KR20060112504A - Downward construction system and method for 1-way girder and slab of underground structure - Google Patents
Downward construction system and method for 1-way girder and slab of underground structure Download PDFInfo
- Publication number
- KR20060112504A KR20060112504A KR1020050035022A KR20050035022A KR20060112504A KR 20060112504 A KR20060112504 A KR 20060112504A KR 1020050035022 A KR1020050035022 A KR 1020050035022A KR 20050035022 A KR20050035022 A KR 20050035022A KR 20060112504 A KR20060112504 A KR 20060112504A
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- support
- deck
- way
- girder
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0061—Production methods for working underwater
- E02D2250/0076—Drilling
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
도 1은 본 발명에 따라 시공된 지하구조물의 1방향 보 및 데크 슬래브를 도시한 평면도, 1 is a plan view showing the one-way beam and deck slab of the underground structure constructed in accordance with the present invention,
도 2는 도 1의 선 'A-A'를 따라 취한 단면도, 2 is a cross-sectional view taken along the line 'A-A' of FIG. 1,
도 3은 도 1의 선 'B-B'를 따라 취한 단면도, 3 is a cross-sectional view taken along the line 'B-B' of FIG. 1,
도 4는 본 발명에 따라 시공된 지하구조물의 데크 슬래브를 도시한 저면사시도,Figure 4 is a bottom perspective view showing a deck slab of the underground structure constructed in accordance with the present invention,
도 5는 본 발명의 제1실시예에서 보 거푸집 및 딥 데크 설치 후 콘크리트가 타설된 상태를 나타낸 단면도, 5 is a cross-sectional view showing a state in which concrete is poured after installing the formwork and deep deck in the first embodiment of the present invention,
도 6은 본 발명의 제1실시예에서 보 거푸집 및 딥 데크 설치상태를 보여주는 사시도,Figure 6 is a perspective view showing a state of the formwork and deep deck installation in the first embodiment of the present invention,
도 7a ~ 도 7e는 본 발명의 제1실시예를 이용하여 1방향 보 및 데크 슬래브를 시공하는 과정을 나타낸 도면, 7A to 7E are views illustrating a process of constructing a one-way beam and a deck slab using the first embodiment of the present invention;
도 8은 본 발명의 제1실시예에서 보 거푸집이 현수 하강장치에 의해 하강되 는 상태를 나타낸 사시도, 8 is a perspective view showing a state in which the formwork is lowered by the suspension lowering device in the first embodiment of the present invention,
도 9a와 도 9b는 본 발명의 제1실시예에 적용된 로울러 기구의 사시도와 단면도,9A and 9B are a perspective view and a sectional view of the roller mechanism applied to the first embodiment of the present invention;
도 10은 본 발명의 제2실시예에서 기둥 지지되는 이동 조립식 지지 브라켓 및 지지거더가 설치된 상태를 도시한 평면도, FIG. 10 is a plan view showing a state in which a mobile prefabricated support bracket and a support girder are installed in a second embodiment of the present invention;
도 11은 본 발명의 제2실시예에서 지지거더 위에 보 거푸집 및 딥 데크가 설치된 상태의 저면도,Figure 11 is a bottom view of the beam formwork and the deep deck is installed on the support girder in the second embodiment of the present invention,
도 12는 본 발명에 따른 제2실시예의 각 구성이 모두 설치된 상태에서 보 및 슬래브 콘크리트가 타설된 상태를 나타낸 단면도, 12 is a cross-sectional view showing a state in which the beam and the slab concrete is poured in a state in which each configuration of the second embodiment according to the present invention,
도 13은 도 12에서 주요부를 확대하여 나타낸 단면도,13 is an enlarged cross-sectional view of a main part in FIG. 12;
도 14a는 본 발명에 따른 제2실시예의 각 이동 조립식 지지 브라켓에서 H-형강 지지거더가 지지된 상태를 도시한 사시도, 14A is a perspective view showing a state in which the H-shaped steel support girder is supported in each movable prefabricated support bracket of the second embodiment according to the present invention;
도 14b는 본 발명에 따른 제2실시예의 각 이동 조립식 지지 브라켓에서 지지거더간을 결합한 예를 도시한 사시도,Figure 14b is a perspective view showing an example of coupling between the support girder in each movable prefabricated support bracket of the second embodiment according to the present invention,
도 15a는 본 발명의 제2실시예에서 나란한 두 지지거더의 설치상태를 나타낸 평면도, 15A is a plan view showing an installation state of two support girders side by side in the second embodiment of the present invention;
도 15b는 도 15a의 선 'E-E'를 따라 취한 단면도로서 나란한 두 지지거더간에 횡좌굴보강앵글이 설치된 상태를 도시한 도면, FIG. 15B is a cross-sectional view taken along the line 'E-E' of FIG. 15A, showing a state in which lateral buckling reinforcement angles are installed between two side-by-side support girders;
도 15c는 도 15a의 선 'F-F'를 따라 취한 단면도로서 승강용 현수재가 지지거더에 연결된 상태를 도시한 도면,15C is a cross-sectional view taken along the line 'F-F' of FIG. 15A and showing a state where the lifting suspension is connected to the support girder,
도 16a ~ 도 16e는 본 발명의 제2실시예를 이용하여 1방향 보 및 데크 슬래브를 시공하는 과정을 나타낸 도면,16A to 16E are views illustrating a process of constructing a one-way beam and a deck slab using the second embodiment of the present invention;
도 17은 본 발명의 제3실시예에서 기둥 지지되는 1방향 지지 브라켓 및 지지거더가 설치된 상태를 도시한 평면도, 17 is a plan view illustrating a state in which a one-way support bracket and a support girder installed in a pillar in a third embodiment of the present invention are installed;
도 18a와 도 18b는 본 발명에 따른 제3실시예의 각 구성이 모두 설치된 상태에서 보 및 슬래브 콘크리트가 타설된 상태를 나타낸 단면도, 18A and 18B are cross-sectional views showing a state in which beams and slab concrete are poured in a state in which all the components of the third embodiment according to the present invention are installed;
도 19a와 도 19b는 각각 도 18a와 도 18b에서 주요부를 확대하여 나타낸 단면도,19A and 19B are enlarged cross-sectional views of main parts of FIGS. 18A and 18B, respectively;
도 20a와 도 20b는 본 발명의 제3실시예에서 1방향 지지 브라켓이 H-형강 기둥에 설치된 상태를 도시한 평면사시도와 저면사시도, 20A and 20B are a plan perspective view and a bottom perspective view showing a state in which a one-way support bracket is installed on an H-beam in a third embodiment of the present invention;
도 21a와 도 21b는 본 발명의 제3실시예에서 1방향 지지 브라켓이 H-형강 기둥에 설치된 상태를 도시한 평면도와 저면도,21A and 21B are a plan view and a bottom view showing a state in which a one-way support bracket is installed on an H-beam in a third embodiment of the present invention;
도 22는 본 발명의 제3실시예에서 스톱 풀러가 클램프 조임에 의해 H-형강 기둥에 고정되는 또 다른 예를 도시한 저면도, FIG. 22 is a bottom view showing another example in which a stop puller is fixed to an H-beam by clamping in a third embodiment of the present invention; FIG.
도 23은 본 발명에서 두 브라켓 본체가 H-형강 기둥에 대해 약축방향으로 설치된 1방향 지지 브라켓의 단면도,FIG. 23 is a cross-sectional view of a one-way support bracket in which two bracket bodies are installed in a weak axis direction with respect to an H-beam;
도 24a와 도 24b는 본 발명에서 두 브라켓 본체가 H-형강 기둥에 대해 약축방향으로 설치된 1방향 지지 브라켓의 평면도와 저면도, 24A and 24B are a plan view and a bottom view of the unidirectional support bracket in which the two bracket bodies are installed in the weak axis direction with respect to the H-beam in the present invention;
도 25는 도 23의 선 'J-J'를 따라 취한 단면도,FIG. 25 is a cross-sectional view taken along the line 'J-J' of FIG. 23;
도 26a와 도 26b는 본 발명의 제3실시예에서 1방향 지지 브라켓 위에 지지거 더가 설치된 예를 도시한 사시도,26A and 26B are perspective views illustrating an example in which a support girder is installed on a one-way support bracket in a third embodiment of the present invention;
도 27a ~ 도 27e는 본 발명의 제3실시예를 이용하여 1방향 보 및 데크 슬래브를 시공하는 과정을 나타낸 도면, 27A to 27E are views illustrating a process of constructing a one-way beam and a deck slab using the third embodiment of the present invention;
도 28a와 도 28b는 본 발명의 제3실시예를 이용하는 과정에서 1방향 지지 브라켓의 브라켓 본체를 하강시키는 방법을 나타낸 도면,28A and 28B illustrate a method of lowering the bracket body of the one-way support bracket in the process of using the third embodiment of the present invention;
도 29는 지하구조물의 역타 시공시 보 거푸집 및 데크 플레이트의 배치상태를 나타낸 평면도.29 is a plan view showing the arrangement of the beam formwork and deck plate during reverse construction of the underground structure.
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
BG: 보 BS : 데크 슬래브BG: Bo BS: Deck Slab
101 : CFT 기둥 102 : H-형강 기둥101: CFT column 102: H-beam column
104 : 동바리 110 : 보 거푸집104: Dongburi 110: Bo die
120 : 딥 데크 136 : 회전형 로울러 기구120: deep deck 136: rotary roller mechanism
138a : 삽입부 138b : 회전부138a:
141 : 베어링 142 : 지지단141: bearing 142: support end
150 : 이동 조립식 지지 브라켓 153 : 지지거더150: movable prefabricated support bracket 153: support girder
155 : 엔드 플레이트 156 : 심 플레이트155: end plate 156: shim plate
180 : 1방향 지지 브라켓 181 : 브라켓 본체180: one-way support bracket 181: bracket body
183 : 체결 플레이트 184 : 베드 플레이트183: fastening plate 184: bed plate
185 : 스톱 풀러 186 : 스톱 플레이트185: stop puller 186: stop plate
194, 195 : 보강 CT-형강194, 195: reinforced CT-beam
본 발명은 지하층의 1방향 보 및 데크 슬래브 시공을 위한 하향 골조 타설 시스템 및 방법에 관한 것으로서, 더욱 상세하게는 보 및 슬래브의 역타 시공시에 1방향 보를 구축하기 위한 보 거푸집, 장스팬 적용이 가능한 골데크 타입의 딥 데크, 그리고 보 거푸집 및 골조용 기둥에 고정 설치되면서 1방향 배치되는 지지거더를 지지하기 위한 지지 브라켓을 사용함으로써, 1방향 보 및 데크 슬래브의 시공이 가능하고, 버림 콘크리트의 타설 작업이 축소 또는 삭제가 가능하며, 지지 브라켓 사용으로 선 시공된 상층 슬래브에 무리한 하중이 가해지 않도록 1방향 보 및 데크 슬래브의 시공이 가능해지는 지하층의 1방향 보 및 데크 슬래브 시공을 위한 하향 골조 타설 시스템 및 방법에 관한 것이다.The present invention relates to a downward frame placing system and method for the construction of a one-way beam and deck slab of the basement, and more specifically, to form a one-way beam for the reverse construction of the beam and slab, it is possible to apply the formwork, long span The construction of one-way beam and deck slab is possible by using the support deck for supporting the deck deck deep deck and the support girder arranged in one direction while being fixedly installed on the beam formwork and the frame column. The work can be reduced or deleted, and the downward frame pour system for the construction of one-way beams and deck slabs in the basement floor, which enables the construction of one-way beams and deck slabs to prevent excessive load on the upper slabs pre-installed by using the support bracket. And to a method.
일반적으로 지하구조물을 구축하는 방법에는 두 가지가 있다.In general, there are two ways to build underground structures.
지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고 토사를 전부 반출한 뒤 맨 아래층부터 구조물을 축조해 올라가는 순타설공법과, 흙막이를 시공하고 1층 구조물을 축조한 다음 그 구조물을 흙막이용 버팀부재로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 역타설공법이 그것이다.After constructing the earthquake on the ground where the underground structure is constructed, install the temporary facility to support the earthquake while excavating the ground, take out all the earth and sand, and build the structure from the bottom floor, After the construction of the first-floor structure, using the structure as a retaining member for the earthquake, the reverse casting method is to construct the structure while drilling the ground from the top to the bottom.
최근 토지 이용의 극대화 차원에서 지하공사가 점차 고심도화되고 있고, 특 히 순타설공법에 의한 시공시에는 흙막이 붕괴의 위험이나 주변 건물들 침하 등으로 인한 균열 발생은 물론, 시각적으로도 불안할 뿐만 아니라 공사기간이 길어지는 등 여러 문제가 있어서, 근래에는 역타설공법이 널리 적용되고 있다.In recent years, underground construction has been gradually intensified in order to maximize land use. Especially, when the construction is performed by the net pouring method, it is not only visually unstable as well as the occurrence of cracks due to the risk of earthquake collapse or settlement of surrounding buildings. Due to various problems such as lengthening of the construction period, the reverse casting method has been widely applied in recent years.
이 역타설공법은 흙막이벽 및 그 안쪽 지중의 골조용 기둥을 시공한 뒤 슬래브 및 보 등의 지하구조물을 지상 1층부터 지하층을 향하여 단계적으로 시공해 내려가는 방식이므로, 지하구조물과 지상구조물의 시공이 동시에 진행 가능하고, 지상 1층의 바닥을 작업장으로 활용할 수 있어 별도의 복공판이 필요하지 않으며, 무지보 거푸집 작업이 가능하다는 장점이 있다.In this reverse casting method, after constructing the retaining wall and the frame for the underground frame, the underground structures such as slabs and beams are constructed step by step from the ground floor to the underground floor. It can proceed at the same time, the floor of the ground floor can be utilized as a workshop, there is no need for a separate perforated plate, there is an advantage that the work can be plain.
이러한 역타설공법으로는 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(Concrete on Grade)과, 지반을 어느 정도 굴착하고 지반을 고른 뒤 동바리를 세우고 거푸집을 설치하여 콘크리트를 타설하는 방법(Form on Supporting)과, 거푸집 지지를 위한 동바리를 세우지 않는 대신에 선 시공한 상층의 콘크리트 슬래브에 거푸집을 현수시켜 콘크리트를 타설하는 방법(무지보 역타설 현수 거푸집 공법) 등이 있다. Such a reverse casting method involves placing concrete slabs and beams on the ground while the ground is stopped (concrete on grade), and excaving the ground to some extent, selecting the ground, and then placing the clubs and installing the formwork to place the concrete. (Form on Supporting) and the method of placing concrete by suspending the formwork on the concrete slab on the upper floor instead of erecting a group for supporting the formwork (inverted reversal suspension formwork).
이중에서 동바리를 이용하는 공법은 상대밀도가 비교적 높은 지층에 적용하는 공법으로서, 지반을 선 굴착한 후 굴착된 지반 위에 버림 콘크리트를 타설하고, 이 버림 콘크리트를 지지기반으로 하여 동바리와 보 거푸집 및 슬래브 거푸집을 설치한 뒤, 보 및 슬래브의 콘크리트를 타설하는 공법이다.The method of using copper barley is a method applied to strata with relatively high relative density. After drilling the ground, the cast concrete is placed on the excavated ground, and the cast concrete is used as the support base for the copper bar, the formwork and the slab formwork. After installing the concrete, the concrete of the beam and slab is poured.
여기서, 보 거푸집 및 슬래브 거푸집은 굴착 지반 위의 버림 콘크리트상에서 동바리에 의해 지지되어진다.Here, beam formwork and slab formwork are supported by clubs on discarded concrete on the excavation ground.
그러나, 동바리의 이용시에는 연약지반상에서의 지지가 불안정하고, 또한 콘크리트 강도가 일정 한도 이상으로 보양되지 않으면 해체가 불가하기 때문에 콘크리트 양생 중 동바리의 존치로 인하여 아래층의 굴토공사가 진행될 수 없다.However, when the copper barrier is used, support on the soft ground is unstable and dismantlement is impossible unless the concrete strength is maintained above a certain limit.
더구나, 거푸집, 동바리 등 가설자재를 굴토작업장 외부로 반출한 뒤 굴토 후 다시 아래층으로 이동하여 재설치해야 하고, 이를 각 층의 시공시마다 반복해야 하는 바, 이러한 작업을 반복 수행하는데 있어서 번잡한 문제점이 있게 된다.In addition, the temporary materials such as formwork, dongbari, etc. should be taken out of the Gulto workshop and moved back to the lower floor after reconstruction, and this should be repeated for each floor construction. do.
또한, 콘크리트를 부어 넣은 뒤 충분한 양생기간을 거쳐 구조체가 제강도를 발현할 때까지 기다려야 하므로 작업대기 시간이 불가피하게 발생하고, 동바리나 거푸집의 소운반 및 재조립에 소요되는 비용과 시간이 과다하여 비경제적일 뿐만 아니라 모든 작업이 인력에 의존하므로 노동집약적이어서 기능공의 인력 부족이 심화되는 현실에서 원가 절감이 어려워지는 등의 문제점이 있게 된다.In addition, after the concrete is poured, it is necessary to wait until the structure develops the steelmaking strength after sufficient curing period. Therefore, waiting time is inevitably generated, and the cost and time required for transporting and reassembling the copper bar or formwork are excessive. In addition to being economical, all work depends on manpower, which is labor intensive, which leads to problems such as difficulty in cost reduction in a situation in which labor force shortages intensify.
이러한 문제점들을 갖는 동바리의 사용을 줄이기 위하여, 최근 무지보 시공의 장점을 가진 데크 플레이트(Deck Plate)가 개발되어 그 사용이 점차 늘고 있는 바, 도 29는 지하구조물의 역타 시공시 보 거푸집 및 데크 플레이트의 배치상태를 나타낸 평면도로서, 이를 설명하면 다음과 같다.In order to reduce the use of clubs with these problems, the deck plate (Deck Plate) has recently been developed with the advantages of unsupported construction has been gradually increasing its use, Figure 29 is a formwork and deck plate for reverse construction of underground structures As a plan view showing the arrangement of the, it will be described as follows.
도 29는 가로, 세로 2방향 보 및 데크 슬래브의 시공을 위한 보 거푸집(2) 및 데크 플레이트(3)의 배치상태를 나타낸 것이다.FIG. 29 shows the arrangement of
흙막이벽(도시하지 않음)과 그 안쪽 지중의 골조용 기둥(1)이 시공된 상태에서, 시공될 보를 따라 그 하측으로 보 거푸집(2)을 버림 콘크리트 위 동바리로 지지시켜 설치하고, 보 거푸집과 보 거푸집 사이에 데크 플레이트(3)를 지지시켜 설 치한 다음, 보 거푸집(2)과 데크 플레이트(3)에 콘크리트를 동시 타설하여 슬래브(데크 슬래브)와 보를 완성한다. In the state in which the retaining wall (not shown) and the frame pillar (1) in the inner underground are constructed, the beam formwork (2) is supported by the clubs on the discarded concrete along the beam to be constructed, and installed. Deck plates (3) are supported and installed between the beam formwork, and then concrete is poured on the beam formwork (2) and the deck plate (3) to complete the slab (deck slab) and the beam.
이때, 역타설공법이 이용되므로, 우선 보 거푸집 및 데크 플레이트에 콘크리트를 타설하여 상층 슬래브 및 보를 선 시공하고, 상층 시공시에 이용된 보 거푸집을 하층 높이에 맞게 하강시켜 재설치한 후 동일하게 콘크리트를 타설하여 하층 슬래브 및 보를 시공하게 된다.In this case, since the reverse casting method is used, first, the concrete is installed on the beam formwork and the deck plate, and the upper slab and the beam are pre-installed. By pouring, the lower slabs and beams will be constructed.
이러한 방법으로 보 거푸집 하강 및 데크 플레이트 설치, 슬래브 및 보의 콘크리트 타설 작업을 각 층의 시공과정에서 반복하여, 지하구조물을 지하층을 향해 단계적으로 시공해 내려가게 된다.In this way, the beam formwork and deck plate installation, slab and concrete placement of the slab are repeated in the construction process of each floor, and the underground structure is constructed step by step toward the basement floor.
그러나, 가로, 세로 2방향의 보를 시공해야 하는 경우에는 도 29에서와 같이 골조용 기둥(1)을 중심으로 총 4방향으로 보 거푸집(2)을 설치해야 하고, 또한 보 거푸집을 지지시키기 위해 기둥 중심 4방향의 보 거푸집 설치공간을 따라 버림 콘크리트 타설 및 동바리를 설치해야 한다.However, in the case where the beams in the horizontal and vertical directions must be constructed, as shown in FIG. 29, the
이와 같이 기둥 중심 4방향의 보 거푸집을 따라 버림 콘크리트를 타설하는 경우, 콘크리트의 사용량이 과다할 수 밖에 없고, 폐기될 버림 콘크리트의 시공면적이 늘어나면서 폐기물의 발생량 및 처리량이 증가하는 문제점이 있게 된다.As such, when the discarded concrete is poured along the pillars in four directions of the pillar center, the amount of used concrete is inevitably increased, and as the construction area of the discarded concrete to be discarded increases, the amount of waste generated and throughput increases. .
특히, 골조용 기둥(1)을 중심으로 버림 콘크리트를 보 거푸집(2)의 설치공간을 따라 좁은 간격으로 시공하는 것이 매우 번거롭기 때문에, 실제 현장에서는 흙막이벽 안쪽 지반 전 영역에 버림 콘크리트를 타설하는 경우가 대부분이다. In particular, since it is very cumbersome to construct the discarded concrete at narrow intervals along the installation space of the formwork (2) around the frame pillar (1), in the actual site when casting the discarded concrete in the entire ground area inside the retaining wall Is most of them.
한편, 동바리 사용시의 문제점을 해결하기 위하여, 지하구조물을 축조할 때 지상 1층부터 지하 최저층을 향해 구축해 나가는 무지보 역타설 거푸집 공법(Non Supporting Formwork System for Top Down Construction)으로서, 거푸집 지지용 동바리를 설치하지 않는 대신, 선 시공한 상층 콘크리트 슬래브에 거푸집을 현수시키는 무지보 역타설 현수 거푸집 공법이 제시된 바 있다.On the other hand, in order to solve the problem of using the grouping, as a non-supporting formwork system for top down construction that is constructed from the ground floor to the lowest basement when building underground structures, Instead of installing it, an unsupported reversal suspension formwork was proposed to suspend the formwork on the pre-installed upper concrete slab.
이 무지보 역타설 현수 거푸집 공법은 선 시공한 상층의 슬래브에 현수재를 이용하여 거푸집을 현수시킨 상태에서 이 거푸집을 이용하여 하층의 슬래브를 시공하는 방법이다.This unsupported reversal suspension formwork is a method of constructing a lower slab by using the formwork while suspending the formwork using a suspension material on the upper slab.
이 방법을 이용하여 각 층의 지하구조물을 축조하기 위해서는, 거푸집에 콘크리트를 타설하여 상층 슬래브를 시공하는 단계, 이 상층 슬래브의 시공시에 이용된 거푸집을 상층 슬래브 위의 유압 승강기를 이용하여 하강시키는 단계, 이 하강된 거푸집을 이용해 하층 슬래브를 시공하는 단계를 각 층마다 반복하게 된다.In order to build underground structures of each floor using this method, concrete is laid on the formwork to construct the upper slab, and the formwork used in the construction of the upper slab is lowered by using a hydraulic lift on the upper slab. The construction of the lower slab using the lowered formwork is repeated for each floor.
이러한 현수식 공법은, 슬래브 거푸집 및 보 거푸집 하부에 동바리를 설치하지 않고 거푸집을 상층의 슬래브에 매달아 설치하기 때문에, 작업장 확보 및 작업자의 안전 보장 측면에서 보다 유리하고, 거푸집 작업과 상관없이 지하 터파기를 연속적으로 진행할 수 있으며, 충분한 양생기간 확보로 우수한 콘크리트 품질을 얻을 수 있는 동시에 공기 단축 및 원가 절감이 가능해지는 장점이 있다.This suspension method is more advantageous in securing the workplace and ensuring the safety of the worker because it is installed by hanging the formwork on the upper slab without installing the copper bar at the bottom of the slab formwork and the beam formwork. It is possible to proceed continuously, it is possible to obtain excellent concrete quality by securing a sufficient curing period, and at the same time has the advantage that it is possible to shorten the air and reduce the cost.
특히, 현수식 공법을 적용하는 경우에는 상층 슬래브에 현수된 거푸집을 연속적으로 달아내리는 지하 골조공사, 하부에서의 굴토공사, 그리고 지상부 구조물 축조공사의 3단계 공정을 동시에 진행할 수 있게 된다.In particular, when the suspension method is applied, it is possible to simultaneously perform the three-stage process of underground frame construction, which continuously runs down the formwork suspended from the upper slab, the excavation work from the bottom, and the ground structure construction.
그러나, 무지보 공법으로 개발된 상기 현수식 공법에도 다음과 같은 문제점 이 있다.However, the suspension method developed by the unsupported method has the following problems.
종래 현수재 지지방식의 공법에서는 유압 승강기 및 현수재가 모두 상층의 콘크리트 슬래브에 지지된 상태에서 하층 슬래브의 콘크리트 시공이 이루어진다. In the conventional suspension support method, the concrete construction of the lower slab is made while both the hydraulic elevator and the suspension are supported by the upper concrete slab.
즉, 하층 슬래브로 타설되는 콘크리트의 하중이 거푸집 및 현수재를 통해 전적으로 상층 슬래브에 지지되는 시스템으로 되어 있는 것이다. In other words, it is a system in which the load of concrete cast into the lower slab is entirely supported by the upper slab through formwork and suspension.
이와 같이 거푸집에 타설되는 하층 콘크리트의 하중이 전적으로 상층 슬래브에 작용하면서 상층 슬래브에 무리한 하중이 가해질 수 있고, 구조적 안정성을 최대한 확보하기 위해서는 하층 슬래브의 콘크리트 시공이 필연적으로 상층 슬래브의 시공이 완료된 후라야 가능하다.As the load of the lower concrete placed on the formwork acts entirely on the upper slab, the excessive load may be applied to the upper slab. It is possible.
결국, 선 시공 슬래브의 완전 양생을 위해 시간이 필요한 만큼 공기 지연의 문제가 불가피하게 발생하게 된다.As a result, the problem of air delay inevitably occurs as time is required for the complete curing of the pre-installed slab.
따라서, 본 발명은 상기와 같은 문제점을 해결하기 위하여 발명한 것으로서, 보 및 슬래브의 역타 시공시에 1방향 보를 구축하기 위한 보 거푸집, 장스팬 적용이 가능한 골데크 타입의 딥 데크, 그리고 보 거푸집 및 골조용 기둥에 고정 설치되면서 1방향 배치되는 지지거더를 지지하기 위한 지지 브라켓을 사용함으로써, 1방향 보 및 데크 슬래브의 시공이 가능하고, 버림 콘크리트의 타설 작업이 축소 또는 삭제가 가능하며, 지지 브라켓 사용으로 선 시공된 상층 슬래브에 무리한 하중이 가해지 않도록 1방향 보 및 데크 슬래브의 시공이 가능해지는 지하층의 1방향 보 및 데크 슬래브 시공을 위한 하향 골조 타설 시스템 및 방법을 제공하는데 그 목적이 있다.Therefore, the present invention has been invented to solve the above problems, the beam formwork for constructing a one-way beam at the time of reversal construction of the beam and slab, the deep deck of the deck deck that can be applied long span, and the formwork and the beam formwork By using the support bracket for supporting the support girder arranged in one direction while fixedly installed in the frame pillar, the construction of the one-way beam and deck slab is possible, the casting work of the discarded concrete can be reduced or deleted, the support bracket It is an object of the present invention to provide a system and a method for laying down-frames for the construction of one-way beams and deck slabs in a basement layer, which enables construction of one-way beams and deck slabs so as not to apply excessive loads to the upper slabs pre-installed.
이하, 첨부한 도면을 참조하여 본 발명을 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.
본 발명은, 지하층의 보 및 슬래브를 역타 시공하는 방법에 있어서,The present invention is a method for reverse construction of a beam and a slab of the basement layer,
(a)지반 굴착 후, 보 거푸집들을 동바리로 지지시켜 설치하되, 가로 또는 세로 1방향으로만 길게 연속 배치하여 전체적으로 1방향 복수열로 설치하는 단계; (b)슬래브 거푸집 구조체로서 강판이 반복적으로 절곡 형성된 골데크 타입의 딥 데크를 나란한 보 거푸집 사이에 지지시켜 설치하는 단계; (c)상기 보 거푸집 및 딥 데크에 의해 형성된 보 및 슬래브 공간에 콘크리트를 타설 및 양생하여 1방향 보 및 데크 슬래브를 시공하는 단계; (d)지반 추가 굴착 후, 승강장치 및 승강장치의 와이어를 슬래브 통공에서 하방 안내하는 로울러 기구를 이용해 보 거푸집을 아래층 상응하는 높이로 현수 하강시켜, 보 거푸집과 딥 데크를 아래층 높이에 동일 방법으로 설치하는 단계; (e)보 및 슬래브 공간에 콘크리트를 타설 및 양생하여 아래층의 1방향 보 및 데크 슬래브를 시공하는 단계; 및 (f)상기 (d)단계 및 (e)단계를 반복하여 그 아래층의 1방향 보 및 데크 슬래브를 시공하는 단계;를 포함하는 것을 특징으로 한다.(a) after the ground excavation, the support is installed by supporting the dies in a group, but installed in a row in a plurality of rows as a whole in a continuous arrangement only in one horizontal or vertical direction; (b) supporting and installing a gold deck-type deep deck in which steel sheets are repeatedly bent as a slab formwork between side by side beam formwork; (c) constructing and curing concrete in the beam and slab space formed by the beam formwork and the deep deck to construct the one-way beam and deck slab; (d) After additional ground excavation, the beam formwork is lowered to the corresponding height downstairs by using roller mechanism to guide the lifting device and the lifting device's wires down the slab hole. Doing; (e) constructing and curing concrete in the beam and slab space to construct a one-way beam and deck slab of the lower floor; And (f) repeating steps (d) and (e) to construct one-way beams and deck slabs of the lower layer.
여기서, 상기 로울러 기구는, 슬래브 통공 내에 삽입되는 파이프 형태의 삽입본체부가 실제 슬래브 통공 내에 삽입되는 부분이면서 외주상에 통공 주변 슬래 브 상면에 걸쳐질 수 있도록 지지단이 설치된 하측 삽입부와, 로울러 지지부가 상부에 일체 결합된 상측 회전부로 분리 구성되어 있고, 상기 회전부가 삽입부에서 자유로이 회전될 수 있도록 삽입부 외주와 회전부 내주 사이에 베어링이 개재된 회전형 구조를 사용하는 것을 특징으로 한다.Here, the roller mechanism is a lower insert portion provided with a support end so that the pipe-shaped insertion main body portion inserted into the slab through hole is actually inserted into the slab through hole and is disposed on the outer periphery of the slab upper surface on the outer periphery, and the roller support. The upper part is separated and integrally coupled to the upper portion, characterized in that the rotating structure is used between the insertion portion outer peripheral portion and the rotating portion inner circumference so that the rotating portion can be freely rotated in the insertion portion.
다른 실시예로서, 본 발명은, 지하층의 보 및 슬래브를 역타 시공하는 방법에 있어서,As another embodiment, the present invention, in the method for reverse construction of the beam and the slab of the basement layer,
(a')지반 굴착 후 노출된 골조용 기둥 상부에 지지 브라켓을 설치하는 단계; (b')지지거더를 상기 지지 브라켓 위에 단부를 지지시키는 방법으로 상기 기둥간에 2개씩 나란히 설치하되, 가로 또는 세로 1방향으로만 길게 연속 배치하여 설치하는 단계; (c')보 거푸집을 상기 지지거더 위에 지지시켜 설치하되, 지지거더를 따라 길게 배치하여 전체적으로 1방향 복수열로 설치하는 단계; (d')슬래브 거푸집 구조체로서 강판이 반복적으로 절곡 형성된 골데크 타입의 딥 데크를 나란한 보 거푸집 사이에 지지시켜 설치하는 단계; (e')상기 보 거푸집 및 딥 데크에 의해 형성된 보 및 슬래브 공간에 콘크리트를 타설 및 양생하여 1방향 보 및 데크 슬래브를 시공하는 단계; (f')지반 추가 굴착 후, 지지 브라켓을 기둥으로부터 해체 및 현수 하강시킨 다음 아래층 상응하는 높이에 재설치하고, 지지거더를 보 거푸집과 함께 유압승강기 및 현수재로 현수 하강시켜, 지지거더 및 보 거푸집, 딥 데크를 아래층 높이에 동일 방법으로 설치하는 단계; (g')보 및 슬래브 공간에 콘크리트를 타설 및 양생하여 아래층의 1방향 보 및 데크 슬래브를 시공하는 단계; 및 (h')상기 (f')단계 및 (g')단계를 반복하여 그 아래층의 1방향 보 및 데크 슬래브를 시공 하는 단계;를 포함하는 것을 특징으로 한다. (a ') installing a support bracket on the exposed framework pillar after ground excavation; (b ') installing two support girders side by side between the pillars in such a manner as to support an end portion on the support bracket, and continuously installing the support girders in a longitudinal or longitudinal direction only; (c ') installing the beam formwork by supporting it on the support girder, and placing the beam form along the support girder so as to be installed in a plurality of rows in one direction as a whole; (d ') supporting and installing a gold deck-type deep deck in which steel sheets are repeatedly bent as a slab formwork between side by side beam formwork; (e ') constructing and curing concrete in the beam and slab space formed by the beam formwork and the deep deck to construct a one-way beam and deck slab; (f ') After additional ground excavation, the support bracket is dismantled and suspended from the column, and then reinstalled at the corresponding height downstairs, and the support girder is suspended with hydraulic lifts and suspension together with the support form, supporting girders and formwork Installing the deep deck at the height of the downstairs in the same manner; (g ') placing and curing concrete in the beam and slab space to construct a one-way beam and deck slab downstairs; And (h ') repeating steps (f') and (g ') to construct the one-way beam and deck slab of the lower layer.
한편, 본 발명은, 지하층의 보 및 슬래브를 역타 시공하기 위한 하향 골조 타설 시스템에 있어서,On the other hand, the present invention, in the down-frame skeleton placing system for reverse construction of the basement beam and slab,
1방향 보 및 데크 슬래브를 구축하기 위한 구조물로서,A structure for constructing one-way beams and deck slabs,
각 골조용 기둥에서 해당 층의 상응하는 높이에 설치되는 1방향 지지 브라켓과; 상기 1방향 지지 브라켓 위에 단부가 고정 지지되는 형태로 상기 기둥간에 2개씩 나란히 설치되되, 가로 또는 세로 1방향으로만 길게 연속 배치되어 설치되는 지지거더와; 상기 지지거더 위에 지지되어 설치되되, 지지거더를 따라 길게 배치되어 전체적으로 1방향 복수열로 설치되는 보 거푸집과; 슬래브 거푸집 구조체로서 강판이 반복적으로 절곡 형성된 골데크 타입으로 제작되어 단부가 나란한 보 거푸집 위에 지지되어 설치되는 딥 데크;를 포함하는 것을 특징으로 한다. A one-way support bracket installed at the corresponding height of the floor in each frame pillar; A support girder installed side by side between the pillars in a form in which an end is fixedly supported on the one-way support bracket, the support girder being continuously disposed in a horizontal or vertical one direction only; A support form installed on the support girder, the support form being long along the support girder and installed in a plurality of rows in one direction; It is characterized in that it comprises a; deep deck as the slab formwork structure is made of a steel deck is repeatedly formed bent over the formwork is formed on a side-by-side beam formwork.
이하, 첨부한 도면을 참조하여 본 발명을 더욱 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.
본 발명은 지하층의 1방향 보 및 데크 슬래브 시공을 위한 하향 골조 타설 시스템 및 방법에 관한 것으로서, 보 및 슬래브의 역타 시공시에 1방향 보를 구축하기 위한 보 거푸집과, 장스팬 적용이 가능한 골데크 타입의 딥 데크(Deep Deck)를 사용한 것에 주안점이 있는 것이다.The present invention relates to a system and a method for laying down frames for the construction of a one-way beam and a deck slab in a basement layer, and to a beam formwork for constructing a one-way beam at the time of reversing the construction of a beam and a slab, and to a long deck, a gold deck type The main focus is on using Deep Deck.
도 1은 본 발명에 따라 시공된 지하구조물의 1방향 넓은 보(wide girder) 및 데크 슬래브를 도시한 평면도이고, 도 2는 도 1의 선 'A-A'를 따라 취한 단면도, 도 3은 도 1의 선 'B-B'를 따라 취한 단면도이며, 도 4는 본 발명에 따라 시공된 지하구조물의 데크 슬래브를 도시한 저면사시도이다.1 is a plan view showing a wide girder and deck slab in one direction of the underground structure constructed in accordance with the present invention, FIG. 2 is a cross-sectional view taken along the line 'A-A' of FIG. 1, FIG. 4 is a cross-sectional view taken along the line 'B-B', and FIG. 4 is a bottom perspective view showing a deck slab of an underground structure constructed according to the present invention.
도시한 바와 같이, 본 발명에 의해 시공된 지하구조물은 각 층 시공시에 1방향 보 거푸집 및 딥 데크를 사용하여 시공됨으로써, 종래와 같은 가로, 세로 2방향이 아닌 1방향의 보(BG) 및 데크 슬래브(BS)를 포함하게 된다.As shown, the underground structure constructed by the present invention is constructed by using a one-way beam formwork and a deep deck at the time of each floor construction, so that the beam (BG) in one direction rather than the two horizontal and vertical directions as in the prior art and It will include a deck slab (BS).
도 1 내지 도 4에서 도면부호 101은 골조용 기둥으로서 CFT 기둥을 나타낸다.1 to 4,
이하, 도 1 내지 도 4에 도시한 1방향 보(BG) 및 데크 슬래브(BS)를 시공하기 위한 본 발명의 제1실시예를 설명하면 다음과 같다. Hereinafter, a first embodiment of the present invention for constructing the one-way beam BG and the deck slab BS shown in FIGS. 1 to 4 will be described.
도 5는 본 발명의 제1실시예에서 보 거푸집 및 딥 데크 설치 후 콘크리트가 타설된 상태를 나타낸 단면도로서, 이는 도 1의 선 'C-C'와 동일한 위치 및 방향에서 취한 단면도이고, 도 6은 본 발명의 제1실시예에서 보 거푸집 및 딥 데크 설치상태를 보여주는 사시도이다.FIG. 5 is a cross-sectional view showing a state in which concrete is poured after installing the formwork and the deep deck in the first embodiment of the present invention, which is a cross-sectional view taken at the same position and direction as the line 'C-C' of FIG. Is a perspective view showing the formwork and the deep deck installation in the first embodiment of the present invention.
본 발명의 제1실시예는, 각 층의 1방향 보(BG) 및 데크 슬래브(BS) 구축을 위한 구조물로서, 보 시공을 위하여 골조용 기둥(101)간에 길게 설치되되, 가로, 세로 2방향이 아닌 가로 또는 세로 1방향으로만 길게 연속 배치되면서 동바리(104)에 의해 지지되는 보 거푸집(110)과; 데크 슬래브 시공을 위하여 나란한 양측의 보 거푸집(110)에 단부가 지지된 상태로 설치되는 딥 데크(120)를 포함한다.The first embodiment of the present invention is a structure for building the one-way beam (BG) and deck slab (BS) of each layer, it is installed between the
여기서, 상기 보 거푸집(110)은 사각강관(113,114)들을 상, 하로 적층하되 상, 하측의 사각강관들을 종, 횡으로 교차시킨 뒤 용접하여 거푸집 지지틀(112)을 구성하고, 이 거푸집 지지틀(112)에서 상측 사각강관(113)의 양 단부 위에는 보 하 단 측면부를 성형하기 위한 측면 사각강관(115)을 횡으로 배치 후 용접 고정하며, 상기 상측 사각강관(113) 위로는 거푸집 하판(116)을 설치하여서 구성된 것이다. Here, the
상기 보 거푸집(110)에서 하측 사각강관(114)과 거푸집 하판(116)은 1방향으로 길게 형성 구비되어, 전체적으로는 보 거푸집(110)이 보(BG)의 길이방향을 따라 길게 배치된 상태에서 하측 사각강관(114)이 버림 콘크리트(103) 위의 동바리(104)에 의해 지지되어 설치된다.In the
또한, 상기 딥 데크(120)는 강판이 반복적으로 절곡 형성된 구조로 되어 있으면서 일반 데크 플레이트에 비해 춤이 깊은 구조로 되어 있는 슬래브 거푸집 구조체로서, 양 단부가 보 거푸집(110)의 측면 사각강관(115)에 얹혀져 설치된다.In addition, the
또한, 상기 딥 데크(120)의 마구리측은 엔드 클로우저(121)가 설치되어 마감되는데, 이 엔드 클로우저(121)는 콘크리트 타설시에 딥 데크(120)의 리브 사이에 생기는 측면 사각강관(115)과 딥 데크(120) 사이의 틈을 막아 콘크리트가 아래로 새는 것을 방지하게 된다.In addition, the finish side of the
상기 엔드 클로우저(121)에는 외측을 따라 딥 데크(120)의 마구리측 형상과 대응하는 형상의 협지부(122)가 형성 구비되며, 딥 데크(120)를 상기 협지부(122)에 끼워 고정시킴으로써, 딥 데크(120)와 엔드 클로우저(121)가 결합되도록 되어 있다.The end closer 121 is provided with a
한편, 위와 같은 본 발명의 제1실시예를 이용하여 지하구조물의 1방향 보 및 데크 슬래브를 시공하는 과정을 설명하면 다음과 같다. Meanwhile, a process of constructing a one-way beam and deck slab of an underground structure using the first embodiment of the present invention as described above is as follows.
도 7a ~ 도 7e는 본 발명의 제1실시예를 이용하여 지하구조물의 1방향 보 및 데크 슬래브를 시공하는 과정을 나타낸 도면이고, 도 8은 본 발명의 제1실시예에서 보 거푸집이 현수 하강장치에 의해 하강되는 상태를 나타낸 사시도이며, 도 9a와 도 9b는 본 발명의 제1실시예에 적용되는 로울러 기구의 사시도와 단면도이다. 7A to 7E are views illustrating a process of constructing a one-way beam and a deck slab of an underground structure using the first embodiment of the present invention, and FIG. 8 shows a formwork suspension suspension in the first embodiment of the present invention. 9A and 9B are a perspective view and a sectional view of the roller mechanism applied to the first embodiment of the present invention.
우선, 흙막이벽(도시하지 않음)의 안쪽 지중에 골조용 기둥, 예를 들어 CFT 기둥(101)을 수직 시공하고, 제1지하층의 보 및 슬래브 시공을 위하여 1차로 소정 깊이만큼 지반을 굴착한 후, 굴착된 지반 위에 시공될 보의 위치를 따라서 버림 콘크리트(103)를 타설한다(도 7a 참조).First, vertically construct a framed pillar, for example, a
이후, 버림 콘크리트(103)를 지지기반으로 하여 보 거푸집(110)들을 동바리(104)에 지지시켜 설치하되, 시공하는 1방향 보의 설계방향을 따라 연속 배치하여 설치한다.Subsequently, the
요컨대, 보 거푸집(110)들은 가로, 세로 2방향이 아닌 도 1에 나타낸 보(BG) 길이방향을 따라 가로 또는 세로 1방향으로만 길게 연속 배치되고, 연속 배치된 보 거푸집(110)들을 하나의 열로 할 때 전체적으로는 1방향 배치된 복수열의 보 거푸집 구조로 설치된다.In other words, the
이후, 보 거푸집(110)의 측면 사각강관(도 5의 도면부호 115임)에 단부를 지지시키는 방법으로 딥 데크(120)를 나란한 양측 보 거푸집(110) 사이에 걸쳐 설치하고(도 7b 참조), 딥 데크(120)의 마구리측에는 전술한 바대로 엔드 클로우저(도 6의 도면부호 121임)가 설치되어 마감된다.Subsequently, the
상기와 같이 보 거푸집(110)과 딥 데크(120)가 설치되고 나면, 보 거푸집(110)과 딥 데크(120)가 형성하는 보 및 슬래브 공간 내부에 보강철근(도 6에서 도 면부호 105임)을 배근하고, 이후 콘크리트를 동시 타설하여 제1지하층의 보(BG1) 및 슬래브(BS1) 시공을 완료한다(도 7c 참조).After the
이와 같이 시공된 제1지하층의 보(BG1) 및 슬래브(BS1)는 도 1 내지 도 4에 도시한 형태, 즉 1방향 보 및 데크 슬래브가 된다. The beams BG1 and slab BS1 of the first underground layer constructed as described above become the shapes shown in FIGS. 1 to 4, that is, the one-way beam and the deck slab.
이와 같이 콘크리트가 타설되어 양생되고 나면, 제2지하층의 보 및 슬래브 시공을 위하여 2차로 지반을 굴착한 후, 굴착된 지반 위에 시공될 보의 위치를 따라 버림 콘크리트(103)를 타설하고, 이후 제1지하층에서 사용된 보 거푸집(110)을 현수 하강장치를 이용하여 제2지하층의 상응하는 높이로 하강시켜 제1지하층에서와 동일하게 설치한다(도 7d 참조).After the concrete is poured and cured as described above, the ground is excavated secondly for the construction of the beam and the slab of the second underground layer, and then the discarded
즉, 제2지하층의 상응하는 높이에서 버림 콘크리트(103)를 지지기반으로 하여 상기 보 거푸집(110)을 동바리(104)에 지지시켜 설치하되, 시공하는 1방향 보의 설계방향으로 보 거푸집(110)들을 길게 연속 배치하여 설치한다.That is, the
상기 보 거푸집(110)을 현수 하강시키기 위한 하강장치는 본 발명자가 출원한 실용신안등록번호 제367259호(2004.11.1 등록)에 개시되어 있으며, 이에 개시된 로울러 기구를 사용하여도 무방하나, 더욱 바람직하기로는 콘크리트 시공된 슬래브에서 용이하게 회전될 수 있도록 개량한 도 9a 및 도 9b의 회전형 로울러 기구(136)를 사용하는 것이 좋다.The lowering device for suspending the
도 8에서 도면부호 131은 선 시공된 상층 슬래브(BS) 또는 보(BG) 위에 위치되는 승강장치를 나타내며, 이 승강장치(131)에서도 도면부호 132는 메인 와이어(134)를 감고 풀게 되는 윈치(winch)를 나타낸다.In FIG. 8,
도면부호 133은 메인 와이어(134)를 안내하는 가이드 로울러를 나타낸다.
그 구성을 살펴보면, 하부가 선 시공한 상층 슬래브(BS)의 통공(106a) 내에 삽입되어 거푸집 하강용 서브 와이어(135)가 통공(106a)을 통과하도록 경로 설정하는 내부공간을 가지는 본체(137)와, 상기 본체 상부의 내부공간에 회전 가능하게 장착되어 상기 서브 와이어(135)를 본체 내부공간을 통해 수직 하방으로 안내하는 로울러(137a)를 포함하여 이루어진다. Looking at the configuration, the
여기서, 상기 본체(137)는 파이프 형태로 제작되어 슬래브(BS)의 통공(106a) 내에 삽입되는 삽입본체부(138)와, 전체적으로 U자 형상을 가지는 판상 구조로 구비되어 양 측벽상에 상기 로울러(137a)가 회전 가능하게 장착되고 상기 삽입본체부(138)의 상부에 일체로 결합된 로울러 지지부(139)로 구성된다.Here, the
단, 회전형 로울러 기구(136)는, 상기 삽입본체부(138)가 실제 슬래브(BS)의 통공(106a) 내에 삽입되는 하측의 삽입부(138a)와, 상기 로울러 지지부(139)가 상부에 일체 결합된 상측의 회전부(138b)로 분리 구성되고, 상기 회전부(138b)가 삽입부(138a)에서 자유로이 회전될 수 있도록 삽입부(138a)의 외주와 회전부(138b)의 내주 사이에 베어링(141)이 개재된 구조로 되어 있는 것이다.However, the
또한, 상기 회전형 로울러 기구(136)에서 삽입부(138a) 외주상에는 통공(106a) 주변의 슬래브(BS) 상면에 걸쳐질 수 있도록 지지단(142)을 설치하여, 로울러 기구(136)가 상기 지지단(142)에 의해 슬래브(BS)상에서 지지되도록 한다.In addition, a
상기 로울러 기구(136)를 설치하여 서브 와이어(135)가 슬래브 상측에서 슬래브 하측으로 연결되도록 하기 위해서는 슬래브 구축용 거푸집 구조체, 즉 딥 데 크(120)의 저면에 통공(106a) 위치의 홀이 미리 가공되어야 하며, 이 홀에 원형 파이프를 설치한 후 슬래브 콘크리트 시공을 하여 슬래브에 상기 원형 파이프에 의해 통공(106a)이 형성되도록 할 수 있다.In order to install the
상기 하강장치(130)에서는 승강장치(131)의 윈치(132)에 감겨진 하나의 메인 와이어(134)에 필요한 수만큼의 서브 와이어(135)가 연결되어 작업이 이루어질 수 있는 바, 각 서브 와이어(135)가 각 통공(106a) 내에 삽입 설치된 로울러 기구(136)에 의해 수직 안내되어 보 거푸집(110)을 지지하고 있는 파이프(117)에 연결 고정된다.In the lowering
결국, 승강장치(131)가 구동되어 윈치(132)에 감겨진 메인 와이어(134)가 풀리게 되면 서브 와이어(135)가 동시에 같은 양만큼 하강하므로 보 거푸집(110) 및 파이프(117)가 균형있게 천천히 하강될 수 있다.As a result, when the
특히, 본 발명에서 회전형 로울러 기구(136)를 사용하는 경우에는 회전부(138b) 및 로울러 지지부(139)를 쉽게 회전시킬 수 있는 바, 서브 와이어(135)의 방향에 따라 로울러 지지부(139)의 방향 설정을 쉽게 할 수 있고, 따라서 로울러 지지부(139)의 정확한 방향이 조정된 상태에서 보다 안정적으로 와이어(135) 및 보 거푸집(110)을 하강시킬 수 있게 된다.In particular, when the
전술한 바와 같이 각 보 거푸집(110)을 제2지하층 높이로 현수 하강시켜 설치한 후에는 제1지하층에서와 동일하게 딥 데크(120)를 설치하고, 이어 보 거푸집(110)과 딥 데크(120)가 형성하는 보 및 슬래브 공간 내부에 보강철근을 배근한 후, 콘크리트를 동시 타설하여 제2지하층의 보(BG2) 및 슬래브(BS2) 시공을 완료한다 (도 7e 참조).As described above, after each
이후, 도면으로 나타내지는 않았지만, 제3지하층 및 그 이하 지하층의 보 및 슬래브를 시공하기 위하여 상기 과정을 반복하게 되는데, 각 층의 보 및 슬래브를 동일한 방법을 이용해 아래층으로 내려가면서 단계적으로 시공한다.Thereafter, although not shown in the drawings, the above process is repeated to construct the beams and slabs of the third basement layer and the basement layer below, and the beams and slabs of each layer are constructed in steps while descending to the lower floor by the same method.
이와 같이 시공되는 각 지하층의 보 및 슬래브는 도 1 내지 도 4에 도시한 형태, 즉 1방향 보 및 데크 슬래브가 된다. The beams and slabs of each basement layer constructed in this way become the shapes shown in FIGS. 1 to 4, that is, the one-way beams and the deck slabs.
이러한 본 발명의 제1실시예 구성 및 이를 이용한 지하구조물의 구축방법에 의하면, 보 거푸집이 가로, 세로 2방향이 아닌 1방향으로만 설치되어 버림 콘크리트 역시 1방향으로만 타설하면 되기 때문에, 종래와 같이 가로, 세로 2방향 또는 지반 전 영역에 타설되던 것에 비해 버림 콘크리트의 타설량을 줄일 수 있고, 결국 콘크리트 폐기물의 발생량을 줄일 수 있게 된다. According to the configuration of the first embodiment of the present invention and the construction method of the underground structure using the same, since the formwork is installed only in one direction rather than in the horizontal and vertical two directions, the discarded concrete also needs to be poured in only one direction. Likewise, it is possible to reduce the amount of discarded concrete, and to reduce the amount of concrete waste, as compared to the case where it is placed in the horizontal, vertical two directions, or the entire ground.
다음으로, 도 1 내지 도 4에 도시한 지하층의 1방향 보(BG) 및 데크 슬래브(BS)를 시공하기 위한 본 발명의 제2실시예를 설명하면 다음과 같다.Next, a second embodiment of the present invention for constructing the one-way beam BG and the deck slab BS of the basement layers shown in FIGS. 1 to 4 will be described.
도 10은 본 발명의 제2실시예에서 기둥 지지되는 이동 조립식 지지 브라켓 및 지지거더가 설치된 상태를 도시한 평면도이고, 도 11은 본 발명의 제2실시예에서 지지거더, 보 거푸집, 딥 데크가 설치된 상태의 저면도이다.FIG. 10 is a plan view illustrating a state in which a movable prefabricated support bracket and a support girder are installed in a second embodiment of the present invention, and FIG. 11 is a support girder, formwork, and deep deck in a second embodiment of the present invention. Bottom view of the installed state.
그리고, 도 12는 본 발명에 따른 제2실시예의 각 구성이 모두 설치된 상태에서 보 및 슬래브 콘크리트가 타설된 상태를 나타낸 단면도로서, 도 11의 선 'D-D'와 동일한 위치 및 방향에서 취한 단면도이다. FIG. 12 is a cross-sectional view showing a state in which beams and slab concrete are poured in a state where all the components of the second embodiment according to the present invention are installed, and taken in the same position and direction as the line 'D-D' of FIG. 11. to be.
도 13은 도 12에서 주요부를 확대하여 나타낸 단면도이다.FIG. 13 is an enlarged cross-sectional view of a main part of FIG. 12.
그리고, 도 14a는 본 발명에 따른 제2실시예의 각 이동 조립식 지지 브라켓에서 H-형강 지지거더가 지지된 상태를 도시한 사시도이고, 도 14b는 본 발명에 따른 제2실시예의 각 이동 조립식 지지 브라켓에서 지지거더간을 결합한 예를 도시한 사시도이다.14A is a perspective view showing a state in which the H-shaped steel support girder is supported in each movable prefabricated support bracket of the second embodiment according to the present invention, and FIG. 14B is a respective movable prefabricated support bracket of the second embodiment according to the present invention. Is a perspective view showing an example of coupling between the support girders.
도시한 바와 같이, 본 발명의 제2실시예는, 각 층의 1방향 보(BG) 및 데크 슬래브(BS) 구축을 위한 구조물로서, 각 골조용 기둥(101)의 해당 층 상응하는 높이에 설치되는 이동 조립식 지지 브라켓(150)과; 상기 이동 조립식 지지 브라켓(150) 위에 단부가 고정 지지되는 형태로 골조용 기둥(101)간에 길게 설치되되, 가로, 세로 2방향이 아닌 1방향으로만 길게 연속 배치되어 설치되는 지지거더(153)와; 이 지지거더(153)에 의해 지지되면서 지지거더(153)를 따라 길게 설치되는 보 거푸집(110)과; 나란한 양측의 보 거푸집(110)에 단부가 지지된 상태로 설치되는 딥 데크(120)를 포함한다.As shown, the second embodiment of the present invention is a structure for constructing a one-way beam (BG) and a deck slab (BS) of each floor, and installed at the corresponding height of the corresponding floor of each frame pillar (101) Moving
여기서, 상기 이동 조립식 지지 브라켓(150)은 본 발명자가 출원한 실용신안등록번호 제372315호(2004.12.29 등록)에 개시되어 있다. Here, the mobile
개시된 바에 따르면, 상기 이동 조립식 지지 브라켓(150)은 상기 지지거더(153)를 하측에서 지지하도록 되어 있으며, 특히 각각 승강용 현수재(174)가 고정되고 서로 마주보도록 대응되는 접합(또는 분할)면을 따라 접합 또는 분할되는 한 쌍의 서브 프레임(151)으로 구성되어 있다. According to the disclosure, the movable
상기 두 서브 프레임(151)이 상호 조립된 상태에서 중앙의 상부 및 하부로 위치되는 한 쌍의 링패널(152)이 골조용 기둥(101)의 둘레면을 동시에 압착하게 될 경우 상기 이동 조립식 지지 브라켓(150)은 골조용 기둥(101)의 정해진 위치에 고정되게 된다.The movable prefabricated support bracket when the pair of
상기 이동 조립식 지지 브라켓(150)은 골조용 기둥(101)상에 고정 지지된 상태에서 보 및 슬래브의 콘크리트 시공시 지지거더(153)를 통해 전달되는 하중을 충분히 견딜 수 있도록 되어 있으며, 특히 보 및 슬래브의 콘크리트 시공 후에는 쉽게 해체가 가능하여 상층의 시공이 완료되면 유압승강기 및 현수재를 이용해 하층으로 이동시킬 수 있고, 또한 하층 이동 후 쉽게 재설치할 수 있도록 되어 있다. The movable
또한, 개시된 바에 따르면, 이동 조립식 지지 브라켓(150)으로서 각형 및 원형 지지 브라켓이 제시되어 있으며, CFT 기둥 뿐만 아니라 H-형강 기둥에 사용할 수 있는 브라켓 구조 또한 제시되어 있다.In addition, as disclosed, angular and circular support brackets are shown as mobile
지지거더(153)는 보 거푸집(110)을 지지하기 위한 철골보로서 H-형강으로 실시될 수 있고, 양 단부가 두 골조용 기둥(101)의 이동 조립식 지지 브라켓(150)에 지지된 상태에서, 지지거더(153) 단부의 하부 플랜지와 이동 조립식 지지 브라켓(150)의 서브 프레임(151)의 상부 플랜지를 조여주는 클램프(154)가 설치됨으로써, 지지거더(153)와 브라켓(150)이 서로 결합된다.The
직선상으로 연이어 배치되는 두 지지거더(153)는 각 이동 조립식 지지 브라켓(150)에서 서로 분리된 상태로 지지시키거나, 바람직하기로는 일체로 결합시켜 지지시킬 수 있는데, 직선상으로 연이어 배치된 모든 지지거더(153)들이 도 14b와 같이 단부간에 서로 결합되어 일체화되는 경우, 각 지지거더에서의 처짐량은 감소될 수 있고, 따라서 구조적으로 보다 유리해진다.The two
도 14b를 설명하면, 연이어 배치되는 전후 지지거더(153)간 결합을 위하여, 각 지지거더(153) 끝단에는 엔드 플레이트(155)를 용접하여 설치하고, 두 지지거더(153)의 엔드 플레이트(155) 사이에는 그 간격만큼 복수개의 심 플레이트(Shim Plate)(156)를 개재한다.Referring to FIG. 14B, in order to engage the front and
이 상태에서 양측 엔드 플레이트(155)와 심 플레이트(156)에 볼트(157a)를 관통시켜 끼우고, 반대쪽에서 너트(미도시됨)를 체결하여 양측 엔드 플레이트(155)가 상기 볼트(157a) 및 너트에 의해 서로 결합되도록 한다.In this state, the
도 15a는 본 발명의 제2실시예에서 나란한 두 지지거더의 설치상태를 나타낸 평면도이고, 도 15b는 도 15a의 선 'E-E'를 따라 취한 단면도로서 나란한 두 지지거더간에 횡좌굴보강앵글이 설치된 상태를 도시한 것이며, 도 15c는 도 15a의 선 'F-F'를 따라 취한 단면도로서 승강용 현수재가 지지거더에 연결된 상태를 도시한 것이다.Figure 15a is a plan view showing the installation state of two support girders side by side in the second embodiment of the present invention, Figure 15b is a cross-sectional view taken along the line 'E-E' in Fig. 15a the lateral buckling reinforcement angle between the two support girders in parallel FIG. 15C is a cross-sectional view taken along the line 'F-F' of FIG. 15A and shows a state in which the lifting suspension is connected to the support girder.
이에 도시한 바와 같이, 두 이동 조립식 지지 브라켓(150) 사이에서 지지거더(153)는 2개씩 평행하게 배치되어 설치되는데, 지지거더(153) 중간쯤 위치에서 양측 지지거더(153)의 마주보는 내측에 제1거싯 플레이트(158)가 용접 설치되고, 두 지지거더(153)의 제1거싯 플레이트(158) 사이에는 두 개의 횡좌굴보강앵글(159)이 'X' 형태로 서로 교차 배치되어 연결 설치된다.As shown in the figure, between two movable
또한, 상기 지지거더(153)는 이동 조립식 지지 브라켓(150)과 마찬가지로 보 및 슬래브의 콘크리트 시공 후에는 하층 시공을 위하여 선 시공된 상층 슬래브 위의 유압승강기(미도시됨) 및 이에 연결된 현수재(172)를 이용해 하층으로 이동시켜 동일하게 재설치하게 되는데, 15a에 나타낸 바와 같이 도면상의 좌우 양측에 현수재 하단이 연결되는 재킹 포인트(도면부호 163 위치)가 설정된다.In addition, the
나란한 두 지지거더(153)가 안정적으로 하강될 수 있도록 지지거더(153)의 길이방향 중심으로부터 동일한 거리의 좌우 두 위치에 재킹 포인트가 설정되는데, 이 재킹 포인트에서 현수재 하단을 연결하기 위하여 재킹 포인트 위치의 두 지지거더(153) 내측에는 제2거싯 플레이트(161)가 용접 설치되고, 양측 지지거더(153)의 제2거싯 플레이트(161) 사이에는 H-형강(162)이 연결 설치된다.A jacking point is set at two left and right positions of the same distance from the longitudinal center of the
그리고, 상기 H-형강(162)의 상부 플랜지 상면에는 연결 브라켓(163)이 설치됨과 아울러 이 연결 브라켓(163)에는 현수재(172) 하단이 핀 결합되어서 결국 현수재(172)가 H-형강(162)을 통해 두 지지거더(153)에 동시 연결되는 구조가 된다.In addition, a connecting
본 발명에서 콘크리트 시공 중인 층의 콘크리트 하중은 보 거푸집(110) 및 지지거더(153)를 통해 이동 조립식 지지 브라켓(150) 및 골조용 기둥(101)이 최종 전달받아 지지하는 것이며, 상기 현수재(172)는 콘크리트 하중에 대한 지지 용도가 아닌 콘크리트 시공 후 유압승강기에 연결하여 이동 조립식 지지 브라켓(150) 및 지지거더(153)의 단순 승강용도로 사용되는 것들이다.In the present invention, the concrete load of the layer under construction is to support the mobile
한편, 본 발명의 제2실시예 구성에서, 상기 보 거푸집(110)은 도 13에 도시한 바와 같이 이동 조립식 지지 브라켓(150)에 지지되는 지지거더(153) 위에 고정된다. On the other hand, in the configuration of the second embodiment of the present invention, the
상기 보 거푸집(110)에서 하측 사각강관(114)과 거푸집 하판(116)은 지지거더(153)의 길이방향을 따르도록 1방향으로 길게 형성 구비되어, 전체적으로는 보 거푸집(110)이 보 길이방향을 따라 길게 배치된 상태에서 하측 사각강관(114)을 매개로 지지거더(153)에 의해 지지되어 설치된다.In the
상기 보 거푸집(110)이 지지거더(153) 위에 완전 고정될 수 있도록, 보 거푸집(110)의 하측 사각강관(114)과 지지거더(153)의 상부 플랜지는 볼팅 또는 용접에 의해 고정되는 앵글 브라켓(도시하지 않음)으로 연결할 수도 있다.An angle bracket is fixed by bolting or welding so that the lower
그리고, 상기 딥 데크(120)는 그 형상이나 구조, 양 단부가 보 거푸집(110)의 측면 사각강관(115)에 얹혀져 설치되는 점, 마구리측에 엔드 클로우저(121)가 설치되어 마감되는 점 등이 제1실시예와 모두 동일하며, 그에 대한 상세한 설명은 앞서 설명하였으므로 여기서는 생략하기로 한다.The
한편, 위와 같은 본 발명의 제2실시예를 이용하여 지하구조물의 1방향 보 및 데크 슬래브를 시공하는 과정을 설명하면 다음과 같다. Meanwhile, a process of constructing a one-way beam and deck slab of an underground structure using the second embodiment of the present invention as described above is as follows.
도 16a ~ 도 16e는 본 발명의 제2실시예를 이용하여 지하구조물의 1방향 보 및 데크 슬래브를 시공하는 과정을 나타낸 도면이다.16A to 16E are views illustrating a process of constructing a one-way beam and a deck slab of an underground structure using the second embodiment of the present invention.
우선, 흙막이벽(도시하지 않음)의 안쪽 지중에 골조용 기둥, 예를 들어 CFT 기둥(101)을 수직 시공한 후, 제1지하층의 보 및 슬래브 시공을 위해 1차로 소정 깊이만큼 지반을 굴착하여 CFT 기둥(101)의 상부 일부가 노출되도록 한다(도 16a 참조).First, after constructing vertically framed pillars, for example,
이후, 노출된 각 CFT 기둥(101)에서 제1지하층의 상응하는 높이에 이동 조립식 지지 브라켓(150)을 설치하고, 이웃한 두 이동 조립식 지지 브라켓(150)에 단부를 지지시키는 방법으로 지지거더(153)를 기둥간에 설치한다.Subsequently, in each exposed
이때, 지지거더(153)들은 1방향 보의 설계방향을 따라 길게 설치하는데, 지지거더(153)들을 가로, 세로 2방향이 아닌 1방향으로만 직선상으로 연속 배치하며, 지지 브라켓(150) 사이에 2개씩을 나란히 지지시킨다.At this time, the
지지거더(153)는 지지 브라켓(150)에 지지시킨 상태에서 클램프(도 14a 및 도 14b에서 도면부호 154임)로 체결하여 고정한다.The
이후, 지지거더(153) 위에 보 거푸집(110)을 고정시켜 설치하는데, 보 거푸집(110) 역시 1방향 보의 설계방향, 즉 지지거더(153)의 길이방향을 따라 길게 배치하여 설치한다.Subsequently, the
요컨대, 지지거더(153)와 보 거푸집(110)은 가로, 세로 2방향이 아닌 도 1에 나타낸 보(BG) 길이방향을 따라 가로 또는 세로 1방향으로만 길게 연속 배치되고, 연속 배치된 보 거푸집(110)들을 하나의 열로 할 때 전체적으로는 1방향 배치된 복수열의 보 거푸집 구조로 설치된다.In other words, the
이후, 보 거푸집(110)의 측면 사각강관에 단부를 지지시키는 방법으로 딥 데크(120)를 나란한 양측 보 거푸집(110) 사이에 걸쳐 설치하고(도 16b 참조), 딥 데크(120)의 마구리측에는 전술한 바대로 엔드 클로우저가 설치되어 마감된다.Subsequently, the
상기와 같이 보 거푸집(110)과 딥 데크(120)가 설치되고 나면, 보 거푸집(110)과 딥 데크(120)가 형성하는 보 및 슬래브 공간 내부에 보강철근을 배근하고, 이후 콘크리트를 동시 타설하여 제1지하층의 보(BG1) 및 슬래브(BS1) 시공을 완료한다(도 16c 참조).After the
이와 같이 시공되는 제1지하층의 보(BG1) 및 슬래브(BS1)는 도 1 내지 도 4 에 도시한 형태, 즉 1방향 보 및 데크 슬래브가 된다. The beams BG1 and slab BS1 of the first underground layer constructed in this way become the shapes shown in FIGS. 1 to 4, that is, one-way beams and deck slabs.
이와 같이 콘크리트가 타설되어 양생되고 나면, 제2지하층의 보 및 슬래브 시공을 위하여 2차로 지반을 굴착한 후, 이동 조립식 지지 브라켓(150)과 지지거더(153), 보 거푸집(110)을 제1지하층에서 해체 및 하강시켜 제2지하층의 상응하는 높이에 동일하게 재설치하게 된다(도 16d 참조).After the concrete is poured and cured as described above, after excavating the ground secondly for the construction of the beam and slab of the second basement layer, the movable
하강시에는 지지 브라켓(150) 및 지지거더(153)에 연결된 현수재(172,174)와 현수재를 하강시키기 위한 유압승강기(173)를 이용하는데, 지지거더(153)를 현수재(172)로 지지시켜 고정한 상태에서 지지 브라켓(150)을 우선 분할 해체 후 하강시키고, 지지 브라켓(150)을 제2지하층 높이에 재설치한 뒤 지지거더(153)를 보 거푸집(110)과 함께 내린다.When descending, the
이러한 하강 작업을 위해서는 지지 브라켓(150)과 지지거더(153)에 연결된 각 현수재(172,174)가 각 위치에서 콘크리트 시공된 제1지하층의 보(BG1)를 통과해야 하는 바, 이를 위하여 제1지하층의 보(BG1)에는 콘크리트 시공시에 현수재가 통과할 수 있는 통공(도시하지 않음)이 시공되어야 한다.For such a lowering operation, each of the
이 통공의 시공은 종래 무지보 역타설 거푸집 공법에서 현수재가 통과하도록 된 통공의 시공과 동일한 방법이 이용될 수 있으며, 또는 현수재 위치에서 보 거푸집(110)의 거푸집 하판(116)에 홀을 형성하고 이 홀에 원형 파이프를 설치한 후 슬래브 콘크리트 시공을 하여, 보(BG1)에 상기 원형 파이프에 의해 통공이 형성되도록 할 수 있다. The construction of the through-hole can be used the same method as the construction of the through-hole to allow the suspension material to pass in the conventional non-reversing formwork method, or to form a hole in the
이동 조립식 지지 브라켓(150)은 실용신안등록번호 제372315호에 개시된 바 와 같이 분할 해체하게 되면 분할된 두 부분 중 어느 한쪽 부분을 우선적으로 하강 시킬 수 있는 바, 한쪽 부분씩 나누어 하강시킨 다음 제2지하층 높이에서 재조립한다. When the mobile
지지거더(153)의 하강시에는 나란한 2개를 보 거푸집(110)과 함께 하강시킬 수 있다.When the
상기 지지거더(153)는 기둥(101)간 지지거더(153)와 보 거푸집(110)을 한 단위로 하여 한 단위씩 순차 하강시키거나, 1방향 직선상으로 연속 배치된 지지거더(153)들이 모두 도 14b와 같이 단부간에 결합되어 있는 경우라면, 이들 지지거더(153)들을 보 거푸집(110)과 함께 모두 동시 하강시킬 수 있다.The support girders 153 are sequentially lowered by one unit by using the
이와 같이 제2지하층의 높이에 지지 브라켓(150), 지지거더(153), 보 거푸집(110)을 모두 설치하고 나면, 딥 데크(120)를 제1지하층에서와 동일하게 설치하고, 이어 보 거푸집(110)과 딥 데크(120)가 형성하는 보 및 슬래브 공간 내부에 보강철근을 배근한 후, 콘크리트를 동시 타설하여 제2지하층의 보(BG2) 및 슬래브(BS2) 시공을 완료한다(도 16e 참조).After the
이후, 도면으로 나타내지는 않았지만, 제3지하층 및 그 이하 지하층의 보 및 슬래브를 시공하기 위하여 상기 과정을 반복하게 되는데, 각 층의 보 및 슬래브를 동일한 방법을 이용해 아래층으로 내려가면서 단계적으로 시공한다.Thereafter, although not shown in the drawings, the above process is repeated to construct the beams and slabs of the third basement layer and the basement layer below, and the beams and slabs of each layer are constructed in steps while descending to the lower floor by the same method.
이와 같이 시공되는 각 지하층의 보 및 슬래브는 도 1 내지 도 4에 도시한 형태, 즉 1방향 보(BG) 및 데크 슬래브(BS)가 된다.The beams and slabs of each basement layer constructed in this way are the shapes shown in FIGS. 1 to 4, that is, the one-way beam BG and the deck slab BS.
이러한 본 발명의 제2실시예 구성 및 이를 이용한 지하구조물의 구축방법에 의하면, 여러 문제점을 야기하던 동바리의 사용이 필요 없을 뿐 아니라 버림 콘크리트의 미타설로 콘크리트 폐기물이 발생하지 않으며, 콘크리트 시공 중인 층의 콘크리트 하중을 지지 브라켓을 통해 기둥으로 고르게 분산시키는 구성이므로 선 시공된 상층 슬래브에 무리한 하중이 가해지 않고, 또한 현수 하강시 보 거푸집 및 지지거더, 지지 브라켓의 하중만을 상층 슬래브가 지지하면 되므로 상층 슬래브가 어느 정도 양생된 후라면 바로 하층 시공이 가능하여 공기 단축이 가능해진다.According to the configuration of the second embodiment of the present invention and the construction method of the underground structure using the same, not only does not need to use the copper bar which caused various problems, but also the concrete waste does not occur due to the non-installation of discarded concrete, The concrete slab is distributed evenly to the column through the supporting bracket, so that the upper slab does not apply excessive load to the pre-installed upper slab, and the upper slab only supports the loads of the formwork, the supporting girder and the supporting bracket when the suspension descends. After curing to some extent, it is possible to construct the lower floor and shorten the air.
이하, 지하층의 1방향 보(BG) 및 데크 슬래브(BS)를 시공하기 위한 본 발명의 제3실시예를 설명하면 다음과 같다. Hereinafter, a third embodiment of the present invention for constructing the one-way beam BG and the deck slab BS of the basement layer will be described.
도 17은 본 발명의 제3실시예에서 기둥 지지되는 1방향 지지 브라켓 및 지지거더가 설치된 상태를 도시한 평면도이고, 도 18a와 도 18b는 본 발명에 따른 제3실시예의 각 구성이 모두 설치된 상태에서 보 및 슬래브 콘크리트가 타설된 상태를 나타낸 단면도이며, 도 19a와 도 19b는 각각 도 18a와 도 18b에서 주요부를 확대하여 나타낸 단면도이다.FIG. 17 is a plan view illustrating a state in which a one-way support bracket and a support girder are pillar-supported in a third embodiment of the present invention, and FIGS. 18A and 18B are all installed in the third embodiment according to the present invention. Fig. 19 is a cross-sectional view showing a state in which beams and slab concrete are poured, and Figs. 19A and 19B are enlarged cross-sectional views of main parts of Figs. 18A and 18B, respectively.
여기서, 도 18a는 도 17의 선 'H-H'와 동일한 위치 및 방향에서 취한 단면도이고, 도 18b는 도 17의 선 'I-I'와 동일한 위치 및 방향에서 취한 단면도이다.Here, FIG. 18A is a cross-sectional view taken at the same position and direction as the line 'H-H' of FIG. 17, and FIG. 18B is a cross-sectional view taken at the same position and direction as the line 'I-I' of FIG. 17.
도시한 바와 같이, 본 발명의 제3실시예는, 각 층의 1방향 보(BG) 및 데크 슬래브(BS) 구축을 위한 구조물로서, 각 골조용 기둥(102)의 해당 층 상응하는 높이에 설치되는 1방향 지지 브라켓(180)과; 상기 1방향 지지 브라켓(180) 위에 단부가 고정 지지되는 형태로 골조용 기둥(102)간에 길게 설치되되, 가로, 세로 2방향이 아닌 1방향으로만 길게 연속 배치되어 설치되는 지지거더(153)와; 이 지지거더 (153)에 의해 지지되면서 지지거더(153)를 따라 길게 설치되는 보 거푸집(110)과; 나란한 양측의 보 거푸집(110)에 단부가 지지된 상태로 설치되는 딥 데크(120)를 포함한다.As shown, the third embodiment of the present invention is a structure for constructing a one-way beam (BG) and a deck slab (BS) of each layer, installed at the corresponding height of the corresponding floor of each frame pillar (102) A one-
본 발명의 제3실시예에서는 가로, 세로 2방향이 아닌 1방향 연속 배치된 지지거더(153)들의 단부를 지지할 수 있는 새로운 지지 브라켓(이하, 1방향 지지 브라켓이라 칭함)이 사용되며, 이 1방향 지지 브라켓(180)은 골조용 기둥으로서 H-형강 기둥(102)이 시공된 경우에 사용 가능하도록 구성된 것이다.In the third embodiment of the present invention, a new support bracket (hereinafter referred to as a one-way support bracket) that can support the ends of the
상기 1방향 지지 브라켓(180)의 경우, 1방향 연속 배치되는 지지거더에만 사용이 가능하도록 제작한 것으로, 앞서 설명한 이동 조립식 지지 브라켓에 비해 구성 및 구조를 훨씬 간단히 하였으며, 부품수 축소 및 제작비 절감 등 여러 분명한 장점들을 가진다.In the case of the one-
이러한 1방향 지지 브라켓의 구성에 대하여 도 19a 및 도 19b와 다음의 도면을 참조하여 상술하기로 한다.The configuration of the one-way support bracket will be described in detail with reference to FIGS. 19A and 19B and the following drawings.
도 20a와 도 20b는 본 발명의 제3실시예에서 1방향 지지 브라켓이 H-형강 기둥에 설치된 상태를 도시한 평면사시도와 저면사시도이고, 도 21a와 도 21b는 본 발명의 제3실시예에서 1방향 지지 브라켓이 H-형강 기둥에 설치된 상태를 도시한 평면도와 저면도이다.20A and 20B are a plan perspective view and a bottom perspective view showing a state in which a one-way support bracket is installed on an H-beam column in a third embodiment of the present invention, and FIGS. 21A and 21B are views of a third embodiment of the present invention. Top and bottom views showing a one-way support bracket mounted on an H-beam.
우선, 1방향 지지 브라켓(180)은 수직 시공된 H-형강 기둥(102)을 중심으로 좌우 대칭되게 수평으로 길게 설치되는 H-형강으로 된 소정 길이의 두 브라켓 본체(181)와, 각 브라켓 본체(181)를 H-형강 기둥(102)의 정해진 높이에 고정하기 위한 브라켓 고정수단으로 구성된다.First, the one-
도시한 예는 양측의 두 브라켓 본체(181)가 H-형강 기둥(102)에 대하여 강축방향으로 설치된 예로서, 두 브라켓 본체(181)는 H-형강 기둥(102)을 중심으로 기둥(120)의 좌우 양 플랜지쪽에 양방향 설치되어서 전체적으로는 직선 배치구조를 형성하고, 각 브라켓 본체(181)의 플랜지 내측으로는 보강 플레이트(182)가 용접 설치된 구조로 되어 있다. In the illustrated example, two
그리고, 상기 브라켓 고정수단은, H-형강 기둥(102)의 양측 플랜지면에 수평으로 용접 고정되고, 각 브라켓 본체(181)의 상부 플랜지 상면에 접합된 상태로 체결되어, 각 브라켓 본체(181)를 H-형강 기둥(102)에 고정하는 두 체결 플레이트(183)와; 각 브라켓 본체(181)의 하부 플랜지 하면에 접합된 상태로 체결되는 두 베드 플레이트(184)와; H-형강 기둥(102)을 양쪽에서 압착하도록 조립되고, 조립된 위치에서 상기 두 베드 플레이트(184)를 지지하면서 이를 매개로 상기 두 브라켓 본체(181)를 지지하게 되는 한 쌍의 스톱 풀러(185)와; 상기 H-형강 기둥(102)의 양쪽 플랜지면에 각각 용접되어 상기 각 스톱 풀러(185)를 하측에서 지지하는 두 스톱 플레이트(186)를 포함하여 이루어진다. The bracket fixing means is horizontally welded to both flange surfaces of the H-
여기서, 상기 두 체결 플레이트(183)는 H-형강 기둥(102)의 플랜지에 볼트(187a) 및 너트(187b)로 체결되며, 상기 두 베드 플레이트(184)에는 좌우 방향으로 길게 슬롯홀(184a)이 형성 구비되어, 이 슬롯홀(184a)과 해당 브라켓 본체(181) 하부 플랜지의 체결홀에 볼트(188a)가 끼워진 뒤 이 볼트(188a)에 너트(188b)가 결합됨으로써, 각 베드 플레이트(184)와 브라켓 본체(181)가 체결되도록 되어 있다.Here, the two
또한, 상기 한 쌍의 스톱 풀러(185)는 H-형강 기둥(102)의 플랜지면에 접합된 상태로 양 단부에 관통 삽입된 조임볼트(189a) 및 반대쪽에서 이 볼트 끝단에 결합된 너트(189b)의 조임력에 의해 H-형강 기둥(102)의 플랜지면을 압착하도록 설치되며, 이와 같이 압착된 상태로 위치 고정되어서 상측의 베드 플레이트(184)를 지지하도록 되어 있다.In addition, the pair of
여기서, 상기 각 베드 플레이트(184)는 같은 쪽 스톱 풀러(185)의 상단에 각각 용접되어, 베드 플레이트(184)와 스톱 풀러(185)가 일체형으로 사용된다.Here, the
도면부호 191은 풀림볼트로서, 양 단부의 조임볼트(189a)와 달리 이들 폴림볼트(191)는 조임방향으로 돌려주게 되면 끝단이 H-형강 기둥(102)의 플랜지면을 밀어주도록 되어 있는 바, 스톱 풀러(185)가 H-형강 기둥(102)으로부터 쉽게 떨어지도록 하는데 사용된다.
바람직하기로는, 1방향 지지 브라켓(180)이 설치되는 부위, 특히 브라켓 본체(181)의 상, 하부 플랜지가 접합되는 H-형강 기둥(102)의 상, 하 각 부위에는 기둥(102) 내측으로 보강 플레이트(109)가 설치된다.Preferably, the one-
상기 각 보강 플레이트(109)는 H-형강 기둥(102)의 플랜지 사이에 용접하여 고정된다.Each
또한, 상기 브라켓 본체(181)의 하부 플랜지 끝단과 H-형강 기둥(102)의 플랜지면 사이에 존재하는 간극을 메우기 위해 심 플레이트(192)가 끼워지며, 이 심 플레이트(192)는 브라켓 본체(181)와 H-형강 기둥(102) 사이의 힘 전달이 이루어질 수 있도록 한다.In addition, the
도 22는 본 발명의 제3실시예에서 스톱 풀러가 클램프 조임에 의해 H-형강 기둥에 고정되는 또 다른 예를 도시한 저면도로서, 조임볼트 및 너트로 체결하는 대신에 각 스톱 풀러(185)를 H-형강 기둥(102)의 플랜지에 직접 클램프(193)로 고정할 수도 있다.FIG. 22 is a bottom view showing another example in which a stop puller is fixed to an H-beam by clamping in a third embodiment of the present invention, each
한편, 도 23은 본 발명에서 양측의 두 브라켓 본체가 H-형강 기둥에 대하여 약축방향으로 설치된 1방향 지지 브라켓의 예를 도시한 단면도로서, 도 19a에 대비되는 도면이다.On the other hand, Figure 23 is a cross-sectional view showing an example of the one-way support bracket in which the two bracket body on both sides in the weak axis direction with respect to the H-beam in the present invention, compared with Figure 19a.
또한, 도 24a와 도 24b는 본 발명에서 양측의 두 브라켓 본체가 H-형강 기둥에 대하여 약축방향으로 설치된 1방향 지지 브라켓의 평면도와 저면도이고, 도 25는 도 23의 선 'J-J'를 따라 취한 단면도이다.24A and 24B are a plan view and a bottom view of the one-way support bracket in which the two bracket bodies on both sides are installed in the weak axis direction with respect to the H-beam in the present invention, and FIG. 25 is a line 'J-J' of FIG. A cross section taken along.
도시한 다른 예의 1방향 지지 브라켓(180)은, H-형강 기둥(102)이 앞서 설명한 예와 비교하여 90°회전된 상태로 수직 시공된 경우, 또는 H-형강 기둥(102)의 방향은 동일하나 보(또는 지지거더)의 시공방향이 앞서 설명한 예와 비교하여 90°방향인 경우에 사용될 수 있는 것으로, 구성은 앞서 설명한 예와 동일하다.In the illustrated one-
즉, 이 1방향 지지 브라켓(180) 역시 수직 시공된 H-형강 기둥(102)을 중심으로 좌우 대칭되게 수평으로 길게 설치되는 H-형강으로 된 소정 길이의 두 브라켓 본체(181)와, 각 브라켓 본체(181)를 H-형강 기둥(102)의 정해진 높이에 고정하기 위한 브라켓 고정수단으로 구성되고, 이 브라켓 고정수단이 동일한 구성인 두 체결 플레이트(183), 두 베드 플레이트(184), 한 쌍의 스톱 풀러(185), 두 스톱 플레이트(186)를 포함하여 이루어진다.That is, the one-
다만, 이 1방향 지지 브라켓(180)에서는 H-형강 기둥(102)이 동일 방향으로 시공되었다 가정할 때 두 브라켓 본체(181)가 앞서 설명한 예와 비교하여 90°방향으로 설치되며, 이때 각 브라켓 본체(181)의 설치를 위하여 1방향 지지 브라켓(180)이 고정되는 부위의 H-형강 기둥(102) 내측에 H-형강을 길이를 따라 반으로 자른 보강 CT-형강(194,195) 두 쌍이 추가로 설치된다.However, in this one-
즉, 각 쌍의 상기 보강 CT-형강(194,195)을 H-형강 기둥(102)의 양측 빈 공간 내에 수직으로 세워, 각 쌍의 두 보강 CT-형강(194,195)의 플랜지와 H-형강 기둥(102)의 양측 플랜지가 4각형의 폐단면구조를 이룰 수 있게 설치하는 것이다.That is, each pair of reinforcement CT-
이때, 상기와 같이 쌍으로 설치되는 보강 CT-형강(194,195)을 브라켓 본체(181)의 상, 하부 플랜지가 접합되는 부위에 각각 설치하여, 총 두 쌍의 보강 CT-형강(194,195)을 아래 위로 동일하게 설치한다.At this time, the reinforcement CT-
이 상태에서 두 개의 스톱 플레이트(186)가 브라켓 본체(181)가 설치되는 방향으로 도 23에 도시한 바와 같이 H-형강 기둥(102)의 플랜지 양 끝단에 용접되어 설치되고, 이 각 스톱 플레이트(186) 위로 베드 플레이트(184)와 일체로 된 스톱 풀러(185)를 지지시켜 H-형강 기둥(102)에 결합한다.In this state, two
상기 스톱 풀러(185)와 베드 플레이트(184)는 하측 보강 CT-형강(195)의 플랜지면에 접합된 상태에서 조립되는데, 한 쌍의 스톱 풀러(185)가 양 단부에 관통 삽입된 조임볼트(189a) 및 너트(189b)의 조임력에 의해, 또는 H-형강 기둥(102)의 플랜지와 함께 조여주는 클램프(193)의 조임력에 의해(도 22 참조), 하측 보강 CT-형강(194)의 플랜지면을 압착하도록 설치되며, 이와 같이 압착된 상태에서 그 위치 가 고정되어진다.The
그리고, 각 체결 플레이트(183)를 각 베드 플레이트(184)와의 사이에 브라켓 본체(181)가 설치될 수 있도록 높이 조정하여 앞서 설명한 강축방향의 예(체결 플레이트가 H-형강 기둥의 플랜지에 설치됨)와 유사하게 상측 두 보강 CT-형강(194)의 플랜지면에 수평으로 용접 설치한다.Then, the height of each
그리고, 각 베드 플레이트(184)와 체결 플레이트(183) 사이에 브라켓 본체(181)를 설치한 뒤, 각 브라켓 본체(181)의 상부 플랜지와 체결 플레이트(183) 그리고 각 브라켓 본체(181)의 하부 플랜지와 베드 플레이트(184)를 볼트(187a,188a) 및 너트(187b,188b)로 상호 체결한다.Then, after installing the
그리고, 상기 브라켓 본체(181)의 하부 플랜지 끝단과 보강 CT-형강(194)의 플랜지면 사이에는 간극을 메우기 위해 심 플레이트(196)가 끼워진다.A
한편, 지지거더(153)는 각각 H-형강 기둥(102)에 고정 설치된 이웃한 1방향 지지 브라켓(180) 사이에 2개씩 평행하게 배치되어 설치되는데, 이때 각 지지거더(153)는 1방향 지지 브라켓(180)의 각 브라켓 본체(181) 위에 단부가 지지된 상태로 브라켓 본체(181)와는 대략 90°방향으로 길게 설치된다.On the other hand, the
도 26a와 도 26b는 본 발명의 제3실시예에서 1방향 지지 브라켓 위에 지지거더가 설치된 예를 도시한 사시도로서, 각 브라켓 본체(181) 위에는 1방향 직선상으로 연속 배치된 두 지지거더(153)의 단부가 함께 지지된다. 26A and 26B are perspective views illustrating an example in which the support girder is installed on the one-way support bracket in the third embodiment of the present invention, and the two
그 밖에 지지거더(153)의 역할, 구조 및 설치방법 등은 제2실시예에서와 동일하다.In addition, the role, structure and installation method of the
예를 들어, 제2실시예와 마찬가지로, 연속 배치된 두 지지거더(153)는 단부가 서로 연결되지 않은 상태에서 단순히 클램프(154)를 이용하여 브라켓 본체(181)의 상부 플랜지에 고정할 수 있다(도 26a).For example, as in the second embodiment, two
또한, 바람직하게는 각 지지거더(153)를 브라켓 본체(181)에 클램프(154)로 고정하되, 도 26b에서와 같이 각 지지거더(153) 끝단에 엔드 플레이트(155)를 용접하여 설치하고, 양측 지지거더(153)의 엔드 플레이트(155) 사이에 복수개의 심 플레이트(156)를 개재한 후, 볼트(157a)와 너트(157b)로 양측을 체결하여 두 지지거더(153)의 단부가 서로 결합되도록 한다. In addition, preferably, each
그리고, 횡좌굴보강앵글 설치, 현수재 연결구조 및 하강방법 등도 제2실시예와 동일하므로 그에 대한 설명은 생략하기로 한다.In addition, since the lateral buckling reinforcement angle installation, suspension structure connection structure and the lowering method is also the same as the second embodiment, description thereof will be omitted.
또한, 본 발명의 제3실시예에서 보 거푸집(110)의 구성도 제2실시예와 모두 동일하며, 도 19a와 도 19b에 나타낸 바와 같이 1방향 지지 브라켓(180)에 지지되는 지지거더(153) 위에 보 거푸집(110)이 고정되고, 이 보 거푸집(110)이 지지거더(153)를 따라 1방향으로만 설치된다.In addition, in the third embodiment of the present invention, the configuration of the
딥 데크(120) 역시 그 형상이나 구조, 양 단부가 보 거푸집(110)의 측면 사각강관(115)에 얹혀져 설치되는 점, 마구리측에 엔드 클로우저(121)가 설치되어 마감되는 점 등이 제1실시예 및 제2실시예와 모두 동일하며, 그에 대한 설명은 제1실시예에서 설명하였으므로 여기서는 생략하기로 한다.
한편, 위와 같은 본 발명의 제3실시예를 이용하여 지하구조물의 1방향 보 및 데크 슬래브를 시공하는 과정을 설명하면 다음과 같다. Meanwhile, a process of constructing a one-way beam and deck slab of an underground structure using the third embodiment of the present invention as described above is as follows.
도 27a ~ 도 27e는 본 발명의 제3실시예를 이용하여 지하구조물의 1방향 보 및 데크 슬래브를 시공하는 과정을 나타낸 도면이고, 도 28a 및 도 28b는 본 발명의 제3실시예를 이용하는 과정에서 1방향 지지 브라켓의 브라켓 본체를 하강시키는 방법을 나타낸 도면이다.27A to 27E are views illustrating a process of constructing a one-way beam and a deck slab of an underground structure using a third embodiment of the present invention, and FIGS. 28A and 28B are views using a third embodiment of the present invention. 2 is a view showing a method of lowering the bracket body of the one-way support bracket.
우선, 흙막이벽(도시하지 않음)의 안쪽 지중에 H-형강 기둥(102)을 수직 시공한 후, 제1지하층의 보 및 슬래브 시공을 위해 1차로 소정 깊이만큼 지반을 굴착하여 H-형강 기둥(102)의 상부 일부가 노출되도록 한다(도 27a 참조).First, after the vertical construction of the H-
이후, 노출된 각 H-형강 기둥(102)에서 제1지하층의 상응하는 높이에 1방향 지지 브라켓(180)을 설치하고, 이웃한 두 1방향 지지 브라켓(180)에 단부를 지지시키는 방법으로 각 지지거더(153)를 기둥간에 설치한다.Subsequently, in each exposed H-
이때, 지지거더(153)들은 1방향 보의 설계방향을 따라 길게 설치하는데, 지지거더(153)들을 가로, 세로 2방향이 아닌 1방향으로만 직선상으로 연속 배치하며, 지지 브라켓(180) 사이에 2개씩을 나란히 지지시킨다.At this time, the
지지거더(153)는 지지 브라켓(180)에 지지시킨 상태에서 클램프(154)로 체결하여 고정한다.The
이후, 지지거더(153) 위에 보 거푸집(110)을 고정시켜 설치하는데, 보 거푸집(110) 역시 1방향 보의 설계방향, 즉 지지거더(153)의 길이방향을 따라 길게 배치하여 설치한다.Subsequently, the
요컨대, 지지거더(153)와 보 거푸집(110)은 가로, 세로 2방향이 아닌 도 1에 나타낸 보(BG)의 길이방향을 따라 가로 또는 세로 1방향으로만 길게 연속 배치되 고, 연속 배치된 보 거푸집(110)들을 하나의 열로 할 때 전체적으로는 1방향 배치된 복수열의 보 거푸집 구조로 설치된다.In other words, the
이후, 보 거푸집(110)의 측면 사각강관에 단부를 지지시키는 방법으로 딥 데크(120)를 나란한 양측 보 거푸집(110) 사이에 걸쳐 설치하고(도 27b 참조), 딥 데크(120)의 마구리측에는 전술한 바대로 엔드 클로우저가 설치되어 마감된다.Subsequently, the
상기와 같이 보 거푸집(110)과 딥 데크(120)가 설치되고 나면, 보 거푸집(110)과 딥 데크(120)가 형성하는 보 및 슬래브 공간 내부에 보강철근을 배근하고, 이후 콘크리트를 동시 타설하여 제1지하층의 보(BG1) 및 슬래브(BS1) 시공을 완료한다(도 27c 참조).After the
이와 같이 시공되는 제1지하층의 보(BG1) 및 슬래브(BS1)는 도 1 내지 도 4에 도시한 형태, 즉 1방향 보 및 데크 슬래브가 된다. The beams BG1 and slab BS1 of the first underground layer constructed in this way become the shapes shown in FIGS. 1 to 4, that is, one-way beams and deck slabs.
이와 같이 콘크리트가 타설되어 양생되고 나면, 제2지하층의 보 및 슬래브 시공을 위하여 2차로 지반을 굴착한 후, 1방향 지지 브라켓(180)과 지지거더(153), 보 거푸집(110)을 제1지하층에서 해체 및 하강시켜 제2지하층의 상응하는 높이에 동일하게 재설치하게 된다(도 27d 참조).After the concrete is poured and cured as described above, after excavating the ground secondly for the construction of the beam and the slab of the second basement layer, the one-
하강시에는 지지거더(153)를 현수재로 지지시켜 고정한 상태에서 1방향 지지 브라켓(180)을 우선 해체 후 체인(201) 및 체인 하강을 위한 체인블럭(200)을 이용해 하강시키고, 1방향 지지 브라켓(180)을 제2지하층 높이에 재설치한 뒤 지지거더(153)를 현수재 및 현수재 하강을 위한 유압승강기를 이용해 보 거푸집(110)과 함께 하강시킨다.At the time of descending, the
1방향 지지 브라켓(180)은 두 브라켓 본체(181) 중 어느 하나를 우선적으로 하강 시킬 수 있는 바, 한쪽 부분씩 나누어 하강시킨 다음 제2지하층 높이에서 재조립한다. The one-
상기 1방향 지지 브라켓(180)의 재조립시에는 스톱 플레이트(186), 스톱 풀러(185) 및 베드 플레이트(184), 체결 플레이트(183) 브라켓 본체(181), 심 플레이트의 순으로 조립할 수 있다.When reassembling the one-
지지거더(153)의 하강시에는 나란한 2개를 보 거푸집(110)과 함께 하강시키며, 하강 후 지지거더(153)는 지지 브라켓(180) 위에서 클램프(154)로 체결하여 고정한다.When the
상기 지지거더(153)는 기둥(102)간 지지거더(153)와 보 거푸집(110)을 한 단위로 하여 한 단위씩 순차 하강시키거나, 1방향 직선상으로 연속 배치된 지지거더(153)들이 모두 단부간에 결합되어 있는 경우라면, 이들 지지거더(153)들을 보 거푸집(110)과 함께 모두 동시 하강시킬 수 있다.The support girders 153 are sequentially lowered by one unit using the
도 28a 및 도 28b는 1방향 지지 브라켓(180)을 해체한 후 브라켓 본체(181)를 하강시키는 방법을 보인 것으로, 각 브라켓 본체(181)에 설치된 보강 플레이트(182)에 연결고리(182a)를 설치하고, 이 연결고리(182a)에 체인(201)의 끝단을 연결한다.28A and 28B illustrate a method of lowering the
그리고, 상기 체인(201)은 도 28a에서와 같이 지지거더(153)의 하부 플랜지에 임시 설치한 로울러 기구(202)와 H-형강 기둥(102)의 하부에 임시 설치한 로울러 기구(203)를 거치도록 하고, 지반 위의 체인블럭(200)을 작동시켜 체인(201)을 풀어줌으로써 브라켓 본체(181)를 하강시킨다.The
또는, 도 28b에서와 같이 지지거더(153)의 하부 플랜지에 임시 설치한 로울러 기구(202)만을 이용하여 체인(201)을 하강시킬 수도 있다.Alternatively, as shown in FIG. 28B, the
체인블럭(200)의 작동시에 체인(201)은 로울러 기구(202,203)에 의해 지지됨과 동시에 안내되면서 이동하는 바, 이 체인(201) 이동으로 각 브라켓 본체(181)가 하강할 수 있게 된다. When the
이와 같이 제2지하층의 높이에 지지 브라켓(180), 지지거더(153), 보 거푸집(110)을 모두 설치하고 나면, 딥 데크(120)를 제1지하층에서와 동일하게 설치하고, 이어 보 거푸집(110)과 딥 데크(120)가 형성하는 보 및 슬래브 공간 내부에 보강철근을 배근한 후, 콘크리트를 동시 타설하여 제2지하층의 보(BG2) 및 슬래브(BS2) 시공을 완료한다(도 27e 참조).As such, after installing the
이후, 도면으로 나타내지는 않았지만, 제3지하층 및 그 이하 지하층의 보 및 슬래브를 시공하기 위하여 상기 과정을 반복하게 되는데, 각 층의 보 및 슬래브를 동일한 방법을 이용해 아래층으로 내려가면서 단계적으로 시공한다.Thereafter, although not shown in the drawings, the above process is repeated to construct the beams and slabs of the third basement layer and the basement layer below, and the beams and slabs of each layer are constructed in steps while descending to the lower floor by the same method.
이와 같이 시공되는 각 지하층의 보 및 슬래브는 도 1 내지 도 4에 도시한 형태, 즉 1방향 보(BG) 및 데크 슬래브(BS)가 된다.The beams and slabs of each basement layer constructed in this way are the shapes shown in FIGS. 1 to 4, that is, the one-way beam BG and the deck slab BS.
이러한 본 발명의 제3실시예 구성 및 이를 이용한 지하구조물의 구축방법에 의하면, 여러 문제점을 야기하던 동바리의 사용이 필요 없을 뿐 아니라 버림 콘크리트의 미타설로 콘크리트 폐기물이 발생하지 않으며, 콘크리트 시공 중인 층의 콘크리트 하중을 지지 브라켓을 통해 기둥으로 고르게 분산시키는 구성이므로 선 시 공된 상층 슬래브에 무리한 하중이 가해지 않고, 또한 현수 하강시 보 거푸집 및 지지거더, 지지 브라켓의 하중만을 상층 슬래브가 지지하면 되므로 상층 슬래브가 어느 정도 양생된 후라면 바로 하층 시공이 가능하여 공기 단축이 가능해진다.According to the configuration of the third embodiment of the present invention and the construction method of the underground structure using the same, it is not necessary to use the copper bar which caused various problems, and the concrete waste does not occur due to the non-installation of the discarded concrete, and the floor under construction The concrete slab is distributed evenly to the column through the supporting bracket, so that the upper slab does not apply excessive load to the prefabricated upper slab, and the upper slab only supports the load of the supporting formwork, the support girder and the support bracket when the suspension descends. After curing to some extent, it is possible to construct the lower floor and shorten the air.
이상에서 살펴본 바와 같이, 본 발명에 따른 지하층의 1방향 보 및 데크 슬래브 시공을 위한 하향 골조 타설 시스템 및 방법에 의하면, 보 및 슬래브의 역타 시공시에 1방향 보를 구축하기 위한 보 거푸집과, 장스팬 적용이 가능한 골데크 타입의 딥 데크를 사용함으로써, 다음과 같은 효과가 있다.As described above, according to the down-frame placing system and method for the one-way beam and deck slab construction of the basement according to the present invention, the beam formwork and the long span for building the one-way beam during the reverse construction of the beam and slab By using a gold deck type deep deck that can be applied, the following effects are obtained.
1) 보 거푸집이 가로, 세로 2방향이 아닌 1방향으로만 설치되어 버림 콘크리트의 타설량을 줄일 수 있고, 콘크리트 폐기물의 발생량을 줄일 수 있게 된다. 1) Since the formwork is installed only in one direction rather than horizontally or vertically, it can reduce the amount of cast concrete and reduce the amount of concrete waste.
2) 회전형 로울러 기구를 사용함으로써, 보 거푸집의 하강 작업을 용이하게 실시할 수 있다.2) By using the rotary roller mechanism, the work of lowering the formwork can be easily performed.
3) 지지 브라켓 사용의 경우, 동바리 사용이 불필요하고, 버림 콘크리트의 미타설로 콘크리트 폐기물이 발생하지 않으며, 콘크리트 시공 중인 층의 콘크리트 하중을 지지 브라켓을 통해 기둥으로 고르게 분산시키는 구성이므로 선 시공된 상층 슬래브에 무리한 하중이 가해지 않고, 상층 슬래브가 어느 정도 양생된 후라면 바로 하층 시공이 가능하여 공기 단축이 가능해진다.3) In the case of using the support bracket, it is not necessary to use copper scoops, no concrete waste occurs due to the non-establishment of the discarded concrete, and the structure is distributed evenly to the columns through the support bracket. If an excessive load is not applied to the slab and the upper slab is cured to some extent, the lower floor construction is possible and the air shortening is possible.
Claims (14)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020050035022A KR100694503B1 (en) | 2005-04-27 | 2005-04-27 | Downward construction system and method for 1-way girder and slab of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020050035022A KR100694503B1 (en) | 2005-04-27 | 2005-04-27 | Downward construction system and method for 1-way girder and slab of underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20060112504A true KR20060112504A (en) | 2006-11-01 |
KR100694503B1 KR100694503B1 (en) | 2007-03-13 |
Family
ID=37620777
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020050035022A KR100694503B1 (en) | 2005-04-27 | 2005-04-27 | Downward construction system and method for 1-way girder and slab of underground structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100694503B1 (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100837831B1 (en) * | 2007-03-30 | 2008-06-13 | 박무용 | Underground downward construction system |
KR100926323B1 (en) * | 2009-03-13 | 2009-11-12 | 황기수 | Constructing method for extension of underground |
KR101409249B1 (en) * | 2014-05-13 | 2014-06-23 | 주식회사무영아멕스건축사사무소 | Top Down Construction method Using Method Of Steel Hybrid Girder Construction |
KR101431009B1 (en) * | 2012-11-05 | 2014-09-23 | (주)한국건설공법 | A temporary skeleton structure used a top down underground construction method |
KR101485563B1 (en) * | 2013-11-04 | 2015-01-26 | 주식회사 씨엠파트너스건축사사무소 | The horizontal structural frame |
CN109759974A (en) * | 2019-03-11 | 2019-05-17 | 汉腾汽车有限公司 | A kind of adjustable vehicle body technique saddle |
KR20190066754A (en) * | 2017-12-06 | 2019-06-14 | 이충규 | Formwork structure supported by column unit |
KR20190116624A (en) * | 2018-04-05 | 2019-10-15 | (주)대우건설 | Support structure of temporary strut for construction period reduction |
KR102184568B1 (en) * | 2019-06-10 | 2020-11-30 | 현대건설(주) | Apparatus for intalling bracket for top-down construction method |
KR20210088852A (en) * | 2020-01-07 | 2021-07-15 | (주)한국건설공법 | Top-down construction method using bracket and double girder |
CN114561975A (en) * | 2022-02-28 | 2022-05-31 | 中铁十一局集团有限公司 | Integrative system of pouring of multilayer subway open cut station |
CN114922218A (en) * | 2022-07-01 | 2022-08-19 | 浙江交工装备工程有限公司 | Assembled template for bridge substructure |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101335796B1 (en) * | 2012-05-03 | 2013-12-05 | 코오롱글로벌 주식회사 | Apparatus for supporting form of underground building and method of constructing the underground building using the same |
KR101251096B1 (en) | 2012-07-02 | 2013-04-05 | (주)한국건설공법 | A temporary skeleton system used a building with a shallow basement and a top down underground construction method using a temporary skeleton system |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR950002481U (en) * | 1993-06-30 | 1995-01-04 | Combination structure of TV screen, focus pack (SCREEN, FOCUS PACK) and board | |
KR200159796Y1 (en) * | 1996-06-07 | 1999-11-01 | 장석준 | Elevating device of form for underground building construction work in the underground |
JPH11303218A (en) * | 1998-04-20 | 1999-11-02 | Kajima Corp | Construction method of floor building frame utilizing steel pipe column |
KR200367259Y1 (en) * | 2004-07-09 | 2004-11-10 | 벽산건설 주식회사 | Roller device for concrete girder form using RC downward construction |
KR200372315Y1 (en) * | 2004-10-11 | 2005-01-10 | 박무용 | Moving-fabricated supporting bracket structure of downward construction system |
-
2005
- 2005-04-27 KR KR1020050035022A patent/KR100694503B1/en active IP Right Grant
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100837831B1 (en) * | 2007-03-30 | 2008-06-13 | 박무용 | Underground downward construction system |
KR100926323B1 (en) * | 2009-03-13 | 2009-11-12 | 황기수 | Constructing method for extension of underground |
KR101431009B1 (en) * | 2012-11-05 | 2014-09-23 | (주)한국건설공법 | A temporary skeleton structure used a top down underground construction method |
KR101485563B1 (en) * | 2013-11-04 | 2015-01-26 | 주식회사 씨엠파트너스건축사사무소 | The horizontal structural frame |
KR101409249B1 (en) * | 2014-05-13 | 2014-06-23 | 주식회사무영아멕스건축사사무소 | Top Down Construction method Using Method Of Steel Hybrid Girder Construction |
KR20190066754A (en) * | 2017-12-06 | 2019-06-14 | 이충규 | Formwork structure supported by column unit |
KR20190116624A (en) * | 2018-04-05 | 2019-10-15 | (주)대우건설 | Support structure of temporary strut for construction period reduction |
CN109759974A (en) * | 2019-03-11 | 2019-05-17 | 汉腾汽车有限公司 | A kind of adjustable vehicle body technique saddle |
KR102184568B1 (en) * | 2019-06-10 | 2020-11-30 | 현대건설(주) | Apparatus for intalling bracket for top-down construction method |
KR20210088852A (en) * | 2020-01-07 | 2021-07-15 | (주)한국건설공법 | Top-down construction method using bracket and double girder |
CN114561975A (en) * | 2022-02-28 | 2022-05-31 | 中铁十一局集团有限公司 | Integrative system of pouring of multilayer subway open cut station |
CN114922218A (en) * | 2022-07-01 | 2022-08-19 | 浙江交工装备工程有限公司 | Assembled template for bridge substructure |
Also Published As
Publication number | Publication date |
---|---|
KR100694503B1 (en) | 2007-03-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100694503B1 (en) | Downward construction system and method for 1-way girder and slab of underground structure | |
KR100951097B1 (en) | Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket | |
US11280055B1 (en) | Construction device and method for lateral bracing in ultra-deep foundation pit with silt | |
KR200417438Y1 (en) | Bracket structure for girder and slab construction | |
JP4060323B2 (en) | Bracket support type downward frame driving system and downward frame driving method using the same | |
KR20120096605A (en) | Bracket support type downward construction system and method | |
KR100694493B1 (en) | Downward construction method capable of using bracket support type temporary structure as working table | |
KR200398231Y1 (en) | 1way-supporting bracket for girder and slab construction | |
KR100605514B1 (en) | Bracket support type downward construction system and construction method using the same | |
CN114775622B (en) | Construction method for special-shaped deep foundation pit with limited construction space of close-proximity building structure | |
JP2006063718A (en) | Method of constructing overhung bridge using corrugated steel plate web | |
JPH09317183A (en) | Construction method of building | |
CN105298147A (en) | Ultra-deep foundation pit spiral descending quick material transportation passage and construction method thereof | |
KR101335796B1 (en) | Apparatus for supporting form of underground building and method of constructing the underground building using the same | |
KR100757710B1 (en) | Dowel bar construction method for downward construction of underground structures | |
JP3470246B2 (en) | Method of reinforcing steel pedestal and reinforced pedestal | |
KR200402363Y1 (en) | Structure for concreting work of column | |
CN212027812U (en) | Template for rapid lining of egg-shaped tunnel | |
JP3644606B2 (en) | Installation method of formwork support in reverse placement method | |
CN210194445U (en) | Vertical transportation self-lifting system for slip form construction | |
CN113403936A (en) | Bracket-free rapid construction method for hollow pier partition plate of bridge | |
CN111365034A (en) | Method and template for rapid lining of egg-shaped tunnel | |
KR100679986B1 (en) | Structure for plastic slab deck system and Downward construction method using the same | |
JPS61109827A (en) | Construction of basement | |
CN111058622A (en) | Large steel mould cast-in-place column construction method adopting binding and lapping mode for column steel bars |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130326 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20140307 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20150306 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20160303 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20170306 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20180305 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20190408 Year of fee payment: 13 |
|
FPAY | Annual fee payment |
Payment date: 20200305 Year of fee payment: 14 |