KR101524272B1 - A repairing assembled structure precast-manhole and constructing method it - Google Patents

A repairing assembled structure precast-manhole and constructing method it Download PDF

Info

Publication number
KR101524272B1
KR101524272B1 KR1020140168342A KR20140168342A KR101524272B1 KR 101524272 B1 KR101524272 B1 KR 101524272B1 KR 1020140168342 A KR1020140168342 A KR 1020140168342A KR 20140168342 A KR20140168342 A KR 20140168342A KR 101524272 B1 KR101524272 B1 KR 101524272B1
Authority
KR
South Korea
Prior art keywords
manhole
construction
variable
precast
body portion
Prior art date
Application number
KR1020140168342A
Other languages
Korean (ko)
Inventor
유조웅
Original Assignee
대실테크 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대실테크 주식회사 filed Critical 대실테크 주식회사
Priority to KR1020140168342A priority Critical patent/KR101524272B1/en
Application granted granted Critical
Publication of KR101524272B1 publication Critical patent/KR101524272B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/122Steps or handrails for shafts

Abstract

The present invention relates to a field assembly type live line precast manhole for repair and a construction method thereof and, more specifically, to a field assembly type live line precast manhole for repair and a construction method thereof capable of installing the precast manhole in consideration of site conditions, such as the position, direction, and height of obstructions, while preventing the shifting construction, damage, and position deviation of the obstructions, and assembling the precast manhole in the site to be easily installed. The field assembly type live line precast manhole for repair comprises a variable body part (10) which is a foundation of a steel frame and a precast upper plate part (20) coupled to the top of the variable body part (10). A method to construct a field assembly type live line precast manhole for repair comprises: a step of excavating the site (S10); a step of checking the continuous footing and excavation of an installation place (S20); a step of disassembling an existing structure and arranging facilities (S30); a step of constructing a foundation and a new structure (S40); and a step of constructing walls and filling back soils around the walls (S50); a step of installing a cut-off plate and coupling a precast (PC) upper plate (S60); a step of constructing and paving the manhole structure (S70); and a step of removing forms and finishing the construction (S80).

Description

보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법{A REPAIRING ASSEMBLED STRUCTURE PRECAST-MANHOLE AND CONSTRUCTING METHOD IT}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast manhole and a method of constructing the precast manhole,

본 발명은 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법으로서, 지하에 매설되어 있는 지장물을 현장 여건에 따라 지장물의 위치, 방향, 높이를 감안하여 이설하지 않고 파손되거나 위치 이탈됨을 방지하며, 용이하게 설치할 수 있도록 현장에서 조립하는 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법에 관한 것이다.
The present invention relates to a field prefabricated manhole for repairing and a method of constructing the same, and more particularly, it relates to a prefabricated manhole for repairing, and a construction method of the same, which prevents a breakwater buried underground from being broken or displaced without considering a location, To a prefabricated prefabricated prefabricated manhole for repair and to a method of construction thereof.

일반적으로 상.하수도관, 도시 가스관, 소화전, 지역 난방관, 송유관, 전력선, 통신 케이블 등을 지하에 매설할 경우에는 일정한 지역에 맨홀을 설치한다. 그 중에서 전력선용 맨홀은 도로가 분기되는 지점, 관로가 분기되는 지점, 관로가 허용 곡률 이상으로 굴곡되어야 할 경우, 급경사 언덕길, 긴교량의 전.후, 및 케이블의 접속 또는 분기 장소에 설치된다.
Generally, a manhole should be installed in a certain area when it is buried underground, sewage pipe, city gas pipe, fire hydrant, district heating pipe, oil pipeline, power line, Among them, manholes for electric power lines are installed at the points where the roads diverge, where the ducts diverge, when the ducts must be bent beyond the allowable curvature, before and after the steep slopes, before and after the long bridges,

전력선용 맨홀을 지하에 설치할 경우에는 주로 현장에서 콘크리트를 타설하여 맨홀을 시공하는 현장 타설식 공법을 채택한다. 그러나, 상기 현장 타설식 공법은 현장에서 모든 작업이 이루어져야 하므로 모든 장비를 현장으로 옮겨 작업을 해야하는 어려움이 있고, 시공 기간이 길고 현장의 교통 혼잡이 발생되는 단점이 있다.When a manhole for a power line is installed underground, a concrete installation method is used to install a manhole mainly in the field. However, the above-mentioned field-borne construction method has a disadvantage in that all the work must be performed in the field, so it is difficult to carry out all the equipment to the site, and the construction period is long and traffic congestion occurs on the site.

한편, 조립식 공법은 벽체, 상부 슬래브, 하부 바닥 등을 미리 제작한 후 현장에서 조립하는 공법인데, 현장 타설식에 비해 공사 기간을 단축할 수는 있지만 조립되는 부품의 연결 부위마다 수팽창 지수제 등으로 방수처리를 해야 하는 어려움이 있다. On the other hand, the prefabrication method is a method of prefabricating the wall, the upper slab, the bottom floor, etc., and assembling them in the field. It is possible to shorten the construction period compared to the field installation method. However, It is difficult to carry out waterproofing treatment.

상기 조립식 공법은 대한민국 공개 특허 제10-2001-0023607호(맨홀 설치 공법, 이하 '선행기술 1' 이라 함)에 개시되어 있다.
The prefabricated construction method is disclosed in Korean Patent Laid-Open No. 10-2001-0023607 (manhole installation method, hereinafter referred to as "Prior Art 1").

최근에는 현장 타설식 공법과 조립식 공법의 단점을 보완하기 위하여 상.하수도 또는 집수정 등에 사용되는 맨홀을 프리캐스트 콘크리트로 제작하고 있다.In recent years, manholes are used as precast concrete to be used for sewage, sewage, or house improvement to compensate for the disadvantages of on-site construction methods and prefabricated construction methods.

상기 프리캐스트 콘크리트 맨홀은 공장에서 철저한 품질 관리가 가능하므로 품질이 균일한 장점이 있다. 또한, 시공시에는 시공 기간이 단축되고 시공 후에도 즉시 되메우기 작업을 할 수 있으므로 교통 혼잡과 시민의 불편을 최소화 할 수 있다.The precast concrete manhole can be thoroughly controlled in quality at the factory, which is advantageous in that the quality is uniform. In addition, the construction period can be shortened at the time of construction, and it is possible to immediately work back after construction, which can minimize traffic congestion and inconvenience of citizens.

그러나, 이러한 프리캐스트 맨홀을 대형으로 제작할 경우에는 몰드의 제작 및 콘크리트 타설에 많은 어려움이 있고, 더욱이 몰드를 일체형으로 만들어 콘크리트를 타설할 경우에는 몰드에 콘크리트를 타설할 공간이 협소하여 제작하는데 어려움이 있다. 즉, 콘크리트를 타설할 공간이 부족하여 한정된 곳에서 콘크리트를 타설하기 때문에 몰드의 구석구석까지 콘크리트가 미치지 않는 경우가 있다. 이러한 문제는 고강도 콘크리트의 경우에 유동성이 부족하기 때문에 더욱 심각하다. 또한, 몰드를 일체형으로 만들어 콘크리트를 타설할 경우에는 전체 중량이 매우 크기 때문에 진동을 가하기가 어렵고 진동의 영향이 제품 전체에 고르게 미칠 수 없게 되는 문제점이 있다.
However, when such precast manholes are manufactured in a large size, there is a great difficulty in the production of molds and concrete pouring, and in the case of pouring concrete by making the molds integral, it is difficult to produce concrete with a small space for pouring concrete into the molds have. In other words, because there is not enough space to place the concrete, concrete is placed in a limited place. Therefore, the concrete may not reach every corner of the mold. This problem is more serious because of the lack of fluidity in the case of high strength concrete. In addition, when the mold is integrally formed and the concrete is poured, the weight of the concrete is very large, so that it is difficult to apply vibration and the influence of the vibration can not be evenly distributed throughout the product.

