CN100482993C - Lay out method of pipeline and synthetic pipeline with pipe frame component - Google Patents

Lay out method of pipeline and synthetic pipeline with pipe frame component Download PDF

Info

Publication number
CN100482993C
CN100482993C CNB2007101073546A CN200710107354A CN100482993C CN 100482993 C CN100482993 C CN 100482993C CN B2007101073546 A CNB2007101073546 A CN B2007101073546A CN 200710107354 A CN200710107354 A CN 200710107354A CN 100482993 C CN100482993 C CN 100482993C
Authority
CN
China
Prior art keywords
pipe
pipeline
cover plate
integrated
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2007101073546A
Other languages
Chinese (zh)
Other versions
CN101082382A (en
Inventor
金正勋
朴孝善
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Samsung E&A Co Ltd
Original Assignee
Samsung Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Samsung Engineering Co Ltd filed Critical Samsung Engineering Co Ltd
Publication of CN101082382A publication Critical patent/CN101082382A/en
Application granted granted Critical
Publication of CN100482993C publication Critical patent/CN100482993C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

本发明提供了一种在较短时间内更容易且更安全地制造综合管管路的方法。在该方法中,铺设作为用于容纳供水和排水管、电缆、和供气管等地下管廊的综合管管路。该方法包括:开凿地面;在所开凿的地面中形成底壁和侧壁;在侧壁之间的底壁上安装管架;以及利用管架作为支撑结构来形成板层。

Figure 200710107354

The present invention provides an easier and safer way to manufacture composite pipe runs in a shorter time. In this method, the integrated pipe line is laid as an underground utility gallery for accommodating water supply and drainage pipes, electrical cables, and gas supply pipes. The method includes: excavating the ground; forming a bottom wall and side walls in the excavated ground; installing a pipe frame on the bottom wall between the side walls; and forming a slab using the pipe frame as a supporting structure.

Figure 200710107354

Description

使用管架组件对管道和综合管路的铺设方法 Methods of Laying Pipelines and Integrated Piping Using Pipe Rack Assemblies

相关申请交叉参考Related Application Cross Reference

本申请要求于2006年5月30日向韩国知识产权局提交的第10-2006-0049013号韩国专利申请的权益,其公开内容整体结合于此作为参考。This application claims the benefit of Korean Patent Application No. 10-2006-0049013 filed with the Korean Intellectual Property Office on May 30, 2006, the disclosure of which is hereby incorporated by reference in its entirety.

技术领域 technical field

本发明涉及一种铺设综合管管路(utility-pipe conduit)的方法,更具体地,涉及一种在较短时间内更容易且更安全地铺设综合管管路的方法。The present invention relates to a method of laying utility-pipe conduits, and more particularly, to a method of laying utility-pipe conduits more easily and safely in a shorter period of time.

背景技术 Background technique

综合管管路是一种地下管廊(tunnel),诸如供水和排水管、各种电缆、以及供气管等的各种综合管被铺设并穿过该地下管廊。由于这样的综合管可以借助于综合管管路而安装于地下,所以可以改进道路结构和交通状况。The integrated pipe line is an underground tunnel through which various integrated pipes, such as water supply and drainage pipes, various cables, and gas supply pipes, are laid and passed. Since such integrated pipes can be installed underground by means of integrated pipe lines, road structures and traffic conditions can be improved.

管道或管子安装在用于容纳诸如供水和排水管、各种电缆、和供气管等综合管的综合管管路中。为此,被称为管架的钢结构安装于综合管管路中,以支撑这些管子和管道。The pipes or pipes are installed in the piping system used to accommodate the piping such as water supply and drainage pipes, various electrical cables, and gas supply pipes. To this end, steel structures known as pipe racks are installed in integrated pipe runs to support these pipes and pipes.

安装综合管管路的传统方法如下进行:开凿地面;在所开凿的地面中形成综合管管路的底壁和侧壁;在综合管管路的底壁和侧壁上安装支撑结构;利用支撑结构在侧壁上形成板层(slab);移除支撑结构;以及在综合管管路中安装管架。The traditional method of installing integrated pipelines is carried out as follows: excavating the ground; forming the bottom and side walls of the integrated pipeline in the excavated ground; installing support structures on the bottom and side walls of the integrated pipeline; The structure forms slabs on the side walls; removes support structures; and installs pipe racks in integrated pipe runs.

