KR20050003726A - The Construction Method of Dividing the Concrete lining into the top and bottom - Google Patents

The Construction Method of Dividing the Concrete lining into the top and bottom Download PDF

Info

Publication number
KR20050003726A
KR20050003726A KR1020030045208A KR20030045208A KR20050003726A KR 20050003726 A KR20050003726 A KR 20050003726A KR 1020030045208 A KR1020030045208 A KR 1020030045208A KR 20030045208 A KR20030045208 A KR 20030045208A KR 20050003726 A KR20050003726 A KR 20050003726A
Authority
KR
South Korea
Prior art keywords
concrete lining
lining
concrete
secure
dividing
Prior art date
Application number
KR1020030045208A
Other languages
Korean (ko)
Inventor
안태훈
Original Assignee
안태훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 안태훈 filed Critical 안태훈
Priority to KR1020030045208A priority Critical patent/KR20050003726A/en
Publication of KR20050003726A publication Critical patent/KR20050003726A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Abstract

PURPOSE: A construction method of concrete lining by dividing into top and bottom is provided to secure the stability and economical efficiency of concrete lining and to decrease the section of a tunnel by reducing the thickness of concrete lining. CONSTITUTION: The construction method of concrete lining by dividing into top and bottom comprises the steps of pre-constructing lower concrete lining(2) on the basis of a lateral wall inflection point(4) when placing concrete lining and to secure a support point of upper concrete lining(1) as a fixed support for reducing the stress occurred on the upper concrete lining, and after curing the surface of the lower concrete lining, filling up a space between a waterproof film and the lining(2) with grouting materials under pressure to secure the enough subgrade reaction factor for a plan for restraining the transformation toward an excavation plane by placing upper concrete lining.

Description

상하 분할 콘크리트 라이닝 타설 공법{The Construction Method of Dividing the Concrete lining into the top and bottom}The Construction Method of Dividing the Concrete lining into the top and bottom}

본 발명은 도로 및 지하철 등 토목분야에 적용되는 터널 콘크리트 라이닝 공법에 관한 것으로 터널의 콘크리트 라이닝은 사용목적에 따라 구조체로서의 역학적 기능, 비배수형 터널에서의 내압기능 및 영구구조물로서의 내구성 확보 및 미관유지 기능 등을 요구한다.The present invention relates to a tunnel concrete lining method applied to civil engineering fields, such as roads and subways, the concrete lining of the tunnel according to the purpose of use, the mechanical function as a structure, the pressure-resistance function in the non-drained tunnel and the durability as a permanent structure and maintain the appearance And so on.

위와 같은 목적을 위해 시공되는 콘크리트 라이닝에 대한 종래의 설계 및 시공상에서 다음과 같은 문제점을 보이고 있다.In the conventional design and construction of concrete lining to be constructed for the above purpose has shown the following problems.

첫째, 콘크리트 라이닝 형태는 아치형태가 아니며 타원형태이다. 따라서, 축력을 받는 구조물이 아니고 휨을 받는 구조물이다.First, the concrete lining is not arched but elliptical. Therefore, it is not a structure subjected to axial force but a structure subjected to bending.

터널 표준 시방서에서 거푸집 탈영시기는 콘크리트 라이닝 강도 30 kgf/㎠가 기준이며 현장에서는 안정성을 고려하여 50 kgf/㎠이다. 이것은 일반적인 콘크리트 라이닝 설계기준 강도 270 kgf/㎠에 10~20% 밖에 되지 않는 것이다. 이러한 시방서의 기준은 콘크리트 구조물 아치구조물에 대한 것으로 타원형 구조물에 대해서는 거푸집 탈영시 발생되는 응력이 거푸집 탈영시의 강도를 초과하므로 적용할 수 없다.In the tunnel standard specification, the die screening time is based on the concrete lining strength of 30 kgf / ㎠ and on the site is 50 kgf / ㎠ considering stability. This is a typical concrete lining design standard strength of 270 kgf / ㎠ only 10-20%. The standard of this specification is for the arch structure of the concrete structure, and the elliptical structure cannot be applied because the stress generated during the form desertion exceeds the strength during form desertion.

또한, 콘크리트 라이닝은 스프링 라인에 변곡점(4)이 위치하므로 자중에 대하여 축력 뿐만 아니라 모멘트가 발생하며 지반반력이 부족하거나 건조수축으로 측벽에 틈이 생길 경우 천단부에 모멘트가 발생하여 허용인장응력을 초과한다.In addition, in the concrete lining, the inflection point 4 is located on the spring line, so that not only the axial force but also the moment is generated against the self-weight. Exceed.

둘째, 콘크리트 라이닝을 전단면으로 타설함에 따라 재료 분리나 다짐불량으로 품질이 저하 되기 쉽다.Second, as the concrete lining is placed on the shear surface, the quality is easily degraded due to material separation or compaction.

도로터널의 경우 개략적으로 내공폭 12m, 높이 7m 정도로 대단면이다. 라이닝 길이 22m, 1회 타설 연장 9m, 콘크리트 라이닝 두께 0.3m로 할 경우 1회 타설 콘크리트량은 60㎥이다. 또한 콘크리트 타설시 완전히 폐합된 상태에서 작업이 이루어지므로 콘크리트 다짐이 용이하지 않고 골재분리가 일어난다. 따라서, 콘크리트 품질이 불량하게 된다.In the case of road tunnels, the cross section is roughly 12m in air width and 7m in height. If the lining length is 22m, the one-time extension is 9m, and the concrete lining thickness is 0.3m, the amount of one-time concrete is 60㎥. In addition, the concrete is not easy to compact and aggregate separation occurs because the work is made in a completely closed state when placing concrete. Therefore, the concrete quality is poor.

세째, 도로터널의 콘크리트 라이닝은 굴착면의 충분한 지지반력이 없을 경우 구조적으로 불안정한 구조물이다.Third, the concrete lining of the road tunnel is a structurally unstable structure when there is not enough supporting reaction of the excavation surface.

이것은 매우 중요한 문제로서 콘크리트 라이닝에 굴착면의 충분한 지지반력이 없을 경우 콘크리트 라이닝에 균열이 발생한다는 것이다. 이에 대하여 설계시에는 충분한 지반반력계수를 적용하여 구조적으로 안정한 것으로 해석하는데, 실제적으로는 지반, 숏크리트(6), 부직포 및 방수막(7)으로 구성된 콘크리트 라이닝(1, 2)의 복합 지지층에 대한 검토가 전혀 이루어지지 못하고 있다. 지반반력계수는 지반형상과도 매우 밀접한 관련이 있는 것이나, 현재 국내에서 사용하고 있는 지반반력계수 산출 방법인 Wolfer의 공식은 근거 문헌도 확인이 안 되며 검증도 이루어지지 못하는 것이 현실이다.This is a very important problem, in which the concrete lining will crack if the concrete lining does not have sufficient bearing reaction. On the other hand, when designing, it is interpreted as structurally stable by applying sufficient ground reaction coefficient. Actually, the composite support layer of concrete lining (1, 2) composed of ground, shotcrete (6), nonwoven fabric and waterproof membrane (7) There is no review at all. Soil reaction coefficient is closely related to soil shape, but Wolfer's formula, which is currently used in Korea, is not able to confirm the evidence and cannot be verified.

따라서, 불확실한 지반반력에 의지하는 기존 설계방법은 문제가 있으므로 안전측 설계를 위해서는 지반반력을 확보하는 것이 필요하다.Therefore, there is a problem in the existing design method that relies on uncertain ground reaction force, so it is necessary to secure the ground reaction force for the safety-side design.

네째, 콘크리트 라이닝의 건조수축을 고려하지 않아 변형 발생 고려를 누락하였다.Fourth, it did not consider the drying shrinkage of the concrete lining, so that the consideration of deformation occurrence was omitted.

기존 터널 라이닝 콘크리트 균열의 경우 전체 발생량의 86%가 천단부에 집중적으로 발생되고 있으며 이 중 종방향(길이방향)이 전체의 83%로 가장 많이 나타나고 있다. 발생시기는 3~4 개월 후에 발견되며 보수 후에도 재발생되는 현상을 가지고 있다. 균열 발생 원인은 다양하게 제시되고 있으나 거푸집을 조기 탈영하므로 인한 콘크리트 강도 부족의 원인을 주원인으로 파악하고 있다.In the case of the existing tunnel lining concrete cracks, 86% of the total generation is concentrated in the top end, and the longitudinal direction (length direction) is the most frequent (83%). Occurrence is found after 3-4 months and reoccurs after repair. The causes of cracks have been suggested in various ways, but the main cause of the lack of concrete strength due to early desertion of formwork is considered.

콘크리트 강도 부족이 균열의 원인이라면 콘크리트 라이닝 타설 후 양생이 완료되는 최대 1개월 이내에 발생되는 것이 타당할 것이다. 그러나, 콘크리트 라이닝 타설 후 3~4개월 후에 발생된다면 건조수축과 상당한 관련이 있을 것이다.If the lack of concrete strength is the cause of the cracks, it would be reasonable to occur within a month after curing of the concrete lining is completed. However, if it occurs three to four months after the concrete lining, it will be of significant relevance to dry shrinkage.

건조수축은 건조개시 후 20∼30일간에는 콘크리트의 배합이나, 건조개시 재령에 관계없이 수축변형량은 거의 같다. 이후 건조개시 재령이 짧을수록 변형량은 커지며, 콘크리트의 건조수축 변형량은 건조조건에 따라 현저한 차이가 있는 것은 당연한 일이지만, 자유수축 가능상태에서 변형율은 약 6∼8×10-4 정도(10M 길이에 약 6∼8㎜)로 보고되고 있다.Dry shrinkage is about 20 to 30 days after the start of drying, but the amount of shrinkage is almost the same regardless of the age of the start of drying. The shorter the drying age is, the larger the deformation is, and it is a matter of course that the dry shrinkage of concrete is significantly different depending on the drying conditions.However, in the free shrinkage state, the strain is about 6-8 × 10-4 (10M in length). About 6 to 8 mm).

국내 2차로 도로터널 내공폭이 약 12m 이므로 6mm 건조수축이 발생되었다고 가정할 때 콘크리트 라이닝 천정부에 6m 의 균열이 발생할 때까지 지반반력은 전혀 작용하지 않을 것이며 라이닝 천단부 균열은 명료하게 설명이 가능하다.Since the internal tunnel width of road tunnel in Korea is about 12m, it is assumed that 6mm dry shrinkage has occurred, so the ground reaction force will not work at all until the 6m crack in the concrete lining ceiling occurs, and the top end crack of the lining can be clearly explained. .

결론적으로 기존의 콘크리트 라이닝의 설계 및 시공방법은 많은 문제점을 가지고 있으며 균열문제를 바라보는 관점은 균열의 억제이나, 실제적으로는 설계 및 시공상의 구조적 안정성에 관련되어 발생되는 균열이므로 반드시 해결해야 하는 문제이다.In conclusion, the existing concrete lining design and construction methods have many problems. The point of view of the crack problem is a problem that must be solved because the cracks are related to the suppression of cracks, but are actually related to structural stability in design and construction. to be.

본 발명의 목적은 경제적으로 콘크리트 라이닝의 구조적 안정성을 확보하는 것과 균열 발생원인을 제거하고자 하는 것으로 콘크리트 라이닝을 기존 타원형 구조물 거동에서 아치형 구조물로 거동하도록 하여 구조적으로 유리하도록 하는 것이다. 또한, 하부 콘크리트 라이닝 다짐을 용이하게 하여 품질을 향상시키고자 한다.An object of the present invention is to economically secure the structural stability of the concrete lining and to remove the causes of cracking to be structurally advantageous by allowing the concrete lining to behave as an arched structure from the existing elliptical structure behavior. In addition, it is to improve the quality by facilitating compaction of the lower concrete lining.

이를 위하여 하부 콘크리트 라이닝(2)을 선시공 후 배면 그라우팅 및 강재쐐기(9)를 설치함으로서 하부 콘크리트 라이닝에서 충분한 지반반력 발휘 및 변형을 억제하므로 상부 콘크리트 라이닝(1)의 응력발생량을 줄이며, 충분한 다짐이 가능하게 하여 품질 향상을 도모하고자 한다.For this purpose, by installing the lower concrete lining (2) after installation, the rear grouting and the steel wedge (9) are suppressed to exhibit sufficient ground force and deformation in the lower concrete lining, thereby reducing the amount of stress generated in the upper concrete lining (1), and ensuring sufficient compaction. It aims to improve quality by making it possible.

선시공 후 배면에 대한 무수축 그라우팅 충전을 통해 건조수축으로 인해 발생될 수 있는 하부 콘크리트 라이닝과 지반과의 공간을 없애는 노력이 필요하다.Efforts are needed to eliminate the space between the lower concrete lining and the ground, which may be caused by dry shrinkage, by filling the shrinkage grouting on the back after pre-installation.

제 1도는 본 발명의 공법에 의하여 상부 콘크리트 라이닝(1)을 타설하는 개념도1 is a conceptual diagram of pouring the upper concrete lining (1) by the method of the present invention

제 2도는 하부 콘크리트 라이닝(2) 타설 후 강재 쐐기(9) 박기와 그라우팅 충진을 위해 선시공된 그라우팅 주입관(10) 에 대한 개념도2 is a conceptual diagram of the grouting injection pipe 10 pre-installed for filling and grouting the steel wedges 9 after the lower concrete lining 2 is poured.

* 도면의 주요 부분에 대한 부호의 설명* Explanation of symbols for the main parts of the drawings

1 : 상부 콘크리트 라이닝 2 : 하부 콘크리트 라이닝1: upper concrete lining 2: lower concrete lining

3 : 전단보강철근 4 : 측벽 변곡점3: shear reinforcing bar 4: side wall inflection point

5 : 강재 거푸집 6 : 숏크리트5: steel formwork 6: shotcrete

7 : 부직포 및 방수막 8 : 비닐막7: nonwoven fabric and waterproof film 8: vinyl film

9 : 강재 쐐기 10 : 그라우팅 주입관9: steel wedge 10: grouting injection tube

본 발명은 터널 라이닝을 아치형 구조물로 거동하기 위해서 스프링 라인을 기준으로 하부콘크리트 라이닝(2)이 상부 콘크리트 라이닝(1)의 고정 지점의 역할을 충분히 할 수 있도록 하는 공법으로 이루어져 있다.The present invention consists of a method that allows the lower concrete lining (2) to serve as a fixed point of the upper concrete lining (1) with respect to the spring line in order to behave as a tunnel lining arched structure.

고정지점의 역할을 하기 위해서는 하반 콘크리트 라이닝이 지반에 밀착되어야 하며 요구되는 지반반력이 확보되어야 한다.In order to act as a fixed point, the lower concrete lining must be in close contact with the ground and the required ground force must be secured.

1도는 상하 분리 콘크리트 라이닝 타설 강재 거푸집(5) 및 타설 형태를 나타낸 것이다. 기존의 전단면 타설 거푸집 대신에 스프링 라인을 기준으로 하부 콘크리트 라이닝을 먼저 타설하고 양생 완료 후 상부 콘크리트 라이닝을 타설한다.Figure 1 shows the top and bottom of the concrete lining pour steel formwork (5) and pour form. Instead of the existing shearing formwork, the lower concrete lining is first casted based on the spring line, and the upper concrete lining is poured after completion of curing.

2도는 하부 콘크리트 라이닝에 대하여 충분한 지반반력을 확보시키기 위하여 강재쐐기(9) 및 무수축 모르타르 그라우팅을 위한 그라우팅 주입관(10)을 나타낸 것이다. 란델을 통한 부직포와 방수막 시공은 라이닝 타설시 배면 공간이 발생할 수 있으며 이 경우 지반반력계수가 작아져 충분한 지반반력이 발휘되지 못한다. 또한 하부콘크리트 라이닝 양생 기간 중 건조수축으로 인하여 배면에 틈새가 발생할 경우 이를 충진하는 역할도 한다.Figure 2 shows the steel wedge 9 and the grouting injection tube 10 for non-contraction mortar grouting to ensure sufficient ground force against the bottom concrete lining. Nonwoven fabric and waterproof membrane construction through Landel may cause back space when lining is placed, in which case the ground force coefficient is small and sufficient ground force is not exerted. It also plays a role in filling gaps in the back surface due to dry shrinkage during curing of the lower concrete lining.

따라서, 하부 콘크리트 라이닝 배면에 그라우팅을 실시하여 배면공동을 없애고 요구되는 지반반력을 확보하는 것이다. 원활한 배면 그라우팅을 위하여 타설전 비닐막(8)로 방수막과 분리시킨다.Therefore, by grouting the lower concrete lining to remove the rear cavity and to secure the required ground force. For smooth back grouting, it is separated from the waterproof membrane by the pre-pour vinyl membrane (8).

하부 콘크리트 라이닝은 주입 및 다짐이 용이하므로 건조수축을 줄이기 위한 콘크리트 배합을 강구하는 것이 유리하다.Since the lower concrete lining is easy to inject and compact, it is advantageous to take concrete mix to reduce dry shrinkage.

콘크리트 라이닝을 상, 하부 분리 시공으로 하부 콘크리트 라이닝은 충분한 다짐이 가능하므로 품질 향상을 기대할 수 있다.As the concrete lining is separated from the upper and lower parts, the lower concrete lining can be sufficiently compacted, so quality improvement can be expected.

또한, 하부 콘크리트 라이닝 양생 후 배면그라우팅 및 쐐기 박기로 충분한 지반반력을 확보 및 변형을 억제하여 상반 콘크리트 라이닝의 지점을 고정지점으로 확보하므로서 상반콘크리트 라이닝에 발생되는 응력을 획기적으로 감소시켜 콘크리트 라이닝의 타설두께를 감소시킬 수 있다.In addition, after curing the lower concrete lining, it is possible to secure sufficient ground reaction force by back grouting and wedge clamping and to prevent deformation, thereby securing the point of the upper concrete lining as a fixed point, thereby drastically reducing the stress generated in the upper half concrete lining The thickness can be reduced.

따라서, 본 발명을 통하여 콘크리트 라이닝의 안정성 및 경제성을 확보할 수 있다. 추가로 콘크리트 라이닝 두께를 감소시킬 경우 터널단면 축소도 가능하다.Therefore, it is possible to ensure the stability and economy of the concrete lining through the present invention. In addition, if the concrete lining thickness is reduced, the tunnel section can be reduced.

Claims (3)

콘크리트 라이닝 타설시 측벽 변곡점(4)을 기준으로 하부 콘크리트 라이닝(2)을 선시공하여 상부 콘크리트 라이닝(1)의 지지점를 고정지지로 확보하여 상부 콘크리트 라이닝에 발생되는 응력을 감소시키는 공법When laying concrete lining, the lower concrete lining (2) is pre-installed based on the sidewall inflection point (4) to secure the support point of the upper concrete lining (1) as a fixed support to reduce the stress generated in the upper concrete lining 하부 콘크리트 라이닝 양생이 완료된 후 방수막(7)과 라이닝(2) 사이에 발생되는 공간을 그라우팅으로 가압 충진하여 설계상에서 요구하는 충분한 지반반력계수를 확보하므로 상부 콘크리트 라이닝 타설에 따른 굴착면 방향으로의 변형을 억제하는 공법After curing of the lower concrete lining is completed, the space generated between the waterproofing membrane 7 and the lining 2 is pressurized and filled with grouting to secure sufficient ground reaction coefficient required by the design. Method to suppress deformation 제 2항에 따라 하부 콘크리트 라이닝 타설시 방수막(7)에 비닐막(8)을 부착하고 양생완료 후 쐐기(9)를 박고 무수축모르타르 혹은 팽창제를 첨가한 모르타르로 벌어진 공간을 충진하는 공법The method of attaching the vinyl film 8 to the waterproofing membrane 7 when placing the lower concrete lining according to claim 2, filling the wedge 9 with the non-shrink mortar or mortar added with an expanding agent after curing is completed.
KR1020030045208A 2003-07-04 2003-07-04 The Construction Method of Dividing the Concrete lining into the top and bottom KR20050003726A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030045208A KR20050003726A (en) 2003-07-04 2003-07-04 The Construction Method of Dividing the Concrete lining into the top and bottom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030045208A KR20050003726A (en) 2003-07-04 2003-07-04 The Construction Method of Dividing the Concrete lining into the top and bottom

Publications (1)

Publication Number Publication Date
KR20050003726A true KR20050003726A (en) 2005-01-12

Family

ID=37218786

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030045208A KR20050003726A (en) 2003-07-04 2003-07-04 The Construction Method of Dividing the Concrete lining into the top and bottom

Country Status (1)

Country Link
KR (1) KR20050003726A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101007012B1 (en) * 2008-04-29 2011-01-12 차응섭 Reinforcement structure for tunnel and reinforcement method using the same
CN103953589A (en) * 2014-03-31 2014-07-30 山东大学 Grouting pressure stabilizing device and mounting method
CN110593893A (en) * 2019-11-01 2019-12-20 中建八局轨道交通建设有限公司 Main body structure construction method and system for intersection of main tunnel and construction transverse channel

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101007012B1 (en) * 2008-04-29 2011-01-12 차응섭 Reinforcement structure for tunnel and reinforcement method using the same
CN103953589A (en) * 2014-03-31 2014-07-30 山东大学 Grouting pressure stabilizing device and mounting method
CN103953589B (en) * 2014-03-31 2016-08-17 山东大学 A kind of grouting pressure stabilising arrangement and installation method
CN110593893A (en) * 2019-11-01 2019-12-20 中建八局轨道交通建设有限公司 Main body structure construction method and system for intersection of main tunnel and construction transverse channel
CN110593893B (en) * 2019-11-01 2024-04-12 中建八局轨道交通建设有限公司 Main body structure construction method and system at intersection of main tunnel and construction transverse channel

Similar Documents

Publication Publication Date Title
CN110747899B (en) Basement waterproof construction method
JP5373979B2 (en) Construction Method of Steel Composite Girder Bridge {ConstructionMethod SteelCompositeGirderBridge}
CN105178357A (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN103726503B (en) Anchor rod pile reinforcing bearing platform structure used for reinforcing deformed bridge pile and construction method thereof
CN106320377A (en) Water-rich soft soil area deep foundation pit cover and excavation top-down construction method
CN108589737A (en) Underground speedy way hands over the construction method that section is built jointly with rail under a kind of major urban arterial highway
CN110593311A (en) Post-cast strip concrete temporary support column
CN111074915B (en) Construction method of retaining plate structure between adjacent slide-resistant piles
CN110042865A (en) Box top board structure for large span city tunnel
CN105821908A (en) Multiple water stop belt, waterproof structure and construction method of waterproof structure
KR100815174B1 (en) Pipe Roof Tunnel and Constructing Method thereof
CN104594389A (en) Post-cast strip external wall plugging structure with elastic water stoppers
KR20050003726A (en) The Construction Method of Dividing the Concrete lining into the top and bottom
KR102079570B1 (en) Soil nailing slope reinforcement system to panel
CN110439035A (en) A kind of basement bottom plate rear pouring tape Seepage method
KR100941437B1 (en) 2 arch tunnel construction method for upper girder void proofing and efficient construction
JP5021526B2 (en) Construction method of underpass and connecting structure of superstructure girder and underground wall
JP2007321450A (en) Installation structure of lining pc slab and its pc slab
CN211714210U (en) Reconstruction and extension engineering interface structure based on C-shaped occlusion beam
KR200331557Y1 (en) Connecting Structure for Head of Pile
CN206768879U (en) A kind of poured band of outer wall of basement structure
CN205329566U (en) Subsiding crack infiltration restoration structure is contained to reinforced concrete apron
CN110159272A (en) The construction method of large span city tunnel with box top board structure
CN109667278A (en) Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing
CN110318372B (en) Anchor rod butt joint method

Legal Events

Date Code Title Description
WITN Withdrawal due to no request for examination