KR101776916B1 - Horizontal casing propulsion type underground line construction method - Google Patents

Horizontal casing propulsion type underground line construction method Download PDF

Info

Publication number
KR101776916B1
KR101776916B1 KR1020160170142A KR20160170142A KR101776916B1 KR 101776916 B1 KR101776916 B1 KR 101776916B1 KR 1020160170142 A KR1020160170142 A KR 1020160170142A KR 20160170142 A KR20160170142 A KR 20160170142A KR 101776916 B1 KR101776916 B1 KR 101776916B1
Authority
KR
South Korea
Prior art keywords
casing
conduit
line
cylindrical body
excavation
Prior art date
Application number
KR1020160170142A
Other languages
Korean (ko)
Inventor
박찬성
Original Assignee
주식회사 도화엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 도화엔지니어링 filed Critical 주식회사 도화엔지니어링
Priority to KR1020160170142A priority Critical patent/KR101776916B1/en
Application granted granted Critical
Publication of KR101776916B1 publication Critical patent/KR101776916B1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/16Machines for digging other holes in the soil
    • E02F5/18Machines for digging other holes in the soil for horizontal holes or inclined holes
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
    • H02G1/081Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling using pulling means at cable ends, e.g. pulling eyes or anchors
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/06Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention relates to a non-excavation underground electric line installation method using underground propulsion. A conduit (41) is installed inside a casing (40) by pulling and binding the conduit (41) to a pulling line (45) embedded in the casing (40) after a preliminary drilling hole with a small diameter is formed along a planned electric line path and burying the casing (40) in which the pulling line (45) is embedded while expanding the preliminary drilling hole at the same. According to the present invention, the stability and durability of the underground electric line can be improved. The breakage of the conduit (41), which may occur in the underground pulling process of the conduit (41) in the construction of the underground electric line, can be fundamentally prevented.

Description

케이싱 수평 추진형 지중 전선로 시공방법{HORIZONTAL CASING PROPULSION TYPE UNDERGROUND LINE CONSTRUCTION METHOD}{HORIZONTAL CASING PROPULATION TYPE UNDERGROUND LINE CONSTRUCTION METHOD}

본 발명은 지중 추진을 이용한 비개착식 지중 전선로 시공방법에 관한 것으로, 계획 전선로의 경로를 따라 소구경 예비 굴착공을 형성하고, 예비 굴착공을 확공함과 동시에 견인선(45)이 내장된 케이싱(40)을 매설한 후, 케이싱(40)에 내장된 견인선(45)에 전선관(41)을 결속하여 견인함으로써, 케이싱(40) 내부에 전선관(41)을 설치하는 것이다.
The present invention relates to a non-detachable underground cable installation method using underground propulsion, in which a small diameter preliminary drilling hole is formed along a path of a planned electric line, and a preliminary drilling hole is provided, The conduit 41 is installed inside the casing 40 by inserting the conduit 41 to the pulling line 45 built in the casing 40 after the casing 40 is buried.

지중 전선로를 구축함에 있어서 적용되는 수평 추진식 전선로 매설 공법은 비교적 장거리의 지중 전선로를 개착 없이 시공할 수 있는 바, 하천, 도로 또는 철도 등을 횡단하는 지중 전선로의 시공은 물론 도서(島嶼) 지역에 전력을 공급하는 해저 전선로의 시공에도 활용되고 있으며, 관련 종래기술로는 특허 제836626호 등을 들 수 있다.The burial method using the horizontal propulsion wire that is applied in the construction of the underground cableway can construct the underground cableway that crosses the river, the road or the railway as well as the construction of the underground cableway, And is also utilized in the construction of a submarine cable line for supplying electric power, and the related art is patent No. 836626 and the like.

도 1은 특허 제836626호를 비롯한 종래기술을 통한 지중 전선로 추진 시공 과정을 도시한 것으로, 동 도면에는 하천 또는 해협 하부 지반을 횡단하는 지중 전선로의 시공과정이 예시되어 있다.FIG. 1 illustrates a construction process of an underground electric cable by way of a conventional electric cable including a No. 836626, which illustrates a construction process of an underground electric cable that traverses a river or a bottom of a strait.

도 1에 도시된 바와 같이, 종래의 수평 추진형 지중 전선로 시공방법은 계획 전선로의 시점 또는 종점에 각각 발진구(11) 또는 도달구(12)를 굴착한 후, 굴착장치(21)에 연결되고 선단에 조향식(調向式) 굴착비트(23)가 장착된 로드(rod)(22)를 발진구(11)로 투입하여 계획 전선로의 경로를 따라 소구경 예비 굴착공을 형성하는 단계로 개시된다.As shown in FIG. 1, in the conventional horizontally-propelled underground cable construction method, after the erection opening 11 or the reaching opening 12 is drilled at the start or end point of the planned electric line, And a rod 22 to which a steering type excavation bit 23 is attached is inserted into a drafting hole 11 at the front end to form a small diameter preliminary drilling hole along the route of the planned electric line .

예비 굴착공의 굴착에서는 굴착장치(21)에 연결된 로드(22) 선단의 굴착비트(23)가 발진구(11)에서 하향 경사를 이루며 진입하여 굴착을 지속하다가, 굴착비트(23)가 소정의 목표 심도에 도달하면 조향식 굴착비트(23)의 선두를 소폭 상향하면서 굴착공에 곡선구간을 조성하고, 굴착비트(23)가 수평상태에 도달하면 수평을 유지하면서 하천 또는 해협 등의 계획 구간 하부 지반을 횡단하게 된다.In the excavation of the preliminary excavation hole, the excavation bit 23 at the front end of the rod 22 connected to the excavation apparatus 21 enters the downward inclined state at the excavation opening 11 to continue excavation, When the target depth is reached, a curved section is formed in the excavation hole while the head of the excavation excavation bit 23 is slightly raised. When the excavation bit 23 reaches the horizontal state, It crosses the ground.

이후, 수평 굴착공이 하천 또는 해협 등을 완전히 횡단하여 계획 전선로의 경로상 소정 지점에 도달하면, 조향식 굴착비트(23)의 선두를 재차 소폭 상향하면서 굴착공에 곡선구간을 조성하고, 굴착비트(23)가 소정의 목표 심도까지 상승되면 직선 상향 경로를 따라 굴착을 지속하며, 결국 도달구(12)로 굴착비트(23)가 노출되면서, 발진구(11)와 도달구(12)를 연결하는 예비 굴착공이 완성된다.Thereafter, when the horizontal excavator completely traverses the river or strait and reaches a predetermined point on the path of the planned electric line, a curved section is formed in the excavator while slightly increasing the head of the steerable excavation bit 23 again, The excavation bit 23 is exposed to the arrival port 12 and the excavation bit 23 is connected to the entrance port 11 and the arrival port 12 The preliminary drilling ball is completed.

예비 굴착공 굴착시, 굴착비트(23)와 연결된 로드(22)를 통하여 벤토나이트 현탁액이 공급되고, 굴착비트(23)에서 벤토나이트 현탁액이 분사됨으로써, 공벽을 유지하고 추전저항을 저감할 수 있으며, 굴착장치(21)로 벤토나이트 현탁액을 공급하고, 굴착공 시점 또는 종점에서 발진구(11) 또는 도달구(12)로 유출되어 저류되는 벤토나이트 현탁액을 수집하고 재활용 가능하도록 처리하는 벤토나이트 취급설비(25)가 도 1에 도시된 바와 같이 발진구(11)와 도달구(12) 주변에 설치될 수 있다.The bentonite suspension is supplied through the rod 22 connected to the excavation bit 23 and the bentonite suspension is injected at the excavation bit 23 so as to maintain the vacant wall and to reduce the estimated resistance, A bentonite handling facility 25 for supplying the bentonite suspension to the device 21 and collecting and recycling the bentonite suspension which is discharged and stored at the excavation opening 11 or the arrival opening 12 at the excavation opening or closing point As shown in FIG. 1, may be installed around the mouthpiece 11 and the mouthpiece 12.

예비 굴착공의 관통 직후 발진구(11) 측의 굴착장치(21)와, 도달구(12) 측의 굴착비트(23)는 다수의 로드(22)로 연결된 상태로서, 도달구(12)로 노출된 굴착비트(23)를 분리하고, 도 1의 발췌 확대부에서와 같이 확공기(31) 및 다수의 전선관(41)을 연결한 후, 굴착장치(21)를 역방향으로 가동하여, 굴착공을 확공함과 동시에 전선관(41)을 견인하여 매설하게 된다.The excavating device 21 on the side of the dredge 11 immediately after penetration of the preliminary drilling hole and the excavation bit 23 on the side of the reaching port 12 are connected to a plurality of rods 22, The exposed excavation bit 23 is separated and the excavation device 21 is operated in the reverse direction after connecting the reamer 31 and the plurality of conduit 41 as in the extract enlargement section of Fig. And at the same time, the conduit pipe 41 is pulled and buried.

이때, 확공기(31) 배후에 결속되는 전선관(41)은 스위벨(swivel)(35)을 통하여 연결되어, 로드(22) 및 확공기(31)의 회전에도 불구하고, 전선관(41)에는 회전력이 전달되지 않고 비회전 상태로 견인되게 된다.At this time, the conduit 41 bound to the rear of the reamer 31 is connected through the swivel 35 so that the conduit 41 is rotated with the rotational force Is not transmitted but is pulled to the non-rotating state.

또한, 대구경 확공이 필요한 경우 예비 굴착공의 1차 확공 후 기 확공된 예비 굴착공을 반대 방향으로 재차 확공하는 과정을 반복할 수도 있으며, 반복 확공시 확공기(31) 배후에는 전선관(41)이 아닌 로드(22)를 연결하되, 최종 확공시에만 확공기(31)에 전선관(41)을 연결하는 방식으로 작업이 진행된다.In addition, when large-diameter enlargement is required, it is also possible to repeat the process of re-opening the pre-drilled hole in the opposite direction after the first opening of the pre-drilled hole, and the conduit 41 The work is carried out by connecting the rod 22 to the reamer 31 and connecting the conduit 41 to the reamer 31 only at the time of final extension.

확공기(31)가 기 형성된 예비 굴착공을 완전히 통과하여 지상에 도달하면서, 견인되던 다수의 전선관(41) 역시 하천 또는 해협 등의 계획 구간 하부 지반을 완전히 횡단하여 매설되며, 도 1 하부의 A-A'선 단면도에서와 같은 횡단면을 형성하는 지중 전선로가 구축된다.
As the reamer 31 completely passes through the pre-drilled holes and reaches the ground, a plurality of conduits 41 that have been pulled are also buried completely across the lower ground of the planned section such as a river or strait. An underground conductor line is formed which forms the same cross-section as in the A 'cross-sectional view.

전술한 바와 같이, 로드(22) 선단에 조향식 굴착비트(23)를 장착하여 예비 굴착공을 형성하고, 배후에 전선관(41)이 스위벨(35)로 연결된 확공기(31)를 로드(22)로 회전, 견인함으로써, 다수의 전선관(41)을 일시에 매설하는 수평 추진형 지중 전선로 시공방법을 통하여, 대규모 개착 없이도 장거리 지중 전선로를 효율적으로 구축할 수 있으며, 특히 하천 또는 해협 등 구간의 지중 전선로 구축에 유용하게 활용될 수 있으나, 이러한 종래의 수평 추진형 지중 전선로 시공방법은 다음과 같은 문제점을 가진다.The preliminary excavating hole is formed by mounting the steering excavation bit 23 at the front end of the rod 22 and the reamer 31 connected to the conduit pipe 41 by the swivel 35 is connected to the rod 22 ), It is possible to efficiently construct a long-distance underground conductor line by a horizontal propulsion type underground cable installation method in which a large number of conduit pipes 41 are buried at once, However, the conventional horizontal propulsion type underground cable installation method has the following problems.

우선, 도 1 하부의 A-A'선 단면도에서와 같이, 기본적으로 다수의 전선관(41)이 지반에 단순 매설되는 구조를 가지는 바, 매설 전선관(41)의 교체 내지 증설이 근본적으로 불가능한 문제점을 가진다.First, as shown in the sectional view taken along the line A-A 'in the lower part of FIG. 1, a plurality of conduit pipes 41 are basically buried in the ground, so that it is basically impossible to replace or extend the buried conduit pipes 41 I have.

또한, 확공기(31) 배후에 스위벨(35)로 결속된 전선관(41) 다발이 공벽 내주면은 물론 굴착공내 잔류된 토사 및 암석 분쇄물과 직접 접촉되는 상태로 견인되는 바, 견인 과정에서의 전선관(41) 손상 가능성이 상존할 뿐 아니라, 견인시 전선관(41)에 작용하는 장력에 대한 고도의 조절 및 제어가 요구되는 시공상 애로점이 존재한다.In addition, the bundle of the conduit pipe 41 bounded by the swivel 35 behind the reamer 31 is pulled in a state of being in direct contact with the ground and the crushed stone material remaining in the excavation hole as well as the inner circumferential surface of the air hole. There is a possibility of damage to the cable 41, and there is a construction difficulty that requires a high degree of control and control of the tension acting on the conduit 41 at the time of traction.

특히, 다수의 전선관(41)이 다발 형태로 확공기(31)에 결속되어 견인되는 바, 지상에서 개별 전선관(41)의 권출(捲出) 속도를 기민하고 정밀하게 조절할 필요가 있어, 작업상 고도로 숙련된 인력이 소요됨은 물론, 직경 또는 재질이 상이한 이종(異種) 전선관(41)의 취합 시공이 사실상 불가능한 한계가 있었다.In particular, since a plurality of conduits 41 are bundled and attracted to the reamer 31 in the form of a bundle, it is necessary to precisely adjust the speed of unwinding the individual conduits 41 on the ground, There is a limit in that it is practically impossible to assemble a heterogeneous conduit 41 having a different diameter or material.

뿐만 아니라, 확공 및 견인과정에서 전선관(41) 다발 사이로, 미처 분쇄되지 않은 암석 파편 등이 진입하는 경우 전선관(41)의 손상 및 파단이 유발되어, 전구간을 재시공하여야 하는 심각한 문제가 있었다.
In addition, when pieces of rock that have not yet been crushed go into the bundles of conduits 41 during the laying and pulling process, damages and breakage of the conduits 41 are caused, and there is a serious problem that the entire section must be reworked.

본 발명은 전술한 문제점을 감안하여 창안된 것으로, 수평 추진형 지중 전선로 시공방법에 있어서, 계획 지중 전선로의 양측 단부에 각각 발진구(11)와 도달구(12)가 굴착되고, 발진구(11)로 투입된 굴착비트(23) 배후에 로드(22)가 반복 연결되면서 계획 전선로의 경로를 따라 소구경 예비 굴착공이 형성되는 예비굴착단계(S10)와, 예비 굴착공에 관입된 로드(22)의 굴착장치(21) 타측 단부에 확공기(31)를 장착하고, 확공기(31) 배후에는 견인선(45)이 내장된 케이싱(40)을 연결한 후, 확공기(31)를 견인하여 케이싱(40)을 매설하는 확공단계(S20)와, 견인선(45)의 일단에 전선관(41)을 결속하고, 전선관(41)을 케이싱(40) 내부로 투입한 후, 견인선(45)을 견인하여, 케이싱(40) 내부에 전선관(41)을 설치하는 전선설치단계(30)로 이루어짐을 특징으로 하는 케이싱(40) 수평 추진형 지중 전선로 시공방법이다.SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and it is an object of the present invention to provide a horizontally-propelled underground cable installation method, in which a power generating opening 11 and a reaching opening 12 are respectively excavated on both sides of a planned underground power cable, A preliminary drilling step S10 of forming a small diameter preliminary drilling hole along the path of the planned electric line path while the rod 22 is repeatedly connected behind the excavation bit 23 inserted into the preliminary drilling hole 11, The reamer 31 is installed at the other end of the excavation apparatus 21 of the excavation apparatus 21 and the casing 40 having the draw line 45 is connected to the rear of the reamer 31 and then the reamer 31 is pulled A drawing step S20 of burying the casing 40 and a step of binding the conduit 41 to one end of the traction line 45 and putting the conduit 41 into the casing 40, And a wire installation step (30) for installing a conduit (41) inside the casing (40) by pulling the casing (40) How is the construction of a wire.

또한, 상기 확공단계(S20)가 수행된 이후, 케이싱(40)의 일측 단부가 밀봉되고, 밀봉부위에 압송장치가 연결되어, 케이싱(40) 내부로 압축공기가 압송됨으로써, 케이싱(40)내 저류수가 외부로 배출되는 가압배수단계(S21)가 수행되고, 케이싱(40) 내주면에 밀착되는 돌출환체(61)가 외주면에 형성된 원통체(60)가 케이싱(40) 내부에서 이동됨으로써, 케이싱(40)내 잔류수가 집수 및 배출되는 잔류수제거단계(S22)가 수행된 후, 전선설치단계(S30)가 수행됨을 특징으로 하는 케이싱(40) 수평 추진형 지중 전선로 시공방법이다.After the spreading step S20 is performed, one end of the casing 40 is sealed, and the pressure-feeding device is connected to the sealing portion, so that the compressed air is fed into the casing 40, The pressurized drainage step S21 is performed in which the stored water is discharged to the outside and the cylindrical body 60 having the protruding annular flange 61 adhered to the inner circumferential surface of the casing 40 is moved inside the casing 40, (S30) is performed after the residual water removal step S22 of collecting and discharging the residual water in the casing 40 is carried out.

또한, 상기 원통체(60)는 외주면에 다수의 통수공(63)이 천공된 중공(中空)의 용기로 구성되고, 원통체(60) 내부에는 고분자흡수체(70)가 적재됨을 특징으로 하는 케이싱(40) 수평 추진형 지중 전선로 시공방법이다.
The cylindrical body 60 is formed of a hollow container in which a plurality of water holes 63 are formed in the outer circumferential surface and the polymeric absorbent 70 is loaded in the cylindrical body 60. (40) Horizontal propulsion type Underground cable construction method.

본 발명을 통하여, 지중 전선로의 안정성 및 내구성을 획기적으로 향상시킬 수 있으며, 지중 전선로 구축시 전선관(41)의 지중 견인과정에서 발생될 수 있는 전선관(41)의 파손을 근본적으로 방지할 수 있다.It is possible to drastically improve the stability and durability of the underground cable line and to prevent the breakage of the conduit pipe 41 which may occur during the grounding process of the conduit pipe 41 when the underground cable is constructed. .

또한, 지중 전선로를 구성하는 전선관(41)의 교체 및 증설이 용이할 뿐 아니라, 직경 또는 재질이 상이한 이종(異種) 전선관(41)의 취합 시공 역시 용이하게 수행할 수 있다.
In addition, it is easy to replace and add the conduit pipes 41 constituting the underground conduit, and also to assemble the conduit pipes 41 having different diameters or different materials.

도 1은 종래기술의 단계별 설명도
도 2는 본 발명의 단계별 설명도
도 3은 본 발명의 케이싱내 전선관 견인 방식 설명도
도 4는 본 발명의 케이싱 내부 청소 방식 설명도
도 5는 본 발명의 원통체 사시도
도 6은 본 발명의 중공형 원통체 사시도
도 7은 본 발명의 중공형 원통체 부분절단 사시도
도 8은 본 발명의 중공형 원통체 사용상태 종단면도
Figure 1 is a step-by-
2 is a step-by-step explanatory diagram
3 is an explanatory view of a conduit tube pulling method in a casing of the present invention
Fig. 4 is an explanatory view of the cleaning method of the inside of the casing of the present invention
5 is a perspective view of a cylindrical body
Fig. 6 is a perspective view of the hollow cylindrical cylindrical body of the present invention
7 is a perspective view of a hollow cylindrical portion cut perspective view of the present invention
8 is a vertical cross-sectional view of the hollow cylindrical body according to the present invention

본 발명의 상세한 구성 및 수행과정을 첨부된 도면을 통하여 설명하면 다음과 같다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

우선, 도 2는 본 발명의 수행과정 전반을 도시한 것으로, 도시된 바와 같이, 본 발명은 발진구(11)에서 도달구(12)에 이르는 예비 굴착공을 형성하는 예비굴착단계(S10)로 개시된다.FIG. 2 is a view showing the overall process of the present invention. As shown in FIG. 2, the present invention is a preliminary drilling step (S10) for forming a preliminary drilling hole reaching a reaching hole 12 from a dusting hole 11 .

예비굴착단계(S10)에서는 계획 전선로의 양단에 각각 발진구(11) 또는 도달구(12)를 굴착한 후, 굴착장치(21)에 연결된 로드(22) 선단에 굴착비트(23)를 장착하여, 발진구(11)에서 도달구(12) 측으로 굴착비트(23)를 회전 및 압입시키는데, 여기서 발진구(11) 및 도달구(12)는 각각 최초 굴착비트(23)의 진입 지점 및 최종 도착 지점을 특정하는 것으로, 계획 전선로의 시점 및 종점과 반드시 일치할 필요는 없다.In the preliminary drilling step S10, the excavation opening 11 or the reaching opening 12 is drilled on both ends of the planned electric line, and then the drilling bit 23 is attached to the end of the rod 22 connected to the excavating device 21 Wherein the excavation opening 11 and the reaching opening 12 respectively rotate at the entry point of the first excavation bit 23 and at the final arrival By specifying the point, it is not necessarily the same as the start point and the end point of the planned line.

즉, 발진구(11)와 도달구(12)는 계획 지중 전선로의 양측 단부에 각각 굴착되어 구축되되, 계획 전선로의 시점에 발진구(11)가 구축되고, 종점에 도달구(12)가 구축되거나, 역으로 계획 전선로의 종점에 발진구(11)가 구축되고, 시점이 도달구(12)가 구축될 수도 있는 것으로, 발진구(11)와 도달구(12)의 위치는 송, 배전 구조상 공급처와 수용가에 의하여 결정되는 것이 아니라, 지형 등 현장 조건은 물론 자재 조달 및 장비 동원 여건 등을 고려하여 선정되는 것이다.In other words, the launching mouth 11 and the reaching mouth 12 are constructed by being respectively excavated at both ends of the planned underground electric line, the launching mouth 11 is constructed at the time of the planned front line, The position of the launching mouth 11 and the reaching mouth 12 can be set to the position on the transmission and distribution structure It is not determined by the supplier and the customer, but is selected in consideration of the site conditions such as the topography, as well as material procurement and equipment mobilization conditions.

예비굴착단계(S10)에서 적용되는 굴착비트(23)는 굴진 방향을 조정할 수 있는 조향식(調向式) 굴착비트(23)가 적용되며, 로드(22)를 통하여 지상의 굴착장치(21)와 연결되어, 회전력과 추진력이 부여된다.The excavation bit 23 applied in the preliminary excavation step S10 is applied with a steering excavation bit 23 capable of adjusting the direction of excavation and is transmitted through the rod 22 to the ground excavator 21, So that a rotational force and a thrust force are imparted.

예비굴착단계(S10)에서는 발진구(11)로 투입된 굴착비트(23) 배후에 로드(22)가 반복 연결되면서 계획 전선로의 경로를 따라 소구경 예비 굴착공이 굴진, 형성되는데, 예비 굴착공의 굴착은 도 2의 상단부에 도시된 바와 같이, 일단, 굴착장치(21)에 연결된 로드(22) 선단의 굴착비트(23)가 발진구(11)에서 하향 경사를 이루며 진입하여 굴착을 지속하다가, 굴착비트(23)가 소정의 목표 심도에 도달하면 조향식 굴착비트(23)의 선두를 소폭 상향하면서 굴착공에 곡선구간을 조성하고, 굴착비트(23)가 수평상태에 도달하면 수평을 유지하면서 하천 또는 해협 등의 계획 구간 하부 지반을 횡단하게 된다.In the preliminary drilling step S10, the rod 22 is repeatedly connected behind the excavation bit 23 inserted into the power generating aperture 11, and a small diameter preliminary drilling hole is punched along the path of the planned electric wire path. The excavation bit 23 at the front end of the rod 22 connected to the excavation apparatus 21 enters the slope 11 at a downward slope and continues to excavate the excavator as shown in the upper part of FIG. When the bit 23 reaches a predetermined target depth, a curved section is formed in the excavation hole while the head of the steerable excavation bit 23 is slightly raised. When the excavation bit 23 reaches the horizontal state, Or across the lower part of the planned section of the strait or the like.

이후, 수평 굴착공이 하천 또는 해협 등을 완전히 횡단하여 계획 전선로의 경로상 소정 지점에 도달하면, 조향식 굴착비트(23)의 선두를 재차 소폭 상향하면서 굴착공에 곡선구간을 조성하고, 굴착비트(23)가 소정의 목표 심도까지 상승되면 직선 상향 경로를 따라 굴착을 지속하며, 결국 도달구(12)로 굴착비트(23)가 노출되면서, 발진구(11)와 도달구(12)를 연결하는 예비 굴착공이 완성된다.Thereafter, when the horizontal excavator completely traverses the river or strait and reaches a predetermined point on the path of the planned electric line, a curved section is formed in the excavator while slightly increasing the head of the steerable excavation bit 23 again, The excavation bit 23 is exposed to the arrival port 12 and the excavation bit 23 is connected to the entrance port 11 and the arrival port 12 The preliminary drilling ball is completed.

도 2에 도시된 바와 같이, 발진구(11)와 도달구(12)를 연결하는 소구경 예비 굴착공에는 다수의 로드(22)가 연결되어 관입된 상태로 존치되며, 이후 후속공정에서, 도달구(12)로 노출된 로드(22)의 선단에 확공기(31)가 연결되어 굴착공을 확공하게 된다.As shown in FIG. 2, a plurality of rods 22 are connected to the small-diameter preliminary drilling hole connecting the gashing mouth 11 and the reaching hole 12, The reamer 31 is connected to the tip of the rod 22 exposed to the sphere 12 to expand the excavation hole.

예비 굴착공 굴착시, 굴착비트(23)와 연결된 로드(22)를 통하여 벤토나이트 현탁액이 공급되고, 굴착비트(23)에서 벤토나이트 현탁액이 분사됨으로써, 공벽을 유지하고 추전저항을 저감할 수 있으며, 굴착장치(21)로 벤토나이트 현탁액을 공급하고, 굴착공 시점 또는 종점에서 발진구(11) 또는 도달구(12)로 유출되어 저류되는 벤토나이트 현탁액을 수집하고 재활용 가능하도록 처리하는 벤토나이트 취급설비(25)가 도 2에 도시된 바와 같이 발진구(11)와 도달구(12) 주변에 설치될 수 있다.The bentonite suspension is supplied through the rod 22 connected to the excavation bit 23 and the bentonite suspension is injected at the excavation bit 23 so as to maintain the vacant wall and to reduce the estimated resistance, A bentonite handling facility 25 for supplying the bentonite suspension to the device 21 and collecting and recycling the bentonite suspension which is discharged and stored at the excavation opening 11 or the arrival opening 12 at the excavation opening or closing point As shown in FIG. 2, it may be installed around the mouth 11 and the mouth 12.

이렇듯, 발진구(11)와 도달구(12)를 연결하는 예비 굴착공이 완성되면, 예비 굴착공을 확공함과 동시에, 견인선(45)이 내장된 케이싱(40)을 지반내 관입시키는 확공단계(S20)가 수행된다.When the preliminary excavation hole connecting the excavation opening 11 and the arrival opening 12 is completed, the preliminary excavating hole is enlarged and the casing 40 in which the drawing line 45 is embedded is introduced into the ground. (S20) is performed.

즉, 예비 굴착공에 관입된 로드(22)의 굴착장치(21) 타측 단부에 확공기(31)를 장착하고, 확공기(31) 배후에는 스위벨(35)을 통하여 견인선(45)이 내장된 케이싱(40)을 연결한 후, 확공기(31)를 회전 및 견인하여 케이싱(40)을 매설하는 것이다.That is, the reamer 31 is installed at the other end of the rod 22 penetrated into the preliminary drill hole, and the pull line 45 is embedded in the rear of the reamer 31 through the swivel 35 After the casing 40 is connected, the casing 40 is buried by rotating and pulling the reamer 31.

전술한 바와 같이, 예비 굴착공의 관통 직후 발진구(11) 측의 굴착장치(21)와, 도달구(12) 측의 굴착비트(23)는 상호 연결된 다수의 로드(22)로 연결된 상태로서, 확공단계(S20)에서는 도달구(12)로 노출된 굴착비트(23)를 분리하고, 도 2의 발췌 확대부에서와 같이 배후에 케이싱(40)이 스위벨(35)을 통하여 연결된 확공기(31)를 로드(22) 선단에 연결한다.As described above, the excavation apparatus 21 on the side of the drafting opening 11 and the excavation bit 23 on the side of the arrival opening 12 are connected to each other by a plurality of mutually connected rods 22 immediately after penetration of the preliminary drilling hole The excavation bit 23 exposed to the arrival port 12 is separated in the exposing step S20 and the casing 40 is connected to the reamer 35 connected to the rear of the casing 40 via the swivel 35 31) to the tip of the rod (22).

이후, 굴착장치(21)를 역방향으로 가동하여, 굴착공을 확공함과 동시에 케이싱(40)을 기 굴착된 예비 굴착공을 따라 견인하게 되는데, 이때, 확공기(31) 배후에 결속되는 케이싱(40)은 스위벨(35)을 통하여 연결되어, 로드(22) 및 확공기(31)의 회전에도 불구하고, 케이싱(40)에는 회전력이 전달되지 않고 비회전 상태로 견인되며, 도 2의 발췌 확대부에 도시된 바와 같이, 스위벨(35)에 직결되는 선두 케이싱(40) 내부에는 견인선(45)을 결속하여, 케이싱(40)과 견인선(45)이 동반 견인될 수 있도록 한다.Thereafter, the excavator 21 is operated in the reverse direction, and the excavator is expanded. At the same time, the casing 40 is pulled along the excavated pre-excavation hole. At this time, 40 are connected to each other through the swivel 35 so that the rotating force is not transmitted to the casing 40 despite the rotation of the rod 22 and the reamer 31, The traction line 45 is coupled to the inside of the leading casing 40 directly connected to the swivel 35 so that the casing 40 and the traction line 45 can be pulled together.

확공기(31)가 기 형성된 예비 굴착공을 완전히 통과하여 지상에 도달하면서, 견인되던 케이싱(40) 역시 하천 또는 해협 등의 계획 구간 하부 지반을 완전히 횡단하여 매설되는데, 다수의 케이싱(40)이 종방향으로 일렬 접합, 연결되고, 지반에 매설되어, 계획 전선로의 시점에서 종점에 이르는 대구경 굴착공이 케이싱(40)에 의하여 공벽이 완벽하게 보호되는 상태로 구축된다.As the reamer 31 completely passes through the pre-drilled holes and reaches the ground, the casing 40 to be towed is also buried completely across the lower ground of the planned section such as a river or a strait. A plurality of casings 40 A large diameter drilling hole extending from the viewpoint of the planned electric line to the end point is constructed in such a state that the walls are completely protected by the casing 40. [

또한, 대구경 추가 확공이 필요한 경우에는 예비 굴착공의 1차 확공 후 기 확공된 예비 굴착공을 반대 방향으로 재차 확공하는 과정을 반복할 수도 있으며, 반복 확공시 확공기(31) 배후에는 전선관(41)이 아닌 로드(22)를 연결하되, 최종 확공시에만 확공기(31)에 케이싱(40)을 연결하는 방식으로 작업이 진행될 수 있다.In addition, if it is necessary to enlarge the diameter of the preliminary drilling machine, it is also possible to repeat the process of re-opening the preliminary drilling machine in the opposite direction after the first drilling of the preliminary drilling machine. And the casing 40 is connected to the reamer 31 only at the time of final extension.

전술한 바와 같이, 확공단계(S20)에서 매설된 케이싱(40)에는 전체 구간에 걸쳐 견인선(45)이 내장되는데, 견인선(45)은 후속 공정에서 전선관(41)을 견인하는 수단으로서, 강연선(鋼撚線) 등의 고강도 선재가 적용된다.As described above, the casing 40 embedded in the spreading step S20 has the traction line 45 built in over the entire section. The traction line 45 is a means for pulling the conduit 41 in the subsequent process, High-strength wire rods such as steel stranded wires are applied.

확공단계(S20)가 완료되면, 견인선(45)의 일단에 전선관(41)을 결속하고, 견인선(45)의 타단을 윈치(winch)(51) 등과 연결하여, 도 3에서와 같이, 전선관(41)을 케이싱(40) 내부로 투입한 후 견인선(45)을 견인함으로써, 케이싱(40) 내부에 전선관(41)을 설치하는 전선설치단계(S30)가 수행되며, 이로써, 도 2 하단부의 B-B'선 단면도에서와 같은 횡단면을 형성하는 지중 전선로가 구축된다.When the expansion step S20 is completed, the conduit pipe 41 is connected to one end of the traction line 45 and the other end of the traction line 45 is connected to a winch 51 or the like, A wire installation step S30 for installing the conduit 41 inside the casing 40 is performed by pulling the wire 45 after the conduit 41 is inserted into the casing 40, An underground conductor line is formed which forms a cross section as in the B-B 'line sectional view of the lower end portion.

즉, 지반에 관입된 케이싱(40) 내부에 전선관(41)이 안정적으로 설치될 수 있을 뿐 아니라, 종래기술에 있어서 전선관(41)의 견인시 빈발하였던 전선관(41)의 파손 및 파단을 억제할 수 있으며, 견인력 조절 등 작업 전반을 용이하게 수행할 수 있어, 종래기술 대비 시공 편의성을 제고할 수 있는 것이다.That is, not only the conduit 41 can be stably installed in the casing 40 penetrated into the ground, but also the breakage and breakage of the conduit 41, which is frequently occurred in the traction of the conduit 41 in the prior art, And it is possible to easily carry out the overall work such as the adjustment of the traction force, thereby making it possible to improve the convenience of construction compared to the prior art.

도 3에서와 같이, 견인선(45)에는 다수의 전선관(41)을 취합하여 결속할 수 있으며, 동 도면에 도시된 바와 같이, 견인선(45)과 전선관(41) 사이에는 스위벨(35)을 설치하여, 전선관(41)의 견인시 발생될 수 있는 불필요한 회전 및 요동을 억제할 수도 있다.3, a plurality of conduits 41 may be combined and coupled to the towing line 45. A swivel 35 may be provided between the towing line 45 and the conduit 41, So that unnecessary rotation and rocking that may occur when the conduit pipe 41 is pulled can be suppressed.

또한, 도면에 도시되지는 않았으나, 전선설치단계(S30)를 수행함에 있어서, 전선관(41)과 견인선(45)의 연결부에 예비 견인선(45)을 추가 결속하여 , 전선관(41)과 예비 견인선(45)을 동반 견인하고, 케이싱(40) 내부에 전선관(41)과 함께 예비 견인선(45)을 존치함으로써, 추후 전선관(41)을 추가 설치하는 등의 작업을 용이하게 수행할 수 있다.Although not shown in the drawing, the preliminary pulling line 45 is further bound to the connecting portion of the wire conduit 41 and the pulling wire 45 in the step of installing the wire (S30) It is possible to easily carry out work such as the additional installation of the conduit 41 by pulling the towing line 45 together and retaining the preliminary towing line 45 together with the conduit 41 inside the casing 40 have.

한편, 도 4 내지 도 8은 전술한 확공단계(S20) 이후, 전선설치단계(S30) 이전에 수행되는 가압배수단계(S21) 및 잔류수제거단계(S22)의 수행과정 및 물리적 구성을 도시한 것이다.4 to 8 illustrate the processes and the physical configuration of the pressure drainage step S21 and the residual water removal step S22 performed after the opening step S20 and before the wire installation step S30 will be.

전술한 바와 같이, 본 발명은 하천 또는 해협을 횡단하는 지중 전선로의 구축에 적용될 수 있을 뿐 아니라, 굴진 과정 전반에 있어서 벤토나이트 현탁액이 활용되는 바, 습윤환경에서 케이싱(40)의 취급 및 설치 과정이 수행된다.As described above, the present invention can be applied not only to the construction of an underground conductor line traversing a river or a strait but also to the use of a bentonite suspension in the entire excavation process, and the handling and installation process of the casing 40 in a wet environment .

또한, 야적된 케이싱(40) 내부에 침적된 오염물을 제거하거나, 전술한 확공단계(S20) 수행 후 케이싱(40)의 연결상태를 점검하고 케이싱(40)의 지반 관입과정에서 발생될 수 있는 케이싱(40)의 손상 여부를 확인하기 위하여 수압시험(水壓試驗)이 실시될 수 있는데, 이 과정에서 케이싱(40) 내부에 다량의 물이 투입된다.It is also possible to check the connection state of the casing 40 after removing the contaminants deposited in the jacketed casing 40 or after performing the above-described spreading step S20, A water pressure test may be performed in order to check the damage of the casing 40. In this process, a large amount of water is injected into the casing 40.

따라서, 케이싱(40) 내부에 전선관(41)을 설치하는 전선설치단계(S30)의 수행 이전에 케이싱(40) 내부의 물을 제거하는 작업이 필요할 수 있으며, 본 발명에서는 도 4에서와 같은 가압배수단계(S21) 및 잔류수제거단계(S22)를 통하여, 케이싱(40) 내부의 물을 완벽하게 제거할 수 있다.Therefore, it may be necessary to remove the water in the casing 40 before the electric wire installation step S30 in which the electric conduit 41 is installed in the casing 40. In the present invention, The water inside the casing 40 can be completely removed through the drainage step S21 and the residual water removal step S22.

