CN106320377A - Water-rich soft soil area deep foundation pit cover and excavation top-down construction method - Google Patents

Water-rich soft soil area deep foundation pit cover and excavation top-down construction method Download PDF

Info

Publication number
CN106320377A
CN106320377A CN201610797321.8A CN201610797321A CN106320377A CN 106320377 A CN106320377 A CN 106320377A CN 201610797321 A CN201610797321 A CN 201610797321A CN 106320377 A CN106320377 A CN 106320377A
Authority
CN
China
Prior art keywords
negative
construction
layers
layer
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610797321.8A
Other languages
Chinese (zh)
Other versions
CN106320377B (en
Inventor
翁谢军
李文涛
王荣华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 6th Engineering Co Ltd
Original Assignee
China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 2 Engineering Group Co Ltd filed Critical China Railway No 2 Engineering Group Co Ltd
Priority to CN201610797321.8A priority Critical patent/CN106320377B/en
Publication of CN106320377A publication Critical patent/CN106320377A/en
Application granted granted Critical
Publication of CN106320377B publication Critical patent/CN106320377B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention belongs to the technical field of construction of civil engineering, and discloses a water-rich soft soil area deep foundation pit cover and excavation top-down construction method. The method comprises the multiple steps that 1, a foundation pit is excavated to the position of a negative second layer plate, and a soil mold is adopted for pouring negative second layer bottom plate concrete; 2, earthwork below negative second and third layer concrete bottom plates is subjected to cover and excavation, a support is erected, and a bottom plate is constructed; 3, the support is dismantled, and side walls, stand columns and a top plate are constructed; and 4, after the strength of side walls and a top plate in the negative first layer meets design requirements, a first concrete support is dismantled. According to the method, cover and excavation construction is adopted, a steel supporting frame is erected in the cover rand excavation process, meanwhile, bottom plate construction and concrete pouring operation are carried out, meanwhile, side wall, stand column and top plate construction is carried out, and the safety problems existing in the prior art are solved; and the construction method is rapid, effective and particularly applicable to water-rich soft soil area deep pit construction.

Description

A kind of rich water soft clay area deep basal pit covered back-digging construction method
Technical field
The present invention relates to engineering construction technology field, particularly to a kind of rich water soft clay area deep basal pit covered back-digging Construction method.
Background technology
Deep-foundation pit engineering refers to the earth excavation of foundation ditch (groove) of more than cutting depth 5m, dewatering project, and excavation of foundation pit is A comprehensive engineering roadblock in foundation construction and high-rise basement construction, relates to the many problems in soil mechanics, simultaneously Relating to the common problems in role of soil and supporting construction, its construction method and technology are extremely important.Carrying out excavation Time, generally including open-cut and lid excavation construction, open-cut refers to first all be excavated, so by rock (native) body of tunnel site After build barrel, portal, then carry out the construction method backfilled, lid excavation construction be faced down by ground and be excavated to certain depth after, will Top seal, remaining bottom engineering is constructed under the top cover closed.
When rich water soft clay area carries out deep foundation pit construction, such as fruit structure design, earth excavation machine fall level of ground water etc. It is improper to manage, it is easy to the adverse effect such as cause that the earthwork is subsided, and serious consequence is hardly imaginable.Prior art is entered in rich water soft clay area During row deep foundation pit construction, have a problem in that
1, being difficult to determine construction method reasonable, effective, causing there is potential safety hazard, efficiency of construction is low simultaneously;
2, comprising silt clay layer and farinose argillic horizon due to rich water soft clay area, its bearing capacity of foundation slab is low, the end of at On plate, during construction, support is had bad luck, is set up the job very difficults such as support;
3, at the built-in soil of foundation ditch, lifting, when soil is circulated operation, owing to construction method and order are the most right, cause making Industry is inefficient.
Summary of the invention
It is an object of the invention to: due to construction party when overcoming prior art to carry out deep foundation pit construction in rich water soft clay area The most perfect the caused potential safety hazard of method and the low problem of efficiency of construction, it is provided that a kind of rich water soft clay area deep basal pit lid digs Reversed construction method, the method uses lid excavation construction, sets up bracing members frame during lid digs, and carries out construction of bottom plates simultaneously and mixes Solidifying soil cast work, and carry out side wall, column and top board construction, solving safety issue present in prior art, this is executed Work method is quickly effective, is particularly well-suited to the dell construction of rich water soft clay area, has bigger application value.
In order to realize foregoing invention purpose, the invention provides techniques below scheme:
A kind of hydrous fluids soft clay area deep basal pit covered back-digging construction method, sets deep basal pit as four-layer structure, wherein bears One layer and negative two layers uses open-cut, and negative three layers and negative four layers is lid excavation construction, and ground is provided with the 1st road concrete and supports, on ground It is disposed with the 2nd road between face and negative one layer to support and the support of the 3rd road, between negative one layer and negative two layers, is disposed with the 4th Road supports and the 5th road supports, and covered back-digging is constructed and included following multiple step:
When a, excavation of foundation pit are to negative two layers of position, use clay model, the negative two layers of underplate concrete of cast, and the construction of reserved side wall Seam;
B, reaching after design strength requires until negative two layers of base plate, lid digs the earthwork of negative two layers of base plate lower position, excavates extremely Set up the 6th road when setting Support Position to support, be excavated to negative Tipple Bottom Board position, and pour into a mould negative Tipple Bottom board concrete;
C, reaching after design strength requires until negative Tipple Bottom plate, lid digs the earthwork of negative Tipple Bottom plate lower position, excavates extremely Set up the 7th road when setting Support Position to support, be excavated to base plate position, and bottom board concrete;
D, reaching after design strength requires until base plate strength, remove the 7th road and support, the negative four layers of side wall of construction and negative four layers stand Post;
E, reach after design requires until negative four layers of side wall intensity, remove the 6th road and support, and negative three layers of side wall of constructing, negative three layers Column;
F, reach after design requires until negative three layers of side wall intensity, remove the 4th road and the 5th road supports, the negative two layers of side wall of construction, negative Two layers of column and negative one layer base plate;
G, reaching after design requires until negative two layers of side wall, negative one layer base plate strength, remove the 2nd road and the 3rd road supports, construction is negative One layer of side wall, negative one layer column and top board;
H, reach after design requires, to remove first concrete and support until negative one layer side wall, strength of roof.
Take aforesaid way, by taking above-mentioned covered back-digging construction method, during lid digs, i.e. set up bracing members frame, Carry out construction of bottom plates and concrete cast work simultaneously, and carry out side wall, column and top board construction, solve in prior art and deposit Safety issue, this construction method is quickly effective, is particularly well-suited to the dell construction of rich water soft clay area.
Preferably, rich water soft clay area deep basal pit covered back-digging construction method includes that earthwork construction, earthwork construction include Following steps:
I1, along foundation ditch length direction foundation ditch is divided into four unit, including first module, second unit, Unit the 3rd and Unit the 4th, and soil outlet is set at each unit, it is included in first module and the first soil outlet is set, arrange at second unit Two soil outlets, arrange the 3rd soil outlet at Unit the 3rd, and configure crawler type grabbing arrangement, and described 3rd soil outlet is single from the 3rd Unit extends to Unit the 4th;
I2, foundation ditch is carried out longitudinal layered excavation, including the 9th layer, the tenth layer, eleventh floor, Floor 12, the 13rd Layer and the 14th layer, described 9th layer, the tenth layer and eleventh floor between negative two layers and negative three layers, described Floor 12, Bearing between three layers and negative four layers for 13rd layer and the 14th layer, corresponding multiple flowing water scopes after each unit layering, including stream Water the 12nd scope, flowing water the 13rd scope, flowing water the 14th scope, flowing water the 15th scope and flowing water the 16th scope;
After i3, first module are born two layers of construction of bottom plates and completed, and intensity reaches 90%, the first soil outlet carry out the 9th layer of soil Side's excavation, in the range of completing flowing water the 12nd after middle groove excavation, laterally opens up limit, sets up first module the 6th road and support;
I4, bear after two layers of construction of bottom plates complete until second unit, continue to dig middle groove to the second soil outlet position to center mileage Putting end, be back to the first soil outlet and laterally open up limit, the earthwork is had bad luck and is gone out to the second soil outlet handling, sets up second unit in time The materials such as the 6th road supports, bracing members are hung in by the second soil outlet, install, are carrying out the 9th layer of earthwork flowing water the 13rd model When enclosing excavation, the tenth layer of earthwork flowing water the 13rd scope earth excavation should be carried out simultaneously;
I5, bear after two layers of construction of bottom plates complete until Unit the 3rd, continue in center mileage excavates groove to the 3rd soil outlet Terminating, be back to the second soil outlet and laterally open up limit, the earthwork is had bad luck and is gone out to the 3rd soil outlet handling, and bracing members is by the 3rd soil outlet Hang in and install, when carrying out the 9th laminar flow of water the 14th scope excavation, carry out the tenth laminar flow of water the 14th scope soil simultaneously Side's excavation;
I6, after eleventh floor flowing water the 15th scope and flowing water the 16th scope earthwork have all been excavated, carry out negative three Layer first module construction of bottom plates, carries out lower road earth excavation after reaching 90% intensity;
I7, the tenth layer and the 13rd layer of earthwork can directly be excavated by longitudinal divisions owing to depth of seam division is shallower.
Taking aforesaid way, at the built-in soil of foundation ditch, lifting, when soil is circulated operation, due to construction method and order Effective and reasonable, working performance is higher.
Preferably, in described step b and step c, when the earthwork of every layer of base plate lower position being carried out lid and digging, each The underplate concrete of unit reaches earth excavation under the laggard andante of design strength, and sequence of excavation is opened for vertical layering from top to bottom Dig, longitudinal layered formation step, the most first dig the middle soil body, then dig soil at both sides.