在开凿操作期间,对地面进行开凿,以形成用于综合管管路的沟槽。根据地面条件和其它条件,开凿操作可以通过各种方法而实施。例如,可以在将桩木(pile)竖直安装于地面中并安装加固结构之后,开凿地面。而且,可以在不使用加固结构的情况下开凿地面。During excavation operations, the ground is excavated to create a trench for the manifold piping. Depending on ground conditions and other conditions, excavation operations may be carried out by various methods. For example, the ground may be excavated after the piles have been installed vertically in the ground and the reinforcing structure installed. Also, it is possible to excavate the ground without using reinforcement structures.

参照图1,在开凿操作之后,在所开凿的地面中形成综合管管路100的底壁10和侧壁20。综合管管路100通常由加筋混凝土制成,同样底壁10和侧壁20也由加筋混凝土制成。底壁10和侧壁20可以通过如下的构造加筋混凝土结构的公知方法而形成:制作混凝土模板;将加固杆布置在混凝土模板中;将混凝土浇注到混凝土模板中并进行固化。Referring to FIG. 1 , after the excavation operation, the bottom wall 10 and the side wall 20 of the integrated pipeline 100 are formed in the excavated ground. The integrated pipe line 100 is usually made of reinforced concrete, as are the bottom wall 10 and the side walls 20 . The bottom wall 10 and the side walls 20 may be formed by a known method of constructing a reinforced concrete structure: making a concrete form; arranging reinforcing rods in the concrete form; pouring concrete into the concrete form and curing.

图2示出了使用支撑结构40而在侧壁20上形成的板层30。支撑结构40包括连接在一起的多个钢杆。外螺纹形成在钢杆的一端上,而内螺纹形成在钢杆的另一端上,从而可以通过连接钢杆而获得所需长度。在连接钢杆以获得所需长度之后,将钢杆以预定间隔布置在直立位置中。接着,在钢杆上形成混凝土模板,并通过将混凝土浇注到该模板上而形成板层30。FIG. 2 shows the ply 30 formed on the side wall 20 using the support structure 40 . The support structure 40 comprises a plurality of steel rods connected together. The external thread is formed on one end of the steel rod, and the internal thread is formed on the other end of the steel rod, so that a desired length can be obtained by connecting the steel rods. After the steel rods are connected to obtain a desired length, the steel rods are arranged in an upright position at predetermined intervals. Next, a concrete form is formed on the steel rods, and the slab 30 is formed by pouring concrete onto the form.

参照图3,在形成板层30之后,移除支撑结构40,并将管架50安装在综合管管路100中。如上所述,管架50为钢结构,并且管架50通常形成为H或I梁。将管道55铺设在管架50上,以容纳诸如供水和排水管、各种电缆、和供气管等的综合管。Referring to FIG. 3 , after the slab 30 is formed, the support structure 40 is removed, and the pipe frame 50 is installed in the integrated pipe line 100 . As noted above, the pipe frame 50 is a steel structure, and the pipe frame 50 is typically formed as an H or I beam. Pipes 55 are laid on the pipe frame 50 to accommodate integrated pipes such as water supply and drainage pipes, various cables, and gas supply pipes.

但是,由于以下事实,使得铺设综合管管路的传统方法具有局限性,该事实是:用于支撑结构40的钢杆在各种施工现场被反复地使用,所以钢杆强度可能降低,并且钢杆具有较大的长细比。因此,钢杆弯曲的可能性增加了。如果支撑结构40的钢杆由于板层30的重量而弯曲,则工人可能会受伤,并且综合管管路100无法按时铺设。However, the conventional method of laying composite pipelines has limitations due to the fact that the steel rods for supporting the structure 40 are repeatedly used at various construction sites, so the strength of the steel rods may decrease, and the steel rods The rod has a larger slenderness ratio. Therefore, the possibility of bending the steel rod increases. If the steel rods of the support structure 40 are bent due to the weight of the slab 30, workers may be injured and the integrated pipe line 100 cannot be laid on time.

而且,由于管架50是在板层30形成之后安装在综合管管路100中的,所以板层30的一部分未形成,以便用作材料入口,从而在综合管管路100中形成管架50时,容易将H梁的材料运送到综合管管路100中。接着,在管架50完全形成在综合管管路100中之后,形成板层30的所述部分。由于H梁的材料通过材料入口而被运送到综合管管路100中的所需位置处,然后将所述H梁的材料组装在综合管管路100中,所以需要很长时间来形成管架50。此外,因为综合管管路100是封闭的,所以在综合管管路100中形成管架50时,进行焊接是危险的。Also, since the pipe frame 50 is installed in the integrated pipe line 100 after the plate layer 30 is formed, a part of the plate layer 30 is not formed so as to be used as a material inlet, thereby forming the pipe frame 50 in the integrated pipe line 100 , it is easy to transport the material of the H-beam into the integrated pipe line 100 . Next, after the pipe frame 50 is completely formed in the integrated pipe line 100, the part of the plate layer 30 is formed. Since the material of the H-beam is transported to the desired position in the integrated pipe line 100 through the material inlet and then assembled in the integrated pipe line 100, it takes a long time to form the pipe frame 50. Furthermore, since the integrated pipe line 100 is closed, it is dangerous to perform welding when forming the pipe frame 50 in the integrated pipe line 100 .

发明内容 Contents of the invention

本发明提供了一种在较短时间内更容易且更安全地铺设综合管管路的方法。The present invention provides an easier and safer method of laying manifold piping in a shorter time.

根据本发明的一方面,提供了一种铺设综合管管路的方法,所述综合管管路作为用于容纳供水和排水管、电缆、和供气管的地下管廊。该方法包括:开凿地面;在所开凿的地面中形成底壁和侧壁;在侧壁之间的底壁上安装管架;以及利用管架作为支撑结构来形成板层。According to an aspect of the present invention, there is provided a method of laying an integrated pipe line as an underground pipe gallery for accommodating water supply and drainage pipes, cables, and gas supply pipes. The method includes: excavating the ground; forming a bottom wall and side walls in the excavated ground; installing a pipe frame on the bottom wall between the side walls; and forming a slab using the pipe frame as a supporting structure.

管架可以预先制成,并安装在侧壁之间的底壁上。Pipe racks can be prefabricated and mounted on the bottom wall between the side walls.

形成板层的步骤可以包括:预制盖板,该盖板包括矩形混凝土本体和布置在该矩形混凝土本体中的加固杆;将预制的盖板放置在管架和侧壁上;以及将混凝土浇注到盖板上。The step of forming the slab may include: prefabricating a cover slab comprising a rectangular concrete body and reinforcing rods disposed in the rectangular concrete body; placing the prefabricated cover slab on the pipe frame and side walls; and pouring concrete into the cover.

该方法可以进一步包括,在为形成板层而浇注的混凝土进行固化的同时,连接铺设在管架上的管道。The method may further include, while the concrete poured to form the slab is curing, connecting the pipes laid on the pipe rack.

附图说明 Description of drawings

通过结合附图对示例性实施例的详细描述,本发明的上述和其它的特征和优点将变得更显而易见,附图中:The above and other features and advantages of the present invention will become more apparent from the detailed description of exemplary embodiments in conjunction with the accompanying drawings, in which:

图1示出了在地面中开凿的沟槽中所形成的综合管管路的底壁和侧壁;Fig. 1 shows the bottom wall and the side wall of the integrated pipe line formed in the trench excavated in the ground;

图2示出了使用支撑结构在侧壁上形成板层时的图1的综合管管路;Fig. 2 shows the integrated pipe line of Fig. 1 when using a support structure to form a slab on the side wall;

图3示出了在移除支撑结构之后形成管架时的图2的综合管管路;Figure 3 shows the integrated pipe run of Figure 2 when a pipe rack is formed after removal of the support structure;

图4示出了在底壁和侧壁上形成管架时的图1的综合管管路;以及Figure 4 shows the integrated pipe line of Figure 1 when pipe racks are formed on the bottom wall and side walls; and

图5示出了根据本发明实施例的在管架上形成盖板时的图4的综合管管路。Fig. 5 shows the integrated pipe line of Fig. 4 when a cover plate is formed on the pipe frame according to an embodiment of the present invention.

具体实施方式 Detailed ways

现在将参照附图更全面地描述铺设综合管管路的方法,附图中示出了本发明的示例性实施例。The method of laying a manifold pipeline will now be described more fully with reference to the accompanying drawings, in which exemplary embodiments of the invention are shown.

图1示出了在地面中开凿的沟槽中所形成的综合管管路100的底壁10和侧壁20。FIG. 1 shows the bottom wall 10 and side walls 20 of an integrated pipeline 100 formed in a trench dug in the ground.

图3示出了在移除支撑结构之后形成管架50时的图2的综合管管路100。FIG. 3 shows the pipe manifold 100 of FIG. 2 as the pipe rack 50 is formed after removal of the support structure.

图4示出了在底壁10和侧壁20上形成管架50时的图1的综合管管路100。FIG. 4 shows the integrated pipe line 100 of FIG. 1 when the pipe rack 50 is formed on the bottom wall 10 and the side wall 20 .

图5示出了根据本发明实施例的在管架50上形成盖板60时的图4的综合管管路100。FIG. 5 shows the integrated pipe pipeline 100 of FIG. 4 when the cover plate 60 is formed on the pipe frame 50 according to an embodiment of the present invention.

根据本发明,铺设综合管管路100的方法包括:开凿地面;形成底壁10和侧壁20;安装管架50;形成板层;以及在板层的混凝土干燥期间连接管道55。According to the present invention, the method of laying the integrated pipeline 100 includes: excavating the ground; forming the bottom wall 10 and the side wall 20; installing the pipe rack 50; forming the slab; and connecting the pipe 55 during the concrete drying of the slab.

在开凿操作期间,开凿地面,以形成用于综合管管路100的沟槽。由于此开凿操作与铺设综合管管路的传统方法的开凿操作相同,因此将省略对于开凿操作的详细描述。During excavation operations, the ground is excavated to form a trench for the manifold conduit 100 . Since this excavation operation is the same as that of the conventional method of laying integrated pipelines, a detailed description of the excavation operation will be omitted.

在形成底壁10和侧壁20的操作期间,如图1所示,使用加筋混凝土形成综合管管路100的底壁10和侧壁20。如上所述,底壁10和侧壁20可以按如下方法形成:制作混凝土模板;将加固杆布置在混凝土模板中;将混凝土浇注到混凝土模板中并进行固化。During the operation of forming the bottom wall 10 and the side wall 20 , as shown in FIG. 1 , the bottom wall 10 and the side wall 20 of the integrated pipe piping 100 are formed using reinforced concrete. As described above, the bottom wall 10 and the side wall 20 may be formed by: making a concrete form; arranging reinforcing rods in the concrete form; pouring concrete into the concrete form and curing.

在安装管架50的操作期间,将在工厂中预先形成的管架50安装在侧壁20之间的底壁10中。由于综合管管路100可以具有的长.度范围是几百米至几千米,所以具有与综合管管路100的长度相对应的长度的管架50无法在工厂中制造。因此,在工厂中制造具有预定长度的子管架,然后将子管架运送到综合管管路100的施工现场,并使用起重机将其安装在综合管管路100中。之后,将子管架组装成管架50。如果在工厂中制造子管架,则可以将管道55和绝缘电缆管以组件形式与子管架形成在一起。因为在综合管管路100上形成板层(未示出)之前将管架50安装在综合管管路100中,所以在安装管架50的过程中具有很多优点。例如,管架50可容易地安装在综合管管路100中的期望位置处,这是因为综合管管路100的顶部没有被板层覆盖。在形成综合管管路的传统方法中,当形成综合管管路的板层时,板层的一部分没有形成,以便用作材料入口,并将用于管架的材料通过该材料入口运送到综合管管路中,然后再将其移动到综合管管路的期望位置处。但是,根据本发明的当前实施例,由于综合管管路100的顶部没有被板层覆盖,所以与传统方法相比,可以很容易地将用于管架50的材料运送到综合管管路100中的期望位置处。During the operation of installing the pipe rack 50 , the pipe rack 50 preformed in a factory is installed in the bottom wall 10 between the side walls 20 . Since the integrated pipe line 100 may have a length ranging from several hundred meters to several thousand meters, the pipe frame 50 having a length corresponding to the length of the integrated pipe line 100 cannot be manufactured in a factory. Therefore, a sub-pipe rack having a predetermined length is manufactured in a factory, and then the sub-pipe rack is transported to the construction site of the integrated pipe line 100 and installed in the integrated pipe line 100 using a crane. Afterwards, the sub-pipe racks are assembled into a pipe rack 50 . If the sub-pipe frame is manufactured in a factory, the pipe 55 and the insulating cable duct can be formed together with the sub-pipe frame in the form of an assembly. Because the pipe rack 50 is installed in the pipe manifold 100 before a ply (not shown) is formed thereon, there are many advantages in installing the pipe rack 50 . For example, the pipe rack 50 can be easily installed at a desired location in the pipe manifold 100 because the top of the pipe manifold 100 is not covered by the ply. In the traditional method of forming integrated pipe runs, when forming the plies of integrated pipe runs, a part of the ply is not formed so as to be used as a material inlet, and the material for pipe racks is delivered to the integrated pipe through this material inlet. pipe run before moving it to the desired location in the pipe run. However, according to the current embodiment of the present invention, since the top of the integrated pipe piping 100 is not covered by the ply, the materials for the pipe rack 50 can be easily delivered to the integrated pipe piping 100 compared with the conventional method. at the desired location in .

而且,由于子管架是在工厂中预先制造的,所以通过将子管架运送到综合管管路100中的期望位置处并将综合管管路100中的子管架连接起来,可以容易地形成管架50。因此,可以节省在施工现场制造管架50所需的时间。Moreover, since the sub-pipe racks are prefabricated in the factory, by transporting the sub-pipe racks to desired positions in the integrated pipe line 100 and connecting the sub-pipe racks in the integrated pipe line 100, it is possible to easily A pipe rack 50 is formed. Therefore, the time required to manufacture the pipe rack 50 at the construction site can be saved.

此外,子管架是在开放空间中例如通过焊接而彼此连接的。因此,可以降低发生意外事故的可能性。Furthermore, the sub-pipe racks are connected to each other in an open space, for example by welding. Therefore, the possibility of accidents can be reduced.

在已经完成管架50的安装之后,形成板层30(图3),作为综合管管路100的上部结构,并且该板层是使用管架50作为支撑结构而形成的,而不必使用附加的支撑结构。After the installation of the pipe rack 50 has been completed, the slab 30 ( FIG. 3 ) is formed as the upper structure of the integrated pipe line 100 , and the slab is formed using the pipe rack 50 as a supporting structure without using additional supporting structure.

将预先制造的盖板60放置在侧壁20和管架50上。接着,将加固杆布置在盖板60上,并将混凝土浇注在盖板60上,以形成板层。A prefabricated cover plate 60 is placed over the side walls 20 and the tube frame 50 . Next, reinforcing rods are arranged on the cover slab 60, and concrete is poured on the cover slab 60 to form a slab.

盖板60具有钢筋混凝土结构,该结构包括矩形混凝土本体以及布置在该矩形混凝土本体中的加固杆。在盖板60的顶表面上形成突起结构61,以便被浇注到盖板60上的混凝土所覆盖,以形成板层。在当前实施例中,突起结构61包括杆和钢丝。杆与盖板60的顶表面隔开,并沿盖板60的长度方向布置。钢丝被锚定到盖板60中,以便支撑与盖板60顶表面隔开的杆。The cover plate 60 has a reinforced concrete structure comprising a rectangular concrete body and reinforcing rods arranged in the rectangular concrete body. Protrusion structures 61 are formed on the top surface of the cover plate 60 so as to be covered with concrete poured onto the cover plate 60 to form a slab. In the current embodiment, the protruding structure 61 includes rods and wires. The rods are spaced apart from the top surface of the cover plate 60 and arranged along the length direction of the cover plate 60 . Steel wires are anchored into the cover plate 60 to support the rods spaced from the top surface of the cover plate 60 .

通过在单独的车间中利用预制工艺进行预制,来预先制造盖板60。在这种情况下,由于可以有效利用车间的设备,所以可以在优化条件下制造盖板60。因此,与在施工现场形成的盖板相比,盖板60可以具有精确的尺寸和较高的强度。The cover plate 60 is prefabricated by prefabrication in a separate workshop using a prefabrication process. In this case, since the facilities of the workshop can be effectively utilized, the cover plate 60 can be manufactured under optimized conditions. Therefore, the cover plate 60 can have precise dimensions and higher strength than a cover plate formed at a construction site.

将通过预制形成的盖板60运送到综合管管路100的施工现场,并将其放置在侧壁20和管架50上。接着,将突起结构61的加固杆布置在盖板60上,并将混凝土浇注到盖板60上,以在综合管管路100上形成板层。The cover plate 60 formed by prefabrication is transported to the construction site of the integrated pipeline 100 and placed on the side wall 20 and the pipe frame 50 . Next, the reinforcing rods of the protruding structures 61 are arranged on the cover plate 60 and concrete is poured on the cover plate 60 to form a slab on the integrated pipe line 100 .

当使用按上述方法预制的盖板60来形成板层时,不需要下部混凝土模板来形成板层。因此,可以节省形成下部混凝土模板以及在形成板层之后移除该下部混凝土模板所需的时间、人力、和设备。而且,由于盖板60是预制的并被运送到综合管管路100的施工现场,所以可以以简单方式形成板层。When the deck 60 prefabricated as described above is used to form the slab, no lower concrete form is required to form the slab. Therefore, time, manpower, and equipment required for forming the lower concrete form and removing the lower concrete form after forming the slab can be saved. Also, since the cover plate 60 is prefabricated and delivered to the construction site of the integrated pipe piping 100, the slabs can be formed in a simple manner.

如果以盖板60的两边缘分别布置在侧壁20上的方式将盖板60放置在综合管管路100上,则盖板60可能被其重量以及浇注到盖板60上的混凝土损坏或折断。但是,由于管架50支撑该盖板60,所以可以安全且适当地形成盖板60。同样,盖板60可以具有与侧壁20相同的高度。If the cover plate 60 is placed on the integrated pipe piping 100 in such a manner that both edges of the cover plate 60 are respectively arranged on the side wall 20, the cover plate 60 may be damaged or broken by its weight and the concrete poured onto the cover plate 60. . However, since the pipe frame 50 supports the cover plate 60, the cover plate 60 can be safely and properly formed. Also, the cover plate 60 may have the same height as the side wall 20 .

在为了形成板层而将混凝土浇注到盖板60上之后,在所浇注的混凝土固化的同时,连接铺设在管架50上的管道55。在将混凝土浇注到盖板60上之后的预定时间内,混凝土固化到用于进行管道55的连接操作的足够强度。因此,可以在混凝土完全固化之前连接管道55,从而减少形成综合管管路100所需的时间。图3示出了在板层形成之后所安装的管架50。After concrete is poured on the cover plate 60 to form a slab, the pipes 55 laid on the pipe frame 50 are connected while the poured concrete is curing. Within a predetermined time after concrete is poured onto the cover plate 60, the concrete cures to a sufficient strength for performing the connecting operation of the pipe 55. Referring to FIG. Therefore, the pipes 55 can be connected before the concrete is fully cured, thereby reducing the time required to form the integrated pipe line 100 . Figure 3 shows the pipe rack 50 installed after the plies have been formed.

在上述实施例中,子管架在工厂中被预先制造,并在综合管管路100的施工现场被组装成管架50。但是,如果需要,可以在不使用预制子管架的情况下,在施工现场形成管架50。In the above embodiments, the sub-pipe racks are prefabricated in the factory, and assembled into the pipe rack 50 at the construction site of the integrated pipeline 100 . However, the pipe rack 50 can be formed at the construction site without the use of prefabricated sub-pipe racks, if desired.

而且,在上述实施例中,使用预制的盖板60而形成板层。但是,如果需要,替代使用盖板60,可以使用下部混凝土模板来形成板层,然后可以在板层形成之后移除该下部混凝土模板。Also, in the above-described embodiment, the ply is formed using the prefabricated cover plate 60 . However, instead of using the cover slab 60, if desired, a lower concrete form could be used to form the slab, which could then be removed after the slab has been formed.

如上所述,本发明提供了以下优点。As described above, the present invention provides the following advantages.

由于不使用附加的支撑结构来形成板层,所以可以在较短时间内铺设综合管管路,并且可以降低发生意外事故的可能性。Since no additional support structure is used to form the slab, the multi-pipeline can be laid in a shorter time and the possibility of accidents can be reduced.

而且,由于管架是在板层形成之前安装的,所以可以在开放空间中安装管架。因此,可以更容易且更安全地运送和组装用于管架的材料。Also, since the pipe racks are installed before the plies are formed, it is possible to install the pipe racks in open spaces. Therefore, the material for the pipe rack can be transported and assembled more easily and safely.

此外,如果使用在单独的工厂中预先制造的子管架来形成管架,则与在综合管管路的施工现场形成管架的情况相比,可以更迅速地铺设综合管管路。而且,如果使用盖板来形成板层,由于无需准备下部混凝土模板来形成板层以及无需在板层形成之后移除该下部混凝土模板,所以可以节省时间、人力、和设备。Furthermore, if the pipe rack is formed using sub-pipe racks prefabricated in a separate factory, the integrated pipe line can be laid more quickly than in the case of forming the pipe rack at the construction site of the integrated pipe line. Also, if the deck is used to form the slab, time, manpower, and equipment can be saved since there is no need to prepare the lower concrete form to form the slab and remove the lower concrete form after the slab is formed.

虽然已参照本发明的示例性实施例具体示出并描述了本发明,但是本领域技术人员可以理解,在不背离所附权利要求限定的本发明的精神和范围的前提下,可以对本发明进行形式和细节上的各种更改。While the invention has been particularly shown and described with reference to exemplary embodiments of the invention, it will be understood by those skilled in the art that modifications may be made to the invention without departing from the spirit and scope of the invention as defined by the appended claims. Various changes in form and detail.

Claims (4)

1. lay comprehensive method of managing pipeline for one kind, described comprehensive pipe pipeline is as the underground pipe gallery that is used to hold water supply and waste pipe, cable and air supply pipe, and described method comprises:
Dig ground;
In the ground of being dug, form diapire and sidewall;
On the described diapire between the described sidewall, pipe support is installed, is placed with pipeline on the described pipe support; And
Utilize described pipe support to form flaggy as supporting structure.
2. method according to claim 1 wherein, is made described pipe support in advance, and described pipe support is installed on the described diapire between the described sidewall.
3. method according to claim 1, wherein, the step that forms described flaggy comprises:
Prefabricated cover plate, described cover plate comprise Rectangular Concrete body and the reinforced pole that is arranged in the described Rectangular Concrete body;
Described prefabricated cover plate is placed on described pipe support and the described sidewall; And with concrete placement to described cover plate.
4. method according to claim 1 further comprises, for when forming the concrete curing that described flaggy pours into a mould, connects the pipeline that is laid on the described pipe support.
CNB2007101073546A 2006-05-30 2007-05-29 Lay out method of pipeline and synthetic pipeline with pipe frame component Expired - Fee Related CN100482993C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020060049013A KR100924701B1 (en) 2006-05-30 2006-05-30 Joint construction method
KR1020060049013 2006-05-30

Publications (2)

Publication Number Publication Date
CN101082382A CN101082382A (en) 2007-12-05
CN100482993C true CN100482993C (en) 2009-04-29

Family

ID=38912097

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007101073546A Expired - Fee Related CN100482993C (en) 2006-05-30 2007-05-29 Lay out method of pipeline and synthetic pipeline with pipe frame component

Country Status (2)

Country Link
KR (1) KR100924701B1 (en)
CN (1) CN100482993C (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101056661B1 (en) * 2009-08-05 2011-08-12 한국가스공사 Finishing method of daily construction section
CN102278528A (en) * 2011-06-15 2011-12-14 中国瑞林工程技术有限公司 Arranging method of composite line pipe of copper and copper alloy plate strip job shop
CN102359123B (en) * 2011-07-21 2013-11-20 济南城建集团有限公司 Cast-in-place concrete cable conduit construction method
CN107142962A (en) * 2017-06-07 2017-09-08 扬州工业职业技术学院 A kind of pipe gallery and its construction method
CN107905257A (en) * 2017-11-24 2018-04-13 上海市机械施工集团有限公司 A kind of construction method of city integrated piping lane
CN109930626B (en) * 2019-03-15 2020-10-30 安徽省公路桥梁工程有限公司 Large-section multi-chamber cast-in-situ integrated pipe gallery and its construction method
CN110230323B (en) * 2019-06-22 2021-06-08 广西聚诚电力线路器材有限公司 Prefabricated part for pipe gallery
KR102180213B1 (en) 2020-04-21 2020-11-18 오헌영 Concrete Formwork for Installation of Water and Sewer Pipes and Construction Method using the same
KR102714639B1 (en) 2024-02-22 2024-10-11 (주)더케이프리캐스트 Pillar wall for utility tunnels that maximizes productivity and economy through high-quality manufacturability, easy workability, construction safety, and shortened construction period, and a construction method for utility tunnels using the above Pillar walls

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4081935A (en) 1976-07-26 1978-04-04 Johns-Manville Corporation Building structure utilizing precast concrete elements
JP3053938B2 (en) * 1991-11-18 2000-06-19 株式会社竹中工務店 Double striking method
KR100422247B1 (en) 2001-06-28 2004-03-12 평산에스아이 주식회사 Corrugated matter plate sanitary sewer
KR100588189B1 (en) * 2004-10-19 2006-06-08 삼성물산 주식회사 Construction method of connecting structure of floor slab and cavity of structure

Also Published As

Publication number Publication date
CN101082382A (en) 2007-12-05
KR100924701B1 (en) 2009-11-03
KR20070115112A (en) 2007-12-05

Similar Documents

Publication Publication Date Title
CN101082382A (en) Lay out method of pipeline and synthetic pipeline with pipe frame component
CN102359123B (en) Cast-in-place concrete cable conduit construction method
CN105201012B (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN111779028A (en) A kind of finished product prefabricated electric power shallow trench and its construction method
KR100926173B1 (en) On-site casting piping structure and construction method
CN104060616B (en) A kind of construction formwork of retaining engineering and construction method
KR101682541B1 (en) Culvert crossing buried pipeline construction and pipeline laying method using the same
CN108643212A (en) A kind of prefabricated reinforced concrete open caisson construction method
CN110067581B (en) Arrangement and construction method of pre-buried holes in reinforced concrete supporting layers at tunnel or roadway forks or openings
CN113338340A (en) Reverse construction method for vertical shaft ensuring normal use of existing pipeline
CN113062236A (en) Wall protection integrated pipe culvert and construction method thereof
JP5288356B2 (en) How to connect existing piping and new piping in the manhole
JP6584979B2 (en) Construction method of underground tank structure, underground tank structure
KR101624518B1 (en) Live wire precast manhole and its construction method
CN203729323U (en) Precast concrete pipeline foundation
CN116815662A (en) Construction method of steel corrugated shed tunnel
KR101084756B1 (en) Manhole structure for transmission and distribution and construction method
CN108487096A (en) A kind of box culvert connection structure
KR100751969B1 (en) Field production pipeline installation method
CN119956819B (en) A method for constructing a gas pipeline with external protection box culvert crossing a box culvert
EP3066262B1 (en) Method for strengthening a structure of a tubular bridge or a culvert and the strengthened tubular bridge or culvert
CN223708775U (en) In-situ protection structure for rectangular pipe jacking under existing sewage pipelines
CN111005320B (en) Pipeline laying method
CN214832907U (en) Temporary protection structure for electric buried pipe stay wire position
CN115199813B (en) Construction process for starting end of oblique jacking pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090429

Termination date: 20200529