KR20200004615A - Construction method for underground wall - Google Patents

Construction method for underground wall Download PDF

Info

Publication number
KR20200004615A
KR20200004615A KR1020180077711A KR20180077711A KR20200004615A KR 20200004615 A KR20200004615 A KR 20200004615A KR 1020180077711 A KR1020180077711 A KR 1020180077711A KR 20180077711 A KR20180077711 A KR 20180077711A KR 20200004615 A KR20200004615 A KR 20200004615A
Authority
KR
South Korea
Prior art keywords
pile
weekend
auxiliary
casing
drilling
Prior art date
Application number
KR1020180077711A
Other languages
Korean (ko)
Other versions
KR102147823B1 (en
Inventor
장동운
Original Assignee
(주)한국리페어엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한국리페어엔지니어링 filed Critical (주)한국리페어엔지니어링
Priority to KR1020180077711A priority Critical patent/KR102147823B1/en
Publication of KR20200004615A publication Critical patent/KR20200004615A/en
Application granted granted Critical
Publication of KR102147823B1 publication Critical patent/KR102147823B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to a construction method for an underground cut-off wall including: a pair of main piles (100) separated from each other and installed one at a time, wherein the lower ends thereof are inserted deeply; and a plurality of auxiliary piles (200) installed in a row between the pair of main piles (100), wherein the lower ends thereof are inserted less deeply than the lower ends of the main piles (100). The construction method for the underground cut-off wall comprises: a main pile (100) installing step of installing the pair of main piles (100) in the ground; an auxiliary pile (200) drilling step of drilling the ground to form a plurality of auxiliary pile holes (201) between the installed pair of main piles (100), and inserting a plurality of auxiliary pile casings (210); an auxiliary pile (200) inserting step of injecting cement milk (M) into the plurality of auxiliary pile casings (210), and inserting the plurality of auxiliary piles (200); and an auxiliary pile casing (210) drawing step of drawing the plurality of auxiliary pile casings (210) from the plurality of auxiliary pile holes (201) before the cement milk (M) is cured, and applying vibration to the plurality of auxiliary pile casings (210). Constructability is excellent, and construction costs can be reduced.

Description

지중 차수벽 시공방법{CONSTRUCTION METHOD FOR UNDERGROUND WALL}Underground wall construction method {CONSTRUCTION METHOD FOR UNDERGROUND WALL}

본 발명은 건설 분야에 관한 것으로서, 상세하게는 지중 차수벽 시공방법에 관한 것이다.The present invention relates to the construction field, and more particularly, to a method for constructing underground water barrier walls.

도 1은 종래의 지중 차수벽 공법에 의해 형성된 지중 차수벽의 평면도이다.1 is a plan view of an underground order wall formed by a conventional underground order wall method.

도시된 바와 같이, 종래의 지중 차수벽은 하단이 고심도로 근입됨과 아울러 간격을 두고 하나씩 설치된 한 쌍의 주말뚝(100)과, 하단이 주말뚝(100)의 하단보다 저심도로 근입됨과 아울러 한 쌍의 주말뚝(100) 사이에 열지어 설치된 복수의 보조말뚝(200)을 포함하여 구성된다.As shown, a conventional underground order wall is a pair of weekend tufts (100) installed one by one at intervals and spaced at the bottom, and the bottom is entered with a lower depth than the bottom of the weekend tufts (100) It is configured to include a plurality of auxiliary piles 200 are installed between the weekend pile 100.

이는 각각 천공작업 및 말뚝의 설치에 의해, 한 쌍의 주말뚝(100) 사이에 열지어 복수의 보조말뚝(200)을 설치하고, 주말뚝(100)과 보조말뚝(200) 사이 및 복수의 보조말뚝(200) 사이에 차수 그라우팅(10)을 실시하는 공법에 의해 시공된다.It is installed between the pair of weekend piles 100, respectively, by the drilling work and the installation of piles, and install a plurality of auxiliary piles 200, between the weekend pile 100 and the auxiliary piles 200 and a plurality of auxiliary It is constructed by the method of performing the order grouting 10 between the pile 200.

그런데 이러한 종래의 지중 차수벽 공법은 말뚝의 설치작업 후 별도의 차수 그라우팅 작업이 필요하므로, 시공성이 좋지 않고, 공사비용이 많이 든다는 문제가 있다.However, such a conventional underground order wall method requires a separate order grouting work after the installation work of the pile, there is a problem that the workability is not good, and the construction cost is high.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 시공성이 우수하고 공사비용을 절감할 수 있도록 하는 지중 차수벽 시공방법을 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems, the object of the present invention is to propose a method for constructing underground water barrier walls that can be excellent in workability and to reduce the construction cost.