Preferably, when the negative two layers of base plate of construction and negative Tipple Bottom plate, concrete floor clay model construction is carried out, including following Aspect:
F1, middle longeron, side wall stock mould are constructed;
F2, clay model concrete construction;
F3, assembling reinforcement and casting concrete.
Owing to rich water soft clay area comprises silt clay layer and farinose argillic horizon, its bearing capacity of foundation slab is low, at base plate Support during upper construction and have bad luck, set up the job very difficults such as support, take aforesaid way, inverse make floor clay model and execute by carrying out Work, improves foundation bearing capacity, makes concrete surface smooth out.
Preferably, when carrying out setting up bracing members, bracing members sets up with digging with support, and applies axial prestress, bracing members Erection should ensure that bracing members is vertical with metope, after holding out against use gad support measure fixation.
Preferably, following steps are specifically included during erection bracing members:
J1, installation steel binder;
J2, installation bracing members,;
J3, Shi Hanzhang, and according to axle power Monitoring Data situation, it is determined whether additional prestressing.
Take above-mentioned operation and step, it is ensured that the stability of deep basal pit, owing to bracing members sets up great timeliness, bracing members It is stable that the size of the time, position and the Shi Hanzhang that set up is directly connected to deep basal pit.Bracing members sets up with digging with support, and executes Add axial prestress, make building enclosure accept reaction of bearing effect in advance, reduce the deformation of building enclosure.The erection of bracing members should Ensure bracing members vertical with metope, after holding out against use gad support measure fixation, prevent bracing members because of deformation of wall with Construction is collided and is come off.
Preferably, when carrying out side wall construction, following multiple step is taked:
H1, respectively twice construction joint on plate and under plate is carried out waterproof construction;
H2, cleaning Full-face pouring pipe, outside the Grouting Pipe mouth of pipe is placed in template, and carries out colligation by tied silk and fix;
H3, install side wall template;
H4, employing steel truss formwork jumbo carry out concreting;
H5, vibrate, and between new-old concrete joint face and dust inlet, use secondary vibration.
Preferably, in described step h1, construction joint on plate is being carried out waterproof construction formula, is using galvanized steel plain sheet waterstop, And the mode of pre-buried Full-face pouring pipe later stage slip casting carries out strengthening water-proofing treatment, under plate, construction joint position uses water-swellable only Glue and Full-face pouring pipe combination carry out waterproof construction.
Preferably, in described step h3, when installing side wall template, chassis top template is adjusted to spacious by closely connected mode Evolution formula, arranges 30~40cm high oblique moulds on chassis punching block top, and oblique template end face exceeds construction joint 10cm.
For pouring concrete after avoiding concrete cannot fill up side wall and the inverse seam doing the side wall watered under plate, take above-mentioned Mode, had both facilitated concrete to enter mould, can be sufficient filling with again the gap, wall top that concrete produces during making firm by ramming due to slump, Ensure that construction joint is closely knit.
Preferably, in step h4, side wall uses high fluidity pea gravel concreten, and top area uses microdilatancy coagulation Soil.Take this mode, utilize the microdilatancy of concrete. compensate later stage concrete shrinkage in hardening process.
Compared with prior art, beneficial effects of the present invention:
1, by taking above-mentioned covered back-digging construction method, during lid digs, i.e. set up bracing members frame, carry out at the end simultaneously Plate construction and concrete cast work, and carry out side wall, column and top board construction, solve safety present in prior art Problem, this construction method is quickly effective, is particularly well-suited to the dell construction of rich water soft clay area, has bigger popularization and application valency Value;
2, comprising silt clay layer and farinose argillic horizon due to rich water soft clay area, its bearing capacity of foundation slab is low, the end of at On plate, during construction, support is had bad luck, is set up the job very difficults such as support, constructs by carrying out inverse floor clay model of making, improves ground and hold Load power, makes concrete surface smooth out;
3, by setting up bracing members, it is ensured that the stability of deep basal pit, owing to bracing members sets up great timeliness, bracing members frame If the size of time, position and Shi Hanzhang to be directly connected to deep basal pit stable, bracing members sets up with digging with support, and applies Axial prestress, makes building enclosure accept reaction of bearing effect in advance, reduces the deformation of building enclosure, and the erection of bracing members should be protected Card bracing members is vertical with metope, uses the measure fixation that gad supports after holding out against, and prevents bracing members from because of deformation of wall and executing Work is collided and is come off.
Accompanying drawing illustrates:
Fig. 1 is structural representation during lower two layers of construction of bottom plates.
Fig. 2 is structural representation during negative Tipple Bottom plate construction.
Fig. 3 is to set up structural representation when supporting.
Fig. 4 is structural representation when lower four layers of side wall and lower four layers of column construction.
Fig. 5 is structural representation when negative three layers of side wall and negative three layers of column construction.
Fig. 6 is structural representation when negative two layers of side wall and negative two layers of column construction.
Fig. 7 is structural representation when negative one layer side wall and the construction of negative one layer column.
Fig. 8 is the structural representation removing first concrete.
Fig. 9 is the structural representation that the lid section of digging longitudinal direction excavation in layers machine puts slope.
Labelling in figure: 1-the first soil outlet, 2-the second soil outlet, 3-the 3rd soil outlet, 4-flowing water the 12nd scope, 5-flows Water the 13rd scope, 6-flowing water the 14th scope, 7-flowing water the 15th scope, 8-flowing water the 16th scope, 9-bears two layers, 11- 9th layer, 12-the tenth layer, 13-eleventh floor, 14-bears three layers, and 15-bears two layers of base plate, and 16-bears Tipple Bottom plate, 17-base plate, 18-bears four layers of side wall, and 19-bears four layers of column, and 20-bears three layers of side wall, and 21-bears three layers of column, and 22-bears two layers of side wall, and 23-bears two Layer column, 24-negative one layer base plate, 25-negative one layer side wall, 26-negative one layer base plate, 27-top board, 28-first concrete supports, 29- 13rd layer, x-first module, y-second unit, z-the 3rd unit, t-the 4th unit.
Detailed description of the invention
Below in conjunction with test example and detailed description of the invention, the present invention is described in further detail.But this should not understood Scope for the above-mentioned theme of the present invention is only limitted to below example, and all technology realized based on present invention belong to this The scope of invention.
Embodiment 1
Rich water soft clay area deep basal pit covered back-digging construction method, sets deep basal pit as four-layer structure, wherein negative one layer and Negative two layers use open-cut, and negative three layers and negative four layers is lid excavation construction, and ground is provided with the 1st road concrete and supports, on ground with negative It is disposed with the 2nd road between one layer to support and the support of the 3rd road, is disposed with the 4th road between negative one layer and negative two layers and supports Supporting with the 5th road, covered back-digging is constructed and is included following multiple step:
When a is as it is shown in figure 1, excavation of foundation pit is to negative two layers of position, use clay model, negative two layers of base plate 15 concrete of cast, and Reserved side wall construction joint;
B is as in figure 2 it is shown, after negative two layers of base plate 15 reach design strength requirement, lid digs negative two layers of base plate 15 lower position The earthwork, excavate to setting up the 6th road when setting Support Position and support, be excavated to negative Tipple Bottom plate 16 position, and pour into a mould negative three layers Base plate 16 concrete;
C is as it is shown on figure 3, after negative Tipple Bottom plate 16 reaches design strength requirement, lid digs negative Tipple Bottom plate 16 lower position The earthwork, excavate to set Support Position time set up the 7th road support, be excavated to base plate 17 position, and bottom board 17 concrete;
D, as shown in Figure 4, reaches after design strength requires until base plate 17 intensity, removes the 7th road and support, the negative four layers of side wall of construction 18 and negative four layers of column 19;
E is as it is shown in figure 5, after negative four layers of side wall 18 intensity reach design requirement, remove the 6th road and support, and constructs negative three layers Side wall 20, negative three layers of column 21;
F, as shown in Figure 6, reaches after design requires until negative three layers of side wall intensity, removes the 4th road and the 5th road supports, and construction is negative Two layers of side wall 22, negative two layers of column 23 and negative one layer base plate 24;
G, as it is shown in fig. 7, reach after design requires until negative two layers of side wall 22, negative one layer base plate 24 intensity, removes the 2nd road and the 3 roads support, construction negative one layer side wall 25, negative one layer column 26 and top board 27;
H, as shown in Figure 8, after negative one layer side wall 25, top board 27 intensity reach after design requires, removes first concrete and props up Support 28.
Take aforesaid way, by taking above-mentioned covered back-digging construction method, during lid digs, i.e. set up bracing members frame, Carry out construction of bottom plates and concrete cast work simultaneously, and carry out side wall, column and top board construction, solve in prior art and deposit Safety issue, this construction method is quickly effective, is particularly well-suited to the dell construction of rich water soft clay area.
In covered back-digging work progress, carry out the inverse floor clay model that does and construct.
Negative two layers of base plate, negative Tipple Bottom plate are positioned at silt clay layer, farinose argillic horizon, and bearing capacity of foundation slab is low, minimum It is only 65KPa, though taking high-pressure rotary jet grouting pile to reinforce in design, but due to reinforcement depth relatively deeply, as deep as to 26.7m, and For the weak reinforcing of 3m stripping, foundation bearing capacity is the highest.If meeting the rainy day, excavator walks back and forth and is supported down in addition Fortune, erection, substrate soil is the most a piece of muddy, and personnel's walking is the most painstaking.Therefore consider that one layer of bamboo plate+20cmC20 element mixes Solidifying soil+sealing coat (PVC board or epoxy glass fabric lamination insulation board) is as clay model layer.Construction content includes:
(1) longeron, the construction of side wall stock mould in
Negative two layers, longeron and abutment wall use the stock mould of brick one-tenths 24cm thickness, the cement sand plaster of 5cm in negative three layers.For The line style of longeron and physical dimension in ensureing after the demoulding, stock mould must be the most straight, and the most vertically, headroom size has to comply with and sets Meter requirement.
(2) clay model concrete construction
Clay model concrete is the C20 concrete of 20cm, and top of concrete absolute altitude improves 2cm than absolute altitude at the bottom of structural slab, as The anticipated settlement of top board structure.For ensureing concrete surface smooth-going, no concave-convex injustice phenomenon, each unit clay model concrete is pressed Laterally framing construction, the channel-section steel arranging 15cm in every width both sides carries out absolute altitude control, after concrete construction, uses aluminium alloy level Strike off, before concrete initial set, carry out press polish wipe one's face.For avoid carry out inverse make earth excavation under plate time, blinding concrete is in blocks Drop and machinery, personnel are damaged.
For ensureing the smooth demoulding of clay model, concrete cushion arranges sealing coat (PVC board or epoxy glass fabric lamination insulation Plate).
(3) reinforcing bar binding and concreting
The all steel bar meter field processing on foundation ditch of the former material of reinforcing bar, semi-finished product use truck crane to hang in foundation ditch, this engineering steel Muscle is connected by the thread rolling bar connection and two kinds of forms of welding.
Because inwall, frame column lid dig along doing, when plate (beam) reinforcing bar binding, it is necessary to by the pre-buried levels of design requirement Chemise and frame column reinforcing bar connector, when embedded ribs is installed, under plate, main muscle exposed length should be less than oblique construction joint lowest part 1.5m, above 1.5m at a length of plate of reserved steel bar or back on plate, it is ensured that connecing when rear construction column and the main muscle of side wall connect Head staggers length.Plate lower contact is taked need to effectively protect steel bar head when being mechanically connected, and cannot be carried out after preventing excavation Effectively connect.
Earthwork construction comprises the following steps:
(1) soil outlet is arranged
Considering effectively to utilize this engineering structure reserving hole, be crisscross arranged 10 unearthed, feed openings along foundation ditch direction.
(2) equipment configuration
Configuring two 10T straddle trucks and a 50T crawler type grab bucket, crawler type grab bucket is for being unearthed and pre-in shield Jing Chu Soil outlet is stayed to be unearthed when leaning on ground-connecting-wall side;Straddle truck utilizes stair hole reserved on floor to be unearthed.Grab bucket is equipped with two PC120 digging machine, every straddle truck is equipped with two PC120 digging machines.
(3) earth excavation
Every unit is inverse reach as board concrete design strength 90% after, under plate, the earthwork is according to " vertical layered, longitudinally point Section, middle kerve, both sides extend, pretensioned girder " principle, stage excavation the most from top to bottom, longitudinal layered formation step, horizontal Dig the middle soil body to first, then dig soil at both sides.
The every layer of earthwork of each step is excavated by the order of " extending to both sides after grooving in the middle of first ", i.e. by the east head to The excavated surface of western end well longitudinally draws groove in the excavation of slope along foundation ditch, and middle well width first has to meet excavator revolution spoir Requirement, ensures to stay soil at both sides the most as far as possible.Middle groove is excavated by 5m, and both sides earthwork balance, symmetry are carried out Excavation.Slope ratio of slope 1:2.5 is put in both sides.After middle kerve is excavated to the distance of 3~4 road bracing members, spread to both sides centre Digging, the excavation of soil at both sides should balance, symmetry is carried out.
As it is shown in figure 9, the concretely comprising the following steps of earthwork construction in the deep basal pit covered back-digging construction method of rich water soft clay area:
I1, along foundation ditch length direction, foundation ditch is divided into four unit, including first module x, second unit y, the 3rd unit z With the 4th unit t, and soil outlet is set at each unit, is included in first module x and the first soil outlet 1 is set, at second unit y Arranging the second soil outlet 2, arrange the 3rd soil outlet 3 at the 3rd unit z, and configure crawler type grabbing arrangement, the described 3rd is unearthed Mouth 3 extends to the 4th unit t from the 3rd unit z;
I2, foundation ditch is carried out longitudinal layered excavation, including the 9th layer 11, the tenth layer 12, eleventh floor 13, Floor 12, 13rd layer and the 14th layer (not identifying in figure), described 9th layer 11, the tenth layer 12 and eleventh floor 13 are positioned at negative two layer 9 And between negative three layers 14, described Floor 12, the 13rd layer and the 14th layer between negative three layer 14 and negative four layers, each unit Corresponding multiple flowing water scopes after layering, including flowing water the 12nd scope 4, flowing water the 13rd scope 5, flowing water the 14th scope 6, stream Water the 15th scope 7 and flowing water the 16th scope 8;
I3, first module x are born two layers of construction of bottom plates and are completed, and after intensity reaches 90%, the first soil outlet 1 carry out the 9th layer 11 Earth excavation, in completing flowing water the 12nd scope 4 after middle groove excavation, laterally opens up limit, sets up bracing members, for first module the 6th road Support;
I4, bear after two layer of 9 construction of bottom plates complete until second unit y, continue to dig middle groove to the second soil outlet 2 to center mileage Position is terminated, and is back to the first soil outlet 1 and laterally opens up limit, and the earthwork is had bad luck and gone out to the second soil outlet 2 handling, sets up steel in time and props up Support, the material such as bracing members is hung in by the second soil outlet 2, installs, opens carrying out the 9th layer 11 cubic metres of earth flowing water the 13rd scopes 5 When digging, the tenth layer 12 cubic metres of earth flowing water the 13rd scope 5 earth excavations should be carried out simultaneously;
I5, bear after two layer of 9 construction of bottom plates complete until the 3rd unit z, continue groove in center mileage excavates and be unearthed to the 3rd Mouth 3 terminates, and is back to the second soil outlet 2 and laterally opens up limit, and the earthwork is had bad luck and gone out to the 3rd soil outlet 3 handling, and bracing members is by the 3rd Soil outlet 3 hangs in be installed, and when carrying out the 9th layer of 11 flowing water the 14th scope 6 and excavating, carries out the tenth layer of 12 flowing water simultaneously 14th scope 6 earth excavation;
I6, after eleventh floor 13 flowing water the 15th scope 7 and flowing water the 16th scope 8 cubic metres of earth have all been excavated, carry out Negative three layer of 14 first module a construction of bottom plates, carries out lower road earth excavation after reaching 90% intensity;
I7, the tenth layer the 12, the 13rd layer 29 cubic metres of earth due to depth of seam division shallower can directly longitudinal divisions excavation.
Taking above-mentioned steps and method, through lid digs part observation on the spot, at the built-in soil of foundation ditch, lifting, soil, to again Arriving foundation ditch down, owing to construction method and order are effective and reasonable, working performance is higher, complete this about 8 minutes used time of circulation ( Fall height 24m~42m), 16 hours working times every day, it is unearthed every day and measures about about 150m3, use crawler type to grab bucket one Individual circulation time about 5 minutes, the time that work every day is identical, amount of being unearthed every day is about at about 260m3, and efficiency is much higher than gantry Hang, when therefore relating to lid excavation construction, pay the utmost attention to use grab bucket to be unearthed, need end bay on floor to reserve every certain Soil outlet.
Embodiment 2
The present embodiment is applied in bracing members erection, demolishing process.
It is the inseparable twice critical process of deep foundation pit construction that bracing members sets up with pit earthwork excavation, bracing members erection Great timeliness, it is stable that the size of time, position and Shi Hanzhang that bracing members sets up is directly connected to deep basal pit.Bracing members Set up with digging with support, and apply axial prestress, make building enclosure accept reaction of bearing effect in advance, reduce the change of building enclosure Shape.The erection of bracing members should ensure that bracing members is vertical with metope.The measure fixation using gad to support after holding out against, prevents steel Support and come off because of deformation of wall and construction collision.Following steps are specifically included when setting up bracing members:
J1, installation steel binder, soil layer is excavated to support after setting up design attitude, digs out the pre-buried steel on diaphram wall Plate, welds pallet, installs steel binder;
J2, installation bracing members, bracing members is in the outer width according to foundation ditch of foundation ditch, the length of ground-connecting-wall to steel binder, steel system Length between beam has spelled tube coupling.First passing through soil outlet and hang into foundation ditch by bracing members tube coupling crane, then passing through digging machine will Bracing members is transported to installation site.First set up fixing end, by two digging machines by bracing members lifting, bracing members one end is held on On the welded angle iron of pre-embedded steel slab, the other end is shelved on steel binder.Continue to set up second section, still through digging machine lifting, will Second section one end is connected by high-strength bolt with first segment, and the other end is shelved on another root steel binder.Finally set up fixing end Obtaining bracing members, first segmented head telescopable portion pulled out, Section of three one end and second section are first passed through high-strength bolt by digging machine lifting Lian Hao, is stably placed at the other end on the most mounted triangular steel plate.Pre-embedded steel slab is withstood in movable head pull-out;
J3, carry out prestress application, and according to axle power Monitoring Data situation, it is determined whether additional prestressing, by 2 hydraulic pressure Jack (according to brace pre axial force size 300T, 500T) plays with digging machine and puts into pressure position, the active crown, and notes keeping very heavy Top line is walked unanimously.Turn on pump Shi Hanzhang is got final product, after prestress application puts in place, at segmented head wedge groove gad plug after connecting oil pipe Tightly, then jack is unclamped in oil return, unties hoisting wirerope, completes the installation that this root supports.Should be taken into account during construction prestressing force Stress loss during operation, construction prestress value should design axle power increase about 10% by ratio, and make a record.
After support Shi Hanzhang terminates, the anchor ear reinforcing bar of " u "-shaped is close to bracing members, and is firmly welded on steel binder On, two pieces of bolts are filled in the gap supported with steel binder, prevents bracing members from being moved left and right by External Force Acting.
Axial force of the supports is added with based on axle power Monitoring Data, is auxiliary with hand inspection.The monitoring of axle power is the change of measurement axis power, If axle force value reduces, prestressing force should be added with in time.Hand inspection be check support segmented head gag, whether loosen depending on it determine be No it is added with.
Embodiment 3
The present embodiment is applied to side wall construction, when carrying out side wall construction, comprises the following steps:
H1, carry out waterproof construction to twice construction joint on plate and under plate respectively;
H2, cleaning Full-face pouring pipe, outside the Grouting Pipe mouth of pipe is placed in template, and carries out colligation by tied silk and fix;
H3, install side wall template;
H4, employing steel truss formwork jumbo carry out concreting;
H5, vibrate, and between new-old concrete joint face and dust inlet, use secondary vibration.
Concrete operations are:
(1) waterproof construction
According to covered back-digging technological characteristics of construction, ground-connecting-wall is overlapping wall, and every layer of side wall has plate with base plate, middle plate joint Above, twice construction joint under plate, it is therefore necessary to attach great importance to the waterproof quality of construction joint.
Ground-connecting-wall carries out brushing cement based penetration crystallization type water proofing paint after dabbing process with inwall structure handing-over position, Utilize it to meet watery vomiting and improve the anti-permeability performance of concrete to osmosis.On plate, construction joint position uses galvanized steel plain sheet waterstop, And the mode of pre-buried Full-face pouring pipe later stage slip casting carries out strengthening water-proofing treatment.Under plate, construction joint position uses water-swellable only Glue and Full-face pouring pipe combination carry out waterproof construction, are pasted onto construction joint surface after water-swellable water-stop glue extrusion, Cross dimensions after curing molding is (8 10) mm × (18 20) mm.Galvanized steel plain sheet waterstop width in construction joint position on plate For 300mm, thickness 4mm, galvanized layer thickness is more than 30 microns, and when steel plate is installed, construction joint should be positioned at steel plate middle, and joint is adopted Dock with welding, it is desirable to steel plate dead in line, dock firm, closely knit, waterproof.
Before side wall reinforcement construction, first construction joint on plate, under plate is carried out dabbing process, cut concrete surface and float Slurry.Steel plate water stopper pre-buried on plate is carried out dress watch, it is ensured that the height that waterstop exposes is the 1/2 of waterstop height, Part concrete is dug out at the position inadequate to proud exposure, it is ensured that the proud exposure of steel plate water stopper, to ensure construction construction The position of seam is substantially at the half height and position of waterstop, it is ensured that the effect of sealing.To concrete laitance on the plate cut, under plate Must clean out, with giant, construction joint is rinsed, it is ensured that construction joint position is without residue.
(2) steel truss formwork jumbo is used to carry out concreting
The advantage that the portable motor of manufacturer production drives walking type steel truss template abutment wall chassis: formwork rigidity is big, anti- Deformability is strong, without repeat to spell assembly and disassembly, mobile in place soon, short construction period (once circulation in 3~4 days), every mould pours Length 12m.After reaching certain intensity after side wall concrete pours, unclamp the adjustable bolt of support shuttering rod member, template After the whole disengaging in face concrete surface, start two motors on chassis, drive chassis to walk to walk to next construction cell in orbit Construct.
(3) concrete construction
Clear up Full-face pouring pipe before casting concrete, outside the Grouting Pipe mouth of pipe is placed in template, and carry out by tied silk Colligation is fixed, it is to avoid poured inside side wall by the Grouting Pipe mouth of pipe in casting process.When installing side wall template, for avoiding coagulation Soil cannot fill up side wall after pouring concrete and the inverse seam doing the side wall watered under plate, chassis top template is adjusted by closely connected mode Whole is to open wide mode, arranges 30~40cm high oblique moulds on chassis punching block top, and oblique template end face exceeds construction joint 10cm.This Sample had both facilitated concrete to enter mould, can be sufficient filling with again the gap, wall top that concrete produces during making firm by ramming due to slump, protected Card construction joint is closely knit.Side wall uses high fluidity pea gravel concreten, and top area uses slightly expanded concrete. utilize concrete Microdilatancy. compensate later stage concrete shrinkage in hardening process.In addition to routine is vibrated, new-old concrete joint face and under Secondary vibration is used between ash mouth.Cut for convenience, because the side wall wedge shape coagulation local product being tiltedly molded as pouring at the beginning of concrete more Cut immediately after Ning, and repair.

Claims (10)

1. a rich water soft clay area deep basal pit covered back-digging construction method, it is characterised in that set deep basal pit as four-layer structure, Wherein negative one layer and negative two layers of employing open-cut, negative three layers and negative four layers is lid excavation construction, and each layer all sets up bracing members, ground Face is provided with the 1st road concrete and supports, and is disposed with the 2nd road and supports and the 3rd road supports between ground and negative one layer, negative one layer and Being disposed with the 4th road between negative two layers to support and the support of the 5th road, covered back-digging is constructed and is included following multiple step:
When a, excavation of foundation pit are to negative two layers of position, use clay model, the negative two layers of underplate concrete of cast, and reserved side wall construction joint;
B, reaching after design strength requires until negative two layers of base plate, lid digs the earthwork of negative two layers of base plate lower position, excavates to setting Set up the 6th road during Support Position to support, be excavated to negative Tipple Bottom Board position, and pour into a mould negative Tipple Bottom board concrete;
C, reaching after design strength requires until negative Tipple Bottom plate, lid digs the earthwork of negative Tipple Bottom plate lower position, excavates to setting Set up the 7th road during Support Position to support, be excavated to base plate position, and bottom board concrete;
D, reach after design strength requires until base plate strength, remove the 7th road and support, the negative four layers of side wall of construction and negative four layers of column;
E, reach after design requires until negative four layers of side wall intensity, remove the 6th road and support, and negative three layers of side wall of constructing, negative three layers of column;
F, reach after design requires until negative three layers of side wall intensity, remove the 4th road and the 5th road supports, negative two layers of side wall of construction, negative two layers Column and negative one layer base plate;
G, reach after design requires until negative two layers of side wall, negative one layer base plate strength, remove the 2nd road and the 3rd road supports, negative one layer of constructing Side wall, negative one layer column and top board;
H, reach after design requires, to remove first concrete and support until negative one layer side wall, strength of roof.
Rich water soft clay area the most according to claim 1 deep basal pit covered back-digging construction method, it is characterised in that carrying out During earthwork lid excavation construction, earthwork lid excavation construction comprises the steps:
I1, along foundation ditch length direction, foundation ditch is divided into four unit, including first module, second unit, Unit the 3rd and the 4th Unit, and soil outlet is set at each unit, it is included in first module and the first soil outlet is set, arrange second at second unit and go out Tu Kou, arranges the 3rd soil outlet at Unit the 3rd, and configures crawler type grabbing arrangement, and described 3rd soil outlet prolongs from Unit the 3rd Extend Unit the 4th;
I2, foundation ditch is carried out longitudinal layered excavation, including the 9th layer, the tenth layer, eleventh floor, Floor 12, the 13rd layer and 14th layer, described 9th layer, the tenth layer and eleventh floor between negative two layers and negative three layers, described Floor 12, the tenth Three layers and the 14th layer between negative three layers and negative four layers, corresponding multiple flowing water scopes after each unit layering, including flowing water the 12 scopes, flowing water the 13rd scope, flowing water the 14th scope, flowing water the 15th scope and flowing water the 16th scope;
After i3, first module are born two layers of construction of bottom plates and completed, and intensity reaches 90%, the first soil outlet carry out the 9th layer of earthwork and open Dig, in the range of completing flowing water the 12nd after middle groove excavation, laterally open up limit, set up first module the 6th road and support;
I4, bear after two layers of construction of bottom plates complete until second unit, continue to dig middle groove to center mileage and tie to the second soil outlet position Bundle, is back to the first soil outlet and laterally opens up limit, and the earthwork is had bad luck and gone out to the second soil outlet handling, sets up second unit the 6th in time The materials such as road supports, bracing members are hung in by the second soil outlet, install, open carrying out the 9th layer of earthwork flowing water the 13rd scope When digging, the tenth layer of earthwork flowing water the 13rd scope earth excavation should be carried out simultaneously;
I5, bear after two layers of construction of bottom plates complete until Unit the 3rd, continue groove in center mileage excavates and terminate to the 3rd soil outlet, Being back to the second soil outlet and laterally open up limit, the earthwork is had bad luck and is gone out to the 3rd soil outlet handling, and bracing members is hung in by the 3rd soil outlet Install, when carrying out the 9th laminar flow of water the 14th scope excavation, carry out the tenth laminar flow of water the 14th scope earthwork simultaneously and open Dig;
I6, after eleventh floor flowing water the 15th scope and flowing water the 16th scope earthwork have all been excavated, carry out negative three layers the One unit baseboard construction, carries out lower road earth excavation after reaching 90% intensity;
I7, the tenth layer and the 13rd layer of earthwork can directly be excavated by longitudinal divisions owing to depth of seam division is shallower.
Rich water soft clay area the most according to claim 2 deep basal pit covered back-digging construction method, it is characterised in that to often The earthwork of layer base plate lower position carries out lid when digging, and the underplate concrete at each unit reaches soil under the laggard andante of design strength Side's excavation, sequence of excavation is vertical stage excavation, longitudinal layered formation step from top to bottom, the most first digs the middle soil body, then digs Soil at both sides.
Rich water soft clay area the most according to claim 2 deep basal pit covered back-digging construction method, it is characterised in that in construction When negative two layers of base plate and negative Tipple Bottom plate, carry out concrete floor clay model construction, including following aspect:
F1, middle longeron, side wall stock mould are constructed;
F2, clay model concrete construction;
F3, assembling reinforcement and casting concrete.
Rich water soft clay area the most according to claim 1 deep basal pit covered back-digging construction method, it is characterised in that carrying out When setting up bracing members, bracing members sets up with digging with support, and applies axial prestress, and the erection of bracing members should ensure that bracing members and wall Face is vertical, uses the measure fixation that gad supports after holding out against.
Rich water soft clay area the most according to claim 5 deep basal pit covered back-digging construction method, it is characterised in that set up steel Following steps are specifically included during support:
J1, installation steel binder;
J2, installation bracing members;
J3, Shi Hanzhang, and according to axle power Monitoring Data situation, it is determined whether additional prestressing.
7. according to the rich water soft clay area deep basal pit covered back-digging construction method one of claim 1-6 Suo Shu, it is characterised in that When carrying out side wall construction, take following multiple step:
H1, respectively twice construction joint on plate and under plate is carried out waterproof construction;
H2, cleaning Full-face pouring pipe, outside the Grouting Pipe mouth of pipe is placed in template, and carries out colligation by tied silk and fix;
H3, install side wall template;
H4, employing steel truss formwork jumbo carry out concreting;
H5, vibrate, and between new-old concrete joint face and dust inlet, use secondary vibration.
Rich water soft clay area the most according to claim 8 deep basal pit covered back-digging construction method, it is characterised in that described step In rapid h1, construction joint on plate is being carried out waterproof construction formula, using galvanized steel plain sheet waterstop, and pre-buried Full-face pouring pipe later stage The mode of slip casting carries out strengthening water-proofing treatment, and under plate, construction joint position uses water-swellable water-stop glue to be combined with Full-face pouring pipe Mode carries out waterproof construction.
Rich water soft clay area the most according to claim 8 deep basal pit covered back-digging construction method, it is characterised in that described step In rapid h3, when installing side wall template, chassis top template is adjusted to unlimited mode by closely connected mode, on chassis punching block top Arranging 30~40cm high oblique moulds, oblique template end face exceeds construction joint 10cm.
Rich water soft clay area the most according to claim 8 deep basal pit covered back-digging construction method, it is characterised in that in step In rapid h4, side wall uses high fluidity pea gravel concreten, and top area uses slightly expanded concrete.
CN201610797321.8A 2016-08-31 2016-08-31 A kind of rich water soft clay area deep basal pit covered back-digging construction method Active CN106320377B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610797321.8A CN106320377B (en) 2016-08-31 2016-08-31 A kind of rich water soft clay area deep basal pit covered back-digging construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610797321.8A CN106320377B (en) 2016-08-31 2016-08-31 A kind of rich water soft clay area deep basal pit covered back-digging construction method

Publications (2)

Publication Number Publication Date
CN106320377A true CN106320377A (en) 2017-01-11
CN106320377B CN106320377B (en) 2019-03-08

Family

ID=57787864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610797321.8A Active CN106320377B (en) 2016-08-31 2016-08-31 A kind of rich water soft clay area deep basal pit covered back-digging construction method

Country Status (1)

Country Link
CN (1) CN106320377B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056795A (en) * 2018-08-16 2018-12-21 庐江荣睿建设工程有限公司 A kind of skyscraper top-down construction method
CN109098182A (en) * 2018-09-04 2018-12-28 中电建南方建设投资有限公司 A kind of cap excavation method foundation pit stand construction method
CN109403342A (en) * 2018-10-31 2019-03-01 中建局集团建设发展有限公司 A kind of foundation pit mixing support construction and its construction method
CN109837910A (en) * 2019-02-19 2019-06-04 中国建筑第八工程局有限公司 The foundation ditch construction method that contrary sequence method and bracing members combine
CN111576431A (en) * 2020-05-25 2020-08-25 中铁隧道局集团有限公司 Excavation method for foundation pit of four-layer subway station
CN113136893A (en) * 2021-04-24 2021-07-20 浙江兴业市政工程有限公司 Unitized construction method of underground connecting channel
CN113202124A (en) * 2021-04-12 2021-08-03 中铁六局集团有限公司 Reverse construction method for water-rich deep foundation pit water collection pit
CN113293766A (en) * 2021-03-30 2021-08-24 内蒙古科技大学 Comprehensive earthwork excavation method for large-scale cover excavation top-down T-shaped transfer subway station
CN113756314A (en) * 2021-08-03 2021-12-07 中铁(上海)投资集团有限公司 Construction method suitable for excavation of deep and large ground iron-based pit of soft soil foundation in long and triangular regions
CN113833024A (en) * 2021-10-21 2021-12-24 中国十九冶集团有限公司 Basin-type excavation combined cover-excavation top-down construction method for water-rich deep and large foundation pit
CN115506364A (en) * 2022-09-21 2022-12-23 中铁建工集团有限公司 Construction method of foundation pit supporting structure
CN116025005A (en) * 2023-01-05 2023-04-28 北京住总集团有限责任公司 Subway station main body structure construction method influenced by double rows of lattice columns

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080098262A (en) * 2007-05-04 2008-11-07 (주)씨.에스 구조 엔지니어링 Non-support construction method using the deckplate for wall girder
CN102433892A (en) * 2011-12-30 2012-05-02 中铁二局股份有限公司 Construction method for cover-excavation reverse method soil moulding bed
CN103628503A (en) * 2013-11-27 2014-03-12 中铁第四勘察设计院集团有限公司 Construction method for using underground second-layer station enclosure to make underground third-layer transfer joint
CN103981898A (en) * 2014-05-12 2014-08-13 铁道第三勘察设计院集团有限公司 Integral open-excavation node top-down underground engineering construction method
CN105297773A (en) * 2015-10-30 2016-02-03 马鞍山十七冶工程科技有限责任公司 Reverse construction method earth excavation method capable of reducing cover-excavation earth volume

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080098262A (en) * 2007-05-04 2008-11-07 (주)씨.에스 구조 엔지니어링 Non-support construction method using the deckplate for wall girder
CN102433892A (en) * 2011-12-30 2012-05-02 中铁二局股份有限公司 Construction method for cover-excavation reverse method soil moulding bed
CN103628503A (en) * 2013-11-27 2014-03-12 中铁第四勘察设计院集团有限公司 Construction method for using underground second-layer station enclosure to make underground third-layer transfer joint
CN103981898A (en) * 2014-05-12 2014-08-13 铁道第三勘察设计院集团有限公司 Integral open-excavation node top-down underground engineering construction method
CN105297773A (en) * 2015-10-30 2016-02-03 马鞍山十七冶工程科技有限责任公司 Reverse construction method earth excavation method capable of reducing cover-excavation earth volume

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李冲: ""填海区地层新型盖挖逆作法施工技术及重难点探讨——以深圳地铁11号线前海湾站工程为例"", 《现代物业.新建设》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056795A (en) * 2018-08-16 2018-12-21 庐江荣睿建设工程有限公司 A kind of skyscraper top-down construction method
CN109098182A (en) * 2018-09-04 2018-12-28 中电建南方建设投资有限公司 A kind of cap excavation method foundation pit stand construction method
CN109403342A (en) * 2018-10-31 2019-03-01 中建局集团建设发展有限公司 A kind of foundation pit mixing support construction and its construction method
CN109837910A (en) * 2019-02-19 2019-06-04 中国建筑第八工程局有限公司 The foundation ditch construction method that contrary sequence method and bracing members combine
CN111576431A (en) * 2020-05-25 2020-08-25 中铁隧道局集团有限公司 Excavation method for foundation pit of four-layer subway station
CN113293766B (en) * 2021-03-30 2022-12-30 内蒙古科技大学 Comprehensive earth excavation method for large-scale cover-excavation top-down T-shaped transfer subway station
CN113293766A (en) * 2021-03-30 2021-08-24 内蒙古科技大学 Comprehensive earthwork excavation method for large-scale cover excavation top-down T-shaped transfer subway station
CN113202124A (en) * 2021-04-12 2021-08-03 中铁六局集团有限公司 Reverse construction method for water-rich deep foundation pit water collection pit
CN113136893B (en) * 2021-04-24 2022-06-17 浙江兴业市政工程有限公司 Unitized construction method of underground connecting channel
CN113136893A (en) * 2021-04-24 2021-07-20 浙江兴业市政工程有限公司 Unitized construction method of underground connecting channel
CN113756314A (en) * 2021-08-03 2021-12-07 中铁(上海)投资集团有限公司 Construction method suitable for excavation of deep and large ground iron-based pit of soft soil foundation in long and triangular regions
CN113833024A (en) * 2021-10-21 2021-12-24 中国十九冶集团有限公司 Basin-type excavation combined cover-excavation top-down construction method for water-rich deep and large foundation pit
CN115506364A (en) * 2022-09-21 2022-12-23 中铁建工集团有限公司 Construction method of foundation pit supporting structure
CN115506364B (en) * 2022-09-21 2024-04-30 中铁建工集团有限公司 Construction method of foundation pit supporting structure
CN116025005A (en) * 2023-01-05 2023-04-28 北京住总集团有限责任公司 Subway station main body structure construction method influenced by double rows of lattice columns
CN116025005B (en) * 2023-01-05 2023-07-25 北京住总集团有限责任公司 Subway station main body structure construction method influenced by double rows of lattice columns

Also Published As

Publication number Publication date
CN106320377B (en) 2019-03-08

Similar Documents

Publication Publication Date Title
CN106320377B (en) A kind of rich water soft clay area deep basal pit covered back-digging construction method
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN103485288A (en) Construction process of double-layer jacking culvert penetrating through existing railway lines
CN103422510A (en) Steel pipe frame type cofferdam structure and construction method
CN111441343A (en) Mountain photovoltaic support micropore cast-in-place pile foundation system, construction method and application
CN110273436A (en) Open trench tunnel utilizes support pile and bear down on one float Structure and its construction method of crown beam
CN109706952A (en) Large-scale well-sinking construction method
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN114673169A (en) Multi-layer large-span deep foundation pit cover-excavation forward-backward combined construction method for urban core area
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN110965473A (en) Construction method of bridge bearing platform
CN204825867U (en) As composite pile structure of secretly digging garage stand
CN108396761A (en) The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit
CN107542065A (en) Suddenly let out the small punching block of groove turns over a liter construction method to a kind of height
CN203066083U (en) Supporting structure for two adjacent foundation pits
CN215211056U (en) Assembled multilayer inner supporting structure
CN111535339B (en) Construction process of concrete dam body of refuse landfill
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area
CN113585336A (en) Quick construction method of sinking type concrete mixing station in soft foundation environment
CN219653491U (en) Steel construction abutment suitable for steel trestle
CN113700004B (en) Deep foundation pit combined support construction device and method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Applicant after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Applicant before: CHINA RAILWAY NO.2 BUREAU ENGINEERING Co.,Ltd.

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20190130

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Applicant after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Applicant after: CHINA RAILWAY ERJU 6TH ENGINEERING CO.,LTD.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Applicant before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant