WO2011072328A1 - A loading platform - Google Patents

A loading platform Download PDF

Info

Publication number
WO2011072328A1
WO2011072328A1 PCT/AU2010/001686 AU2010001686W WO2011072328A1 WO 2011072328 A1 WO2011072328 A1 WO 2011072328A1 AU 2010001686 W AU2010001686 W AU 2010001686W WO 2011072328 A1 WO2011072328 A1 WO 2011072328A1
Authority
WO
WIPO (PCT)
Prior art keywords
building
floor
inboard
level
loading platform
Prior art date
Application number
PCT/AU2010/001686
Other languages
French (fr)
Inventor
Steve Hardiman
Original Assignee
Steve Hardiman
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2009906110A external-priority patent/AU2009906110A0/en
Application filed by Steve Hardiman filed Critical Steve Hardiman
Publication of WO2011072328A1 publication Critical patent/WO2011072328A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/166Landings, receiving platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/22Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by roofs or ceilings

Definitions

  • the present invention relates to the building construction industry and in particular to cantilevered loading platforms that allow the loading of building materials in between constructed flows of a building under construction or refurbishment and will be described hereinafter with reference to this application.
  • the invention is not limited to this particular field of use.
  • the building material is typically delivered to each level using an on site tower crane which picks up the material and places it on a loading platform that is secured to the end of a level of the building. The materials delivered can then be used in the construction of each level. Similarly material to be removed is placed on the loading platform and removed by the tower crane. The material can then be moved to a desired location by the tower crane.
  • One prior art method includes the construction of a platform which protrudes from a level of a building on two large steel beams. A platform is placed in between the beams and the weight of the platform is supported by the beams. While this method generally provides a cheap solution it has large limitations.
  • the first major limitation is that the steel beams are heavy which makes the weight of the decks about 3tonnes. This limits the distance from the crane where they can be installed. This is because as a tower crane's capacity is reduced the further the distance a load is taken from the cranes centre. This also reduces the capacity of the load put onto the platform as the weight of the platform plus the load is transmitted onto the building structure.
  • the second major limitation is that the platforms cannot be located directly above one another as a platform below another platform is inaccessible to lowering loads onto with the tower crane. Therefore the platforms are staggered about the building which means the builder must leave staggered penetrations in the protective scaffold around the job.
  • Each platform is still extremely heavy weighing about 3 tonnes and each platform must be installed as a single unit on each floor which increases costs and the number of complete platforms required.
  • the prior art platforms also require large capacity tower cranes on building sites to allow the lifting of the heavy platforms.
  • Large capacity cranes are expensive and there is a need at some sites to use smaller more cost effective cranes.
  • inboard and outboard are used with reference to a building as follows. Items that are designated as inboard are disposed, when in use, within the perimeter of the relevant floor or level of the building. Items that are designated as outboard project from the building when in use and are disposed outside of that perimeter. The terms are also used to designate the relevant position of items at a point in time. Such items may be movable between an inboard position and an outboard position.
  • a loading platform for use on a building, the platform including: a first portion that is securely attachable to a level of the building; and a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
  • the first portion is substantially inboard. More preferably the second portion is substantially outboard.
  • the first portion is selectively detachable and reattachable to the level of a building.
  • the second portion is selectively detachable and reattachable to the first portion.
  • the second portion is adapted to support a load that includes building materials.
  • the building includes a plurality of levels.
  • the first portion is secured to the floor of the selected level.
  • the first portion is secured to the roof of the selected level.
  • the first portion is secured to the floor and roof of the selected level.
  • the second portion includes a truss structure that supports the load.
  • a building having a plurality of levels, the building including: a plurality of first portions of a loading support platform securely attached respectively to each of the plurality of levels; at least one second portion of the support platform that is securely attachable to at least one of the second portions, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
  • the second portion is selectively detachable and reattachable to a selected one of the first portions.
  • the second portion is adapted to support a load that includes building materials.
  • each respective first portion is secured to the respective floor of each respective level.
  • each respective first portion is secured to the respective roof of each respective level.
  • each first portion is secured to the respective floor and roof of each respective level.
  • each second portion includes a truss structure that supports the load.
  • a method of providing a loading support platform for use on a building including the step of: providing a first portion that is securely attachable to a floor of the building; and providing a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
  • Figure l is a side view of a loading platform according to the invention.
  • Figure 2 is a side view of a loading platform according to the invention.
  • Figure 3 is a side view of a loading platform according to the invention.
  • Figure 4 is a cut away top view of the loading platform of Figure 3;
  • Figure 5 is a side view of the loading platform of Figure 3;
  • Figure 6 is a section view of the loading platform of Figure 5;
  • Figure 7 is a close up view of a section of the loading platform of Figure 3;
  • Figure 8 is another section view of the loading platform of Figure 5;
  • Figure 9 is a view of the connection of the inboard and outboard portions shown at different degrees of rotation.
  • Figure 10 shows portions of the loading platform of Figure 5;
  • Figure 11 shows various strut or prop arrangements according to the invention
  • Figure 12 shows a cutting schedule according to the invention
  • Figures 13a - g show an animation of the loading platform
  • Figure 14 shows a view of a platform according to the invention.
  • Figure 15a - L show an animation of the engagement and disengagement of the outboard and inboard according to the invention.
  • FIG. 1 there is shown a side view of a construction site having a building 101 under construction.
  • the building includes a plurality of building levels 102, 103 and 104.
  • Level 102 is ground level and can be accessed from the ground or street level.
  • Levels 103 and 104 are raised off the ground and cannot be easily accessed for the supply and removal of building materials. Accordingly, the preferred embodiment of the invention provides access to supply and remove building materials from each level.
  • the preferred embodiment of the invention provides a loading platform 105 for use on the levels of the building.
  • the platform includes a first inboard portion 106a that is securely attachable to any of the levels of the building. It is preferred that each level of the building includes a respective first inboard portion as shown in Figure 1 where inboards 106b and 106c are attached to levels 103 and 102 respectively.
  • a second outboard portion 107a is securely attachable to any of the first inboard portions.
  • the outboard portion 107a is shown securely attached to inboard portion 106a.
  • the outboard portion 107a has a substantially horizontal support surface 108 that extends across an edge of the floor 104 for supporting a load that is placed on the support surface 108.
  • the first inboard portion is substantially disposed within the perimeter of the relevant floor on which it is placed or installed. That is, it does not protrude in any significant way outside the perimeter of the floor on which it is installed and as such does not inhibit the movement of building materials or the operation of cranes in any manner.
  • the second outboard portions project from the building when in use and are disposed outside of the perimeter of the relevant floor. In this way building materials are able to be delivered to and disposed on from the second outboard portions.
  • the first portions 106a, 106b and 106c are selectively detachable and reattachable to the level of a building. That is, they can be installed on all required levels of the building and can be removed when required or when the necessary construction or building on the relevant floor is completed. In some instances the inboard portions are moved and installed on a new floor once work on a completed floor has been completed so as to minimise the number of inboard portions required. In some embodiments the inboard portions are installed at different ends on each different level.
  • the second outboard portion 107a is selectively detachable and reattachable to any of the inboard portions 106a, 106b and 106c.
  • the building site may include a plurality of second portions similar or the same as 107a and each one may be installed simultaneously on a respective inboard portion if desired, although this would limit the delivery and removal of building materials and it is preferable that only one outboard portion be attached to an inboard portion in any one working area. This ensures that materials can be removed and delivered easily.
  • the outboard portion 107a is adapted to support any desired and suitable load. Under normal conditions the load includes building materials such as tools, equipment, bricks, cement, woodwork, rubble and the like. It would be understood that the load can be any suitable load that needs to be delivered or removed from the floor.
  • the inboard portions 106a, 106b and 106c are secured to the each level such that they will not move under normal loading conditions of the inboard or attached outboard portions.
  • any suitable securing means can be used.
  • the inboard portions are secured using one or more extendable struts that are connected on either end and on both sides of the inboard.
  • the struts are preferably telescopically extendable and are extended once the inboard is in place.
  • the struts secure the inboard portion to the level of the building on which it is placed. That is, the strut secures the inboard to the floor and ceiling of the level on which it is installed. In other words, the strut secured the inboard between two levels or "floors" of a building under construction.
  • the inboard can be secured by bolts or other means to the floor and/or ceiling/roof of each level.
  • Figure 2 shows a level 200 of a multi level building under construction.
  • Inboard portion 201 is installed and secured to one end 202 of level 200.
  • Outboard portion 203 is secured to inboard portion 201.
  • the inboard portion is secured to the level by means of pairs of struts 204 and 205.
  • the pair of struts 204 and 205 each have a strut installed on either side of the inboard portion however only one side can be seen in Figure 2. That is, four struts are used to secure the inboard to the level.
  • the struts can be positioned as necessary on the inboard portion. In some embodiments the struts are fixedly connected to the inboard and their position cannot be changed relative to the inboard.
  • the struts are simply moved into the unextended position which allows the struts to be removed or at least allows the inboard portion to be moved or removed.
  • aspects of the invention include rubbish or debris chutes are attached temporarily or permanently to the inboard or outboard portions so as to aid the removal of some debris or rubbish.
  • the cantilevered loading platforms according to the invention are constructed from steel although other suitable material may be used. Embodiments of the invention facilitate the loading of building materials in between the constructed floors of a building under construction or refurbishment where the crane cannot access.
  • Platforms according to the invention are preferably installed with an on site tower crane.
  • Preferred embodiments of platforms according to the invention have main structural members of a truss type design instead of a universal beam.
  • the truss design gives the tension strength required with much lighter materials which reduces the total deck self weight.
  • the outboard is removable from the section which is inside the building known as the inboard. This way the outboard deck can be located on which ever floor is desired so long as an inboard section is located there.
  • the platform is broken down in 6 manageable components making it easy to store and transport.
  • the first inboard portion and the second outboard portion include a truss structure that supports the load.
  • aspects of the invention extend to a building having a plurality of levels.
  • the building can have a plurality of first portions of a loading support platform securely attached respectively to each of the plurality of levels.
  • At least one second portion of the support platform is securely attachable to at least one of the second portions, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
  • the second portion is selectively detachable and reattachable to a selected one of the first portions.
  • a further embodiment of the invention provides a method of providing a loading support platform for use on a building, the method including the step of: providing a first portion that is securely attachable to a floor of the building; and providing a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
  • Figure 3 shows an embodiment of a loading platform secured to a level 301 of a building under construction.
  • Inboard portion 303 is secured to the level 301 using strut pairs 304 and 305 which can be telescopically extended to secure the inboard portion between the ceiling and floor of level 301.
  • the outboard portion 303 extends past the perimeter 306 of the level 301 by 1.2 metres.
  • the inboard does not extend past the perimeter.
  • the total length of the inboard portion is 4.8m with the portion inside the perimeter of the building being 3.6 metres. As would be understood these lengths can be amended as required.
  • Outboard portion 302 is securely attached to the inboard portion 303 and provides a secure and level platform on which to load or remove building material.
  • the length of the outboard portion is 3 metres and the thickness of the platform itself is 200 millimetres.
  • Figure 4 shows a top view of the loading platform of Figure 3 where the ceiling 401 has been cut away.
  • Figure 5 shows a side view of the loading platform of Figure 3.
  • the outboard portion 302 includes a floor 401 upon which a load can be placed.
  • inboard portion 303 includes a floor 402 upon which a load can be placed.
  • Railing 403 and 404 extends above the respective floors 401 and can be used by a person on standing or walking along the platform.
  • the railing 403 and 404 is also part of a truss structure which provides strength to the platform.
  • the truss structure used is Pratt truss design that uses vertical beams for compression and horizontal beams to respond to tension.
  • the truss includes vertical parts 405a, 405b, 405c, 405d, 405e, 405f and 405g.
  • the horizontal beams include the railing 403, 404 and floors 401 and 402.
  • Strut sections 406a, 406b, 406c, 406d, 406e and 406f extend between the floor and rail to form the required triangular
  • Figure 7 is a close up view of the attachment of the outboard in inboard portions.
  • the outboard portion includes male lugs 701 and the inboard includes engagable female lugs into which the male lugs engage.
  • a locking pin 703 locks the outboard and inboard lugs together.
  • Figure 9 is a view of the connection of the inboard and outboard portions shown at different degrees of rotation.
  • Figure 10 shows portions of the loading platform of Figure 5.
  • Figure 11 shows various strut or prop arrangements that securely attach the inboard portion to the required level.
  • Figure 12 shows a cutting schedule for an embodiment of the invention.
  • Figures 13a - g show an animation of the outboard portion disengaging from the inboard portion.
  • Figure 14 shows a further view of a platform according to an embodiment of the invention.
  • Figures 15a - L show an animation of the engagement and disengagement of the outboard and inboard. This shows the engagement and disengagement of the respective male and female portions.
  • a system according to the invention works by having an inboard deck on each floor where materials are to be delivered or removed.
  • An Inboard deck consists of 2 structural truss frames standing vertically, running perpendicular to the edge of the building, parallel to each other and 2.4m apart. Each of these is held into position via 2 props located at the innermost end. These two sections will be 4.8m long and protrude from the building by 1.2m (the width of one bay of scaffold) and therefore have a 3.6m inboard measurement. These frames are connected at the bottom of the protruding section by a floor plate. They will also have gates to prevent falling from the floor when an outboard deck is not in place.
  • the top of the trusses has a female lug arrangement on the outermost point.
  • the outboard deck consists of 2 truss frames for the sides, 3m long standing vertically, parallel and 2.4m apart. They are connected by a floor section and the deck also has gates fitted to it. It is assembled and maintained as one unit. The sides have a male lug attachment protruding from them which engage the female lugs on the inboard deck.
  • the outboard deck is connected to the crane and lifted to which ever floor is required.
  • the crane operator or dogman is standing on the inboard floor plate inside the safety gates he/she then lowers the outboard deck until the male connectors on the outboard engage the female connectors on the inboard.
  • a pin is inserted on each side to connect the lugs.
  • the crane is lowered and the outboard deck is suspended via the pins connecting it to the inboard deck.
  • the crane operator or dogman can then open the gates and commence working from the outboard deck.
  • the components can be modular thus making it easier to change the size of the deck required. Typically several sizes such as 2.4m or 3m in length are available in the building industry however each one is a whole separate unit.
  • Embodiments according to the invention are adapted so that to change the overall dimensions of the platform only 2 or 3 of the 6 main components will need to be swapped. That is, the outboard may be supplied in a plurality of sections each being mutually engagable with each other and at least one being engagable with the inboard portion. One portion may also be designated as an end section which includes a gate, loading zone or the like. As such, the number of middle sections can be varied and increased and decreased according to the required outboard length.
  • outboard will be extended out with the required number of sections, preferably middle sections, until the required length is reached.
  • protruding attachments can be added to the inboard section as opposed to a deck.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A loading platform for use on a building, the platform including: a first portion that is securely attachable to a level of the building; and a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.

Description

A LOADING PLATFORM
FIELD OF THE INVENTION
The present invention relates to the building construction industry and in particular to cantilevered loading platforms that allow the loading of building materials in between constructed flows of a building under construction or refurbishment and will be described hereinafter with reference to this application. However, it will be appreciated that the invention is not limited to this particular field of use.
BACKGROUND OF THE INVENTION
In this specification unless the contrary is expressly stated, where a document, act or item of knowledge is referred to or discussed, this reference or discussion is not an admission that the document, act or item of knowledge or any combination thereof was at the priority date, publicly available, known to the public, part of common general knowledge; or known to be relevant to an attempt to solve any problem with which this specification is concerned.
During the construction of a multi level building, there is a need to facilitate the supply and removal of building materials to and from each level of the building. Due to the volume, weight and size, the building material is typically delivered to each level using an on site tower crane which picks up the material and places it on a loading platform that is secured to the end of a level of the building. The materials delivered can then be used in the construction of each level. Similarly material to be removed is placed on the loading platform and removed by the tower crane. The material can then be moved to a desired location by the tower crane.
One prior art method includes the construction of a platform which protrudes from a level of a building on two large steel beams. A platform is placed in between the beams and the weight of the platform is supported by the beams. While this method generally provides a cheap solution it has large limitations.
The first major limitation is that the steel beams are heavy which makes the weight of the decks about 3tonnes. This limits the distance from the crane where they can be installed. This is because as a tower crane's capacity is reduced the further the distance a load is taken from the cranes centre. This also reduces the capacity of the load put onto the platform as the weight of the platform plus the load is transmitted onto the building structure. The second major limitation is that the platforms cannot be located directly above one another as a platform below another platform is inaccessible to lowering loads onto with the tower crane. Therefore the platforms are staggered about the building which means the builder must leave staggered penetrations in the protective scaffold around the job. This also means a crane operator, who may not be in view of the platform he is working on, must remember where each platform on each floor is located. The large size of the platforms also makes them difficult to transport, store and move around. To overcome the staggered platform scenario described above a platform which rolls back inside itself and into the building was developed. This allowed a platform to be fixed to a floor of the building. An inside portion of the platform would remain fixed and secured to the inside of the building with an extendable portion of the platform being rolled outside the building to allow the loading of materials thereon. When not required, the extendable portion can be rolled in allowing delivery of materials to other floors of the building without causing an obstruction.
There are still disadvantages with the extendable platform. Each platform is still extremely heavy weighing about 3 tonnes and each platform must be installed as a single unit on each floor which increases costs and the number of complete platforms required.
The prior art platforms also require large capacity tower cranes on building sites to allow the lifting of the heavy platforms. Large capacity cranes are expensive and there is a need at some sites to use smaller more cost effective cranes.
Within this specification the terms inboard and outboard are used with reference to a building as follows. Items that are designated as inboard are disposed, when in use, within the perimeter of the relevant floor or level of the building. Items that are designated as outboard project from the building when in use and are disposed outside of that perimeter. The terms are also used to designate the relevant position of items at a point in time. Such items may be movable between an inboard position and an outboard position.
It is an object of the present invention in its preferred embodiment to overcome or ameliorate at least one of the disadvantages of the prior art, or to provide a useful alternative.
SUMMARY OF THE INVENTION
According to a first aspect of the invention there is provided a loading platform for use on a building, the platform including: a first portion that is securely attachable to a level of the building; and a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
Preferably the first portion is substantially inboard. More preferably the second portion is substantially outboard.
Preferably the first portion is selectively detachable and reattachable to the level of a building. Preferably the second portion is selectively detachable and reattachable to the first portion.
Preferably the second portion is adapted to support a load that includes building materials.
Preferably the building includes a plurality of levels.
Preferably the first portion is secured to the floor of the selected level.
Preferably the first portion is secured to the roof of the selected level.
Preferably the first portion is secured to the floor and roof of the selected level.
Preferably the second portion includes a truss structure that supports the load.
According to a second aspect of the invention there is provided a building having a plurality of levels, the building including: a plurality of first portions of a loading support platform securely attached respectively to each of the plurality of levels; at least one second portion of the support platform that is securely attachable to at least one of the second portions, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
Preferably the second portion is selectively detachable and reattachable to a selected one of the first portions.
Preferably the second portion is adapted to support a load that includes building materials.
Preferably each respective first portion is secured to the respective floor of each respective level.
Preferably each respective first portion is secured to the respective roof of each respective level.
Preferably each first portion is secured to the respective floor and roof of each respective level.
Preferably each second portion includes a truss structure that supports the load.
According to a third aspect of the invention there is provided a method of providing a loading support platform for use on a building, the method including the step of: providing a first portion that is securely attachable to a floor of the building; and providing a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
BRIEF DESCRIPTION OF THE DRAWINGS
A preferred embodiment of the invention will now be described, by way of example only, with reference to the accompanying drawings in which:
Figure lis a side view of a loading platform according to the invention;
Figure 2 is a side view of a loading platform according to the invention;
Figure 3 is a side view of a loading platform according to the invention;
Figure 4 is a cut away top view of the loading platform of Figure 3;
Figure 5 is a side view of the loading platform of Figure 3;
Figure 6 is a section view of the loading platform of Figure 5;
Figure 7 is a close up view of a section of the loading platform of Figure 3;
Figure 8 is another section view of the loading platform of Figure 5;
Figure 9 is a view of the connection of the inboard and outboard portions shown at different degrees of rotation; and
Figure 10 shows portions of the loading platform of Figure 5;
Figure 11 shows various strut or prop arrangements according to the invention;
Figure 12 shows a cutting schedule according to the invention;
Figures 13a - g show an animation of the loading platform;
Figure 14 shows a view of a platform according to the invention; and
Figure 15a - L show an animation of the engagement and disengagement of the outboard and inboard according to the invention.
PREFERRED EMBODIMENT OF THE INVENTION Referring to Figure 1 there is shown a side view of a construction site having a building 101 under construction. The building includes a plurality of building levels 102, 103 and 104. Level 102 is ground level and can be accessed from the ground or street level.
Levels 103 and 104 are raised off the ground and cannot be easily accessed for the supply and removal of building materials. Accordingly, the preferred embodiment of the invention provides access to supply and remove building materials from each level.
The preferred embodiment of the invention provides a loading platform 105 for use on the levels of the building. The platform includes a first inboard portion 106a that is securely attachable to any of the levels of the building. It is preferred that each level of the building includes a respective first inboard portion as shown in Figure 1 where inboards 106b and 106c are attached to levels 103 and 102 respectively.
A second outboard portion 107a is securely attachable to any of the first inboard portions. In Figure 1 the outboard portion 107a is shown securely attached to inboard portion 106a. The outboard portion 107a has a substantially horizontal support surface 108 that extends across an edge of the floor 104 for supporting a load that is placed on the support surface 108.
As would be understood the first inboard portion is substantially disposed within the perimeter of the relevant floor on which it is placed or installed. That is, it does not protrude in any significant way outside the perimeter of the floor on which it is installed and as such does not inhibit the movement of building materials or the operation of cranes in any manner.
The second outboard portions project from the building when in use and are disposed outside of the perimeter of the relevant floor. In this way building materials are able to be delivered to and disposed on from the second outboard portions.
The first portions 106a, 106b and 106c are selectively detachable and reattachable to the level of a building. That is, they can be installed on all required levels of the building and can be removed when required or when the necessary construction or building on the relevant floor is completed. In some instances the inboard portions are moved and installed on a new floor once work on a completed floor has been completed so as to minimise the number of inboard portions required. In some embodiments the inboard portions are installed at different ends on each different level.
As would be understood the second outboard portion 107a is selectively detachable and reattachable to any of the inboard portions 106a, 106b and 106c. The building site may include a plurality of second portions similar or the same as 107a and each one may be installed simultaneously on a respective inboard portion if desired, although this would limit the delivery and removal of building materials and it is preferable that only one outboard portion be attached to an inboard portion in any one working area. This ensures that materials can be removed and delivered easily. The outboard portion 107a is adapted to support any desired and suitable load. Under normal conditions the load includes building materials such as tools, equipment, bricks, cement, woodwork, rubble and the like. It would be understood that the load can be any suitable load that needs to be delivered or removed from the floor.
It would be understood that embodiments of the invention can be used on buildings including any number of levels.
The inboard portions 106a, 106b and 106c are secured to the each level such that they will not move under normal loading conditions of the inboard or attached outboard portions. In securing the inboard portion any suitable securing means can be used. It is preferable that the inboard portions are secured using one or more extendable struts that are connected on either end and on both sides of the inboard. The struts are preferably telescopically extendable and are extended once the inboard is in place. The struts secure the inboard portion to the level of the building on which it is placed. That is, the strut secures the inboard to the floor and ceiling of the level on which it is installed. In other words, the strut secured the inboard between two levels or "floors" of a building under construction.
In other embodiments the inboard can be secured by bolts or other means to the floor and/or ceiling/roof of each level.
Figure 2 shows a level 200 of a multi level building under construction. Inboard portion 201 is installed and secured to one end 202 of level 200. Outboard portion 203 is secured to inboard portion 201. The inboard portion is secured to the level by means of pairs of struts 204 and 205. It would be understood that the pair of struts 204 and 205 each have a strut installed on either side of the inboard portion however only one side can be seen in Figure 2. That is, four struts are used to secure the inboard to the level. It would be understood that the struts can be positioned as necessary on the inboard portion. In some embodiments the struts are fixedly connected to the inboard and their position cannot be changed relative to the inboard. As would be understood, when the inboard portion 201 is to be removed, possible to be moved to another level or at the completion of the constructions the struts are simply moved into the unextended position which allows the struts to be removed or at least allows the inboard portion to be moved or removed.
In some embodiments aspects of the invention include rubbish or debris chutes are attached temporarily or permanently to the inboard or outboard portions so as to aid the removal of some debris or rubbish.
It is preferred that the cantilevered loading platforms according to the invention are constructed from steel although other suitable material may be used. Embodiments of the invention facilitate the loading of building materials in between the constructed floors of a building under construction or refurbishment where the crane cannot access. Platforms according to the invention are preferably installed with an on site tower crane. Preferred embodiments of platforms according to the invention have main structural members of a truss type design instead of a universal beam. The truss design gives the tension strength required with much lighter materials which reduces the total deck self weight. The outboard is removable from the section which is inside the building known as the inboard. This way the outboard deck can be located on which ever floor is desired so long as an inboard section is located there. In the preferred embodiment the platform is broken down in 6 manageable components making it easy to store and transport. As such, it is preferable that the first inboard portion and the second outboard portion include a truss structure that supports the load.
It would be understood that aspects of the invention extend to a building having a plurality of levels. The building can have a plurality of first portions of a loading support platform securely attached respectively to each of the plurality of levels. At least one second portion of the support platform is securely attachable to at least one of the second portions, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load. As would be understood, the second portion is selectively detachable and reattachable to a selected one of the first portions.
A further embodiment of the invention provides a method of providing a loading support platform for use on a building, the method including the step of: providing a first portion that is securely attachable to a floor of the building; and providing a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
Figure 3 shows an embodiment of a loading platform secured to a level 301 of a building under construction. Inboard portion 303 is secured to the level 301 using strut pairs 304 and 305 which can be telescopically extended to secure the inboard portion between the ceiling and floor of level 301. In this embodiment the outboard portion 303 extends past the perimeter 306 of the level 301 by 1.2 metres. In some embodiments the inboard does not extend past the perimeter. As can be seem from the Figure, the total length of the inboard portion is 4.8m with the portion inside the perimeter of the building being 3.6 metres. As would be understood these lengths can be amended as required.
Outboard portion 302 is securely attached to the inboard portion 303 and provides a secure and level platform on which to load or remove building material. In this embodiment the length of the outboard portion is 3 metres and the thickness of the platform itself is 200 millimetres.
Figure 4 shows a top view of the loading platform of Figure 3 where the ceiling 401 has been cut away.
Figure 5 shows a side view of the loading platform of Figure 3. As can be seen, the outboard portion 302 includes a floor 401 upon which a load can be placed. Similarly inboard portion 303 includes a floor 402 upon which a load can be placed. Railing 403 and 404 extends above the respective floors 401 and can be used by a person on standing or walking along the platform. The railing 403 and 404 is also part of a truss structure which provides strength to the platform. The truss structure used is Pratt truss design that uses vertical beams for compression and horizontal beams to respond to tension. As can be seen, the truss includes vertical parts 405a, 405b, 405c, 405d, 405e, 405f and 405g. The horizontal beams include the railing 403, 404 and floors 401 and 402. Strut sections 406a, 406b, 406c, 406d, 406e and 406f extend between the floor and rail to form the required triangular truss.
Figure 7 is a close up view of the attachment of the outboard in inboard portions. The outboard portion includes male lugs 701 and the inboard includes engagable female lugs into which the male lugs engage. A locking pin 703 locks the outboard and inboard lugs together.
Figure 9 is a view of the connection of the inboard and outboard portions shown at different degrees of rotation.
Figure 10 shows portions of the loading platform of Figure 5.
Figure 11 shows various strut or prop arrangements that securely attach the inboard portion to the required level.
Figure 12 shows a cutting schedule for an embodiment of the invention.
Figures 13a - g show an animation of the outboard portion disengaging from the inboard portion.
Figure 14 shows a further view of a platform according to an embodiment of the invention.
Figures 15a - L show an animation of the engagement and disengagement of the outboard and inboard. This shows the engagement and disengagement of the respective male and female portions.
In use, a system according to the invention works by having an inboard deck on each floor where materials are to be delivered or removed. An Inboard deck consists of 2 structural truss frames standing vertically, running perpendicular to the edge of the building, parallel to each other and 2.4m apart. Each of these is held into position via 2 props located at the innermost end. These two sections will be 4.8m long and protrude from the building by 1.2m (the width of one bay of scaffold) and therefore have a 3.6m inboard measurement. These frames are connected at the bottom of the protruding section by a floor plate. They will also have gates to prevent falling from the floor when an outboard deck is not in place. The top of the trusses has a female lug arrangement on the outermost point.
When it is necessary to load or remove materials from a particular floor the outboard deck attachment must be fitted. The outboard deck consists of 2 truss frames for the sides, 3m long standing vertically, parallel and 2.4m apart. They are connected by a floor section and the deck also has gates fitted to it. It is assembled and maintained as one unit. The sides have a male lug attachment protruding from them which engage the female lugs on the inboard deck. The outboard deck is connected to the crane and lifted to which ever floor is required. The crane operator or dogman is standing on the inboard floor plate inside the safety gates he/she then lowers the outboard deck until the male connectors on the outboard engage the female connectors on the inboard. A pin is inserted on each side to connect the lugs. The crane is lowered and the outboard deck is suspended via the pins connecting it to the inboard deck. The crane operator or dogman can then open the gates and commence working from the outboard deck.
Other Advantages of the embodiments of the invention are that the components can be modular thus making it easier to change the size of the deck required. Typically several sizes such as 2.4m or 3m in length are available in the building industry however each one is a whole separate unit. Embodiments according to the invention are adapted so that to change the overall dimensions of the platform only 2 or 3 of the 6 main components will need to be swapped. That is, the outboard may be supplied in a plurality of sections each being mutually engagable with each other and at least one being engagable with the inboard portion. One portion may also be designated as an end section which includes a gate, loading zone or the like. As such, the number of middle sections can be varied and increased and decreased according to the required outboard length. As such the outboard will be extended out with the required number of sections, preferably middle sections, until the required length is reached. A further advantage is that other protruding attachments can be added to the inboard section as opposed to a deck. A large rubbish bin for example or even a crane attachment that could access materials on an outboard deck on a floor below.
Although the invention has been described with reference to specific examples, it will be appreciated by those skilled in the art that the invention may be embodied in many other forms.

Claims

THE CLAIMS DEFINING THE INVENTION ARE AS FOLLOWS:
1. A loading platform for use on a building, the platform including: a first portion that is securely attachable to a level of the building; and a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
2. A loading platform according to claim 1 wherein the first portion is substantially inboard.
3. A loading platform according to claim 2 wherein the second portion is substantially outboard.
4. A loading platform according to claim 3 wherein the first portion is selectively detachable and reattachable to the level of a building.
5. A loading platform according to claim 4 wherein the second portion is selectively detachable and reattachable to the first portion.
6. A loading platform according to claim 5 wherein the second portion is adapted to support a load that includes building materials.
7. A loading platform according to claim 6 wherein the building includes a plurality of levels.
8. A loading platform according to claim 7 wherein the first portion is secured to the floor of the selected level.
9. A loading platform according to claim 7 wherein the first portion is secured to the roof of the selected level.
10. A loading platform according to claim 7 wherein the first portion is secured to the floor and roof of the selected level.
11. A loading platform according to claim 7 wherein the second portion includes a truss structure that supports the load.
12. A loading platform according to claim 7 wherein the first portion includes truss structure that supports the load.
13. A building having a plurality of levels, the building including: a plurality of first portions of a loading support platform securely attached respectively to each of the plurality of levels; at least one second portion of the support platform that is securely attachable to at least one of the second portions, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
14. A building according to claim 13 wherein the second portion is selectively detachable and reattachable to a selected one of the first portions.
15. A building according to claim 14 wherein the second portion is adapted to support a load that includes building materials.
16. A building according to claim 15 wherein each respective first portion is secured to the respective floor of each respective level.
17. A building according to claim 15 wherein each respective first portion is secured to the respective roof of each respective level.
18. A building according to claim 15 wherein each first portion is secured to the respective floor and roof of each respective level.
19. A building according to claim 18 wherein each second portion includes a truss structure that supports the load.
20. A method of providing a loading support platform for use on a building, the method including the step of: providing a first portion that is securely attachable to a floor of the building; and providing a second portion that is securely attachable to the first portion, the second portion having a substantially horizontal support surface that extends across an edge of the floor for supporting a load.
PCT/AU2010/001686 2009-12-17 2010-12-15 A loading platform WO2011072328A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AU2009906110A AU2009906110A0 (en) 2009-12-17 A loading platform
AU2009906110 2009-12-17

Publications (1)

Publication Number Publication Date
WO2011072328A1 true WO2011072328A1 (en) 2011-06-23

Family

ID=44166641

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/AU2010/001686 WO2011072328A1 (en) 2009-12-17 2010-12-15 A loading platform

Country Status (2)

Country Link
AU (1) AU2010253486B2 (en)
WO (1) WO2011072328A1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926915A (en) * 2016-05-05 2016-09-07 河南省第建筑工程集团有限责任公司 Construction method of Bailey beam high-altitude long overhanging working platform
WO2017079786A1 (en) * 2015-11-12 2017-05-18 True Power Pty Ltd A furling crane loading platform
CN107060308A (en) * 2017-03-17 2017-08-18 南通理工学院 A kind of operation platform outside window
CN109610849A (en) * 2018-12-12 2019-04-12 中国建筑第四工程局有限公司 A kind of construction method of large span skybridge truss
CN109736583A (en) * 2019-01-30 2019-05-10 上海建工集团股份有限公司 Fork lifting-type guard system and its construction method
CN111236606A (en) * 2020-03-30 2020-06-05 淮安市博彦土木工程科学研究院有限公司 Isolation system of overhanging scaffold

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06346585A (en) * 1993-06-08 1994-12-20 Megumi Sangyo Kk Protruded structure platform

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU649856B2 (en) * 1991-07-25 1994-06-02 Australasian Mining & Forestry Equipment Manufacturing Pty. Ltd. Cantilever scaffold device
AUPN087395A0 (en) * 1995-01-31 1995-02-23 Preston, John Clement Suspendable container
CA2150578C (en) * 1995-05-26 2006-02-07 Theodore Richard Palmer Building roof eave mounting guard structures

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06346585A (en) * 1993-06-08 1994-12-20 Megumi Sangyo Kk Protruded structure platform

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017079786A1 (en) * 2015-11-12 2017-05-18 True Power Pty Ltd A furling crane loading platform
GB2558490A (en) * 2015-11-12 2018-07-11 True Power Pty Ltd A furling crane loading platform
GB2558490B (en) * 2015-11-12 2019-05-29 True Power Pty Ltd A furling crane loading platform
US10633876B2 (en) 2015-11-12 2020-04-28 True Power Pty Ltd Furling crane loading platform
CN105926915A (en) * 2016-05-05 2016-09-07 河南省第建筑工程集团有限责任公司 Construction method of Bailey beam high-altitude long overhanging working platform
CN105926915B (en) * 2016-05-05 2018-02-02 河南省第一建筑工程集团有限责任公司 Grow the construction method for workbench of encorbelmenting in Bailey beam high-altitude
CN107060308A (en) * 2017-03-17 2017-08-18 南通理工学院 A kind of operation platform outside window
CN107060308B (en) * 2017-03-17 2022-11-04 南通理工学院 Outside-window operation rack
CN109610849A (en) * 2018-12-12 2019-04-12 中国建筑第四工程局有限公司 A kind of construction method of large span skybridge truss
CN109736583A (en) * 2019-01-30 2019-05-10 上海建工集团股份有限公司 Fork lifting-type guard system and its construction method
CN111236606A (en) * 2020-03-30 2020-06-05 淮安市博彦土木工程科学研究院有限公司 Isolation system of overhanging scaffold

Also Published As

Publication number Publication date
AU2010253486B2 (en) 2018-08-09
AU2010253486A1 (en) 2011-07-07

Similar Documents

Publication Publication Date Title
US10329781B2 (en) Safety barrier netting system
US10738488B2 (en) Lift truck operated stacking formwork table system and a method of operation thereof
AU2010253486B2 (en) A loading platform
AU2013212529B2 (en) Automated formwork climbing system
CN113931313B (en) Construction method of super high-rise core tube horizontal structure
US20050263351A1 (en) Modular multilevel access platform and method for erecting the same
CN111255217A (en) Elevator shaft shaping operation platform and operation method thereof
NZ235421A (en) Foldable landing platform for building construction
CN106437123A (en) Supporting leg automatic turnover type overall lifting elevator well operation platform
US9440820B2 (en) Escalator lifting frame and method of using the same
WO2003080954A1 (en) Work platform for roof construction work
CN206110635U (en) Automatic convertible integrally lift up elevator shaft operating platform of landing leg
CN210598083U (en) Elevator shaft construction platform
CN210976552U (en) Foldable operation platform device in elevator shaft
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
CN106193621A (en) Fabricated construction superimposed sheet string hangs construction method
AU2008323613A1 (en) Perimeter screening system
CN211923466U (en) Elevator shaft regularization operation platform
JP2008196210A (en) Portable simplified elevator
CN108755419B (en) Construction platform for hoisting bridge shock-proof steel stop block and installation method
CN110206298A (en) A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces
KR101733948B1 (en) Both sides supporting type loading deck for landing of building materials
CN218714939U (en) Adjustable elevator shaft lifting platform
CN214246662U (en) Whole jacking formula under bracing discharge apparatus for super high-rise building construction
Mogarkar et al. A concept for development, safe erection and use of scaffolding for high rise buildings

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 10836839

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 10836839

Country of ref document: EP

Kind code of ref document: A1