SU1059107A1 - Method of constructing a flue - Google Patents

Method of constructing a flue Download PDF

Info

Publication number
SU1059107A1
SU1059107A1 SU802974721A SU2974721A SU1059107A1 SU 1059107 A1 SU1059107 A1 SU 1059107A1 SU 802974721 A SU802974721 A SU 802974721A SU 2974721 A SU2974721 A SU 2974721A SU 1059107 A1 SU1059107 A1 SU 1059107A1
Authority
SU
USSR - Soviet Union
Prior art keywords
height
installation
trunks
installing
trunk
Prior art date
Application number
SU802974721A
Other languages
Russian (ru)
Inventor
Василий Федорович Демин
Original Assignee
Demin Vasilij F
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Demin Vasilij F filed Critical Demin Vasilij F
Priority to SU802974721A priority Critical patent/SU1059107A1/en
Application granted granted Critical
Publication of SU1059107A1 publication Critical patent/SU1059107A1/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

СПОСОБ ВОЗВЕДЕНИЯ ДБ1МОВОЙ ТРУББ1, включающий установку арматурного каркаса, элементов футеровочной стенки на высоту  руса, крепление последней к арматурному каркасу, монтаж наружных щитов опалубки несущего железобетонного ствола, бетонирование ствола на высоту не менее 2/3 высоты футеровочной стенки и установку элементов следующего 8 «V Г7 по высоте  руса с помощью подъемных механизмов , отличающийс  тем, что. с целью обеспечени  возможности возведени  многоствольной трубы, при установке арматурных каркасов и элементов футеровочной стенки вначале осуществл ют их монтаж дл  ствола щахты лифта в центре трубы и дл  соединенных между собой внутренних цилиндрических частей стенок газоотвод щих стволов, а затем монтируют каркасы и футеровку наружных полуокружностей стволов в виде соединенных между собой усеченных полуконусов с одновременным соединением их с каркасами внутренних стенок, при этом одновременно с установкой ajv матурных каркасов стволов ведут возведение каркасов и установку опалубки направл ющих каналов дл  размещени  поль емных механизмов. Л О ел CD О METHOD OF CONSTRUCTION OF DB1MOVA TUBE1, including installation of the reinforcement cage, elements of the lining wall at the height of the rus, fastening the latter to the reinforcement cage, installation of the external shields of the supporting reinforced concrete trunk, concreting the trunk at a height of at least 2/3 of the height of the lining wall and installing the following 8 "V G7 taller with the help of lifting mechanisms, characterized in that. in order to allow the erection of a multi-barreled pipe, when installing reinforcing cages and elements of the lining wall, they are first installed for the barrel of the elevator at the center of the pipe and for interconnected internal cylindrical parts of the walls of the exhaust pipe trunks, and then the frames and lining of the outer semicircles of the trunks are connected in the form of interconnected truncated half-cones with their simultaneous connection with the frameworks of the inner walls, while simultaneously installing ajv matted cards The trunks of the trunks conduct the erection of the frameworks and the installation of the formwork of the guide channels to accommodate the use of conventional mechanisms. L O CD E

Description

Изобретение относитс  к области строительства , а именно к возведению дымовых труб.The invention relates to the field of construction, namely the construction of chimneys.

Известна дымова  труба, при возведении которой устанавливают наружный железобетонный ствол, а затем внутри него возвод т футеровоч ну ю стенку 1.A chimney pipe is known, during the erection of which an external reinforced concrete shaft is installed, and then a lining wall 1 is erected inside it.

Недостатками такого решени   вл ютс  значительна  трудоемкость и длительность монтажа.The disadvantages of this solution are considerable complexity and duration of installation.

