RU2101438C1 - Method for reconstruction of building - Google Patents
Method for reconstruction of building Download PDFInfo
- Publication number
- RU2101438C1 RU2101438C1 RU96113366/03A RU96113366A RU2101438C1 RU 2101438 C1 RU2101438 C1 RU 2101438C1 RU 96113366/03 A RU96113366/03 A RU 96113366/03A RU 96113366 A RU96113366 A RU 96113366A RU 2101438 C1 RU2101438 C1 RU 2101438C1
- Authority
- RU
- Russia
- Prior art keywords
- building
- tent
- reconstructed
- reconstruction
- supports
- Prior art date
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Tents Or Canopies (AREA)
Abstract
Description
Изобретение относитоя к области строительства и может быть использовано при реконструкции протяженных домов с увеличением этажности без отселения жильцов. The invention relates to the field of construction and can be used in the reconstruction of long houses with an increase in the number of storeys without resettlement of residents.
Известен способ ведения строительных работ, в процессе которых требуется защита от атмосферных воздействий, например ведение арматурных и бетонных работ в тепляках (шатрах) при строительстве железобетонных вытяжных труб [1] Такие тепляки крепят на самоподъемном кране, обеспечивающем перемещение лесов, тепляка и опалубки по мере возведения трубы. There is a method of conducting construction work, in the process of which protection from weathering is required, for example, reinforcing and concrete work in greenhouses (tents) during the construction of reinforced concrete exhaust pipes [1] Such greenhouses are mounted on a self-hoisting crane that allows scaffolding, greenhouse and formwork to be moved as pipe construction.
Наиболее близким к предлагаемому способу является способ реконструкции доменного цеха [2] Этот способ позволяет проводить работы по реконструкции сооружений основного производства под защитой шатра, смонтированного на временных опорах, установленных рядом с существующими колоннами реконструируемого здания. К недостаткам такого способа можно отнести необходимость применения тяжелого кранового оборудования, потребность в дополнительных площадях за пределами реконструируемого цеха, а также то, что при переходе к реконструкции следующего участка цеха шатер надо разобрать, а затем вновь собрать. Closest to the proposed method is a method of reconstruction of a blast furnace workshop [2] This method allows reconstruction of the main production facilities under the protection of a tent mounted on temporary supports installed next to the existing columns of the reconstructed building. The disadvantages of this method include the need to use heavy crane equipment, the need for additional space outside the reconstructed workshop, and the fact that when moving to the reconstruction of the next section of the workshop, the tent must be dismantled and then reassembled.
Техническая задача заключается в упрощении способа и сокращении сроков реконструкции протяженных зданий за счет возможности использования возведенного шатра поэтапно- последовательно на отдельных захватках здания без его демонтажа. The technical task is to simplify the method and reduce the time required for reconstruction of extended buildings due to the possibility of using the erected tent in stages and on separate grips of the building without dismantling it.
Поставленная задача решается таким образом, что в способе реконструкции здания, включающем возведение шатра над реконструируемой захваткой здания с опиранием его на устанавливаемые вдоль продольных стен временные опоры, разбору старых конструкций, возведение новых конструкций здания, демонтаж шатра и временных опор, согласно изобретению, предварительно в продольных стенах здания выше перекрытия последнего этажа устраивают отверстия и протягивают в них связи, устанавливают временные опоры снаружи здания, опирая на стену в оконных проемах последнего этажа и закрепляя их связями, после чего на опорах вдоль стен здания на расстоянии, равном сумме длин реконструируемой захватки здания и последующей захватки, подлежащей реконструкции, монтируют направляющие, возводят шатер над реконструируемой захваткой здания, опирая его на направляющие, затем производят разборку старых конструкций и возведение новых, после этого шатер перемещают по направляющим на последующую захватку, подлежащую реконструкции, и осуществляют перестановку временных опор и направляющих на следующие захватки здания, а демонтаж шатра осуществляют после реконструкции здания по всей длине. The problem is solved in such a way that in the method of building reconstruction, including erecting a tent over the reconstructed building grab with its support on temporary supports installed along the longitudinal walls, disassembling old structures, erecting new building structures, dismantling the tent and temporary supports, according to the invention, previously the longitudinal walls of the building above the ceiling of the last floor make holes and stretch the bonds in them, establish temporary supports outside the building, resting on the wall in the window rails of the last floor and securing them with ties, after which on the supports along the walls of the building at a distance equal to the sum of the lengths of the reconstructed building grab and the subsequent grab to be reconstructed, the rails are mounted, the tent is erected over the reconstructed building grab, resting it on the rails, then the old ones are disassembled structures and the construction of new ones, after that the tent is moved along the guides to the next grab to be reconstructed, and the temporary supports and the guides are rearranged to the following capturing the building, and dismantling the tent is carried out after the reconstruction of the building along the entire length.
Предлагаемый способ отличается от известного тем, что предварительно в продольных стенах здания выше перекрытия последнего этажа устраивают отверстия и протягивают в них связи из арматурной стали, на концах связей имеется резьба. Затем устанавливают временные опоры снаружи здания, опирая на стену в оконных проемах последнего этажа и закрепляя их связями при помощи гаек, что позволяет вести работы по реконструкции крыши, наращиванию стен и другие строительные работы по надстройке здания без отселения жильцов. Кроме того, предлагаемый способ отличается тем, что опоры фиксируют раскосными элементами, после чего на опорах вдоль стен здания на расстоянии, равном сумме длин реконструируемой захватки здания и последующей захватки, подлежащей реконструкции, монтируют направляющие, с опиранием на которые возводят шатер над реконструирумой захваткой здания. Затем под защитой шатра производят разборку старых конструкций и возведение новых, таким образом, строительные работы по реконструкции ведутся в благоприятных условиях под крышей, а существующее здание предохраняется от неблагоприятных атмосферных воздействий. Шатер после этого, не разбирая, перемещают по направляющим на последующую захватку, подлежащую реконструкции. Временные опоры и направляющие с захватки, на которой закончены работы по реконструкции, переставляют на следующие эахватки здания. Такой способ позволяет исключить затраты на разборку и последующее возведение шатра над очередной захваткой. Демонтаж шатра и всех временных опор осуществляют после реконструкции здания по всей длине. The proposed method differs from the known one in that previously holes are made in the longitudinal walls of the building above the ceiling of the last floor and the reinforcement steel ties are drawn into them, there is a thread at the ends of the ties. Then, temporary supports are installed outside the building, resting on a wall in the window openings of the last floor and securing them with ties using nuts, which allows for reconstruction of the roof, wall extension and other construction work on the building superstructure without resettling residents. In addition, the proposed method is characterized in that the supports are fixed with diagonal elements, after which the rails are mounted on supports along the walls of the building at a distance equal to the sum of the lengths of the reconstructed building grab and the subsequent grapple to be reconstructed, based on which the tent is erected over the reconstructed building grab . Then, under the protection of the tent, old structures are dismantled and new ones are erected, thus, reconstruction works are carried out under favorable conditions under the roof, and the existing building is protected from adverse atmospheric influences. The tent after that, without disassembling, is moved along the guides to the subsequent grapple to be reconstructed. Temporary supports and guides from the gripper, on which reconstruction work is completed, are rearranged to the next eahvatki of the building. This method eliminates the cost of disassembling and the subsequent erection of the tent over the next grab. Dismantling of the tent and all temporary supports is carried out after the reconstruction of the building along the entire length.
На фиг. 1 изображено реконструируемое здание в процессе надстройки, на фиг. 2 вид А А фиг. 1, на фиг. 3 узел А фиг. 2 пример конструктивного решения временной опоры. In FIG. 1 shows a reconstructed building during the superstructure; FIG. 2 view A A of FIG. 1, in FIG. 3 node A of FIG. 2 example of a constructive solution of temporary support.
На фиг. 1 показано, как организована по захваткам реконструкция с увеличением этажности протяженного дома: начаты и закончены работы на захватке "а", ведутся работы на реконструируемой захватке "б". In FIG. Figure 1 shows how reconstruction was organized by seizures with an increase in the number of storeys of an extended house: work on capture "a" was started and completed, work is underway on the reconstructed capture "b".
Способ осуществляют в следующей последовательности. Для реконструкции протяженного здания 1 с надстройкой мансарды 2 здание разделяют на технологические захватки "а", "б", "в" и т.д. размер которых определяется удобством ведения работ. Целесообразными являются захватки площадью 200-300 кв. м, что соответствует одному подъезду (одной секции) жилого дома. The method is carried out in the following sequence. For the reconstruction of an extended
В продольных стенах здания выше перекрытия последнего этажа устраивают отверстия 3 и протягивают в них связи 4. Затем устанавливают временные опоры 5, опирая на стену в оконных проемах 6 и закрепляя их при помощи гаек связями 4. Временные опоры 5 устанавливают вдоль наружных стен здания на двух соседних захватках, например на реконструируемую "б" и последующую, подлежащую реконструкции "в". Верхние части опор 5 вдоль стен здания объединяют смонтированные на них направляющие 7. Затем возводят защитный шатер 8 над реконструируемой захваткой "б" здания, опирая его на направляющие 7, и производят разборку старых конструкций 9 и возведение новых конструкций 2. Шатер 8 перемещают на последующую захватку "в", подлежащую реконструкции, и переставляют временные опоры 5 и направляющие 7 на следующую захватку "г". Демонтаж шатра 8 и временных опор 5 со связями 4 осуществляют после окончания реконструкции здания 1 по всей длине. In the longitudinal walls of the building above the ceiling of the last floor,
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU96113366/03A RU2101438C1 (en) | 1996-06-28 | 1996-06-28 | Method for reconstruction of building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
RU96113366/03A RU2101438C1 (en) | 1996-06-28 | 1996-06-28 | Method for reconstruction of building |
Publications (2)
Publication Number | Publication Date |
---|---|
RU2101438C1 true RU2101438C1 (en) | 1998-01-10 |
RU96113366A RU96113366A (en) | 1998-01-27 |
Family
ID=20182699
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
RU96113366/03A RU2101438C1 (en) | 1996-06-28 | 1996-06-28 | Method for reconstruction of building |
Country Status (1)
Country | Link |
---|---|
RU (1) | RU2101438C1 (en) |
-
1996
- 1996-06-28 RU RU96113366/03A patent/RU2101438C1/en not_active IP Right Cessation
Non-Patent Citations (1)
Title |
---|
Дубровский В.Б. и др. Строительство атомных электростанций. - М.: Энергоиздат, 1985, с.90 - 91. * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108625483B (en) | Equipment for jacking construction of assembled additional elevator shaft structure | |
CN109356167B (en) | Deep foundation pit support dismantling system and construction method | |
CN107327068B (en) | Steel structure truss string system roof ceiling structure and construction method thereof | |
CN110685459B (en) | Breaking hammer dismantling construction method for dismantling hoist bent from lower part | |
RU2101438C1 (en) | Method for reconstruction of building | |
RU2101437C1 (en) | Method for reconstruction of building | |
CN108584646B (en) | Assembled type additional elevator shaft structure suitable for jacking construction | |
CN115306137B (en) | Operation platform structure for installing suspended ceiling at bottom of high-altitude corridor and construction method thereof | |
JPS6049675B2 (en) | Relocation scaffolding for coke oven construction work | |
CN212562423U (en) | Ring type sliding scaffold for corridor | |
CN210768009U (en) | Movable steel bar processing shed structure | |
CN210563531U (en) | Steel structure support for building protection | |
RU2338843C1 (en) | Method of multistorey building carcassing | |
US3295266A (en) | Suspended floor system for a multi-level building | |
CN114059658A (en) | Construction method of overweight big wood structure vertical frame in historic building reconstruction and restoration | |
CN213539797U (en) | Outer wall supports protection device | |
RU2097513C1 (en) | Process of erection of superstructure of building | |
CN213572931U (en) | Hydraulic climbing operation platform for chimney construction | |
JP2621748B2 (en) | All-weather temporary shed | |
CN102465598A (en) | Construction method of high-altitude cast-in-site arch roof truss | |
CN1097229A (en) | Overhead site-casting method for broad-span presrtressed arch plate | |
CN216740618U (en) | Steel construction protection scaffold puts up system suitable for light rail station | |
US20230383558A1 (en) | Formwork system and a method of forming a wall | |
CN112681705A (en) | Steel wire rope net platform for construction and installation method thereof | |
SU1544902A1 (en) | Method of erecting multistorey building skeleton |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
MM4A | The patent is invalid due to non-payment of fees |
Effective date: 20060629 |