상기 과제의 해결을 위하여, 본 발명은 하단이 고심도로 근입됨과 아울러 간격을 두고 하나씩 설치된 한 쌍의 주말뚝(100)과, 하단이 상기 주말뚝(100)의 하단보다 저심도로 근입됨과 아울러 상기 한 쌍의 주말뚝(100) 사이에 열지어 설치된 복수의 보조말뚝(200)을 포함하는 지중 차수벽의 시공방법으로서, 지반에 대하여 한 쌍의 주말뚝 천공홀(101)을 형성하고, 상기 한 쌍의 주말뚝(100)을 설치하는 주말뚝(100) 설치단계; 설치된 상기 한 쌍의 주말뚝(100)의 사이에 복수의 보조말뚝 천공홀(201)을 형성하기 위하여, 지반을 천공함과 아울러, 복수의 보조말뚝 케이싱(210)을 근입하는 보조말뚝(200) 천공단계; 상기 복수의 보조말뚝 케이싱(210)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 복수의 보조말뚝(200)을 근입하는 보조말뚝(200) 근입단계; 상기 시멘트밀크(M)의 양생 이전, 상기 복수의 보조말뚝 천공홀(201)로부터 상기 복수의 보조말뚝 케이싱(210)을 인발하되, 상기 복수의 보조말뚝 케이싱(210)에 진동을 인가하는 보조말뚝 케이싱(210) 인발단계;를 포함하는 것을 특징으로 하는 지중 차수벽 시공방법을 제시한다.In order to solve the above problems, the present invention is a pair of weekend chimney 100 and the lower one is installed at intervals and installed at intervals, and the lower end is entered at a lower depth than the lower end of the weekend chimney 100 and As a method of constructing a ground order wall including a plurality of auxiliary piles 200 installed in a row between a pair of weekend piles 100, a pair of weekend pile drilling holes 101 are formed in the ground, and the pair Weekend stack 100 installation step of installing the weekend stack 100; In order to form a plurality of auxiliary pile boring holes 201 between the pair of weekend piles 100 installed, the auxiliary pile 200 which drills the ground and also enters the plurality of auxiliary pile casings 210. Perforation step; Injecting the cement pile (M) into the interior of the plurality of auxiliary pile casing 210, the auxiliary pile 200 indenting the plurality of auxiliary pile 200; Before curing of the cement milk (M), while drawing the plurality of auxiliary pile casing 210 from the plurality of auxiliary pile drilling holes 201, the auxiliary pile for applying vibration to the plurality of auxiliary pile casing 210 Casing 210 draw step; proposes underground construction wall construction method comprising a.

상기 보조말뚝(200)은 PHC 말뚝인 것이 바람직하다.The auxiliary pile 200 is preferably a PHC pile.

상기 주말뚝(100)은 강관말뚝(100a)인 것이 바람직하다.The weekend pile 100 is preferably a steel pipe pile (100a).

상기 주말뚝(100) 설치단계는, 상기 주말뚝 천공홀(101)을 형성하기 위하여, 지반을 천공함과 아울러, 주말뚝 케이싱(110)을 근입하는 주말뚝(100) 천공단계; 상기 주말뚝 케이싱(110)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 강관말뚝(100a)을 근입하는 강관말뚝(100a) 근입단계; 상기 주말뚝 천공홀(101)로부터 상기 주말뚝 케이싱(110)을 인발하는 주말뚝 케이싱(110) 인발단계;를 포함하는 것이 바람직하다.The weekend chimney 100 installation step, in order to form the weekend chimney drilling hole 101, while drilling the ground, weekend chimney (100) drilling step of entering the weekend chimney casing 110; Injecting the cement milk (M) into the interior of the weekend pile casing 110, the steel pipe pile (100a) incorporating the steel pipe pile (100a); It is preferred to include; weekend tulle casing (110) drawing step for drawing the weekend chimney casing 110 from the weekend tuft hole (101).

상기 주말뚝(100) 설치단계는, 상기 강관말뚝(100a)을 항타하는 항타단계;를 포함하는 것이 바람직하다.The weekend pile 100 installation step, the driving step for driving the steel pipe pile (100a); preferably includes.

상기 주말뚝(100)은 현장타설 말뚝(100b)인 것이 바람직하다.The weekend pile 100 is preferably a cast-in-place pile (100b).

상기 주말뚝(100) 설치단계는, 상기 주말뚝 천공홀(101)을 형성하기 위하여, 지반을 천공함과 아울러, 주말뚝 케이싱(110)을 근입하는 주말뚝(100) 천공단계; 상기 주말뚝 케이싱(110)의 내부에 H 파일(11) 또는 철근망을 설치함과 아울러, 콘크리트(C)를 타설하여 상기 현장타설 말뚝(100b)을 형성하는 현장타설단계; 상기 주말뚝 천공홀(101)로부터 상기 주말뚝 케이싱(110)을 인발하는 주말뚝 케이싱(110) 인발단계;를 포함하는 것이 바람직하다.The weekend chimney 100 installation step, in order to form the weekend chimney drilling hole 101, while drilling the ground, weekend chimney (100) drilling step of entering the weekend chimney casing 110; An in-site casting step of installing the H pile 11 or the reinforcing bar network in the weekend pile casing 110 and adding the concrete C to form the on-site placing pile 100b; It is preferred to include; weekend tulle casing (110) drawing step for drawing the weekend chimney casing 110 from the weekend tuft hole (101).