우선, 가압배수단계(S21)는 도 4의 상단부에 도시된 바와 같이, 종방향으로 연결된 케이싱(40)의 일측 단부를 밀봉하고, 밀봉부위에 압축공기를 공급하는 압송장치를 연결하여, 케이싱(40) 내부로 압축공기를 압송함으로써, 케이싱(40)내 저류수가 외부로 배출될 수 있도록 하는 것이다.First, in the pressure drainage step S21, one end of the casing 40 connected in the longitudinal direction is sealed as shown in the upper end of Fig. 4, and a pressure feeding device for supplying compressed air to the sealing portion is connected to the casing 40, the stored water in the casing 40 can be discharged to the outside.

도 4에 도시된 실시예에서는 발진구(11) 측 케이싱(40)의 단부를 밀봉하여 컴프레서(compressor) 등의 압송장치를 연결하고, 도달구(12) 측 케이싱(40)의 단부는 개방하여, 압송장치를 가동함에 따라 발진구(11) 측에서 압축공기가 케이싱(40) 내부로 주입되고, 도달구(12) 측의 개방된 케이싱(40) 단부를 통하여 케이싱(40)내 저류수가 토출되고 있으나, 이러한 압송장치의 연결지점과 케이싱(40) 개방 지점은 각각 발진구(11)와 도달구(12)로 한정되는 것은 아니며, 현장 여견에 따라 역으로 도달구(12)에 압송장치가 연결될 수도 있다.4, the end of casing 40 on the side of mouth 11 is sealed to connect a pressure feeding device such as a compressor and the end of casing 40 on the side of mouth 12 is opened The compressed air is injected into the casing 40 from the side of the dust outlet 11 and the stored water in the casing 40 is discharged through the end of the opened casing 40 on the side of the arrival port 12 The connection point of the press-feeding device and the opening point of the casing 40 are not limited to the mouthpiece 11 and the mouthpiece 12, Lt; / RTI >

케이싱(40)에 대한 수압시험이 실시되는 경우, 수압시험 종료 후, 발진구(11)에서 도달구(12)에 이르는 케이싱(40) 전구간에 걸쳐 저류수가 충만되는데, 전술한 가압배수단계(S21)를 통하여 저류수의 대부분을 케이싱(40) 외부로 배제할 수 있다.When the hydraulic pressure test is performed on the casing 40, the reservoir water is filled between the whole of the casing 40 extending from the dust collecting mouth 11 to the access port 12 after the completion of the hydraulic pressure test. In the above- So that most of the stored water can be discharged outside the casing 40.

이러한 가압배수단계(S21)의 실시과정에서, 압축공기의 진행 방향상 케이싱(40)의 하향 경사구간 및 수평 구간에서는 대부분의 저류수를 제거할 수 있으나, 상향 경사구간에서는 압축공기가 기포 형태로 배출되거나 수면이 형성되면서 케이싱(40) 내부에 상당량의 잔류수가 형성될 수 밖에 없으며, 이들 잔류수는 가압배수단계(S21)의 종료후 케이싱(40)의 수평 구간으로 이동하여 광범위한 구간으로 확산 분포하게 된다.In the course of the pressure drainage step S21, most of the stored water can be removed in the downward inclined section and the horizontal section of the casing 40 in the traveling direction of the compressed air. However, in the upward inclined section, A large amount of residual water must be formed in the casing 40 as the water is discharged or the water surface is formed and these residual water moves to the horizontal section of the casing 40 after the completion of the pressure drainage step S21, .

이에, 본 발명에서는 도 4에서와 같이, 케이싱(40) 내주면에 밀착되는 돌출환체(61)가 외주면에 형성된 원통체(60)를 케이싱(40) 내부에서 이동시킴으로써, 케이싱(40)내 잔류수를 집수(集水) 및 배출하는 잔류수제거단계(S22)를 실시하여, 케이싱(40)내 잔류수를 완벽하게 제거할 수 있도록 하였다.4, the cylindrical body 60 having the projecting annular flange 61 which is in close contact with the inner peripheral surface of the casing 40 is moved in the casing 40, The water remaining in the casing 40 can be completely removed by performing the step S22 of removing residual water by collecting and collecting the water.

잔류수제거단계(S22)에서 케이싱(40) 내부로 투입되는 원통체(60)는 도 5에서와 같이, 원통형 본체 외주면에 다수의 돌출환체(61)가 원통체(60)의 축방향으로 상호 이격 형성되어 구성되는데, 돌출환체(61)의 외경은 케이싱(40)의 내경과 일치하도록 형성되거나, 돌출환체(61)의 소재로서 합성수지 또는 고무 등의 신축성 소재가 적용되는 경우, 돌출환체(61)의 외경이 케이싱(40)의 내경 이상으로 형성됨으로써, 원통체(60)의 케이싱(40)내 투입시 돌출환체(61)의 외곽부가 케이싱(40)의 내주면에 긴밀하게 밀착될 수 있도록 한다.5, in the residual water removing step S22, a plurality of projecting fins 61 are arranged on the outer circumferential surface of the cylindrical body in the axial direction of the cylindrical body 60, When the outer diameter of the projecting annulus 61 is made to coincide with the inner diameter of the casing 40 or when a stretchable material such as synthetic resin or rubber is applied as the material of the projecting annulus 61, So that the outer periphery of the projecting annulus 61 can be closely attached to the inner peripheral surface of the casing 40 when the cylindrical body 60 is inserted into the casing 40 .

또한, 도 4 및 도 5에 도시된 바와 같이, 돌출환체(61)에는 전방에서 후방측으로 직경이 점차 확대되도록 경사를 형성하여, 케이싱(40)으로의 원활한 투입 및 케이싱(40) 내부에서의 원활한 활동을 도모한다.4 and 5, inclined so that the diameter gradually increases from the front to the rear side is provided in the projecting annulus 61 so that smooth insertion into the casing 40 and smoothness in the casing 40 We plan activity.

원통체(60)의 전단 및 후단에는 각각 견인선(45)이 결속되어, 도 4에 도시된 바와 같이, 원통체(60) 전단에 연결된 견인선(45)에 윈치(51) 등의 견인수단을 연결하여 견인하게 되며, 이로써 케이싱(40) 내부의 원통체(60)가 전방으로 이동하면서, 도 4의 타원내 확대부에서와 같이, 케이싱(40) 내주면에 밀착된 원통체(60)의 돌출환체(61)가 케이싱(40)내 잔류수를 전방측으로 수집, 이송하게 된다.Towing lines 45 are connected to the front end and the rear end of the cylindrical body 60 so that the pulling line 45 connected to the front end of the cylindrical body 60 is pulled by pulling means such as a winch 51 So that the cylindrical body 60 inside the casing 40 is moved forward so that the cylindrical body 60 in close contact with the inner peripheral surface of the casing 40 as in the enlarged portion in the ellipse of FIG. The projecting annulus 61 collects and transfers the remaining water in the casing 40 to the front side.

특히, 본 발명의 원통체(60)에는 원통체(60)의 축방향으로 이격된 다수의 돌출환체(61)가 형성되는 바, 설령 최전방의 돌출환체(61)에서 잔류수가 후방측으로 누출된다 하여도, 최전방 돌출환체(61)와 이후의 돌출환체(61)사이의 공간에 누출된 잔류수가 포집된 상태로 이송될 수 있다.Particularly, in the cylindrical body 60 of the present invention, a plurality of projecting fins 61 spaced in the axial direction of the cylindrical body 60 are formed, so that the remaining water leaks to the rear side in the foremost projecting fins 61 Can also be transferred in a state in which residual water leaking into the space between the forwardmost projecting annulus 61 and the subsequent projecting annulus 61 is collected.

도 4의 하단부에 도시된 바와 같이, 일단 전체 구간의 케이싱(40)을 통과한 원통체(60)는 견인선(45)에서 분리하고 방향을 전환하여 견인선(45)에 결속한 후 케이싱(40)을 재차 통과하도록 할 수도 있으며, 이렇듯 원통체(60)의 케이싱(40) 통과를 반복함으로써, 케이싱(40)내 잔류수를 일층 완전하게 제거할 수 있다.4, the cylindrical body 60 having passed through the casing 40 of the entire one section is separated from the traction line 45, is changed in direction and bound to the traction line 45, 40). By repeating the passage of the cylindrical body 60 through the casing 40, the remaining water in the casing 40 can be completely removed.

도 4 및 도 5에서 도시된 바와 같이, 원통체(60)에는 전단 뿐 아니라 후단에도 견인선(45)이 연결되는데, 이는 원통체(60)의 견인 이동과 동시에 원통체(60) 후단에 연결된 견인선(45)이 케이싱(40)에 내장될 수 있도록 하기 위한 것으로, 이로써 잔류수제거단계(S22)의 후속 공정인 전선설치단계(S30)는 물론 잔류수제거단계(S22)를 반복함에 있어서도 견인선(45)을 계속 활용할 수 있다.As shown in FIGS. 4 and 5, a traction line 45 is connected to the cylindrical body 60 not only at the front end but also at the rear end thereof, which is connected to the rear end of the cylindrical body 60 at the same time as pulling movement of the cylindrical body 60 In order to allow the pulling wire 45 to be housed in the casing 40. In this way, in repeating the step of removing the residual water S22 as well as the step of installing the wire S30 which is a subsequent step of the step S22 of removing the residual water The traction line 45 can be continuously utilized.

도 6 내지 도 8은 중공(中空)의 원통체(60)에 고분자흡수체(70)를 적재하여 잔류수가 원통체(60) 내부의 고분자흡수체(70)에 흡수된 상태로 이송될 수 있도록 한 것으로, 이로써 전류수 제거 효율을 극대화하고, 잔류수의 완벽한 제거를 위한 원통체(60)의 케이싱(40) 반복 통과 회수를 경감하여, 작업 속도 및 편의성을 향상시킬 수 있다.6 to 8 show that a polymeric absorption body 70 is loaded on a hollow cylindrical body 60 so that the residual water can be transferred in a state absorbed by the polymeric absorption body 70 inside the cylindrical body 60 , Thereby maximizing the efficiency of removing the electric current and reducing the number of repeated passes of the casing (40) of the cylindrical body (60) for the complete removal of the residual water, thereby improving the working speed and convenience.

이러한 본 발명의 고분자흡수체(70) 적재용 원통체(60)는 도 6 및 도 7에서와 같이, 외주면에 다수의 통수공(63)이 천공된 중공(中空)의 용기로 구성되고, 도 8에서와 같이, 원통체(60) 내부에 고분자흡수체(70)가 적재되어, 원통체(60)의 케이싱(40)내 이동시 돌출환체(61)들 사이로 침투된 잔류수가 통수공(63)을 통하여 원통체(60) 내부로 유입된 후, 고분자흡수체(70)에 흡수된다.As shown in Figs. 6 and 7, the cylindrical body 60 for loading the polymeric absorber 70 of the present invention is constituted by a hollow container in which a plurality of water holes 63 are perforated on the outer peripheral surface, The polymeric absorbent 70 is loaded in the cylindrical body 60 so that the remaining water permeated through the projecting fins 61 when the cylindrical body 60 is moved in the casing 40 passes through the water hole 63 Is introduced into the cylindrical body (60), and then absorbed into the polymer absorbent body (70).

고분자흡수체(70) 적재용 원통체(60)의 구체적인 구조 및 구성은 도 7에 예시되어 있으며, 동 도면에서와 같이, 전단부는 폐쇄되고, 후단부는 개방된 원관(圓管)으로 원통체(60)가 구성되고, 원통체(60)의 관벽(管壁)을 관통하는 다수의 통수공(63)이 형성된다.7, the front end is closed, and the rear end is opened with a circular tube, and the cylindrical body 60 (see FIG. 7) And a plurality of water holes 63 penetrating the pipe wall of the cylindrical body 60 are formed.

또한, 원통체(60)의 중심부에는 원통체(60)의 축방향으로 중심봉(65)이 접합되되, 중심봉(65)의 후단부에는 나사선이 형성되며, 원통체(60)의 개방된 후단부에는 폐합반(67)이 결합되되, 중심봉(65)의 후단부가 폐합반(67)의 중심부를 관통하여 후방측으로 노출되고, 노출된 중심봉(65) 후단부에 고정너트(68)가 체결됨으로써, 원통체(60)의 후단부에 폐합반(67)이 긴밀하게 결합된다.A center bar 65 is joined to the center of the cylindrical body 60 in the axial direction of the cylindrical body 60. A thread is formed at the rear end of the center bar 65, The rear end of the center rod 65 is exposed to the rear side through the center portion of the closing member 67 and the fixing nut 68 is fastened to the rear end of the exposed center rod 65, The closing member 67 is tightly coupled to the rear end of the cylindrical body 60.

이렇듯, 형성된 원통체(60)의 내부 공간에는 고분자흡수체(70)가 적재되는데, 본 발명에 있어서 고분자흡수체(70)로는 흡수팽윤(吸水膨潤)특성을 가진 고분자화합물을 입자상(粒子狀)으로 가공한 입상체(粒狀體) 또는 분말상의 흡수팽윤성 고분자화합물을 통수성(通水性) 원단으로 봉제(縫製)된 주머니에 충전한 팽윤낭(膨潤囊)이 적용된다.The polymeric absorber 70 is loaded in the inner space of the formed cylindrical body 60. In the present invention, the polymeric absorber 70 is formed by processing a polymer compound having absorption swelling (water swelling) A swollen bag filled with a granular or powdery absorbent-swellable polymer compound in a bag sewn into a water-permeable fabric is applied.

고분자흡수체(70)는 자체 부피의 수배 내지 수십배의 물을 흡수할 수 있음은 물론, 스펀지 등 여타의 흡수재와 달리 일단 물을 흡수한 후 팽윤 및 고화되어, 흡수한 물이 재방출되지 않으므로, 케이싱(40)내 잔류수가 일단 원통체(60) 내부로 유입되면, 원통체(60)의 이동에도 불구하고 원통체(60) 외부로 누출되지 않게 된다.The polymer absorbent body 70 can absorb water several times to several tens of times its own volume, and, unlike other absorbent materials such as sponge, swollen and solidified after once absorbing the water, Once the remaining water in the cylindrical body 40 flows into the cylindrical body 60, the cylindrical body 60 is prevented from leaking to the outside of the cylindrical body 60 despite the movement of the cylindrical body 60.

도 8은 상당량의 잔류수를 흡수하여 고분자흡수체(70)가 팽창된 상태를 예시하고 있으며, 이렇듯 잔류수를 흡수하면 고분자흡수체(70)가 팽창되는 바, 잔류수제거단계(S22)의 수행전 원통체(60) 내부에 고분자흡수체(70)를 투입함에 있어서는 원통체(60) 내부를 완전히 채우지 않도록 하는 것이 바람직하다.
FIG. 8 illustrates a state in which the polymer absorbent 70 is expanded by absorbing a considerable amount of residual water. When the residual water is absorbed as described above, the polymer absorbent 70 is expanded, and before the residual water removing step S22 It is preferable that the inside of the cylindrical body 60 is not completely filled when the polymer absorbent body 70 is inserted into the cylindrical body 60. [

11 : 발진구
12 : 도달구
21 : 굴착장치
22 : 로드
23 : 굴착비트
25 : 벤토나이트 취급설비
31 : 확공기
35 : 스위벨
40 : 케이싱
41 : 전선관
45 : 견인선
51 : 윈치
60 : 원통체
61 : 돌출환체
63 : 통수공
65 : 중심봉
67 : 폐합반
68 : 고정너트
70 : 고분자흡수체
S10 : 예비굴착단계
S20 : 확공단계
S21 : 가압배수단계
S22 : 잔류수제거단계
S30 : 전선설치단계
11: Hwajinggu
12: Reach
21: Excavator
22: Load
23: Excavation bit
25: Bentonite handling equipment
31: Reamer
35: Swivel
40: casing
41: conduit
45: traction line
51: Winch
60: Cylindrical body
61: protruding flange
63: water ball
65: center rod
67: closing class
68: Fixing nut
70: polymer absorber
S10: preliminary drilling step
S20: Expansion phase
S21: Pressurized drainage step
S22: step of removing residual water
S30: Step of wiring installation

Claims (2)

수평 추진형 지중 전선로 시공방법에 있어서,
계획 지중 전선로의 양측 단부에 각각 발진구(11)와 도달구(12)가 굴착되고, 발진구(11)로 투입된 굴착비트(23) 배후에 로드(22)가 반복 연결되면서 계획 전선로의 경로를 따라 소구경 예비 굴착공이 형성되는 예비굴착단계(S10)와;
예비 굴착공에 관입된 로드(22)의 굴착장치(21) 타측 단부에 확공기(31)를 장착하고, 확공기(31) 배후에는 견인선(45)이 내장된 케이싱(40)을 연결한 후, 확공기(31)를 견인하여 케이싱(40)을 매설하는 확공단계(S20)와;
견인선(45)의 일단에 전선관(41)을 결속하고, 전선관(41)을 케이싱(40) 내부로 투입한 후, 견인선(45)을 견인하여, 케이싱(40) 내부에 전선관(41)을 설치하는 전선설치단계(30)로 이루어짐을 특징으로 하는 케이싱(40) 수평 추진형 지중 전선로 시공방법.
In a horizontally propelled underground cable installation method,
The projecting mouth 11 and the reaching mouth 12 are respectively excavated at both ends of the planned underground conductor line and the rod 22 is repeatedly connected behind the excavating bit 23 inserted into the emanation opening 11, A preliminary drilling step (S10) of forming a small diameter preliminary drilling hole;
The reamer 31 is attached to the other end of the rod 22 penetrated into the preliminary drilling hole and the casing 40 having the pulling line 45 is connected to the rear of the reamer 31 (S20) of towing the reamer (31) and embedding the casing (40);
The conduit pipe 41 is connected to one end of the traction line 45 and the conduit pipe 41 is inserted into the casing 40 and then the traction line 45 is pulled to connect the conduit pipe 41 to the inside of the casing 40, (30) for installing the horizontal propulsion type underground cable (40).
청구항 1에 있어서, 확공단계(S20)가 수행된 이후,
케이싱(40)의 일측 단부가 밀봉되고, 밀봉부위에 압송장치가 연결되어, 케이싱(40) 내부로 압축공기가 압송됨으로써, 케이싱(40)내 저류수가 외부로 배출되는 가압배수단계(S21)가 수행되고,
케이싱(40) 내주면에 밀착되는 돌출환체(61)가 외주면에 형성된 원통체(60)가 케이싱(40) 내부에서 이동됨으로써, 케이싱(40)내 잔류수가 집수 및 배출되는 잔류수제거단계(S22)가 수행된 후,
전선설치단계(S30)가 수행됨을 특징으로 하는 케이싱(40) 수평 추진형 지중 전선로 시공방법.
2. The method of claim 1, wherein after the widening step (S20)
A pressure drainage step S21 in which one end of the casing 40 is sealed and a pressure feeding device is connected to the sealing portion so that compressed air is fed into the casing 40 to discharge the stored water in the casing 40 to the outside Lt; / RTI &
A residual water removing step S22 for collecting and discharging residual water in the casing 40 by moving the cylindrical body 60 formed on the outer circumferential surface of the casing 40 in the casing 40, Is performed,
And a wire installation step (S30) is performed.
KR1020160170142A 2016-12-14 2016-12-14 Horizontal casing propulsion type underground line construction method KR101776916B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160170142A KR101776916B1 (en) 2016-12-14 2016-12-14 Horizontal casing propulsion type underground line construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160170142A KR101776916B1 (en) 2016-12-14 2016-12-14 Horizontal casing propulsion type underground line construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020160114237A Division KR101705694B1 (en) 2016-09-06 2016-09-06 Horizontal casing propulsion type underground line construction method

Publications (1)

Publication Number Publication Date
KR101776916B1 true KR101776916B1 (en) 2017-09-08

Family

ID=59925879

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160170142A KR101776916B1 (en) 2016-12-14 2016-12-14 Horizontal casing propulsion type underground line construction method

Country Status (1)

Country Link
KR (1) KR101776916B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102105160B1 (en) 2019-11-04 2020-04-28 (주)몰크리켓 Piercing tool indentation method
KR20200064372A (en) 2018-11-29 2020-06-08 (주)몰크리켓 Piercing tool indentation method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100967308B1 (en) * 2009-12-01 2010-07-01 프로몰엔지니어링주식회사 Cable carring mathod for submarine conduit line
KR101310715B1 (en) * 2013-02-14 2013-09-24 주식회사 디엔텍 Eco-friendly submarine pipeline establishing method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100967308B1 (en) * 2009-12-01 2010-07-01 프로몰엔지니어링주식회사 Cable carring mathod for submarine conduit line
KR101310715B1 (en) * 2013-02-14 2013-09-24 주식회사 디엔텍 Eco-friendly submarine pipeline establishing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200064372A (en) 2018-11-29 2020-06-08 (주)몰크리켓 Piercing tool indentation method
KR102105160B1 (en) 2019-11-04 2020-04-28 (주)몰크리켓 Piercing tool indentation method

Similar Documents

Publication Publication Date Title
RU2693805C2 (en) System (versions) and method for near-surface laying of underground cables or underground lines in ground
KR100836626B1 (en) P.m.g construction method and constructing system thereof
JP2011052536A5 (en)
KR101776916B1 (en) Horizontal casing propulsion type underground line construction method
KR101705694B1 (en) Horizontal casing propulsion type underground line construction method
JP3974090B2 (en) Long face bolt construction method
KR101309774B1 (en) A methode for constructing
JP2009287326A (en) Pulling out method of existing pile
US6183163B1 (en) Method and apparatus for laying out a pipeline
JP2012021390A (en) Method of constructing steel pipe pile foundation, and head of drilling insertion apparatus
CN210660211U (en) Device for processing water detection and drainage drilling and punching
JP2003214085A (en) Mouth forming method on arrival of shield machine and shield machine
EA017789B1 (en) Tool for drilling through loosely-packed materials
JP2000248887A (en) Method for guiding ramer in non-open-cut pipe laying and guide for use in the same
JP4967103B2 (en) Underground construction method for synthetic resin pipes
JP3755472B2 (en) Ground improvement method
KR101089815B1 (en) The method for laying pipes for underground wire
RU2128310C1 (en) Method of flying pipe line and system for realization of this method
JP2006132079A (en) Construction method for dissipating excess pore water pressure
JP2000248893A (en) Pipe laying by non-cut and cover method
JP2741653B2 (en) Drilling tube for chemical injection
KR102323639B1 (en) Leading pipe with radial type grouting apparatus and steel pipe pressing method using the same
JP2018115424A (en) Underground drawing-in method of pipe
JP2000290989A (en) Strengthening construction method for ground under existing structure
JP2001182496A (en) Water leakage measure of tunnel

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant