KR20090114000A - Reinforcement structure for tunnel and reinforcement method using the same - Google Patents

Reinforcement structure for tunnel and reinforcement method using the same Download PDF

Info

Publication number
KR20090114000A
KR20090114000A KR1020080039737A KR20080039737A KR20090114000A KR 20090114000 A KR20090114000 A KR 20090114000A KR 1020080039737 A KR1020080039737 A KR 1020080039737A KR 20080039737 A KR20080039737 A KR 20080039737A KR 20090114000 A KR20090114000 A KR 20090114000A
Authority
KR
South Korea
Prior art keywords
tunnel
members
reinforcement
top end
lining concrete
Prior art date
Application number
KR1020080039737A
Other languages
Korean (ko)
Other versions
KR101007012B1 (en
Inventor
차응섭
Original Assignee
차응섭
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 차응섭 filed Critical 차응섭
Priority to KR1020080039737A priority Critical patent/KR101007012B1/en
Publication of KR20090114000A publication Critical patent/KR20090114000A/en
Application granted granted Critical
Publication of KR101007012B1 publication Critical patent/KR101007012B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

PURPOSE: A tunnel crown reinforcing structure and a tunnel crown reinforcing method using the same are provided to prevent the stress concentration and cracking of a crown of a tunnel. CONSTITUTION: A tunnel crown reinforcing structure is composed of plural anchor members(100), plural reinforcing bar arrangement members(200), and a lining concrete(300). The plural anchor members are installed in a crown of a tunnel(10). A hook is formed in the lower part of the anchor member. The plural reinforcing bar arrangement members are installed to be supported by being hanged at the hook of the anchor member. The anchor members and the reinforcing bar arrangement members are laid in the lining concrete.

Description

터널 천단부 보강 구조물 및 이를 이용한 터널 천단부 보강공법{REINFORCEMENT STRUCTURE FOR TUNNEL AND REINFORCEMENT METHOD USING THE SAME}Tunnel end reinforcement structure and tunnel end reinforcement method using same {REINFORCEMENT STRUCTURE FOR TUNNEL AND REINFORCEMENT METHOD USING THE SAME}

본 발명은 토목 분야에 관한 것으로서, 상세하게는 터널의 천단부를 보강하기 위한 구조 및 공법에 관한 것이다.The present invention relates to the field of civil engineering, and more particularly, to a structure and a method for reinforcing the top end of a tunnel.

터널은 지반을 관통하여 주위 토압에 저항하기 위한 구조물로서, 구조 전체가 일체로서 외력에 저항하므로, 일부분에 응력집중, 균열이 발생하는 경우, 구조적 안정성이 대단히 취약해진다는 문제가 있다.The tunnel is a structure for resisting the surrounding earth pressure through the ground, and since the whole structure is integrally resistant to external force, there is a problem that structural stability is very weak when stress concentration and cracking occur in a part.

특히, 도 1에 도시된 바와 같이, 터널(10)의 천단부(상측 단부)는 온도변화, 건조수축, 진동 등에 의한 응력집중이 발생하기 쉬운 부위라는 점, 라이닝 콘크리트(1)가 밀실하게 타설되기 어렵다는 점 등의 이유로 균열이 자주 발생하며, 이는 상기와 같은 터널 전체 구조의 안정성에 영향을 미치게 된다.In particular, as shown in Figure 1, the top end (upper end) of the tunnel 10 is a site where stress concentration is likely to occur due to temperature changes, drying shrinkage, vibration, etc., the lining concrete 1 is placed firmly Cracks frequently occur for reasons such as being difficult to do, which affects the stability of the entire tunnel structure as described above.

따라서 터널의 천단부를 효율적으로 보강하기 위한 구조에 관한 연구가 절실한 실정이었다.Therefore, the study on the structure for efficiently reinforcing the top end of the tunnel was urgently needed.

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 터널의 천단부의 응력집중 및 균열을 방지할 수 있도록 하는 터널 천단부 보강 구조물 및 이를 이용한 터널 천단부 보강공법을 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems, and an object of the present invention is to propose a tunnel top end reinforcing structure and a tunnel top end reinforcing method using the same to prevent stress concentration and cracking at the top end of the tunnel. .