상기 보조말뚝(200) 천공단계, 보조말뚝(200) 근입단계 및 보조말뚝 케이싱(210) 인발단계는, 상기 복수의 보조말뚝 천공홀(201) 중 중앙부 보조말뚝 천공홀(201a)을 형성하기 위하여, 지반을 천공함과 아울러, 상기 복수의 보조말뚝 케이싱(210) 중 중앙부 보조말뚝 케이싱(210a)을 근입하는 중앙부 보조말뚝(200a) 천공단계; 상기 중앙부 보조말뚝 케이싱(210a)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 복수의 보조말뚝(200) 중 중앙부 보조말뚝(200a)을 근입하는 중앙부 보조말뚝(200a) 근입단계; 상기 시멘트밀크(M)의 양생 이전, 상기 중앙부 보조말뚝 천공홀(201a)로부터 상기 중앙부 보조말뚝 케이싱(210a)을 인발하는 중앙부 보조말뚝 케이싱(210a) 인발단계; 상기 복수의 보조말뚝 천공홀(201) 중 양측 보조말뚝 천공홀(201b)을 형성하기 위하여, 상기 중앙부 보조말뚝(200a)의 양측과 상기 한 쌍의 주말뚝(100) 사이의 지반을 천공함과 아울러, 상기 복수의 보조말뚝 케이싱(210) 중 양측 보조말뚝 케이싱(210b)을 근입하는 양측 보조말뚝(200b) 천공단계; 상기 양측 보조말뚝 케이싱(210b)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 복수의 보조말뚝(200) 중 양측 보조말뚝(200b)을 근입하는 양측 보조말뚝(200b) 근입단계; 상기 시멘트밀크(M)의 양생 이전, 상기 양측 보조말뚝 천공홀(201b)로부터 상기 양측 보조말뚝 케이싱(210b)을 인발하되, 상기 양측 보조말뚝 케이싱(210b)에 진동을 인가하는 양측 보조말뚝 케이싱(210b) 인발단계;를 포함하는 것이 바람직하다.The auxiliary pile 200 drilling step, the auxiliary pile 200 indentation step and the auxiliary pile casing 210 drawing step, in order to form a central secondary pile drilling hole 201a of the plurality of auxiliary pile drilling holes 201 Perforating the ground, and drilling the central secondary pile (200a) to approach the central secondary pile casing (210a) of the plurality of secondary pile casing (210); Injecting a cement milk (M) into the inside of the central secondary pile casing (210a), and the central secondary pile (200a) indentation step of injecting the central secondary pile (200a) of the plurality of secondary piles (200); Before curing the cement milk (M), drawing the central secondary pile casing (210a) for drawing the central secondary pile casing (210a) from the central secondary pile drilling hole (201a); Perforating the ground between both sides of the central secondary pile (200a) and the pair of weekend piles (100) in order to form the two secondary pile drilling holes (201b) of the plurality of secondary pile drilling holes (201) In addition, the drilling step of the two side piles (200b) for entering the two side of the secondary pile casing (210b) of the plurality of auxiliary pile casing (210); Injecting cement milk (M) into the inside of the both side auxiliary pile casings (210b), and injecting both side auxiliary piles (200b) into the two side auxiliary piles (200b) of the plurality of auxiliary piles (200); Before curing of the cement milk (M), both side auxiliary pile casing 210b is drawn from the two side secondary pile drilling holes 201b, and both side secondary pile casings for applying vibration to the side secondary pile casing 210b ( 210b) drawing step; preferably.

본 발명은 시공성이 우수하고 공사비용을 절감할 수 있도록 하는 지중 차수벽 시공방법을 제시한다.The present invention proposes a method for constructing underground water barrier walls, which is excellent in workability and can reduce construction cost.

도 1은 종래의 지중 차수벽 공법에 의해 형성된 지중 차수벽의 평면도.
도 2 이하는 본 발명의 실시예를 도시한 것으로서,
도 1 내지 7은 지중 차수벽의 시공방법의 제1 실시예의 공정도.
도 8 내지 10은 지중 차수벽의 시공방법의 제2 실시예의 공정도.
도 11 내지 16은 지중 차수벽의 시공방법의 제3 실시예의 공정도.
1 is a plan view of an underground order wall formed by a conventional underground order wall method.
Figure 2 below shows an embodiment of the present invention,
1 to 7 are process charts of the first embodiment of the method for constructing underground order walls.
8 to 10 are process drawings of a second embodiment of the construction method for underground water barrier walls.
11 to 16 are process charts of a third embodiment of the construction method of underground order walls.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2 이하에 도시된 바와 같이, 본 발명은 기본적으로, 하단이 고심도로(일반적으로 암반층까지) 근입됨과 아울러 간격을 두고 하나씩 설치된 한 쌍의 주말뚝(100)과, 하단이 주말뚝(100)의 하단보다 저심도로 근입됨과 아울러 한 쌍의 주말뚝(100) 사이에 열지어 설치된 복수의 보조말뚝(200)을 포함하는 지중 차수벽의 시공방법에 관한 것이다.As shown in FIG. 2 or less, the present invention basically includes a pair of weekend tufts 100 and a lower tuft tuft 100 that are installed one by one while spaced apart from each other at a high depth (typically to a rock layer). It is related to the construction method of the underground order wall including a plurality of auxiliary piles 200 which are installed in a lower depth than the bottom of the pair and are arranged between a pair of weekend piles (100).

이는 다음과 같은 공정에 의해 이루어진다.This is done by the following process.

지반에 대하여 간격을 두고 한 쌍의 주말뚝(100)을 설치한다(도 2 내지 4,8.9).A pair of weekend tufts 100 are installed at intervals with respect to the ground (FIGS. 2 to 4, 8.9).

설치된 한 쌍의 주말뚝(100)의 사이에 복수의 보조말뚝 천공홀(201)을 형성하기 위하여, 지반을 천공함과 아울러, 복수의 보조말뚝 케이싱(210)을 근입한다(도 5).In order to form a plurality of auxiliary pile drilling holes 201 between the pair of weekend piles 100 installed, the ground is drilled and a plurality of auxiliary pile casings 210 are mounted (FIG. 5).

이는 지반이 연약하여 천공장비에 의해 천공된 천공홀에 케이싱을 남겨두지 않으면 천공홀이 무너지는 경우를 전제로 한 것이다.This is based on the premise that if the ground is fragile and the casing is not left in the drilling hole drilled by the drilling equipment, the drilling hole collapses.

복수의 보조말뚝 케이싱(210)의 내부에 시멘트밀크(M)를 주입함과 아울러, 복수의 보조말뚝(200)을 근입한다(도 6).While injecting cement milk (M) into the plurality of auxiliary pile casings 210, the plurality of auxiliary piles 200 are driven (FIG. 6).

시멘트밀크(M)의 양생 이전, 복수의 보조말뚝 천공홀(201)로부터 복수의 보조말뚝 케이싱(210)을 인발하되, 복수의 보조말뚝 케이싱(210)에 진동을 인가한다(도 7).Before curing the cement milk M, the plurality of auxiliary pile casing 210 is drawn out from the plurality of auxiliary pile drilling holes 201, and vibration is applied to the plurality of auxiliary pile casings 210 (FIG. 7).

보조말뚝 케이싱(210)의 인발과 함께 보조말뚝 케이싱(210)에 인가되는 진동으로 인하여, 양생 이전의 시멘트밀크(M)는 복수의 보조말뚝(200) 사이의 간극을 충전하여 메움과 아울러, 주말뚝(100)과 보조말뚝(200) 사이의 간극 또한 충전하여 메우게 된다.Due to the vibration applied to the auxiliary pile casing 210 together with the drawing of the auxiliary pile casing 210, the cement milk M before curing fills the gap between the plurality of auxiliary piles 200, and The gap between the pile 100 and the auxiliary pile 200 is also filled to fill.

즉, 이러한 공정에 의해 지중 차수벽을 형성하는 경우, 보조말뚝(200)의 설치작업과 동시에 시멘트밀크(M) 주입작업이 이루어지므로, 보조말뚝(200)의 설치가 완료되면 자연스럽게 주말뚝(100)과 보조말뚝(200) 사이 및 복수의 보조말뚝(200) 사이를 시멘트밀크(M)가 충전하여 메우게 된다.That is, when the underground order wall is formed by such a process, since the cement milk (M) is injected at the same time as the installation work of the auxiliary pile 200, the weekend pile 100 is naturally completed when the installation of the auxiliary pile 200 is completed. Cement milk (M) is filled and filled between the auxiliary pile 200 and a plurality of auxiliary piles (200).

따라서 종래의 공법과 같이, 보조말뚝(200)의 설치 이후, 별도의 차수 그라우팅 작업이 필요없게 되므로, 시공성이 우수하고, 공사비용을 절감할 수 있다는 효과가 있다.Therefore, as in the conventional method, since the installation of the auxiliary pile 200, since the separate order grouting work is not required, the workability is excellent, there is an effect that can reduce the construction cost.

위 공정과 함께 또는 위 공정 이후, 다수의 주말뚝(100)과 보조말뚝(200)을 위와 같은 방식으로 시공함으로써, 필요한 규모의 지중 차수벽을 형성할 수 있다.In conjunction with or after the above process, by constructing a number of weekend pile 100 and the auxiliary pile 200 in the same manner, it is possible to form the underground order wall of the required scale.

보조말뚝(200)으로는 어떤 구조를 시공하더라도 관계없으나, PHC 말뚝을 사용하는 것이 구조적 안정성 및 시공성 측면에서 바람직하다.The auxiliary pile 200 may be any structure, but it is preferable to use a PHC pile in terms of structural stability and workability.

이하, 주말뚝(100)의 시공방법에 관한 실시예에 대하여 설명한다.Hereinafter, embodiments of the construction method of the weekend stack 100 will be described.

첫째, 주말뚝(100)으로 강관말뚝(100a)이 적용되는 경우, 다음과 같은 공정에 의해 시공된다.First, when the steel pipe pile 100a is applied as the weekend pile 100, it is constructed by the following process.

한 쌍의 주말뚝 천공홀(101)을 형성하기 위하여, 지반을 천공함과 아울러, 주말뚝 케이싱(110)을 근입한다(도 2).In order to form a pair of weekend tuft boring holes 101, while drilling the ground, the weekend tuft casing 110 is driven (Fig. 2).

주말뚝 케이싱(110)의 내부에 시멘트밀크(M)를 주입함과 아울러, 한 쌍의 강관말뚝(100a)을 근입한다(도 3).While injecting cement milk (M) into the weekend pile casing (110), a pair of steel pipe piles (100 a) are indented (FIG. 3).

이에 따라 시멘트밀크(M)가 강관말뚝(100a)의 내부에 충전됨과 아울러, 강관말뚝(100a)의 외주를 둘러싸 보호하게 된다.Accordingly, the cement milk (M) is filled in the interior of the steel pipe pile (100a), and also surrounds and protects the outer circumference of the steel pipe pile (100a).

강관말뚝(100a)의 내부 전체를 시멘트밀크(M)에 의해 충전할 필요가 없을 경우에는, 주말뚝 케이싱(110)의 내부에 먼저 강관말뚝(100a)을 근입하고, 주말뚝 케이싱(110)의 내면과 강관말뚝(100a)의 외면 사이에 시멘트밀크(M)를 주입하여 충전한다.When it is not necessary to fill the entire inside of the steel pipe pile 100a with cement milk M, the steel pipe pile 100a is first introduced into the weekend pile casing 110, and the weekend pile casing 110 Fill the cement milk (M) is injected between the inner surface and the outer surface of the steel pipe pile (100a).

주말뚝 천공홀(101)로부터 주말뚝 케이싱(110)을 인발한다(도 4).A weekend stack casing 110 is drawn from the weekend stack hole 101 (FIG. 4).

이후, 보조말뚝(200)의 시공을 위한 천공작업 시, 천공장비가 주말뚝(100)에 인접하여 천공작업을 하게 되는데, 이때 강관말뚝(100a)의 외주를 둘러싸도록 타설된 시멘트밀크(M)가 일부 절삭되면서 강관말뚝(100a)의 파손을 방지하게 된다.Subsequently, during the drilling work for the construction of the auxiliary pile 200, the drilling equipment is to be drilled adjacent to the weekend pile 100, at this time cement milk (M) was cast so as to surround the outer periphery of the steel pipe pile (100a) As part of the cutting to prevent breakage of the steel pipe pile (100a).

경우에 따라, 강관말뚝(100a)을 항타하여 설치할 수도 있는데, 이 경우에도 위와 같이 시멘트밀크(M)를 주입하여 강관말뚝(100a)을 보호할 수 있다.In some cases, it may be installed by driving the steel pipe pile (100a), in this case it can also protect the steel pipe pile (100a) by injecting cement milk (M) as described above.

둘째, 주말뚝(100)으로 현장타설 말뚝(100b)이 적용되는 경우, 다음과 같은 공정에 의해 시공된다.Second, when the site-placed pile 100b is applied as the weekend pile 100, it is constructed by the following process.

한 쌍의 주말뚝 천공홀(101)을 형성하기 위하여, 지반을 천공함과 아울러, 주말뚝 케이싱(110)을 근입한다(도 2).In order to form a pair of weekend tuft boring holes 101, while drilling the ground, the weekend tuft casing 110 is driven (Fig. 2).

주말뚝 케이싱(110)의 내부에 H 파일(11) 또는 철근망을 설치함과 아울러, 콘크리트(C)를 타설하여 현장타설 말뚝(100b)을 형성한다(도 8).In addition to installing the H pile 11 or the reinforcing bar network inside the weekend pile casing 110, concrete (C) is poured to form a cast-in-place pile 100b (FIG. 8).

주말뚝 천공홀(101)로부터 주말뚝 케이싱(110)을 인발한다(도 9).The weekend stack casing 110 is drawn from the weekend stack hole 101 (FIG. 9).

이 경우에도, 보조말뚝(200)의 시공을 위한 천공작업 시, 천공장비가 주말뚝(100)에 인접하여 천공작업을 하게 되는데, 이때에는 현장타설 말뚝(100b)의 외측 콘크리트 일부가 절삭되면서, 현장타설 말뚝(100b)의 전체적인 파손을 방지하게 된다.Even in this case, during the drilling work for the construction of the auxiliary pile 200, the drilling equipment is to be drilled adjacent to the weekend pile 100, at this time, while part of the outer concrete of the cast-in-place pile (100b), It is to prevent the overall damage of the cast-in-place pile (100b).

이하, 보조말뚝(200)의 시공방법에 관한 실시예에 대하여 설명한다.Hereinafter, embodiments of the construction method of the auxiliary pile 200 will be described.

상술한 복수의 보조말뚝(200)은 한번에 시공할 수도 있으나, 다음과 같은 공정을 취하는 것이 시공의 편의성 및 구조적 안정성을 위하여 더욱 바람직하다.Although the above-described plurality of auxiliary piles 200 may be constructed at a time, it is more preferable to take the following process for convenience of construction and structural stability.

복수의 보조말뚝 천공홀(201) 중 중앙부 보조말뚝 천공홀(201a)을 형성하기 위하여, 지반을 천공함과 아울러, 복수의 보조말뚝 케이싱(210) 중 중앙부 보조말뚝 케이싱(210a)을 근입한다(도 11).In order to form the central auxiliary pile drilling hole 201a among the plurality of auxiliary pile drilling holes 201, the central auxiliary pile casing 210a of the plurality of auxiliary pile casings 210 is drilled in addition to drilling the ground ( 11).

중앙부 보조말뚝 케이싱(210a)의 내부에 시멘트밀크(M)를 주입함과 아울러, 복수의 보조말뚝(200) 중 중앙부 보조말뚝(200a)을 근입한다(도 12).While injecting cement milk (M) into the inside of the central secondary pile casing (210a), the central secondary pile (200a) of the plurality of secondary piles 200 is indented (FIG. 12).

시멘트밀크(M)의 양생 이전, 중앙부 보조말뚝 천공홀(201a)로부터 중앙부 보조말뚝 케이싱(210a)을 인발한다(도 13).Before curing the cement milk M, the central auxiliary pile casing 210a is drawn from the central auxiliary pile drilling hole 201a (FIG. 13).

