CN110206298A - A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces - Google Patents

A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces Download PDF

Info

Publication number
CN110206298A
CN110206298A CN201910542041.6A CN201910542041A CN110206298A CN 110206298 A CN110206298 A CN 110206298A CN 201910542041 A CN201910542041 A CN 201910542041A CN 110206298 A CN110206298 A CN 110206298A
Authority
CN
China
Prior art keywords
sliding
construction
warehouse
remove
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910542041.6A
Other languages
Chinese (zh)
Inventor
蒋泉
成张佳宁
蒋光明
吴锡东
戴卫阳
何思涛
康新春
邹永远
崔健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong University
Original Assignee
Nantong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong University filed Critical Nantong University
Priority to CN201910542041.6A priority Critical patent/CN110206298A/en
Publication of CN110206298A publication Critical patent/CN110206298A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • E04G11/24Construction of lifting jacks or climbing rods for sliding forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces, includes the following steps: to carry out preparation of construction, each section of sliding mode system is designed respectively, then BIM construction simulation is carried out to sliding form apparatus;It constructs to sliding form apparatus, sliding module assembled is arranged jack and oil circuit, quality testing is carried out to assembled device;After the assembling for completing sliding mode system, to bulkhead slding form operation, reinforcement construction is carried out, concreting, promotion are carried out according still further to the schedule of slding form operation;After the completion of silo roof concrete placings, start to remove sliding system, be split into principle afterwards according to removing first to fill, then cooperates with tower crane and complete to remove;Vertically, the measurement reversed carries out construction detection and takes surveillance and control measure.The present invention simulates operation optimization construction technology by BIM, the construction difficult problem by stopping sliding, sliding empty, secondary assembling, the connection of reinforcing bar embedded sleeve barrel etc., after solving matrix storehouse, different level, staggered floor construction.

Description

一种用于错位矩阵方仓的优化滑模结构施工工艺An optimized sliding form structure construction technology for dislocation matrix square warehouse

技术领域technical field

本发明涉及滑模工程辅助装置技术领域,具体为一种用于错位矩阵方仓的优化滑模结构施工工艺。The invention relates to the technical field of sliding-form engineering auxiliary devices, in particular to an optimized sliding-form structure construction process for a dislocation matrix square silo.

背景技术Background technique

滑模工程技术是我国现浇混凝土结构工程施工中机械化程度高、施工速度快、现场场地占用少、结构整体性强、抗震性能好、安全作业有保障、环境与经济综合效益显著的一种施工技术,通常简称为“滑模”。滑模施工与常规施工方法相比,这种施工工艺具有施工速度快、机械化程度高、可节省支模和搭设脚手架所需的工料、能较方便地将模板拆散和灵活组装并可重复使用的优点。Slipform engineering technology is a kind of construction with high degree of mechanization, fast construction speed, less site occupation, strong structural integrity, good seismic performance, guaranteed safe operation, and significant comprehensive environmental and economic benefits in the construction of cast-in-place concrete structures in my country. technique, often referred to simply as "slip mode". Compared with conventional construction methods, slip form construction has the advantages of fast construction speed, high degree of mechanization, saving of materials required for formwork and scaffolding, convenient disassembly of formwork, flexible assembly and reusability. advantage.

而目前在施工矩阵仓、不同标高、错层结构时,采用混凝土剪力墙错层结构;使用滑模工程技术,直接照搬施工规范,不会很好结合工程的实际情况,但是滑模效率低,增加施工的的难度和后期使用的危险性。At present, when constructing matrix warehouses, different elevations, and split-level structures, concrete shear wall split-level structures are used; using sliding-form engineering technology to directly copy construction specifications, it will not be well combined with the actual situation of the project, but the sliding-form efficiency is low. , increasing the difficulty of construction and the danger of later use.

发明内容SUMMARY OF THE INVENTION

本发明的目的是为了提供一种用于错位矩阵方仓的优化滑模结构施工工艺,借助BIM模拟工况优化施工工艺,通过停滑、滑空、二次组装、钢筋预埋套筒连接等,解决了矩阵仓、不同标高、错层结构后的施工难题。The purpose of the present invention is to provide an optimized sliding-form structure construction process for a dislocation matrix square warehouse, which optimizes the construction process with the help of BIM simulation working conditions, through stopping sliding, sliding, secondary assembly, steel embedded sleeve connection, etc., The construction problems of matrix warehouses, different elevations and split-level structures have been solved.

为了实现上述发明目的,本发明采用了以下技术方案:一种用于错位矩阵方仓的优化滑模结构施工工艺,包括如下步骤:步骤1.进行施工准备,对滑模系统的各部分分别进行设计,再对滑模装置进行BIM模拟施工;In order to achieve the above-mentioned purpose of the invention, the present invention adopts the following technical solutions: an optimized sliding form structure construction process for a dislocation matrix square warehouse, comprising the following steps: Step 1. Carry out construction preparation, and carry out the steps for each part of the sliding form system respectively. Design, and then carry out BIM simulation construction for the sliding form device;

步骤2.对滑模装置进行施工,将滑升模块组装,对千斤顶及油路进行布置,对组装好的装置进行质量检测;Step 2. Carry out the construction of the sliding form device, assemble the sliding module, arrange the jack and oil circuit, and conduct quality inspection on the assembled device;

步骤3.完成滑模系统的组装后,对仓壁滑模施工,进行钢筋施工,混凝土浇筑、提升,再按照滑模施工的进度计划来进行;Step 3. After the assembly of the sliding form system is completed, the sliding form construction of the warehouse wall, steel reinforcement construction, concrete pouring and lifting, and then proceed according to the progress plan of the sliding form construction;

步骤4.仓顶砼浇筑完成后,开始拆除滑升系统,根据拆除以先装后拆为原则,再跟塔吊配合完成拆除;Step 4. After the concrete pouring of the warehouse roof is completed, start to dismantle the sliding system. According to the principle of dismantling first, then dismantling, and then cooperate with the tower crane to complete the demolition;

步骤5.垂直、扭转的测量,进行施工检测并且采取监控措施。Step 5. Vertical and torsional measurement, construction inspection and monitoring measures.

优选的,在步骤1中,所述滑模系统设计包括液压提升系统、模板系统、围圈、滑升平台系统、吊脚手架和施工精度控制系统。Preferably, in step 1, the design of the sliding form system includes a hydraulic lifting system, a formwork system, an enclosure, a sliding platform system, a hanging scaffold and a construction precision control system.

优选的,所述围圈由斜撑与直撑装配成桁架式,所述围圈桁架与操作平台的支撑桁架相连接。Preferably, the enclosure is assembled into a truss type by diagonal braces and straight braces, and the enclosure truss is connected to the support truss of the operating platform.

优选的,在步骤2中,进行滑模装置的组装,包括以下步骤:Preferably, in step 2, the assembly of the sliding mold device includes the following steps:

步骤1.将钢筋进行放样、采购、制作和绑扎,并进行复检;Step 1. Stake out, purchase, fabricate and bind the steel bars, and conduct re-inspection;

步骤2.模板系统放样,进行材料准备,拼装开字架并且制作围圈;Step 2. Stake out the template system, prepare materials, assemble the open frame and make a circle;

步骤3.隐蔽验收钢筋结构,安装开字架进行模板拼接;Step 3. Conceal acceptance of the steel structure, install the open frame for template splicing;

步骤4.提升系统放样,进行材料准备,对千斤顶、油管、油泵检测,安装上千斤顶,制作支撑杆,安装支撑杆就位;Step 4. Stake out the lifting system, prepare materials, test the jack, oil pipe, and oil pump, install the jack, make the support rod, and install the support rod in place;

步骤5.操作平台系统放样,进行材料准备,搭设平台支架,对平台进行铺设,搁置仓顶钢梁,安装油泵、油管;Step 5. Operate the platform system to stake out, prepare materials, set up platform brackets, lay the platform, set aside the steel beams on the top of the warehouse, and install oil pumps and oil pipes;

步骤6.安装照明系统,综合验收滑模系统,试滑后对模板下口进行补缝;Step 6. Install the lighting system, comprehensively accept the sliding formwork system, and repair the bottom of the formwork after the trial slip;

步骤7.垂直运输机就位安装,验收后,负荷试运转,脚手架搭设,进入滑模施工阶段。Step 7. The vertical conveyor is installed in place. After acceptance, the load test run, the scaffolding is erected, and the slip form construction stage is entered.

优选的,在步骤3中,进行仓壁滑模施工,内外竖筋、采用环筋绑扎连接——预埋、预留——对仓壁进行混凝土浇筑、提升——仓壁的表面进行处理、养护——垂直、扭转的测量、预防与纠正——支承杆进行加固——将滑模系统拆除。Preferably, in step 3, the sliding form construction of the warehouse wall is carried out, the inner and outer vertical bars are connected by ring bars binding - pre-embedded, reserved - concrete pouring and lifting on the warehouse wall - the surface of the warehouse wall is treated, Maintenance - Vertical, torsional measurement, prevention and correction - Reinforcement of support rods - Remove the slipform system.

优选的,所述滑模的滑升过程中遇到特殊情况采取停工处理时,需要按照规定要求设置施工缝。Preferably, when special circumstances are encountered during the sliding process of the sliding form and the work is stopped, the construction joints need to be set up according to the specified requirements.

优选的,所述滑模系统拆除时,加固支撑杆的同时清除多余荷载滑模,拆除油路、油泵——利用塔吊拆除高架平台——拆除操作平台、栏杆、安全网——利用塔吊拆除内、外模板——拆除支撑、提升架、千斤顶——支撑杆堵头。Preferably, when the sliding form system is dismantled, the support rod is reinforced and the excess load slip form is removed, the oil circuit and oil pump are removed - the elevated platform is removed by the tower crane - the operation platform, the railing and the safety net are removed - the inner wall is removed by the tower crane , Outer formwork - remove support, lifting frame, jack - support rod plug.

优选的,所述仓壁采用喷淋进行养护,所述吊脚手架上设有环型PRR管,所述PRR管上设有多个开孔,所述开孔的开口方向对准仓壁混凝土面,所述PRR管通过增压泵加压连接供水管。Preferably, the warehouse wall is maintained by spraying, the hanging scaffold is provided with a ring-shaped PRR pipe, the PRR pipe is provided with a plurality of openings, and the opening direction of the openings is aligned with the concrete surface of the warehouse wall , the PRR pipe is pressurized and connected to the water supply pipe through a booster pump.

与现有技术相比,采用了上述技术方案的用于错位矩阵方仓的优化滑模结构施工工艺,具有如下有益效果:采用本发明的用于错位矩阵方仓的优化滑模结构施工工艺,通过BIM模拟工况优化施工工艺,停滑、滑空及二次组装等方式,使得较难的工程能够轻易解决,并且使用的模板组装拆卸后能够重复使用。Compared with the prior art, the optimized sliding-form structure construction technology for the dislocation matrix square silo that adopts the above-mentioned technical solution has the following beneficial effects: the optimized slip-form structure construction technology for the dislocation matrix square silo of the present invention is adopted, Through BIM simulation of working conditions to optimize the construction process, stop-slip, slip-out and secondary assembly, etc., make difficult projects be easily solved, and the used formwork can be reused after assembly and disassembly.

附图说明Description of drawings

图1为本发明用于错位矩阵方仓的优化滑模结构施工工艺实施例的工艺流程图;Fig. 1 is the process flow diagram of the optimized sliding form structure construction process embodiment of the dislocation matrix square warehouse of the present invention;

图2为本实施例中组装滑模装置的工艺流程图;Fig. 2 is the process flow diagram of assembling the sliding mold device in the present embodiment;

图3为本实施例中滑模系统拆除的工艺流程图。FIG. 3 is a process flow diagram of dismantling the sliding mold system in this embodiment.

具体实施方式Detailed ways

下面结合附图对本发明做进一步描述。The present invention will be further described below with reference to the accompanying drawings.

如图1所示为用于错位矩阵方仓的优化滑模结构施工工艺的工艺流程图,包括如下步骤:步骤1.进行施工准备,对滑模系统的各部分分别进行设计,滑模系统设计包括液压提升系统、模板系统、围圈、滑升平台系统、吊脚手架和施工精度控制系统。围圈既是模板的支撑体系,又要承担操作平台等其它设备的施工荷载,由斜撑与直撑装配成桁架式,围圈桁架与操作平台的支撑桁架相连接。再对滑模装置进行BIM模拟施工。As shown in Figure 1, the process flow chart of the optimized sliding-form structure construction process for the dislocation matrix square warehouse, including the following steps: Step 1. Make construction preparations, design each part of the sliding-form system separately, and design the sliding-form system. Including hydraulic lifting system, formwork system, enclosure, sliding platform system, hanging scaffold and construction precision control system. The enclosure is not only the support system of the formwork, but also bears the construction load of the operation platform and other equipment. It is assembled into a truss type by diagonal braces and straight braces. Then the BIM simulation construction of the sliding form device is carried out.

步骤2.对滑模装置进行施工,将滑升模块组装,对组装好的装置进行质量检测。如图2所示为组装滑模装置的工艺流程图,包括以下步骤:Step 2. Construct the sliding-form device, assemble the sliding module, and conduct quality inspection on the assembled device. As shown in Figure 2, the process flow chart of assembling the sliding mold device includes the following steps:

(1)将钢筋进行放样、采购、制作和绑扎,并进行复检;(1) Stake out, purchase, fabricate and bind steel bars, and conduct re-inspection;

(2)模板系统放样,进行材料准备,拼装开字架并且制作围圈;(2) Stake out the template system, prepare materials, assemble the open frame and make a circle;

(3)隐蔽验收钢筋结构,安装开字架进行模板拼接;(3) Concealed acceptance of steel structure, installation of open frame for template splicing;

(4)提升系统放样,进行材料准备,对千斤顶、油管、油泵检测,安装上千斤顶,制作支撑杆,安装支撑杆就位;(4) Stake out the hoisting system, prepare materials, test the jack, oil pipe, and oil pump, install the jack, make the support rod, and install the support rod in place;

(5)操作平台系统放样,进行材料准备,搭设平台支架,对平台进行铺设,搁置仓顶钢梁,安装油泵、油管;(5) Stake out the platform system, prepare materials, set up platform brackets, lay the platform, set aside the steel beams on the top of the warehouse, and install oil pumps and oil pipes;

(6)安装照明系统,综合验收滑模系统,试滑后对模板下口进行补缝;(6) Install the lighting system, comprehensively accept the sliding formwork system, and repair the bottom of the formwork after the trial slip;

(7)垂直运输机就位安装,验收后,负荷试运转,脚手架搭设,进入滑模施工阶段。(7) The vertical conveyor is installed in place. After acceptance, the load test run, the scaffolding is erected, and the slip form construction stage is entered.

步骤3.完成滑模系统的组装后,对仓壁滑模施工,进行钢筋施工,混凝土浇筑、提升,再按照滑模施工的进度计划来进行。进行仓壁滑模施工,内外竖筋、采用环筋绑扎连接;在滑升前准备好预埋件和预留孔,预埋预留由专人负责,需凿出的预埋件、预留孔、预留插筋一旦出模立即凿出,注意找准位置再进行,以免影响仓壁表现,各种预埋预留件均不得与仓壁环筋焊接,预留洞口两侧砼须对称浇筑;对仓壁进行混凝土浇筑、提升滑模的滑升过程中遇到特殊情况采取停工处理时,需要按照规定要求设置施工缝;仓壁的表面进行处理、养护,仓壁采用喷淋进行养护,吊脚手架上设有环型PRR管,PRR管上设有多个开孔,开孔的开口方向对准仓壁混凝土面,PRR管通过增压泵加压连接供水管。组装完成后,进行垂直、扭转的测量、预防与纠正;对支承杆进行加固,如工艺要求支承杆全部脱空时,支承杆应加固,要求支承杆竖直,接头焊接牢靠。加固时注意保持加固围圈及水平拉结杆以上支承杆最大脱空长度不超过2.2米。预留洞口处支承杆可在支承杆一侧加设立钢管架子加固。筒壁内支承杆可采用短钢筋加焊在竖向钢筋上,形成整体骨架以减少杆件的计算长度。再将滑模系统拆除。Step 3. After the assembly of the sliding form system is completed, the sliding form construction of the warehouse wall, steel reinforcement construction, concrete pouring and lifting, and then proceed according to the progress plan of the sliding form construction. Carry out the sliding form construction of the warehouse wall, and use the inner and outer vertical bars to bind and connect the ring bars; prepare the embedded parts and reserved holes before sliding, and the embedded parts and reserved holes are in charge of the pre-embedded parts and reserved holes. . Once the reserved inserts are out of the mold, they will be chiseled out immediately. Pay attention to the correct position before proceeding, so as not to affect the performance of the warehouse wall. All kinds of pre-embedded reserved parts must not be welded with the ring ribs of the warehouse wall, and the concrete on both sides of the reserved opening must be placed symmetrically. ;Concrete pouring on the warehouse wall and when the sliding form is lifted and the sliding process is stopped in special circumstances, construction joints need to be set up in accordance with the regulations; the surface of the warehouse wall is treated and maintained, and the warehouse wall is maintained by spraying. The hanging scaffold is provided with a ring-shaped PRR pipe. The PRR pipe is provided with a plurality of openings. The opening direction of the openings is aligned with the concrete surface of the warehouse wall. The PRR pipe is pressurized by a booster pump and connected to the water supply pipe. After the assembly is completed, carry out vertical and torsional measurement, prevention and correction; reinforce the support rod. If the process requires that the support rod is completely empty, the support rod should be reinforced, the support rod is required to be vertical, and the joints are welded firmly. During reinforcement, pay attention to keeping the maximum empty length of the support rod above the reinforcement ring and the horizontal tie rod not exceeding 2.2 meters. The support rod at the reserved hole can be reinforced with a steel pipe frame on one side of the support rod. The support rods in the cylinder wall can be welded with short steel bars on the vertical steel bars to form an integral skeleton to reduce the calculated length of the rods. Then remove the slip-form system.

步骤4.仓顶板模板拆除,仓顶板混凝土浇筑完成后,不立即拆除模板,而是先施工上层结构(此时仓顶板混凝土处于养护期),待上层结构完成及混凝土达到拆模强度后拆除仓顶板支撑体系及模板。支撑体系拆除后钢管、扣件等材料通过仓顶人孔位置传递至仓顶板位置。开始拆除滑升系统,根据拆除以先装后拆为原则,再跟塔吊配合完成拆除。如图3所示为滑模系统拆除的工艺流程图,滑模系统拆除时,加固支撑杆的同时清除多余荷载滑模,拆除油路、油泵;利用塔吊拆除高架平台;拆除操作平台、栏杆、安全网;利用塔吊拆除内、外模板;拆除支撑、提升架、千斤顶;支撑杆堵头。Step 4. Remove the formwork of the warehouse roof. After the concrete of the warehouse roof is poured, the formwork will not be removed immediately, but the superstructure will be constructed first (the concrete of the warehouse roof is in the curing period at this time), and the warehouse will be removed after the superstructure is completed and the concrete reaches the strength of the formwork removal. Roof support system and formwork. After the support system is removed, the steel pipes, fasteners and other materials are transferred to the position of the warehouse roof through the position of the manhole on the roof of the warehouse. Begin to dismantle the sliding system, according to the principle of dismantling first and then dismantling, and then cooperate with the tower crane to complete the dismantling. Figure 3 shows the process flow diagram of the dismantling of the slip form system. When the slip form system is dismantled, the excess load slip form is removed while the support rod is reinforced, and the oil circuit and oil pump are dismantled; the elevated platform is dismantled by a tower crane; Safety net; use tower crane to remove inner and outer formwork; remove support, lifting frame, jack; support rod plug.

步骤5.垂直、扭转的测量,进行随时的施工检测并且采取监控措施。根据现场实际情况,在外挑平台上挂设12只自制线锤,并用激光经纬仪配合,在整板基础面相应位置做出红油标志,滑升时,每90厘米检验一次测量相对标志偏移值,纠偏纠扭时每30厘米检验一次,项目部准备在现场采用钢尺、线锤、水准仪和经纬仪对支模系统进行施工过程的监测。根据现场实际情况,项目部准备在现场采用钢尺、线锤、水准仪和经纬仪对支模系统进行施工过程的监测。Step 5. Vertical and torsional measurement, carry out construction inspection at any time and take monitoring measures. According to the actual situation on site, hang 12 self-made wire hammers on the outrigger platform, and cooperate with the laser theodolite to make red oil marks on the corresponding position of the base surface of the whole board. When sliding, check the relative mark offset value every 90 cm. The project department plans to use steel ruler, line hammer, level and theodolite to monitor the construction process of the formwork system on site. According to the actual situation on site, the project department plans to use steel ruler, line hammer, level and theodolite to monitor the construction process of the formwork system on site.

在本实施例中,针对储存小米的麦仓,施工为现浇钢筋混凝土错位矩阵方仓,仓底错层与钢筋混凝土框架结构车间连接,并且仓顶为高空现浇钢筋混凝土板。麦仓为16连体,各仓轴线尺寸为3.7米乘以3.125米,壁厚为160毫米,高度23.05米,标高从7.45米到30.50米,仓顶为钢筋砼平顶板,其中有10个仓仓底全封闭。In this embodiment, for the wheat silo for storing millet, the construction is a cast-in-place reinforced concrete dislocation matrix square silo, the staggered floor of the silo is connected to the reinforced concrete frame structure workshop, and the top of the silo is a high-altitude cast-in-place reinforced concrete slab. The wheat warehouse is 16 conjoined pieces. The axis dimension of each warehouse is 3.7 meters by 3.125 meters, the wall thickness is 160 mm, the height is 23.05 meters, and the elevation ranges from 7.45 meters to 30.50 meters. The bottom of the warehouse is completely closed.

在设计液压提升系统时,采用2台YKT—56型液压控制台,液压系统千斤顶使用GYD60滚珠式千斤顶120台,每榀提升架设置一台GYD60滚珠式千斤顶。本麦仓共设120榀提升架,每方格3700毫米乘以3125毫米,每边均设3榀提升架,布置均匀并合理,一次行程为30毫米,额定顶推力60KN,施工设计时取额定顶推力50%计算为30KN,保证整个滑模体系的安全爬升。支承杆为直径48.3毫米乘以3.6毫米的普通建筑钢管,支撑杆初次安装应选6米和3米两种高度,依次错开安装,接头不在同一水平面。支撑杆对接连接选用焊接连接,钢管管口对接应满焊,焊接质量要求必须达Ⅱ级焊缝标准。焊接后用电动砂轮磨光机磨平。模板围圈以管卡勾头螺丝拉结模板,每条拼缝不少于2个。安装好的模板单面倾斜度为模板高度的0.2到0.5%。按规范要求模板高二分之一处净距为结构截面尺寸。When designing the hydraulic lifting system, 2 sets of YKT-56 hydraulic consoles are used, 120 sets of GYD60 ball-type jacks are used for hydraulic system jacks, and one GYD60 ball-type jack is set for each lifting frame. The barn has a total of 120 lifting racks, each square is 3700 mm by 3125 mm, and each side is equipped with 3 lifting racks. The arrangement is uniform and reasonable. The one stroke is 30 mm and the rated top thrust is 60KN. 50% of the top thrust is calculated as 30KN, which ensures the safe climbing of the entire sliding mode system. The support rod is an ordinary construction steel pipe with a diameter of 48.3 mm by 3.6 mm. The support rod should be installed at two heights of 6 meters and 3 meters for the first time, and the installation should be staggered in sequence, and the joints should not be on the same level. The butt connection of the support rod shall be welded connection, the butt joint of the steel pipe shall be fully welded, and the welding quality requirements must meet the standard of Class II welding seam. After welding, smooth it with an electric wheel grinder. The template circle is tied with the pipe clip hook head screw, and each seam is not less than 2. The inclination of one side of the installed formwork is 0.2 to 0.5% of the formwork height. According to the requirements of the specification, the clear distance at one-half the height of the formwork is the size of the structural section.

吊脚手架的吊杆采用钢管扣件连接,吊脚手架的吊杆上下端均另用扣件拧紧作防滑保险扣,连接处再用18钢筋弯成L形把扣件连接的两根钢管作焊接加固,做到安全万无一失。其铺板宽度不应窄于30厘米,厚度不小于4厘米,铺板长度不少于4米。吊脚手架内、外侧必须设置防护栏杆高度不低于1.2米,并牢挂尼龙安全网从底部到两侧城整体防护网。用水准仪或水平管测量水平面,在仓壁外两个轴线上设四个点,用线坠可做垂直度的测量。为保证支撑杆连接时垂直,每次支撑杆连接前用水平尺进行垂直度检测,当支撑杆焊接完毕后再次用水平尺进行垂直度检测。The boom of the hanging scaffold is connected by steel pipe fasteners. The upper and lower ends of the boom of the hanging scaffold are tightened with fasteners as anti-skid safety buckles. The connection is then bent into an L shape with 18 steel bars. The two steel pipes connected by the fasteners are welded and strengthened. , to be safe and foolproof. The width of the slab should not be narrower than 30 cm, the thickness should not be less than 4 cm, and the length of the slab should not be less than 4 meters. The inner and outer side of the hanging scaffold must be set with protective railings with a height of not less than 1.2 meters, and the nylon safety net must be firmly hung from the bottom to the overall protective net of the city on both sides. Use a level or a horizontal tube to measure the horizontal plane, set four points on the two axes outside the warehouse wall, and use a line pendant to measure the verticality. In order to ensure that the support rods are vertical when connected, use a level to check the verticality before each support rod is connected, and use a level to check the verticality again after the support rods are welded.

在对麦仓进行滑模施工工况BIM演示时,麦仓实际滑升高度22.93m,一次性组装16个仓体同时滑模施工,保证仓体不存在水平与竖向施工缝。滑模组装完成、初次浇筑900mm高混凝土;滑升2.m左右、安装吊脚手架;每次浇筑300mm高混凝土滑升一次、连续施工至顶。In the BIM demonstration of the sliding-form construction condition of the wheat silo, the actual sliding height of the wheat silo was 22.93m, and 16 silo bodies were assembled at one time for slip-form construction to ensure that there were no horizontal and vertical construction joints in the silo body. The sliding form is assembled, and the 900mm high concrete is poured for the first time; the slide is about 2.m, and the hanging scaffolding is installed; the 300mm high concrete is slid once every time it is poured, and the construction is continued to the top.

对麦仓进行滑模平台组装,麦仓的四周和内剪力墙共设120榀提升架,提升架之间用钢管连接组装。四周外侧平台1.8米宽、设置栏杆高度1.2米,内侧用钢管搭设刚性满桁架,滑升平台组装好上面铺设40毫米乘以40毫米的方管和3毫米厚花纹钢板铺成施工人员操作平台,滑模平台下口满挂安全网,外侧四周栏杆设置密目安全网。砼按30厘米分层浇筑,每一分层砼从开始浇筑至结束须经过四至三层浇筑时间才出模,按控制砼出模时间不大于5小时考虑,则容许每分层砼浇筑时间为75分钟。油管必须均匀布置,确保送油速度同步,方可确保滑模质量。The wheat warehouse is assembled on a sliding-form platform. There are 120 lifting frames around the wheat warehouse and the inner shear wall, and the lifting frames are connected and assembled by steel pipes. The outer platform is 1.8 meters wide, and the height of the railing is 1.2 meters. The inner side is built with a rigid full truss. After the sliding platform is assembled, a 40 mm by 40 mm square tube and a 3 mm thick patterned steel plate are laid on it to form an operating platform for construction personnel. The bottom of the sliding-form platform is full of safety nets, and the outer surrounding railings are set with dense mesh safety nets. Concrete is poured in layers of 30 cm, and each layer of concrete must pass four to three layers of pouring time from the beginning of pouring to the end before it is released from the mold. Considering that the time for controlling the mold release time is not more than 5 hours, the allowable time for each layer of concrete pouring is 75 minutes. The oil pipes must be evenly arranged to ensure that the oil feeding speed is synchronous to ensure the quality of the sliding mold.

拆除支撑平台,拆除前先将仓顶板支撑平台采用钢丝绳反吊在仓顶板上,人系好五点式安全带通过人孔下到平台上,割除直径22毫米的吊拉钢筋,将4角卷扬机钢丝绳锁扣好平台,然后每仓4个角配置1台2吨的小型卷扬机,将支撑平台降至仓底解体,清运出所有材料。麦仓10个仓底板没有洞口的,采用卷扬机从顶板洞口运出。在10个仓底板中间位置预留800乘以800的上人孔,人员材料从此洞口进出,安全方便。上人爬梯采用附着外脚手架设置的方案,搭设高度33米,平面尺寸为4.0米乘以6.0米,采用之字型斜道,坡道入口处设置1.2米宽通道,上面设置两层防护层。最后底板钢筋焊接连接、补浇混凝土封闭。Before dismantling the support platform, firstly hang the support platform of the warehouse roof on the warehouse roof with steel wire ropes, and then fasten the five-point safety belt to the platform through the manhole, cut off the 22 mm diameter hoisting and pulling steel bars, and hoist the 4-angle hoist. The steel wire rope locks the platform, and then configures a small 2-ton winch at the 4 corners of each warehouse to lower the support platform to the bottom of the warehouse and disassemble it, and remove all materials. The 10 wheat warehouses without openings on the bottom plate shall be transported out from the openings on the top plate by a winch. A manhole of 800 times 800 is reserved in the middle of the 10 warehouse bottom plates, and personnel and materials can enter and exit from this hole, which is safe and convenient. The climbing ladder adopts the scheme of attaching external scaffolding, with a height of 33 meters and a plane size of 4.0 meters by 6.0 meters. Finally, the steel bars of the bottom plate are welded and connected, and the concrete is poured to seal.

以上是本发明的优选实施方式,对于本领域的普通技术人员来说不脱离本发明原理的前提下,还可以做出若干变型和改进,这些也应视为本发明的保护范围。The above are the preferred embodiments of the present invention. For those of ordinary skill in the art, without departing from the principles of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention.

Claims (8)

1.一种用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:包括如下步骤:1. an optimized sliding form structure construction technique for dislocation matrix square warehouse, is characterized in that: comprise the steps: 步骤1.进行施工准备,对滑模系统的各部分分别进行设计,再对滑模装置进行BIM模拟施工;Step 1. Carry out construction preparation, design each part of the sliding form system separately, and then carry out BIM simulation construction for the sliding form device; 步骤2.对滑模装置进行施工,将滑升模块组装,对千斤顶及油路进行布置,对组装好的装置进行质量检测;Step 2. Carry out the construction of the sliding form device, assemble the sliding module, arrange the jack and oil circuit, and conduct quality inspection on the assembled device; 步骤3.完成滑模系统的组装后,对仓壁滑模施工,进行钢筋施工,混凝土浇筑、提升,再按照滑模施工的进度计划来进行;Step 3. After the assembly of the sliding form system is completed, the sliding form construction of the warehouse wall, steel reinforcement construction, concrete pouring and lifting, and then proceed according to the progress plan of the sliding form construction; 步骤4.仓顶砼浇筑完成后,开始拆除滑升系统,根据拆除以先装后拆为原则,再跟塔吊配合完成拆除;Step 4. After the concrete pouring of the warehouse roof is completed, start to dismantle the sliding system. According to the principle of dismantling first, then dismantling, and then cooperate with the tower crane to complete the demolition; 步骤5.垂直、扭转的测量,进行施工检测并且采取监控措施。Step 5. Vertical and torsional measurement, construction inspection and monitoring measures. 2.根据权利要求1所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:在步骤1中,所述滑模系统设计包括液压提升系统、模板系统、围圈、滑升平台系统、吊脚手架和施工精度控制系统。2. The optimized sliding form structure construction technique for dislocation matrix square warehouse according to claim 1, is characterized in that: in step 1, described sliding form system design comprises hydraulic lifting system, formwork system, encirclement, sliding Lifting platform system, hanging scaffold and construction precision control system. 3.根据权利要求2所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:所述围圈由斜撑与直撑装配成桁架式,所述围圈桁架与操作平台的支撑桁架向连接。3. The optimized sliding-form structure construction process for a dislocation matrix square warehouse according to claim 2, characterized in that: the enclosure is assembled into a truss type by diagonal braces and straight braces, and the enclosure trusses and the operating platform The supporting trusses are connected. 4.根据权利要求1所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:在步骤2中,进行滑模装置的组装,包括以下步骤:4. the optimized sliding-form structure construction technique for dislocation matrix square warehouse according to claim 1, is characterized in that: in step 2, carry out the assembling of sliding-form device, comprise the following steps: 步骤1.将钢筋进行放样、采购、制作和绑扎,并进行复检;Step 1. Stake out, purchase, fabricate and bind the steel bars, and conduct re-inspection; 步骤2.模板系统放样,进行材料准备,拼装开字架并且制作围圈;Step 2. Stake out the template system, prepare materials, assemble the open frame and make a circle; 步骤3.隐蔽验收钢筋结构,安装开字架进行模板拼接;Step 3. Conceal acceptance of the steel structure, install the open frame for template splicing; 步骤4.提升系统放样,进行材料准备,对千斤顶、油管、油泵检测,安装上千斤顶,制作支撑杆,安装支撑杆就位;Step 4. Stake out the lifting system, prepare materials, test the jack, oil pipe, and oil pump, install the jack, make the support rod, and install the support rod in place; 步骤5.操作平台系统放样,进行材料准备,搭设平台支架,对平台进行铺设,搁置仓顶钢梁,安装油泵、油管;Step 5. Operate the platform system to stake out, prepare materials, set up platform brackets, lay the platform, set aside the steel beams on the top of the warehouse, and install oil pumps and oil pipes; 步骤6.安装照明系统,综合验收滑模系统,试滑后对模板下口进行补缝;Step 6. Install the lighting system, comprehensively accept the sliding formwork system, and repair the bottom of the formwork after the trial slip; 步骤7.垂直运输机就位安装,验收后,负荷试运转,脚手架搭设,进入滑模施工阶段。Step 7. The vertical conveyor is installed in place. After acceptance, the load test run, the scaffolding is erected, and the slip form construction stage is entered. 5.根据权利要求1所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:在步骤3中,进行仓壁滑模施工,内外竖筋、采用环筋绑扎连接——预埋、预留——对仓壁进行混凝土浇筑、提升——仓壁的表面进行处理、养护——垂直、扭转的测量、预防与纠正——支承杆进行加固——将滑模系统拆除。5. the optimized sliding form structure construction technique for dislocation matrix square warehouse according to claim 1, is characterized in that: in step 3, carry out warehouse wall sliding form construction, inside and outside vertical reinforcement, adopt ring reinforcement to bind and connect—— Pre-embedded and reserved - Concrete pouring and lifting of the warehouse wall - Treatment and maintenance of the surface of the warehouse wall - Measurement, prevention and correction of vertical and torsion - Reinforcement of support rods - Remove the slip form system. 6.根据权利要求5所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:所述滑模的滑升过程中遇到特殊情况采取停工处理时,需要按照规定要求设置施工缝。6. The optimized sliding form structure construction technique for dislocation matrix square silo according to claim 5, is characterized in that: in the sliding process of described sliding form, when encountering special circumstances and taking shutdown treatment, it needs to be set according to the specified requirements Construction joints. 7.根据权利要求5所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:所述滑模系统拆除时,加固支撑杆的同时清除多余荷载滑模,拆除油路、油泵——利用塔吊拆除高架平台——拆除操作平台、栏杆、安全网——利用塔吊拆除内、外模板——拆除支撑、提升架、千斤顶——支撑杆堵头。7. The optimized sliding form structure construction technique for dislocation matrix square silo according to claim 5, it is characterized in that: when the described sliding form system is dismantled, while reinforcing the support rod, remove the excess load slip form, remove the oil circuit, Oil pump - use tower crane to remove elevated platform - remove operating platform, railings, safety net - use tower crane to remove inner and outer formwork - remove support, lifting frame, jack - support rod plug. 8.根据权利要求4所述的用于错位矩阵方仓的优化滑模结构施工工艺,其特征在于:所述仓壁采用喷淋进行养护,所述吊脚手架上设有环型PRR管,所述PRR管上设有多个开孔,所述开孔的开口方向对准仓壁混凝土面,所述PRR管通过增压泵加压连接供水管。8. The optimized sliding-form structure construction technique for dislocation matrix square warehouse according to claim 4, is characterized in that: described warehouse wall is maintained by spraying, and described hanging scaffold is provided with annular PRR pipe, so The PRR pipe is provided with a plurality of openings, the opening directions of the openings are aligned with the concrete surface of the warehouse wall, and the PRR pipe is pressurized and connected to the water supply pipe by a booster pump.
CN201910542041.6A 2019-06-21 2019-06-21 A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces Pending CN110206298A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910542041.6A CN110206298A (en) 2019-06-21 2019-06-21 A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910542041.6A CN110206298A (en) 2019-06-21 2019-06-21 A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces

Publications (1)

Publication Number Publication Date
CN110206298A true CN110206298A (en) 2019-09-06

Family

ID=67793893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910542041.6A Pending CN110206298A (en) 2019-06-21 2019-06-21 A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces

Country Status (1)

Country Link
CN (1) CN110206298A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112360216A (en) * 2020-12-02 2021-02-12 中国二十冶集团有限公司 Concrete storage bin top plate construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882321A (en) * 2017-11-23 2018-04-06 中铁建设集团南方工程有限公司 Diameter Silo slding form operation engineering method
CN207228737U (en) * 2017-07-12 2018-04-13 广州麦芽有限公司 More specification section cylinder group storehouses and its sliding formwork system
WO2018223144A1 (en) * 2017-06-02 2018-12-06 Zitting James System and method for automating vertical slip forming in concrete construction
CN109267803A (en) * 2018-10-09 2019-01-25 刘全义 The concrete prefabricated assembly combined storehouse of Contiuum type and method of construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018223144A1 (en) * 2017-06-02 2018-12-06 Zitting James System and method for automating vertical slip forming in concrete construction
CN207228737U (en) * 2017-07-12 2018-04-13 广州麦芽有限公司 More specification section cylinder group storehouses and its sliding formwork system
CN107882321A (en) * 2017-11-23 2018-04-06 中铁建设集团南方工程有限公司 Diameter Silo slding form operation engineering method
CN109267803A (en) * 2018-10-09 2019-01-25 刘全义 The concrete prefabricated assembly combined storehouse of Contiuum type and method of construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112360216A (en) * 2020-12-02 2021-02-12 中国二十冶集团有限公司 Concrete storage bin top plate construction method

Similar Documents

Publication Publication Date Title
CN101435276B (en) Hydraulic lifting and positioning device for steel beam at top of silo structure and construction method thereof
CN204098463U (en) Builder's jack
CN110230393B (en) Large concrete tank dome climbing high formwork support system and installation method
AU2013212529B2 (en) Automated formwork climbing system
CN102535845A (en) Construction method of bearing frame of corridor structure
CN106013774B (en) A kind of sliding formwork flexibility platform device for being suitble to dispatch
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN112458918A (en) High-pier hydraulic jacking integral steel frame platform formwork turnover construction system and construction method
CN113090019A (en) Construction method and construction device for high-rise structure
CN115030046A (en) Hydraulic creeping formwork for hollow thin-wall pier and construction method thereof
CN116290916A (en) Temporary support devices and low-carbon construction methods for heavy fabricated components
CN112575948A (en) Truss string beam and cantilever truss combined roof truss and construction method
CN110206298A (en) A kind of optimization sliding-mode structure construction technology for the matrix side storehouse that misplaces
CN113833263A (en) Integral lantern type support circulating hoisting construction method for frame column
CN110847289B (en) An ultra-deep and large-span circular water pump house roof support and construction method thereof
CN104831928B (en) High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method
CN208152583U (en) A kind of high-building construction ancillary equipment
CN115142666B (en) Reverse cone shell water tower construction device and method thereof
CN111847272A (en) Supporting method of tower crane for renovation of existing buildings
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
CN112647425A (en) Integral hoisting construction method for pier stud reinforcement cage
CN214737421U (en) Sliding and overturning construction device
JPH03125755A (en) Constructing method for cylindrical multistoried structure
CN221194195U (en) Can have enough to meet need scaffold frame operation platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190906

RJ01 Rejection of invention patent application after publication