RU2012132640A - Способ и система управления для планирования нагрузки электростанции - Google Patents

Способ и система управления для планирования нагрузки электростанции Download PDF

Info

Publication number
RU2012132640A
RU2012132640A RU2012132640/08A RU2012132640A RU2012132640A RU 2012132640 A RU2012132640 A RU 2012132640A RU 2012132640/08 A RU2012132640/08 A RU 2012132640/08A RU 2012132640 A RU2012132640 A RU 2012132640A RU 2012132640 A RU2012132640 A RU 2012132640A
Authority
RU
Russia
Prior art keywords
generating units
components
maintenance
load
plan
Prior art date
Application number
RU2012132640/08A
Other languages
English (en)
Other versions
RU2523191C2 (ru
Inventor
Гопинатх СЕЛВАРАДЖ
Сентхил Кумар СУНДАРАМ
Мохан Кумар ШАНМУГАМ
Шрикант БХАТ
Original Assignee
Абб Рисерч Лтд
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Абб Рисерч Лтд filed Critical Абб Рисерч Лтд
Publication of RU2012132640A publication Critical patent/RU2012132640A/ru
Application granted granted Critical
Publication of RU2523191C2 publication Critical patent/RU2523191C2/ru

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B23/00Testing or monitoring of control systems or parts thereof
    • G05B23/02Electric testing or monitoring
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Tourism & Hospitality (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Feedback Control In General (AREA)

Abstract

1. Способ оптимизации планирования нагрузки для электростанции, имеющей один или более блоков генерирования, при этом способ, содержащий этапы, на которых:- анализируют рабочее состояние одного или более компонентов блоков генерирования, имеющих один или более индексов риска, ассоциированных с одним или более компонентами блоков генерирования;- обновляют, по меньшей мере, одну целевую функцию, которая отражает состояние одного или более компонентов блоков генерирования;- решают одну или более целевых функций, чтобы оптимизировать план одного или более блоков генерирования и рабочее состояние одного или более компонентов блоков генерирования; и- управляют одним или более блоками генерирования при оптимизированном плане и рабочем состоянии.2. Способ по п.1, в котором этап анализа включает в себя этап, на котором оценивают характеристики, оценивают эксплуатационные затраты и смещения в плане технического обслуживания в горизонте прогнозирования.3. Способ по п.1, в котором оптимизация планирования нагрузки включает в себя этап, на котором планируют выработку, планируют техническое обслуживание или нагрузку для одного или более блоков генерирования или комбинацию вышеозначенного.4. Способ по п.1, в котором оптимизация планирования нагрузки включает в себя этап, на котором оптимизируют индексы риска для одного или более компонентов одного или более блоков генерирования посредством надлежащего изменения регулируемых переменных.5. Способ по п.1, в котором оптимизация планирования нагрузки включает в себя этап, на котором задают отсрочку или опережение запуска технического обслуживания для технического обслужи�

Claims (10)

1. Способ оптимизации планирования нагрузки для электростанции, имеющей один или более блоков генерирования, при этом способ, содержащий этапы, на которых:
- анализируют рабочее состояние одного или более компонентов блоков генерирования, имеющих один или более индексов риска, ассоциированных с одним или более компонентами блоков генерирования;
- обновляют, по меньшей мере, одну целевую функцию, которая отражает состояние одного или более компонентов блоков генерирования;
- решают одну или более целевых функций, чтобы оптимизировать план одного или более блоков генерирования и рабочее состояние одного или более компонентов блоков генерирования; и
- управляют одним или более блоками генерирования при оптимизированном плане и рабочем состоянии.
2. Способ по п.1, в котором этап анализа включает в себя этап, на котором оценивают характеристики, оценивают эксплуатационные затраты и смещения в плане технического обслуживания в горизонте прогнозирования.
3. Способ по п.1, в котором оптимизация планирования нагрузки включает в себя этап, на котором планируют выработку, планируют техническое обслуживание или нагрузку для одного или более блоков генерирования или комбинацию вышеозначенного.
4. Способ по п.1, в котором оптимизация планирования нагрузки включает в себя этап, на котором оптимизируют индексы риска для одного или более компонентов одного или более блоков генерирования посредством надлежащего изменения регулируемых переменных.
5. Способ по п.1, в котором оптимизация планирования нагрузки включает в себя этап, на котором задают отсрочку или опережение запуска технического обслуживания для технического обслуживания одного или более компонентов одного или более блоков генерирования на основе состояния компонента или потребности нагрузки.
6. Способ по п.1, в котором целевая функция включает в себя, по меньшей мере, один член для управления технологическим процессом одного или более компонентов одного или более блоков генерирования или, по меньшей мере, один член, ассоциированный с техническим обслуживанием одного или более компонентов одного или более блоков генерирования, или комбинацию вышеозначенного.
7. Способ по п.1, в котором обновление включает в себя этап, на котором обновляют целевую функцию (a) затратами, ассоциированными с отсрочкой или опережением технического обслуживания одного или более компонентов одного или более блоков генерирования, или (b) затратами, ассоциированными с жизненным циклом одного или более компонентов одного или более блоков генерирования, или комбинацией (a) и (b).
8. Система управления для планирования нагрузки электростанции, имеющей один или более блоков генерирования, причем система управления содержит:
- оптимизатор, имеющий, по меньшей мере, одну целевую функцию для оптимизации планирования нагрузки, которая включает в себя планирование технического обслуживания, и для оптимального управления технологическими процессами одного или более блоков генерирования, причем упомянутый оптимизатор использует компонент модели станции и компонент модели повреждений для оптимизации планирования нагрузки.
9. Система по п.8, в которой оптимизатор содержит:
- анализатор планировщика для анализа рабочего состояния одного или более компонентов блоков генерирования, имеющих один или более индексов риска, ассоциированных с одним или более компонентами блоков генерирования.
10. Система по п.8, в которой оптимизатор выполнен с возможностью планирования технического обслуживания, осуществляемого посредством устройства запуска технического обслуживания на основе индексов риска, ассоциированных с одним или более компонентами одного или более блоков генерирования, либо прогноза потребности или улучшений в рабочем состоянии, обусловленных новыми регулируемыми переменными, либо плана заранее запланированного технического обслуживания, либо осуществляемого пользователем через пользовательский интерфейс, или комбинации вышеозначенного.
RU2012132640/08A 2009-12-31 2010-05-13 Способ и система управления для планирования нагрузки электростанции RU2523191C2 (ru)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
IN3244CH2009 2009-12-31
IN3244/CHE/2009 2009-12-31
PCT/IB2010/001106 WO2011080548A1 (en) 2009-12-31 2010-05-13 Method and control system for scheduling load of a power plant

Publications (2)

Publication Number Publication Date
RU2012132640A true RU2012132640A (ru) 2014-02-10
RU2523191C2 RU2523191C2 (ru) 2014-07-20

Family

ID=42556691

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2012132640/08A RU2523191C2 (ru) 2009-12-31 2010-05-13 Способ и система управления для планирования нагрузки электростанции

Country Status (10)

Country Link
US (1) US10013660B2 (ru)
EP (1) EP2519863A1 (ru)
JP (1) JP5996436B2 (ru)
KR (1) KR101733393B1 (ru)
CN (2) CN107862463B (ru)
AU (1) AU2010337991B2 (ru)
CA (1) CA2785752C (ru)
RU (1) RU2523191C2 (ru)
WO (1) WO2011080548A1 (ru)
ZA (1) ZA201204798B (ru)

Families Citing this family (55)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9069725B2 (en) 2011-08-19 2015-06-30 Hartford Steam Boiler Inspection & Insurance Company Dynamic outlier bias reduction system and method
GB201200491D0 (en) 2012-01-12 2012-02-22 Romax Technology Ltd Method for operating a wind turbine generator
US9411326B2 (en) * 2012-08-21 2016-08-09 General Electric Company Plant control optimization system including visual risk display
US9255525B2 (en) * 2012-11-30 2016-02-09 General Electric Company System and method for gas turbine operation
US20140324495A1 (en) * 2013-02-22 2014-10-30 Vestas Wind Systems A/S Wind turbine maintenance optimizer
US20140244328A1 (en) * 2013-02-22 2014-08-28 Vestas Wind Systems A/S Wind turbine maintenance optimizer
US10418833B2 (en) 2015-10-08 2019-09-17 Con Edison Battery Storage, Llc Electrical energy storage system with cascaded frequency response optimization
US9430311B2 (en) * 2013-07-23 2016-08-30 Halliburton Energy Services, Inc. Cause and effect mapping for failure mode effect analysis creation and risk management
US9471080B2 (en) 2013-10-21 2016-10-18 Restore Nv Portfolio managed, demand-side response system
EP2889711B1 (en) 2013-12-30 2020-07-01 Rolls-Royce Corporation System and method for optimizing component life in a power system
US9404426B2 (en) * 2013-12-31 2016-08-02 General Electric Company Methods and systems for enhancing control of power plant generating units
CA3116974A1 (en) * 2014-04-11 2015-10-15 Hartford Steam Boiler Inspection And Insurance Company Improving future reliability prediction based on system operational and performance data modelling
US10101731B2 (en) 2014-05-01 2018-10-16 Johnson Controls Technology Company Low level central plant optimization
US9605559B2 (en) 2015-02-02 2017-03-28 General Electric Company Wash timing based on turbine operating parameters
CN105929687B (zh) * 2015-02-27 2020-02-04 约翰逊控制技术公司 高层级中央设施优化
US10205322B1 (en) 2015-03-09 2019-02-12 Cummins Power Generation Ip, Inc. Economically efficient operation of a power generator
US10339461B2 (en) 2015-09-30 2019-07-02 The Boeing Company System for maintenance of a manufactured product
US10282687B2 (en) * 2015-10-07 2019-05-07 University Of Utah Research Foundation Systems and methods for managing power generation resources
US10509374B2 (en) 2015-10-07 2019-12-17 University Of Utah Research Foundation Systems and methods for managing power generation and storage resources
US10296030B2 (en) * 2015-10-07 2019-05-21 University Of Utah Research Foundation Systems and methods for power system management
US10186889B2 (en) 2015-10-08 2019-01-22 Taurus Des, Llc Electrical energy storage system with variable state-of-charge frequency response optimization
US10554170B2 (en) 2015-10-08 2020-02-04 Con Edison Battery Storage, Llc Photovoltaic energy system with solar intensity prediction
US10197632B2 (en) 2015-10-08 2019-02-05 Taurus Des, Llc Electrical energy storage system with battery power setpoint optimization using predicted values of a frequency regulation signal
US10418832B2 (en) 2015-10-08 2019-09-17 Con Edison Battery Storage, Llc Electrical energy storage system with constant state-of charge frequency response optimization
US10283968B2 (en) 2015-10-08 2019-05-07 Con Edison Battery Storage, Llc Power control system with power setpoint adjustment based on POI power limits
US11210617B2 (en) 2015-10-08 2021-12-28 Johnson Controls Technology Company Building management system with electrical energy storage optimization based on benefits and costs of participating in PDBR and IBDR programs
US10742055B2 (en) 2015-10-08 2020-08-11 Con Edison Battery Storage, Llc Renewable energy system with simultaneous ramp rate control and frequency regulation
US10700541B2 (en) 2015-10-08 2020-06-30 Con Edison Battery Storage, Llc Power control system with battery power setpoint optimization using one-step-ahead prediction
US10222427B2 (en) 2015-10-08 2019-03-05 Con Edison Battery Storage, Llc Electrical energy storage system with battery power setpoint optimization based on battery degradation costs and expected frequency response revenue
US10250039B2 (en) 2015-10-08 2019-04-02 Con Edison Battery Storage, Llc Energy storage controller with battery life model
US10190793B2 (en) 2015-10-08 2019-01-29 Johnson Controls Technology Company Building management system with electrical energy storage optimization based on statistical estimates of IBDR event probabilities
US10564610B2 (en) 2015-10-08 2020-02-18 Con Edison Battery Storage, Llc Photovoltaic energy system with preemptive ramp rate control
US10389136B2 (en) 2015-10-08 2019-08-20 Con Edison Battery Storage, Llc Photovoltaic energy system with value function optimization
US20170242081A1 (en) * 2016-02-24 2017-08-24 General Electric Company System and method for optimization of recommended service intervals
CN106096815A (zh) * 2016-05-31 2016-11-09 中国电力科学研究院 一种配电网运行效率影响度分析方法
US10778012B2 (en) 2016-07-29 2020-09-15 Con Edison Battery Storage, Llc Battery optimization control system with data fusion systems and methods
US10594153B2 (en) 2016-07-29 2020-03-17 Con Edison Battery Storage, Llc Frequency response optimization control system
JP6812169B2 (ja) * 2016-08-29 2021-01-13 川崎重工業株式会社 エネルギー需要設備の運用に関する計画作成装置及び計画作成方法
JP6677608B2 (ja) * 2016-09-05 2020-04-08 株式会社東芝 水力機械の壊食予測装置および予測方法
CN106779443B (zh) * 2016-12-26 2020-11-03 国网山东省电力公司泰安供电公司 电力调度中的操作风险确定方法和装置
US20180253087A1 (en) * 2017-03-06 2018-09-06 General Electric Company Scheduling maintenance to reduce degradation of a power generation system
US10333987B2 (en) * 2017-05-18 2019-06-25 Bank Of America Corporation Security enhancement tool for a target computer system operating within a complex web of interconnected systems
KR102073537B1 (ko) * 2017-09-06 2020-02-04 가부시키가이샤 티엘브이 리스크 평가 장치, 리스크 평가 시스템, 리스크 평가 방법 및 리스크 평가 프로그램
US10504195B2 (en) 2017-11-13 2019-12-10 Mitsubishi Electric Research Laboratories, Inc. System and method for decentralized energy production
US10838441B2 (en) 2017-11-28 2020-11-17 Johnson Controls Technology Company Multistage HVAC system with modulating device demand control
US10838440B2 (en) 2017-11-28 2020-11-17 Johnson Controls Technology Company Multistage HVAC system with discrete device selection prioritization
US10678227B2 (en) 2018-03-15 2020-06-09 Johnson Controls Technology Company Central plant control system with plug and play EMPC
US11159022B2 (en) 2018-08-28 2021-10-26 Johnson Controls Tyco IP Holdings LLP Building energy optimization system with a dynamically trained load prediction model
US11163271B2 (en) 2018-08-28 2021-11-02 Johnson Controls Technology Company Cloud based building energy optimization system with a dynamically trained load prediction model
US11636292B2 (en) 2018-09-28 2023-04-25 Hartford Steam Boiler Inspection And Insurance Company Dynamic outlier bias reduction system and method
WO2021055847A1 (en) 2019-09-18 2021-03-25 Hartford Steam Boiler Inspection And Insurance Company Computer-based systems, computing components and computing objects configured to implement dynamic outlier bias reduction in machine learning models
US11328177B2 (en) 2019-09-18 2022-05-10 Hartford Steam Boiler Inspection And Insurance Company Computer-based systems, computing components and computing objects configured to implement dynamic outlier bias reduction in machine learning models
US11615348B2 (en) 2019-09-18 2023-03-28 Hartford Steam Boiler Inspection And Insurance Company Computer-based systems, computing components and computing objects configured to implement dynamic outlier bias reduction in machine learning models
KR102209858B1 (ko) * 2020-08-21 2021-01-29 주식회사 아라아이티이엔지 인공신경망 기반의 가열 및 냉각 설비 가동 스케쥴링 방법
FR3137835A1 (fr) 2022-07-15 2024-01-19 L'oreal Composition pour la coloration des fibres kératineuses

Family Cites Families (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU399606A1 (ru) * 1972-04-29 1973-10-03 Способ оптимизации режима работы тепловой
RU2035107C1 (ru) * 1992-01-22 1995-05-10 Игорь Анатольевич Козурман Система электроснабжения
US6278899B1 (en) * 1996-05-06 2001-08-21 Pavilion Technologies, Inc. Method for on-line optimization of a plant
US7406431B2 (en) * 2000-03-17 2008-07-29 Siemens Aktiengesellschaft Plant maintenance technology architecture
JP3442059B2 (ja) 2000-05-11 2003-09-02 松下電器産業株式会社 電子放出性薄膜およびこれを用いたプラズマディスプレイパネルならびにこれらの製造方法
US6611773B2 (en) * 2000-11-28 2003-08-26 Power Measurement Ltd. Apparatus and method for measuring and reporting the reliability of a power distribution system with improved accuracy
US6671634B2 (en) * 2000-12-27 2003-12-30 Abb Research Ltd. System and method for reliability assessment of a power system having integrated modules
US6853930B2 (en) * 2001-02-27 2005-02-08 Hitachi, Ltd. System for aiding the preparation of operation and maintenance plans for a power generation installation
JP3801063B2 (ja) * 2001-02-27 2006-07-26 株式会社日立製作所 発電設備の運転・保全計画支援システム
JP4737735B2 (ja) * 2001-05-01 2011-08-03 学校法人東海大学 多品目多工程ロットサイズスケジューリング方法
US7089190B2 (en) * 2001-05-18 2006-08-08 Power Resource Managers, Llp System and method for managing utility power use
US8417360B2 (en) * 2001-08-10 2013-04-09 Rockwell Automation Technologies, Inc. System and method for dynamic multi-objective optimization of machine selection, integration and utilization
US6999829B2 (en) * 2001-12-26 2006-02-14 Abb Inc. Real time asset optimization
JP2003284260A (ja) * 2002-03-25 2003-10-03 Hitachi Ltd 発電設備改修及び更新支援方法、及びそのシステム
FR2849238A1 (fr) * 2002-12-20 2004-06-25 Elyo Systeme de prise en charge et d'exploitation des installations et services d'un site
US7203622B2 (en) * 2002-12-23 2007-04-10 Abb Research Ltd. Value-based transmission asset maintenance management of electric power networks
US7272516B2 (en) * 2002-12-23 2007-09-18 Abb Research Failure rate adjustment for electric power network reliability analysis
EP1513085A1 (en) * 2003-09-08 2005-03-09 Abb Research Ltd. Method of scheduling maintenance actions
JP2007293889A (ja) * 2004-01-05 2007-11-08 Hitachi Ltd 発電設備の運用管理システム及び保守管理サービス方法
US20060247798A1 (en) * 2005-04-28 2006-11-02 Subbu Rajesh V Method and system for performing multi-objective predictive modeling, monitoring, and update for an asset
US8055358B2 (en) * 2005-12-05 2011-11-08 Fisher-Rosemount Systems, Inc. Multi-objective predictive process optimization with concurrent process simulation
WO2007087537A2 (en) * 2006-01-23 2007-08-02 The Trustees Of Columbia University In The City Of New York System and method for grading electricity distribution network feeders susceptible to impending failure
FI118642B (fi) * 2006-04-28 2008-01-31 Kone Corp Hissijärjestelmä
CN1916949B (zh) * 2006-09-06 2010-11-10 成都赛康信息技术有限责任公司 电力设备状态评估及维修策略支撑系统
RU2007139972A (ru) * 2007-10-29 2009-05-10 Закрытое акционерное общество "Техсистем груп" (RU) Способ оптимизации режимов работы электростанций
CN101232182A (zh) * 2008-01-18 2008-07-30 清华大学 三维协调的电网能量管理系统及对电网的评估及控制方法
CN100555792C (zh) * 2008-01-30 2009-10-28 湖南大学 基于多智能体的配电网节能降耗综合管理系统及其管理方法
CN101465616B (zh) * 2008-12-30 2013-11-27 上海市电力公司 一种基于ucps的agc机组评价系统
US8433450B2 (en) * 2009-09-11 2013-04-30 Emerson Process Management Power & Water Solutions, Inc. Optimized control of power plants having air cooled condensers
AU2010327985B2 (en) * 2009-12-10 2012-12-13 Accenture Global Services Limited Energy facility control system

Also Published As

Publication number Publication date
EP2519863A1 (en) 2012-11-07
AU2010337991A1 (en) 2012-07-19
KR101733393B1 (ko) 2017-05-10
CN107862463A (zh) 2018-03-30
WO2011080548A1 (en) 2011-07-07
RU2523191C2 (ru) 2014-07-20
AU2010337991B2 (en) 2014-06-26
CA2785752A1 (en) 2011-07-07
CN107862463B (zh) 2021-09-28
JP2013516671A (ja) 2013-05-13
KR20120117847A (ko) 2012-10-24
JP5996436B2 (ja) 2016-09-21
CA2785752C (en) 2017-04-18
CN102893227A (zh) 2013-01-23
US10013660B2 (en) 2018-07-03
ZA201204798B (en) 2013-08-28
US20130006439A1 (en) 2013-01-03

Similar Documents

Publication Publication Date Title
RU2012132640A (ru) Способ и система управления для планирования нагрузки электростанции
WO2009114309A3 (en) Apparatus for optimizing a chemical looping combustion plant using a model predictive controller
JP5860612B2 (ja) 発電設備を改良するシステムおよび方法
US10591875B2 (en) Process optimization method and system for a power plant
CN101498458B (zh) 一种锅炉在线燃烧优化的模型更新方法
KR101771985B1 (ko) 에너지 수급 운용 가이던스 장치 및 제철소 내의 에너지 수급 운용 방법
CN113131523A (zh) 一种分品种电力供应预测方法及系统
CN112686571B (zh) 基于动态自适应建模的综合智慧能源优化调度方法及系统
MY191055A (en) Process model predictive control system and method for promoting production of anaerobic digestion gas
CN104376372A (zh) 基于源网荷互动模式的智能配电网调度业务优化方法
EP3945385A1 (en) Continuous flow engine monitoring method and system
CN112950001A (zh) 基于云边端闭环架构的智慧能量管控系统及方法
CN117270410A (zh) 一种智能家居能耗控制方法、设备及计算机可读存储介质
CN105740069B (zh) 一种多级数据转化任务的自动调度方法
CN104299055B (zh) 一种抑制电厂内机组反向调节的发电计划优化方法
JP2017028816A (ja) 計画策定装置、計画策定方法、及びプログラム
CN115220708A (zh) 一种航天器飞行程序的半自动编排方法
CN107730046A (zh) 一种电力短期负荷预测系统及方法
CN104299054A (zh) 一种引入水电机组振动区的发电计划优化方法
CN104578175A (zh) 一种用于电网备用调节的agc控制方法
Wang et al. Research on spare parts requirement quantity forecasting for communication equipment
Warsokusumo et al. Real-time online monitoring for maintaining energy efficiency performance of power generation system
Carpenter Data-Driven Management Strategy Can Reduce Environmental Effect of Production Plants
CN106292411B (zh) 一种采茶机群控制优化系统
ATE540559T1 (de) Betriebsverfahren und schaltungsanordnung für lichtquellen

Legal Events

Date Code Title Description
PC43 Official registration of the transfer of the exclusive right without contract for inventions

Effective date: 20200528