이와 같이 중앙부 보조말뚝(200a)의 시공을 완료한 이후, 복수의 보조말뚝 천공홀(201) 중 양측 보조말뚝 천공홀(201b)을 형성하기 위하여, 중앙부 보조말뚝(200a)의 양측과 한 쌍의 주말뚝(100) 사이의 지반을 천공함과 아울러, 복수의 보조말뚝 케이싱(210) 중 양측 보조말뚝 케이싱(210b)을 근입한다(도 14).After completing the construction of the central auxiliary pile 200a as described above, in order to form the two auxiliary pile drilling holes 201b of the plurality of auxiliary pile drilling holes 201, both sides and a pair of the central auxiliary pile 200a In addition to drilling the ground between the weekend pile 100, both of the auxiliary pile casing 210 of the plurality of auxiliary pile casing 210 is indented (Fig. 14).

이 경우, 양측 보조말뚝(200b)의 시공을 위한 천공작업 시, 천공장비가 주말뚝(100) 및 중앙부 보조말뚝(200a)에 인접하여 천공작업을 하게 되는데, 중앙부 보조말뚝(200a)의 외측 콘크리트 일부가 절삭되면서, 중앙부 보조말뚝(200a)의 전체적인 파손을 방지하게 된다.In this case, when the drilling work for the construction of the side auxiliary pile (200b), the drilling equipment is to be drilled adjacent to the weekend pile 100 and the central secondary pile (200a), the outer concrete of the central secondary pile (200a) As a part is cut, the entire breakage of the central auxiliary pile 200a is prevented.

양측 보조말뚝 케이싱(210b)의 내부에 시멘트밀크(M)를 주입함과 아울러, 복수의 보조말뚝(200) 중 양측 보조말뚝(200b)을 근입한다(도 15).While injecting cement milk (M) into the interior of both side auxiliary pile casings (210b), both side auxiliary piles (200b) of the plurality of auxiliary piles (200) are incorporated (FIG. 15).

시멘트밀크(M)의 양생 이전, 양측 보조말뚝 천공홀(201b)로부터 양측 보조말뚝 케이싱(210b)을 인발하되, 양측 보조말뚝 케이싱(210b)에 진동을 인가한다(도 16).Before curing of the cement milk (M), while drawing both side pile pile casing (210b) from both side pile pile drilling holes (201b), the vibration is applied to both side pile pile casing (210b) (Fig. 16).

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has been described only with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above It will be said that both the technical idea and the technical idea which together with the base are included in the scope of the present invention.

100 : 주말뚝 100a : 강관말뚝
100b : 현장타설 말뚝 101 : 주말뚝 천공홀
110 : 주말뚝 케이싱 200 : 보조말뚝
201 : 보조말뚝 천공홀 210 : 보조말뚝 케이싱
M : 시멘트밀크 C : 콘크리트
100: weekend pile 100a: steel pipe pile
100b: cast-in-place pile 101: weekend pile drilling hole
110: weekend pile casing 200: auxiliary pile
201: secondary pile drilling hole 210: secondary pile casing
M: Cement Milk C: Concrete

Claims (8)

하단이 고심도로 근입됨과 아울러 간격을 두고 하나씩 설치된 한 쌍의 주말뚝(100)과, 하단이 상기 주말뚝(100)의 하단보다 저심도로 근입됨과 아울러 상기 한 쌍의 주말뚝(100) 사이에 열지어 설치된 복수의 보조말뚝(200)을 포함하는 지중 차수벽의 시공방법으로서,
지반에 대하여 한 쌍의 주말뚝 천공홀(101)을 형성하고, 상기 한 쌍의 주말뚝(100)을 설치하는 주말뚝(100) 설치단계;
설치된 상기 한 쌍의 주말뚝(100)의 사이에 복수의 보조말뚝 천공홀(201)을 형성하기 위하여, 지반을 천공함과 아울러, 복수의 보조말뚝 케이싱(210)을 근입하는 보조말뚝(200) 천공단계;
상기 복수의 보조말뚝 케이싱(210)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 복수의 보조말뚝(200)을 근입하는 보조말뚝(200) 근입단계;
상기 시멘트밀크(M)의 양생 이전, 상기 복수의 보조말뚝 천공홀(201)로부터 상기 복수의 보조말뚝 케이싱(210)을 인발하되, 상기 복수의 보조말뚝 케이싱(210)에 진동을 인가하는 보조말뚝 케이싱(210) 인발단계;를
포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
A pair of weekend tufts (100) installed one by one at intervals and the interval is entered at a lower depth, and the lower end is entered in a lower depth than the bottom of the weekend tufts (100) and between the pair of weekend tufts (100) As a construction method of the underground order wall including a plurality of auxiliary piles 200 installed in a row,
Forming a pair of weekend chimney holes 101 on the ground, and installing a pair of weekend chimneys 100 at the weekend;
In order to form a plurality of auxiliary pile boring holes 201 between the pair of weekend piles 100 installed, the auxiliary pile 200 which drills the ground and also enters the plurality of auxiliary pile casings 210. Perforation step;
Injecting the cement pile (M) into the interior of the plurality of auxiliary pile casing 210, the auxiliary pile 200 indenting the plurality of auxiliary pile 200;
Before curing of the cement milk (M), while drawing the plurality of auxiliary pile casing 210 from the plurality of auxiliary pile drilling holes 201, the auxiliary pile for applying vibration to the plurality of auxiliary pile casing 210 Casing 210 drawing step;
Underground order wall construction method comprising a.
제1항에 있어서,
상기 보조말뚝(200)은 PHC 말뚝인 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
The secondary pile 200 is a ground order wall construction method, characterized in that the PHC pile.
제1항에 있어서,
상기 주말뚝(100)은 강관말뚝(100a)인 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
The weekend pile 100 is a ground order wall construction method, characterized in that the steel pipe pile (100a).
제3항에 있어서,
상기 주말뚝(100) 설치단계는,
상기 주말뚝 천공홀(101)을 형성하기 위하여, 지반을 천공함과 아울러, 주말뚝 케이싱(110)을 근입하는 주말뚝(100) 천공단계;
상기 주말뚝 케이싱(110)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 강관말뚝(100a)을 근입하는 강관말뚝(100a) 근입단계;
상기 주말뚝 천공홀(101)로부터 상기 주말뚝 케이싱(110)을 인발하는 주말뚝 케이싱(110) 인발단계;를
포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 3,
The weekend chimney 100 installation step,
In order to form the weekend chimney bore hole 101, while drilling the ground, the weekend chimney (100) drilling step of entering the weekend chimney casing 110;
Injecting the cement milk (M) into the interior of the weekend pile casing 110, the steel pipe pile (100a) incorporating the steel pipe pile (100a);
A weekend stacking casing 110 drawing out step of drawing the weekend stack casing 110 from the weekend stack hole 101;
Underground order wall construction method comprising a.
제3항에 있어서,
상기 주말뚝(100) 설치단계는,
상기 강관말뚝(100a)을 항타하는 항타단계;를
포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 3,
The weekend chimney 100 installation step,
A driving step for driving the steel pipe pile (100a);
Underground order wall construction method comprising a.
제1항에 있어서,
상기 주말뚝(100)은 현장타설 말뚝(100b)인 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
The weekend pile 100 is the underground order wall construction method, characterized in that the cast-in-place pile (100b).
제6항에 있어서,
상기 주말뚝(100) 설치단계는,
상기 주말뚝 천공홀(101)을 형성하기 위하여, 지반을 천공함과 아울러, 주말뚝 케이싱(110)을 근입하는 주말뚝(100) 천공단계;
상기 주말뚝 케이싱(110)의 내부에 H 파일(11) 또는 철근망을 설치함과 아울러, 콘크리트(C)를 타설하여 상기 현장타설 말뚝(100b)을 형성하는 현장타설단계;
상기 주말뚝 천공홀(101)로부터 상기 주말뚝 케이싱(110)을 인발하는 주말뚝 케이싱(110) 인발단계;를
포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 6,
The weekend chimney 100 installation step,
In order to form the weekend chimney bore hole 101, while drilling the ground, the weekend chimney (100) drilling step of entering the weekend chimney casing 110;
An in-site casting step of installing the H pile 11 or the reinforcing bar network in the weekend pile casing 110 and adding the concrete C to form the on-site placing pile 100b;
A weekend stacking casing 110 drawing out step of drawing the weekend stack casing 110 from the weekend stack hole 101;
Underground order wall construction method comprising a.
제1항에 있어서,
상기 보조말뚝(200) 천공단계, 보조말뚝(200) 근입단계 및 보조말뚝 케이싱(210) 인발단계는,
상기 복수의 보조말뚝 천공홀(201) 중 중앙부 보조말뚝 천공홀(201a)을 형성하기 위하여, 지반을 천공함과 아울러, 상기 복수의 보조말뚝 케이싱(210) 중 중앙부 보조말뚝 케이싱(210a)을 근입하는 중앙부 보조말뚝(200a) 천공단계;
상기 중앙부 보조말뚝 케이싱(210a)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 복수의 보조말뚝(200) 중 중앙부 보조말뚝(200a)을 근입하는 중앙부 보조말뚝(200a) 근입단계;
상기 시멘트밀크(M)의 양생 이전, 상기 중앙부 보조말뚝 천공홀(201a)로부터 상기 중앙부 보조말뚝 케이싱(210a)을 인발하는 중앙부 보조말뚝 케이싱(210a) 인발단계;
상기 복수의 보조말뚝 천공홀(201) 중 양측 보조말뚝 천공홀(201b)을 형성하기 위하여, 상기 중앙부 보조말뚝(200a)의 양측과 상기 한 쌍의 주말뚝(100) 사이의 지반을 천공함과 아울러, 상기 복수의 보조말뚝 케이싱(210) 중 양측 보조말뚝 케이싱(210b)을 근입하는 양측 보조말뚝(200b) 천공단계;
상기 양측 보조말뚝 케이싱(210b)의 내부에 시멘트밀크(M)를 주입함과 아울러, 상기 복수의 보조말뚝(200) 중 양측 보조말뚝(200b)을 근입하는 양측 보조말뚝(200b) 근입단계;
상기 시멘트밀크(M)의 양생 이전, 상기 양측 보조말뚝 천공홀(201b)로부터 상기 양측 보조말뚝 케이싱(210b)을 인발하되, 상기 양측 보조말뚝 케이싱(210b)에 진동을 인가하는 양측 보조말뚝 케이싱(210b) 인발단계;를
포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
The auxiliary pile 200 drilling step, the auxiliary pile 200 indentation step and the auxiliary pile casing 210 drawing step,
In order to form a central auxiliary pile drilling hole 201a among the plurality of auxiliary pile drilling holes 201, the ground is drilled, and the central auxiliary pile casing 210a of the plurality of auxiliary pile casings 210 is applied. Centering the secondary pile (200a) drilling step;
Injecting a cement milk (M) into the inside of the central secondary pile casing (210a), and the central secondary pile (200a) indentation step of injecting the central secondary pile (200a) of the plurality of secondary piles (200);
Before curing the cement milk (M), drawing the central secondary pile casing (210a) for drawing the central secondary pile casing (210a) from the central secondary pile drilling hole (201a);
Perforating the ground between both sides of the central secondary pile (200a) and the pair of weekend piles (100) in order to form both side secondary pile drilling holes (201b) of the plurality of secondary pile drilling holes (201) In addition, the drilling step of the two side piles (200b) for entering the two side pile piles (210b) of the plurality of auxiliary pile casings 210;
Injecting cement milk (M) into the inside of the both side auxiliary pile casings (210b), and injecting both side auxiliary piles (200b) into the two side auxiliary piles (200b) of the plurality of auxiliary piles (200);
Before curing of the cement milk (M), both side auxiliary pile casing (210b) is drawn from the side auxiliary pile drilling holes (201b), both side auxiliary pile casing for applying vibration to the side auxiliary pile casing (210b) ( 210b) drawing step;
Underground order wall construction method comprising a.
KR1020180077711A 2018-07-04 2018-07-04 Construction method for underground wall KR102147823B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180077711A KR102147823B1 (en) 2018-07-04 2018-07-04 Construction method for underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180077711A KR102147823B1 (en) 2018-07-04 2018-07-04 Construction method for underground wall

Publications (2)

Publication Number Publication Date
KR20200004615A true KR20200004615A (en) 2020-01-14
KR102147823B1 KR102147823B1 (en) 2020-08-25

Family

ID=69152859

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180077711A KR102147823B1 (en) 2018-07-04 2018-07-04 Construction method for underground wall

Country Status (1)

Country Link
KR (1) KR102147823B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112609704A (en) * 2020-12-07 2021-04-06 浙江大东吴集团建设有限公司 Construction pile based on SMW construction method and construction method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102247720B1 (en) 2020-12-28 2021-05-03 (주)태창기초 Method for wall collapse preventing and water-repellency improving
KR102637328B1 (en) 2022-09-23 2024-02-15 정국 Water gate

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004238818A (en) * 2003-02-04 2004-08-26 Takenaka Komuten Co Ltd Work execution method for soil cement column-row wall with tip foot protection pile structure
KR20100035349A (en) * 2008-09-26 2010-04-05 주식회사 한미파슨스건축사사무소 Construction method of retaining wall using cast-in-place pile
KR20160025242A (en) * 2014-08-27 2016-03-08 (주)백경지앤씨 The Earth Retaining Wall using the Hybrid-CIP(Cast-In place concrete Pile) method, and thereof Construction Method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004238818A (en) * 2003-02-04 2004-08-26 Takenaka Komuten Co Ltd Work execution method for soil cement column-row wall with tip foot protection pile structure
KR20100035349A (en) * 2008-09-26 2010-04-05 주식회사 한미파슨스건축사사무소 Construction method of retaining wall using cast-in-place pile
KR20160025242A (en) * 2014-08-27 2016-03-08 (주)백경지앤씨 The Earth Retaining Wall using the Hybrid-CIP(Cast-In place concrete Pile) method, and thereof Construction Method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112609704A (en) * 2020-12-07 2021-04-06 浙江大东吴集团建设有限公司 Construction pile based on SMW construction method and construction method thereof
CN112609704B (en) * 2020-12-07 2022-01-07 浙江大东吴集团建设有限公司 Construction pile based on SMW construction method and construction method thereof

Also Published As

Publication number Publication date
KR102147823B1 (en) 2020-08-25

Similar Documents

Publication Publication Date Title
KR102009077B1 (en) Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type
KR20200004615A (en) Construction method for underground wall
KR101655077B1 (en) Construction method of block for prefabricated retaining wall
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
KR20100043600A (en) Underground excuvation pile construction method using percussion rotary drill
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR101674656B1 (en) CIP retaining wall with steel tube
JP2009174178A (en) Method of constructing underground structure
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
CN111827280B (en) Ex-situ pouring, jacking and in-place hole digging pile retaining wall device and construction method thereof
JP2000352296A (en) Method o constructing passage just under underground structure
KR102494824B1 (en) CIP retaining wall and water barrier construction method using PHC-pile
JP2009287172A (en) Method for constructing base-isolated building by inverted construction method
KR100976620B1 (en) Construction method for basement extention
JP6326294B2 (en) Construction method of earth retaining structure
KR20200026467A (en) Precast concrete wall structure for underground using steel water-stop
KR102267641B1 (en) PHC pile construction method using joint PHC pile and detachable auxiliary pile
KR101253841B1 (en) Vertically Inserting Column into the Eccentrically Bored Hole & the Method Thereof
KR102337545B1 (en) Underground retaining wall using concrete pile and soil retaining plate
KR102601336B1 (en) PRD method proceeding from the upper part of the underground structure and casing guide device
JP6534026B2 (en) Seismic isolation building and its construction method
KR20190142492A (en) PHC pile to facilitate soil guard and construction method of soil guard structure using the same
RU2646267C1 (en) Precast pile with widening
KR20240098654A (en) Construction method of cast in place concrete pile for impermeable wall
JP2761531B2 (en) Construction method of guide for underground diaphragm wall

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant