KR200232750Y1 - Construction for preventing from upset of prestressed concrete beam - Google Patents

Construction for preventing from upset of prestressed concrete beam Download PDF

Info

Publication number
KR200232750Y1
KR200232750Y1 KR2020010002647U KR20010002647U KR200232750Y1 KR 200232750 Y1 KR200232750 Y1 KR 200232750Y1 KR 2020010002647 U KR2020010002647 U KR 2020010002647U KR 20010002647 U KR20010002647 U KR 20010002647U KR 200232750 Y1 KR200232750 Y1 KR 200232750Y1
Authority
KR
South Korea
Prior art keywords
pedestal
prestressed concrete
concrete beam
support
bolt
Prior art date
Application number
KR2020010002647U
Other languages
Korean (ko)
Inventor
박상송
남현우
박영준
엄태학
Original Assignee
벽산엔지니어링주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 벽산엔지니어링주식회사 filed Critical 벽산엔지니어링주식회사
Priority to KR2020010002647U priority Critical patent/KR200232750Y1/en
Application granted granted Critical
Publication of KR200232750Y1 publication Critical patent/KR200232750Y1/en

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

본 고안은 교량 프리스트레스트 콘크리트 빔의 전도 방지시설에 관한 것으로서, 특히 일체형으로 형성하여 안정성을 높인 교량 프리스트레스트 콘크리트 빔의 일체형 전도 방지시설에 관한 것이며, 수평으로 길게 지면에 놓이는 받침대(12)를 형성하여 일단부가 상기 슈받침 블록(4)의 측벽에 닿도록 위치시키고, 몸체 상부에 볼트 삽입 슬릿홀(20)을 수직으로 길게 형성되고 하부에 받침대 고정부(11)가 형성된 측면지지 파이프(15)를 받침대(12)에 서로 직각을 이루도록 고정하며, 양단부에 지지파이프 고정 플랜지(18)와 받침대 고정 플랜지(19)가 각각 형성되어 있는 지지봉(17)을 상기 측면지지 파이프(15)와 받침대(12)에 형성된 볼트공에 볼트로 체결하며, 상기 지지봉(17)의 몸체 중앙에 수직 수평을 조절하기 위한 수직미세조정키(16)가 형성되고, 상기 프리스트레스트 콘크리트 빔(1)의 측벽에 측면지지 파이프(15)를 대고 양단에 나사산이 형성된 원형파이프 양면볼트(13)를 프리스트레스트 콘크리트 빔(1)에 형성된 인양홀(6)과 볼트삽입 슬릿홀(20)을 동시에 관통하여 너트(14)로 체결하여 고정하는 것을 특징으로 한다.The present invention relates to a fall prevention facility of bridge prestressed concrete beams, and more particularly, to an integrated fall prevention facility of bridge prestressed concrete beams having improved stability by forming a single piece, and forming a pedestal 12 placed horizontally long on the ground. The side support pipe 15 is positioned so that one end thereof is in contact with the side wall of the shroud block 4, and the bolt insertion slit hole 20 is vertically elongated at the upper portion of the body and the pedestal fixing portion 11 is formed at the lower portion thereof. To the pedestal 12 at right angles to each other, and a support rod 17 having a support pipe fixing flange 18 and a pedestal fixing flange 19 formed at both ends thereof is provided with the side support pipe 15 and the pedestal 12. Fastening with a bolt formed in the bolt hole), a vertical fine adjustment key 16 for adjusting the vertical and horizontal in the center of the body of the support bar 17 is formed, the free Lifting holes 6 and bolting slit holes formed in the prestressed concrete beam 1 by attaching side pipes 15 to the side walls of the thrust concrete beam 1 and threaded circular pipe double-sided bolts 13 formed at both ends thereof. Simultaneously penetrates the 20 and fastens with the nut 14 to fix the same.

Description

교량 프리스트레스트 콘크리트 빔의 일체형 전도 방지시설{Construction for preventing from upset of prestressed concrete beam}Integrated fall prevention of bridge prestressed concrete beams {Construction for preventing from upset of prestressed concrete beam}

본 고안은 교량 프리스트레스트 콘크리트 빔의 전도 방지시설에 관한 것으로서, 특히 일체형으로 형성하여 안정성을 높인 교량 프리스트레스트 콘크리트 빔의 일체형 전도 방지시설에 관한 것이다.The present invention relates to a fall prevention facility of a bridge prestressed concrete beam, and more particularly, to an integrated fall prevention facility of a bridge prestressed concrete beam which is formed integrally to increase stability.

종래에 사용하는 프리스트레스트 콘크리트 빔(prestressed concrete beam; PSC-BEAM)의 전도 방지시설은 도 1에 도시되어 있듯이, 몸체 중앙에 인양홀(6)이 형성되어 있는 프리스트레스트 콘크리트 빔(1)은 슈받침 블록(4)위에 탄성받침(5)을 개재하여 설치된다. 이러한 프리스트레스트 콘크리트 빔(1)은 프리스트레스트 콘크리트 빔(1)의 양측면 상단과 지면에 형성된 고정앵커(3)를 와이어 로프(2)로 연결하여 고정한다.As shown in FIG. 1, the prestressed concrete beam (PSC-BEAM), which is conventionally used for the fall prevention facility, is a prestressed concrete beam 1 having a lifting hole 6 formed at the center of the body. The elastic block 5 is installed on the supporting block 4. The prestressed concrete beam 1 connects and fixes the fixed anchors 3 formed on both top surfaces of the prestressed concrete beam 1 and the ground with a wire rope 2.

이러한 신설교량의 프리스트레스트 콘크리트 빔(PSC-BEAM)(1) 설치시 빔 자체의 전도의 위험을 내포하고 있고, 단순히 프리스트레스트 콘크리트 빔(1)을 와이어 로프(2)에 의하여 전도를 방지하고 있으나 안정성이 미흡하고, 상기 프리스트레스트 콘크리트 빔(1)의 수직 수평을 유지하고 있지 못하여 교량 시공후 콘크리트의 균열 및 하자가 발생된다. 이러한 이유로 해서 상기 프리스트레스트 콘크리트 빔(1)의 받침틀인 교좌장치까지 수평, 수직하중에 의한 영향을 받게 되어 복합적인 하자가 발생되는 문제도 발생한다.The installation of the prestressed concrete beam (PSC-BEAM) 1 of the new bridge implies the danger of the conduction of the beam itself, and the prestressed concrete beam 1 is simply prevented from falling by the wire rope 2. Insufficient stability and failure to maintain the vertical level of the prestressed concrete beam 1 causes cracking and defects in concrete after the bridge construction. For this reason, even the bridge device, which is the support frame of the prestressed concrete beam 1, is affected by the horizontal and vertical loads, thereby causing a problem of complex defects.

본 고안은 전술한 문제점을 해결하기 위하여 고안한 것으로서, 프리스트레스트 콘크리트 빔에 형성된 인양홀을 이용하여 양 측면에 전도 방지 시설을 고정하여 안정적인 전도방지를 하고자 하는 목적을 가지고 있다.The present invention is devised to solve the above problems, and has the purpose of fixing the fall prevention facility on both sides by using a lifting hole formed in the prestressed concrete beam.

본 고안은 전술한 목적을 달성하기 위하여 슈받침 블록위에 탄성 받침을 개재하여 프리스트레스트 콘크리트 빔이 놓여지는 교량 교각구조의 전도방지 시설에 있어서, 수평으로 길게 지면에 놓이는 받침대를 형성하여 일단부가 상기 슈받침 블록의 측벽에 닿도록 위치시키고, 몸체 상부에 볼트 삽입 슬릿홀을 수직으로 길게 형성되고 하부에 받침대 고정부가 형성된 측면지지 파이프를 받침대에 서로 직각을 이루도록 고정하며, 양단부에 지지파이프 고정 플랜지와 받침대 고정 플랜지가 각각 형성되어 있는 지지봉을 상기 측면지지 파이프와 받침대에 형성된 볼트공에 볼트로 체결하며, 상기 지지봉의 몸체 중앙에 수직 수평을 조절하기 위한 수직미세조정키가 형성되고, 상기 프리스트레스트 콘크리트 빔의 측벽에 측면지지 파이프를 대고 양단에 나사산이 형성된 원형파이프 양면볼트를 프리스트레스트 콘크리트 빔에 형성된 인양홀과 볼트삽입 슬릿홀을 동시에 관통하여 너트로 체결하여 고정하는 것을 특징으로 하는 교량 프리스트레스트 콘크리트 빔의 일체형 전도 방지시설을 제공한다.The present invention, in the fall prevention facility of the bridge bridge structure in which the prestressed concrete beam is placed via the elastic support on the shoe support block in order to achieve the above object, one end is formed by forming a pedestal placed horizontally long Position it so as to be in contact with the side wall of the support block, and fix the side support pipe having a bolt insertion slit hole vertically formed on the upper part of the body to be perpendicular to each other on the pedestal, and supporting pipe fixing flanges and pedestals at both ends. Fastening the support rods, each of which is formed with a fixing flange with bolts formed in the side support pipes and the pedestals, and a vertical fine adjustment key is formed at the center of the body of the support rods to adjust the vertical horizontality. On the sidewalls of the side Provides the acid lifting hole and prevents the conduction of one-piece concrete bridge beam prestressed, it characterized in that the bolt through the slit hole at the same time to fix the fastening nut facilities formed a circular pipe formed on both sides of the bolt prestressed concrete beam.

도 1은 종래의 프리스트레스트 콘크리트 빔의 전도 방지 시설을 도시한 도면.1 is a view showing a fall prevention facility of a conventional prestressed concrete beam.

도 2는 본 고안의 프리스트레스트 콘크리트 빔 일체형 전도 방지시설의 주요 부품도.Figure 2 is a main part of the prestressed concrete beam integrated fall prevention facility of the present invention.

도 3은 본 고안의 프리스트레스트 콘크리트 빔의 전도 방지 시설을 도시한 도면.Figure 3 is a view showing a fall prevention facility of the prestressed concrete beam of the present invention.

< 도면의 주요 부분에 대한 부호의 간단한 설명 ><Brief description of symbols for the main parts of the drawings>

1 : 프리스트레스트 콘크리트 빔(Prestressed concrete -BEAM)1: Prestressed concrete beam (BEAM)

2 : 와이어 로프 3 : 고정 앵커2: wire rope 3: fixed anchor

4 : 슈받침 블록 5 : 탄성 받침4: shoe support block 5: elastic support

6 : 인양홀 12 : 받침대6: lifting hole 12: base

13 : 원형파이프 양면볼트 14 : 너트13 round pipe double-sided bolt 14 nut

15 : 측면지지 파이프 16 : 수직 미세 조정키15: side support pipe 16: vertical fine adjustment key

17 : 지지봉 18 : 지지파이프 고정 플랜지17: support rod 18: support pipe fixing flange

19 : 받침대 고정 플랜지 20 : 볼트 삽입 슬릿홀19: base fixing flange 20: bolt insertion slit hole

이하 첨부된 도면을 참조하여 본 고안의 구성을 상세히 설명하면 다음과 같다.Referring to the configuration of the present invention in detail with reference to the accompanying drawings as follows.

도 2는 본 고안의 전도 방지시설에 사용하는 부품도로서, 프리스트레스트 콘크리트 빔의 양 측벽에 밀착시켜 지지시킬 측면 지지파이프(15)를 구비하고, 상기 측면 지지파이프(15)의 상부에 수직으로 볼트 삽입 슬릿홀(20)을 형성한다. 상기 측면 지지파이프(15)의 볼트 삽입 슬릿홀(20)을 관통하고 프리스트레스트 콘크리트 빔의 인양홀(6)을 관통한 후 다시 다른 측벽에 설치되는 측면 지지파이프(15)의 볼트 삽입 슬릿홀(20)을 관통하여 체결되도록 양단에 나사산이 형성된 원형 파이프 양면 볼트를 구비한다.2 is a part diagram used in the fall prevention facility of the present invention, and has side support pipes 15 to be held in close contact with both sidewalls of the prestressed concrete beam, and is perpendicular to the upper portion of the side support pipes 15. The bolt insertion slit hole 20 is formed. The bolt insertion slit hole of the side support pipe 15 which penetrates the bolt insertion slit hole 20 of the side support pipe 15 and penetrates the lifting hole 6 of the prestressed concrete beam and is installed on another side wall again ( 20) and a round pipe double-sided bolt threaded at both ends to be fastened through.

상기 측면지지 파이프(15)의 하단에 받침대 고정부(11)를 형성하고, 상기 받침대 고정부(11)를 지면에 수평으로 길게 놓이도록 형성된 받침대(12)에 직각의 각도를 이루어 ㄴ자 형태를 이루도록 볼트와 너트로 고정한다.A pedestal fixing part 11 is formed at the lower end of the side support pipe 15, and the pedestal fixing part 11 is formed at a right angle to the pedestal 12 formed so as to lie horizontally long on the ground to form a c-shape. Secure with bolts and nuts.

상기 받침대(12)의 상면과 측면지지 파이프(15)의 측면에 고정되어 받침대(12)와 측면 지지파이프(15)를 지지하도록 지지봉(17)을 사이에 고정한다. 상기 지지봉(17)의 양단부는 고정면이 서로 90도의 각도를 이루도록 지지파이프 고정 플랜지(18)와 받침대 고정 플랜지(19)가 형성되어 있다.The support rod 17 is fixed between the upper surface of the pedestal 12 and the side of the side support pipe 15 to support the pedestal 12 and the side support pipe 15. Both ends of the support bar 17 are formed with a support pipe fixing flange 18 and a pedestal fixing flange 19 such that the fixing surfaces form an angle of 90 degrees to each other.

상기 지지파이프 고정 플랜지(18)와 받침대 고정 플랜지(19)에는 볼트홀이 형성되어 있어서, 상기 측면지지 파이프(15)와 받침대(12)에 형성된 볼트홀에 맞추어 볼트로 고정한다.A bolt hole is formed in the support pipe fixing flange 18 and the pedestal fixing flange 19 so that the support pipe fixing flange 18 and the pedestal fixing flange 19 are bolted in accordance with the bolt holes formed in the side support pipe 15 and the pedestal 12.

볼트로 체결하는 과정에서 생기는 오차는 상기 지지봉(17)에 설치된 수직 미세 조정키(16)로 조정한다.The error generated in the process of fastening with the bolt is adjusted by the vertical fine adjustment key 16 installed on the support bar 17.

도 3에는 본 고안의 전도 방지시설이 설치된 상태가 도시되어 있는데, 프리스트레스트 콘크리트 빔(1)의 양 측벽에 측면지지 파이프(15)를 대고 상기 측면지지 파이프(15)에 형성된 볼트 삽입 슬릿홀(20)과 인양홀(6)을 통하여 원형 파이프 양면볼트(13)를 삽입 관통하여 너트(14)로 고정한다.3 shows a state in which the fall prevention facility of the present invention is installed, and a bolt insertion slit hole formed on the side support pipe 15 by attaching side support pipes 15 to both sidewalls of the prestressed concrete beam 1. 20) and the circular pipe double-sided bolt (13) through the lifting hole (6) to be fixed with a nut (14).

상기 측면지지 파이프(15)의 하단부에 형성된 받침대 고정부(11)에 받침대(12)의 일단이 고정되고 상기 받침대(12)는 수평으로 길게 지면에 놓여 측면지지 파이프(15)와 받침대(12)가 서로 직각을 이루도록 설치된다.One end of the pedestal 12 is fixed to the pedestal fixing part 11 formed at the lower end of the side support pipe 15, and the pedestal 12 is horizontally elongated and placed on the ground to support the side support pipe 15 and the pedestal 12. Are installed to be perpendicular to each other.

양단부에 각각 지지파이프 고정 플랜지(18)와 받침대 고정 플랜지(19)의 면이 서로 90도의 각도를 이루도록 형성된 지지봉(17)의 일단을 상기 측면 지지파이프(15)의 볼트 삽입 슬릿홀(20)의 하측으로 형성된 볼트홀에 볼트로 고정하고, 타단은 받침대(12)의 상면에 형성된 볼트홀에 볼트로 체결하여 고정한다.One end of the support rod 17 formed so that the surfaces of the support pipe fixing flange 18 and the pedestal fixing flange 19 are formed at an angle of 90 degrees to each other at both ends of the bolt insertion slit hole 20 of the side support pipe 15. The bolt is fixed to the bolt hole formed at the lower side, and the other end is fixed by bolting to the bolt hole formed on the upper surface of the pedestal 12.

이상과 같이 본 고안은 프리스트레스트 콘크리트 빔에 형성된 인양홀을 이용하여 견고한 지지구조를 형성하여 수직 수평을 확실하게 유지하는 안정적인 전도방지를 하는 효과가 있다.As described above, the present invention forms a solid support structure by using a lifting hole formed in the prestressed concrete beam, thereby providing a stable fall prevention that maintains the vertical level.

Claims (1)

슈받침 블록위에 탄성 받침을 개재하여 프리스트레스트 콘크리트 빔이 놓여지는 교량 교각구조의 전도방지 시설에 있어서, 수평으로 길게 지면에 놓이는 받침대(12)를 형성하여 일단부가 상기 슈받침 블록(4)의 측벽에 닿도록 위치시키고, 몸체 상부에 볼트 삽입 슬릿홀(20)을 수직으로 길게 형성되고 하부에 받침대 고정부(11)가 형성된 측면지지 파이프(15)를 받침대(12)에 서로 직각을 이루도록 고정하며, 양단부에 지지파이프 고정 플랜지(18)와 받침대 고정 플랜지(19)가 각각 형성되어 있는 지지봉(17)을 상기 측면지지 파이프(15)와 받침대(12)에 형성된 볼트공에 볼트로 체결하며, 상기 지지봉(17)의 몸체 중앙에 수직 수평을 조절하기 위한 수직미세조정키(16)가 형성되고, 상기 프리스트레스트 콘크리트 빔(1)의 측벽에 측면지지 파이프(15)를 대고 양단에 나사산이 형성된 원형파이프 양면볼트(13)를 프리스트레스트 콘크리트 빔(1)에 형성된 인양홀(6)과 볼트삽입 슬릿홀(20)을 동시에 관통하여 너트(14)로 체결하여 고정하는 것을 특징으로 하는 교량 프리스트레스트 콘크리트 빔의 일체형 전도 방지시설.In a fall prevention structure of a bridge bridge structure in which a prestressed concrete beam is placed on a shoe support block through an elastic support, a pedestal 12 is formed to be horizontally elongated so that one end of the side wall of the shoe support block 4 is formed. The side support pipe 15 having the bolt insertion slit hole 20 vertically formed on the upper part of the body and having a pedestal fixing part 11 formed at the lower part thereof so as to be perpendicular to each other on the pedestal 12. And bolts to the bolt holes formed in the side support pipes 15 and the pedestal 12, the support rods 17 having the support pipe fixing flanges 18 and the pedestal fixing flanges 19 formed at both ends thereof, respectively. A vertical fine adjustment key 16 is formed at the center of the body of the support rod 17 to adjust the vertical and horizontal sides. The side support pipe 15 is placed on the sidewall of the prestressed concrete beam 1, The bridge is characterized in that the round pipe double-sided bolt 13 formed with a mountain through the lifting hole 6 and the bolt insertion slit hole 20 formed in the prestressed concrete beam 1 at the same time to be fastened by a nut 14 to be fixed. Integrated fall prevention of prestressed concrete beams.
KR2020010002647U 2001-02-05 2001-02-05 Construction for preventing from upset of prestressed concrete beam KR200232750Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010002647U KR200232750Y1 (en) 2001-02-05 2001-02-05 Construction for preventing from upset of prestressed concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010002647U KR200232750Y1 (en) 2001-02-05 2001-02-05 Construction for preventing from upset of prestressed concrete beam

Publications (1)

Publication Number Publication Date
KR200232750Y1 true KR200232750Y1 (en) 2001-09-26

Family

ID=73062644

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010002647U KR200232750Y1 (en) 2001-02-05 2001-02-05 Construction for preventing from upset of prestressed concrete beam

Country Status (1)

Country Link
KR (1) KR200232750Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908661A (en) * 2022-05-17 2022-08-16 华设设计集团股份有限公司 Rubber energy-consuming self-resetting socket-and-spigot type pier connection structure and assembling method thereof
KR20230026787A (en) * 2021-08-18 2023-02-27 주식회사동일기술공사 Prevention apparatus for turnover of girder for remote construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20230026787A (en) * 2021-08-18 2023-02-27 주식회사동일기술공사 Prevention apparatus for turnover of girder for remote construction
KR102612270B1 (en) * 2021-08-18 2023-12-11 주식회사동일기술공사 Prevention apparatus for turnover of girder for remote construction
CN114908661A (en) * 2022-05-17 2022-08-16 华设设计集团股份有限公司 Rubber energy-consuming self-resetting socket-and-spigot type pier connection structure and assembling method thereof
CN114908661B (en) * 2022-05-17 2023-07-21 华设设计集团股份有限公司 Rubber energy consumption self-resetting socket pier connection structure and assembly method thereof

Similar Documents

Publication Publication Date Title
US7938379B2 (en) Three axis adjustable mounting system
KR100632816B1 (en) Construction for preventing from upset of i-girder for bridge
KR100837230B1 (en) A fixing apparatus for a shape steel beam
KR102168881B1 (en) reinforcement structure of bridge inspection facility
KR200232750Y1 (en) Construction for preventing from upset of prestressed concrete beam
KR101131079B1 (en) Multi U-head Support Apparatus For Bridge Construction
KR200226626Y1 (en) Bracket for Supporting Flooring Slab Form of Bridge
KR20110010248A (en) Multi u-head bracket apparatus for bridge construction
KR100863256B1 (en) Double floor structure
JP3556197B2 (en) Support structure for measuring large silos
KR100880250B1 (en) Potal base of tower crane
CN214996176U (en) Municipal administration public facilities built-in fitting mounting tool
JP2004083264A (en) Beam attaching device
KR200322140Y1 (en) Triangle support structure of beam for concrete slab of bridge
JP3996741B2 (en) Fence transverse beam support bracket and fence transverse beam support method
SU1472554A1 (en) Arrangement for securing roadway panels to beams of railway bridge span structure
KR20010095915A (en) Guide frame for anchoring bar
JP7192153B1 (en) Anchor bolt construction method and level adjustment member
JP2580671Y2 (en) Temporary handrail
JP4460377B2 (en) Clean room joists and clean room joists using the same
KR102416492B1 (en) Inspection road
KR200143185Y1 (en) Support for wall forms
JPH08333719A (en) Wall handrail and setup method thereof
JPH045644Y2 (en)
KR200361540Y1 (en) Truss beam mount structure of power transmission tower f0r high electric

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T601 Decision to invalidate utility model after technical evaluation
LAPS Lapse due to unpaid annual fee