한편, 지중 배전용 맨홀은 직선 구간에 적용되는 A형과, 90˚ 굴곡 구간에 적용되는 B형과, 45˚정도의 굴곡 구간에 적용되는 C형과, 1 방향 분기 지점에 사 용되는 D형과, T형 분기 지점에 적용되는 1E형, 및 4 방향 분기 지점에 적용되는 2E형이 있다. On the other hand, the underground manhole can be classified into two types: A type applied to the straight section, B type applied to the 90 ° bending section, C type applied to the bending section of about 45 °, and D type Type 1E applied to the T-type branch point, and 2E type applied to the 4-way branch point.

이 중에서, B형 또는 C형 지중 배전용 맨홀의 한쪽 벽체에는 관로구가 형성되어 있지 않다. 따라서, 기 설치된 B형 또는 C형 맨홀에 신규로 관로구를 형성하는 작업은 매우 어려운 문제이고, 또한 지형상의 문제 또는 공간이 협소하여 D형 또는 E형을 사용할 수 없는 경우에는 B형 또는 C형 맨홀을 사용해야 한다. 이러한 경우에도 관로구가 형성되지 않은 벽체 쪽으로 관로를 설치하는 것도 어려운 문제점이 있다.
Of these, a channel is not formed in one wall of the B type or C type underground manhole. Therefore, it is very difficult to form a new channel on the previously installed B-type or C-type manhole, and when the D-type or E-type can not be used because of a problem in the topography or a narrow space, Should be used. Even in such a case, it is also difficult to install the pipeline on the wall side where the piping is not formed.

상기와 같은 문제점을 보완하기 위해 이에 다양한 기능의 시멘트콘크리트로 구조물을 성형한 후, 시공현장에 설치하는 프리캐스트 콘크리트(Precast Concret, 통상 'PC'라 함.)공법과 관련된 기술이 개발되고, 이중 대한민국 공개 특허 제10-2001-0078879호(프리캐스트 콘크리트로 제작된 전력맨홀의 체결구조, 이하 '선행기술 2'이라 함.)In order to solve the above problems, there has been developed a technique relating to a precast concrete (commonly referred to as PC) method in which a structure is formed from various functions of cement concrete and then installed in a construction site. Korean Patent Publication No. 10-2001-0078879 (fastening structure of power manhole made of precast concrete, hereinafter referred to as "prior art 2").

대한민국 공개 특허 제10-1995-0024255호(합성거더의 상판을 프리캐스트 구조체으로 바꿀때 발생하는 메인거더 붕괴의 방지공법, 이하 '선행기술 3'이라 함.)Korean Patent Laid-Open No. 10-1995-0024255 (Prevention Technique for Preventing Collapse of Main Girders Occurring When Precast Structure of Composite Girder is Replaced by Precast Structure, hereinafter referred to as Prior Art 3)

대한민국 공개 특허 제10-1999-0044192호(맨홀의 설치방법 및 그 맨홀, 이하 '선행기술 4'이라 함.)
Korean Patent Laid-Open No. 10-1999-0044192 (How to install a manhole and its manhole, hereinafter referred to as "Prior Art 4")

그러나, 이러한 종래기술은 지하에 매설되어 있는 지장물을 옮겨 설치하는 등의 과도한 시공기간 및 경비를 지출하게 되는 문제점이 있으며, 또한 시공기간이 길어지면 도로를 차단시키고 공사를 진행해야하므로 장시간 도로를 이용하는 이용자의 불편이 초래되는 문제점이 있다.
However, this conventional technique has a problem that excessive construction period and expense are incurred such as moving the obstacles buried in the underground, and when the construction period becomes longer, the roads must be shut off and construction must be carried out. There is a problem that inconvenience of the user who uses it occurs.

본 발명은 상기와 같은 문제점을 해소하기 위해 발명된 것으로, 지하에 복잡하게 매설되어 있는 지장물 이설 또는 파손없이 시설물의 기능유지 즉, 활선상태에서 시공이 용이하며, 프리캐스트 공법을 적용하여 공정시간을 단축할 수 있는 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법을 제공하는 것이다.SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems and it is an object of the present invention to provide a method and apparatus for maintaining the function of a facility without being damaged or broken, Which can be shortened, and a method of constructing the pre-cast manhole.

본 발명의 또다른 목적은 시공현장의 굴착면적 및 굴착량을 최소화 하여, 교통흐름의 장애를 최소화하고 시공경비를 절감할 수 있는 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법을 제공하는 것이다.
It is still another object of the present invention to provide a field prefabricated prefabricated manhole for repairing which minimizes the obstruction of traffic flow and minimizes the construction cost by minimizing the excavation area and excavation amount at the construction site and a method of construction thereof.

상기와 같은 목적을 달성하기 위한 보수용 현장조립식 활선 프리캐스트맨홀은 철골기초가 되는 가변형몸체부(10)와 상기 가변형몸체부(10)의 상단에 결합되는 프리캐스트하여 완성되는 상판부(20)로 구성되는 것을 특징으로 하는 보수용 현장조립식 활선 프리캐스트맨홀을 제공하게 된다.
In order to achieve the above-mentioned object, a maintenance prefabricated prefabricated manhole for repairing comprises a movable body 10 as a steel frame foundation and a top plate portion 20 completed by precast joining to the upper end of the movable body 10 The present invention provides a prefabricated prefabricated manhole for a maintenance work.

여기서, 상기 가변형몸체부(10)는 상판부(20)를 지지하기 위한 상측프레임(11)과 상기 상측프레임(11)의 하단부 각각의 모서리에 수직방향으로 설치되는 기둥부(12)와 상기 기둥부(12)의 하단에 결합되는 하측프레임(13)으로 구성되되, 다수개의 철골부재를 연결부재(30)를 이용하여 결합하여 입방체 형상으로 형성되고, 상기 가변형몸체부(10)의 측면에는 지장물의 위치이탈 및 처짐현상을 방지하기 위한 지장물거치대(14)가 더 구비된다.
The variable body portion 10 includes an upper frame 11 for supporting the upper plate portion 20 and a column portion 12 disposed in a direction perpendicular to a corner of the lower end of the upper frame 11, And a lower frame 13 coupled to a lower end of the movable body 12, wherein a plurality of steel members are coupled to each other using a connecting member 30 to form a cubic shape, And an obstacle holding stand 14 for preventing displacement and deflection phenomenon is further provided.

또한, 상기 가변형몸체부(10)는 현장상황에 따라 복수개의 입방체 형상으로 연장가능한 것을 특징으로 하는 보수용 현장조립식 활선 프리캐스트맨홀을 제공하게 된다.
Also, the variable body portion 10 can be extended in a plurality of cubes depending on the situation of the site.

상기와 같은 프리캐스트맨홀을 이용하는 시공방법에 있어서, 보수가 필요한 시공현장의 크기에 따라 도로컷팅 및 아스팔트 제거와 기초시설인 맨홀뚜껑 및 맨홀목을 철거하는 시공현장 터파기 단계(S10), 상기 시공현장 터파기 단계(S10) 후 지하에 매설되어 있는 전기배선 및 상하수도 시설과 같은 지장물의 위치를 확인하기 위한 설치장소 줄기초 터파기 확인 단계(S20), 상기 줄기초 터파기 확인 단계(S20) 후 시공현장에 있는 지장물 및 설치되어 있는 구조물 등을 철거하고 작업이 용이하게 정기하는 구조물 철거 및 시설물 정리 단계(S30), 상기 구조물 철거 및 시설물 정리 단계(S30) 후 현장바닥 정리 및 바닥 콘크리트 시공후 가변형몸체부(10)를 현장에서 보수하거나 현장에서 제작된 가변형몸체부(10)를 시공 현장에 설치하는 기초 및 구조물시공 단계(S40), 상기 기초 및 구조물시공 단계(S40) 후 설치된 가변형몸체부(10)의 벽체를 시공하기 위해, 벽체용 철근 배근 및 거푸집 설치와 함께 콘크리트타설 후 양생 및 되메우기 작업이 시행되는 벽체 시공 및 되메우기 단계(S50), 상기 벽체 시공 및 되메우기 단계(S50) 후 가변형몸체부(10)의 상단에 지수판을 설치한 후, 프리캐스트 된 상판부(20)를 결합하는 지수판설치 및 PC상판 결합 단계(S60), 상기 지수판설치 및 PC상판 결합단계(S60) 후 맨홀 뚜껑과 같은 구조물을 시공하고, 터파기된 도로를 포장하는 맨홀구조물 시공 및 포장 단계(S70) 및 벽체용 거푸집을 제거하고, 방수처리하는 거푸집 제거 및 마감 단계(S80)로 구성되는 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법을 제공한다.In the construction method using the precast manhole as described above, a construction site disposal step (S10) for removing the road cutting and asphalt removal and the manhole cover and the manhole, which are foundations, according to the size of the construction site requiring repair, (S20) for confirming the location of the obstacle such as the electric wiring and the water supply and drainage facility buried in the basement after the trenching step (S10), the step (S20) (S30), demolishing the structure and demolishing the structures and the installed structures in the construction site and arranging the work easily, after the demolition of the structure and arranging the facilities (S30) A base and structure construction step (S40) in which the variable-shape body portion 10 is repaired in situ or the variable-shape body portion 10 manufactured in the field is installed on a construction site ), A step of constructing a wall of the flexible body 10 installed after the foundation and structure construction step (S40), a step of installing a reinforcing steel for a wall and a formwork, and a step of curing and backfilling (S50), installing a waterproofing plate on the upper end of the flexible body 10 after the wall construction and backfilling step (S50), attaching a pre-casted upper plate 20 to the upper plate, After the step of installing the water level plate and PC top plate (S60), a structure such as a manhole cover is constructed, and a manhole structure construction and packaging step (S70) for packing the road surface is performed, and a mold for a wall is removed, And a finishing step (S80). ≪ IMAGE >

여기서, 상기 설치장소 줄기초 터파기 확인 단계(S20)는 시공장소의 지하에 매설되어 있는 전기배선 및 상하수도 시설물과 같은 지장물의 실제 설치위치 및 범위를 파악하기 위하여 지장물의 설치방향 즉, 길이방향을 따라 추가 터파기 작업을 더 수행하고, 상기 기초 및 구조물시공 단계(S40)에서 시공현장에 가변형몸체부(10)의 기둥부(12)가 위치할 자리에 기초PC블럭을 설치한 후 버림콘크리트를 타설하거나, 기초PC블럭 설치없이 바로 버림콘크리트를 타설하며, 상기 벽체 시공 및 되메우기 단계(S50)에서 가변형몸체부(10)에 벽체를 시공한 후 스팀을 공급하거나 마이크로웨이브를 이용하는 발열장치를 이용하여 양생시키는 것을 특징으로 한다.
Here, in the step S20 of confirming the installation location of the installation site, in order to determine the actual installation location and range of the obstacle such as the electric wiring and the water supply and drainage facilities buried under the construction site, In addition, in the foundation and structure construction step (S40), a foundation PC block is installed in a place where the column portion 12 of the variable-shape body portion 10 is to be placed at the construction site, Or the concrete is poured directly without installing the base PC block. In the step of constructing and backing the wall, the wall is constructed in the variable body portion 10, and then steam is supplied or a heating device using microwave is used And curing.

또한 상기 벽체에 공급하는 스팀은 65℃ 내지 75℃의 온도를 유지하도록 하는 것을 특징으로 하는 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법을 제공함으로써 본 발명의 목적을 달성할 수 있는 것이다.
And the steam to be supplied to the wall is maintained at a temperature of 65 ° C to 75 ° C. The object of the present invention can be achieved by providing a method of constructing a prefabricated manhole for maintenance work.

본 발명의 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법을 제공함으로써, 종 방향 및 횡 방향으로 지하에 매설되어 있는 지장물을 현장 여건에 따라 지장물의 위치, 방향, 높이를 감안하여 지장물을 이설하지 않고 시공할 수 있으며, 또한 지장물이 파손되거나 위치 이탈 없이, 시설물의 사용기능을 중단 없이 유지하면서 시공될 수 있으며, 시공이 용이하며 연속작업으로 인해 공정시간을 단축하고, 굴착면적 및 굴착량을 최소화할 수 있으므로 교통의 장애를 최소화하고 경비를 절감할 수 있는 효과를 제공하게 된다.
The present invention provides a pre-cast manhole for repairing a live precast casting manhole and a method of construction thereof, which can prevent the obstacles buried in the underground in the longitudinal direction and the transverse direction from damaging the obstacle in consideration of the location, It is possible to construct without disruption, without damaging or dislocating the obstacle, to keep the use function of the facility uninterrupted, to be easy to construct, to shorten the process time due to continuous operation, It is possible to minimize the obstacle of traffic and reduce the cost.

또한, 맨홀의 규격 및 현장 여건에 따라 맨홀의 크기를 확장해야 할 경우에도 보수용 현장조립식 활선 프리캐스트맨홀을 구성하는 몸체부에 연결부재가 볼트와 너트로 간단히 고정 결합되어 용이하게 연장 설치가 가능한 장점이 있다.
Also, even if the size of the manhole needs to be enlarged according to the manhole standard and site conditions, the connecting member can be easily fixedly connected to the body portion constituting the prefabricated prefabricated manhole for repairing by the bolt and nut, There are advantages.

도 1은 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 사시도이다.
도 2는 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 분해사시도이다.
도 3은 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 가변형몸체부의 사시도이다.
도 4는 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 가변형몸체부의 실시예를 도시한 도면이다.
도 5는 본 발명의 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법에 대한 순서도이다.
도 6은 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 설치예시도이다.
1 is a perspective view of a field prefabricated live precast manhole for repair of the present invention.
2 is an exploded perspective view of a field prefabricated live precast manhole for repair of the present invention.
3 is a perspective view of a variable body portion of a field prefabricated live precast manhole for repair of the present invention.
4 is a view showing an embodiment of a variable-type body portion of a field prefabricated live precast manhole for repairing the present invention.
FIG. 5 is a flowchart of a method of constructing a live pre-cast manhole for repair in the present invention.
6 is a view illustrating the installation of a field prefabricated live precast manhole for repairing the present invention.

이하에서 당업자가 본 발명의 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법을 용이하게 실시할 수 있도록 도면을 참조하여 설명하도록 한다.
Hereinafter, persons skilled in the art will be described with reference to the drawings so as to easily carry out the field prefabricated prefabricated manhole for repair and the method of construction thereof according to the present invention.

도 1은 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 사시도이고, 도 2는 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 분해사시도이고, 도 3은 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 가변형몸체부의 사시도이며, 도 4는 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 몸체부의 실시예를 도시한 도면이다.
FIG. 1 is a perspective view of a live pre-cast manhole for repairing the present invention, FIG. 2 is an exploded perspective view of a field prefabricated live pre-cast manhole for repair of the present invention, and FIG. 3 is a perspective view of a movable pre- FIG. 4 is a view showing an embodiment of a body part of a field prefabricated live pre-cast manhole for repairing the present invention. FIG.

도 1 내지 도 4를 참조하여 상세하게 설명하면, 보수용 현장조립식 활선 프리캐스트맨홀은 철골기초가 되는 가변형몸체부(10)와 상기 가변형몸체부(10)의 상단에 현장에서 결합되는 프리캐스트 상판부(20)로 구성된다.
1 to 4, a maintenance prefabricated live precast casting manhole comprises a variable-type body portion 10 serving as a steel-frame foundation and a precast upper plate portion 10 jointed at the top of the variable- (20).

상기 가변형몸체부(10)는 상판부(20)를 지지하기 위한 상측프레임(11)과 상기 상측프레임(11)의 하단부 각각의 모서리에 수직방향으로 설치되는 기둥부(12)와 상기 기둥부(12)의 하단에 결합되는 하측프레임(13)으로 구성되는 입방체 형상으로 형성된다.
The variable body portion 10 includes an upper frame 11 for supporting the upper plate portion 20 and a column portion 12 provided in a direction perpendicular to an edge of the lower end portion of the upper frame 11, And a lower frame 13 coupled to a lower end of the lower frame 13.

또한, 상기 가변형몸체부(10)의 상측에 현장에서 결합되는 상판부(20)는 철근과 콘크리트 및 강재를 혼합하여 성형하되 중앙부에 홀(21)이 형성되도록 한다.
The upper plate portion 20 coupled to the upper portion of the variable body portion 10 at the site is formed by mixing the reinforcing bars, concrete, and steel material, and the holes 21 are formed at the center portion.

이와 같은 상판부(20)는 프리캐스트공법을 이용하여 제조한 후, 시공현장에서 가변형몸체부(10)에 결합되도록 하는 것이다.
The upper plate 20 is manufactured by using the precast method, and is then coupled to the variable-shape body 10 at the construction site.

상기와 같은 가변형몸체부(10)에는 지하에 매설되어 있는 지장물이 작업공정 중 설치위치에서 이탈되지 않도록 하기 위해, 지지될 수 있는 지장물거치대(14)가 더 구비된다.The variable body portion 10 is further provided with a supporting device 14 which can be supported to prevent the supporting device embedded in the underground from being detached from the installation position during the operation process.

이때, 상기 지장물거치대(14)는 가변형몸체부(10)의 각각의 기둥부(12)의 사이에 수평방향으로 구비되는데, 보다 상세하게 설명하면, 일개의 기둥부와 상기 기둥부와 인접한 또다른 기둥부의 사이에 지장물거치대(14)의 각각의 단부가 결합되어 형성된다.At this time, the supporting device 14 is horizontally disposed between the pillars 12 of the variable-type body 10. More specifically, the pillars 12 and the pillars 12, which are adjacent to the pillars, And each of the ends of the barrier cage 14 is formed between the other pillars.

이와 같은 지장물거치대(14)는 현장 상황에 따라 가감여부가 달라지게 되며, 이는 현장에 설치되어 있는 지장물의 수에 따라 시공현장에서 선택하여 적용할 수 있는 것이다.
Such an obstacle cradle 14 can be selected depending on the number of obstacles installed on the site.

상기와 같은 가변형몸체부(10)는 지하에 매설되어 있는 지장물이 파손되거나 위치 이탈을 방지함과 동시에 활선상태를 유지하고, 시공을 위한 작업자의 작업공간 확보를 위해 다양한 단면형상(예로써, H, I 등의 단면형상)을 가진 다수개의 철골부재가 결합되어 형성된다. (본 발명의 도면에서는 이해를 돕기 위하여 H 단면형상으로 도시하였으나, 이에 한정되는 것은 아니다.)
The variable-shape body 10 may have various cross-sectional shapes (for example, a curved shape, a curved shape, a curved shape, a curved shape, a curved shape, H, I, and the like) are combined with each other. (In the drawings of the present invention, for the sake of better understanding, it is shown in an H-sectional shape, but it is not limited thereto.)

이러한 가변형몸체부(10)의 구조를 보다 상세하게 설명하면, 4개의 철골부재의 단부를 연결하여 사각형상으로 형성되는 상부프레임(11)을 형성하고, 상기 상부프레임(11)의 하부면 각각의 모서리에 4개의 철골부재를 수직방향으로 고정 결합하여 기둥부(12)를 형성하고, 상기 기둥부(12)의 하측방향으로 상부프레임(11)과 동일한 형상으로 4개의 기둥부(12)의 단부를 연결하여 사각형상으로 형성되는 하부프레임(13)을 결합하여 완성하게 된다.
The structure of the variable body portion 10 will be described in more detail. An upper frame 11 is formed by connecting end portions of four steel members to form a rectangular shape. Four columnar members are vertically fixedly coupled to each other at the corners to form the columns 12 and the lower ends of the four pillars 12 are formed in the same shape as the upper frame 11 in the lower direction of the columns 12, And the lower frame 13, which is formed in a rectangular shape, is connected and completed.

이때, 상기 가변형몸체부(10)는 현장 상황에 따라 다양한 형태로 변형가능하며, 본 발명의 바람직한 실시예를 설명하기 위해, 1개의 입방체 형상을 기준으로 설명하고 있으나 이를 한정하는 것은 아니다.In this case, the variable-shape body 10 can be modified into various shapes according to the field conditions. In order to describe the preferred embodiment of the present invention, one cube shape is used as a reference, but the present invention is not limited thereto.

이는 시공현장의 지장물의 배치 및 갯수 등에 따라 현장에서 추가적으로 변형이 가능하기 때문이다.
This is because additional modifications can be made on site depending on the arrangement and number of obstacles at the construction site.

또한, 상기 상부프레임(11)과 하부프레임(13)의 형상은 각을 이루는 정사각, 직사각, 사다리꼴, 오각, 육각, 팔각 등의 다각을 갖는 형상이면 변형이 가능하고, 상기 기둥부(12)의 경우 상부프레임(11)과 하부프레임(13)의 형상에 따라 각이 형성되는 모서리 부위에 모두 설치 가능한 것이다.
The shape of the upper frame 11 and the lower frame 13 can be deformed as long as the shape of the upper frame 11 and the lower frame 13 has a polygonal shape such as a square angle, a rectangle, a trapezoid, a pentagon, a hexagon, It can be installed at the corner where the angle is formed according to the shape of the upper frame 11 and the lower frame 13.

또한, 상기 다수개의 철골 기둥들이 결합되어 형성되는 가변형몸체부(10)는 철골부재를 이용하여 입방체를 형성할 때, 각각의 철골부재간에 연결부재(30)를 이용하여 결합하게 된다.In addition, when the cube is formed by using the steel frame member, the variable body portion 10 formed by joining the plurality of steel column members is coupled using the connecting member 30 between the steel frame members.

상기와 연결부재(30)는 "ㅡ", "ㄱ", "ㄴ", "ㄷ" 등의 다양한 형상으로 구비되고, 철골부재와 인접하는 철골부재 사이에 덧대여 맞닿는 위치에 연결홀(31)을 형성하여 볼트와 너트로 고정 결합하는 것이다.
The connecting member 30 is provided in various shapes such as "a", "a", "b", and "c" And the bolts and nuts are fixedly coupled.

또한, 현장 여건에 따라 가변형몸체부(10)의 크기를 확장해야 할 경우에도 가변형몸체부(10)의 일측 철골부재와 연장될 철골부재 사이에 덧대여 용이하게 연장 설치가 가능한 것이다.(도 4 참조)
Further, even when the size of the variable-shape body part 10 is to be enlarged according to the site conditions, it can be extended easily between one steel member of the variable-type body part 10 and the steel member to be extended. Reference)

이와 같은 철골부재와 연결부재는 현장상황에 따라 용접 등의 결합방법을 적용하기도 한다.
Such steel members and connecting members may be combined with welding methods depending on the field conditions.

상기와 같은 가변형몸체부(10)의 상측에 결합되는 상판부(20)는 시공현장에서 작업자가 작업을 위해 맨홀의 내부로 진출입할 수 있고, 시공 후 뚜껑 등의 맨홀부재가 결합될 수 있는 홀(21)이 형성하며, 가변형몸체부(10)와 현장에서 결합하게 된다.The upper plate portion 20 coupled to the upper side of the variable body portion 10 as described above can be moved into and out of the inside of the manhole for work by the operator at the construction site, 21, and is engaged with the variable body portion 10 in the field.

이때, 상기 가변형몸체부(10)와 상판부(20)는 체결볼트 등의 결합부재를 이용하여 현장에서 결합하여 완성하는 것이며, 현장시공시 가변형몸체부(10)와 상판부(20)의 사이에는 수밀 및 완충역할을 하기 위한 수팽창지수판(미도시)이 더 구비된다.At this time, the variable body portion 10 and the upper plate portion 20 are joined together in the field by using a coupling member such as a fastening bolt, and a watertight seal is formed between the flexible body portion 10 and the upper plate portion 20 And a water expansion plate (not shown) to serve as a buffer.

이는 현장시공시 프리캐스트되어 성형된 상판부(20)와 가변형몸체부(10)의 시공오차를 감소시키게 되는 것이다.This reduces the construction errors of the formed upper plate portion 20 and the deformable body portion 10 by precasting at the time of field construction.

또한, 상기 가변형몸체부(10)와 상판부(20)의 체결시 접합면의 대응위치에 동일한 결합홀(15)을 형성하여 볼트체결 하거나, 현장에서 상판부(20)에 천공시켜 결합홀(15)을 대체하기도 하는 것이다.
The coupling hole 15 may be formed at a corresponding position of the joint surface when the variable body 10 and the upper plate 20 are fastened to each other, .

상기와 같이 가변형몸체부(10)와 상판부(20)를 현장상황에 맞게 결합한 후, 콘크리트 주입 등을 통하여 내벽 설치 등의 작업을 마무리 하여 보수용 현장조립식 활선 프리캐스트맨홀을 적용하여 맨홀 보수를 완료하게 된다.
As described above, after fitting the flexible body 10 and the upper plate 20 according to the circumstances, the work such as the installation of the inner wall is completed through concrete injection and the like, and a manhole repair is performed by applying a field prefabricated prefabricated manhole for repairing .

도 5는 본 발명의 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법에 대한 순서도이고, 도 6은 본 발명 보수용 현장조립식 활선 프리캐스트맨홀의 설치예시도이다.
FIG. 5 is a flowchart illustrating a method of constructing a live pre-cast manhole for repair according to the present invention, and FIG. 6 is a view illustrating an installation example of a field pre-assembled live precast manhole for repairing the present invention.

도 5와 도 6을 참조하여 상세하게 설명하면, 본 발명의 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법은 시공현장 터파기 단계(S10), 설치장소 줄기초 터파기 확인 단계(S20), 구조물 철거 및 시설물 정리 단계(S30), 기초 및 구조물시공 단계(S40), 벽체 시공 및 되메우기 단계(S50), 지수판설치 및 PC상판 결합 단계(S60), 맨홀구조물 시공 및 포장 단계(S70) 및 거푸집 제거 및 마감 단계(S80)로 구성된다.
5 and 6, the method for constructing the field pre-cast manhole for repair according to the present invention comprises the step of constructing the construction site (S10), the step of confirming the location of the installation site (step S20) (Step S30), the wall construction construction and backfill step (S50), the water level installation and PC top plate combination step (S60), the manhole structure construction and packaging step (S70), and the mold removal And a finishing step S80.

상기 시공현장 터파기 단계(S10)는 차량 및 보행자의 안전한 통행을 위한 안전확보 후 보수가 필요한 맨홀이 설치되어 있는 시공현장의 크기에 따라 도로컷팅 후, 아스팔트 표층 및 기층 등을 제거한 후 기초시설인 맨홀뚜껑 및 맨홀목 등을 철거하는 과정이다.
The construction site disposal step (S10) is a step of removing the asphalt surface layer and the base layer after the road cutting according to the size of the construction site in which the manhole requiring repair is secured after ensuring safety for safe passage of the vehicle and the pedestrian, It is a process to remove manhole cover and manhole.

상기 시공현장 터파기 단계(S10)가 마무리 된 후 설치장소 줄기초 터파기 확인 단계(S20)를 거치게 된다.After the construction site disposal step S10 is completed, the installation site disposal site disposal confirmation step S20 is performed.

상기 줄기초 터파기 확인 단계(S20)는 상기 시설현장 터파기 단계(S10)에서 도로 및 맨홀 등의 기초시설물을 철거한 후, 지하에 매설되어 있는 전선 및 각종 배관 등의 지장물이 매설되어 있는 범위 등을 파악하기 위하여 줄기초 터파기 확인 단계(S20)를 거치게 된다.In the step S20, the substation grounder dismantles the substructures such as roads and manholes in the facility site disposal step S10, and then disposes obstacles such as electric wires embedded in the grounds and various pipes And the step of confirming the row grounding tester (S20) is performed in order to grasp the range and the like.

보다 상세하게 설명하면, 시공현장 터파기 후, 지장물의 설치방향 즉, 길이방향을 따라 추가 터파기 작업을 더 수행하는 것이다.
More specifically, after the construction site is destroyed, additional trenching work is further performed along the installation direction of the obstacle, that is, the longitudinal direction.

이는 기존에 매설되어 있는 전기배선 및 상·하수도 시설물과 같은 지장물이 오랜시간 동안 증설 또는 가설되면서 초기에 설치된 맨홀의 범위를 넘는 경우가 대부분이기 때문에 실제 설치되어 있는 지장물의 범위를 파악하여, 맨홀의 규격을 확정하기 위한 것이다.This is because most of the obstacles such as electric wiring and water and sewage facilities buried in the past are extended or installed over a long period of time, In order to confirm the specifications of the apparatus.

이와 같이 줄기초 터파기 확인 단계(S20)를 통하여 종래의 프리캐스트 맨홀을 이용한 보수작업시 설치되어 있는 맨홀의 규격에 따라 시공전에 제조되어 현장에서 설치할 때, 증설 또는 가설된 지장물이 새로 설치되는 보수용 맨홀에 포함되지 않는 문제점 및 지장물을 보수용 맨홀에 포함되도록 하기 위해 신설 또는 보수를 위해 절단 등의 과정없이 활선상태를 유지하며 보수용 맨홀을 설치하기 위해 확인 단계를 거쳐 현장에 사용될 맨홀의 규격을 정하게 된다.As described above, in the step of confirming the row foundation terraces (S20), according to the standard of the manhole installed at the repair work using the conventional precast manhole, it is manufactured before the installation, In order to make the repair manhole included in the repair manhole, the maintenance of the live condition without the cutting process for new construction or maintenance, and the confirmation of the maintenance manhole to be installed, .

여기서는 프리캐스트 된 상판의 규격을 선택하고, 구조물인 가변형몸체부(10) : 도 1 내지 4참조) 및 철골구조물 등을 현장상황에 맞게 보수 또는 현장제작하기 위한 것이다.
1 to 4) and a steel structure or the like in accordance with the situation of the site.

상기와 같은 줄기초 터파기 확인단계(S20) 후 구조물 철거 및 시설물 정리 단계(S30)를 시행하게 된다.After the above-described line foundation terra cotta verification step (S20), the structure demolition and facility arrangement step (S30) are performed.

이는 시공현장에 매설되어 있는 지장물 및 설치되어 있는 구조물 등을 철거하고 시설물들을 작업하기 용이하게 정리하는 과정이다.This is a process of dismantling the obstacles and the installed structures buried in the construction site and arranging the facilities easily.

여기서, 전선 등의 지장물은 작업공정 중 파손되는 것을 방지하기 위해, 전선방호관 등의 보호부재를 이용하여 보호하며, 전선관 등이 하중에 의한 처짐현상 등을 방지하기 위해, 매달아서 위치를 유지하도록 한다.
Here, in order to prevent breakage of the wire or the like during the working process, it is protected by using a protective member such as a wire protection tube, and the conduit tube is held in a suspended position to prevent a sag due to a load .

상기 구조물 철거 및 시설물 정리 단계(S30)가 완료된 후 기초 및 구조물시공 단계(S40)에서는 현장시공을 위한 현장바닥 정리 및 바닥 콘크리트 시공 등을 시행하고, 완성형 가변형몸체부(10)를 현장에서 보수하거나 또는 현장에서 제작된 가변형몸체부(10)를 시공 굴착된 시공현장에 설치하게 된다.After the demolition of the structure and the arrangement of the facility (S30) are completed, in the base and structure construction step (S40), the site floor arrangement and the floor concrete construction for the field construction are performed and the finished type body part Or the variable body portion 10 manufactured in the field is installed in the construction site excavated.

여기서, 현장시공을 위한 현장바닥 정리 및 콘크리트 시공시 버림콘크리트 타설을 하게 된다. 이때, 상기 버림콘크리트 타설전에 기초PC블럭을 설치한 후 버림콘크리트를 타설하거나, 현장상황에 따라 기초PC블럭 시공없이 버림콘크리트 타설을 시행하게 된다.In this case, site flooring for construction of the site and concrete pouring at the time of concrete construction are made. At this time, before installing the forbidden concrete, it is necessary to install the forbidden concrete after installing the base PC block, or to place the forbidden concrete without installing the basic PC block according to the situation of the site.

상기와 같은 기초PC블럭은 가변형몸체부(10)의 기둥부(12)가 위치할 자리에 맞게 배치하게 된다.The above-mentioned basic PC block is arranged to fit the place where the pillar portion 12 of the variable-shape body portion 10 is located.

상기와 같이 배치된 기초PC블럭상에 가변형몸체부(10)를 배치한 후 지하에 가설되어 있는 지장물의 위치에 따라 가변형몸체부(10)의 지장물거치대(14)를 배치하여 지장물이 파손되어 정전 또는 불통상태가 되지 않도록 활선상태를 유지하며 작업을 하게 되는 것이다.After the variable body portion 10 is disposed on the basic PC block arranged as described above, the obstacle holder 14 of the variable body portion 10 is disposed according to the position of the obstacle suspended in the ground, So that it is maintained in a live state so as not to be in a power failure state or a non-power state.

보다 상세하게 설명하면, 상부프레임(11)에 기둥부(12)만을 결합하여 하단부분이 개방된 상태로 설치장소에 설치한 후 각각의 기둥부(12) 하단부분을 하부프레임(13)으로 결속하여 완성하게 된다.More specifically, the lower end portion of each column portion 12 is connected to the lower frame 13 after the column portion 12 is coupled to the upper frame 11 so that the lower end portion of the column portion 12 is opened. .

이는 현장에 설치되어 있는 지장물에 영향을 미치지 않도록 설치하기 위한 것으로, 지장물의 상측에서 하측방향으로 이동시켜 개방된 부분으로 지장물을 인입시키 설치하게 되는 것이다.This is for installation so as not to affect the obstacle installed in the field, and the obstacle is introduced by being moved from the upper side to the lower side of the obstacle by the open part.

상기와 같은 방법으로 현장에 가설되어 있는 지장물의 활선상태를 유지하며, 가변형몸체부(10)의 상부프레임(11)과 기둥부(12)만으로 이루어진 구조체를 가설한 후, 하부프레임(13)을 결합하여 가변형몸체부(10)를 현장에 설치하게 되는 것이다.After the structure including only the upper frame 11 and the pillar 12 of the variable body portion 10 is installed and the lower frame 13 is fixed to the lower frame 13, And the variable-shape body portion 10 is installed in the field.

상기와 같이 가변형몸체부(10)를 설치함과 동시에 현장에 가설되어 있는 지장물이 가설위치에서 이탈 또는 자중에 의해 처지는 현상을 방지하기 위해, 가변형몸체부(10)의 지장물거치대(14)를 적절하게 설치하여 지장물을 지지하게 되는 것이다.
In order to prevent the tangible object installed on the site from being separated from the tentative position or sagging due to the self weight, it is preferable to install the variable tangible body 10 in the tangible water cradle 14 of the variable- So as to support the obstacle.

상기 기초 및 구조물 시공 단계(S40)가 완료된 후 벽체 시공 및 되메우기 단계(S50)가 시행된다.After the foundation and structure construction step S40 is completed, the wall construction and backfilling step S50 is performed.

이러한 벽체 시공 및 되메우기 단계(S50)는 전단계(S40)에서 시공현장에 설치된 가변형몸체부(10)의 측면에 벽체를 시공하기 위해, 벽체용 철근 배근 및 거푸집 설치와 함께 콘크리트타설을 통하여 가변형몸체부(10)에 벽체를 시공한 후 스팀 또는 마이크로웨이브를 이용하는 발열장치를 이용하여 양생시키게 된다.In the step S50 of constructing and refurbishing the wall, in order to construct a wall on the side of the variable-type body portion 10 installed at the construction site in the previous stage S40, the reinforcing bars for the wall and the formwork are installed, The wall is cured by using a heating device using steam or microwave after the wall is installed in the heating device 10.

여기서 거푸집은 시공후 제거가 용이하도록 가변형몸체부(10)의 내측 즉, 내벽에 설치하게 되는데, 이는 시공완료 후, 맨홀의 내측에서 제거하기 위한 것이다.In this case, the form is installed on the inner side of the variable-type body portion 10 so as to be easily removed after the construction, which is to be removed from the inside of the manhole after completion of the construction.

이는 기존의 구조물의 외측벽에 설치할 경우 콘크리트가 양생되고 나서, 거푸집을 제거한 후 되메우기 작업을 수행해야 하며, 또한 기존의 완성형 프리캐스트 맨홀을 설치할 경우 단순히 되메우기 작업만이 수행되기 때문에, 매설장소의 지표와의 결속력이 저하되는 문제점을 극복하기 위한 것이다.
This is because when the concrete is installed on the outer wall of the existing structure, after the concrete is cured, it is necessary to perform back-up work after removing the form, and when the existing pre-cast manhole is installed, only the back-up operation is performed. Therefore, And the bonding force of the adhesive is lowered.

이때, 상기 측면벽체는 흙막이인 토류판 또는 합판 중 어느 하나를 설치하며, 상기와 같은 측면벽체는 외부 토류벽 겸 거푸집을 적용하여 설치한 후 측벽 되메우기 작업이 시행되는데, 이때는 모래, 고운흙 또는 자갈 등을 이용하여 되메우기 작업이 수행된다.At this time, the side wall is installed with one of soil board or plywood which is a retaining wall, and the side wall is installed by applying an external soil wall and formwork and then sidewall backing work is performed. In this case, sand, fine soil or gravel The back-up operation is performed.

이와 같이 흙막이인 토류벽겸 거푸집을 동시에 적용하는 것은 공기단축을 위한 것이며, 공기단축으로 인한 보행자 및 차량통행의 불편을 최소화하기 위한 것이다.In this way, it is intended to shorten the length of air and to minimize the inconvenience of pedestrian and vehicle traffic due to shortening of the air.

상기와 같이 거푸집이 설치된 후 측면벽체부분에 콘크리트를 타설한 후, 양생공정을 거치게 된다.After the mold is installed as described above, the concrete is poured into the side wall portion, and then the curing process is performed.

이때, 콘크리트양생공정은 초속경 콘크리트를 적용하여 신속하게 양생시키거나, 65℃~75℃의 온도를 유지하는 스팀을 공급하여 스팀양생 또는 마이크로 웨이브를 공급하여 신속하게 콘크리트를 양생하게 되는 것이다.At this time, the concrete curing process is to cure rapidly by applying ultra fast speed concrete, or to supply steam which maintains the temperature of 65 ° C to 75 ° C, to supply steam curing or microwave, thereby rapidly curing the concrete.

여기서, 상기 스팀양생을 위한 스팀온도를 65℃~75℃를 유지하는 것은 최적의 양생조건을 유지하기 위한 것으로 65℃미만의 스팀을 공급할 경우 양생시간이 길어짐과 동시에 양생전의 콘크리트에 스팀이 접할 경우 액화되어 수분이 과하게 공급되며, 75℃이상의 스팀이 양생전의 콘크리트에 분사될 경우 높은 온도로 인하여 콘크리트가 양생되기 전에 건조되어 콘크리트의 강도가 저하되는 문제가 발생하기 때문이다.
Here, maintaining the steam temperature for the steam curing at 65 ° C to 75 ° C is for maintaining the optimal curing condition. When steam of less than 65 ° C is supplied, the curing time is prolonged, and when steam is cured before curing And when steam of 75 ° C or higher is sprayed onto the concrete before curing, there is a problem that the strength of the concrete is lowered due to drying due to the high temperature before the concrete is cured.

상기 벽체 시공 및 되메우기 단계(S50)후 지수판설치 및 PC상판 결합단계(S60)가 시행되는데, 시공현장에 설치되어 있는 철골구조물인 가변형몸체부(10)의 상단부에 PC상판 즉 프리캐스트된 상판부(20)를 결합하기 위한 것으로, 가변형몸체부(10)와 상판부(20)사이의 빈 공간을 보강하기 위해 지수판을 설치하게 된다.After the wall construction and backfilling step (S50), a water level setting and a PC top plate joining step (S60) are performed. The PC top plate, that is, the pre-cast upper plate (10) is attached to the upper end of the variable- 20, and a diaphragm is installed to reinforce the void space between the variable-type body portion 10 and the upper plate portion 20.

이때, 상기 지수판은 수팽장지수판으로서 가변형몸체부(10)와 상판부(20)의 사이에 배치되어 완충 및 방수의 역할을 하게 되는 것이다.At this time, the waterproof plate is disposed between the flexible body 10 and the upper plate 20 as a water swell plate, and functions as a buffer and waterproof.

상기와 같이 지수판이 설치된 후, 가변형몸체부(10)와 상판부(20)는 체결볼트를 이용하여 체결하게 되는 것이다.
After the diaphragm is installed as described above, the variable-shape body portion 10 and the upper plate portion 20 are fastened using fastening bolts.

상기와 같이 지수판설치 및 PC상판 결합단계(S60)후 맨홀구조물 시공 및 포장 단계(S70)를 시행하게 되는데, 상기 맨홀구조물은 맨홀뚜껑 및 맨홀목과 같은 시설물을 말하는 것이며, 상기와 같은 맨홀구조물 시공이 완료된 후 설치작업을 위해 터파기된 도로에 포장작업을 시행함으로써, 원상회복시키게 된다.
As described above, the manhole structure construction and packaging step (S70) is performed after the installation of the water level plate and the PC top plate (S60). The manhole structure refers to a facility such as a manhole cover and a manhole. After completion, the road is repaired by performing a paving operation on the digged road for installation work.

상기와 같은 공정이 완료된 후, 맨홀 내부에 설치된 거푸집 제거 및 케이블 정리 등과 같은 후속작업을 마무리한 후, 공사를 완료하는 거푸집 제거 및 마감단계(S80)를 시행하게 되는 것이다.After completion of the above-described process, after completing a subsequent work such as removing a formwork and arranging a cable installed in a manhole, a form removing and finishing step (S80) for completing the work is performed.

이때, 상기 마감단계에서는 내부 거푸집을 제거한 후, 맨홀 내부에 방수처리한 후 주변정리 및 청소 등의 마무리 작업을 하는 것이다.
At this time, the inner mold is removed in the finishing step, and the inner surface of the manhole is waterproofed, and the finishing work such as the surrounding arrangement and cleaning is performed.

상기와 같은 일련의 공정을 통하여 본 발명의 보수용 현장조립식 활선 프리캐스트맨홀 및 그 시공방법을 제공하게 된다.
The present invention provides a prefabricated prefabricated manhole for repair and a method of construction thereof, through the series of steps as described above.

10 : 가변형몸체부 11 : 상부프레임
12 : 기둥부 13 : 하부프레임
14 : 지장물지지대 20 : 상판부
10: Adjustable body part 11: Upper frame
12: column portion 13: lower frame
14: obstacle support 20: top plate

Claims (9)

보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선상태를 유지하며 보수작업을 실시할 수 있는 프리캐스트맨홀에 있어서, 철골기초가 되며 상판부(20)를 지지하기 위한 상측프레임(11)과 상기 상측프레임(11)의 하단부 각각의 모서리에 수직방향으로 설치되는 기둥부(12)와 상기 기둥부(12)의 하단에 결합되는 하측프레임(13)으로 구성되고, 측면에는 지장물의 위치이탈 및 처짐현상을 방지하기 위한 지장물거치대(14)가 더 구비되며, 다수개의 철골부재를 연결부재(30)를 이용하여 결합하여 입방체 형상으로 형성되되, 현장상황에 따라 복수개의 입방체 형상으로 연장가능한 가변형몸체부(10);와
상기 가변형몸체부(10)의 상단에 결합되는 프리캐스트하여 완성되는 상판부(20)로 구성되고, 현장시공시 가변형몸체부(10)와 상판부(20)의 사이에는 수밀 및 완충역할을 위한 수팽창지수판이 더 구비되며, 가변형몸체부(10)와 상판부(20)를 현장상황에 맞게 결합한 후, 콘크리트 타설을 통하여 가변형몸체부(10)의 벽체를 시공하여 맨홀을 보수하는 것을 특징으로 하는 보수용 현장조립식 활선 프리캐스트맨홀.
A precast manhole capable of performing maintenance work while maintaining the live condition without damaging the obstacles such as communication lines, electric wires and various piping installed at the installation place of the manhole requiring maintenance, And a lower frame 13 coupled to a lower end of the column portion 12. The upper frame 11 and the lower frame 13 are connected to each other at a lower end of the upper frame 11, A plurality of steel members are connected to each other by using a connecting member 30 to form a cube shape, A variable body portion 10 which can be extended in a plurality of cube shapes according to a situation of a site;
And a top plate 20 which is joined to the upper end of the deformable body 10 and which is precasted and completed. In the field construction, water swell for water tightness and buffering function between the flexible body 10 and the upper plate 20 And a manhole is repaired by installing a wall of the variable-type body part (10) through concrete pouring after the variable-shape body part (10) and the upper plate part (20) On-site prefabricated live-line precast manhole.
삭제delete 삭제delete 삭제delete 보수가 요구되는 맨홀의 설치장소에 가설되어 있는 통신선, 전선 및 각종 배관과 같은 지장물을 파손시키지 않고 활선상태를 유지하며 보수작업을 실시하기 위한 가변형몸체부(10)와 프리캐스트된 상판부(20)로 구성된 보수용 현장조립식 활선 프리캐스트맨홀을 이용하는 시공방법에 있어서,
보수가 필요한 시공현장의 크기에 따라 도로컷팅 및 아스팔트 제거와 기초시설인 맨홀뚜껑 및 맨홀목을 철거하는 시공현장 터파기 단계(S10);
상기 시공현장 터파기 단계(S10) 후 지하에 매설되어 있는 전기배선 및 상하수도 시설과 같은 지장물의 위치를 확인하되, 시공장소의 지하에 매설되어 있는 전기배선 및 상하수도 시설물과 같은 지장물의 실제 설치위치 및 범위를 파악하기 위하여 지장물의 설치방향 즉, 길이방향을 따라 추가 터파기 작업을 더 수행하며, 프리캐스트된 상판의 규격을 선택하고 구조물인 가변형 몸체부 및 철골구조물 등을 현장 상황에 맞게 보수 또는 현장 제작하기 위한 설치장소 줄기초 터파기 확인 단계(S20);
상기 줄기초 터파기 확인 단계(S20) 후 시공현장에 있는 지장물 및 설치되어 있는 구조물 등을 철거하고 작업이 용이하게 정기하는 구조물 철거 및 시설물 정리 단계(S30);
상기 구조물 철거 및 시설물 정리 단계(S30) 후 현장바닥 정리 및 바닥 콘크리트 시공후 가변형몸체부(10)를 현장에서 보수하거나 현장에서 제작된 가변형몸체부(10)를 시공 현장에 설치하는 기초 및 구조물시공 단계(S40);
상기 기초 및 구조물시공 단계(S40) 후 설치된 가변형몸체부(10)의 벽체를 시공하기 위해, 벽체용 철근 배근 및 거푸집 설치와 함께 콘크리트타설을 통하여 가변형몸체부(10)의 벽체를 시공한 후 65℃ 내지 75℃의 온도를 유지하도록 하는 스팀을 공급하거나 마이크로웨이브를 이용하는 발열장치를 이용하여 양생 및 되메우기 작업이 시행되는 벽체 시공 및 되메우기 단계(S50);
상기 벽체 시공 및 되메우기 단계(S50) 후 가변형몸체부(10)의 상단에 지수판을 설치한 후, 프리캐스트 된 상판부(20)를 결합하는 지수판설치 및 PC상판 결합 단계(S60);
상기 지수판설치 및 PC상판 결합단계(S60) 후 맨홀 뚜껑과 같은 구조물을 시공하고, 터파기된 도로를 포장하는 맨홀구조물 시공 및 포장 단계(S70); 및
벽체용 거푸집을 제거하고, 방수처리하는 거푸집 제거 및 마감 단계(S80)로 구성되는 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법.
A variable body portion 10 for performing maintenance work while maintaining a live state without damaging obstacles such as communication lines, electric wires and various pipelines installed at a place where manholes are required to be repaired, and a precast upper plate portion 20 A method of constructing a prefabricated prefabricated prefabricated manhole,
(S10) of removing the road cutting and asphalt removal and the manhole cover and the manhole, which are foundations, according to the size of the construction site requiring maintenance;
After the construction site disposal step (S10), it is necessary to confirm the position of the obstacle such as the electric wiring and the water supply and sewerage facilities buried in the underground, and the actual installation position of the obstacle such as the electric wiring and water and sewerage facilities buried in the underground of the construction site In order to determine the range, additional trenching work is performed along the installation direction of the obstacle, that is, along the longitudinal direction, and the precast precast top plate is selected, and the deformable body portion and the steel structure, (Step S20);
A step S30 of demolishing the structure and removing the structure and the installed structure at the construction site after the step S30 of confirming the string foundation terraces,
After the demolition of the structure and the arrangement of the facility (S30), after the floor flooring and floor concrete construction, the variable body portion 10 is repaired in the field or the variable body portion 10 manufactured in the field is installed on the construction site. Step S40;
In order to construct the wall of the variable-shape body portion 10 installed after the foundation and structure construction step S40, the wall of the variable-shape body portion 10 is constructed through concrete pouring together with the reinforcement for the wall and the formwork installation, (S50) of applying and backing up the curing and refilling operation by supplying steam to maintain the temperature of 50 to 75 占 폚 or using a microwave heating device;
A step of installing a waterproof plate and a PC top plate (S60) for joining the pre-cast upper plate 20 after installing a waterproof plate on the upper end of the flexible body 10 after the wall construction and back-up step S50;
A manhole structure construction and packaging step (S70) for constructing a structure such as a manhole cover after the installation of the water level plate and the PC top plate (S60); And
And removing the formwork for the wall, removing the formwork to be waterproofed, and finishing step (S80).
삭제delete 제 5항에 있어서,
상기 기초 및 구조물시공 단계(S40)에서 시공현장에 가변형몸체부(10)의 기둥부(12)가 위치할 자리에 기초PC블럭을 설치한 후 버림콘크리트를 타설하거나, 기초PC블럭 설치없이 바로 버림콘크리트를 타설하는 것을 특징으로 하는 보수용 현장조립식 활선 프리캐스트맨홀의 시공방법.




6. The method of claim 5,
In the base and structure construction step (S40), the foundation PC block is installed at the place where the column portion 12 of the variable-shape body portion 10 is to be placed at the construction site, and then the foreside concrete is laid, A concrete prefabricated prefabricated prefabricated manhole construction method, characterized in that concrete is laid.




삭제delete 삭제delete
KR1020140168342A 2014-11-28 2014-11-28 A repairing assembled structure precast-manhole and constructing method it KR101524272B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140168342A KR101524272B1 (en) 2014-11-28 2014-11-28 A repairing assembled structure precast-manhole and constructing method it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140168342A KR101524272B1 (en) 2014-11-28 2014-11-28 A repairing assembled structure precast-manhole and constructing method it

Publications (1)

Publication Number Publication Date
KR101524272B1 true KR101524272B1 (en) 2015-06-10

Family

ID=53505636

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140168342A KR101524272B1 (en) 2014-11-28 2014-11-28 A repairing assembled structure precast-manhole and constructing method it

Country Status (1)

Country Link
KR (1) KR101524272B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101624518B1 (en) * 2015-12-29 2016-05-26 대실테크 주식회사 Live wire precast manhole and its construction method
CN106786026A (en) * 2016-12-14 2017-05-31 聊城华昌实业有限责任公司 A kind of new prefabricated quick-mounting pedestal of box controller switching equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005030044A (en) * 2003-07-11 2005-02-03 Takiron Co Ltd Hand hole
KR100693307B1 (en) * 2006-03-27 2007-03-14 한종숙 Manufacturing equipment for a manhole block, assembling method for the same equipment, and manufacturing method for a manhole block
KR100806134B1 (en) * 2007-11-19 2008-02-22 삼영기술주식회사 A valve room structures
KR101104823B1 (en) * 2011-07-29 2012-01-16 (주)대흥이엔지 Assembly steel frame

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005030044A (en) * 2003-07-11 2005-02-03 Takiron Co Ltd Hand hole
KR100693307B1 (en) * 2006-03-27 2007-03-14 한종숙 Manufacturing equipment for a manhole block, assembling method for the same equipment, and manufacturing method for a manhole block
KR100806134B1 (en) * 2007-11-19 2008-02-22 삼영기술주식회사 A valve room structures
KR101104823B1 (en) * 2011-07-29 2012-01-16 (주)대흥이엔지 Assembly steel frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101624518B1 (en) * 2015-12-29 2016-05-26 대실테크 주식회사 Live wire precast manhole and its construction method
CN106786026A (en) * 2016-12-14 2017-05-31 聊城华昌实业有限责任公司 A kind of new prefabricated quick-mounting pedestal of box controller switching equipment

Similar Documents

Publication Publication Date Title
KR100438794B1 (en) Construction method for three arch excavation tunnel
KR101130923B1 (en) the mold with self-propelled type trolley for construction of continuous structure and the construction method of continuous structure therewith
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
US4697955A (en) Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
CN109056656B (en) Flood discharge ditch construction method based on portable slip form integral cast-in-place molding
KR101415106B1 (en) The back feel grouting apparatus for upper part of tunnel
KR20160131410A (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
KR102431393B1 (en) Construction Method of Underground Structures
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
KR20190091397A (en) Grouting method for joint portion of concrete structure in construction and top-down joint grouting method for underground structure using the same
KR20100034496A (en) Underground constructure form system for preventing concretes of underground slab and girder from crack
JP4881555B2 (en) Construction method of underground structure
KR101524272B1 (en) A repairing assembled structure precast-manhole and constructing method it
CN109024324B (en) Steep slope ladder culvert for dismantling-free and protection of pipeline and construction method
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
CN109797776B (en) Construction method for underground pipe gallery to meet cross pipeline based on open cut method
KR101624518B1 (en) Live wire precast manhole and its construction method
CN113338340A (en) Reverse construction method for vertical shaft ensuring normal use of existing pipeline
KR20190072213A (en) Method Of Ground Half-Openning For Tunnel Excavation
KR100389054B1 (en) Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof
KR101027921B1 (en) Underground constructure form system for preventing concretes of underground slab and girder from crack
CN111779487B (en) Construction method of end well of automatic footpath
KR102026112B1 (en) Pre-cast concrete segment blocks for vertical structures with various bracket connection means
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20180327

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20190923

Year of fee payment: 5