본 발명은 상술한 바와 같은 목적을 달성하기 위하여, 터널(10)의 천단부에 간격을 두고 설치됨과 아울러, 하단에 갈고리(101)가 형성된 복수의 앵커부재(100); 상기 복수의 앵커부재(100)의 갈고리(101)에 걸려 지지되도록 설치된 복수의 배근부재(200); 상기 앵커부재(100) 및 배근부재(200)가 매립되도록 타설된 라이닝 콘크리트(300);를 포함하는 터널 천단부 보강 구조물을 제시한다.The present invention, in order to achieve the above object, a plurality of anchor members 100 are provided with a gap at the top end of the tunnel 10, the hook 101 is formed at the bottom; A plurality of reinforcement members 200 installed to be caught and supported by the hooks 101 of the plurality of anchor members 100; The anchor member 100 and the reinforcement member 200 is presented to the tunnel top end reinforcement structure including;

상기 앵커부재(100)는 상기 터널(10)에 삽입설치된 볼트(110); 상기 볼트(110)의 하부 외주에 설치된 방수팩(120); 상기 볼트(110)의 하부에 결합한 너트(130); 상단이 상기 볼트(110) 또는 상기 너트(130)의 하부에 결합함과 아울러, 하단에 상기 갈고리(101)가 형성된 연장부(140);를 포함하는 것이 바람직하다.The anchor member 100 is a bolt 110 inserted into the tunnel 10; Waterproof pack 120 installed on the lower outer circumference of the bolt 110; Nut 130 coupled to the lower portion of the bolt 110; It is preferred that the upper end is coupled to the lower portion of the bolt 110 or the nut 130, the extension portion 140 is formed with the hook 101 at the bottom.

상기 너트(130)는 상기 볼트(110)가 삽입되는 상부영역과 상기 연장부(140)가 삽입되는 하부영역을 분리하도록 심부에 분리부(132)를 구비한 것이 바람직하다.The nut 130 is preferably provided with a separating portion 132 in the core portion to separate the upper region into which the bolt 110 is inserted and the lower region into which the extension 140 is inserted.

상기 터널(10)의 천단부 벽면에 설치된 배수시트(20); 상기 배수시트(20)의 외면에 설치된 방수시트(30);를 더 포함하고, 상기 방수팩(120)은 상기 방수시 트(30)의 외면에 설치된 것이 바람직하다.A drain sheet 20 installed on the top wall of the tunnel 10; It further comprises a; waterproof sheet 30 installed on the outer surface of the drain sheet 20, the waterproof pack 120 is preferably installed on the outer surface of the waterproof sheet (30).

상기 너트(130)의 상단에는 측방으로 고정부(131)가 연장형성되고, 상기 고정부(131)는 상기 방수팩(120)에 삽입고정된 것이 바람직하다.The upper end of the nut 130, the fixing portion 131 is formed extending in the side, the fixing portion 131 is preferably inserted into the waterproof pack 120 is fixed.

상기 복수의 배근부재(200)는 와이어 메쉬(210)를 포함하는 구조에 의해 구현될 수 있다.The plurality of reinforcement members 200 may be implemented by a structure including a wire mesh 210.

상기 복수의 배근부재(200)는 상기 복수의 앵커부재(100)에 걸려 지지되는 복수의 배력철근(220); 상기 복수의 배력철근(220)과 실질적인 직각을 이루도록 설치된 복수의 주철근(221);을 포함하는 것이 바람직하다.The plurality of reinforcement member 200 is a plurality of reinforcing bars 220 is supported by the plurality of anchor members 100; It is preferable to include; a plurality of main reinforcing bars 221 installed to form a substantially right angle with the plurality of lifting bars (220).

본 발명은 상기 터널 천단부 보강 구조물을 시공하기 위한 터널 천단부 보강공법으로서, 상기 터널(10)의 천단부 벽면에 복수의 앵커부재 설치공(11)을 천공하는 단계; 상기 복수의 앵커부재 설치공(11)에 상기 복수의 앵커부재(100)를 설치하는 단계; 상기 복수의 앵커부재(100)에 걸려 지지되도록 상기 복수의 배근부재(200)를 설치하는 단계; 상기 터널(10)의 길이방향으로 일정구간의 양단이 폐쇄되도록, 상기 라이닝 콘크리트(300)의 타설을 위한 거푸집(310)을 설치하는 단계; 상기 거푸집(310)의 폐쇄된 일단부 중 상부에 타설공(311)을 형성하고, 상기 타설공(311)을 통해 상기 라이닝 콘크리트(300)를 타설하는 라이닝 콘크리트 타설단계;를 포함하는 것을 특징으로 하는 터널 천단부 보강공법을 제시한다.The present invention is a tunnel top end reinforcing method for constructing the tunnel top end reinforcing structure, comprising: drilling a plurality of anchor member installation holes (11) on the top end wall of the tunnel (10); Installing the plurality of anchor members (100) in the plurality of anchor member installation holes (11); Installing the plurality of reinforcement members (200) so as to be caught and supported by the plurality of anchor members (100); Installing formwork (310) for placing the lining concrete (300) such that both ends of the predetermined section are closed in the longitudinal direction of the tunnel (10); And a lining concrete pouring step of forming a pouring hole 311 at an upper end of the closed end of the formwork 310 and pouring the lining concrete 300 through the pouring hole 311. The tunnel tip reinforcement method is presented.

상기 라이닝 콘크리트(300) 타설단계는 상기 타설공(311)에 파이프(320)를 삽입하여, 상기 파이프(320)의 개구를 상기 거푸집(310)의 폐쇄된 타단부에 위치시키는 단계; 상기 파이프(320)를 통해 상기 라이닝 콘크리트(300)를 타설하는 단계; 상기 파이프(320)를 점진적으로 후퇴하면서 상기 라이닝 콘크리트(300)를 타설하는 단계;를 포함하는 것이 바람직하다.The laying of the lining concrete 300 may include inserting a pipe 320 into the pouring hole 311 to position the opening of the pipe 320 at the other closed end of the formwork 310; Pouring the lining concrete (300) through the pipe (320); It is preferable to include; pouring the lining concrete 300 while gradually retreating the pipe 320.

상기 파이프(320)는 상기 배근부재(200)의 상부를 통해 가이드되는 것이 바람직하다.The pipe 320 is preferably guided through the upper portion of the reinforcement member 200.

본 발명은 터널의 천단부의 응력집중 및 균열을 방지할 수 있도록 하는 터널 천단부 보강 구조물 및 이를 이용한 터널 천단부 보강공법을 제시한다.The present invention proposes a tunnel top end reinforcing structure and a tunnel top end reinforcing method using the same to prevent stress concentration and cracking at the top end of the tunnel.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2 이하에 도시된 바와 같이, 본 발명에 의한 터널 천단부 보강 구조물은 기본적으로, 터널(10)의 천단부에 간격을 두고 설치됨과 아울러, 하단에 갈고리(101)가 형성된 복수의 앵커부재(100); 복수의 앵커부재(100)의 갈고리(101)에 걸려 지지되도록 설치된 복수의 배근부재(200); 앵커부재(100) 및 배근부재(200)가 매립되도록 타설된 라이닝 콘크리트(300);를 포함하여 구성된다.As shown in FIG. 2 or less, the tunnel end reinforcement structure according to the present invention is basically installed at intervals at the top end of the tunnel 10, and a plurality of anchor members having hooks 101 formed at the bottom thereof ( 100); A plurality of reinforcement members 200 installed to be caught and supported by the hooks 101 of the plurality of anchor members 100; Anchor member 100 and the reinforcement member 200 is lining concrete 300 is placed to be embedded; is configured to include.

즉, 터널(10)의 천단부에 앵커부재(100)를 복수 설치하고, 그 앵커부재(100)에 의해 지지되도록 배근부재(200)를 복수 설치한 후, 이들이 매립되도록 라이닝 콘크리트(300)를 타설함으로써, 앵커-배근-콘크리트의 복합구조에 의해 터널의 천단부가 보강되도록 한 것이다.That is, a plurality of anchor members 100 are installed at the top end of the tunnel 10, and a plurality of back members 200 are installed to be supported by the anchor member 100, and then the lining concrete 300 is embedded so that they are embedded. By pouring, the top end of the tunnel is reinforced by the composite structure of anchor-reinforcement-concrete.

이러한 구조를 취하는 경우, 온도변화, 건조수축, 진동 등에 의한 유해 응력이 발생하더라도, 배근부재(200) 및 앵커부재(100)를 통해 터널(10) 전 영역으로 그 응력이 분산될 것인바 응력집중을 방지할 수 있고, 이에 따라 균열의 발생 가능성을 대폭 줄일 수 있다는 효과가 있다.In this structure, even if harmful stresses occur due to temperature change, drying shrinkage, vibration, etc., the stress will be distributed to the entire area of the tunnel 10 through the reinforcement member 200 and the anchor member 100. Can be prevented, and thus the possibility of cracking can be greatly reduced.

또한, 앵커부재(100)의 하단에 갈고리(101)를 형성하고, 이에 배근부재(200)가 설치되도록 하므로, 터널(10) 천단부의 높이가 높더라도 배근부재(200)의 설치작업을 용이하게 할 수 있다는 효과를 추가로 얻을 수 있다.In addition, since the hook 101 is formed at the lower end of the anchor member 100 and the reinforcement member 200 is installed thereon, even if the height of the top end of the tunnel 10 is high, the installation work of the reinforcement member 200 is easy. You can get additional effects.

앵커부재(100)는 터널(10)의 천단부에 간격을 두고 설치되는 구성으로서, 배근부재(200)의 지지를 위해 하단에 갈고리(101)가 형성된 구조이면, 어느 것이나 관계없다.The anchor member 100 is provided at intervals at the top end of the tunnel 10, and any structure may be used as long as the hook 101 is formed at the lower end to support the back muscle member 200.

다만, 도 4에 도시된 바와 같이, 터널(10)의 설치공(11)에 삽입설치된 볼트(110); 볼트(110)의 하부 외주에 설치된 방수팩(120); 볼트(110)의 하부에 결합한 너트(130); 상단이 볼트(110) 또는 너트(130)의 하부에 결합함과 아울러, 하단에 갈고리(101)가 형성된 연장부(140);를 포함하는 구조를 취하는 경우, 앵커부재(100)의 설치를 위해 터널(10)에 형성된 설치공(11)을 통해 지하수가 유출되는 것을 방지할 수 있다는 측면에서 더욱 바람직하다.4, the bolt 110 inserted into the installation hole 11 of the tunnel 10; Waterproof pack 120 installed on the lower outer circumference of the bolt 110; Nut 130 coupled to the lower portion of the bolt 110; When the upper portion is coupled to the lower portion of the bolt 110 or nut 130, and the extension portion 140 is formed with a hook 101 at the bottom; taking a structure including, for the installation of the anchor member 100 It is more preferable in terms of preventing groundwater from flowing out through the installation hole 11 formed in the tunnel 10.

나아가, 너트(130)에서 볼트(110)가 삽입되는 상부영역과 연장부(140)가 삽입되는 하부영역을 분리하도록 심부에 분리부(132)가 형성된 구조를 취하는 경우, 위 지하수의 유출을 더욱 확실하게 방지할 수 있다는 효과가 있다.Furthermore, in the case where the separating part 132 is formed in the core portion so as to separate the upper region into which the bolt 110 is inserted from the nut 130 and the lower region into which the extension 140 is inserted, the outflow of the groundwater is further increased. There is an effect that can be reliably prevented.

일반적으로, 터널(10)의 천단부 벽면에는 배수시트(20)가 설치되고, 그 외면에는 방수시트(30)가 설치되는데, 위 구조에서 방수팩(120)은 이러한 방수시트(30)의 외면에 열융착 등의 방식으로 설치되는 것이 더욱 우수한 방수효과를 얻을 수 있다는 측면에서 바람직하다.In general, the drainage sheet 20 is installed on the top end wall surface of the tunnel 10, the waterproof sheet 30 is installed on the outer surface, the waterproof pack 120 in the above structure on the outer surface of the waterproof sheet 30 It is preferable to install in a manner such as thermal fusion in terms of obtaining a more excellent waterproof effect.

나아가, 너트(130)의 상단에 측방으로 고정부(131)가 연장형성되고, 이 고정부(131)가 방수팩(120)에 삽입고정된 구조를 취하는 경우, 방수효과와 더불어 너트(130) 및 연장부재(140)의 견고한 결합구조를 이룰 수 있다는 측면에서 더욱 바람직하다.Furthermore, when the fixing part 131 is extended to the upper side of the nut 130, and the fixing part 131 has a fixed structure inserted into the waterproof pack 120, the nut 130 and the waterproof effect More preferred in terms of achieving a rigid coupling structure of the extension member 140.

복수의 배근부재(200)는 앵커부재(100)의 갈고리(101)에 의해 지지되고, 라이닝 콘크리트(300)에 매립되어 터널(10)의 천단부를 보강할 수 있는 구조이면, 어느 것이나 가능하다.The plurality of reinforcement members 200 may be any structure as long as they are supported by the hooks 101 of the anchor members 100 and embedded in the lining concrete 300 to reinforce the top ends of the tunnels 10.

도 2는 배근부재(200)로서 와이어 메쉬(210)가 적용된 경우의 실시예를 도시한 것이고, 도 3은 철근이 사용된 경우의 실시예를 도시한 것이다.Figure 2 shows an embodiment when the wire mesh 210 is applied as the reinforcement member 200, Figure 3 shows an embodiment when the reinforcing bar is used.

도 3의 실시예의 경우, 배근부재(200)로서 앵커부재(100)에 걸려 지지되는 복수의 배력철근(220); 복수의 배력철근(220)과 실질적인 직각을 이루도록 설치된 복수의 주철근(221);을 포함하여 구성되므로, 더욱 우수한 보강효과를 얻을 수 있다는 측면에서 바람직하고, 필요에 따라 보조철근(222) 등을 추가로 설치할 수 있다.In the case of the embodiment of Figure 3, a plurality of lifting rebar 220 is supported by the anchor member 100 as the reinforcement member 200; Since a plurality of main reinforcing bars (221) installed to form a substantially right angle with the plurality of lifting reinforcing bars 220; is configured to include, it is preferable in terms of obtaining a superior reinforcing effect, and additional auxiliary reinforcing bars (222), etc. as necessary Can be installed as

본 발명에 의한 터널 천단부 보강공법은 위와 같은 터널 천단부 보강 구조물을 시공하기 위한 것으로서, 터널(10)의 천단부 벽면에 복수의 앵커부재 설치공(11)을 천공하는 단계; 복수의 앵커부재 설치공(11)에 복수의 앵커부재(100)를 설치하는 단계; 복수의 앵커부재(100)에 걸려 지지되도록 복수의 배근부재(200)를 설치하는 단계; 터널(10)의 길이방향으로 일정구간의 양단이 폐쇄되도록, 라이닝 콘크리트(300)의 타설을 위한 거푸집(310)을 설치하는 단계; 거푸집(310)의 폐쇄된 일단부 중 상부에 타설공(311)을 형성하고, 타설공(311)을 통해 상기 라이닝 콘크리트(300)를 타설하는 라이닝 콘크리트 타설단계;를 포함하여 구성된다.Tunnel top end reinforcement method according to the present invention is to construct a tunnel end end reinforcement structure as described above, the step of drilling a plurality of anchor member installation hole 11 on the top end wall surface of the tunnel (10); Installing a plurality of anchor members 100 in the plurality of anchor member installation holes 11; Installing a plurality of reinforcement members 200 so as to be caught and supported by the plurality of anchor members 100; Installing formwork 310 for placing lining concrete 300 so that both ends of the predetermined section are closed in the longitudinal direction of the tunnel 10; Forming the pouring hole 311 in the upper end of the closed end of the formwork 310, the lining concrete pouring step of pouring the lining concrete 300 through the pouring hole (311); is configured to include.

즉, 라이닝 콘크리트(300)의 타설을 위한 거푸집(310)을 설치함에 있어서, 도 6에 도시된 바와 같이, 터널(10)의 길이방향으로 일정구간의 양단이 폐쇄되도록 하고, 거푸집(310)의 폐쇄된 일단부 중 상부에 타설공(311)을 형성하고, 타설공(311)을 통해 라이닝 콘크리트(300)를 타설하도록 한 것이다.That is, in installing the formwork 310 for placing the lining concrete 300, as shown in Figure 6, so that both ends of a certain section in the longitudinal direction of the tunnel 10 is closed, of the formwork 310 It is to form a pour hole 311 in the upper end of the closed one, and to pour the lining concrete 300 through the pour hole (311).

따라서 콘크리트가 거푸집(310)의 위 폐쇄된 구간 내에만 타설되므로, 밀실한 구조를 얻을 수 있다는 효과가 있다.Therefore, since concrete is poured only within the closed section above the formwork 310, there is an effect that a tight structure can be obtained.

나아가, 도 6,7에 도시된 바와 같이, 타설공(311)에 파이프(320)를 삽입하여, 파이프(320)의 개구를 상기 거푸집(310)의 폐쇄된 타단부에 위치시키고, 파이프(320)를 통해 라이닝 콘크리트(300)를 타설하는데, 파이프(320)를 점진적으로 후퇴하면서 라이닝 콘크리트(300)의 타설을 마감하는 것이 더욱 바람직하다.6 and 7, the pipe 320 is inserted into the pour hole 311 so that the opening of the pipe 320 is positioned at the other closed end of the formwork 310 and the pipe 320 is inserted into the pipe 320. In order to pour the lining concrete 300, it is more preferable to finish the pour of the lining concrete 300 while gradually retreating the pipe 320.

즉, 거푸집(310)의 타설공(311)으로부터 먼 부분(거푸집의 구석 부분)으로부터 콘크리트를 타설하여, 타설공(311)에 가까운 부분에서 타설작업을 마무리하도록 한 것이므로, 더욱 밀실한 콘크리트의 타설작업을 가능해지기 때문이다.That is, since the concrete is poured from a part far away from the casting hole 311 (the corner portion of the die) of the formwork 310, the casting work is finished at the portion close to the placing hole 311, so that the more concrete placing Because work becomes possible.

이와 같은 파이프(320)의 삽입 및 후진 구동은 거푸집(310)의 상면에 면접촉되면서 이루어지는 것보다, 위 배근부재(200)의 상부를 통해 가이드되도록 하는 것이 콘크리트의 밀실한 타설을 위해 더욱 바람직하다.Such insertion and reversal driving of the pipe 320 is more preferable for the tight casting of concrete to be guided through the upper part of the upper reinforcement member 200 than the surface contact with the upper surface of the formwork 310. .

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설 명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above is merely described with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above All of the technical ideas together with the technical idea of the base will be included in the scope of the present invention.

도 1은 종래의 터널의 단면도.1 is a cross-sectional view of a conventional tunnel.

도 2 이하는 본 발명의 실시예를 도시한 것으로서,Figure 2 below shows an embodiment of the present invention,

도 2는 보강 구조물의 제1실시예의 단면도.2 is a sectional view of a first embodiment of a reinforcing structure;

도 3은 보강 구조물의 제2실시예의 단면도.3 is a sectional view of a second embodiment of a reinforcing structure;

도 4는 앵커부재의 단면도.4 is a cross-sectional view of the anchor member.

도 5는 보강 구조물의 제2실시예의 저면도.5 is a bottom view of a second embodiment of a reinforcing structure.

도 6,7은 라이닝 콘크리트 타설작업의 공정도.6,7 is a process chart of the lining concrete pouring work.

**도면의 주요부분에 대한 부호의 설명**** Description of the symbols for the main parts of the drawings **

10 : 터널 11 : 앵커부재 설치공10 tunnel 11 anchor member installation hole

20 : 배수시트 30 : 방수시트20: drain sheet 30: waterproof sheet

100 : 앵커부재 101 : 갈고리100: anchor member 101: hook

110 : 볼트 120 : 방수팩110: bolt 120: waterproof pack

130 : 너트 140 : 연장부130: nut 140: extension

200 : 배근부재 210 : 와이어 메쉬200: reinforcement member 210: wire mesh

220 : 배력철근 221 : 주철근220: reinforced bar 221: cast iron

300 : 라이닝 콘크리트 310 : 거푸집300: lining concrete 310: formwork

311 : 타설공 320 : 파이프311: pour ball 320: pipe

Claims (10)

터널(10)의 천단부에 간격을 두고 설치됨과 아울러, 하단에 갈고리(101)가 형성된 복수의 앵커부재(100);A plurality of anchor members 100 installed at intervals at the top ends of the tunnels 10 and having hooks 101 formed at lower ends thereof; 상기 복수의 앵커부재(100)의 갈고리(101)에 걸려 지지되도록 설치된 복수의 배근부재(200);A plurality of reinforcement members 200 installed to be caught and supported by the hooks 101 of the plurality of anchor members 100; 상기 앵커부재(100) 및 배근부재(200)가 매립되도록 타설된 라이닝 콘크리트(300);를Lining concrete 300 is placed so that the anchor member 100 and the reinforcement member 200 is embedded; 포함하는 터널 천단부 보강 구조물.Tunnel end reinforcement structure comprising. 제1항에 있어서,The method of claim 1, 상기 앵커부재(100)는 The anchor member 100 상기 터널(10)에 삽입설치된 볼트(110);A bolt 110 inserted into the tunnel 10; 상기 볼트(110)의 하부 외주에 설치된 방수팩(120);Waterproof pack 120 installed on the lower outer circumference of the bolt 110; 상기 볼트(110)의 하부에 결합한 너트(130);Nut 130 coupled to the lower portion of the bolt 110; 상단이 상기 볼트(110) 또는 상기 너트(130)의 하부에 결합함과 아울러, 하단에 상기 갈고리(101)가 형성된 연장부(140);를The upper portion is coupled to the lower portion of the bolt 110 or the nut 130, and the extension portion 140 is formed with the hook 101 at the bottom; 포함하는 것을 특징으로 하는 터널 천단부 보강 구조물.Tunnel top end reinforcement structure comprising a. 제2항에 있어서,The method of claim 2, 상기 너트(130)는The nut 130 is 상기 볼트(110)가 삽입되는 상부영역과 상기 연장부(140)가 삽입되는 하부영역을 분리하도록 심부에 분리부(132)를 구비한 것을 특징으로 하는 터널 천단부 보강 구조물.Tunnel top end reinforcement structure, characterized in that provided with a separating portion 132 in the core to separate the upper region into which the bolt 110 is inserted and the lower region into which the extension 140 is inserted. 제2항에 있어서,The method of claim 2, 상기 터널(10)의 천단부 벽면에 설치된 배수시트(20);A drain sheet 20 installed on the top wall of the tunnel 10; 상기 배수시트(20)의 외면에 설치된 방수시트(30);를 더 포함하고,Further comprising; a waterproof sheet 30 installed on the outer surface of the drain sheet 20, 상기 방수팩(120)은 상기 방수시트(30)의 외면에 설치된 것을 특징으로 하는 터널 천단부 보강 구조물.The waterproof pack 120 is a tunnel top end reinforcement structure, characterized in that installed on the outer surface of the waterproof sheet (30). 제4항에 있어서,The method of claim 4, wherein 상기 너트(130)의 상단에는 측방으로 고정부(131)가 연장형성되고, 상기 고정부(131)는 상기 방수팩(120)에 삽입고정된 것을 특징으로 하는 터널 천단부 보강 구조물.Tunnel end reinforcement structure, characterized in that the fixing portion 131 is extended to the upper side of the nut 130, the fixing portion 131 is fixed to the waterproof pack 120. 제1항에 있어서,The method of claim 1, 상기 복수의 배근부재(200)는The plurality of muscle members 200 와이어 메쉬(210)를 포함하는 것을 특징으로 하는 터널 천단부 보강 구조물.Tunnel top end reinforcement structure comprising a wire mesh (210). 제1항에 있어서,The method of claim 1, 상기 복수의 배근부재(200)는The plurality of muscle members 200 상기 복수의 앵커부재(100)에 걸려 지지되는 복수의 배력철근(220);A plurality of lifting rebars 220 supported by the plurality of anchor members 100; 상기 복수의 배력철근(220)과 실질적인 직각을 이루도록 설치된 복수의 주철근(221);을A plurality of cast iron bars 221 installed to form a substantially right angle with the plurality of lifting bars 220; 포함하는 것을 특징으로 하는 터널 천단부 보강 구조물.Tunnel top end reinforcement structure comprising a. 제1항 내지 제7항 중 어느 한 항의 터널 천단부 보강 구조물을 시공하기 위한 터널 천단부 보강공법으로서, A tunnel tip end reinforcement method for constructing a tunnel end end reinforcement structure according to any one of claims 1 to 7, 상기 터널(10)의 천단부 벽면에 복수의 앵커부재 설치공(11)을 천공하는 단계;Drilling a plurality of anchor member installation holes (11) on the top end wall of the tunnel (10); 상기 복수의 앵커부재 설치공(11)에 상기 복수의 앵커부재(100)를 설치하는 단계;Installing the plurality of anchor members (100) in the plurality of anchor member installation holes (11); 상기 복수의 앵커부재(100)에 걸려 지지되도록 상기 복수의 배근부재(200)를 설치하는 단계;Installing the plurality of reinforcement members (200) so as to be caught and supported by the plurality of anchor members (100); 상기 터널(10)의 길이방향으로 일정구간의 양단이 폐쇄되도록, 상기 라이닝 콘크리트(300)의 타설을 위한 거푸집(310)을 설치하는 단계;Installing formwork (310) for placing the lining concrete (300) such that both ends of the predetermined section are closed in the longitudinal direction of the tunnel (10); 상기 거푸집(310)의 폐쇄된 일단부 중 상부에 타설공(311)을 형성하고, 상기 타설공(311)을 통해 상기 라이닝 콘크리트(300)를 타설하는 라이닝 콘크리트 타설 단계;를A lining concrete pouring step of forming a pouring hole 311 at an upper end of the closed end of the formwork 310 and pouring the lining concrete 300 through the pouring hole 311; 포함하는 것을 특징으로 하는 터널 천단부 보강공법.Tunnel top end reinforcement method comprising a. 제8항에 있어서,The method of claim 8, 상기 라이닝 콘크리트(300) 타설단계는The lining concrete 300 pouring step 상기 타설공(311)에 파이프(320)를 삽입하여, 상기 파이프(320)의 개구를 상기 거푸집(310)의 폐쇄된 타단부에 위치시키는 단계;Inserting a pipe (320) into the pour hole (311) to position the opening of the pipe (320) at the other closed end of the formwork (310); 상기 파이프(320)를 통해 상기 라이닝 콘크리트(300)를 타설하는 단계;Pouring the lining concrete (300) through the pipe (320); 상기 파이프(320)를 점진적으로 후퇴하면서 상기 라이닝 콘크리트(300)를 타설하는 단계;를Pouring the lining concrete 300 while gradually retracting the pipe 320; 포함하는 것을 특징으로 하는 터널 천단부 보강공법.Tunnel top end reinforcement method comprising a. 제9항에 있어서,The method of claim 9, 상기 파이프(320)는 상기 배근부재(200)의 상부를 통해 가이드되는 것을 특징으로 하는 터널 천단부 보강공법.The pipe 320 is a tunnel tip reinforcement method, characterized in that guided through the upper portion of the reinforcement member (200).
KR1020080039737A 2008-04-29 2008-04-29 Reinforcement structure for tunnel and reinforcement method using the same KR101007012B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080039737A KR101007012B1 (en) 2008-04-29 2008-04-29 Reinforcement structure for tunnel and reinforcement method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080039737A KR101007012B1 (en) 2008-04-29 2008-04-29 Reinforcement structure for tunnel and reinforcement method using the same

Publications (2)

Publication Number Publication Date
KR20090114000A true KR20090114000A (en) 2009-11-03
KR101007012B1 KR101007012B1 (en) 2011-01-12

Family

ID=41555286

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080039737A KR101007012B1 (en) 2008-04-29 2008-04-29 Reinforcement structure for tunnel and reinforcement method using the same

Country Status (1)

Country Link
KR (1) KR101007012B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112610254A (en) * 2020-12-11 2021-04-06 东北大学 Deep underground engineering large-deformation support control method based on cracking inhibition method
CN113090285A (en) * 2021-04-22 2021-07-09 中铁一局集团有限公司 Tunnel secondary lining reinforcing steel bar protective layer control and stress system conversion construction method
CN114753633A (en) * 2022-03-18 2022-07-15 五冶集团上海有限公司 Turnover bolt reinforcing method for preventing suspended mold from expanding

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102422895B1 (en) 2022-03-15 2022-07-20 고려정공주식회사 Waterproof anchor system for tunnels

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200149280Y1 (en) 1996-03-12 1999-06-15 어봉수 The fixing device of rock bolt
EP1046551B1 (en) * 1999-04-22 2003-06-18 TRW Occupant Restraint Systems GmbH & Co. KG Knee protection device
KR20050003726A (en) * 2003-07-04 2005-01-12 안태훈 The Construction Method of Dividing the Concrete lining into the top and bottom
KR100626820B1 (en) 2004-12-24 2006-09-21 서동현 Shallow overbuden tunnel construction method
KR100794228B1 (en) * 2005-10-20 2008-01-14 홍건영 Multi-use block, assistance implement used it and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112610254A (en) * 2020-12-11 2021-04-06 东北大学 Deep underground engineering large-deformation support control method based on cracking inhibition method
CN112610254B (en) * 2020-12-11 2022-02-15 东北大学 Deep underground engineering large-deformation support control method based on cracking inhibition method
CN113090285A (en) * 2021-04-22 2021-07-09 中铁一局集团有限公司 Tunnel secondary lining reinforcing steel bar protective layer control and stress system conversion construction method
CN113090285B (en) * 2021-04-22 2022-12-02 中铁一局集团有限公司 Tunnel secondary lining reinforcing steel bar protective layer control and stress system conversion construction method
CN114753633A (en) * 2022-03-18 2022-07-15 五冶集团上海有限公司 Turnover bolt reinforcing method for preventing suspended mold from expanding

Also Published As

Publication number Publication date
KR101007012B1 (en) 2011-01-12

Similar Documents

Publication Publication Date Title
KR100747661B1 (en) Mold-concrete composite Crossbeam and construction method using the same
CN102900168B (en) Splitting and assembling structure and assembling connecting method of assembled type concrete frame-shear wall
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR101007012B1 (en) Reinforcement structure for tunnel and reinforcement method using the same
KR100966144B1 (en) Rahmen bridge construction method with abutment socket and tendon
JP5229913B2 (en) Slope reinforcement method
KR101675441B1 (en) Integrated wall structure, form and manufacturing method for integrated wall structure
KR101038945B1 (en) A filling structure of upper part of a tunnel and its procedure
KR101066198B1 (en) Underground construction method of top-down with slurry walls
JP2007162266A (en) Two-step earth retaining wall and its construction method
KR100991341B1 (en) Precast Foundation and Pile Connection Structure between Precast Foundation and Pile
KR20060096706A (en) Deck suspension top-down method of sub-structure
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
KR101521558B1 (en) Underground wall construction method using the wall members
KR102447617B1 (en) Construction method of cast in place concrete pile
KR100860422B1 (en) Mold device for horizontal, vertical all style concrete construction
KR200395627Y1 (en) Concrete composite Crossbeam
KR20060127631A (en) Wall structure using precast concrete panel with rib rows
KR101215764B1 (en) A burial slab structure of an outer wall of an underground construction
KR101194866B1 (en) Rahmen bridge construction method using longitudinal and lateral steel member
JP5056534B2 (en) Structure installation method for water gradient floor
KR100664965B1 (en) Carbon-glass fiber composite concrete mold, its manufacturing method and construction method
KR20090044961A (en) Concrete elevator pit structure
JP5452805B2 (en) Precast concrete column member
KR20110006225U (en) Combination reinforcement

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140103

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150102

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20151223

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee