и после окончания каждого слоя, количество которых зависит от объема, качества разнообразия типов футеровки; после выполнения всех слоев футеровки блоки грузовой клети крепят на обрезе ствола трубы, ячейки шахтного подъемника перекрывают установленными на ригели щитами, с которых ведут его демонтаж, опуская демонтируемые элементы в грузовой клети, после чего демонтируют все устройство.1. A method of constructing high-rise reinforced concrete industrial pipes with a multilayer lining with a small output diameter, comprising erecting a pipe trunk using a multicellular shaft hoist, a hoisting device covering the shaft hoist, and a work platform moved along it with formwork for concreting the pipe trunk; pipe trunk concreting is combined with the gradual installation of a mine hoist and the installation of flexible connections; supply of concrete mixture, which is carried out by a cargo cage, the rope of which through the blocks located on the lifting device of the working platform, is sent to the winch located at zero level; multilayer lining works, including heat-insulating ones, and anticorrosive protection, which are carried out from the lining pad, characterized in that the pipe is constructed in several stages; at the first stage, the pipe trunk is concreted with a simultaneous gradual buildup of the mine hoist; at the second stage, after concreting the pipe trunk, dismantling the working platform and tent elements that go beyond the size of the output diameter of the pipe trunk, lowering the dismantled elements in the cargo stand to the zero mark, rest the cargo stand blocks on the shaft lift, and the remaining lightweight tent on the edge of the trunk, supporting the necessary microclimate inside the pipe trunk and protecting installers and operating equipment from precipitation; the device for lifting the working platform is lowered along the shaft lift, at the same time the corner posts and the crossbars and braces of the shaft lift adjacent to them, which are lowered to the zero mark in the cargo stand, are installed, the diagonal crossbars are installed in the area of the partially dismantled corner cells of the shaft lift to increase its rigidity, device lowered to zero, where it is completely dismantled; the mine hoist is used for lining, heat insulation and anticorrosion works, for which a self-elevating device is assembled at the zero point, covering the outside of a multicellular mine hoist with dismantled corner posts and adjacent crossbars and braces, having a smaller overall diameter, allowing the device to pass through the smallest cross-section of the trunk pipes and having a lower carrying capacity, providing the lifting of a fully loaded device at the required load, which I significantly less load required during the concreting pipe barrel; moving a self-elevating device containing a frame with four winches parallel to the diagonal crossbars in the direction of the diagonal axes of the mine hoist, eight safety slings running parallel to the central racks of the outer contour of the mine hoist; carry out the four mentioned winches when winding or winding ropes from the drums of winches, while to increase the lifting capacity of the winches, the rope of each winch is sent to the mounting block and returned to the self-lifting device, on which the mounting block is attached to the assembly specially designed for this purpose on the frame with its hook with a latch they hang on the ring of a two-branch chain sling, each branch of which is fixed on a quick-disconnect collar installed on the coupling of the rack of the mine hoist; a self-lifting device is insured with eight single-branch chain slings, of variable length, using this design, they can, if necessary, change the length of the chain sling by an amount minimally equal to the chain pitch, as much as a multiple of the rack length equal to 2500 mm, thereby creating the conditions for lining as piece materials with a variable lifting step (foam glass blocks, brick pressing masonry), and from monolithic polymer-claydite concrete with the use of internal pipe formwork and suspended scaffolding, hung to the lining pad, from which the inner formwork panels are installed and reinstalled, observing the necessary distance between the previous layer and the boards equal to the thickness of the concrete layer of polymer-cement-concrete, the panels are reinstalled with a constant lifting step, determined by the height of the inner formwork shield 1250 or 2500 mm; when reinstalling the shields, two or three identical internal shields are used, mounted on top of each other, while the lower one is used as a support for the upstream ones, after concreting the next tier, the lower shield (support) is removed and rearranged to the upper one, which is transferred to the support slot, in the ring gap formed the next layer of the monolithic lining is laid with the upper shields with the previous layer of the lining; before laying the next layer of the monolithic lining, the upper shields are fastened with special bandages made of round steel whether installed in the clamps on the boards to obtain the geometric immutability of the annular gap and the required thickness of the monolithic lining, with the new position of the self-lifting device after lifting it with winches, the necessary length of the safety sling is installed using the connecting link and the limiter hook and suspended using a quick-release collar to the rack coupling shaft hoist, lower the winch self-lifting device until the load is transferred from the winch rope to the safety sling, the follower but moving the quick attachment mounting block clamps suspension rope winches and installation of the safety rope and the corresponding jack-lifting device are moved hanging from it lining pad, which produce various types of lining works; the installation of quick-release clamps for attaching a two-branch chain sling and a safety sling is carried out at various levels with a height offset of at least half the rack length equal to 1250 mm, thereby eliminating the need to fasten them to the same shaft coupling of the shaft lift; To maintain the necessary safety gap between the lining pad and the lining equal to not more than 150 mm, extendable consoles are installed around the perimeter of the lining pad to regulate this gap, when the next layer of the lining is installed, when lifting a special device, flexible connections and corner posts are restored, and adjacent to them crossbars and braces under the lining pad; when lowering the device to prepare the production of the next layer under the liner, dismantle the corner posts, crossbars, braces and flexible connections; these works are repeated during the preparation, conduct and after the end of each layer, the amount of which depends on the volume, quality of the variety of types of lining; after all layers of the lining have been completed, the blocks of the cargo stand are mounted on the edge of the pipe trunk, the cells of the mine hoist are covered with shields installed on the crossbars, from which they are dismantled, lowering the dismantled elements in the cargo stand, after which the entire device is dismantled. 2. Способ по п.1, отличающийся тем, что некоторые слои, близкие по назначению, способу производства работ и степени их совместимости, выполняют одним этапом, например, выполнение теплоизоляции из пеностекла и прижимной кладки из кислотоупорного кирпича.2. The method according to claim 1, characterized in that some layers, similar in purpose, to the method of work and the degree of their compatibility, are performed in one step, for example, insulation from foam glass and pressure masonry made of acid-resistant brick. 3. Способ по п.1, отличающийся тем, что при обосновании необходимой жесткости и продольной устойчивости шахтного подъемника диагональные ригели устанавливают не на каждом уровне стоек шахтного подъемника.3. The method according to claim 1, characterized in that when justifying the necessary rigidity and longitudinal stability of the mine hoist, diagonal crossbars are not installed at each level of the racks of the mine hoist. 4. Способ по п.1, отличающийся тем, что для устройства футеровки из легкого монолитного полимер-керамзитобетона к футеровочной площадке в местах выдвижных консолей подвешивают подвесные леса, с которых производят установку и перестановку внутренних щитов опалубки, чтобы в кольцевую щель между предыдущим слоем футеровки и щитами опалубки уложить монолитный полимер-керамзитобетон. 4. The method according to claim 1, characterized in that for the lining of lightweight monolithic polymer-expanded clay concrete, suspended scaffolds are suspended from the lining platform at the places of the retractable consoles, from which the inner formwork panels are installed and rearranged so that in the annular gap between the previous lining layer and formwork monolithic expanded clay-concrete concrete sheets to be placed on the formwork panels.
RU2012141074/03A 2012-09-26 2012-09-26 Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter RU2518601C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2012141074/03A RU2518601C2 (en) 2012-09-26 2012-09-26 Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2012141074/03A RU2518601C2 (en) 2012-09-26 2012-09-26 Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter

Publications (2)

Publication Number Publication Date
RU2012141074A RU2012141074A (en) 2014-04-10
RU2518601C2 true RU2518601C2 (en) 2014-06-10

Family

ID=50435634

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2012141074/03A RU2518601C2 (en) 2012-09-26 2012-09-26 Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter

Country Status (1)

Country Link
RU (1) RU2518601C2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU80815A1 (en) * 1948-11-19 1948-11-30 Н.И. Смирнов Scaffolding for the construction of factory pipes and similar structures
SU1059107A1 (en) * 1980-08-13 1983-12-07 Demin Vasilij F Method of constructing a flue
SU1116135A1 (en) * 1982-04-21 1984-09-30 Demin Vasilij F Arrangement for erecting flues
SU1441038A1 (en) * 1986-11-24 1988-11-30 Проектная Контора Треста "Спецжелезобетонстрой" Method of erecting high ferroconcrete flues
SU1527406A1 (en) * 1987-10-27 1989-12-07 Проектная Контора Треста "Спецжелезобетонстрой" Method of erecting industrial flues
RU2405897C1 (en) * 2009-09-09 2010-12-10 Закрытое Акционерное Общество "Спецжелезобетонстрой" Method for construction of heat-resistant high-rise reinforced concrete pipes with low exit diametre with high thickness of heat insulation and lining of piece materials

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU80815A1 (en) * 1948-11-19 1948-11-30 Н.И. Смирнов Scaffolding for the construction of factory pipes and similar structures
SU1059107A1 (en) * 1980-08-13 1983-12-07 Demin Vasilij F Method of constructing a flue
SU1116135A1 (en) * 1982-04-21 1984-09-30 Demin Vasilij F Arrangement for erecting flues
SU1441038A1 (en) * 1986-11-24 1988-11-30 Проектная Контора Треста "Спецжелезобетонстрой" Method of erecting high ferroconcrete flues
SU1527406A1 (en) * 1987-10-27 1989-12-07 Проектная Контора Треста "Спецжелезобетонстрой" Method of erecting industrial flues
RU2405897C1 (en) * 2009-09-09 2010-12-10 Закрытое Акционерное Общество "Спецжелезобетонстрой" Method for construction of heat-resistant high-rise reinforced concrete pipes with low exit diametre with high thickness of heat insulation and lining of piece materials

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
СТУКАНОВ А.А. Возведение монолитных железобетонных промышленных труб. Москва, Стройиздат, 1973, стр.63, рис.27, стр.110, рис.41, стр.128-131, стр.148-149 *

Also Published As

Publication number Publication date
RU2012141074A (en) 2014-04-10

Similar Documents

Publication Publication Date Title
EP3752691B1 (en) Apparatus and method for slipforming a shaft
CN108678422B (en) Method for dismantling steel chimney
CN104652807A (en) Self-turnover construction system and method for internal-climbing tower crane supporting steel beams in hydraulic formwork climbing system
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN103669845A (en) High-altitude long-span overhung cornice formwork supporting system and constructing method thereof
CN105569242A (en) Assembling method for composite floor slabs
KR20180127066A (en) Prefabricated shoring system
CN112324231A (en) Construction method for ultrahigh chimney lining layer
RU2380502C1 (en) Construction method of high-rise reinforced concrete buildings for example with industrial pipes and towers of small inner diametre
RU2476653C1 (en) Method of erecting high-rise reinforced concrete structures, for example, industrial chimney-stacks and towers
KR101068229B1 (en) Dismantled tower crane cargo handling system and cargo handling method using thereof
WO2011072328A1 (en) A loading platform
CN114109123A (en) Construction method of chimney barrel body
RU2518601C2 (en) Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter
RU2405897C1 (en) Method for construction of heat-resistant high-rise reinforced concrete pipes with low exit diametre with high thickness of heat insulation and lining of piece materials
CN104131706A (en) Vertical steel bar two-layer connecting structure of concrete framework structure and construction method of vertical steel bar two-layer connecting structure
US20070096006A1 (en) Overhead beam assembly
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN106284997A (en) The big punching block construction method for lifting whole of reinforced concrete chimney
RU2658397C2 (en) Method of construction of reinforced high-rise buildings with small inner diameter, with small slope of trunk and large wall, for example of supporting towers and masts
RU2574226C1 (en) Method of construction using multi-cage mine hoist of height reinforced concrete pipes with large thickness of lining with small outlet diameter and large ratio of outlet diameter to diameter in base
RU2544921C1 (en) Method to use multi-basket mine hoist for construction of reinforced concrete high-rise pipes with high thickness of lining, with small output diameter and with high ratio of outlet diameter to diameter in base
RU2334068C2 (en) Method of repair and reconstruction of high-rise reinforced concrete structures with variable taper, for instance, cooling towers and industrial pipes
CN210438301U (en) Light slat lifting device for building partition wall
JP5773343B2 (en) Method for constructing multi-story building and lifting device for multi-story scaffold used therefor

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20140927