JP4630215B2 - Relocation method for buried objects - Google Patents

Relocation method for buried objects Download PDF

Info

Publication number
JP4630215B2
JP4630215B2 JP2006097321A JP2006097321A JP4630215B2 JP 4630215 B2 JP4630215 B2 JP 4630215B2 JP 2006097321 A JP2006097321 A JP 2006097321A JP 2006097321 A JP2006097321 A JP 2006097321A JP 4630215 B2 JP4630215 B2 JP 4630215B2
Authority
JP
Japan
Prior art keywords
buried
road
box
buried object
underpass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2006097321A
Other languages
Japanese (ja)
Other versions
JP2007270512A (en
Inventor
正士 武田
充 柴沼
達哉 上田
秀公 今西
豊 保立
正治 勝又
徹也 三島
雄司 赤坂
雅典 福山
規之 川端
宏二 本間
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Maeda Corp
Original Assignee
Nippon Steel Corp
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp, Maeda Corp filed Critical Nippon Steel Corp
Priority to JP2006097321A priority Critical patent/JP4630215B2/en
Publication of JP2007270512A publication Critical patent/JP2007270512A/en
Application granted granted Critical
Publication of JP4630215B2 publication Critical patent/JP4630215B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、例えば、道路の交差点において一部の道路をアンダーパス道路にするような場合に好適な技術に関するものであり、通信ケーブル、電線、ガス管、上水道管等の既存の地中埋設物が設けられた道路の下部に、新たに構造物を構築する場合の前記埋設物の移設工法に関する。   The present invention relates to a technique suitable for, for example, a case where some roads are underpass roads at road intersections, and existing underground buried objects such as communication cables, electric wires, gas pipes, water pipes, etc. The present invention relates to a method for moving the buried object when a structure is newly constructed at a lower part of a road provided with the above.

一般に、幹線道路等である道路50には、図14に示すように、その長手方向に沿って延びる通信ケーブル、電線、ガス管、上水道管などの地中の埋設物51が設けられている。   In general, a road 50 such as a main road is provided with a buried object 51 such as a communication cable, an electric wire, a gas pipe, and a water pipe extending in the longitudinal direction as shown in FIG.

そして、例えば、埋設物51が設けられた道路50と交差する道路60をアンダーパス道路とするように施工する場合に、その交差点部の埋設物51の移設は、従来、次のように行っていた。   For example, when the road 60 intersecting with the road 50 provided with the buried object 51 is constructed as an underpass road, the buried object 51 at the intersection is conventionally moved as follows. It was.

まず、アンダーパス道路の工事を行う前工程として、アンダーパス道路との交差部に設
けられた地中の埋設物51を、工事に支障とならないように、側道部若しくは歩道部となる位置に移設する。この移設は、通信、電気、ガス、上水道などの事業者が道路管理者等と協議しながら行うが、通常は事業者毎に個別に実施するため、長期間を要することが多い。なお、アンダーパス道路の工事前に移設ができない地中の埋設物もあり、その場合には、覆工板の下で前記埋設物を吊り防護して、アンダーパス道路構築後に前記埋設物を埋め戻して当初の状態に戻す。
First, as a step prior to performing the work of underpass road, the underground buried object 51 provided at the intersection of the underpass road, so as not to interfere with work, the position where the side road portion or the pavement section Relocate. This relocation is carried out by operators such as communication, electricity, gas, and waterworks in consultation with road managers, etc., but usually it is carried out individually for each operator, so it often takes a long time. There are some underground objects that cannot be relocated before construction of the underpass road. In that case, the buried object is suspended and protected under the lining plate, and the buried object is buried after the construction of the underpass road. Return to the original state.

次に、従来のアンダーパス道路の工事と地中の埋設物移設工事を説明する。   Next, the conventional underpass road construction and the underground relocation work will be described.

従来のアンダーパス道路の工事は、ボックスカルバート58(図16〜図18参照)を用いて行う。すなわち、アンダーパス道路の工事は、アンダーパス道路とすべき道路60(図14参照)の両側に、図15に示すように、鋼矢板52などを並べて打設して他方の道路50を横切るように山留め壁53、53を設ける。   Conventional underpass road construction is performed using a box culvert 58 (see FIGS. 16 to 18). That is, in the construction of the underpass road, as shown in FIG. 15, steel sheet piles 52 are arranged side by side on both sides of the road 60 (see FIG. 14) that should be an underpass road so as to cross the other road 50. Mountain retaining walls 53, 53 are provided.

次に、交差点部における山留め壁53、53の上に、他方の道路50の交通確保のための覆工板54を設置する。次に、これらの山留め壁53、53間の土55を工事前に移設ができずに残った埋設物51より少し深いところまで掘削し、覆工板54の下側に設けられた吊り下げ部材56で埋設物51を吊り下げて所定位置に保持する。   Next, a lining board 54 for securing traffic on the other road 50 is installed on the retaining walls 53, 53 at the intersection. Next, the soil 55 between the retaining walls 53 and 53 is excavated to a depth slightly deeper than the buried object 51 that cannot be relocated before construction, and a suspension member provided below the lining plate 54. At 56, the embedded object 51 is suspended and held at a predetermined position.

次に、図16に示すように、山留め壁53、53間の土55を更に掘削して、山留め壁53、53間の空間57に底版、側壁、頂版の順にボックスカルバート58を構築する。このボックスカルバート58は、埋設物の設置エリアの確保のため、その頂版が少なくとも2.5mの深さになるように構築することを要し、その内部が、上記の道路60から連続するアンダーパス道路59となる。そして、上記の埋設物51は、ボックスカルバート58の頂版の上部に配置される。   Next, as shown in FIG. 16, the soil 55 between the retaining walls 53 and 53 is further excavated, and a box culvert 58 is constructed in the space 57 between the retaining walls 53 and 53 in the order of bottom plate, side wall, and top plate. The box culvert 58 needs to be constructed so that the top plate has a depth of at least 2.5 m in order to secure the installation area of the buried object, and the inside of the box culvert 58 is continuous from the road 60 described above. It becomes pass road 59. The above-described embedded object 51 is disposed on the top of the top plate of the box culvert 58.

従って、ボックスカルバート58構築の際には、予め試掘を実施するなど埋設位置を十分に確認をしておく必要がある。また、山留め壁53、53施工時には、これら地中の埋設物51を避けて施工し、その後の切り梁の設置や内部掘削時には、切り梁を利用してこれら地中の埋設物51を吊り、防護する。   Therefore, when the box culvert 58 is constructed, it is necessary to sufficiently check the burial position, for example, by performing trial digging in advance. In addition, during the construction of the retaining walls 53, 53, construction is performed avoiding these underground objects 51, and during the subsequent installation of the cut beams and internal excavation, the underground objects 51 are suspended using the beams. Protect.

次に、図17に示すように、山留め壁53、53、覆工板54及び吊り下げ部材56を撤去し、ボックスカルバート58の周囲に土55を埋め戻す。これにより、埋設物51がボックスカルバート58の上側に埋設された状態で保持される。このように、工事中に防護・養生していた地中の埋設物51を設置・埋設するためのエリアを確保した上で、最終的に移設していた。   Next, as shown in FIG. 17, the retaining walls 53, 53, the lining plate 54 and the suspension member 56 are removed, and the soil 55 is backfilled around the box culvert 58. Thereby, the embedded object 51 is held in a state of being embedded above the box culvert 58. In this way, after securing an area for installing and burying the underground buried object 51 that was protected and cured during the construction, it was finally relocated.

なお、アンダーパス道路の構築は、渋滞道路の交差点部であれば、工事による2次渋滞が生じるため、昼間の施工をできるだけ避ける必要があり、通常夜間工事により行う。
特開2006−2399号公報
Note that underpass roads are constructed at the intersections of congested roads because secondary traffic congestion occurs due to construction, so it is necessary to avoid daytime construction as much as possible.
JP 2006-2399 A

従来のアンダーパス道路の施工方法では、山留め壁53、53施工時に、通信ケーブル、電線、ガス管、上水道管を含む地中の埋設物51を避けて施工する必要があり、また、これら埋設物51の設置エリアを確保する必要性から、アンダーパス道路の構築のための地盤の掘削範囲が大きくなる問題があった。   In the conventional construction method of the underpass road, it is necessary to avoid the underground buried object 51 including the communication cable, the electric wire, the gas pipe, and the water pipe when the mountain retaining walls 53 and 53 are constructed. Due to the necessity of securing 51 installation areas, there was a problem that the excavation range of the ground for the construction of the underpass road became large.

また、従来のアンダーパス道路等の施工方法では、工事期間を通じて埋設物51の防護・養生あるいは点検・管理が必要であるが、土留め壁53、53間の土55を掘削するときに、埋設物51が覆工板54に吊り下げられて空間57内に露出された状態となるので、突発的な原因、例えば埋設物51に掘削機などが衝突するなどして破損するおそれがある。   Further, in the conventional construction method such as an underpass road, it is necessary to protect, cure, or inspect and manage the buried object 51 throughout the construction period. However, when excavating the soil 55 between the retaining walls 53, 53, Since the object 51 is suspended from the lining plate 54 and is exposed in the space 57, there is a possibility that it may be damaged due to a sudden cause, for example, an excavator or the like collides with the embedded object 51.

本発明は、このような問題に鑑みなされたもので、通信ケーブル、電線等を収納した管、上水道管等の既存の地中埋設物が存在する道路の下部に新たな構造物を構築する場合に、埋設物の防護・養生をしながらの煩雑な作業を回避し、かつ、掘削範囲の縮小化が実現することで全体の工期の短縮化が可能な埋設物の移設工法を提供することを課題とする。   This invention is made in view of such a problem, and when constructing a new structure in the lower part of the road where existing underground objects such as pipes storing communication cables, electric wires, etc., water pipes, etc. exist In addition, it is possible to provide a method for moving buried objects that can reduce the overall construction period by avoiding complicated work while protecting and curing the buried objects and reducing the excavation range. Let it be an issue.

前記課題を解決するために、本発明は、地中に通信ケーブル、電線、ガス管、上水道管を含む既設の地中埋設物が存在する道路の一部を開削して、この道路の下部に所定の構造物を構築する場合に、
前記道路に沿って前記埋設物を挿通可能な貫通部を有する埋設物用ボックスを設置する工程と、
前記埋設物用ボックスの前記貫通部内に前記埋設物を移設する工程と、
所定の構造物を構築すべき部分の地盤の両側に沿って前記道路と交差する山留め壁を形成する工程と、
山留め壁内を掘削して所定の構造物を構築する工程と、
を含み、
前記埋設物用ボックスには、通信、電気、ガス、上水道を含む前記埋設物を目的・用途に応じて分類載置する受台が前記埋設物用ボックスの長手方向に沿って設けられ、この受台に前記埋設物を載置して分類収納する
ことを特徴とする。
In order to solve the above-mentioned problems, the present invention cuts a part of a road where existing underground buried objects including communication cables, electric wires, gas pipes, and waterworks pipes exist in the ground, and When building a given structure,
A step of installing a buried object boxes with can be inserted through portions of the front SL buried object along the road,
Transferring the buried object in the penetrating portion of the buried object box;
Forming a mountain retaining wall that intersects the road along both sides of the ground of a portion where a predetermined structure is to be constructed;
A process of excavating the retaining wall to construct a predetermined structure;
Only including,
The buried box is provided with a cradle along the longitudinal direction of the buried box, on which the buried object including communication, electricity, gas, and water supply is classified and placed according to the purpose and application. The embedded objects are placed on a table and classified and stored .

なお、前記構造物は、様々なものが想定でき、道路の他、鉄道の軌道、地下街等の地下構造物等が例示できる。   Note that various structures can be assumed, and examples include roads, railway tracks, underground structures such as underground shopping malls, and the like.

本発明の埋設物の移設工法では、前記埋設物用ボックスは軽量で剛性に優れた鋼管、特
に角形鋼管を用いると良い。
The relocation method of buried objects of the present invention, prior SL buried object boxes steel pipe excellent in rigidity lightweight, may in particular use of the square tube.

更に、工期中における道路の交通を確保するため、前記山留め壁の上に覆工を施すことが必要となる場合がある。そのような覆工を施す際に、前記基礎に支持された埋設物用ボックスを基礎として用い、前記埋設物用ボックス上に覆工用材を載置することが可能である。   Furthermore, in order to secure road traffic during the construction period, it may be necessary to cover the mountain retaining wall. When performing such lining, it is possible to place a lining material on the buried object box using the buried object box supported by the foundation as a foundation.

このようにすれば、工事の省力化及び工期短縮が実現できる。   In this way, labor saving and shortening of the construction period can be realized.

本発明の埋設物の移設工法において、埋設物用ボックスには点検用のハッチを設けておくことができる。従来は地中に埋設してしまえば、点検のためには掘り起こさなければならなかったが、この埋設物用ボックスに収納すれば、点検用のハッチがあるため容易に点検が可能である。   In the method for transferring a buried object according to the present invention, an inspection hatch can be provided in the buried object box. Conventionally, if it was buried in the ground, it had to be dug up for inspection, but if it was housed in this box for buried objects, it can be easily inspected because of the hatch for inspection.

本発明の埋設物の移設工法によれば、前記埋設物用ボックスを予め設置しておき、山留め壁間の土(内部土)掘削前に工事の障害となる地中の埋設物を移設しておくため、山留め壁間の土(内部土)掘削後に地中の埋設物を移設する作業が不要となり、アンダーパス道路の構築に必要な期間が従来工法に比較して短くなる。   According to the method for relocating a buried object of the present invention, the buried box is installed in advance, and the buried object in the ground that becomes an obstacle to the construction is excavated before excavating the soil (inner soil) between the retaining walls. Therefore, it is not necessary to relocate underground objects after excavating the soil between the retaining walls (inner soil), and the time required for constructing the underpass road is shortened compared to the conventional method.

また、予め設置された埋設物用ボックスに、交差点部に埋設されている埋設物や、アンダーパス道路を横断する埋設物の移設を済ませておくことで、工事中も防護・養生の必要がなく、最終的な移設場所へ移設しておくため、破損などの恐れも少ない。   In addition, there is no need for protection and curing during construction by transferring the buried objects buried in the intersection or the buried objects crossing the underpass road to the previously installed buried boxes. Because it is relocated to the final relocation site, there is little risk of damage.

更に、本発明では、山留め壁間の土を掘削する前に、アンダーパス道路とすべき道路以外の道路に設けられた埋設物のうち、交差点部を通過する部分を、山留め壁の上に載置された埋設物用ボックスの貫通孔内に移設するので、山留め壁間の土(内部土)を掘削する
際には、埋設物が埋設物用ボックスによって保護される。従って、埋設物の養生が不要になる。
Further, in the present invention, before excavating the soil between the retaining walls, a portion passing through the intersection of the buried objects provided on the road other than the road that should be the underpass road is placed on the retaining wall. Since it is moved into the through hole of the buried object box, the buried object is protected by the buried object box when excavating the soil (inner soil) between the retaining walls. Therefore, curing of the buried object is not necessary.

更に、本発明では、山留め壁間の土(内部土)を掘削する際に、埋設物が保護部材によって保護されるので、埋設物の養生が不要になる。   Furthermore, in the present invention, when excavating the soil between the retaining walls (inner soil), the buried object is protected by the protection member, so that curing of the buried object becomes unnecessary.

更に、本発明では、貫通孔を有する埋設物用ボックスを使用するだけで、埋設物を保護できるので、構成を簡略化できる。   Furthermore, in this invention, since a buried thing can be protected only by using the box for buried objects which has a through-hole, a structure can be simplified.

なお、以上述べた各構成要素は、本発明の要旨を逸脱しない限り、互いに組み合わせることが可能である。   The constituent elements described above can be combined with each other without departing from the gist of the present invention.

以上説明したように、本発明によれば、土留め壁間の土を掘削する際に埋設物を養生をする必要がないので、養生部材及び養生作業の削減が可能である。   As described above, according to the present invention, it is not necessary to cure the buried object when excavating the soil between the retaining walls, so that the curing member and the curing work can be reduced.

また、既存の埋設物を埋設物用ボックスに収納するので、従来必要であった埋設物の設置エリアを大幅に縮小することができる結果、構造物の構築のための掘削範囲の縮小化が実現され、全体工期の短縮化及び工事費の削減が達成できる。   In addition, since the existing buried object is stored in the buried object box, the installation area for the buried object, which was necessary in the past, can be greatly reduced, resulting in a reduction in the excavation range for constructing the structure. As a result, the overall construction period can be shortened and the construction cost can be reduced.

以下、本発明の実施の形態に係るアンダーパス道路交差点部の埋設物の移設工法を添付した図1〜図12に基づいて詳細に説明する。 Hereinafter, a method for moving a buried object at an underpass road intersection according to an embodiment of the present invention will be described in detail with reference to FIGS.

[アンダーパス道路]
まず、本実施の形態のアンダーパス道路10を説明する。本実施の形態のアンダーパス道路10、10は、図1に示すように、上り側車線と下り側車線の2車線である。そして、この2車線のアンダーパス道路10、10は、それぞれコンクリート底版11、11が敷設されている。
[Underpass road]
First, the underpass road 10 of this Embodiment is demonstrated. As shown in FIG. 1, the underpass roads 10 and 10 of the present embodiment are two lanes, an up lane and a down lane. The two-lane underpass roads 10 and 10 are provided with concrete bottom slabs 11 and 11, respectively.

この2車線のアンダーパス道路10、10の両側には、自立性の山留め壁12、12が設けられている。また、本実施の形態では、この2車線のアンダーパス道路10、10の間にも、山留め壁13が設けられている。   Self-supporting mountain retaining walls 12 and 12 are provided on both sides of the two-lane underpass roads 10 and 10, respectively. In the present embodiment, a mountain retaining wall 13 is also provided between the two-lane underpass roads 10 and 10.

なお、この山留め壁13は、アンダーパス道路10、10の施工に際して山留めとして用いられるものであるが、アンダーパス道路10、10が完成した後もこの山留め壁13は、そのまま残されて上り側車線及び下り側車線の隔壁として用いられる。   The mountain retaining wall 13 is used as a mountain retaining when the underpass roads 10 and 10 are constructed. However, the mountain retaining wall 13 is left as it is even after the underpass roads 10 and 10 are completed, and the upstream lane is left. And used as a partition for the down lane.

上記の山留め壁12、13は、例えば直径800mmの鋼管が略隙間なく並べて打設され、鋼管矢板としての機能を果たすように構成されている(図3参照)。また、両側の山留め壁12、12の内側面、及び中央の山留め壁13の両側面には、内装板15がそれぞれ貼り付けられている(図1参照)。   The above-mentioned retaining walls 12 and 13 are configured such that, for example, steel pipes having a diameter of 800 mm are arranged side by side with substantially no gap and function as a steel pipe sheet pile (see FIG. 3). Moreover, the interior board 15 is each affixed on the inner surface of the mountain retaining walls 12 and 12 of both sides, and the both side surfaces of the central mountain retaining wall 13 (refer FIG. 1).

アンダーパス道路10、10の交差点部における両側の山留め壁12、12及び中央の山留め壁13の上には、アンダーパス道路10、10と交差する道路49をアンダーパス道路10、10の上側で通過させるため、覆工17が設けられている。一方、前記交差点部以外の部分は、覆工17がなく上部側が解放されている(図3参照)。   On the mountain retaining walls 12, 12 on both sides and the central mountain retaining wall 13 at the intersection of the underpass roads 10, 10, a road 49 intersecting with the underpass roads 10, 10 passes above the underpass roads 10, 10. For this purpose, a lining 17 is provided. On the other hand, the portions other than the intersections are free from the upper side without the lining 17 (see FIG. 3).

上記の覆工17は、長さがアンダーパス道路(上り車線側あるいは下り車線側)10の道幅より少し長い角形鋼管床版18を2本長手方向につなぎ合わせた状態で、アンダーパ
ス道路10と略直交する向きで隙間なく並べ、かつ角形鋼管床版18、18の上を舗装して構成される。
The lining 17 is formed by connecting two square steel pipe decks 18 having a length slightly longer than the width of the underpass road (upward lane side or down lane side) 10 in the longitudinal direction. They are arranged in a substantially orthogonal direction without gaps and paved on the square steel pipe decks 18, 18.

[埋設物用ボックス]
そして、通信、電気、ガス、上水道を含む地中の埋設物51を収納する埋設物用ボックス20が、図3に示すように、アンダーパス道路10、10の交差点部から所定距離(例えば3m)外れた部分にアンダーパス道路を横断するように(跨ぐように)複数(図3では2本)設けられている。この埋設物用ボックス20、20は、比較的入手が容易で軽量で剛性に優れた800mm×800mm程度の角形鋼管製(コンクリート製でもよい)であり、地中の埋設物51を一括して若しくはそれらの内のいくつかを分類して収納する。
[Box for buried objects]
And, as shown in FIG. 3, the buried object box 20 for storing the buried object 51 in the ground including communication, electricity, gas, and waterworks is a predetermined distance (for example, 3 m) from the intersection of the underpass roads 10 and 10. A plurality (two in FIG. 3) are provided so as to cross the underpass road at the disengaged portion. The buried object boxes 20 and 20 are made of a square steel pipe of about 800 mm × 800 mm, which is relatively easy to obtain, lightweight and excellent in rigidity (may be made of concrete), and the underground buried objects 51 are collectively or Some of them are classified and stored.

すなわち、埋設物用ボックス20に収める埋設物51(51a〜51g)は、図2(a)に示すように、目的・用途に応じて分類収納されており、埋設物用ボックス20内部の側方や下方にそれぞれの受台20a〜20gを介して懸架されている。すなわち、埋設物用ボックス20内部の長手方向に沿って、方形鋼板よりなる受台20a〜20eが埋設物用ボックス20内部の左側方に固定され、それぞれの受台20a〜20eに目的・用途に応じて、例えば比較的小径の電気、通信等の埋設物51a〜51eが分類収納されている。また、埋設物用ボックス20内部の長手方向に沿って、方形鋼板よりなる受台20f、20gが埋設物用ボックス20内部の右側方に固定され、それぞれの受台20f、20gに比較的大径の水道管、ガス管等の埋設物51f、51gが分類収納されている。   That is, the embedded objects 51 (51a to 51g) stored in the embedded object box 20 are classified and stored according to the purpose and application as shown in FIG. It suspends via each receiving stand 20a-20g. That is, the cradle 20a-20e which consists of a rectangular steel plate is fixed to the left side inside the buried object box 20 along the longitudinal direction inside the buried object box 20, and each cradle 20a-20e is used for the purpose and application. Accordingly, for example, buried objects 51a to 51e having relatively small diameters such as electricity and communication are classified and stored. In addition, along the longitudinal direction inside the buried object box 20, pedestals 20f, 20g made of rectangular steel plates are fixed to the right side inside the buried object box 20, and each of the cradle 20f, 20g has a relatively large diameter. The buried objects 51f and 51g such as water pipes and gas pipes are classified and stored.

[埋設物用ボックスの基礎]
この埋設物用ボックス20、20の設置位置を交差点部から外れた位置とする場合、アンダーパス道路完成時は道路上方を横断することとなる。
[Fundamental box basics]
When the installation position of the buried object boxes 20 and 20 is set to a position deviating from the intersection, the underpass road is completed when the underpass road is completed.

また、この埋設物用ボックス20、20は、アンダーパス道路10、10の山留め壁間の土(内部土)掘削工事前に予め埋設される。そして、埋設物用ボックス20は、アンダーパス道路10、10を構築する際に、山留め壁12、13、12に用いた鋼管を基礎として支持されている。   Further, the buried object boxes 20 and 20 are buried in advance before the soil (internal soil) excavation work between the mountain retaining walls of the underpass roads 10 and 10. And when the underpass roads 10 and 10 are constructed, the buried object box 20 is supported on the basis of the steel pipes used for the retaining walls 12, 13 and 12.

更に、この埋設物用ボックス20を山留め壁12、13、12で支持する際は、図1及び図2(a)に示すように、ボックス受け梁21を介して埋設物用ボックス20を載置する。   Furthermore, when the buried object box 20 is supported by the retaining walls 12, 13, 12, the buried object box 20 is placed via the box receiving beam 21 as shown in FIGS. 1 and 2A. To do.

次に、このアンダーパス道路10の施工方法について説明し、その中で埋設物の移設工法も説明する。なお、ここでは、一方のアンダーパス道路(上り線側)10を構築する場合について説明するが、もう一方のアンダーパス道路(下り線側)10を構築する場合も同様である。   Next, a construction method for the underpass road 10 will be described, and a method for moving the buried object will be described therein. Here, the case where one underpass road (upline side) 10 is constructed will be described, but the same applies to the case where the other underpass road (downline side) 10 is constructed.

この実施の形態のアンダーパス道路10の施工方法は、図4の施工流れ図に示すように、部分的に交通を規制する工程、埋設物用ボックスの設置及び埋設物の移設工程、簡易山留め工程、鋼管矢板打設工程、台座設置工程、床版設置部の掘削工程、角形鋼管床版の設置工程、内部掘削工程、床版設置部周囲の埋め戻し工程、全面的に交通規制を解除し開放する工程、の順に施工する。   As shown in the construction flow chart of FIG. 4, the construction method of the underpass road 10 according to this embodiment includes a step of partially restricting traffic, a step of installing a buried box and a step of moving a buried item, a simple mountain retaining step, Steel pipe sheet pile placing process, pedestal installation process, floor slab installation part excavation process, square steel pipe floor slab installation process, internal excavation process, backfilling process around the floor slab installation part, traffic control is completely released and released Install in order of process.

すなわち、部分的に交通を規制する工程の後、埋設物用ボックスの設置及び埋設物の移設工程を実施する。   That is, after the step of partially restricting traffic, the installation of the box for buried objects and the process of moving the buried objects are performed.

(埋設物用ボックスの設置及び埋設物の移設工程)
この移設工程では、埋設物51を収納する埋設物用ボックス20を、図3に示すように
、アンダーパス道路10、10の交差点部から所定距離(例えば3m)外れた位置にアンダーパス道路を横断するように2本設置する。
(Installation of buried object boxes and relocation process of buried objects)
In this relocation process, the buried object box 20 that stores the buried object 51 crosses the underpass road at a position that is off a predetermined distance (for example, 3 m) from the intersection of the underpass roads 10 and 10, as shown in FIG. Install two so that it does.

そして、この埋設物用ボックス20を設置する際は、図1及び図2(a)に示すように、埋設物用ボックス20をボックス受け梁21を介して予めアンダーパス道路10、10を横断するように打設する。   And when installing this box 20 for buried objects, as shown in FIG.1 and FIG.2 (a), the box 20 for buried objects crosses the underpass roads 10 and 10 beforehand via the box receiving beam 21. FIG. To be placed.

次に、地中の埋設物51を埋設物用ボックス20内に一括して若しくはそれらの内のいくつかを分類して収納する。   Next, the underground buried objects 51 are stored in the buried object box 20 in a lump or some of them are classified.

すなわち、埋設物用ボックス20に収める埋設物51(51a〜51g)は、図2(a)に示すように、目的・用途に応じて分類収納されており、埋設物用ボックス20内部の側方や下方にそれぞれの受台20a〜20gを介して懸架する。   That is, the embedded objects 51 (51a to 51g) stored in the embedded object box 20 are classified and stored according to the purpose and application as shown in FIG. Suspend downward via the respective cradles 20a to 20g.

(部分的に交通を規制する工程・簡易山留め工程)
次に、アンダーパス道路10にすべき道路を部分的に交通規制した後、山留め壁を設置する位置に沿って簡易山留め40(図5参照)を施工する。この簡易山留め工程では、アンダーパス道路10にすべき道路に対し、山留め壁12、13、12(図1参照)を設置する位置に沿って、例えば、幅3m、深さ1mの溝を掘削し、掘削した壁面に矢板を隙間無く設置する。
(鋼管矢板打設工程)
次に、図5に示すように、簡易山留め40の位置に、複数の鋼管14を打設して自立性の山留め壁12、13を設ける。この鋼管14は、略隙間なく並べて打設されて鋼管矢板を形成し、鋼管14の打設には、全周旋回杭打機34などを使用する。
(台座設置工程)
次に、図6に示すように、鋼管矢板の頭部に台座61を設置する。また、台座61は、頂部に、角形鋼管床版18を載置する溝が形成されている。
(床版設置部の掘削工程)
次に、図7に示すように、山留め壁12側の簡易山留めと山留め壁13側の簡易山留めの間である床版設置部を所定の深さ掘削する。
(角形鋼管床版の設置工程)
図8に示すように、台座61,61との間に、隙間無く角形鋼管床版18を設置する。なお、角形鋼管床版18は、台座61の頂部に載置される。
(Partial traffic regulation process / Simple mountain retaining process)
Next, after partially restricting traffic on the road to be the underpass road 10, a simple mountain retaining 40 (see FIG. 5) is constructed along the position where the mountain retaining wall is installed. In this simple mountain retaining process, for example, a groove having a width of 3 m and a depth of 1 m is excavated along the position where the mountain retaining walls 12, 13, 12 (see FIG. 1) are installed on the road to be the underpass road 10. Install sheet piles on the excavated wall without any gaps.
(Steel pipe sheet pile placing process)
Next, as shown in FIG. 5, a plurality of steel pipes 14 are driven at the position of the simple mountain retaining 40 to provide self-supporting mountain retaining walls 12 and 13. The steel pipes 14 are driven side by side with substantially no gap to form a steel pipe sheet pile, and for the placement of the steel pipe 14, an all-round turning pile driver 34 or the like is used.
(Pedestal installation process)
Next, as shown in FIG. 6, the base 61 is installed in the head of a steel pipe sheet pile. Further, the pedestal 61 is formed with a groove on the top for placing the square steel pipe deck 18.
(Excavation process of floor slab installation part)
Next, as shown in FIG. 7, the floor slab installation part between the simple mountain retaining on the mountain retaining wall 12 side and the simple mountain retaining on the mountain retaining wall 13 side is excavated to a predetermined depth.
(Installation process of square steel pipe deck)
As shown in FIG. 8, the square steel pipe floor slab 18 is installed between the pedestals 61 and 61 without a gap. The square steel pipe floor slab 18 is placed on the top of the pedestal 61.

図9に示すように、隙間無く設置された角形鋼管床版18の上面に舗装するなど覆工を行い、上り線側アンダーパス道路10の床版部分の設置を完了させる。   As shown in FIG. 9, lining is performed such as paving on the upper surface of the square steel pipe floor slab 18 that is installed without gaps, and the installation of the floor slab portion of the upside underpass road 10 is completed.

次に、下り線側アンダーパス道路10の床版部分を構築する。この構築は、上り線側アンダーパス道路10の床版部分の構築で説明した施工方法と同様に、部分的に交通を規制する工程、簡易山留め工程、鋼管矢板打設工程、台座設置工程、床版設置部の掘削工程、角形鋼管床版の設置工程、の順に施工する。   Next, the floor slab portion of the down line side underpass road 10 is constructed. This construction is similar to the construction method described in the construction of the floor slab portion of the up-line side underpass road 10, a process for partially restricting traffic, a simple mountain retaining process, a steel pipe sheet pile placing process, a pedestal installing process, a floor It is constructed in the order of the excavation process of the plate installation section and the installation process of the square steel pipe deck.

図10は、下り線側アンダーパス道路10の床版部分の設置が完了した状態を示す。
(内部掘削工程)
図11に示すように、鋼管矢板(山留め壁12)と鋼管矢板(山留め壁13)との間にある土を掘削し、上り線側アンダーパス道路10部分を開通させる。その際、交差点から離れるに従って徐々に浅くなるように適宜な勾配を付けて掘削する。次に、鋼管矢板(山留め壁13)と鋼管矢板(山留め壁12)との間にある土を掘削し、下り線側アンダーパス道路10部分を開通させる。この場合も、上り線側と同様に、交差点から離れるに従って徐々に浅くなるように適宜な勾配を付けて掘削する。
(床版設置部周囲の埋め戻し工程・全面的に交通規制を解除し開放する工程)
図1に示すように、上り及び下りの2列に設けられているアンダーパス道路10、10にそれぞれコンクリート底版11、11を敷設する。そして、両側の山留め壁12、12の内側面、及び中央の山留め壁13の両側面に内装板15をそれぞれ貼り付ける。更に、床版設置部周囲の掘削後を埋め戻し、全面的に交通規制を解除し開放する。
(埋設物用ボックス20の設置効果)
従来のアンダーパス道路工事では、工事の際に地中の埋設物を移設する場合、山留めの施工、内部掘削を行いながら、または一時中断して実施しなければならず、アンダーパス道路の構築に多大な期間(工期)が必要であった。
FIG. 10 shows a state where the installation of the floor slab portion of the down line side underpass road 10 is completed.
(Internal drilling process)
As shown in FIG. 11, the soil between the steel pipe sheet pile (mountain wall 12) and the steel pipe sheet pile (mountain wall 13) is excavated, and the upward line side underpass road 10 portion is opened. At that time, excavation is performed with an appropriate gradient so that the depth gradually decreases as the distance from the intersection increases. Next, the soil between the steel pipe sheet pile (mountain wall 13) and the steel pipe sheet pile (mountain wall 12) is excavated, and the downward line side underpass road 10 portion is opened. Also in this case, similarly to the up line side, excavation is performed with an appropriate gradient so that the depth gradually decreases as the distance from the intersection increases.
(Refilling process around the floor slab installation area / Process to completely release and release traffic restrictions)
As shown in FIG. 1, concrete bottom slabs 11 and 11 are laid on underpass roads 10 and 10 provided in two rows of up and down, respectively. And the interior board 15 is affixed on the inner surface of the mountain retaining walls 12 and 12 of both sides, and the both sides of the central mountain retaining wall 13, respectively. Furthermore, after the excavation around the floor slab installation section, it will be backfilled, and traffic restrictions will be completely released and released.
(Effect of installation of the box 20 for buried objects)
In conventional underpass road construction, when transferring underground objects during construction, it must be carried out with construction of a mountain stop, internal excavation, or temporarily suspended, for the construction of an underpass road. An enormous period (work period) was required.

本実施の形態の埋設物の移設工法では、埋設物用ボックス20を予めアンダーパス道路交差点部の交差点内もしくは交差点部から外れた部分に設置し、山留め壁間の土(内部土)掘削前に工事の障害となる地中埋設物をこの埋設用ボックス20内に移設しておくため、山留め壁間の土(内部土)掘削後に地中の埋設物を移設する必要がない。従って、アンダーパス道路の構築に必要な期間が従来工法に比較して短くなる。   In the method for relocating a buried object according to the present embodiment, the buried object box 20 is installed in advance in the intersection of the underpass road intersection or in a part off the intersection, and before excavating the soil (inner soil) between the retaining walls. Since the underground object that obstructs the construction is relocated in the burying box 20, it is not necessary to relocate the underground object after excavating the soil (internal soil) between the retaining walls. Therefore, the period required for the construction of the underpass road is shortened compared to the conventional method.

この事前に設置しておく埋設物用ボックス20に、交差点部に埋設されている地中埋設物や、アンダーパス道路を横断する地中の埋設物を、山留め壁間の土(内部土)掘削前に移設を済ませておくことで、工事中も防護・養生の必要がなく、工事の初期段階で、これらを最終的な移設場所へ予め移設しておくため、破損などの恐れも少ない。   Excavation between the retaining walls in the underground box embedded in the intersection or underpass road in the underground box 20 to be installed in advance. By relocating in advance, there is no need for protection and curing during construction, and since these are relocated in advance to the final relocation site at the initial stage of construction, there is little risk of damage.

また、図12に示すように、埋設物用ボックス20を用いた場合、従来に比して省スペース化が図れるので埋設物用空間が圧縮でき、アンダーパス道路の道路盤が浅い位置で施工できる。すなわち、埋設物ボックス20を設置する場合は、ボックスカルバート上部にある地中埋設物の設置のための2.5m以上の深さ(土かぶり)は必要なくなり、その結果、道路の路盤深さを浅くでき、アンダーパス道路の延長を短くすることができる。よって、埋設物用ボックス20を設置した場合は、前述の実施の形態のアンダーパス区間長L2(図12(b)参照)が、図12(a)に示す従来の工法の区間長L1に比して短くできる。特に、埋設物用ボックス20を、交差点部から外れた位置に複数設ける場合には、各々の埋設物用ボックス20をさらに小型化できるので、埋設物の設置スペースはより縮小される。   In addition, as shown in FIG. 12, when the buried object box 20 is used, the space for the buried object can be reduced as compared with the conventional case, so that the space for the buried object can be compressed and the road board of the underpass road can be constructed at a shallow position. . In other words, when the buried object box 20 is installed, a depth of 2.5 m or more (earth cover) for the installation of the underground buried object at the upper part of the box culvert is not required, and as a result, the roadbed depth of the road is reduced. It can be shallow and the length of the underpass road can be shortened. Therefore, when the embedded box 20 is installed, the underpass section length L2 (see FIG. 12B) of the above-described embodiment is compared with the section length L1 of the conventional method shown in FIG. Can be shortened. In particular, when a plurality of buried object boxes 20 are provided at positions deviated from the intersection, each buried object box 20 can be further reduced in size, and the installation space for the buried object is further reduced.

前述の実施の形態では埋設物用ボックス20の設置位置を交差点部から所定距離離れた位置とする場合(図3参照)で説明したが、埋設物用ボックス20の設置位置は交差点部の内側の位置に設けても良い。次に、埋設物用ボックス20の設置位置を交差点部の内側の位置に設けた別の実施の形態を図13及び図2(b)に基づき説明する。なお、図13及び図2(b)に使用する符号で前述の実施の形態で用いた符号と同一のものは同一機能を有するものであり、その説明の詳細を省略する。
(別の実施の形態)
別の実施の形態では、通信、電気、ガス、上水道を含む地中の埋設物51を収納する埋設物用ボックス20が、図13に示すように、アンダーパス道路10、10の交差点部の内側の位置にアンダーパス道路を横断するように1本設けられている。この埋設物用ボックス20は、前述の実施の形態と同様に、角形鋼管製であり、地中の埋設物51を一括して若しくはそれらの内のいくつかを分類して収納する。
In the above-described embodiment, the case where the installation position of the buried object box 20 is set at a predetermined distance from the intersection (see FIG. 3) has been described. However, the installation position of the buried object box 20 is located inside the intersection. You may provide in a position. Next, another embodiment in which the installation position of the buried object box 20 is provided at a position inside the intersection will be described with reference to FIGS. 13 and 2B. In addition, the code | symbol used in FIG.13 and FIG.2 (b) and the code | symbol same as the code | symbol used in the above-mentioned embodiment has the same function, The detail of the description is abbreviate | omitted.
(Another embodiment)
In another embodiment, the buried object box 20 for storing underground buried objects 51 including communication, electricity, gas, and waterworks is located inside the intersection of the underpass roads 10 and 10 as shown in FIG. One is provided so as to cross the underpass road. This embedded object box 20 is made of a square steel pipe, as in the above-described embodiment, and stores the underground embedded objects 51 collectively or some of them.

すなわち、埋設物用ボックス20に収める埋設物51(51a〜51g)は、図2(b)に示すように、目的・用途に応じて分類収納されており、埋設物用ボックス20内部の側方や下方にそれぞれの受台20a〜20gを介して懸架されている。すなわち、埋設物用ボックス20内部の長手方向に沿って、方形鋼板よりなる受台20a〜20eが埋設物用ボックス20内部の左側方に固定され、それぞれの受台20a〜20eに目的・用途に
応じて、例えば比較的小径の電気、通信等の埋設物51a〜51eが分類収納されている。また、埋設物用ボックス20内部の長手方向に沿って、方形鋼板よりなる受台20f、20gが埋設物用ボックス20内部の右側方に固定され、それぞれの受台20f、20gに比較的大径の水道、ガス等の埋設物51f、51gが分類収納されている。
That is, the embedded objects 51 (51a to 51g) stored in the embedded object box 20 are classified and stored according to the purpose and application as shown in FIG. It suspends via each receiving stand 20a-20g. That is, the cradle 20a-20e which consists of a rectangular steel plate is fixed to the left side inside the buried object box 20 along the longitudinal direction inside the buried object box 20, and each cradle 20a-20e is used for the purpose and application. Accordingly, for example, buried objects 51a to 51e having relatively small diameters such as electricity and communication are classified and stored. In addition, along the longitudinal direction inside the buried object box 20, pedestals 20f, 20g made of rectangular steel plates are fixed to the right side inside the buried object box 20, and each of the cradle 20f, 20g has a relatively large diameter. The buried objects 51f and 51g such as water and gas are classified and stored.

[埋設物用ボックスの基礎]
この埋設物用ボックス20の設置位置を交差点部の内側の位置とする場合、アンダーパス道路完成時は道路上方を横断することとなる。そこで、この埋設物用ボックス20は、アンダーパス道路10、10の山留め壁間の土(内部土)掘削工事前に予め埋設される。そして、この埋設物用ボックス20を埋設する際、図2(b)に示すように、埋設物用ボックス20は、山留め壁12、13、12に用いた鋼管を基礎として支持されている。また、埋設物用ボックス20を予めアンダーパス道路10、10を横断するように打設しておく。なお、埋設物用ボックス20は、ボックス受け梁21介して山留め壁12,13に載置される。
[Fundamental box basics]
When the installation position of the buried object box 20 is set to a position inside the intersection, when the underpass road is completed, the upper side of the road is crossed. Therefore, the buried object box 20 is buried in advance before the soil (internal soil) excavation work between the mountain retaining walls of the underpass roads 10 and 10. And when burying this buried object box 20, as shown in FIG.2 (b), the buried object box 20 is supported on the basis of the steel pipe used for the mountain retaining walls 12,13,12. Further, the buried object box 20 is placed in advance so as to cross the underpass roads 10 and 10. The buried object box 20 is placed on the mountain retaining walls 12 and 13 via the box receiving beams 21.

更に、覆工用の鋼材を載置する際に、前記基礎(山留め壁12、13、12)に支持された埋設物用ボックス20及びボックス受け梁21を基礎として兼用させ、埋設物用ボックス20の上に覆工用の鋼材を載置する(図2(b)参照)。   Further, when the steel material for lining is placed, the buried object box 20 and the box receiving beam 21 supported by the foundation (mounting walls 12, 13, 12) are also used as the foundation, and the buried object box 20 A steel material for lining is placed on (see FIG. 2B).

なお、本発明のアンダーパス道路交差点部の埋設物の移設工法において、埋設物用ボックスには点検用のハッチ(図示せず)を設けておくことができる。従来は地中に埋設してしまえば、点検のためには通信ケーブル等の埋設物を掘り起こさなければならなかったが、この埋設物用ボックスに収納すれば、点検用のハッチがあるため容易に点検が可能である。 In addition, in the transfer method of the buried object of the underpass road intersection of the present invention, an inspection hatch (not shown) can be provided in the buried object box. Conventionally, if buried in the ground, it was necessary to dig up a buried object such as a communication cable for inspection, but if it is stored in this buried object box, there will be a hatch for inspection and it will be easy. Inspection is possible.

本発明に係る第1実施形態の交差点におけるアンダーパス道路の正面図である。It is a front view of the underpass road in the intersection of a 1st embodiment concerning the present invention. 埋設物用ボックスを基礎により支持している状態を示す図であり、図2(a)は第1実施形態の埋設物用ボックスの基礎を示し、図2(b)は別の実施形態の埋設物用ボックスの基礎を示す。It is a figure which shows the state which is supporting the box for buried objects by the foundation, Fig.2 (a) shows the foundation of the box for buried objects of 1st Embodiment, FIG.2 (b) is the embedding of another embodiment. The basics of the material box are shown. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の構造を示す斜視図である。It is a perspective view which shows the structure of the underpass road in the intersection of 1st Embodiment which concerns on this invention. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す工程図である。It is process drawing which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、鋼管矢板の打設工程を示す図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is a figure which shows the placement process of a steel pipe sheet pile. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、台座の設置工程を示す図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is a figure which shows the installation process of a base. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、床版設置部の掘削工程図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is an excavation process figure of a floor slab installation part. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、角形鋼管床版の設置工程図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is an installation process figure of a square steel pipe deck. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、上り車線側の床版設置完了図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is a floor slab installation completion figure by the side of an up lane. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、下り車線側の床版の施工工程図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is a construction process figure of the floor slab on the down lane side. 本発明に係る第1実施形態の交差点におけるアンダーパス道路の施工方法を示す図であり、内部の掘削工程図である。It is a figure which shows the construction method of the underpass road in the intersection of 1st Embodiment which concerns on this invention, and is an internal excavation process figure. 従来工法と第1実施形態の工法におけるアンダーパス区間長の比較図である。It is a comparison figure of the underpass section length in the conventional construction method and the construction method of a 1st embodiment. 本発明に係る別の実施形態の交差点におけるアンダーパス道路の構造を示す斜視図である。It is a perspective view which shows the structure of the underpass road in the intersection of another embodiment which concerns on this invention. 一般的な道路に埋設された埋設物を示す図である。It is a figure which shows the embedment embed | buried in the general road. 従来例に係る交差点におけるアンダーパス道路の施工方法を示す図であり、埋設物の養生方法を示す断面図である。It is a figure which shows the construction method of the underpass road in the intersection which concerns on a prior art example, and is sectional drawing which shows the curing method of an embedded object. 従来例に係る交差点におけるアンダーパス道路の構造を示す図であり、ボックスカルバートの設置方法を示す断面図である。It is a figure which shows the structure of the underpass road in the intersection which concerns on a prior art example, and is sectional drawing which shows the installation method of a box culvert. 従来例に係るアンダーパス道路を構成するボックスカルバートと埋設物との位置関係を示す断面図である。It is sectional drawing which shows the positional relationship of the box culvert which comprises the underpass road which concerns on a prior art example, and an embedded object. 従来例に係るアンダーパス道路を構成するボックスカルバートである。It is a box culvert which constitutes an underpass road concerning a conventional example.

符号の説明Explanation of symbols

10 アンダーパス道路
11 コンクリート底版
12、13 山留め壁
14 鋼管
15 内装板
17 覆工
18 角形鋼管床版
20 埋設物用ボックス
21 ボックス受け梁
30 アンダーパス道路にすべき道路
31 土
49 アンダーパス道路と交差する道路
50 道路
51(51a〜51g) 埋設物
52 鋼矢板
53 山留め壁
54 覆工
55 土
56 吊り下げ部材
57 空間
58 ボックスカルバート
59 アンダーパス道路
60 アンダーパス道路と交差する道路
61 台座
DESCRIPTION OF SYMBOLS 10 Underpass road 11 Concrete bottom slab 12, 13 Retaining wall 14 Steel pipe 15 Interior board 17 Covering 18 Square steel pipe floor slab 20 Box 21 for buried objects Box receiving beam 30 Road 31 which should be underpass road Soil 49 Crossing with underpass road Road 50 Road 51 (51a to 51g) Buried object 52 Steel sheet pile 53 Retaining wall 54 Covering 55 Earth 56 Suspension member 57 Space 58 Box culvert 59 Underpass road 60 Road 61 crossing the underpass road

Claims (3)

地中に通信ケーブル、電線、ガス管、上水道管を含む既設の地中埋設物が存在する道路の一部を開削して、この道路の下部に所定の構造物を構築する場合に、
前記道路に沿って前記埋設物を挿通可能な貫通部を有する埋設物用ボックスを設置する工程と、
前記埋設物用ボックスの前記貫通部内に前記埋設物を移設する工程と、
所定の構造物を構築すべき部分の地盤の両側に沿って前記道路と交差する山留め壁を形成する工程と、
山留め壁内を掘削して所定の構造物を構築する工程と、
を含み、
前記埋設物用ボックスには、通信、電気、ガス、上水道を含む前記埋設物を目的・用途に応じて分類載置する受台が前記埋設物用ボックスの長手方向に沿って設けられ、この受台に前記埋設物を載置して分類収納することを特徴とする埋設物の移設工法。
When excavating a part of a road where existing underground buried objects including communication cables, electric wires, gas pipes, and water pipes exist in the ground, and building a predetermined structure below this road,
A step of installing a buried object boxes with can be inserted through portions of the front SL buried object along the road,
Transferring the buried object in the penetrating portion of the buried object box;
Forming a mountain retaining wall that intersects the road along both sides of the ground of a portion where a predetermined structure is to be constructed;
A process of excavating the retaining wall to construct a predetermined structure;
Only including,
The buried box is provided with a cradle along the longitudinal direction of the buried box, on which the buried object including communication, electricity, gas, and water supply is classified and placed according to the purpose and application. A method for relocating an embedded object , wherein the embedded object is placed on a table and classified and stored .
前記埋設物用ボックスは鋼管であることを特徴とする請求項1に記載の埋設物の移設工法。 The method for transferring an embedded object according to claim 1, wherein the box for embedded object is a steel pipe . 工期中における道路の交通を確保するため覆工を施す際に、前記基礎に支持された埋設物用ボックスを基礎として用い、前記埋設物用ボックス上に覆工用材を載置することを特徴とする請求項1又は2に記載の埋設物の移設工法。 When carrying out lining to ensure road traffic during the construction period, the laying material is placed on the burying material box using the burying material box supported by the foundation as a foundation. The method for moving a buried object according to claim 1 or 2 .
JP2006097321A 2006-03-31 2006-03-31 Relocation method for buried objects Active JP4630215B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006097321A JP4630215B2 (en) 2006-03-31 2006-03-31 Relocation method for buried objects

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006097321A JP4630215B2 (en) 2006-03-31 2006-03-31 Relocation method for buried objects

Publications (2)

Publication Number Publication Date
JP2007270512A JP2007270512A (en) 2007-10-18
JP4630215B2 true JP4630215B2 (en) 2011-02-09

Family

ID=38673598

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006097321A Active JP4630215B2 (en) 2006-03-31 2006-03-31 Relocation method for buried objects

Country Status (1)

Country Link
JP (1) JP4630215B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7284800B1 (en) 2021-11-18 2023-05-31 西武建設株式会社 Construction method of underpass under railroad tracks

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000045299A (en) * 1998-07-24 2000-02-15 Toda Constr Co Ltd Supporting method of underground buried structure
JP2005273302A (en) * 2004-03-25 2005-10-06 Maeda Corp Under path constructing method at intersection, and under path structure, as well as underground structure and method of constructing the same
JP2006002399A (en) * 2004-06-16 2006-01-05 Maeda Corp Construction method and structure of underpass road in intersection

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000045299A (en) * 1998-07-24 2000-02-15 Toda Constr Co Ltd Supporting method of underground buried structure
JP2005273302A (en) * 2004-03-25 2005-10-06 Maeda Corp Under path constructing method at intersection, and under path structure, as well as underground structure and method of constructing the same
JP2006002399A (en) * 2004-06-16 2006-01-05 Maeda Corp Construction method and structure of underpass road in intersection

Also Published As

Publication number Publication date
JP2007270512A (en) 2007-10-18

Similar Documents

Publication Publication Date Title
AU2005300344B2 (en) Communications ducting system and method of laying same
CN113482044A (en) Power pipeline relocation method for invading subway station structure
JP4361839B2 (en) Construction method and structure of underpass road at intersection
CN104184097B (en) Non-migration suspension protection system and method for communication pipes and cables
KR20060097891A (en) Pipe roof structures and construction method of pipe roof structures
JP4630215B2 (en) Relocation method for buried objects
CA2803782C (en) Systems and apparatus for protecting subsurface conduit and methods of making and using the same
KR101682541B1 (en) Culvert crossing buried pipeline construction and pipeline laying method using the same
US5582477A (en) Finned container bases
CN109797776B (en) Construction method for underground pipe gallery to meet cross pipeline based on open cut method
KR101049061B1 (en) Underground pipeline multi-protector and method for constructing undergound pipeline using the same
KR101427812B1 (en) Open cut method for constructing an underground structure
KR101624518B1 (en) Live wire precast manhole and its construction method
KR200385542Y1 (en) Pipe roof structures
JP3938777B2 (en) Construction method of crossing underground structure and crossing underground structure
KR20200024519A (en) Solar panel installing structure using linear site
KR102170561B1 (en) Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert
Konstantis et al. Box jacking/pushing method for tunnel construction in rock: Doha Metro, Gold Line Project
CN214940194U (en) Supporting construction based on uncovered formula structure in underground
JP7215436B2 (en) sidewalk boundary block
KR100833700B1 (en) Pipe roof structures
JP5970305B2 (en) Pipe laying method
JP2020066973A (en) Construction method of lifeline
JP6121504B1 (en) Road lining method
KR101106196B1 (en) Wall pannel for aggregate construction to protect underground pipe line

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080407

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100219

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100713

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100819

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20101019

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20101112

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131119

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4630215

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131119

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350