KR101624518B1 - Live wire precast manhole and its construction method - Google Patents

Live wire precast manhole and its construction method Download PDF

Info

Publication number
KR101624518B1
KR101624518B1 KR1020150188024A KR20150188024A KR101624518B1 KR 101624518 B1 KR101624518 B1 KR 101624518B1 KR 1020150188024 A KR1020150188024 A KR 1020150188024A KR 20150188024 A KR20150188024 A KR 20150188024A KR 101624518 B1 KR101624518 B1 KR 101624518B1
Authority
KR
South Korea
Prior art keywords
manhole
precast
upper plate
columns
live
Prior art date
Application number
KR1020150188024A
Other languages
Korean (ko)
Inventor
송관흠
상형주
유순경
Original Assignee
대실테크 주식회사
(주)세정엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대실테크 주식회사, (주)세정엔지니어링 filed Critical 대실테크 주식회사
Priority to KR1020150188024A priority Critical patent/KR101624518B1/en
Application granted granted Critical
Publication of KR101624518B1 publication Critical patent/KR101624518B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/125Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

An objective of the present invention is to provide a live wire precast manhole and an installation method thereof which facilitate installation in a live wire state without relocating or damaging an obstruction complexly buried underground. According to the present invention, the live wire precast manhole comprises: an upper plate unit having at least one hole in which a manhole cover is mounted; a plurality of pillars which are integrated into the upper plate unit by precast concrete, and support the upper plate unit; a through hole formed between two neighboring pillars, through which an obstruction passes; and an exposed rebar exposed to the upper plate unit on a side of the through hole and one surface of the pillars to be buried in concrete when forming a side wall.

Description

활선 프리캐스트맨홀 및 이의 시공방법{Live wire precast manhole and its construction method}Live wire precast manhole and its construction method "

본 발명은 활선 프리캐스트맨홀 및 이의 시공방법에 관한 것으로서, 지하에 매설되어 있는 지장물을 이설하지 않고 용이하게 설치할 수 있는 활선 프리캐스트맨홀 및 이의 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a live precast manhole and a method of constructing the same, and more particularly, to a live precast manhole and a method of constructing the same.

일반적으로 상.하수도관, 도시 가스관, 소화전, 지역 난방관, 송유관, 전력선, 통신 케이블 등을 지하에 매설할 경우에는 일정한 지역에 맨홀을 설치한다. 그 중에서 전력선용 맨홀은 도로가 분기되는 지점, 관로가 분기되는 지점, 관로가 허용 곡률 이상으로 굴곡되어야 할 경우, 급경사 언덕길, 긴교량의 전.후, 및 케이블의 접속 또는 분기 장소에 설치된다.Generally, a manhole should be installed in a certain area when it is buried underground, sewage pipe, city gas pipe, fire hydrant, district heating pipe, oil pipeline, power line, Among them, manholes for electric power lines are installed at the points where the roads diverge, where the ducts diverge, when the ducts must be bent beyond the allowable curvature, before and after the steep slopes, before and after the long bridges,

전력선용 맨홀을 지하에 설치할 경우에는 주로 현장에서 콘크리트를 타설하여 맨홀을 시공하는 현장 타설식 공법을 채택한다. 그러나, 상기 현장 타설식 공법은 현장에서 모든 작업이 이루어져야 하므로 모든 장비를 현장으로 옮겨 작업을 해야하는 어려움이 있고, 시공 기간이 길고 현장의 교통 혼잡이 발생되는 단점이 있다.When a manhole for a power line is installed underground, a concrete installation method is used to install a manhole mainly in the field. However, the above-mentioned field-borne construction method has a disadvantage in that all the work must be performed in the field, so it is difficult to carry out all the equipment to the site, and the construction period is long and traffic congestion occurs on the site.

한편, 조립식 공법은 벽체, 상부 슬래브, 하부 바닥 등을 미리 제작한 후 현장에서 조립하는 공법인데, 현장 타설식에 비해 공사 기간을 단축할 수는 있지만 조립되는 부품의 연결 부위마다 수팽창 지수제 등으로 방수처리를 해야 하는 어려움이 있다.On the other hand, the prefabrication method is a method of prefabricating the wall, the upper slab, the bottom floor, etc., and assembling them in the field. It is possible to shorten the construction period compared to the field installation method. However, It is difficult to carry out waterproofing treatment.

대한민국 등록특허 0693307호(2007년 3월 14일 공고)Korean Patent No. 0693307 (published on March 14, 2007)

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 본 발명의 목적은 지하에 복잡하게 매설되어 있는 지장물을 이설하거나 파손시키지 않고, 활선 상태에서 시공이 용이한 활선 프리캐스트맨홀 및 이의 시공방법을 제공하는 것이다.SUMMARY OF THE INVENTION It is an object of the present invention to provide a live precast manhole and a method of constructing the live precast manhole that are easy to install in a live state without damaging or damaging the obstacle, .

또한 프리캐스트 공법을 적용하여 공정시간을 단축할 수 있는 활선 프리캐스트맨홀 및 이의 시공방법을 제공하는 것이다.Also, it is intended to provide a live precast manhole and a method of constructing the same that can shorten the processing time by applying a precast method.

또한 시공현장의 굴착면적 및 굴착량을 최소화하여, 교통흐름의 장애를 최소화하고 시공경비를 절감할 수 있는 활선 프리캐스트맨홀 및 이의 시공방법을 제공하는 것이다.The present invention also provides a live precast manhole and a method of constructing the same that minimize the excavation area and excavation amount of a construction site to minimize obstacles in traffic flow and reduce construction cost.

상기와 같은 목적을 달성하기 위하여, 본 발명의 일 측면에 따른 활선 프리캐스트맨홀은 보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선 상태를 유지하며 보수작업을 실시할 수 있는 프리캐스트맨홀에 있어서, 맨홀 뚜껑과 결합하는 적어도 하나의 홀을 구비하는 상판부와, 상기 상판부와 프리캐스트콘크리트에 의해 일체로 형성되며 상기 상판부를 지지하는 복수개의 기둥과, 상기 이웃하는 2개의 기둥 사이에 형성되어 지장물이 통과하는 통과홀과, 상기 통과홀 측 상기 상판부 및 상기 기둥 일면에 노출되어 측벽 형성시 콘크리트에 매설되는 노출철근을 구비할 수 있다.In order to accomplish the above object, a live precast manhole according to an aspect of the present invention is characterized in that the live precast manhole is in a live state without damaging the obstacle such as a communication line, The present invention relates to a precast manhole capable of maintaining and repairing a manhole cover, comprising: an upper plate portion having at least one hole that engages with a manhole cover; and a plurality of pillar portions integrally formed with the upper plate portion and the precast concrete, And an exposed reinforcing bar formed between the adjacent two pillars and through which the barrier material passes, and an exposed reinforcing bar exposed in the through hole-side upper plate portion and one side of the column and embedded in the concrete when the side wall is formed.

상기 복수개의 기둥 외측 하부에는 개착된 설치장소 내부 하측에 다짐작업을 하기 위한 스틸플레이트가 구비될 수 있다.And a steel plate for compaction operation may be provided on the lower side of the outside of the plurality of columns in a place where the installation site is installed.

상기 복수개의 기둥 내측에는 개착된 설치장소 내부에 콘크리트 타설을 하기 위한 토류판이 설치될 수 있다.And a soil plate for pouring concrete may be installed inside the installation place inside the plurality of columns.

상기 이웃하는 2개의 기둥 사이에서 프리캐스트콘크리트에 의해 일체로 형성되는 프리캐스트 측벽을 더 구비할 수 있다.And a precast sidewall formed integrally with the precast concrete between the adjacent two columns.

상기 상판부에는 상기 프리캐스트맨홀을 인양 및 안착하기 위한 고리가 형성될 수 있다.The upper plate portion may be formed with a ring for lifting and seating the precast manhole.

상기와 같은 목적을 달성하기 위하여, 본 발명의 일 측면에 따른 활선 프리캐스트맨홀의 시공방법은 보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선 상태를 유지하며 보수작업을 실시하기 위한 활선 프리캐스트맨홀을 이용하는 시공방법에 있어서, 보수가 필요한 시공현장의 크기에 따라 도로 컷팅 및 포장층 제거와 맨홀뚜껑 및 맨홀목을 비롯한 기존맨홀을 철거하는 단계; 지하에 매설되어 있는 지장물의 위치를 확인하여 정리한 후 현장바닥을 정리하고 바닥콘크리트를 타설하는 단계; 맨홀 뚜껑과 결합하는 적어도 하나의 홀을 구비하는 상판부와, 상기 상판부와 프리캐스트콘크리트에 의해 일체로 형성되며 상기 상판부를 지지하는 복수개의 기둥과, 상기 이웃하는 2개의 기둥 사이에 형성되어 지장물이 통과하는 통과홀과, 상기 통과홀 측 상기 상판부 및 상기 기둥 일면에 노출되어 측벽 형성시 콘크리트에 매설되는 노출철근을 구비하는 프리캐스트맨홀을 안착시키는 단계; 상기 복수개의 기둥 외측 하부에 스틸플레이트를 설치하는 단계; 개착된 설치장소 내부 하측과 상기 스틸플레이트 사이 공간에 모래물 다짐작업을 하는 단계; 상기 복수개의 기둥 내측에 ㄷ형강 및 토류판을 설치하는 단계; 개착된 설치장소 내부에 콘크리트 타설을 하는 단계; 65℃ 내지 75℃의 온도를 유지하도록 하는 스팀을 공급하거나 마이크로웨이브를 이용하는 발열장치를 이용하여 양생 및 되메우기 작업이 시행되는 벽체 시공 및 되메우기 단계; 맨홀 뚜껑과 같은 구조물을 시공하고, 터파기된 도로를 포장하는 맨홀구조물 시공 및 포장 단계; 및 상기 복수개의 기둥 내측에 설치된 토류판을 철거하고 방수 및 방식하는 단계; 를 구비할 수 있다.In order to accomplish the above object, according to one aspect of the present invention, there is provided a method of constructing a live precast manhole, comprising: disposing a manhole, In the construction method using live cast precast manhole to perform maintenance work while maintaining the live condition, it is necessary to remove the road cut and the pavement layer according to the size of the construction site requiring repair, and to remove the existing manhole including the manhole cover and manhole step; Confirming the location of the obstacles buried in the basement, arranging the floor and laying the floor concrete; A plurality of pillars formed integrally with the upper plate portion and the precast concrete and supporting the upper plate portion, and a plurality of pillars formed between the adjacent two pillars, Placing a precast manhole having a through hole passing through the through hole and the exposed reinforcing bars exposed in the upper plate portion and the one side of the column to form a sidewall when the sidewall is formed; Installing a steel plate on the outside of the plurality of columns; A sand compaction operation is performed in a space between an inside lower part of the installed installation place and the steel plate; Installing a U-shaped beam and a current plate on the inside of the plurality of columns; Placing concrete within the installed installation site; A step of curing and backing the curing and refilling operation by supplying steam to maintain a temperature of 65 to 75 ° C or using a heating device using a microwave; A step of constructing a manhole cover, and a step of constructing and packing a manhole structure for packing a road that has been erected; And removing and watering the soil plate installed on the inner side of the plurality of columns; .

상기 복수개의 기둥 내측에 토류판을 설치하는 단계는 상기 이웃하는 2개의 기둥 사이에 측벽철근을 배근하는 단계와, 배근 된 상기 측벽철근과 상기 노출철근을 연결하는 단계를 구비할 수 있다.The step of installing the earth plate on the inner side of the plurality of columns may include the steps of arranging the side wall reinforcement bars between the adjacent two columns and connecting the reinforced side wall reinforcement bars to the exposed reinforcing bars.

상기 복수개의 기둥 내측에 설치된 토류판을 철거하고 방수 및 방식하는 단계는 지장물이 통과하는 관로구를 설치하는 단계를 구비할 수 있다.The step of dismantling, waterproofing, and disposing the dust plate installed on the inner side of the plurality of columns may include the step of providing a channel through which the obstacle is passed.

상기 프리캐스트맨홀을 안착시키는 단계 이전에는 상기 상판부에 상기 프리캐스트맨홀을 인양 및 안착하기 위한 고리를 구비하는 단계가 구비될 수 있다.And a step of lifting and securing the precast manhole to the upper plate part before the step of seating the precast manhole.

본 발명의 일 측면에 따른 활선 프리캐스트맨홀 및 이의 시공방법에 의하면, 지하에 매설되어 있는 지장물을 이설하지 않고 시공할 수 있으므로, 공사현장 주변에 사는 주민들이 단전 또는 단수로 불편함을 겪는 것을 방지할 수 있다.According to one aspect of the present invention, the live precast manhole and the method of constructing the same can prevent the residents living in the vicinity of the construction site from experiencing discomfort or discomfort due to the construction, can do.

또한, 시공이 용이하며 연속적으로 작업을 할 수 있으므로 공정시간을 단축시킬 수 있다.In addition, since the construction is easy and the work can be continuously performed, the processing time can be shortened.

또한 굴착면적 및 굴착량을 최소화할 수 있으므로 교통의 장애를 최소화하고 경비를 절감할 수 있는 효과를 제공하게 된다.In addition, since the excavation area and excavation amount can be minimized, it is possible to minimize the obstacle of traffic and reduce the cost.

도 1은 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀의 사시도.
도 2는 도 1에 도시된 활선 프리캐스트맨홀이 설치된 모습의 단면도.
도 3은 도 1에 도시된 활선 프리캐스트맨홀이 설치된 모습의 또 다른 단면도.
도 4는 도 1에 도시된 활선 프리캐스트맨홀이 설치된 모습의 또 다른 단면도.
도 5는 도 1에 도시된 활선 프리캐스트맨홀의 변형 예를 나타낸 사시도.
도 6은 도 1에 도시된 활선 프리캐스트맨홀의 또 다른 변형 예를 나타낸 사시도.
도 7은 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀의 시공방법을 나타낸 순서도.
도 8은 도 7에 도시된 활선 프리캐스트맨홀의 시공방법의 세부공정을 나타낸 순서도.
1 is a perspective view of a live precast manhole according to an embodiment of the present invention;
2 is a cross-sectional view of a state in which the live-line precast manhole shown in Fig. 1 is installed.
3 is another cross-sectional view of a state in which the live-line precast manhole shown in Fig. 1 is installed.
4 is another cross-sectional view of a state in which the live-line precast manhole shown in Fig. 1 is installed.
5 is a perspective view showing a modified example of the live-line precast manhole shown in Fig.
FIG. 6 is a perspective view showing still another modification of the live line precast manhole shown in FIG. 1; FIG.
7 is a flowchart showing a method of constructing a live precast manhole according to an embodiment of the present invention.
8 is a flowchart showing a detailed process of a method of constructing the live line precast manhole shown in FIG.

이하에서는 본 발명의 바람직한 일 실시 예에 따른 활선 프리캐스트맨홀 및 이의 시공방법에 대해 상세히 설명하기로 한다.Hereinafter, a live precast manhole according to a preferred embodiment of the present invention and a construction method thereof will be described in detail.

도 1은 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀의 사시도이고, 도 2는 도 1에 도시된 활선 프리캐스트맨홀이 설치된 모습의 단면도이고, 도 3은 도 1에 도시된 활선 프리캐스트맨홀이 설치된 모습의 또 다른 단면도이고, 도 4는 도 1에 도시된 활선 프리캐스트맨홀이 설치된 모습의 또 다른 단면도이다.FIG. 1 is a perspective view of a live-line precast manhole according to an embodiment of the present invention, FIG. 2 is a sectional view of the live-line precast manhole shown in FIG. 1, Fig. 4 is another cross-sectional view of a state in which the live-line precast manhole shown in Fig. 1 is installed. Fig.

도 1 내지 도 4에 도시된 바와 같이, 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀(10)은 상판부(100), 기둥(200), 통과홀(300) 및 노출철근(400)을 구비할 수 있다.1 to 4, a live precast manhole 10 according to an embodiment of the present invention includes an upper plate 100, a column 200, a through hole 300, and an exposed reinforcing bar 400 can do.

상기의 활선 프리캐스트맨홀(10)은 보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선 상태를 유지하며 보수작업이 이루어지도록 할 수 있다. 이를 위해, 우선적으로 보수가 요구되는 맨홀의 설치장소를 개착하여 활선 프리캐스트맨홀(10)이 지중에 매설되도록 할 수 있다.The live precast manhole 10 can be maintained in a live state without repairing obstacles such as communication lines, electric wires, and various pipelines installed at the installation place of the manhole requiring maintenance, and maintenance work can be performed. For this purpose, it is possible to open the installation place of the manhole in which maintenance is required first, so that the live precast manhole 10 can be buried in the ground.

여기서, 개착된 설치장소(30)에 매설되는 활선 프리캐스트맨홀(10)의 상기 상판부(100)는 지면과 인접한 위치에 구비될 수 있다. 그리고, 상판부(100)에는 적어도 하나의 홀(110)이 형성되어 활선 프리캐스트맨홀(10)이 맨홀 된 후 맨홀 뚜껑이 상판부(100)와 결합하도록 할 수 있다.Here, the upper plate 100 of the hot-line precast manhole 10, which is embedded in the installed place 30, may be provided at a position adjacent to the ground. At least one hole 110 is formed in the upper plate 100 so that the manhole cover can be engaged with the upper plate 100 after the hot-line precast manhole 10 is completely filled.

상기의 기둥(200)은 상판부(100)와 프리캐스트 콘크리트에 의해 일체로 형성되며 활선 프리캐스트맨홀(10)이 필로티(pilotis)구조가 되도록 구비될 수 있다. The column 200 is integrally formed with the top plate 100 and the precast concrete, and the live precast manhole 10 may have a pilot structure.

필로티란 건물 상층을 지탱하는 독립기둥으로, 벽이 없는 일층의 주열(柱列)을 말한다. 건물 1층을 거의 기둥만으로 한 층이 되게 하고 주위의 지반과 연속시켜, 건물로 지상을 점유하지 않고 지상의 교통을 방해하지 않는 효과를 발휘할 수 있다.Piloti is an independent column supporting the upper floors of the building. The first floor of the building is made up of only one column and is continuous with the surrounding ground, so that the effect of not obstructing the traffic on the ground without occupying the ground with the building can be demonstrated.

상기와 같이, 활선 프리캐스트맨홀(10)이 필로티 구조로 구비됨으로써 이웃하는 2개의 기둥(200) 사이에 형성된 통과홀(300)을 통해 지중에 매설되어 있는 지장물이 자유롭게 통과 및 방향 전환을 할 수 있다.As described above, since the live-line precast manhole 10 is provided in a pilotty structure, the obstacle buried in the ground can freely pass and change direction through the through hole 300 formed between the two adjacent pillars 200 .

그리고, 지장물의 파손 없이 활선 상태에서 보수를 한 후 활선 프리캐스트맨홀(10)을 설치함으로써 시공이 용이하고 이에 따라 공정시간이 단축될 수 있다.By installing the live precast manhole 10 after repairing in a live state without damaging the obstacle, the construction can be facilitated and the processing time can be shortened accordingly.

또한, 활선 프리캐스트맨홀(10)이 매설될 정도만을 굴착하더라도 지장물의 보수작업 및 활선 프리캐스트맨홀(10)의 안착 및 매설이 가능하므로 굴착면적뿐만 아니라 굴착량을 최소화할 수 있어 교통 흐름 장애를 최소화하고 시공비를 절감하는 효과를 발휘할 수 있다.In addition, even if only the live precast manhole 10 is excavated, it is possible to perform the repair work of the obstacle and the seating and burying of the live precast manhole 10, so that not only the excavation area but also the excavation amount can be minimized, And the effect of reducing the construction cost can be exhibited.

노출철근(400)은 상판부(100)와 기둥(200)에서 통과홀(300) 측으로 노출되는 철근으로써 보수작업을 마무리하고 활선 프리캐스트맨홀(10)을 안착시킨 후 이웃하는 2개의 기둥(200) 사이에 측벽(700)을 형성할 시 콘크리트에 매설될 수 있다.The exposed reinforcing bar 400 is a reinforcing bar exposed from the upper plate 100 and the column 200 toward the through hole 300. The reinforcing bar 400 is finished with the repair work and seats the live precast manhole 10, The side wall 700 can be embedded in the concrete when it is formed.

상기의 측벽(700)을 형성할 시에는 콘크리트를 타설하기 전에 측벽(700)의 강성을 높이기 위한 측벽철근(710)이 배근 될 수 있다. 이때, 측벽철근(710)은 상판부(100)와 기둥(200)에 노출되어 있는 상기의 노출철근(400)과 연결되어 용이하게 배근되도록 하는 효과를 발휘할 수 있다.When forming the sidewall 700, a sidewall reinforcing bar 710 for increasing the rigidity of the sidewall 700 may be disposed before the concrete is laid. At this time, the sidewall reinforcing bars 710 are connected to the exposed reinforcing bars 400 exposed on the top plate 100 and the pillars 200, so that the side reinforcing bars 710 can be easily placed.

본 실시 예에서는 기둥(200)에 구비되는 노출철근(400)이 두 개의 열을 형성하여 기둥(200)의 길이방향으로 따라 일정간격으로 구비되고 상판부(100)에 구비되는 노출철근(400)이 한 개의 열을 형성하여 통과홀(300) 측 일면에 일정간격으로 구비된 것을 보였으나, 기둥(200)과 상판부(100)에 구비되는 상기의 노출철근(400)은 활선 프리캐스트맨홀(10)이 매설되는 현장에 따라 다양한 형태와 개수로 구비될 수 있다.In the present embodiment, the exposed reinforcing bars 400 provided in the column 200 form two rows so as to be spaced apart along the longitudinal direction of the columns 200, and the exposed reinforcing bars 400 provided on the upper plate 100 The exposed reinforcing bars 400 provided on the pillars 200 and the upper plate 100 are formed in the same manner as the live precast manholes 10, May be provided in various shapes and numbers depending on the field in which they are embedded.

한편, 활선 프리캐스트맨홀(10)을 개착된 설치장소(30)에 안착하기 전에는 바닥면에 바닥콘크리트(20)를 타설하여 활선 프리캐스트맨홀(10)이 용이하게 지면과 수평을 이루도록 할 수 있다.The floor pre-cast manhole 10 can be easily placed horizontally with the ground by placing the floor concrete 20 on the floor surface before the live pre-cast manhole 10 is seated in the installed place 30 .

그리고, 바닥콘크리트(20)를 타설한 후에는 활선 프리캐스트맨홀(10)을 개착된 설치장소(30)에 안착시키고 복수개의 기둥(200) 외측 하부를 감싸는 형태로 개착된 설치장소(30)에 스틸플레이트(500)를 설치할 수 있다.After the floor concrete 20 is laid, the hot-line precast manhole 10 is placed in the installed place 30 and the place 30 is installed in the form of wrapping the lower outside of the plurality of pillars 200 The steel plate 500 can be installed.

스틸플레이트(500)는 복수개의 기둥(200) 외측 하부에 구비되어 개착된 설치장소(30)의 내부 하측에 다짐작업이 이루어지도록 할 수 있다. 이때, 스틸플레이트(500)의 높이는 관통구(50)의 하단부에 이르도록 하여 관통구(50) 및 관통구(50) 내부에 구비되는 통신선, 전선 및 각종 배관과 같은 지장물에 영향을 끼치지 않도록 할 수 있다. 스틸플레이트(500)가 설치됨에 따라 스틸플레이트(500)와 개착된 설치장소(30)의 개착면(31) 사이에는 공간이 형성되고 상기의 공간에는 모래(40)가 채워질 수 있다. 모래(40)가 채워진 후에는 모래(40)를 물다짐 함으로써 개착된 설치장소(30)의 내부 하측이 단단해지도록 할 수 있다.The steel plate 500 may be provided on the lower outer side of the plurality of columns 200 to enable the compaction operation to be performed on the inner lower side of the installed installation site 30. At this time, the height of the steel plate 500 reaches the lower end of the through-hole 50, so that the height of the steel plate 500 does not affect the obstacles such as communication lines, electric wires and various pipes provided in the through- . As the steel plate 500 is installed, a space is formed between the steel plate 500 and the attachment surface 31 of the installed installation site 30, and the space may be filled with the sand 40. After the sand 40 is filled, the inner side of the installed place 30 can be made hard by sanding the sand 40.

이에 따라, 스틸플레이트(500)와 함께 향후 활선 프리캐스트맨홀(10) 상부에 가해지는 충격이나 진동에 의해 활선 프리캐스트맨홀(10)이 매설된 주변 지반이 무너지는 것을 방지할 수 있다.Accordingly, it is possible to prevent collapse of the surrounding ground in which the live-line precast manhole 10 is buried by impact or vibration applied to the upper part of the live-line precast manhole 10 together with the steel plate 500.

한편, 스틸플레이트(500)를 설치하여 모래(40)를 물다짐 방법을 통해 다짐작업이 이루어진 후에는 개착된 설치장소(30)에 콘크리트를 타설하여 활선 프리캐스트맨홀(10)을 매설하는 작업이 이루어질 수 있다.Meanwhile, after the steel plate 500 is installed and the sand 40 is compacted through the water compacting method, the operation of placing the concrete into the installed installation site 30 to place the live precast manhole 10 Lt; / RTI >

이때, 복수개의 기둥(200) 내측에는 토류판(600)이 구비될 수 있다.At this time, a soil plate 600 may be provided inside the plurality of columns 200.

상기의 토류판(600)은 거푸집과 같은 역할을 하여 개착된 설치장소(30)에 콘크리트를 타설할 시 콘크리트가 통과홀(300)을 통해 복수개의 기둥(200) 내측 공간으로 침투하는 것을 방지함과 동시에 통과홀(300)에 측벽(700)이 형성되도록 할 수 있다.The soil plate 600 acts as a mold to prevent the concrete from penetrating into the inner space of the plurality of columns 200 through the through hole 300 when the concrete is installed in the installed place 30, At the same time, the side wall 700 can be formed in the through hole 300.

따라서, 활선 프리캐스트맨홀(10)이 지중에 완전히 매설되더라도 토류판(600)에 의해 복수개의 기둥(200) 내측 공간은 유지되므로 향후 상판부(100)에 형성된 홀(110)을 통해 지장물의 관찰 또는 유지보수가 용이하게 이루어질 수 있다.Therefore, even if the hot-line precast manhole 10 is completely buried in the ground, the inner space of the plurality of pillars 200 is held by the dust plate 600. Therefore, the user can observe or hold the suspended object through the hole 110 formed in the upper plate 100, Maintenance can be easily performed.

다음은 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀(10)의 변형 예에 대해 설명하도록 한다. 이하의 설명에서는 상술한 실시 예와 서로 다른 부분만을 상세하게 설명하며 동일하거나 극히 유사한 부분에 대해서는 상세한 설명을 생략한다.Next, a modified example of the live precast manhole 10 according to an embodiment of the present invention will be described. In the following description, only different parts from the above-described embodiment will be described in detail and the same or similar parts will not be described in detail.

도 5는 도 1에 도시된 활선 프리캐스트맨홀의 변형 예를 나타낸 사시도이고, 도 6은 도 1에 도시된 활선 프리캐스트맨홀의 또 다른 변형 예를 나타낸 사시도이다.Fig. 5 is a perspective view showing a modified example of the live-line precast manhole shown in Fig. 1, and Fig. 6 is a perspective view showing still another modified example of the live-line precast manhole shown in Fig.

도 1 내지 도 6에 도시된 바와 같이, 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀(10)은 맨홀 뚜껑과 결합하는 적어도 하나의 홀(110)을 구비하는 상판부(100), 상판부(100)와 프리캐스트콘크리트에 의해 일체로 형성되며 상기 상판부(100)를 지지하는 복수개의 기둥(200), 이웃하는 2개의 기둥(200) 사이에 형성되어 지장물이 통과하는 통과홀(300) 및 통과홀(300) 측 상판부(100) 및 기둥(200) 일면에 노출되어 측벽(700) 형성시 콘크리트에 매설되는 노출철근(400)을 구비할 수 있다.1 to 6, a hot-line precast manhole 10 according to an embodiment of the present invention includes a top plate 100 having at least one hole 110 to be coupled with a manhole cover, a top plate 100 A plurality of columns 200 formed integrally with the precast concrete and supporting the upper plate 100, a through hole 300 through which the obstacle is formed, and a through hole 300 formed between the adjacent two columns 200, And an exposed reinforcing bar 400 exposed to one side of the upper plate 100 and the pillars 200 on the side of the hole 300 and embedded in the concrete when the side walls 700 are formed.

도 5를 참조하면, 상기의 활선 프리캐스트맨홀(10)은 이웃하는 2개의 기둥(200) 사이에서 프리캐스트 콘크리트에 의해 일체로 형성되는 프리캐스트 측벽(800)을 구비할 수 있다.5, the live precast manhole 10 may include a precast sidewall 800 integrally formed by precast concrete between two adjacent pillars 200.

즉, 프리캐스트 측벽(800)을 통해 지장물이 통과홀(300)을 통과하는 방향을 사전에 한정함과 동시에 현장에서 활선 프리캐스트맨홀(10)을 안착한 후 복수개의 기둥(200) 내측에 토류판(600)을 설치하는 작업량을 상대적으로 줄일 수 있다.That is, the direction of the obstacle passing through the through hole 300 is limited in advance through the precast sidewall 800, and the hot-line precast manhole 10 is seated in the field, It is possible to relatively reduce the amount of work for installing the battery 600.

또한, 활선 프리캐스트맨홀(10)이 매설되는 개착된 설치장소(30) 인근에 상하수도관 등과 같은 또 다른 관이 인접해 있을 경우, 시공시 다른 관에 피해가 가지 않도록 작업공간을 구획하는 역할을 할 수 있다.In addition, when another pipe such as a water supply and drainage pipe is adjacent to the installed place 30 where the live hot-cast manhole 10 is buried, it is a function to divide the work space so as not to damage other pipes can do.

이에 따라, 안전한 시공이 이루어지도록 함과 동시에 현장에서 이루어지는 전체적인 공사시간을 단축하는 효과를 발휘할 수 있을 뿐만 아니라 공장에서 미리 제작됨에 따라 현장에서 콘크리트 타설을 통해 제작되었을 때에 비해 상대적으로 높은 품질을 기대할 수 있다.As a result, it is possible to achieve a safe construction and shorten the overall construction time in the field. In addition, since the factory is manufactured in advance, relatively high quality can be expected compared with the case where the concrete is put on the site have.

본 실시 예에서는 프리캐스트 측벽(800)이 하나인 것을 보였으나, 상기의 프리캐스트 측벽(800)은 활선 프리캐스트맨홀(10)이 설치되는 위치에 따라 복수개 이상이 구비될 수 있다.In the present embodiment, there is one precast sidewall 800, but the precast sidewall 800 may be provided more than one according to the position where the live precast manhole 10 is installed.

한편, 도 6을 참조하면, 상기의 활선 프리캐스트맨홀(10)은 상판부(100)의 상면에 고리(120)가 형성될 수 있다.6, a ring 120 may be formed on the upper surface of the upper plate 100 in the hot-line precast manhole 10.

활선 프리캐스트맨홀(10)은 공장에서 제작된 후 현장으로 이송하여 설치하는 공정을 통해 시공되므로 인양 및 안착하는 작업을 위해 인양장치와 연결되어야 한다. 이때, 인양장치의 케이블 등을 활선 프리캐스트맨홀(10)의 상판부(100)나 다리에 감아 연결할 수 있으나 이러한 방법은 시간이 오래 걸리고 감는 위치나 방법에 따라 특정부위에 많은 힘이 가해져 활선 프리캐스트맨홀(10)이 파손될 수 있다.The live precast manhole 10 is manufactured at the factory and then transported to the site to be installed, so it must be connected to the lifting device for lifting and seating. At this time, the cable of the lifting device can be wound around the top plate 100 or the leg of the live precast manhole 10, but this method takes a long time and a lot of force is applied to a specific part depending on the winding position and method, The manhole 10 may be damaged.

이를 방지하기 위해 상판부(100)에 형성되는 상기의 고리(120)는 활선 프리캐스트맨홀(10)을 최초 제작할 시 상판부(100)의 상면에 형성되도록 구비되거나 활선 프리캐스트맨홀(10)을 제작완료한 후 별도로 상판부(100)의 상면에 설치할 수 있다.To prevent this, the loop 120 formed on the top plate 100 is formed to be formed on the upper surface of the top plate 100 when the live-line precast manhole 10 is initially manufactured, or the live-line precast manhole 10 is manufactured And may be separately provided on the upper surface of the upper plate 100.

이와 같이, 고리(120)가 활선 프리캐스트맨홀(10)의 상판부(100)에 구비됨으로써 활선 프리캐스트맨홀(10)을 인양 및 개착된 설치장소(30)에 안착하고자 할 시 인양장치와 활선 프리캐스트맨홀(10)을 쉽고 빠르게 연결할 수 있을 뿐만 아니라 인양장치가 들어올리는 힘이 특정부위에 많은 힘이 가해지는 것을 막아 활선 프리캐스트맨홀(10)이 파손되는 것을 방지하는 효과를 발 휘할 수 있다.When the hook 120 is provided on the top plate 100 of the live precast manhole 10 and the live precast manhole 10 is desired to be placed in the lifted and installed place 30, It is possible to easily and quickly connect the cast manhole 10 and to prevent the lifting of the lifting precast manhole 10 from being damaged by preventing the force of lifting the lifting device from exerting too much force on the specific portion.

본 실시 예에서는 고리(120)가 두 개인 것을 보였으나, 상기의 고리(120)는 활선 프리캐스트맨홀(10)의 크기나 무게 등에 따라 다수개가 구비될 수 있다.In this embodiment, the number of the rings 120 is two. However, the number of the rings 120 may be plural according to the size and weight of the live precast manhole.

다음은 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀(10)의 시공방법에 대해 설명하도록 한다.  Next, a method of constructing the live precast manhole 10 according to an embodiment of the present invention will be described.

도 7은 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀의 시공방법을 나타낸 순서도이고, 도 8은 도 7에 도시된 활선 프리캐스트맨홀의 시공방법의 세부공정을 나타낸 순서도이다.FIG. 7 is a flowchart illustrating a method of constructing a live precast manhole according to an embodiment of the present invention, and FIG. 8 is a flowchart illustrating a detailed process of a method of constructing a live precast manhole shown in FIG.

본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀(10)의 시공방법은 보수가 필요한 시공현장의 크기에 따라 도로 컷팅 및 포장층 제거와 맨홀뚜껑 및 맨홀목을 비롯한 기존맨홀을 철거하는 단계(S100); 지하에 매설되어 있는 지장물의 위치를 확인하여 정리한 후 현장바닥을 정리하고 바닥콘크리트(20)를 타설하는 단계(S200); 맨홀 뚜껑과 결합하는 적어도 하나의 홀(110)을 구비하는 상판부(100), 상판부(100)와 프리캐스트콘크리트에 의해 일체로 형성되며 상판부(100)를 지지하는 복수개의 기둥(200), 이웃하는 2개의 기둥(200) 사이에 형성되어 지장물이 통과하는 통과홀(300) 및 통과홀(300) 측 상판부(100) 및 기둥(200) 일면에 노출되어 측벽(700) 형성시 콘크리트에 매설되는 노출철근(400)을 구비하는 프리캐스트맨홀(10)을 안착시키는 단계(S300); 복수개의 기둥(200) 외측 하부에 스틸플레이트(500)를 설치하는 단계(S400); 개착된 설치장소(30) 내부 하측과 스틸플레이트(500) 사이 공간에 다짐작업을 하는 단계(S500); 복수개의 기둥(200) 내측에 ㄷ형강 및 토류판(600)을 설치하는 단계(S600); 개착된 설치장소(30) 내부에 콘크리트 타설을 하는 단계(S700); 65℃ 내지 75℃의 온도를 유지하도록 하는 스팀을 공급하거나 마이크로웨이브를 이용하는 발열장치를 이용하여 양생 및 되메우기 작업이 시행되는 벽체 시공 및 되메우기 단계(S800); 맨홀 뚜껑과 같은 구조물을 시공하고, 터파기된 도로를 포장하는 맨홀구조물 시공 및 포장 단계(S900); 및 복수개의 기둥 내측에 설치된 토류판을 철거하고 방수 및 방식하는 단계(S1000); 를 구비할 수 있다.The method of constructing the live precast manhole 10 according to an embodiment of the present invention includes a step of removing a road cut and a packing layer according to a size of a construction site requiring repair, and removing a existing manhole including a manhole cover and a manhole ); (S200) of arranging the ground floor after arranging and checking the location of the obstacle embedded in the underground and installing the bottom concrete 20; (100) having at least one hole (110) to be coupled with a manhole cover, a plurality of pillars (200) integrally formed with the top plate part (100) and precast concrete and supporting the top plate part (100) The through hole 300 is formed between the two pillars 200 and is exposed to one surface of the upper plate 100 and the column 200 on the side of the through hole 300 through which the obstacle passes, Placing (S300) a precast manhole (10) having an exposed reinforcing bar (400); A step (S400) of installing a steel plate (500) at a lower outer side of the plurality of columns (200); (S500) a compaction operation in a space between the lower inside of the installed installation place (30) and the steel plate (500); A step (S600) of installing a U-shaped steel and a soil plate (600) inside the plurality of columns (200); (S700) placing concrete in the installed installation place (30); A step S800 of performing a curing and back-up operation by supplying steam to maintain a temperature of 65 ° C to 75 ° C or using a heating device using a microwave; A manhole structure constructing and packaging step (S900) for constructing a structure such as a manhole cover, and packaging a road that has been erected; And a step (S1000) of removing and watering the soil plate installed inside the plurality of columns; .

여기서, 복수개의 기둥(200) 내측에 토류판(600)을 설치하는 단계(S600)는 이웃하는 2개의 기둥(200) 사이에 측벽철근(710)을 배근하는 단계(S610)와 배근 된 측벽철근(710)과 노출철근(400)을 연결하는 단계(S620)를 구비할 수 있다.The step S600 of installing the soil plate 600 inside the plurality of columns 200 includes a step S610 of placing the side wall reinforcing bars 710 between the adjacent two pillars 200 and a step 710 and the exposed reinforcing bar 400 (S620).

한편, 도면에는 도시하지 않았지만, 또한, 복수개의 기둥 내측에 설치된 토류판을 철거하고 방수 및 방식하는 단계(S1000)는 지장물이 통과하는 관로구(50)를 설치하는 단계를 구비하여 콘크리트가 타설된 후 지장물이 용이하게 통과홀(300)을 통과하도록 할 수 있다.Although not shown in the drawing, a step (S1000) for dismantling and waterproofing the earth plates installed on the inner side of the plurality of columns has a step of providing a channel 50 through which the obstacle is passed, So that the obstacle can be easily passed through the through hole 300.

또한, 활선 프리캐스트맨홀(10)을 안착시키는 단계(S300) 이전에는 상판부(100)에 프리캐스트맨홀(10)을 인양 및 안착하기 위한 고리(120)를 구비하는 단계가 구비되어 인양장치와 프리캐스트맨홀(10)을 쉽고 빠르게 연결할 수 있을 뿐만 아니라 인양장치가 들어올리는 힘이 특정부위에 많은 힘이 가해지는 것을 막아 활선 프리캐스트맨홀(10)이 파손되지 않도록 할 수 있다.Also, before the step S300 of seating the live-line precast manhole 10, a step of lifting and placing the precast manhole 10 in the top plate 100 is provided, It is possible to easily and quickly connect the cast manhole 10 and prevent the lifting force of the lifting device from being applied to a specific portion so that the live precast manhole 10 is not damaged.

상기와 같은 시공방법을 통해 보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선 상태를 유지하며 보수작업을 용이하게 실시할 수 있다.The maintenance work can be easily performed without damaging the obstacle such as the communication line, electric wire, and various pipelines installed at the installation place of the manhole requiring repair through the above-mentioned construction method.

이상에서는 본 발명의 일 실시 예에 따른 활선 프리캐스트맨홀 및 이의 시공방법에 대해 설명하였으나, 본 발명의 사상은 본 명세서에 제시되는 실시 예에 제한되지 아니한다. 그리고, 본 발명의 사상을 이해하는 당업자는 동일한 사상의 범위 내에서 구성요소의 부가, 변경, 삭제, 추가 등에 의해서 다른 실시 예를 용이하게 제안할 수 있을 것이나, 이 또한 본 발명의 사상범위 내에 든다고 할 것이다.Although the present invention has been described in connection with the above-described embodiments, it is to be understood that the subject matter encompassed by the present invention is not limited to the disclosed embodiments. Those skilled in the art, who understands the spirit of the present invention, can readily suggest another embodiment by adding, changing, deleting, or adding elements within the scope of the same idea, but this is also within the spirit of the present invention something to do.

10: 활선 프리캐스트맨홀 100: 상판부
200: 기둥 300: 통과홀
400: 노출철근 500: 스틸플레이트
600: 토류판 700: 측벽
800: 프리캐스트 측벽
10: live-line precast manhole 100: upper plate
200: column 300: through hole
400: exposed reinforcing steel 500: steel plate
600: dust plate 700: side wall
800: precast sidewall

Claims (9)

보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선 상태를 유지하며 보수작업을 실시할 수 있는 프리캐스트맨홀에 있어서,
맨홀 뚜껑과 결합하는 적어도 하나의 홀을 구비하는 상판부와,
상기 상판부와 프리캐스트콘크리트에 의해 일체로 형성되며 상기 상판부를 지지하는 복수개의 기둥과,
상기 이웃하는 2개의 기둥 사이에 형성되어 지장물이 통과하는 통과홀과,
상기 통과홀 측 상기 상판부 및 상기 기둥 일면에 노출되어 측벽 형성시 콘크리트에 매설되는 노출철근을 구비하고,
상기 복수개의 기둥 외측 하부에는 개착된 설치장소 내부 하측에 다짐작업을 하기 위한 스틸플레이트가 구비되는 것을 특징으로 하는 활선 프리캐스트맨홀.
The present invention relates to a precast manhole capable of performing maintenance work while maintaining a live state without damaging obstacles such as communication lines, electric wires, and various pipelines installed at a manhole installation site requiring maintenance,
An upper plate portion having at least one hole for engaging with the manhole cover,
A plurality of pillars integrally formed with the upper plate portion and the precast concrete and supporting the upper plate portion,
A through hole formed between the adjacent two pillars through which the barrier material passes,
And an exposed reinforcing bar that is exposed to the upper plate portion on the side of the through hole and embedded in the concrete when the side wall is formed,
And a steel plate for performing a compaction operation is provided in a lower portion inside the installation place installed in the outer side of the plurality of columns.
삭제delete 제 1항에 있어서,
상기 복수개의 기둥 내측에는 개착된 설치장소 내부에 콘크리트 타설을 하기 위한 토류판이 설치되는 것을 특징으로 하는 활선 프리캐스트맨홀.
The method according to claim 1,
And a soil plate for pouring concrete is installed inside the installation place inside the plurality of columns.
제 1항에 있어서,
상기 이웃하는 2개의 기둥 사이에서 프리캐스트콘크리트에 의해 일체로 형성되는 프리캐스트 측벽을 더 구비하는 것을 특징으로 하는 활선 프리캐스트맨홀.
The method according to claim 1,
Further comprising precast sidewalls integrally formed by precast concrete between the adjacent two columns. ≪ RTI ID = 0.0 > 11. < / RTI >
제 1항에 있어서,
상기 상판부에는 상기 프리캐스트맨홀을 인양 및 안착하기 위한 고리가 형성되는 것을 특징으로 하는 활선 프리캐스트맨홀.
The method according to claim 1,
Wherein the upper plate portion is formed with a ring for lifting and seating the precast manhole.
보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선 상태를 유지하며 보수작업을 실시하기 위한 활선 프리캐스트맨홀을 이용하는 시공방법에 있어서,
보수가 필요한 시공현장의 크기에 따라 도로 컷팅 및 포장층 제거와 맨홀뚜껑 및 맨홀목을 비롯한 기존맨홀을 철거하는 단계;
지하에 매설되어 있는 지장물의 위치를 확인하여 정리한 후 현장바닥을 정리하고 바닥콘크리트를 타설하는 단계;
맨홀 뚜껑과 결합하는 적어도 하나의 홀을 구비하는 상판부와, 상기 상판부와 프리캐스트콘크리트에 의해 일체로 형성되며 상기 상판부를 지지하는 복수개의 기둥과, 상기 이웃하는 2개의 기둥 사이에 형성되어 지장물이 통과하는 통과홀과, 상기 통과홀 측 상기 상판부 및 상기 기둥 일면에 노출되어 측벽 형성시 콘크리트에 매설되는 노출철근을 구비하는 프리캐스트맨홀을 안착시키는 단계;
상기 복수개의 기둥 외측 하부에 스틸플레이트를 설치하는 단계;
개착된 설치장소 내부 하측과 상기 스틸플레이트 사이 공간에 모래물 다짐작업을 하는 단계;
상기 복수개의 기둥 내측에 ㄷ형강 및 토류판을 설치하는 단계;
개착된 설치장소 내부에 콘크리트 타설을 하는 단계;
65℃ 내지 75℃의 온도를 유지하도록 하는 스팀을 공급하거나 마이크로웨이브를 이용하는 발열장치를 이용하여 양생 및 되메우기 작업이 시행되는 벽체 시공 및 되메우기 단계;
맨홀 뚜껑과 같은 구조물을 시공하고, 터파기된 도로를 포장하는 맨홀구조물 시공 및 포장 단계; 및
상기 복수개의 기둥 내측에 설치된 토류판을 철거하고 방수 및 방식하는 단계; 를 포함하는 활선 프리캐스트맨홀의 시공방법.
A construction method using a live precast manhole for performing maintenance work while maintaining a live state without damaging obstacles such as communication lines, electric wires and various pipelines installed at installation sites of repairing manholes,
Removing the road cutting and pavement layer according to the size of the construction site requiring repair, and removing the existing manhole including the manhole cover and the manhole;
Confirming the location of the obstacles buried in the basement, arranging the floor and laying the floor concrete;
A plurality of pillars formed integrally with the upper plate portion and the precast concrete and supporting the upper plate portion, and a plurality of pillars formed between the adjacent two pillars, Placing a precast manhole having a through hole passing through the through hole and the exposed reinforcing bars exposed in the upper plate portion and the one side of the column to form a sidewall when the sidewall is formed;
Installing a steel plate on the outside of the plurality of columns;
A sand compaction operation is performed in a space between an inside lower part of the installed installation place and the steel plate;
Installing a U-shaped beam and a current plate on the inside of the plurality of columns;
Placing concrete within the installed installation site;
A step of curing and backing the curing and refilling operation by supplying steam to maintain a temperature of 65 to 75 ° C or using a heating device using a microwave;
A step of constructing a manhole cover, and a step of constructing and packing a manhole structure for packing a road that has been erected; And
A step of dismantling, waterproofing and sanitizing the earth plates installed inside the plurality of columns; Wherein said method comprises the steps of:
제 6항에 있어서,
상기 복수개의 기둥 내측에 ㄷ형강 및 토류판을 설치하는 단계는 상기 이웃하는 2개의 기둥 사이에 측벽철근을 배근하는 단계와,
배근 된 상기 측벽철근과 상기 노출철근을 연결하는 단계를 구비하는 것을 특징으로 하는 활선 프리캐스트맨홀의 시공방법.
The method according to claim 6,
The step of installing the U-shaped steel and the earth plate on the inside of the plurality of columns includes the steps of arranging a side wall reinforcement between the adjacent two columns,
And connecting the reinforced side wall reinforcing bars to the exposed reinforcing bars.
제 7항에 있어서,
상기 복수개의 기둥 내측에 설치된 토류판을 철거하고 방수 및 방식하는 단계는 지장물이 통과하는 관로구를 설치하는 단계를 구비하는 것을 특징으로 하는 활선 프리캐스트맨홀의 시공방법.
8. The method of claim 7,
The method of claim 1, wherein the step of disposing and disposing the earth plates installed on the inner side of the plurality of columns comprises the step of providing a channel through which the obstacle is passed.
제8항에 있어서,
상기 프리캐스트맨홀을 안착시키는 단계 이전에는 상기 상판부에 상기 프리캐스트맨홀을 인양 및 안착하기 위한 고리를 구비하는 단계가 구비되는 것을 특징으로 하는 활선 프리캐스트맨홀의 시공방법.
9. The method of claim 8,
Wherein the pre-cast manhole is provided with a ring for lifting and seating the precast manhole on the upper plate before the step of seating the precast manhole.
KR1020150188024A 2015-12-29 2015-12-29 Live wire precast manhole and its construction method KR101624518B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150188024A KR101624518B1 (en) 2015-12-29 2015-12-29 Live wire precast manhole and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150188024A KR101624518B1 (en) 2015-12-29 2015-12-29 Live wire precast manhole and its construction method

Publications (1)

Publication Number Publication Date
KR101624518B1 true KR101624518B1 (en) 2016-05-26

Family

ID=56104840

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150188024A KR101624518B1 (en) 2015-12-29 2015-12-29 Live wire precast manhole and its construction method

Country Status (1)

Country Link
KR (1) KR101624518B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102170561B1 (en) * 2020-03-17 2020-10-27 (주)세정엔지니어링 Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert
KR20220035696A (en) * 2020-09-14 2022-03-22 안덕테크 주식회사 Piloti manhall and its construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200365985Y1 (en) * 2004-08-09 2004-10-28 두우균 up and down separating type pc culvert with welding connecting structure
JP2005042376A (en) * 2003-07-28 2005-02-17 Sumiken Concrete Kogyo Kk Manhole structure and its construction method
KR101524272B1 (en) * 2014-11-28 2015-06-10 대실테크 주식회사 A repairing assembled structure precast-manhole and constructing method it

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042376A (en) * 2003-07-28 2005-02-17 Sumiken Concrete Kogyo Kk Manhole structure and its construction method
KR200365985Y1 (en) * 2004-08-09 2004-10-28 두우균 up and down separating type pc culvert with welding connecting structure
KR101524272B1 (en) * 2014-11-28 2015-06-10 대실테크 주식회사 A repairing assembled structure precast-manhole and constructing method it

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102170561B1 (en) * 2020-03-17 2020-10-27 (주)세정엔지니어링 Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert
KR20220035696A (en) * 2020-09-14 2022-03-22 안덕테크 주식회사 Piloti manhall and its construction method
KR102447317B1 (en) * 2020-09-14 2022-09-26 안덕테크 주식회사 Piloti manhall and its construction method

Similar Documents

Publication Publication Date Title
CN108560684B (en) Heavy-load traffic road inspection well ring and construction method thereof
CN100482993C (en) Lay out method of pipeline and synthetic pipeline with pipe frame component
KR100926173B1 (en) Piping structure and method for constructing the same
KR101624518B1 (en) Live wire precast manhole and its construction method
KR20110132910A (en) Underpass using precast concrete pile and bottom slab and method for constructing the same
JP2004232328A (en) Structure of half precast type arch culvert and its construction method
JP4361839B2 (en) Construction method and structure of underpass road at intersection
CN109797776B (en) Construction method for underground pipe gallery to meet cross pipeline based on open cut method
JP5168697B2 (en) Small river bridge replacement method
KR101524272B1 (en) A repairing assembled structure precast-manhole and constructing method it
KR101682541B1 (en) Culvert crossing buried pipeline construction and pipeline laying method using the same
KR100872126B1 (en) trough and the construction method of this for cable laying under the ground
KR200409783Y1 (en) Supprot apparatus of drainage
KR101534641B1 (en) The method for constructing the basement
KR101377017B1 (en) Supporting means for hume pipe and forming means for waterway and the construction method
KR101117774B1 (en) Basic concrete structure of valve room and valve room embedding method using the same
JP2018059362A (en) Catch basin, u-shaped side gutter, and construction method
JP5288356B2 (en) How to connect existing piping and new piping in the manhole
JP2021102886A (en) Pedestrian road boundary block
KR102118064B1 (en) Uninterruptible construction method of high and low pressure uninterruptible junction box using recycled composite resin
CN109667278A (en) Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing
JP4630215B2 (en) Relocation method for buried objects
KR101318301B1 (en) Frame structure for underground structure and method of constructing underground structure using the same
KR102447317B1 (en) Piloti manhall and its construction method
JP4535480B2 (en) Removal method of underground structure

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
R401 Registration of restoration