KR20110135496A - Construction method for building and form - Google Patents
Construction method for building and form Download PDFInfo
- Publication number
- KR20110135496A KR20110135496A KR1020100055246A KR20100055246A KR20110135496A KR 20110135496 A KR20110135496 A KR 20110135496A KR 1020100055246 A KR1020100055246 A KR 1020100055246A KR 20100055246 A KR20100055246 A KR 20100055246A KR 20110135496 A KR20110135496 A KR 20110135496A
- Authority
- KR
- South Korea
- Prior art keywords
- formwork
- wire
- concrete
- foundation
- building
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
- E02D27/013—Shuttering specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
본 발명은 건축물의 기초 시공방법 및 이를 위한 거푸집에 관한 것이다.The present invention relates to a basic construction method of the building and formwork for the same.
일반적으로 건축물을 시공하기 위해서는, 먼저 바닥에 기초시공을 한 후, 기초에 설치된 토대 상에 용접 및 볼트체결로 벽체를 설치하고, 벽체 상에 지붕을 설치하고, 건축물의 외부에 테라스나 데크를 설치할 경우 건축물 기초 시공과는 무관하게 평탄화된 지면에 기둥을 세우고 그 상부에 데크 혹은 테라스를 형성하는 플레이트 등을 설치하여 완성하였다.In general, in order to construct a building, first install the foundation on the floor, then install the walls by welding and bolting on the foundation installed on the foundation, install the roof on the walls, and install the terrace or deck outside the building. In this case, the pillars were built on the leveled ground irrespective of the basic construction of the building, and the decks or terraces were formed on the upper part of the building.
상기에서 기초 시공은, 바닥 평탄화 작업 후, 바닥면에 수직으로 위치되는 패널을, 바닥에 고정설치되는 지지대 및 패널들을 연결하는 연결바와 체결시켜 거푸집을 형성하고, 상기한 거푸집 내부로 콘크리트를 타설하여 지반을 형성하고, 지반 타설 과정에 앵커를 설치한 후, 앵커를 통해서 토대와 지반을 서로 연결하여 시공하였다.In the above-mentioned basic construction, after the floor flattening operation, the panel vertically positioned on the floor surface is fastened to the support bar and the connection bar connecting the panels fixed to the floor to form a formwork, and cast concrete into the formwork. After the ground was formed, and the anchor was installed in the ground placing process, the foundation and the ground were connected to each other through the anchor.
그러나, 이러한 종래의 기초 시공방법에 있어서는 기초를 타설하는 과정에 앵커를 설치하고 이후 앵커와 토대를 체결하였으므로 체결에 시간이 많이 소요될 뿐 아니라, 앵커의 위치가 타설과정에서 몰탈의 수축 등으로 인하여 위치가 정밀하게 제어되지 않아서 토대 설치 시 토대에 별도의 앵커 체결공을 천공하여야 하는 불편이 있었고 이로 인하여 공기가 많이 소요되는 문제점도 있었다.However, in the conventional foundation construction method, since the anchor is installed in the process of placing the foundation and then the foundation is fastened with the anchor, it takes a lot of time to fasten, and the position of the anchor is due to shrinkage of mortar during the casting process. There was a problem in that a separate anchor fastening hole must be drilled in the foundation when the foundation is installed because it is not precisely controlled, and this causes a lot of air consumption.
더욱이 종래에는 토대 설치후 벽체 시공 후 벽체로 인하여 구획된 공간에 각각 난방 배관 설치작업을 하였으므로, 난방 배관 설치과정에서 시멘트몰탈의 평탄화를 오로지 수작업에 의존하여야 하였으므로 정밀한 평탄화가 불가능할 뿐 아니라 작업에도 오랜 시간이 소요되는 문제점이 있었다.Furthermore, in the past, heating pipes were installed in the space partitioned by the wall after the foundation was installed. Therefore, the flattening of cement mortar had to be relied only on manual work during the heating pipe installation process. There was an issue that took place.