Наиболее близким по технической сущности к изобретению  вл етс  способ возведени  дымовой трубы, включающий установку арматурного каркаса, возведение элементов футеровочной стенки на высоту  руса , крепление последней к арматурному каркасу , монтаж наружных щитов опалубки несущего железобетонного ствола, бетонирование ствола на высоту не менее 2/3 высоты футеровочной стенки и установку элементов следующего по высоте  руса с помощью подъемных механизмов 2.The closest to the technical essence of the invention is a method of erecting a chimney, including installation of a reinforcement cage, erection of elements of the lining wall at the height of the floor, fixing the latter to the reinforcement cage, installation of external shields of the bearing reinforced concrete trunk, concreting the trunk at a height of at least 2/3 the height of the lining wall and the installation of the elements of the next tier by means of lifting mechanisms 2.

Недостатком известного решени   вл етс  невозможность возведени  многоствольной трубы.A disadvantage of the known solution is the impossibility of erecting a multi-barrel pipe.

Цель изобретени  - обеспечение возможности возведени  многоствольной трубы.The purpose of the invention is to provide the possibility of erecting a multi-barreled tube.

Это достигаетс  тем,что согласно способу возведени  дымовой трубы, включающему установку арматурного каркаса, элементов футеровочной стенки на высоту  руса,крепление последней к арматурному каркасу, монтаж наружных щитов опалубки несущего железобетонного ствола, бетонирование ствола на высоту не менее 2/3 высоты футеровочной стенки и установку элементов следующего по высоте  руса с помощью подъемных механизмов, при установке арматурных каркасов и элементов футеровочной стенки вначале осуществл ют их монтаж дл  ствола щахты лифта в центре трубы и дл  соединенных между собой внутренних цилиндрических частей стенок газоотвод щих стволов, а затем монтируют каркасы и футеровку наружных полуокружностей стволов в виде соединенных между собой усеченных полуконусов с одновременным соединением их с каркасами внутренних стенок , при этом одновременно с установкой арматурных каркасов стволов ведут возведение каркасов и установку опалубки направл ющих каналов дл  размещени  подъемных механизмов.This is achieved by the fact that, according to the method of erecting a chimney, including the installation of the reinforcement cage, the elements of the lining wall to the height of the truss, fixing the latter to the reinforcement cage, the installation of the outer shields of the bearing reinforced concrete trunk, concreting the trunk to a height of at least 2/3 of the lining wall height and installation of elements of the next height with the help of lifting mechanisms; when installing reinforcement cages and elements of the lining wall, they are first mounted for the trunk shaft of the elevator in the center of the pipe and for interconnected inner cylindrical parts of the walls of the exhaust barrels, and then assemble the frames and lining of the outer semicircles of the barrels in the form of interconnected truncated semi-cones with their simultaneous connection with the frameworks of the inner walls, while simultaneously installing the reinforcement barrels of the barrels frames and installation of formwork guide channels for the placement of lifting mechanisms.

На фиг. 1 показана многоствольна  труба в начале возведени , план; на фиг. 2 -FIG. 1 shows a multi-barreled pipe at the beginning of the erection, a plan; in fig. 2 -

разрез А-А на фиг. I; на фиг. 3 - разрез на фиг. 1; на фиг. 4 - многоствольна  труба с несущим металлическим каркасом , план; на фиг. 5 - разрез В-В на фиг. 4.Section A-A in FIG. I; in fig. 3 shows a section in FIG. one; in fig. 4 - multi-barreled pipe with a supporting metal frame, plan; in fig. 5 shows a section B-B in FIG. four.

В начале возведени  осуществл ют монтаж элементов футеровочной стенки и каркасов ствола щахты лифта 1 в центре трубы и соединенных между собой внутренних цилиндрических частей 2 стенок газоотвод щих стволов, а затем монтируют футеровку в виде блок-панелей 3 и каркасы 4 наружных полуокружностей стоволов в виде соединенных между собой усеченных полуконусов 5 с одновременным соединением их с каркасами 6 внутренних стенок. Одновременно с установкой арматурных каркасов стволов ведут возведение каркасов и установку опалубки направл ющих каналов 7 дл  размещени  подъемных механизмов.At the beginning of the erection, the elements of the lining wall and the scaffolds of the elevator shaft 1 are mounted in the center of the pipe and the inner cylindrical parts 2 of the walls of the gas exhaust trunks are interconnected, and then the lining is mounted in the form of block panels 3 and the frames 4 of the outer semi-circles of the walls in the form of connected between each truncated half-cones 5 with their simultaneous connection with the frames of 6 inner walls. Simultaneously with the installation of the reinforcement cages of the trunks, the cages are erected and the formwork of the guide channels 7 is installed to accommodate the lifting mechanisms.

Устанавливают металлическую опалубку 8 снаружи стволов.Install the metal formwork 8 outside the trunks.

Одновременно внутри стволов устанавливают блок-панели 3 отдельными по сами по внутренней окружности стволов, установив предварительно вентил ционные бло5 ки 9. Наружна  стенка 10 блок-панелей 3 служит в качестве опалубки при бетонировании стенок ствола 11.At the same time, inside the trunks, the block panels are mounted 3 separate by themselves along the inner circumference of the trunks, by installing pre-ventilation blocks 9. The outer wall 10 of the block panels 3 serves as a formwork for concreting the walls of the barrel 11.

Блокгпанели 3 закрепл ютс  анкерами 12. Вертикальный канал 13 заполн етс  утеплителем 14.Block panels 3 are secured with anchors 12. Vertical channel 13 is filled with insulation 14.

0 После бетонировани  стенок ствола на высоту не менее 2/3 высоты блок-панелей 3 по всей окружности приступают к установке следующего по высоте по са.0 After concreting the walls of the trunk to a height of at least 2/3 of the height of the block panels 3 around the entire circumference, they proceed to the installation of the next highest height.

Бетонирование стволов ведут с помощью виброжелобов 15, соедин ющихс  с бетон5 ным бункером 16, который поднимаетс  лебедкой 17 через щахтный ствол 1 на высоту 1,5-2 м выше установленных блок-панелей 3, что позвол ет применить виброжелоба 15.The shafts are concreted using vibro-grooves 15, which are connected to a concrete bunker 16, which is raised by a winch 17 through a shaft 1 to a height of 1.5-2 m above the installed block panels 3, which allows the vibro-chutes 15 to be used.

Направл ющие каналы 7 используют дл The guide channels 7 are used for

прохождени  штанг-толкателей 18, которые соедин ютс  с металлическим несущим каркасом 19, поднимаемым ими с, помощью гидравлических подъемников 20, причем 5 подъем осуществл ют по окончании бетонировани  очередного по са стенок стволов. Изобретение позволит обеспечить возможность возведени  многоствольной трубы .the passage of the pushrod 18, which are connected to the metal support frame 19, lifted by them with the help of hydraulic lifts 20, and 5 lifting is carried out at the end of the concreting of the next wall of the trunks. The invention will allow the construction of a multi-barreled pipe.

АBUT

1212

Фуг.Fug.

Claims (1)

СПОСОБ ВОЗВЕДЕНИЯ ДЫМОВОЙ ТРУБЫ, включающий установку арматурного каркаса, элементов футеровочной стенки на высоту яруса, крепление последней к арматурному каркасу, монтаж наружных щитов опалубки несущего железобетонного ствола, бетонирование ствола на высоту не менее 2/3 высоты футеровочной стенки и установку элементов следующего по высоте яруса с помощью подъемных механизмов, отличающийся тем, что. с целью обеспечения возможности возведения многоствольной трубы, при установке арматурных каркасов и элементов футеровочной стенки вначале осуществляют их монтаж для ствола шахты лифта в центре трубы и для соединенных между собой внутренних цилиндрических частей стенок газоотводящих стволов, а затем монтируют каркасы и футеровку наружных полуокружностей стволов в виде соединенных между собой усеченных полуконусов с одновременным соединением их с каркасами внутренних стенок, при этом одновременно с установкой арматурных каркасов стволов ведут возведение каркасов и установку опалубки направляющих каналов для размещения подь емных механизмов.METHOD FOR SMOKE PIPE CONSTRUCTION, including installation of a reinforcing cage, elements of the lining wall to the tier height, fastening the latter to the reinforcing cage, installing external formwork panels of the bearing reinforced concrete trunk, concreting the trunk to a height of at least 2/3 of the height of the lining wall and installing elements of the next tier wall using lifting mechanisms, characterized in that. in order to provide the possibility of erecting a multi-barrel pipe, when installing reinforcing cages and elements of the lining wall, they are first installed for the trunk of the elevator shaft in the center of the pipe and for the interconnected inner cylindrical parts of the walls of the exhaust pipes, and then the frames and the lining of the outer semicircles of the trunks are mounted in the form interconnected truncated half-cones with their simultaneous connection with the frames of the inner walls, while simultaneously with the installation of reinforcing frames with oxen erection lead frames and installation of guide channels for placing formwork pod emnyh mechanisms. ib>)ib>)
SU802974721A 1980-08-13 1980-08-13 Method of constructing a flue SU1059107A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU802974721A SU1059107A1 (en) 1980-08-13 1980-08-13 Method of constructing a flue

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU802974721A SU1059107A1 (en) 1980-08-13 1980-08-13 Method of constructing a flue

Publications (1)

Publication Number Publication Date
SU1059107A1 true SU1059107A1 (en) 1983-12-07

Family

ID=20915080

Family Applications (1)

Application Number Title Priority Date Filing Date
SU802974721A SU1059107A1 (en) 1980-08-13 1980-08-13 Method of constructing a flue

Country Status (1)

Country Link
SU (1) SU1059107A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2518601C2 (en) * 2012-09-26 2014-06-10 Закрытое Акционерное Общество "Спецжелезобетонстрой" Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter
RU2648741C2 (en) * 2016-03-15 2018-03-28 Алексей Анатольевич Ладнушкин Method for mounting gas-outlet bore of chimney without crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР № 394523, кл. Е 04 Н 12/28,1971. 2. Авторское свидетельство СССР по за вке № 2713585/29-33, кл. Е 04 Н 12/28, 1979. *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2518601C2 (en) * 2012-09-26 2014-06-10 Закрытое Акционерное Общество "Спецжелезобетонстрой" Method to construct high-rise reinforced concrete industrial pipes with multi-layer lining with small outlet diameter
RU2648741C2 (en) * 2016-03-15 2018-03-28 Алексей Анатольевич Ладнушкин Method for mounting gas-outlet bore of chimney without crane

Similar Documents

Publication Publication Date Title
US4231148A (en) Elevator erection method
US20050072000A1 (en) Steam generator and assembly method
SU1059107A1 (en) Method of constructing a flue
CN111502067A (en) Node structure of prefabricated bearing wallboard of assembled PC combines light-duty steel skeleton
RU2102572C1 (en) Multibarrel smoke stack
US3552080A (en) Method for erecting multistory buildings
US4804320A (en) Sliding shuttering device
SU876941A1 (en) Flue erecting method
SU958642A1 (en) Flue erecting method
US4391070A (en) Chimney
RU96105130A (en) METHOD OF CONSTRUCTION OF MONOLITHIC BUILDINGS AND STRUCTURES
SU1008391A1 (en) Method for erecting building with cantilevered floors
SU1116135A1 (en) Arrangement for erecting flues
RU2338843C1 (en) Method of multistorey building carcassing
SU1368421A1 (en) Flue and method of constructing same
RU2101437C1 (en) Method for reconstruction of building
SU1661335A1 (en) Method of constructing ferroconcrete vaults on pneumatic formwork
SU1682472A1 (en) Strip foundation
RU2097513C1 (en) Process of erection of superstructure of building
SU977644A1 (en) Method for erecting cast-in-place buildings
RU2295010C2 (en) Low building
SU1527406A1 (en) Method of erecting industrial flues
RU2101438C1 (en) Method for reconstruction of building
SU755968A1 (en) Method of erecting multistorey building with suspended storeys
JPH0270861A (en) Mounting and overhaulting method of work scaffold in step-up technique