KR102645823B1 - Top-down and bottom-up parallel decommissioning of existing building - Google Patents

Top-down and bottom-up parallel decommissioning of existing building Download PDF

Info

Publication number
KR102645823B1
KR102645823B1 KR1020220098537A KR20220098537A KR102645823B1 KR 102645823 B1 KR102645823 B1 KR 102645823B1 KR 1020220098537 A KR1020220098537 A KR 1020220098537A KR 20220098537 A KR20220098537 A KR 20220098537A KR 102645823 B1 KR102645823 B1 KR 102645823B1
Authority
KR
South Korea
Prior art keywords
strut
dismantling
floor
demolished
retaining wall
Prior art date
Application number
KR1020220098537A
Other languages
Korean (ko)
Other versions
KR20240020470A (en
Inventor
차상호
Original Assignee
동방산업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 동방산업 주식회사 filed Critical 동방산업 주식회사
Priority to KR1020220098537A priority Critical patent/KR102645823B1/en
Publication of KR20240020470A publication Critical patent/KR20240020470A/en
Application granted granted Critical
Publication of KR102645823B1 publication Critical patent/KR102645823B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

본 발명은 기존건물의 하향식 및 상향식 병행 해체 방법에 관한 것으로서, 더욱 상세하게는 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식 해체 공정을 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식 해체 공정을 수행함으로써, H 빔을 기초 구조물까지 천공하여 설치할 필요없이 옹벽 하단 철거시, 처짐 현상을 방지하면서 해체 공사를 진행할 수 있어 간편하면서도 견고하고 안전하게 해체 작업을 수행할 수 있는 기존건물의 하향식 및 상향식 병행 해체 방법에 관한 것이다.The present invention relates to a top-down and bottom-up parallel dismantling method of an existing building. More specifically, in the case of the first floor above ground and the first basement floor, the slab and retaining wall are demolished, then struts and earth plates are installed, and from the second basement floor to the basement. After demolishing the slab up to the structure, performing a top-down dismantling process to install struts, demolishing the foundation structure, and performing soil backfilling, demolition of retaining walls, dismantling of struts, and soil for each floor from the foundation structure to the second basement floor. By performing a bottom-up dismantling process that performs backfilling, dismantling work can be carried out while preventing sagging when demolishing the bottom of a retaining wall without the need to drill and install H beams to the foundation structure, allowing dismantling work to be performed simply, robustly, and safely. It concerns top-down and bottom-up parallel dismantling methods of existing buildings.

Description

기존건물의 하향식 및 상향식 병행 해체 방법{Top-down and bottom-up parallel decommissioning of existing building} Top-down and bottom-up parallel decommissioning of existing building}

본 발명은 기존건물의 하향식 및 상향식 병행 해체 방법에 관한 것으로서, 더욱 상세하게는 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식 해체 공정을 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식 해체 공정을 수행함으로써, H 빔을 기초 구조물까지 천공하여 설치할 필요없이 옹벽 하단 철거시, 처짐 현상을 방지하면서 해체 공사를 진행할 수 있어 간편하면서도 견고하고 안전하게 해체 작업을 수행할 수 있는 기존건물의 하향식 및 상향식 병행 해체 방법에 관한 것이다.The present invention relates to a top-down and bottom-up parallel dismantling method of an existing building. More specifically, in the case of the first floor above ground and the first basement floor, the slab and retaining wall are demolished, then struts and earth plates are installed, and from the second basement floor to the basement. After demolishing the slab up to the structure, performing a top-down dismantling process to install struts, demolishing the foundation structure, and performing soil backfilling, demolition of retaining walls, dismantling of struts, and soil for each floor from the foundation structure to the second basement floor. By performing a bottom-up dismantling process that performs backfilling, dismantling work can be carried out while preventing sagging when demolishing the bottom of a retaining wall without the need to drill and install H beams to the foundation structure, allowing dismantling work to be performed simply, robustly, and safely. It concerns top-down and bottom-up parallel dismantling methods of existing buildings.

흙막이 공법 적용에 따라 지하옹벽이 구축된 다음 흙막이 토목공사용 가설부재(흙막이 파일, 토류판, CIP 등)는 인발되어 제거되거나 일부는 지중에 매립존치되며, 구축되는 대부분의 지하옹벽은 직접 흙에 접하여 토압을 지지한다. After the underground retaining wall is built according to the application of the earth retaining method, temporary members for earth retaining civil engineering work (soil retaining piles, earth plates, CIP, etc.) are pulled out and removed or some are buried in the ground, and most of the underground retaining walls built are in direct contact with the soil and are subject to earth pressure. support.

30년이 넘는 국내 건물들은 건물이 상당 규모의 바닥 면적을 갖는 빌딩으로서 지하층을 갖는 경우일지라도 대부분 그 지하층의 깊이가 대략 3층 이하이며 깊이는 약 4m ~ 17m정도가 되는데, 오래된 건물들이 이처럼 비교적 낮은 지하층을 가지는 이유는 과거에는 차량 대수가 많지 않아 지하 주차공간의 확보가 필수 불가결한 요청이 아닌 것과 관련한다. Domestic buildings that are over 30 years old have a significant floor area, and even if they have a basement, most of them have a basement depth of about 3 stories or less and a depth of about 4m to 17m. Older buildings have this relatively low floor area. The reason for having an underground floor is related to the fact that there were not many cars in the past, so securing underground parking space was not an essential request.

철거대상이 되는 30년이상의 과거 건물들의 지하옹벽은 흙막이 파일과 토류벽 및 엄지말뚝을 사용하거나 지반의 조건에 따라 CIP를 사용한 토공사에 기초하여 구축된 것이 대부분이다. Most underground retaining walls of buildings older than 30 years old that are subject to demolition are constructed based on earthworks using retaining piles, earth walls, and thumb piles, or using CIP depending on the ground conditions.

본 발명에 의한 해체 공법이 적용될 수 있는 지하층의 깊이는 기본적으로 대략 지하 2 이상인 경우에 기존 건물 구조와 관련한 옹벽지지 방식에 따라 적용이 가능하다.Basically, if the depth of the basement to which the dismantling method according to the present invention can be applied is approximately 2 or more underground, it can be applied according to the retaining wall support method related to the existing building structure.

따라서, 일반적으로 철거의 대상으로 되는 건물들의 대부분 30년이 넘는 노후된 건물로서 그 지하층의 깊이가 대개 지하 3층 이하 혹은 지하 3층 이상인 것을 감안할 때, 본 발명에 따른 해체 공법은 지하층을 포함한 건물 전체를 철거한 후, 동일한 대지 경계 내에 건물을 신축하고자 하는 경우의 국내 대부분의 노후된 건물들에 대하여 무리없이 적용될 수 있다.Therefore, considering that most of the buildings that are generally subject to demolition are older than 30 years and the depth of the basement is usually less than 3 stories underground or more than 3 stories underground, the demolition method according to the present invention is used to remove the entire building including the basement floor. It can be applied without difficulty to most old buildings in Korea when a new building is to be constructed within the same site boundary after demolition.

지하층을 갖는 건물을 철거한 이후에 동일한 대지경계 내에 새 건물을 신축하고자 할 경우, 구건물 지상부에 대한 철거는 비교적 어려움이 없으나, 그 지하부분, 특히 지하 옹벽은 상당한 토압을 받고 있는 부분이기 때문에 지하 옹벽으로 둘러싸인 내부의 공간, 즉 지하실 내부공간으로부터 직접 그 옹벽을 무단 파괴하여 철거할 경우에는 토압을 지탱하던 내력벽(옹벽)이 한순간에 없어지는 결과로 되어, 그 옹벽의 철거와 동시에 그 옹벽에 의해 버텨지고 있던 토압이 한꺼번에 작용함으로써 철거공간 내로 일시에 흙이 무너져 내릴 수 있기 때문에 대단히 위험하다.If a new building is to be constructed within the same property boundary after demolishing a building with a basement, there is relatively no difficulty in demolishing the above-ground part of the old building, but since the underground part, especially the underground retaining wall, is a part that is subject to significant earth pressure, the underground retaining wall is required. If the retaining wall is destroyed and demolished directly from the inner space surrounded by the basement, that is, the inner space of the basement, the load-bearing wall (retaining wall) that supported the earth pressure will disappear in an instant, and at the same time as the retaining wall is demolished, it will be held by the retaining wall. It is very dangerous because the earth pressure exerted all at once can cause the soil to collapse into the demolition space.

이러한 이유로 건물의 철거 공사시 지하층의 내부기둥을 포함한 바닥슬라브의 대부분이 모두 철거된 경우일지라도 토압을 받고 있는 건물의 외벽인 지하옹벽은 철거할 수 없는 경우가 많아 결국 그 옹벽을 그대로 남겨둔 상태에서 지하내부 공간 전체를 신속히 외부 반입토사로 되메우기 하게 된다.For this reason, even if most of the floor slabs, including the internal columns of the basement, are demolished during the demolition work of the building, there are many cases where the underground retaining wall, which is the outer wall of the building under earth pressure, cannot be demolished. In the end, the retaining wall is left in place in the basement. The entire interior space will be quickly backfilled with soil brought in from outside.

이 경우, 다음 공정인 신축건물 지하 터파기 공사시 신축하고자 하는 건물의 흙막이 라인이 철거대상이었던 잔류된 지하 옹벽 라인과 겹치거나 교차하는 경우에 흙막이 공사를 위한 파일 천공작업 등에 문제점이 발생하는데 이를 해결하기 위하여 부득이하게 단지 그 존치된 지하 옹벽을 제거하기 위한 목적만의 흙막이 공사 및 굴토를 시행하여 잔류되었던 지하 옹벽을 제거한 다음에 또다시 2차 되메우기를 함으로써 신축하고자 하는 대지경계 내의 지중에 아무런 장애물이 없는 나대지 상태를 만들고, 이처럼 지중에 아무런 장애물이 없는 나대지에 대하여 비로소 신축하고자 하는 건물의 지하 옹벽선에 맞춘 토공사를 재시작하지 않으면 안된다.In this case, during the next process, the underground excavation of a new building, if the retaining line of the building to be newly constructed overlaps or intersects the line of the remaining underground retaining wall that was subject to demolition, problems arise in the pile drilling work for retaining the retaining wall. This problem is solved. In order to do this, it was necessary to carry out earth retaining work and excavation just for the purpose of removing the remaining underground retaining wall, and then perform secondary backfilling to ensure that there were no obstacles in the ground within the boundary of the new construction site. It is necessary to create a bare land condition and restart earthworks in accordance with the underground retaining wall line of the building to be newly built on a bare land with no obstacles in the ground.

일반적인 상향식 지하옹벽 제거 및 매립 공법은 문제로 되는 지하 옹벽을 철거하기 위하여 대단히 번거롭고 공기가 길며 비용이 많이 드는 토공사가 필요한 경우, 특히 신축하고자 하는 건물의 지하 옹벽 라인이 철거 대상으로 되는 지하옹벽라인과 겹치는 경우에 매우 효과적으로 사용할수 있는 공법이다.The general upward underground retaining wall removal and reclamation method is used in cases where extremely cumbersome, long-term, and expensive earthworks are required to demolish the problematic underground retaining wall, especially when the underground retaining wall line of the building to be newly constructed is used to replace the underground retaining wall line to be demolished. This is a method that can be used very effectively in cases of overlap.

즉, 지하옹벽을 제외한 나머지 지하구축물을 완전히 제거한 후 레이커 파일 및 레어커를 설치하여 지하옹벽을 지지하고, 이 상태에서 지하옹벽을 하단부에서부터 부분절개하여 제거한 후 토사 되메우기를 실시하는 과정을 지하옹벽의 하단측으로부터 순차적으로 실시함으로써, 토압에 의해 지하옹벽이 무너지는 것을 방지하면서 안전하게 지하옹벽을 철거하는 것이다.In other words, after completely removing the remaining underground structures except for the underground retaining wall, raker piles and raker are installed to support the underground retaining wall. In this state, the underground retaining wall is partially incised from the bottom to be removed, and then soil backfill is performed. By performing this sequentially from the bottom, the underground retaining wall is safely demolished while preventing it from collapsing due to earth pressure.

그러나, 상기한 상향식 지하옹벽 제거 공법은 지하 옹벽에 가해지는 토압을 레이커 및 레이커 파일을 통해 지지하게 되므로 레이커 파일의 크기가 과도하게 커지거나 레이커의 갯수가 많아지거나 레이커가 길이방향으로 길게 연결 설치되어야 하는 경향이 있어, 레이커에 큰 하중이 작용할 뿐만 아니라, 레이커에 의해 지지되지 않는 지하옹벽 부분이 토압에 의해 밀려들어 레어커 파일 및 결합부 보강을 위한 거셋 플레이트의 경계면에 전단력이 집중되어 거셋 플레이트 부분이 지하옹벽을 뚫고 나가는 현상이 발생할 수 있는 문제점이 발견되었다.However, in the above-mentioned bottom-up underground retaining wall removal method, the earth pressure applied to the underground retaining wall is supported through the raker and raker pile, so the size of the raker pile must be excessively large, the number of rakers must be increased, or the raker must be installed long in the longitudinal direction. Not only does a large load apply to the raker, but the part of the underground retaining wall that is not supported by the raker is pushed in by earth pressure, and the shear force is concentrated on the interface between the raker pile and the gusset plate for reinforcing the joint, thereby concentrating the gusset plate portion. A problem was discovered that could cause the underground retaining wall to break through.

또한, 상향식 지하옹벽 제거공법은 지하옹벽을 제외한 나머지 지하구축물을 완전히 제거한 상태에서 레이커 파일을 박고 레이커를 설치하도록 하고 있으므로, 레이커 파일 및 레이커를 설치하기 이전에 지하옹벽이 토압에 의해 무너질 수 있다. In addition, the bottom-up underground retaining wall removal method involves driving raker piles and installing the raker while completely removing all underground structures except the underground retaining wall, so the underground retaining wall may collapse due to earth pressure before installing the raker piles and rakers.

따라서, 지하옹벽을 제외한 지하구축물의 제거시 바닥 슬래브 및 옹벽 내측 내력벽의 일부를 남긴 상태로 제거한 후 레이커 파일 및 레이커를 설치하게 되는데, 이들 잔류 지하구축물이 레이커 설치에 장애가 될 수 있고 이들을 치우기 위한 작업으로 인해 작업 시간 및 비용이 증가할 수 있다.Therefore, when removing underground structures other than the underground retaining wall, the floor slab and part of the load-bearing wall inside the retaining wall are removed and then raker piles and rakers are installed. These remaining underground structures can become obstacles to raker installation, and work to remove them is required. This may increase work time and costs.

또한, 전술한 상향식 지하옹벽 제거 공법은 옹벽 버팀방식이 레이커에 의하므로 구조검토상 옹벽의 깊이가 약 GL-12m 이상일 경우에는 레이커의 시공이 사실상 불가능하며, 지하층의 평면상의 넓이가 좁음에도 불구하고 레이커를 설치하였을 경우 장비의 작업동선이 나오지 않는 등의 시공상 문제점도 발견되었다.In addition, in the above-mentioned upward underground retaining wall removal method, the retaining wall support method is based on a raker, so when the depth of the retaining wall is more than about GL-12m according to the structural review, raker construction is virtually impossible, and even though the planar area of the basement is narrow, When the raker was installed, construction problems were also discovered, such as the equipment's work movement line not being visible.

따라서, 본 발명에서는 상기한 문제점을 개선하고자 하향식 해체 방법과 상향식 해체 방법을 동시에 제공할 수 있는 공법을 제안하게 된 것이다.Therefore, in order to improve the above-mentioned problems, the present invention proposes a method that can simultaneously provide a top-down dismantling method and a bottom-up dismantling method.

일본 공개특허 평성 1995-150564호Japanese Patent Publication No. 1995-150564

따라서, 본 발명은 상기 종래의 문제점을 해소하기 위해 안출된 것으로,Therefore, the present invention was devised to solve the above conventional problems,

본 발명의 목적은 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식 해체 공정을 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식 해체 공정을 수행함으로써, H 빔을 기초 구조물까지 천공하거나, 아주 깊이 설치할 필요없이 옹벽 하단 철거시, 처짐 현상을 방지하면서 해체 공사를 진행할 수 있어 간편하면서도 견고하고 안전하게 해체 작업을 수행할 수 있도록 하는데 있다.The purpose of the present invention is to install struts and earthen plates after demolishing the slabs and retaining walls in the case of the first floor above ground and the first floor underground, and to install struts after demolishing the slabs from the second basement floor to the underground structure. After performing the demolition of the basic structure, performing soil backfilling, and performing a bottom-up dismantling process of demolishing retaining walls, dismantling struts, and performing soil backfilling for each floor from the basic structure to the second basement floor, the H beam was laid as a foundation. The purpose is to allow dismantling work to be carried out while preventing sagging when demolishing the bottom of a retaining wall without the need to drill into the structure or install it very deeply, making it simple, sturdy, and safe.

본 발명이 해결하고자 하는 과제를 달성하기 위하여, 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법은,In order to achieve the problem that the present invention seeks to solve, the top-down and bottom-up parallel dismantling method of an existing building according to an embodiment of the present invention is,

기존건물의 중앙 부위와 사이드 부위에 센타 파일 및 사이드 파일을 설치하는 파일설치단계(S1000)와, A pile installation step (S1000) in which center piles and side piles are installed in the center and side areas of the existing building,

상기 파일설치단계를 수행한 후, 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식해체단계(S2000)와,After performing the above pile installation step, in the case of the first floor above ground and the first basement floor, the slabs and retaining walls are demolished, then struts and earth plates are installed, and the slabs are demolished from the second basement floor to the underground structure, and then the struts are installed. A top-down disassembly step (S2000),

상기 하향식해체단계를 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식해체단계(S3000)를 포함하여 구성함으로써, 본 발명의 과제를 해결하게 된다.After performing the top-down dismantling step, the basic structure is demolished, soil backfilling is performed, and then a bottom-up dismantling step (S3000) is performed in which retaining wall demolition, strut dismantling, and soil backfilling are performed for each floor from the basic structure to the second basement floor. By including and configuring, the problem of the present invention is solved.

본 발명에 따른 기존건물의 하향식 및 상향식 병행 해체 방법은,The top-down and bottom-up parallel dismantling method of an existing building according to the present invention,

지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식 해체 공정을 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식 해체 공정을 수행함으로써, H 빔을 기초 구조물까지 천공하거나, 아주 깊이 설치할 필요없이 옹벽 하단 철거시, 처짐 현상을 방지하면서 해체 공사를 진행할 수 있어 간편하면서도 견고하고 안전하게 해체 작업을 수행할 수 있도록 함으로써, 불의의 사고를 사전에 방지할 수 있는 효과를 제공하게 된다.In the case of the first floor above ground and the first basement floor, the slabs and retaining walls are demolished, then struts and earth plates are installed. After the slabs are demolished from the second basement floor to the underground structure, and the struts are installed, a top-down dismantling process is performed. After demolishing the foundation structure and performing soil backfilling, a bottom-up dismantling process is performed to demolish retaining walls, dismantle struts, and perform soil backfilling for each floor from the foundation structure to the second basement level, thereby drilling the H beam to the foundation structure, or When dismantling the bottom of a retaining wall without having to install it very deeply, dismantling work can be carried out while preventing sagging, allowing dismantling work to be performed simply, robustly and safely, providing the effect of preventing unexpected accidents in advance. .

도 1은 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법의 전체 공정도이다.
도 2는 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법의 전체 공정을 간략하게 나타낸 예시도이다.
도 3은 종래 기존건물의 하향식 해체 방법을 개략적으로 나타낸 예시도이다.
도 4는 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법의 전체 공정을 간략하게 나타낸 예시도이다.
도 5 내지 도 6은 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법을 공정별로 나타낸 예시도이다.
Figure 1 is an overall process diagram of a top-down and bottom-up parallel dismantling method of an existing building according to an embodiment of the present invention.
Figure 2 is an exemplary diagram briefly showing the entire process of the top-down and bottom-up parallel dismantling method of an existing building according to an embodiment of the present invention.
Figure 3 is an example diagram schematically showing a conventional top-down dismantling method of an existing building.
Figure 4 is an exemplary diagram briefly showing the entire process of the top-down and bottom-up parallel dismantling method of an existing building according to an embodiment of the present invention.
Figures 5 and 6 are exemplary diagrams showing the top-down and bottom-up parallel dismantling methods of an existing building by process, according to an embodiment of the present invention.

본 발명의 과제를 해결하기 위한 기존건물의 하향식 및 상향식 병행 해체 방법은,The top-down and bottom-up parallel dismantling method of an existing building to solve the problem of the present invention is,

기존건물의 중앙 부위와 사이드 부위에 센타 파일 및 사이드 파일을 설치하는 파일설치단계(S1000)와, A pile installation step (S1000) in which center piles and side piles are installed in the center and side areas of the existing building,

상기 파일설치단계를 수행한 후, 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식해체단계(S2000)와,After performing the above pile installation step, in the case of the first floor above ground and the first basement floor, the slabs and retaining walls are demolished, then struts and earth plates are installed, and the slabs are demolished from the second basement floor to the underground structure, and then the struts are installed. A top-down disassembly step (S2000),

상기 하향식해체단계를 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식해체단계(S3000)를 포함하는 것을 특징으로 한다.After performing the top-down dismantling step, the basic structure is demolished, soil backfilling is performed, and then a bottom-up dismantling step (S3000) is performed in which retaining wall demolition, strut dismantling, and soil backfilling are performed for each floor from the basic structure to the second basement floor. It is characterized by including.

구체적으로, 본 발명인 기존건물의 하향식 및 상향식 병행 해체 방법은,Specifically, the top-down and bottom-up parallel dismantling method of an existing building according to the present invention is,

지상 철거후, 사이드 파일 설치를 위하여 천공하며, 천공된 위치에 사이드 파일을 설치하기 위한 사이드파일설치단계(S100);와After demolition of the ground, drilling is performed to install the side piles, and a side pile installation step (S100) to install the side piles at the perforated location;

상기 사이드 파일 설치한 후, 센타 파일 설치를 위하여 천공하며, 천공된 위치에 센타 파일을 설치하기 위한 센타파일설치단계(S200);와After installing the side piles, drilling holes for installing center piles, and installing center piles at the perforated positions (S200);

상기 센타 파일 설치한 후, 지상 1층 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치하기 위한 지상스트러트및토류판설치단계(S300);와After installing the center pile, the slab and retaining wall on the first floor above ground are demolished, the first strut and the first earth plate are installed on the lower side of the demolished location, and the second strut and the second earth plate are installed on the upper side of the first strut and the first earth plate. Ground strut and earth plate installation step for installing the earth plate (S300); and

상기 공정을 마친 후, 지하 1층 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치하기 위한 지하1층스트러트및토류판설치단계(S400);와After completing the above process, the slab and retaining wall of the first basement floor are demolished, the first strut and the first earth plate are installed on the lower side of the demolished location, and the second strut and the second earth plate are installed on the upper side of the first strut and the first earth plate. Basement first floor strut and earth plate installation step (S400) to install; and

상기 공정을 마친 후, 지하 2층부터 하방으로 각 층마다 슬라브를 철거하고, 철거된 위치의 하측에 제1스트러트를 설치하고, 제1스트러트의 상측으로 제2스트러트를 설치하는 공정을 지하 2층부터 하방으로 각층마다 순차적으로 반복하여 실시하는 지하층별스트러트설치단계(S500);와After completing the above process, the slabs are demolished on each floor starting from the 2nd basement floor downward, the first strut is installed on the lower side of the demolished position, and the second strut is installed on the upper side of the first strut. Strut installation step for each basement floor (S500), which is performed sequentially and repeatedly for each floor starting downwards;

상기 공정을 마친 후, 지하 최하단의 기초 구조물과 옹벽을 철거하고, 지하 최하측에 설치된 제1스트러트를 해체한 후, 제1스트러트가 제거된 높이 이상으로 토사 되메우기를 실시하는 1차 복토를 수행하기 위한 기초철거및1차복토단계(S600);와After completing the above process, the foundation structure and retaining wall at the lowest level of the basement are demolished, the first strut installed at the lowest level underground is dismantled, and then the first covering is performed by backfilling soil above the height at which the first strut was removed. Foundation demolition and first covering stage (S600) for

상기 1차 복토 과정을 진행한 후, 지하 하측부터 상측으로 스트러트들을 해체하면서 옹벽을 철거하고, 해당 위치에 토사 되메우기를 실시하는 2차 복토를 수행하는 공정을 각층마다 반복적으로 실시하는 스트러트해체및2차복토단계(S700);를 포함하는 것을 특징으로 한다.After carrying out the first covering process, the retaining wall is demolished while dismantling the struts from the lower part of the basement to the upper side, and the second covering process of performing soil backfilling at the corresponding location is repeatedly performed for each floor. Strut dismantling and 2 It is characterized in that it includes a subsoil step (S700).

이때, 상기 하향식 해체와 상향식 해체를 병행하여 슬라브 및 옹벽을 제거함으로써, H 빔을 기초 구조물까지 천공하여 설치할 필요가 없는 것을 특징으로 한다.At this time, by removing the slab and retaining wall by performing the top-down dismantling and bottom-up dismantling in parallel, there is no need to drill and install the H beam to the foundation structure.

이때, 하향식 해체와 상향식 해체를 병행함에 따라, 옹벽 하단 철거시, 처짐 현상을 방지하는 것을 특징으로 한다.At this time, as top-down dismantling and bottom-up dismantling are performed in parallel, sagging is prevented when the lower part of the retaining wall is demolished.

이하, 본 발명에 의한 기존건물의 하향식 및 상향식 병행 해체 방법의 실시예를 통해 상세히 설명하도록 한다.Hereinafter, the top-down and bottom-up parallel dismantling method of an existing building according to the present invention will be described in detail through examples.

도 1은 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법의 전체 공정도이다.Figure 1 is an overall process diagram of a top-down and bottom-up parallel dismantling method of an existing building according to an embodiment of the present invention.

도 2는 본 발명의 일실시예에 따른 기존건물의 하향식 및 상향식 병행 해체 방법의 전체 공정을 간략하게 나타낸 예시도이다.Figure 2 is an exemplary diagram briefly showing the entire process of the top-down and bottom-up parallel dismantling method of an existing building according to an embodiment of the present invention.

도 1에 도시한 바와 같이, 본 발명은 기존건물의 중앙 부위와 사이드 부위에 센타 파일 및 사이드 파일을 설치하는 파일설치단계(S1000)와, As shown in Figure 1, the present invention includes a pile installation step (S1000) of installing center piles and side piles in the center and side areas of an existing building,

상기 파일설치단계를 수행한 후, 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식해체단계(S2000)와,After performing the above pile installation step, in the case of the first floor above ground and the first basement floor, the slabs and retaining walls are demolished, then struts and earth plates are installed, and the slabs are demolished from the second basement floor to the underground structure, and then the struts are installed. A top-down disassembly step (S2000),

상기 하향식해체단계를 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식해체단계(S3000)를 포함하는 것을 특징으로 한다.After performing the top-down dismantling step, the basic structure is demolished, soil backfilling is performed, and then a bottom-up dismantling step (S3000) is performed in which retaining wall demolition, strut dismantling, and soil backfilling are performed for each floor from the basic structure to the second basement floor. It is characterized by including.

일반적으로 도 3에 도시한 바와 같이, 종래 하향식 해체 방식은 H 빔을 기초 구조물까지 깊이 설치하기 위하여 천공 작업을 수행하고, 기초 구조물까지 깊이 박아야 하기 때문에 이에 따른 공사비와 공기가 늦어지는 문제점이 발생하였다.In general, as shown in FIG. 3, the conventional top-down dismantling method requires drilling to install the H beam deeply into the foundation structure and driving it deep into the foundation structure, which causes the problem of delayed construction costs and construction period. did.

또한, 기초 구조물이 강성이 높을 경우에는 천공이 불가능하여 이에 따른 공사가 지연되는 문제점이 발생하였다.In addition, when the rigidity of the foundation structure is high, drilling is impossible, which causes delays in construction.

그러나 도 4에 도시한 바와 같이, 상기와 같이 공정을 수행하게 되면, 하향식 해체와 상향식 해체를 병행하여 슬라브 및 옹벽을 제거함으로써, H 빔을 기초 구조물까지 천공하여 설치할 필요가 없는 것을 특징으로 한다.However, as shown in Figure 4, when the process is performed as above, the slab and retaining wall are removed through top-down dismantling and bottom-up dismantling in parallel, so there is no need to drill and install the H beam to the basic structure.

구체적으로 설명하자면, 파일설치단계(S1000)는 기존건물의 중앙 부위와 사이드 부위에 센타 파일 및 사이드 파일을 설치하는 공정으로서, 도 2에 도시한 바와 같이, 지상 철거후, 사이드 파일 설치를 위하여 천공하며, 천공된 위치에 사이드 파일을 설치하기 위한 사이드파일설치단계(S100);와To be specific, the pile installation step (S1000) is a process of installing center piles and side piles in the center and side areas of the existing building. As shown in Figure 2, after demolition of the ground, drilling is performed to install side piles. And a side pile installation step (S100) to install the side pile at the perforated location; and

상기 사이드 파일 설치한 후, 센타 파일 설치를 위하여 천공하며, 천공된 위치에 센타 파일을 설치하기 위한 센타파일설치단계(S200);를 포함하게 된다.After installing the side piles, a center pile installation step (S200) is included to drill a hole for installing the center pile and install the center pile at the perforated location.

즉, 도 5에 도시한 바와 같이, 지상 철거후, 사이드 파일 설치를 위하여 천공하며, 천공된 위치에 사이드 파일을 설치(S100)하게 되는 것이다.That is, as shown in FIG. 5, after the ground is removed, a hole is drilled to install the side pile, and the side pile is installed at the perforated location (S100).

이후, 센타 파일 설치를 위하여 천공 공정을 수행하며, 해당 천공된 위치에 센타 파일을 설치하여 안전하게 기존 건물에 대한 해체 작업을 수행할 수 있도록 하게 된다.Afterwards, a drilling process is performed to install the center pile, and the center pile is installed at the perforated location to safely dismantle the existing building.

이후, 하향식해체단계(S2000)는 파일설치단계를 수행한 후, 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 공정으로서, 도 2에 도시한 바와 같이, 상기 센타 파일 설치한 후, 지상 1층 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치하기 위한 지상스트러트및토류판설치단계(S300);와Afterwards, in the top-down dismantling step (S2000), after performing the pile installation step, in the case of the first floor above ground and the first basement floor, the slab and retaining wall are demolished, then struts and earth plates are installed, and the slab is installed from the second basement floor to the underground structure. As a process of installing struts after demolishing, as shown in FIG. 2, after installing the center pile, the first floor slab and retaining wall are demolished, and the first strut and first earth plate are installed on the lower side of the demolished position. Installing a ground strut and earth plate installation step (S300) for installing the second strut and the second earth plate on the upper side of the first strut and the first earth plate; and

상기 공정을 마친 후, 지하 1층 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치하기 위한 지하1층스트러트및토류판설치단계(S400);와After completing the above process, the slab and retaining wall of the first basement floor are demolished, the first strut and the first earth plate are installed on the lower side of the demolished location, and the second strut and the second earth plate are installed on the upper side of the first strut and the first earth plate. Basement first floor strut and earth plate installation step (S400) to install; and

상기 공정을 마친 후, 지하 2층부터 하방으로 각 층마다 슬라브를 철거하고, 철거된 위치의 하측에 제1스트러트를 설치하고, 제1스트러트의 상측으로 제2스트러트를 설치하는 공정을 지하 2층부터 하방으로 각층마다 순차적으로 반복하여 실시하는 지하층별스트러트설치단계(S500);를 포함하게 된다.After completing the above process, the slabs are demolished on each floor starting from the 2nd basement floor downward, the first strut is installed on the lower side of the demolished position, and the second strut is installed on the upper side of the first strut. It includes a strut installation step for each basement floor (S500), which is sequentially repeated for each floor downward.

구체적으로 설명하면, 도 5에 도시한 바와 같이, 지상 1층의 슬라브 및 옹벽을 철거하는 공정을 실시하게 되며, 해당 1층 슬라브 및 옹벽이 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하게 된다.Specifically, as shown in Figure 5, the process of demolishing the slab and retaining wall on the first floor above ground is carried out, and the first strut and first earth plate are installed below the location where the first floor slab and retaining wall were demolished. It will be installed.

그리고, 제1스트러트 및 제1토류판의 상측으로 일정 간격 이격된 위치에 제2스트러트 및 제2토류판을 설치(S300)하게 되는 것이다.Then, the second strut and the second earth plate are installed at a certain distance above the first strut and the first earth plate (S300).

이후, 지하 1층의 경우도 지상 1층과 마찬가지로 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치(S400)하게 되는 것이다.Afterwards, in the case of the first basement floor, the slab and retaining wall were demolished like the first floor above ground, the first strut and the first earth plate were installed on the lower side of the demolished location, and the second strut was installed on the upper side of the first strut and the first earth plate. And the second earthen plate is installed (S400).

상기 공정을 마친 후, 지하 2층부터 하방으로 각 층마다 슬라브를 철거하고, 철거된 위치의 하측에 제1스트러트를 설치하고, 제1스트러트의 상측으로 제2스트러트를 설치하는 공정을 지하 2층부터 하방으로 각층마다 순차적으로 반복하여 실시(S500)하게 되는 것이다.After completing the above process, the slabs are demolished on each floor starting from the 2nd basement floor downward, the first strut is installed on the lower side of the demolished position, and the second strut is installed on the upper side of the first strut. The process is repeated sequentially for each floor starting downwards (S500).

본 발명의 예시에서는 지하 3층까지 설명하고 있으므로 지하 2층부터 지하 3층까지 제1스트러트 및 제2스트러트 설치 공정을 각각 실시하게 되는 것이다.In the example of the present invention, the 3rd basement floor is described, so the first and second strut installation processes are performed from the 2nd basement floor to the 3rd basement floor, respectively.

예를 들어, 지하 2층의 슬라브를 철거하고, 제1스트러트(6단), 제2스트러트(5단)을 설치하게 된다.For example, the slab on the second basement floor is demolished, and the first strut (6 stages) and the second strut (5 stages) are installed.

상기 지하 2층의 공정을 마무리하고, 지하 3층의 슬라브를 철거하고, 제1스트러트(8단), 제2스트러트(7단)을 설치하게 된다.The process for the second basement floor is completed, the slab on the third basement floor is demolished, and the first strut (8 stages) and the second strut (7 stages) are installed.

이후, 상향식해체단계(S3000)는 하향식해체단계를 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 공정으로서, 도 2에 도시한 바와 같이, 상기 공정을 마친 후, 지하 최하단의 기초 구조물과 옹벽을 철거하고, 지하 최하측에 설치된 제1스트러트를 해체한 후, 제1스트러트가 제거된 높이 이상으로 토사 되메우기를 실시하는 1차 복토를 수행하기 위한 기초철거및1차복토단계(S600);와Afterwards, in the bottom-up dismantling step (S3000), the top-down dismantling step is performed, the basic structure is demolished, soil backfilling is performed, and retaining wall demolition, strut dismantling, and soil backfilling are performed for each floor from the basic structure to the second basement floor. As a process, as shown in FIG. 2, after completing the above process, the foundation structure and retaining wall at the lowest underground level are demolished, and the first strut installed at the lowest underground level is dismantled, and then the height above the height at which the first strut was removed is removed. Foundation demolition and first covering step (S600) to perform the first covering with soil backfilling; and

상기 1차 복토 과정을 진행한 후, 지하 하측부터 상측으로 스트러트들을 해체하면서 옹벽을 철거하고, 해당 위치에 토사 되메우기를 실시하는 2차 복토를 수행하는 공정을 각층마다 반복적으로 실시하는 스트러트해체및2차복토단계(S700);를 포함하게 된다.After carrying out the first covering process, the retaining wall is demolished while dismantling the struts from the lower part of the basement to the upper side, and the second covering process of performing soil backfilling at the corresponding location is repeatedly performed for each floor. Strut dismantling and 2 It includes a sub-covering soil step (S700).

즉, 도 6에 도시한 바와 같이, 지하 최하단의 기초 구조물과 옹벽을 철거하고, 지하 최하측에 설치된 제1스트러트를 해체한 후, 제1스트러트가 제거된 높이 이상으로 토사 되메우기를 실시하는 1차 복토를 수행(S600)하게 된다.That is, as shown in FIG. 6, the foundation structure and retaining wall at the lowest underground level are demolished, the first strut installed at the lowest underground level is dismantled, and then soil backfilling is performed above the height at which the first strut was removed. Covering soil is performed (S600).

본 발명의 예시에서는 지하 3층까지 존재하고 있으므로 지하 3층 바닥의 기초 구조물을 제거하고, 옹벽을 철거한 후, 지하 최하측에 설치된 제1스트러트(8단)를 해체한 후, 제1스트러트가 제거된 높이 이상으로 토사 되메우기를 실시하게 되는 것이다.In the example of the present invention, since it exists up to the 3rd basement floor, the foundation structure of the 3rd basement floor is removed, the retaining wall is demolished, and the first strut (8 stages) installed at the lowest basement is dismantled, and then the first strut is Soil backfilling is carried out beyond the removed height.

상기 1차 복토 과정을 진행한 후, 지하 하측부터 상측으로 스트러트들을 해체하면서 옹벽을 철거하고, 해당 위치에 토사 되메우기를 실시하는 2차 복토를 수행하는 공정을 각층마다 반복적으로 실시(S700)하게 되는 것이다.After carrying out the first covering process, the process of performing a secondary covering process of dismantling the retaining wall by dismantling the struts from the lower part of the basement to the upper side and performing soil backfilling at the corresponding location is repeatedly performed for each floor (S700). will be.

즉, 제2스트러트(7단)을 해체하면서 옹벽을 철거하고, 해당 위치에 토사 되메우기를 실시하게 된다.In other words, while dismantling the second strut (7th stage), the retaining wall is removed and soil backfill is performed at the corresponding location.

그리고, 지하 2층의 스트러트들을 해체하면서 옹벽을 철거하고, 해당 위치에 토사 되메우기를 실시하게 되는 것이다.In addition, while dismantling the struts on the second basement floor, the retaining wall will be removed, and soil backfill will be performed at the corresponding location.

이러한 공정들을 각층마다 반복적으로 실시하여 최종 지상까지 토사 되메우기를 실시하게 되는 것이다.These processes are performed repeatedly for each layer, and soil backfill is carried out until the final ground level.

이를 통해, 처짐 발생을 방지시켜 구조물이 철거된 공간으로 흙이 유입되는 불상사를 방지하게 되는 것이다.Through this, sagging is prevented and the unfortunate event of soil flowing into the space where the structure was demolished is prevented.

상기와 같은 구성 및 공정을 통해, 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식 해체 공정을 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식 해체 공정을 수행함으로써, H 빔을 기초 구조물까지 천공하거나, 아주 깊이 설치할 필요없이 옹벽 하단 철거시, 처짐 현상을 방지하면서 해체 공사를 진행할 수 있어 간편하면서도 견고하고 안전하게 해체 작업을 수행할 수 있도록 함으로써, 불의의 사고를 사전에 방지할 수 있는 효과를 제공하게 된다.Through the above configuration and process, in the case of the first floor above ground and the first basement floor, the slabs and retaining walls are removed, then struts and earth plates are installed, and the slabs are demolished from the second basement floor to the underground structure, and then struts are installed. After performing a top-down dismantling process, demolishing the basic structure, performing soil backfilling, and then performing a bottom-up dismantling process of demolishing retaining walls, dismantling struts, and performing soil backfilling for each floor from the basic structure to the second basement floor, Dismantling work can be carried out while preventing sagging when demolishing the bottom of a retaining wall without the need to drill H beams to the foundation structure or install them very deeply, allowing dismantling work to be performed simply, robustly and safely, preventing unexpected accidents in advance. It provides preventable effects.

상기와 같은 내용의 본 발명이 속하는 기술분야의 당업자는 본 발명의 기술적 사상이나 필수적 특징을 변경하지 않고서 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시 예들은 모든 면에서 예시된 것이며 한정적인 것이 아닌 것으로서 이해해야만 한다. Those skilled in the art to which the present invention pertains as described above will understand that the present invention can be implemented in other specific forms without changing its technical idea or essential features. Therefore, the embodiments described above should be understood in all respects as illustrative and not limiting.

S1000 : 파일설치단계
S2000 : 하향식해체단계
S3000 : 상향식해체단계
S1000: File installation stage
S2000: Top-down disassembly phase
S3000: Bottom-up disassembly stage

Claims (3)

기존 건물의 하향식 및 상향식 병행 해체 방법에 있어서,
기존 건물의 중앙 부위와 사이드 부위에 센타 파일 및 사이드 파일을 설치하는 파일설치단계(S1000)와,
상기 파일설치단계를 수행한 후, 지상 1층과 지하 1층의 경우, 슬라브 및 옹벽을 철거한 후, 스트러트와 토류판을 설치하며, 지하 2층부터 지하 구조물까지 슬라브를 철거한 후, 스트러트를 설치하는 하향식해체단계(S2000)와,
상기 하향식해체단계를 수행한 후, 기초구조물을 철거하고, 토사 되메우기를 수행한 후, 기초구조물부터 지하 2층까지 각 층별로 옹벽 철거와 스트러트 해체 및 토사 되메우기를 수행하는 상향식해체단계(S3000)를 포함하는 것을 특징으로 하되,
상기 파일설치단계(S1000)는,
지상 철거후, 사이드 파일 설치를 위하여 천공하며, 천공된 위치에 사이드 파일을 설치하기 위한 사이드파일설치단계(S100);와
상기 사이드 파일 설치한 후, 센타 파일 설치를 위하여 천공하며, 천공된 위치에 센타 파일을 설치하기 위한 센타파일설치단계(S200);를 포함하는 것을 특징으로 하며,
상기 하향식해체단계(S2000)는,
센타 파일 설치한 후, 지상 1층 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치하기 위한 지상스트러트및토류판설치단계(S300);와
상기 지상스트러트및토류판설치단계(S300)를 마친 후, 지하 1층 슬라브 및 옹벽을 철거하고, 철거된 위치의 하측에 제1스트러트 및 제1토류판을 설치하고, 제1스트러트 및 제1토류판의 상측으로 제2스트러트 및 제2토류판을 설치하기 위한 지하1층스트러트및토류판설치단계(S400);와
상기 지하1층스트러트및토류판설치단계(S400)를 마친 후, 지하 2층부터 하방으로 각 층마다 슬라브를 철거하고, 철거된 위치의 하측에 제1스트러트를 설치하고, 제1스트러트의 상측으로 제2스트러트를 설치하는 공정을 지하 2층부터 하방으로 각층마다 순차적으로 반복하여 실시하는 지하층별스트러트설치단계(S500);를 포함하는 것을 특징으로 하며,
상기 상향식해체단계(S3000)는,
지하 최하단의 기초 구조물과 옹벽을 철거하고, 지하 최하측에 설치된 제1스트러트를 해체한 후, 제1스트러트가 제거된 높이 이상으로 토사 되메우기를 실시하는 1차 복토를 수행하기 위한 기초철거및1차복토단계(S600);와
상기 1차 복토 과정을 진행한 후, 지하 하측부터 상측으로 스트러트들을 해체하면서 옹벽을 철거하고, 해당 위치에 토사 되메우기를 실시하는 2차 복토를 수행하는 공정을 각층마다 반복적으로 실시하는 스트러트해체및2차복토단계(S700);를 포함하는 것을 특징으로 하는 기존 건물의 하향식 및 상향식 병행 해체 방법.
In the top-down and bottom-up parallel dismantling method of an existing building,
A pile installation step (S1000) in which center piles and side piles are installed in the center and side areas of the existing building,
After performing the above pile installation step, in the case of the first floor above ground and the first basement floor, the slabs and retaining walls are demolished, then struts and earth plates are installed, and the slabs are demolished from the second basement floor to the underground structure, and then the struts are installed. A top-down disassembly step (S2000),
After performing the top-down dismantling step, the basic structure is demolished, soil backfilling is performed, and then a bottom-up dismantling step (S3000) is performed in which retaining wall demolition, strut dismantling, and soil backfilling are performed for each floor from the basic structure to the second basement floor. Characterized by including,
The file installation step (S1000) is,
After demolition of the ground, drilling is performed to install the side piles, and a side pile installation step (S100) to install the side piles at the perforated location;
After installing the side piles, drilling holes to install center piles, and a center pile installation step (S200) for installing the center piles at the perforated positions,
In the top-down disassembly step (S2000),
After installing the center pile, the slab and retaining wall on the first floor above ground are demolished, the first strut and first earth plate are installed on the lower side of the demolished location, and the second strut and second earth plate are installed on the upper side of the first strut and first earth plate. Ground strut and earth plate installation step (S300) to install; and
After completing the ground strut and earth plate installation step (S300), the slab and retaining wall on the first basement floor are demolished, the first strut and the first earth plate are installed on the lower side of the demolished location, and the upper side of the first strut and the first earth plate First basement floor strut and earth plate installation step (S400) to install the second strut and second earth plate; and
After completing the first basement floor strut and earth plate installation step (S400), the slabs are demolished for each floor from the second basement floor downward, the first strut is installed below the demolished location, and the first strut is installed on the upper side of the first strut. It is characterized in that it includes a basement-level strut installation step (S500) in which the process of installing two struts is sequentially repeated for each floor from the second basement floor downward,
In the bottom-up disassembly step (S3000),
Foundation demolition and primary covering to perform primary covering, which involves demolishing the foundation structure and retaining wall at the lowest underground level, dismantling the first strut installed at the lowest underground level, and then backfilling with soil above the height where the first strut was removed. Covering stage (S600); and
After carrying out the first covering process, the retaining wall is demolished while dismantling the struts from the lower part of the basement to the upper side, and the second covering process of performing soil backfilling at the corresponding location is repeatedly performed for each floor. Strut dismantling and 2 A top-down and bottom-up parallel dismantling method of an existing building, comprising a sub-soil step (S700).
제 1항에 있어서,
상기 하향식 해체와 상향식 해체를 병행하여 슬라브 및 옹벽을 제거함으로써, H 빔을 기초 구조물까지 천공하여 설치할 필요가 없는 것을 특징으로 하는 기존 건물의 하향식 및 상향식 병행 해체 방법.
According to clause 1,
A top-down and bottom-up parallel dismantling method of an existing building, characterized in that there is no need to drill and install an H beam to the foundation structure by removing the slab and retaining wall by performing the top-down and bottom-up dismantling in parallel.
제 1항에 있어서,
상기 하향식 해체와 상향식 해체를 병행함에 따라, 옹벽 하단 철거시, 처짐 현상을 방지하는 것을 특징으로 하는 기존 건물의 하향식 및 상향식 병행 해체 방법.
According to clause 1,
A top-down and bottom-up parallel dismantling method of an existing building, characterized in that it prevents sagging when demolishing the lower part of a retaining wall by performing the top-down and bottom-up dismantling in parallel.
KR1020220098537A 2022-08-08 2022-08-08 Top-down and bottom-up parallel decommissioning of existing building KR102645823B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220098537A KR102645823B1 (en) 2022-08-08 2022-08-08 Top-down and bottom-up parallel decommissioning of existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220098537A KR102645823B1 (en) 2022-08-08 2022-08-08 Top-down and bottom-up parallel decommissioning of existing building

Publications (2)

Publication Number Publication Date
KR20240020470A KR20240020470A (en) 2024-02-15
KR102645823B1 true KR102645823B1 (en) 2024-03-11

Family

ID=89899197

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220098537A KR102645823B1 (en) 2022-08-08 2022-08-08 Top-down and bottom-up parallel decommissioning of existing building

Country Status (1)

Country Link
KR (1) KR102645823B1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102400229B1 (en) * 2021-12-20 2022-05-20 박차순 Method for demolishing underground building

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0819676B2 (en) 1993-03-04 1996-02-28 房夫 坂野 Method for removing underground structures and obstacles within the adjacent line of 1.000 mm from the boundary
KR102333978B1 (en) * 2019-11-04 2021-12-03 신용동 Pileless-up wall demolition method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102400229B1 (en) * 2021-12-20 2022-05-20 박차순 Method for demolishing underground building

Also Published As

Publication number Publication date
KR20240020470A (en) 2024-02-15

Similar Documents

Publication Publication Date Title
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
US20220098817A1 (en) Method for constructing structure
KR101187170B1 (en) Application of under pinning method in remodeling
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JP2000352296A (en) Method o constructing passage just under underground structure
KR102522619B1 (en) Upward basement structure demolition method
KR102645823B1 (en) Top-down and bottom-up parallel decommissioning of existing building
JP2012233349A (en) Earth retaining method
KR101052363B1 (en) Freestanding Digging Method for Deep Excavation
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JP2005002671A (en) Underpinning method and viaduct
KR20170035321A (en) Retaining wall construction method and retaining wall structure by the method
KR102568229B1 (en) Bottom-up dismantling method using existing building slab
KR100397958B1 (en) The structure timbering of cut with separating wale and the construction method thereof
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR102579002B1 (en) Method of demolition of underground exterior walls
KR102570649B1 (en) Method of demolition of underground exterior walls
JP6827256B2 (en) How to rebuild the building
KR100515971B1 (en) Soil retaining method using H-pile having large section
KR101256311B1 (en) Structual deepening method
KR102601694B1 (en) Method for demolishing underground building
CN115262568B (en) Deepening support and excavation construction method based on zero-field deep foundation pit
KR102149709B1 (en) Deformation prevention method of files for retaining wall of underground

Legal Events

Date Code Title Description
GRNT Written decision to grant