또한, 테라스나 데크를 별도로 설치하였으므로 이를 위한 기둥설치과정이 필요하므로 작업에 시간과 인력이 많이 소요되는 문제점이 있었다.
In addition, since the terrace or deck is installed separately, a pillar installation process is required for this, which requires a lot of time and manpower.
한편, 상기한 기초 시공 등을 포함하여 콘크리트를 일정한 모양과 크기로 형성하는 데 사용되는 거푸집 구조에 대한 선행기술을 대한민국 등록특허 10-0897501호를 참조하여 살펴본다.On the other hand, the prior art for the formwork structure used to form a concrete in a certain shape and size, including the above-described basic construction will be described with reference to Republic of Korea Patent Registration 10-0897501.
상기한 대한민국 등록특허 10-0897501호에서는 연결케이블을 통해서 거푸집을 지지한 구성이 개시되었다.In the Republic of Korea Patent Registration No. 10-0897501 discloses a configuration for supporting the formwork through a connecting cable.
상기에서 연결케이블은 거푸집의 양측에 설치되는 지지빔을 관통하여 거푸집 고정 장치에 고정되며, 상기한 거푸집 고정 장치는 거푸집측 고정부재와 반대측 이탈방지부재측 고정 부재를 서로 다른 방향 나사산이 형성된 간격조절부재로 나사결합시켜 놓고, 상기 이탈방지부재는 다수의 조각으로 절개형성된 이탈방지콘을 콘 삽입부에 삽입하여 와이어를 고정하도록 하며, 상기 콘 삽입부가 이탈방지부재측 고정부재내부로 삽입되도록 한 것이다.In the above connection cable is fixed to the formwork fixing device through the support beams installed on both sides of the formwork, the formwork fixing device is the gap-side adjustment member formed in the direction of the fixing member and the fixing member on the opposite side of the separation prevention member side Screwed to the member, the release preventing member is to insert the escape prevention cone cut into a plurality of pieces to the cone insert to secure the wire, the cone insert is to be inserted into the release preventing member side fixing member. .
이와 같은 종래 구성에 의하면 와이어를 거푸집과 복수개 고정부재와 간격조절부재 및 이탈방지부재 내부로 관통시킨 후 이탈방지콘을 콘 삽입부로 삽입하고, 간격조절부재를 회전시키면 와이어가 팽팽하게 당겨지고, 거푸집을 해체하고자 할 경우 간격조절부재를 반대방향으로 회전시키면 와이어의 장력이 제거되어 거푸집의 해체가 가능하게 된다.According to such a conventional configuration, after penetrating the wire into the formwork, the plurality of fixing members, the gap adjusting member, and the separation preventing member, the separation preventing cone is inserted into the cone insertion portion, and the wire is pulled tightly by rotating the gap adjusting member. If you want to dismantle the rotation of the spacing member in the opposite direction to remove the tension of the wire is possible to dismantle the formwork.
그러나, 상기한 종래의 와이어 고정구조에 의하면 실제 와이어의 고정이 이탈방지콘과의 마찰력에 의존하고 있기 때문에 사용 중 와이어의 장력이 해제되어 거푸집이 견고하게 위치고정하지 못하게 되는 문제점이 있었고, 이탈방지콘이 다수개로 조각된 형태로 형성되므로 사용 중 이탈방지콘의 조각이 분실되거나 이탈되는 문제점이 발생되며, 부품 수가 많은 문제점이 있었다.However, according to the conventional wire fixing structure, since the actual fixing of the wire depends on the friction force with the release preventing cone, the tension of the wire is released during use, so that the formwork cannot be firmly fixed. Since the cone is formed in the form of a plurality of pieces, the problem that the pieces of the departure-avoidance cone is lost or detached during use, there is a problem in the number of parts.
상기한 문제점을 해결하기 위한 본 발명의 목적은 기초를 시공하는 과정에서 토대를 기초와 함께 설치하고, 데크 혹은 테라스를 위한 기초도 함께 시공하여 공기를 단축시키고, 이러한 기초시공을 위하여 거푸집도 조립 및 분해가 간단하도록 하면서 구성이 간단하도록 개선한 건축물의 기초 시공 방법 및 이를 위한 거푸집을 제공하는 데 있다.An object of the present invention for solving the above problems is to install the foundation along with the foundation in the process of constructing the foundation, and also to shorten the air by installing the foundation for decks or terraces, assembling formwork for such foundation construction and It is to provide a basic construction method and formwork for the structure improved to simplify the disassembly and to simplify the configuration.
상기한 목적을 달성하기 위한 본 발명의 특징은, 바닥 평탄화작업 후, 토대를 건축물의 형상 및 설치위치에 따른 콘크리트 타설 위치 및 모양에 맞게 바닥면에 수직으로 설치되는 수직바에 의하여 정해진 높이로 수평 설치하고, 상기한 토대의 외곽을 따라 거푸집을 설치한 후, 각종 배관을 설치하고 콘크리트를 타설하여 양생하며, 양생이 종료된 후에는 거푸집을 제거하여 기초공사를 완료한다.A feature of the present invention for achieving the above object is, after the floor planing operation, the foundation is installed horizontally to a predetermined height by a vertical bar installed vertically on the floor according to the concrete placement position and shape according to the shape and installation location of the building After the formwork is installed along the periphery of the foundation, various pipes are installed and concrete is cured, and after the curing is completed, the formwork is removed to complete the foundation work.
한편, 상기한 기초공사 과정에서 거푸집 설치 과정에서 데크 혹은 테라스의 위치에도 거푸집을 동시에 설치하여 콘크리트를 타설하되, 상기한 콘크리트 타설과정에서 데크 혹은 테라스의 콘크리트 타설면은 건축물의 외측을 향해서 하향 경사지도록 하면서 종단에 배수홈이 더 형성되도록 한다.On the other hand, in the above-mentioned basic construction process in the formwork installation process to install the formwork on the deck or terrace at the same time to place the concrete, but in the above concrete installation process, the concrete placing surface of the deck or terrace is inclined downward toward the outside of the building While the drain groove is formed at the end.
이때 배수홈은 외관을 위하여 양측부로 배수가 이루어지도록 형성한다.
At this time, the drain groove is formed to be drained to both sides for the appearance.
그리고, 상기한 기초공사를 위한 거푸집은 우선, 거푸집을 형성하는 다수개의 패널, 상기한 패널을 수직으로 지지하는 수직지지대, 대향되는 패널과 상기 패널에 설치된 수직 지지대를 관통하는 와이어, 상기한 수직 지지대에 설치되며 와이어가 고정되는 고정부재로 구성되며, 상기한 고정부재는 거푸집에 밀착설치되며 중심에 와이어 관통공이 천공된 고정브라켓과, 상기한 고정브라켓에 회전가능하도록 설치되어 거푸집과 수평하게 위치되며 중심에 와이어 관통공이 천공된 조절레버, 상기한 조절레버의 회전위치를 고정하는 고정수단으로 구성되며, 상기한 조절레버와 고정수단의 고정예로는 조절레버의 종단에 나사홈이 형성되어 고정브라켓의 외측에서 내주면에 조절레버의 나사홈과 대응되는 나사홈이 형성된 고정수단을 조여서 조절레버의 위치를 고정한다.In addition, the formwork for the foundation work, first, a plurality of panels forming the formwork, a vertical support for vertically supporting the panel, a wire passing through the opposing panel and the vertical support installed on the panel, the vertical support The fixing member is installed in the fixed member is fixed to the wire, the fixing member is installed in close contact with the formwork, the fixing bracket with a wire through-hole perforated in the center, and installed to be rotatable to the fixing bracket is positioned horizontally with the formwork. It consists of a control lever for puncturing a wire through-hole in the center, the fixing means for fixing the rotation position of the control lever, the fixing lever and the fixing means of the fixing means is a screw groove is formed at the end of the control lever fixed bracket Tightening the fixing means formed with the screw groove corresponding to the screw groove of the control lever on the inner peripheral surface of the Value is fixed.
그리고, 상기한 조절레버에는 와이어 관통공의 측부에 와이어를 감아서 고정할 수 있는 와이어 지지부재가 더 형성되어, 와이어 관통공을 관통한 와이어의 종단을 와이어 지지부재에 권취한 후 조절레버를 회전시켜 와이어가 적당한 장력을 갖도록 한다.Further, the control lever is further formed with a wire support member that can be fixed by winding the wire on the side of the wire through-hole, winding the end of the wire through the wire through-hole to the wire support member to rotate the control lever So that the wire has the proper tension.
한편, 상기한 거푸집에는 수직으로 설치되는 패널의 하부에 지면에 대하여 수평하게 위치되며 선단은 패널과 일체로 체결되는 수평지지대가 더 설치되어 패널이 지면에 대하여 쉽게 수직위치를 유지할 수 있도록 한다.On the other hand, the formwork is positioned horizontally with respect to the ground at the bottom of the panel is installed vertically, the front end is further provided with a horizontal support that is integrally fastened with the panel so that the panel can easily maintain a vertical position with respect to the ground.
이상과 같이 구성된 본 발명에 의하면, 기초시공과정에서 토대를 함께 매설하므로, 이후 벽체시공과정에서 벽체를 토대 상에 바로 올리면 되므로 작업공정이 종래에 비하여 대폭 감소되는 효과가 있다.According to the present invention configured as described above, since the foundation is embedded together in the basic construction process, since the wall is placed directly on the foundation in the wall construction process, there is an effect that the work process is greatly reduced as compared with the prior art.
더욱이, 상기한 토대를 먼저 시공한 후 거푸집을 설치하므로 거푸집 설치과정에서 거푸집을 토대를 따라 배치하기만 하면 되므로 거푸집 설치과정이 대폭 단축되는 효과가 있다.Moreover, since the formwork is installed after the foundation is installed first, the formwork installation process is greatly shortened because only the formwork is disposed along the foundation during the formwork installation process.
또한, 기초시공과정에서 테라스 또는 데크설치용 기초까지 함께 시공하게 되므로 작업성이 개선되는 효과가 있다.In addition, since the construction work up to the terrace or deck installation foundation in the basic construction process has the effect of improving workability.
더욱이 기초를 형성한 후 벽체를 시공하지 않고 필요한 위치에 난방배관을 설치하므로 난방배관 작업 후 콘크리트를 타설시 기계를 이용하여 평탄화가 가능하게 되므로 작업성이 대폭 개선되는 효과가 있다.In addition, since the heating pipe is installed in the required position after constructing the foundation, the workability is greatly improved since the flattening is possible by using the machine when the concrete is poured after the heating pipe work.
또한, 거푸집을 와이어로 고정하고, 상기한 와이어를 고정하며 적당한 장력을 갖도록 하는 수단의 구성이 간단하여 거푸집의 설치 및 해체가 용이한 효과가 있으며, 와이어 고정을 위한 구성이 간단하여 와이어 고정수단의 제조비용 및 시간이 감소되는 효과가 있다.In addition, since the configuration of the means for fixing the formwork with a wire, fixing the wire and having a suitable tension is simple, there is an effect that the installation and disassembly of the formwork is easy, and the structure for fixing the wire is simple, The manufacturing cost and time is reduced.
그리고, 상기한 토대가 바닥면에 수직바를 통해서 설치되고 콘크리트 타설과정에서 콘크리트에 일부가 묻힌 상태로 일체로 설치되므로 지진에도 안전한 특성이 있다.In addition, the foundation is installed through a vertical bar on the bottom surface and is integrally installed in a state where a part of the concrete is buried in the concrete pouring process, so it is safe even in earthquakes.
도 1은 본 발명에 따른 기초 시공과정에서 콘크리트 몰탈 투입 전을 나타내는 도면
도 2는 본 발명에 따른 기초 시공과정에서 콘크리트 몰탈 투입 후를 나타내는 도면
도 3은 본 발명에 따른 기초의 단면구조를 나타내는 단면도
도 4는 본 발명에 따른 데크 혹은 테라스부분의 콘크리트 타설면을 나타내는 측면도
도 5는 본 발명에 따른 와이어 고정부재를 나타내는 사시도1 is a view showing before the concrete mortar input in the basic construction process according to the present invention
2 is a view showing after the concrete mortar input in the basic construction process according to the present invention
3 is a cross-sectional view showing a cross-sectional structure of the foundation according to the present invention
Figure 4 is a side view showing the concrete pouring surface of the deck or terrace portion according to the present invention
5 is a perspective view showing a wire fixing member according to the present invention
상기한 목적을 달성하기 위한 본 발명의 실시예를 하기에서 첨부된 도면을 참조하여 보다 상세하게 살펴본다.An embodiment of the present invention for achieving the above object will be described in more detail with reference to the accompanying drawings.
우선, 건축물의 기초 시공 방법을 살펴본다.First, the basic construction method of the building will be examined.
도 1에 나타내는 바와 같이, 바닥 평탄화작업 후, 건축물의 설계도에 따라 토대(200)를 바닥면(300) 상에 위치되는 설치프레임(400)을 이용하여 수평으로 설치한 뒤, 거푸집(100)을 상기한 토대(200)의 외곽을 따라 콘크리트 타설 위치 및 모양에 맞게 배치하고, 거푸집(100) 내부에는 각종 배관(930)을 설치한 후 도 2에 나타내는 바와 같이 콘크리트(600)를 타설하여 양생하며, 양생이 종료된 후에는 거푸집(100)을 제거하여 기초공사를 완료하고, 기초의 양생이 완료되면 그 상부에 바로 도 3에 나타내는 바와 같이 난방배관(500)을 시공한다.As shown in FIG. 1, after the floor planing operation, the
한편, 상기한 거푸집(100)과 토대(200) 설치 및 콘크리트(600) 타설 과정에서 데크 혹은 테라스(700) 부분도 함께 시공을 하며, 상기한 데크 혹은 테라스(700) 부분은 다수개의 프레임(720)을 서로 이격시켜 배치함으로서 상부에 데크 혹은 테라스 형성용 목재를 설치할 수 있도록 한다.On the other hand, during the installation of the
또한 상기한 콘크리트 타설 과정에서 도 4에 나타내는 바와 같이 데크 혹은 테라스(700) 부분 콘크리트의 상부면은 건축물의 외측을 향해서 하향 경사지도록 성형하여 건축물 완성 후 빗물이 자연스럽게 흘러내릴 수 있도록 하고, 데크 혹은 테라스의 외측 종단에는 측면으로 배수홈(D)을 형성하여 빗물이 흘러내리면서 건축물의 전방으로 흘러내려서 외관을 해치지 않도록 한다.In addition, as shown in FIG. 4 in the above concrete pouring process, the upper surface of the concrete part of the deck or
그리고, 상기에서 설치프레임(400)은 지면에 수직으로 설치되는 수직바(410)와 상기한 수직바(410)의 상단에 지면에 대하여 수평으로 설치되는 수평바(420)로 구성되며, 상기한 수직바(410)는 토대(200)가 수평을 유지하도록 하며, 수평바(420)는 토대(200)의 하부로 설치되어 콘크리트 타설시 타설면이 다른 부분보다 다소 낮은 화장실,현관 등의 타설면 높이를 조절하는 데 사용된다.In addition, the
또한, 상기한 토대(200)는 중공부가 형성된 사각바를 사용하므로 그 상부면이 수평을 유지할 수 있게 되고 콘크리트 타설과정에서 콘크리트의 일부가 상기한 사각바의 중공부로 투입되므로 콘크리트와 결합강도도 향상되는 효과가 있다.In addition, since the
도면 중 미설명부호 910은 벽체를 나타내고, 920은 콘크리트 타설용 철근을 나타낸다.
In the figure,
한편, 상기한 기초공사를 위한 거푸집를 보다 구체적으로 살펴본다.On the other hand, look at the formwork for the above-mentioned basic construction in more detail.
본 발명에 따른 거푸집는, 거푸집(100)을 형성하는 다수개의 패널(110), 상기한 패널(110)을 수직으로 지지하는 수직지지대(120), 대향하는 복수개의 패널(110)과 상기 패널(110)에 설치된 수직지지대(120)를 관통하는 와이어(130), 상기한 수직지지대(120)에 설치되며 와이어(130)가 고정되는 고정부재(140)로 구성된다.Formwork according to the present invention, a plurality of
한편, 상기한 거푸집(100)에는 수직으로 설치되는 패널(110)의 하부에 지면에 대하여 수평하게 위치되며 선단은 패널(110) 혹은 수직지지대(120)와 일체로 체결되는 수평지지대(150)가 더 설치되어 패널(110)이 지면에 대하여 쉽게 수직위치를 유지할 수 있도록 한다.On the other hand, the
상기에서 고정부재(140)는 도 5에 나타내는 바와 같이 수직 고정부(142)의 양종단에 수평돌출부(143)가 형성되어 'ㄷ'형으로 형성되고 수직 고정부(142)의 중심에 와이어 관통공(142a)이 천공되어 수직 고정부(142)가 수직지지대(120)에 밀착설치되는 고정브라켓(144)과, 상기한 고정브라켓(144)의 복수개 수평돌출부(143)에 수직으로 회전가능하도록 설치되어 수직지지대(120)와 수평하게 위치되며 중심에 와이어 관통공(146a)이 천공된 조절레버(146), 상기한 조절레버(146)의 회전위치를 고정하는 고정수단(148)으로 구성되며, 상기한 조절레버(146)와 고정수단(148)의 고정예로는 조절레버(146)의 종단에 나사홈이 형성되어 고정브라켓(144)의 외측에서 내주면에 조절레버(146)의 나사홈과 대응되는 나사홈이 형성된 고정수단(148)을 조여서 조절레버(146)의 위치를 고정한다.As shown in FIG. 5, the
그리고, 상기한 조절레버(146)에는 와이어 관통공(146a)의 측부에 와이어(130)를 감아서 고정할 수 있는 고리형 와이어 지지부재(149)가 더 형성되어, 와이어 관통공(146a)을 관통한 와이어(130)의 종단을 와이어 지지부재(149)에 권취한 후 조절레버(146)를 회전시켜 와이어(130)가 적당한 장력을 갖도록 한다.In addition, the
100 : 거푸집 110 : 패널
120 : 수직지지대 130 : 와이어
140 : 고정부재 200 : 토대
300 : 바닥면 400 : 설치프레임
600 : 콘크리트 700 : 데크 혹은 테라스100: die 110: panel
120: vertical support 130: wire
140: fixing member 200: foundation
300: floor 400: mounting frame
600 Concrete 700 Deck or Terrace
Claims (4)
건축물의 설계도에 따라 토대(200)를 바닥면(300)에 수직으로 설치되는 수직바(410)를 이용하여 수평으로 설치하고,
거푸집(100)을 상기 토대(200)의 외곽을 따라 콘크리트 타설 위치 및 모양에 맞게 배치하고,
거푸집(100) 내부에 각종 배관(930)을 설치하며,
콘크리트(600)를 타설하여 양생하고,
양생이 종료된 후에는 거푸집(100)을 제거하는 것을 특징으로 하는 건축물의 기초 시공 방법.After floor leveling,
The foundation 200 is installed horizontally using the vertical bar 410 installed vertically on the floor 300 according to the design of the building,
Place the formwork 100 in accordance with the concrete casting position and shape along the outer periphery of the base 200,
Install various pipes 930 in the formwork 100,
Curing by pouring concrete (600),
After curing is completed, the foundation construction method of the building, characterized in that to remove the formwork (100).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100055246A KR101220811B1 (en) | 2010-06-11 | 2010-06-11 | construction method for building and form |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100055246A KR101220811B1 (en) | 2010-06-11 | 2010-06-11 | construction method for building and form |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20110135496A true KR20110135496A (en) | 2011-12-19 |
KR101220811B1 KR101220811B1 (en) | 2013-01-11 |
Family
ID=45502412
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100055246A KR101220811B1 (en) | 2010-06-11 | 2010-06-11 | construction method for building and form |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101220811B1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101467308B1 (en) * | 2014-03-24 | 2014-12-01 | 동일건설(주) | Revetment Assembly and Construction Method Thereof |
KR200475858Y1 (en) * | 2012-06-26 | 2015-01-08 | 이병화 | Connection devices for Steel skeleton |
KR101884571B1 (en) | 2017-09-07 | 2018-08-01 | 김둘례 | Structure for Outer Wall of Building |
KR101884572B1 (en) | 2017-09-07 | 2018-08-29 | 김둘례 | Assembly External wall structure of a building |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102216972B1 (en) | 2019-04-19 | 2021-02-19 | 삼성물산 주식회사 | Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100821663B1 (en) | 2005-11-25 | 2008-04-11 | 근보건설주식회사 | Construction method of Top-down concrete slab |
KR200417368Y1 (en) * | 2006-01-10 | 2006-05-26 | 이강선 | Rebar and Piping Attachment Formwork |
KR100897501B1 (en) | 2008-12-22 | 2009-05-15 | 문경철 | Form fixing apparatus |
KR100949440B1 (en) | 2009-04-10 | 2010-03-25 | 윤정배 | Slab reinforced structure and the form of construction work of concrete structure |
-
2010
- 2010-06-11 KR KR1020100055246A patent/KR101220811B1/en active IP Right Grant
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200475858Y1 (en) * | 2012-06-26 | 2015-01-08 | 이병화 | Connection devices for Steel skeleton |
KR101467308B1 (en) * | 2014-03-24 | 2014-12-01 | 동일건설(주) | Revetment Assembly and Construction Method Thereof |
KR101884571B1 (en) | 2017-09-07 | 2018-08-01 | 김둘례 | Structure for Outer Wall of Building |
KR101884572B1 (en) | 2017-09-07 | 2018-08-29 | 김둘례 | Assembly External wall structure of a building |
Also Published As
Publication number | Publication date |
---|---|
KR101220811B1 (en) | 2013-01-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101220811B1 (en) | construction method for building and form | |
JP5737554B2 (en) | Seismic isolation foundation construction method | |
KR100873266B1 (en) | Prefabricated pillar structure | |
KR101990065B1 (en) | Joint of PC column using steel block | |
KR101978599B1 (en) | Apparatus for fixing gangform to the wall | |
US20120304564A1 (en) | System for Anchoring Precast Concrete Wall Columns to Foundations | |
KR200352506Y1 (en) | Supporting structure of mold | |
KR102065623B1 (en) | the improved yoke truss and the wall form structure using the same | |
KR101057167B1 (en) | Apparatus for reinforcing pile head and construction method of foundation using therof | |
KR101077971B1 (en) | Elementary Block for Supporting of Steel Pipe | |
JP5912194B1 (en) | Construction method of wooden building and basic member used in the construction method | |
KR200443097Y1 (en) | steel rest including insert | |
KR200142434Y1 (en) | Setting-up structure of angle | |
KR101322581B1 (en) | Spacer for fastening Reinforcement Bar and Hanger Bolt | |
JP2006002428A (en) | Reinforcing method of existing floor and base isolation method of existing building | |
KR200342718Y1 (en) | Euroform Raker System | |
KR20090122670A (en) | Ceiling-frame facility using bracket | |
JP2008115534A (en) | Coin laundry and its installation method | |
KR102546788B1 (en) | Slab Type Sleeve for installing Pipe | |
JP2006348480A (en) | Building and building forming method | |
KR200298097Y1 (en) | Mold supporting structure | |
JP4247175B2 (en) | Seismic reinforcement structure for existing buildings | |
JP2001193079A (en) | Work method for mat foundation | |
JP7182383B2 (en) | Building foundation construction method | |
CN211775201U (en) | Embedded pipeline bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20151022 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20180302 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20181211 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20191231 Year of fee payment: 8 |