KR102170561B1 - Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert - Google Patents

Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert Download PDF

Info

Publication number
KR102170561B1
KR102170561B1 KR1020200032414A KR20200032414A KR102170561B1 KR 102170561 B1 KR102170561 B1 KR 102170561B1 KR 1020200032414 A KR1020200032414 A KR 1020200032414A KR 20200032414 A KR20200032414 A KR 20200032414A KR 102170561 B1 KR102170561 B1 KR 102170561B1
Authority
KR
South Korea
Prior art keywords
culvert
installation
manhole
steps
conduit
Prior art date
Application number
KR1020200032414A
Other languages
Korean (ko)
Inventor
유조웅
Original Assignee
(주)세정엔지니어링
주식회사 지아이에스21
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)세정엔지니어링, 주식회사 지아이에스21 filed Critical (주)세정엔지니어링
Priority to KR1020200032414A priority Critical patent/KR102170561B1/en
Application granted granted Critical
Publication of KR102170561B1 publication Critical patent/KR102170561B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/07Tunnels or shuttering therefor preconstructed as a whole or continuously made, and moved into place on the water-bed, e.g. into a preformed trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/06Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/40Protecting water resources
    • Y02A20/402River restoration

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

An objective of the present invention is to shorten construction periods. According to an embodiment of the present invention, an eco-friendly excavation-type power line river crossing method using a line protection PC culvert to install a new cable comprises: a preliminary preparation step including a PC culvert manufacturing step and an obstruction investigation and agreement step; a preliminary construction step including a construction sign and safety facility installation step, a walking and bicycle road detour bridge installation step, a pollution prevention film installation step, a construction way installation step, and a cofferdam installation step; a PC culvert installation step including an earth-retaining temporary facility assembly and installation step, a bed excavation step, a bottom leveling step, a foundation sand laying step, a lower culvert installation step, a steel strand tension step, an anchor groove mortar filling step, a wire pipe installation step, a spacer installation step, a sand laying and compacting step, a spacer removal step, an upper culvert installation step, a backfilling step, an earth-retaining temporary facility removal step, and a remaining soil discharge step; a cable installation step including a conduction test step and a step of installing a new cable; and a finishing step including a river original state restoration step and an equipment and tool discharge step.

Description

관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법{Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert} Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert}

본 발명은 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 관한 것으로, 더욱 상세하게는 신설, 보수 및 증설이 용이한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 관한 것이다.The present invention relates to a river crossing method for an eco-friendly open and close power pipe using a pipeline protection PC culvert, and more particularly, to an eco-friendly open and close power pipe crossing method using a pipe protection PC culvert, which is easy to install, repair and expand. .

일반적으로, 하천 및 해저 관로를 횡단하는 관로의 매설시에는 수심이 낮은 지역을 선택하고, 뻘 층 혹은 하천바닥을 광범위하게 개착하여 매설(개착식 공법)하거나, 시트파일 공법을 이용하여 매설하는 방법을 선택하고 있다.In general, when burying a pipeline that crosses a river or a submarine pipeline, select a low-depth area, and bury the ground floor or river floor extensively (cracking method), or using a sheet pile method. You are choosing.

이때, 개착식 공법 및 시트파일 공법은 광범위한 환경파괴가 발생하는 문제점이 있다. 즉, 하천 및 해저 관로를 횡단하는 관로의 매설시 태풍, 해일 및 준설장비로부터 관로가 보호되도록 하기 위해, 관로는 일정 깊이 이상으로 매설하여야 하는데, 개착식 공법과 시트파일 공법은 뻘 층 및 하천바닥을 훼손하여 이루어지므로, 생태계를 파괴하여 심각한 환경문제를 유발시키게 된다.At this time, there is a problem in that a wide range of environmental destruction occurs in the open-ended method and sheet pile method. In other words, in order to protect the pipeline from typhoons, tsunamis and dredging equipment when the pipelines crossing rivers and submarine pipelines are buried, the pipelines must be buried at a certain depth or more. Because it is done by damaging the system, it destroys the ecosystem and causes serious environmental problems.

한편, 비개착식 굴착공법은 "대한민국 등록특허 제10-1436816호(2014.08.27)"와 같이, 도로를 직접 굴착하지 않고 지하에 터널을 만드는 공사 방식이다. 이와 같은 비개착식 굴착공법은 통상 지향성압입공법(H.D.D공법; Horizontal Directional Drilling method)으로 알려져 있고, 이 공법은 타 공법에 비해 사회적 비용절감, 안전성 확보에 우수한 것으로 인식되고 있다.On the other hand, the non-cracking excavation method is a construction method of making a tunnel underground without directly excavating a road, such as "Korea Patent Registration No. 10-1436816 (2014.08.27)". Such non-cracking excavation method is commonly known as the H.D.D method (Horizontal Directional Drilling method), and this method is recognized to be superior to other methods in reducing social cost and securing safety.

그러나, 이와 같은 지향성압입공법 또한 특성상 굴착과정에서 발생하는 많은 양의 벤토나이트 오니(벤토나이트 혼합액과 굴착시 혼합되는 점토, 잔토, 이물질 등)에 의해 심각한 환경피해 및 주변환경을 오염시키는 문제점이 있고, 모래나 자갈층에는 홀이 형성되지 않으며, 암반 구간에는 공정이 용이하지 않아 많은 시간이 소요되며, 개착식에 비해 월등한 시공성을 발휘하지 못한다는 문제점 또한 발생한다.However, due to the nature of this directional press-in method, there is also a problem of serious environmental damage and contamination of the surrounding environment due to a large amount of bentonite sludge (clay, residual soil, foreign substances, etc., which are mixed with the bentonite mixture during excavation), which occurs in the excavation process. B. Holes are not formed in the gravel layer, and the process is not easy in the rock section, so it takes a lot of time, and there is also a problem that it does not exhibit superior constructability compared to the open-ended type.

본 발명은 상기와 같은 문제점을 해결하기 위해 안출된 것으로, 본 발명의 목적은 공기를 단축할 수 있는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법을 제공하는 것이다.The present invention has been conceived to solve the above problems, and an object of the present invention is to provide an eco-friendly open and close power pipe cross-river method using a pipe protection PC culvert capable of shortening the time.

또한, 법면을 손상시키지 않고 관로를 매설할 수 있는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법을 제공하고, 시공성과 경제성이 우수한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법을 제공하는 것이다.In addition, the river crossing method is provided by using a pipeline protection PC culvert that can bury the pipeline without damaging the slope, and the eco-friendly cracking type power pipeline using a pipeline protection PC culvert with excellent workability and economy. Is to provide.

또한, 관로의 부등침하 방지 및 선형 유지를 용이하게 할 수 있는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법을 제공하는 것이다.In addition, it is to provide an eco-friendly cut-off power pipe cross-river method using a pipe protection PC culvert that can prevent differential subsidence of pipe lines and maintain linearity easily.

또한, 신규 설치 및 기존 관로의 보수를 용이하게 할 수 있는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법을 제공하는 것이다.In addition, it is to provide an eco-friendly, open and close power pipe cross-river method using a pipe protection PC culvert that can facilitate new installation and repair of existing pipe lines.

상기와 같은 목적을 달성하기 위한 본 발명의 일 실시 예에 따른 신설 케이블의 부설을 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 PC암거 제작단계와, 지장물 조사 및 협의 단계를 구비하는 사전 준비단계; 공사안내판 및 안전시설 설치단계와, 보행 및 자전거 도로 우회 가교 설치단계와, 오탁방지막 설치단계와, 공사용 가도 설치단계와, 가물막이 설치단계를 구비하는 사전 공사단계; 흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부 암거 설치단계와, 강연선 인장단계와, 정착구 홈 모르타르 채움단계와, 전선관 부설단계와, 스페이서 설치단계와, 모래 포설 및 다짐 단계와, 스페이서 제거단계와, 상부 암거 설치단계와, 되메우기 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC암거 설치 단계; 도통 시험단계와, 신설 케이블을 부설하는 단계를 구비하는 케이블 부설단계; 및 하천 원상 복구단계와, 장비 및 공구 반출단계를 구비하는 마무리단계; 를 구비할 수 있다.In order to achieve the above object, the eco-friendly open-and-seat power pipeline river crossing method using a conduit protection PC culvert for laying a new cable according to an embodiment of the present invention includes a PC culvert manufacturing step and an obstacle investigation and consultation step. A preliminary preparation step; A pre-construction step including a construction guide board and safety facility installation step, a pedestrian and bicycle road bypass bridge installation step, a pollution barrier installation step, a construction road installation step, and a temporary block installation step; Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower culvert installation steps, strand tensioning steps, fixing groove mortar filling steps, conduit laying steps, spacer installation steps And, a PC culvert installation step including a sand laying and compaction step, a spacer removal step, an upper culvert installation step, a backfilling step, a soil barrier temporary facility removal step, and a residual soil removal step; A cable laying step including a conduction test step and a step of laying a new cable; And a finishing step including a restoration step of a river and a step of carrying out equipment and tools. It can be provided.

한편, 본 발명의 일 실시 예에 따른 기설 케이블의 증설을 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 PC암거 제작단계와, PC맨홀 제작단계와, 지장물 조사 및 협의 단계를 구비하는 사전 준비단계; 공사안내판 및 안전시설 설치단계와, 보행 및 자전거 도로 우회 가교 설치단계와, 오탁방지막 설치단계와, 공사용 가도 설치단계와, 가물막이 설치단계를 구비하는 사전 공사단계; 흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부맨홀 설치단계와, 접착체 도포단계와, 상부맨홀 설치단계와, 접합부 모르타르 방수단계와, 접지단계와, 조정용 부재 설치단계와, 맨홀 뚜껑 설치단계와, 관로구 몸체 설치단계와, 미사용 관로구에 관로구덮개 설치단계와, 되메우기 및 다짐 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC맨홀 설치단계; 가시설을 설치하는 단계와, 가이드관을 설치하는 단계와, 기존 맨홀에서 하천 방향으로 천공하는 단계와, 주입관을 설치하는 단계와, 배관후 내부를 몰탈 그라우팅하는 단계와, 상기 배관을 상기 PC맨홀에 연결하는 단계와, 가시설을 철거하는 단계를 구비하는 주입관 설치 단계; 흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부 암거 설치단계와, 강연선 인장단계와, 정착구 홈 모르타르 채움단계와, 전선관 부설단계와, 스페이서 설치단계와, 모래 포설 및 다짐 단계와, 스페이서 제거단계와, 상부 암거 설치단계와, 되메우기 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC암거 설치단계; 도통 시험단계와, 신설 케이블을 부설하는 단계를 구비하는 케이블 부설단계; 및 하천 원상 복구단계와, 장비 및 공구 반출단계를 구비하는 마무리단계; 를 구비할 수 있다.On the other hand, the river crossing method for eco-friendly power pipes using a pipe protection PC culvert for extension of an existing cable according to an embodiment of the present invention includes a PC culvert production step, a PC manhole production step, and an obstacle investigation and consultation step. A preliminary preparation step; A pre-construction step including a construction guide board and safety facility installation step, a pedestrian and bicycle road bypass bridge installation step, a pollution barrier installation step, a construction road installation step, and a temporary block installation step; Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower manhole installation steps, adhesive application steps, upper manhole installation steps, joint mortar waterproofing steps, and grounding steps Wow, installation of a PC manhole including an adjustment member installation step, a manhole cover installation step, a conduit body installation step, a conduit cover installation step in an unused conduit, a backfilling and compaction step, a soil barrier temporary facility removal step, and a residual soil removal step step; Installing a temporary facility, installing a guide pipe, drilling an existing manhole in the direction of a river, installing an injection pipe, mortar grouting the inside after the pipe, and connecting the pipe to the PC manhole. Injecting pipe installation step comprising the step of connecting to and removing the temporary facility; Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower culvert installation steps, strand tensioning steps, fixing groove mortar filling steps, conduit laying steps, spacer installation steps And, a PC culvert installation step including a sand laying and compaction step, a spacer removal step, an upper culvert installation step, a backfilling step, a soil barrier temporary facility removal step, and a residual soil removal step; A cable laying step including a conduction test step and a step of laying a new cable; And a finishing step including a restoration step of a river and a step of carrying out equipment and tools. It can be provided.

한편, 본 발명의 일 실시 예에 따른 기설 케이블의 보수를 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 PC암거 제작단계와, PC맨홀 제작단계와, 지장물 조사 및 협의 단계를 구비하는 사전 준비단계; 공사안내판 및 안전시설 설치단계와, 보행 및 자전거 도로 우회 가교 설치단계와, 오탁방지막 설치단계와, 공사용 가도 설치단계와, 가물막이 설치단계를 구비하는 사전 공사단계; 흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부맨홀 설치단계와, 접착체 도포단계와, 상부맨홀 설치단계와, 접합부 모르타르 방수단계와, 접지단계와, 조정용 부재 설치단계와, 맨홀 뚜껑 설치단계와, 관로구 몸체 설치단계와, 미사용 관로구에 관로구덮개 설치단계와, 되메우기 및 다짐 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC맨홀 설치단계; 가시설을 설치하는 단계와, 가이드관을 설치하는 단계와, 기존 맨홀에서 하천 방향으로 천공하는 단계와, 주입관을 설치하는 단계와, 배관후 내부를 몰탈 그라우팅하는 단계와, 상기 배관을 상기 PC맨홀에 연결하는 단계와, 가시설을 철거하는 단계를 구비하는 주입관 설치 단계; 흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부 암거 설치단계와, 강연선 인장단계와, 정착구 홈 모르타르 채움단계와, 전선관 부설단계와, 스페이서 설치단계와, 모래 포설 및 다짐 단계와, 스페이서 제거단계와, 상부 암거 설치단계와, 되메우기 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC암거 설치단계; 도통 시험단계와, 신설 케이블을 부설하는 단계와, 기설 케이블을 전환하는 단계와, 기설 전선관을 철거단계를 구비하는 케이블 부설단계; 및 하천 원상 복구단계와, 장비 및 공구 반출단계를 구비하는 마무리단계; 를 구비할 수 있다.On the other hand, the eco-friendly open-and-seat power pipeline river crossing method using a conduit protection PC culvert for repairing an existing cable according to an embodiment of the present invention includes a PC culvert manufacturing step, a PC manhole manufacturing step, and an obstacle investigation and consultation step. A preliminary preparation step; A pre-construction step including a construction guide board and safety facility installation step, a pedestrian and bicycle road bypass bridge installation step, a pollution barrier installation step, a construction road installation step, and a temporary block installation step; Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower manhole installation steps, adhesive application steps, upper manhole installation steps, joint mortar waterproofing steps, and grounding steps Wow, installation of a PC manhole including an adjustment member installation step, a manhole cover installation step, a conduit body installation step, a conduit cover installation step in an unused conduit, a backfilling and compaction step, a soil barrier temporary facility removal step, and a residual soil removal step step; Installing a temporary facility, installing a guide pipe, drilling an existing manhole in the direction of a river, installing an injection pipe, mortar grouting the inside after the pipe, and connecting the pipe to the PC manhole. Injecting pipe installation step comprising the step of connecting to and removing the temporary facility; Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower culvert installation steps, strand tensioning steps, fixing groove mortar filling steps, conduit laying steps, spacer installation steps And, a PC culvert installation step including a sand laying and compaction step, a spacer removal step, an upper culvert installation step, a backfill step, a soil barrier temporary facility removal step, and a residual soil removal step; A cable laying step including a continuity test step, a step of laying a new cable, a step of switching an existing cable, and a step of removing the existing conduit; And a finishing step including a restoration step of a river and a step of carrying out equipment and tools. It can be provided.

상기 PC암거는 상기 전선관과, 상기 전선관의 하부에 구비되어 상기 전선관의 하부를 받치는 상기 하부 암거와, 상기 전선관의 상부에 구비되어 상기 전선관의 상부를 덮는 상기 상부 암거와, 상기 하부 암거의 내부에 구비되어 선형유지 및 부등침하를 방지하는 상기 강연선을 구비할 수 있다.The PC culvert includes the conduit, the lower culvert provided under the conduit to support the lower part of the conduit, the upper culvert provided above the conduit to cover the upper part of the conduit, and inside the lower culvert It may be provided with the above-mentioned stranded wire for maintaining linearity and preventing differential settlement.

상기 하부 암거는 상기 강연선이 내장되는 바닥판과, 상기 바닥판의 너비방향 양단에서 상 방향으로 연장되어 상기 전선관의 측면을 덮는 한 쌍의 옆판과, 상기 바닥판과 한 쌍의 상기 옆판에 의해 둘러싸인 형태로 구비되어 상기 전선관이 안착하는 안착홀을 구비할 수 있다.The lower culvert is surrounded by a bottom plate in which the strands are embedded, a pair of side plates extending upward from both ends in the width direction of the bottom plate to cover the side surfaces of the conduit, and the bottom plate and the pair of side plates. It is provided in a form and may have a seating hole in which the conduit is seated.

상기 상부 암거는 상판과, 상기 상판의 너비방향 양단에서 하 방향으로 연장되어 한 쌍의 상기 옆판을 덮는 한 쌍의 측판을 구비할 수 있다.The upper culvert may include an upper plate, and a pair of side plates extending downward from both ends of the upper plate in the width direction to cover the pair of side plates.

상기 PC맨홀은 맨홀 뚜껑과 결합하는 홀을 구비하는 상판부와, 상기 상판부에서 하 방향으로 연장되어 상기 상판부를 지지하는 복수개의 제1기둥부를 구비하는 상기 상부맨홀; 상기 상부맨홀의 하부에 위치하는 하판부와, 상기 하판부에서 상 방향으로 연장되어 상기 제1기둥부와 결합하는 복수개의 제2기둥부를 구비하는 상기 하부맨홀; 및 상기 제1기둥부와 상기 제2기둥부에 구비되어 상기 상부맨홀과 상기 하부맨홀이 용이하게 결합하도록 하는 결합부; 를 구비할 수 있다.The PC manhole includes an upper manhole having an upper plate portion having a hole coupled with a manhole cover, and a plurality of first pillar portions extending downward from the upper plate portion to support the upper plate portion; The lower manhole having a lower plate portion positioned below the upper manhole, and a plurality of second pillar portions extending upward from the lower plate portion and coupled to the first pillar portion; And a coupling portion provided on the first and second pillars to facilitate coupling between the upper manhole and the lower manhole. It can be provided.

결합 된 상기 상부맨홀과 상기 하부맨홀에는 관로구가 형성되고, 상기 상부맨홀과 상기 하부맨홀은 상기 관로구 측 상기 상판부, 상기 제1기둥부, 상기 하판부 및 상기 제2기둥부 일면에 노출되는 노출철근을 구비할 수 있다.The combined upper manhole and the lower manhole have a pipe passage, and the upper manhole and the lower manhole are exposed reinforcement exposed on one surface of the upper plate part, the first pillar part, the lower plate part and the second pillar part at the pipe passage side It can be provided.

상기 관로구에는 상기 노출철근이 매설되도록 형성되어 미사용되는 상기 관로구를 덮는 관로구덮개가 구비될 수 있다.The conduit port may be provided with a conduit cover for covering the conduit port which is formed to be buried in the exposed reinforcing bar.

상기 주입관은 굴곡 된 원통 형상의 본체와, 상기 본체의 외면에서 돌출되도록 구비되는 다수의 원형 돌기를 구비할 수 있다.The injection tube may include a curved cylindrical body and a plurality of circular protrusions protruding from the outer surface of the body.

본 발명의 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 의하면, 공기를 단축할 수 있으며 법면을 손상시키지 않고 관로를 매설할 수 있다.According to the eco-friendly cut-off power pipe cross-river method using a pipe protection PC culvert according to the present invention, it is possible to shorten the air time and to bury the pipe without damaging the slope.

또한, 시공성과 경제성이 우수한 관로 매설 방법을 제공할 수 있다.In addition, it is possible to provide a method for buriing a pipe with excellent workability and economy.

또한, 관로의 부등침하 방지 및 선형 유지를 용이하게 할 수 있다.In addition, it is possible to prevent unequal settling of the pipeline and facilitate linear maintenance.

또한, 신규 설치 및 기존 관로의 보수를 용이하게 할 수 있다.In addition, it is possible to facilitate new installation and repair of existing pipelines.

도 1은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 신설 케이블의 부설을 위한 순서도.
도 2는 도 1에 도시된 순서도를 따라 시공된 모습을 나타낸 도면.
도 3은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 기설 케이블의 증설을 위한 순서도.
도 4는 도 3에 도시된 순서도를 따라 시공된 모습을 나타낸 도면.
도 5는 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 기설 케이블의 보수를 위한 순서도.
도 6은 도 5에 도시된 순서도를 따라 시공된 모습을 나타낸 도면.
도 7은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC암거를 나타낸 사시도.
도 8 및 도 9는 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC맨홀을 나타낸 사시도.
도 10은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 주입관을 나타낸 사시도.
1 is a flow chart for laying a new cable according to the river crossing method of an eco-friendly power pipe using a pipe protection PC culvert according to an embodiment of the present invention.
Figure 2 is a view showing a state constructed according to the flow chart shown in Figure 1;
Figure 3 is a flow chart for the expansion of an existing cable of the river crossing method of an eco-friendly power pipe using a pipe protection PC culvert according to an embodiment of the present invention.
4 is a view showing a state constructed according to the flow chart shown in FIG.
Figure 5 is a flow chart for the maintenance of an existing cable of the river crossing method of an eco-friendly power pipe using a pipe protection PC culvert according to an embodiment of the present invention.
6 is a view showing a state constructed according to the flow chart shown in FIG.
7 is a perspective view showing a PC culvert of an eco-friendly open-and-run electric power duct river crossing method using a duct protection PC culvert according to an embodiment of the present invention.
8 and 9 are perspective views showing a PC manhole of an eco-friendly openable power pipeline using a pipeline protection PC culvert according to an embodiment of the present invention.
10 is a perspective view showing the injection pipe of the cross-river method of an eco-friendly power pipe using a pipe protection PC culvert according to an embodiment of the present invention.

이하에서는 첨부된 도면을 참조하여 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 대해 상세히 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail an eco-friendly open-and-seat power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention.

도 1은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 신설 케이블의 부설을 위한 순서도이고, 도 2는 도 1에 도시된 순서도를 따라 시공된 모습을 나타낸 도면이다.FIG. 1 is a flow chart for laying a new cable according to an eco-friendly plugging-type power pipeline using a pipeline protection PC culvert according to an embodiment of the present invention, and FIG. 2 is a view constructed according to the flow chart shown in FIG. It is a figure shown.

도 1 및 도 2에 도시된 바와 같이, 신설 케이블의 부설을 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 사전 준비단계(S100). 사전 공사단계(S200), PC암거(100) 설치 단계(S300), 케이블 부설단계(S400) 및 마무리단계(S500)로 이루어질 수 있다.As shown in Figures 1 and 2, the environment-friendly cutting-edge power pipe cross-river method using a pipe protection PC culvert for laying a new cable is a preliminary preparation step (S100). It may be made of a pre-construction step (S200), a PC culvert 100, an installation step (S300), a cable laying step (S400), and a finishing step (S500).

사전 준비단계(S100)는 PC암거(100)를 제작단계(S101)와 지장물 조사 및 협의 단계(S102)를 구비할 수 있다.The preliminary preparation step (S100) may include a manufacturing step (S101) of the PC culvert 100 and an obstacle investigation and consultation step (S102).

사전 공사단계(S200)는 공사안내판 및 안전시설을 설치하는 단계(S201), 보행 및 자전거 도로 우회 가교를 설치하는 단계(S202), 오탁방지막을 설치하는 단계(S203), 공사용 가도를 설치하는 단계(S204) 및 가물막이를 설치하는 단계(S205)를 구비할 수 있다.The pre-construction step (S200) is the step of installing a construction guide board and safety facilities (S201), installing a pedestrian and bicycle road bypass bridge (S202), installing a pollution barrier (S203), installing a road for construction It may be provided with (S204) and a step (S205) of installing a temporary barrier.

PC암거(100) 설치 단계(S300)는 흙막이 가시설 조립 및 설치단계(S301), 터파기단계(S302), 바닥 고르기 단계(S303), 기초 모래 포설단계(S304), 하부 암거(120) 설치단계(S305), 강연선(140) 인장단계(S306), 정착구 홈에 모르타르를 채우는 단계(S307), 전선관(110) 부설단계(S308), 스페이서 설치단계(S309), 모래 포설 및 다짐 단계(S310), 스페이서 제거단계(S311), 상부 암거(130) 설치단계(S312), 되메우기 단계(S313), 흙막이 가시설 철거 단계(S314) 및 잔토반출 단계(S315)를 구비할 수 있다.The PC culvert 100 installation step (S300) is an assembling and installation step of a soil barrier temporary facility (S301), digging step (S302), floor selection step (S303), foundation sand laying step (S304), lower culvert 120 installation step (S305), strand 140, tensile step (S306), step of filling mortar in the anchorage groove (S307), conduit 110 laying step (S308), spacer installation step (S309), sand laying and compaction step (S310) , The spacer removal step (S311), the upper culvert 130, the installation step (S312), the backfilling step (S313), the soil barrier temporary facility removal step (S314) and the residual soil removal step (S315) may be provided.

케이블 부설단계(S400)는 도통 시험단계(S401)와 신설 케이블을 부설하는 단계(S402)를 구비할 수 있다.The cable laying step (S400) may include a conduction test step (S401) and a step (S402) of laying a new cable.

마무리단계(S500)는 하천 원상 복구단계(S501)와 장비 및 공구 반출단계(S502)를 구비할 수 있다.The finishing step (S500) may include a river restoration step (S501) and an equipment and tool carrying step (S502).

다음은 기설 케이블의 증설을 위한 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 대해 설명하도록 한다. 이하의 설명에서는 상술한 실시 예와 서로 다른 부분만을 상세하게 설명하며 동일하거나 극히 유사한 부분에 대해서는 상세한 설명을 생략한다.The following describes an eco-friendly open-and-seat power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention for extension of an existing cable. In the following description, only parts different from those of the above-described embodiment will be described in detail, and detailed descriptions of the same or extremely similar parts will be omitted.

도 3은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 기설 케이블의 증설을 위한 순서도이고, 도 4는 도 3에 도시된 순서도를 따라 시공된 모습을 나타낸 도면이다.Figure 3 is a flow chart for the extension of the existing cable of the eco-friendly power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention, Figure 4 is a state constructed according to the flow chart shown in FIG. It is a figure shown.

도 1 내지 도 4를 참조하면, 기설 케이블의 증설을 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 사전 준비단계(S100), 사전 공사단계(S200), PC맨홀(200) 설치단계(S500), PC암거(100) 설치 단계(S300), 케이블 부설단계(S400) 및 마무리단계(S500)로 이루어질 수 있다.Referring to Figures 1 to 4, the environment-friendly open-and-seat power pipe cross-river method using a pipe protection PC culvert for the extension of an existing cable is a preliminary preparation step (S100), a pre-construction step (S200), and a PC manhole 200 installation. Step (S500), the PC culvert 100, the installation step (S300), the cable laying step (S400) and the finishing step (S500).

사전 준비단계는 PC암거(100) 제작단계(S101), PC맨홀(200) 제작단계(S103) 및 지장물 조사 및 협의 단계(S102)를 구비할 수 있다.The preliminary preparation step may include a PC culvert 100 manufacturing step (S101), a PC manhole 200 manufacturing step (S103), and an obstacle investigation and consultation step (S102).

사전 공사단계(S200)는 공사안내판 및 안전시설을 설치하는 단계(S201), 보행 및 자전거 도로 우회 가교를 설치하는 단계(S202), 오탁방지막을 설치하는 단계(S203), 공사용 가도를 설치하는 단계(S204) 및 가물막이를 설치하는 단계(S205)를 구비할 수 있다.The pre-construction step (S200) is the step of installing a construction guide board and safety facilities (S201), installing a pedestrian and bicycle road bypass bridge (S202), installing a pollution barrier (S203), installing a road for construction It may be provided with (S204) and a step (S205) of installing a temporary barrier.

PC맨홀(200) 설치단계(S600)는 흙막이 가시설 조립 및 설치단계(S601), 터파기단계(S602), 바닥 고르기 단계(S603), 기초 모래 포설단계(S604), 하부맨홀(220) 설치단계(S605), 접착체 도포단계(S606), 상부맨홀(210) 설치단계(S607), 접합부 모르타르 방수단계(S608), 접지단계(S609), 조정용 부재 설치단계(S610), 맨홀 뚜껑 설치단계(S611), 관로구(240) 몸체 설치단계(S612), 미사용 관로구(240)에 관로구덮개(260) 설치단계(S613), 되메우기 및 다짐 단계(S614), 흙막이 가시설 철거 단계(S615) 및 잔토반출 단계(S616)를 구비할 수 있다.The PC manhole 200 installation step (S600) is an assembly and installation step (S601), digging step (S602), floor selection step (S603), foundation sand laying step (S604), lower manhole 220 installation step (S605), adhesive application step (S606), upper manhole 210 installation step (S607), joint mortar waterproof step (S608), grounding step (S609), adjustment member installation step (S610), manhole cover installation step ( S611), pipe duct 240, body installation step (S612), pipe duct cover 260 on unused pipe duct 240, installation step (S613), backfilling and compaction step (S614), soil barrier temporary facility removal step (S615) and residual soil removal step (S616) may be provided.

주입관(300) 설치단계(S700)는 가시설을 설치하는 단계(S710), 가이드관을 설치하는 단계(S720), 기존 맨홀(미부호)에서 하천 방향으로 천공하는 단계(S730), 주입관(300)을 설치하는 단계(S740), 배관 후 내부를 몰탈 그라우팅하는 단계(S750)와, 배관을 PC맨홀(200)에 연결하는 단계(S760) 및 가시설을 해체하는 단계(S770)를 구비할 수 있다.The injection pipe 300 installation step (S700) includes the step of installing temporary facilities (S710), installing the guide pipe (S720), drilling in the direction of the river from the existing manhole (unsigned) (S730), and the injection pipe ( 300) installing (S740), mortar grouting the inside after piping (S750), connecting the piping to the PC manhole 200 (S760) and dismantling temporary facilities (S770). have.

PC암거(100) 설치 단계(S300)는 흙막이 가시설 조립 및 설치단계(S301), 터파기단계(S302), 바닥 고르기 단계(S303), 기초 모래 포설단계(S304), 하부 암거(120) 설치단계(S305), 강연선(140) 인장단계(S306), 정착구 홈에 모르타르를 채우는 단계(S307), 전선관(110) 부설단계(S308), 스페이서 설치단계(S309), 모래 포설 및 다짐 단계(S310), 스페이서 제거단계(S311), 상부 암거(130) 설치단계(S312), 되메우기 단계(S313), 흙막이 가시설 철거 단계(S314) 및 잔토반출 단계(S315)를 구비할 수 있다.The PC culvert 100 installation step (S300) is an assembling and installation step of a soil barrier temporary facility (S301), digging step (S302), floor selection step (S303), foundation sand laying step (S304), lower culvert 120 installation step (S305), strand 140, tensile step (S306), step of filling mortar in the anchorage groove (S307), conduit 110 laying step (S308), spacer installation step (S309), sand laying and compaction step (S310) , The spacer removal step (S311), the upper culvert 130, the installation step (S312), the backfilling step (S313), the soil barrier temporary facility removal step (S314) and the residual soil removal step (S315) may be provided.

케이블 부설단계(S400)는 도통 시험단계(S401)와 신설 케이블을 부설하는 단계(S402)를 구비할 수 있다.The cable laying step (S400) may include a conduction test step (S401) and a step (S402) of laying a new cable.

마무리단계(S500)는 하천 원상 복구단계(S501)와 장비 및 공구 반출단계(S502)를 구비할 수 있다.The finishing step (S500) may include a river restoration step (S501) and an equipment and tool carrying step (S502).

다음은 기설 케이블의 보수를 위한 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 대해 설명하도록 한다. 이하의 설명에서는 상술한 실시 예와 서로 다른 부분만을 상세하게 설명하며 동일하거나 극히 유사한 부분에 대해서는 상세한 설명을 생략한다.The following describes an eco-friendly open-and-run power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention for repairing an existing cable. In the following description, only parts different from those of the above-described embodiment will be described in detail, and detailed descriptions of the same or extremely similar parts will be omitted.

도 5는 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 기설 케이블의 보수를 위한 순서도이고, 도 6은 도 5에 도시된 순서도를 따라 시공된 모습을 나타낸 도면이다.Figure 5 is a flow chart for the maintenance of an existing cable of the eco-friendly power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention, Figure 6 is a state constructed according to the flow chart shown in FIG. It is a figure shown.

도 1 내지 도 6을 참조하면, 기설 케이블의 보수를 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 사전 준비단계(S100), 사전 공사단계(S200), PC맨홀(200) 설치단계(S500), PC암거(100) 설치 단계(S300), 케이블 부설단계(S400) 및 마무리단계(S500)로 이루어질 수 있다.Referring to Figures 1 to 6, the environment-friendly open-and-seat power pipe cross-river method using a pipe protection PC culvert for the maintenance of existing cables is a preliminary preparation step (S100), a pre-construction step (S200), and a PC manhole 200 installation. Step (S500), the PC culvert 100, the installation step (S300), the cable laying step (S400) and the finishing step (S500).

사전 준비단계는 PC암거(100) 제작단계(S101), PC맨홀(200) 제작단계(S103) 및 지장물 조사 및 협의 단계(S102)를 구비할 수 있다.The preliminary preparation step may include a PC culvert 100 manufacturing step (S101), a PC manhole 200 manufacturing step (S103), and an obstacle investigation and consultation step (S102).

사전 공사단계(S200)는 공사안내판 및 안전시설을 설치하는 단계(S201), 보행 및 자전거 도로 우회 가교를 설치하는 단계(S202), 오탁방지막을 설치하는 단계(S203), 공사용 가도를 설치하는 단계(S204) 및 가물막이를 설치하는 단계(S205)를 구비할 수 있다.The pre-construction step (S200) is the step of installing a construction guide board and safety facilities (S201), installing a pedestrian and bicycle road bypass bridge (S202), installing a pollution barrier (S203), installing a road for construction It may be provided with (S204) and a step (S205) of installing a temporary barrier.

PC맨홀(200) 설치단계(S600)는 흙막이 가시설 조립 및 설치단계(S601), 터파기단계(S602), 바닥 고르기 단계(S603), 기초 모래 포설단계(S604), 하부맨홀(220) 설치단계(S605), 접착체 도포단계(S606), 상부맨홀(210) 설치단계(S607), 접합부 모르타르 방수단계(S608), 접지단계(S609), 조정용 부재 설치단계(S610), 맨홀 뚜껑 설치단계(S611), 관로구(240) 몸체 설치단계(S612), 미사용 관로구(240)에 관로구덮개(260) 설치단계(S613), 되메우기 및 다짐 단계(S614), 흙막이 가시설 철거 단계(S615) 및 잔토반출 단계(S616)를 구비할 수 있다.The PC manhole 200 installation step (S600) is an assembly and installation step (S601), digging step (S602), floor selection step (S603), foundation sand laying step (S604), lower manhole 220 installation step (S605), adhesive application step (S606), upper manhole 210 installation step (S607), joint mortar waterproof step (S608), grounding step (S609), adjustment member installation step (S610), manhole cover installation step ( S611), pipe duct 240, body installation step (S612), pipe duct cover 260 on unused pipe duct 240, installation step (S613), backfilling and compaction step (S614), soil barrier temporary facility removal step (S615) and residual soil removal step (S616) may be provided.

주입관(300) 설치단계(S700)는 가시설을 설치하는 단계(S710), 가이드관을 설치하는 단계(S720), 기존 맨홀(미부호)에서 하천 방향으로 천공하는 단계(S730), 주입관(300)을 설치하는 단계(S740), 배관 후 내부를 몰탈 그라우팅하는 단계(S750)와, 배관을 PC맨홀(200)에 연결하는 단계(S760) 및 가시설을 해체하는 단계(S770)를 구비할 수 있다.The injection pipe 300 installation step (S700) includes the step of installing temporary facilities (S710), installing the guide pipe (S720), drilling in the direction of the river from the existing manhole (unsigned) (S730), and the injection pipe ( 300) installing (S740), mortar grouting the inside after piping (S750), connecting the piping to the PC manhole 200 (S760) and dismantling temporary facilities (S770). have.

PC암거(100) 설치 단계(S300)는 흙막이 가시설 조립 및 설치단계(S301), 터파기단계(S302), 바닥 고르기 단계(S303), 기초 모래 포설단계(S304), 하부 암거(120) 설치단계(S305), 강연선(140) 인장단계(S306), 정착구 홈에 모르타르를 채우는 단계(S307), 전선관(110) 부설단계(S308), 스페이서 설치단계(S309), 모래 포설 및 다짐 단계(S310), 스페이서 제거단계(S311), 상부 암거(130) 설치단계(S312), 되메우기 단계(S313), 흙막이 가시설 철거 단계(S314) 및 잔토반출 단계(S315)를 구비할 수 있다.The PC culvert 100 installation step (S300) is an assembling and installation step of a soil barrier temporary facility (S301), digging step (S302), floor selection step (S303), foundation sand laying step (S304), lower culvert 120 installation step (S305), strand 140, tensile step (S306), step of filling mortar in the anchorage groove (S307), conduit 110 laying step (S308), spacer installation step (S309), sand laying and compaction step (S310) , The spacer removal step (S311), the upper culvert 130, the installation step (S312), the backfilling step (S313), the soil barrier temporary facility removal step (S314) and the residual soil removal step (S315) may be provided.

케이블 부설단계(S400)는 도통 시험단계(S401), 신설 케이블을 부설하는 단계(S402), 기설 케이블을 전환하는 단계(S403) 및 기설 전선관(110) 철거단계(S404)를 구비할 수 있다.The cable laying step (S400) may include a conduction test step (S401), a step of laying a new cable (S402), a step of converting the existing cable (S403), and a step of removing the existing conduit 110 (S404).

마무리단계(S500)는 하천 원상 복구단계(S501)와 장비 및 공구 반출단계(S502)를 구비할 수 있다.The finishing step (S500) may include a river restoration step (S501) and an equipment and tool carrying step (S502).

다음은 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC암거(100)에 대해 설명하도록 한다. 이하의 설명에서는 상술한 실시 예와 서로 다른 부분만을 상세하게 설명하며 동일하거나 극히 유사한 부분에 대해서는 상세한 설명을 생략한다.The following will describe the PC culvert 100 of the eco-friendly cut-and-run electric power duct river crossing method using the duct protection PC culvert according to an embodiment of the present invention. In the following description, only parts different from those of the above-described embodiment will be described in detail, and detailed descriptions of the same or extremely similar parts will be omitted.

도 7은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC암거를 나타낸 사시도이다.7 is a perspective view showing a PC culvert of an eco-friendly open-and-run electric power pipe cross-river method using a duct protection PC culvert according to an embodiment of the present invention.

도 1 내지 도 7을 참조하면, 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC암거(100)는 전선관(110), 전선관(110)의 하부에 구비되어 전선관(110)을 받치는 하부 암거(120), 전선관(110)의 상부에 구비되어 전선관(110)의 상부를 덮는 상부 암거(130) 및 하부 암거(120)과 상부 암거(130)의 내부에 구비되어 선형유지 및 부등침하를 방지하는 강연선(140)을 구비할 수 있다.Referring to FIGS. 1 to 7, the PC culvert 100 of the eco-friendly open-and-run electric power pipeline river crossing method using the conduit protection PC culvert according to an embodiment of the present invention is a conduit 110 and a lower portion of the conduit 110 The interior of the lower culvert 120 provided to support the conduit 110, the upper culvert 130 and the lower culvert 120 and the upper culvert 130 provided on the upper part of the conduit 110 and covering the upper part of the conduit 110 It may be provided with a stranded wire 140 that is provided to prevent linear maintenance and differential settlement.

전선관(110)은 도면에 도시된 바와 같이, 다수개가 적층형태를 이루도록 구비될 수 있으며, 하부 암거(120)과 상부 암거(130)는 전선관(110)의 적층형태를 고정함과 동시에 다수개의 전선관(110)을 보호하는 역할을 할 수 있다.As shown in the drawing, the conduit 110 may be provided to form a stacked form, and the lower culvert 120 and the upper culvert 130 fix the stacked form of the conduit 110 and at the same time It can play a role of protecting (110).

하부 암거(120)에 대해 살펴보면, 하부 암거(120)은 바닥판(121), 한 쌍의 옆판(122) 및 안착홀(123)을 구비할 수 있다. 바닥판(121)과 한 쌍의 옆판(122)은 일 방향으로 길게 형성되고, 'U'자 형태가 되도록 구비될 수 있다. 그리고 바닥판(121)은 지면과 맞대어지고 강연선(140)이 내장되어 PC암거(100)의 선형유지 및 부등침하를 방지하는 효과를 발휘할 수 있다. 한 쌍의 옆판(122)은 바닥판(121)의 너비방향 양단에서 상 방향으로 연장되어 전선관(110)의 측면을 덮을 수 있다. 안착홀(123)은 바닥판(121)과 한 쌍의 옆판(122)에 의해 둘러싸인 형태의 공간으로써 전선관(110)이 안착할 수 있다.Looking at the lower culvert 120, the lower culvert 120 may include a bottom plate 121, a pair of side plates 122, and a seating hole 123. The bottom plate 121 and the pair of side plates 122 are formed to be elongated in one direction and may be provided in a'U' shape. In addition, the bottom plate 121 is abutted to the ground and the stranded wire 140 is embedded, so that the linearity of the PC culvert 100 and the prevention of differential settlement can be exhibited. A pair of side plates 122 may extend upward from both ends in the width direction of the bottom plate 121 to cover the side surfaces of the conduit 110. The seating hole 123 is a space surrounded by the bottom plate 121 and the pair of side plates 122 and the conduit 110 can be seated.

한편, 상부 암거(130)는 상판(131)과 한 쌍의 측판(132)을 구비할 수 있다. 상판(131)과 한 쌍의 측판(132)은 일 방향으로 길게 형성되고, 'U'자 형태의 하부 암거(120)의 상부를 덮도록 '∩'자 형태로 하부 암거(120)의 상부에 얹혀지는 형태로 구비될 수 있다. 한 쌍의 측판(132)은 상부 암거(130)의 너비방향 양단에서 하 방향으로 연장되어 한 쌍의 옆판(122)을 덮는 형태로 구비될 수 있다.Meanwhile, the upper culvert 130 may include an upper plate 131 and a pair of side plates 132. The upper plate 131 and the pair of side plates 132 are formed to be elongated in one direction, and have a'∩' shape on the upper part of the lower culvert 120 to cover the upper part of the'U'-shaped lower culvert 120. It may be provided in the form of being placed on. The pair of side plates 132 may extend downward from both ends in the width direction of the upper culvert 130 to cover the pair of side plates 122.

상기와 같이, 하부 암거(120)와 상부 암거(130)가 구비됨에 따라, 전선관(110)의 상부에 조성되는 하천(10)과 둔치(30)의 하중에 전선관(110)이 손상 또는 파손되는 것을 방지하고, 강연선(140)을 구비함에 따라, PC암거(100)의 선형유지 및 부등침하를 방지하는 효과를 발휘할 수 있다.As described above, as the lower culvert 120 and the upper culvert 130 are provided, the conduit 110 is damaged or damaged by the load of the river 10 and the blunt 30 formed on the upper part of the conduit 110. In addition, as the stranded wire 140 is provided, it is possible to exhibit the effect of maintaining the linearity of the PC culvert 100 and preventing differential settlement.

또한, 하부 암거(120)의 단부와 상부 암거(130)의 단부가 수직 방향으로 서로 동일선상에 위치하지 않도록 즉, 하부 암거(120)의 단부와 상부 암거(130)의 단부가 수직 방향으로 엇갈리는 형태가 되도록 시공함으로써 부등침하를 방지하는 효과를 더욱 향상시킬 수 있다.In addition, so that the ends of the lower culvert 120 and the ends of the upper culvert 130 are not located on the same line in the vertical direction, that is, the ends of the lower culvert 120 and the ends of the upper culvert 130 are staggered in the vertical direction. By constructing it in a shape, the effect of preventing differential settlement can be further improved.

한편, 도면에는 도시하지 않았지만, 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 적용 위치와 주변 환경 등에 따라 PC암거(100)를 대신하여 강관이 사용될 수 있다.On the other hand, although not shown in the drawings, the eco-friendly cut-off power pipe cross-river method using a pipe protection PC culvert may use a steel pipe instead of the PC culvert 100 depending on the application location and surrounding environment.

다음은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC맨홀(200)에 대해 설명하도록 한다. 이하의 설명에서는 상술한 실시 예와 서로 다른 부분만을 상세하게 설명하며 동일하거나 극히 유사한 부분에 대해서는 상세한 설명을 생략한다.The following will describe the PC manhole 200 of the eco-friendly cut-off power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention. In the following description, only parts different from those of the above-described embodiment will be described in detail, and detailed descriptions of the same or extremely similar parts will be omitted.

도 8 및 도 9는 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC맨홀을 나타낸 사시도이다.8 and 9 are perspective views showing a PC manhole of an eco-friendly open-and-run power pipeline using a pipeline protection PC culvert according to an embodiment of the present invention.

도 1 내지 도 9를 참조하면, 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 PC맨홀(200)은 맨홀 뚜껑과 결합하는 홀(2111)을 구비하는 상판부(211)와 상판부(211)에서 하 방향으로 연장되어 상판부(211)를 지지하는 복수개의 제1기둥부(212)를 구비하는 상부맨홀(210)을 구비할 수 있다. 상판부(211)는 지면과 인접한 위치에 구비되고 적어도 하나의 홀(2111)이 형성되어 PC맨홀(200)이 매설된 후 맨홀 뚜껑이 상판부(211)와 결합하도록 할 수 있다. 제1기둥부(212)는 상판부(211)와 프리캐스트 콘크리트에 의해 일체로 형성되며 PC맨홀(200)이 필로티(pilotis)구조가 되도록 구비될 수 있다. 필로티란 건물 상층을 지탱하는 독립기둥으로, 벽이 없는 일층의 주열(柱列)을 말한다. 건물 1층을 거의 기둥만으로 한 층이 되게 하고 주위의 지반과 연속시켜, 건물로 지상을 점유하지 않고 지상의 교통을 방해하지 않는 효과를 발휘할 수 있다. Referring to Figures 1 to 9, the PC manhole 200 of the eco-friendly power pipe cross-river method using a pipe protection PC culvert according to an embodiment of the present invention is provided with a hole 2111 coupled to the manhole cover. An upper manhole 210 having a plurality of first pillars 212 extending downward from the upper plate 211 and the upper plate 211 to support the upper plate 211 may be provided. The top plate 211 may be provided at a position adjacent to the ground and at least one hole 2111 is formed so that the PC manhole 200 is buried and the manhole cover may be coupled to the top plate 211. The first pillar portion 212 is integrally formed of the upper plate portion 211 and precast concrete, and may be provided so that the PC manhole 200 has a pilotis structure. Pilotti is an independent pillar that supports the upper floor of a building, and refers to the main row of the first floor without walls. By making the first floor of a building almost one floor with only pillars and continuing with the surrounding ground, the building does not occupy the ground and does not interfere with traffic on the ground.

그리고 상부맨홀(210)의 하부에 위치하는 하판부(221)와 하판부(221)에서 상 방향으로 연장되어 제1기둥부(212)와 결합하는 복수개의 제2기둥부(222)를 구비하는 하부맨홀(220)을 구비할 수 있다.In addition, a lower plate portion 221 positioned under the upper manhole 210 and a plurality of second pillar portions 222 extending upwardly from the lower plate portion 221 and coupled with the first pillar portion 212 are provided. A lower manhole 220 may be provided.

또한, 제1기둥부(212)와 제2기둥부(222)에는 돌기-홈 등과 같은 방식을 통해 상부맨홀(210)과 하부맨홀(220)이 용이하게 결합하도록 하는 결합부(230)를 구비할 수 있다. 상부맨홀(210)과 하부맨홀(220)이 결합부(230)를 통해 결합함으로써 예기치 않은 외부의 충격 등에 의해 하부맨홀(220)에 얹혀진 상부맨홀(210)이 이탈하여 안전사고가 발생하는 것을 방지할 수 있으며, PC맨홀(200)의 구조적 강성을 높이는 효과를 발휘할 수 있다.In addition, the first pillar portion 212 and the second pillar portion 222 are provided with a coupling portion 230 that facilitates coupling of the upper manhole 210 and the lower manhole 220 through a method such as a protrusion-groove. can do. By combining the upper manhole 210 and the lower manhole 220 through the coupling unit 230, the upper manhole 210 placed on the lower manhole 220 is separated by unexpected external shocks, thereby preventing a safety accident. It can, and can exert the effect of increasing the structural rigidity of the PC manhole 200.

한편, 결합 된 상부맨홀(210)과 하부맨홀(220)에는 관로구(240)가 형성될 수 있다. 관로구(240)를 통해 작업자가 PC맨홀(200)의 내외부를 자유롭게 이동할 수 있으며, 기설 케이블과 신설 케이블의 연결 및 교체가 용이하게 이루질 수 있으며, 통과 및 방향 전환이 자유롭게 이루어질 수 있다.Meanwhile, a conduit 240 may be formed in the combined upper manhole 210 and the lower manhole 220. The operator can freely move the inside and outside of the PC manhole 200 through the conduit 240, the connection and replacement of the existing cable and the new cable can be easily achieved, and passage and direction change can be made freely.

그리고 상부맨홀(210)과 하부맨홀(220)의 관로구(240) 측 상판부(211), 제1기둥부(212), 하판부(221) 및 제2기둥부(222) 일면에는 노출철근(250)을 구비할 수 있다.In addition, exposed reinforcement 250 is provided on one side of the upper manhole 210 and the lower manhole 220 on the side of the upper plate part 211, the first post part 212, the lower part part 221, and the second post part 222. ) Can be provided.

또한, 관로구(240)에는 노출철근(250)이 매설되도록 형성되어 미사용되는 관로구(240)를 덮는 관로구덮개(260)가 구비될 수 있다. 관로구덮개(260)를 통해 PC맨홀(200)과 연결되는 전선관(110)의 방향을 사전에 한정할 수 있고, PC맨홀(200)이 매설되는 인근에 또 다른 관이 인접해 있을 경우, 시공시 다른 관에 피해가 가지 않도록 작업공간을 구획하는 역할을 할 수 있다.In addition, the conduit port 240 may be provided with a conduit cover 260 that covers the unused conduit port 240 by being formed so that the exposed reinforcing bar 250 is buried. The direction of the conduit 110 connected to the PC manhole 200 through the conduit cover 260 can be limited in advance, and when another pipe is adjacent to the vicinity where the PC manhole 200 is buried, during construction It can play a role of dividing the work space so that other pipes are not damaged.

이에 따라, 안전한 시공이 이루어지도록 함과 동시에 현장에서 이루어지는 전체적인 공사시간을 단축하는 효과를 발휘할 수 있을 뿐만 아니라 공장에서 미리 제작됨에 따라 현장에서 콘크리트 타설을 통해 제작되었을 때에 비해 상대적으로 높은 품질을 기대할 수 있다.Accordingly, it is possible to achieve a safe construction and at the same time reduce the overall construction time on the site, and as it is manufactured in advance at the factory, a relatively high quality can be expected compared to when manufactured through concrete pouring on the site. have.

다음은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 주입관(300)에 대해 설명하도록 한다. 이하의 설명에서는 상술한 실시 예와 서로 다른 부분만을 상세하게 설명하며 동일하거나 극히 유사한 부분에 대해서는 상세한 설명을 생략한다.The following will describe the injection pipe 300 of the river crossing method of an eco-friendly openable power pipe using a pipe protection PC culvert according to an embodiment of the present invention. In the following description, only parts different from those of the above-described embodiment will be described in detail, and detailed descriptions of the same or extremely similar parts will be omitted.

도 10은 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 주입관을 나타낸 사시도이다.FIG. 10 is a perspective view showing an injection pipe of an eco-friendly pluggable power pipe using a pipe protection PC culvert according to an embodiment of the present invention.

도 1 내지 도 10을 참조하면, 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법의 주입관(300)은 굴곡 된 원통 형상의 본체(310)와 본체(310)의 외면에서 돌출되도록 구비되는 다수의 원형 돌기(320)를 구비할 수 있다.Referring to Figures 1 to 10, the injection pipe 300 of the eco-friendly open-and-close power pipe cross-river method using the pipe protection PC culvert according to an embodiment of the present invention is a curved cylindrical body 310 and a body ( A plurality of circular protrusions 320 may be provided to protrude from the outer surface of 310).

주입관(300)은 별도의 천공장비(미도시)를 통해 천공된 홀에 삽입되며 삽입된 후 본체(310)의 내부를 통해 배관될 수 있다. 배관 후에는 본체(310)의 내부에 몰탈 그라우팅을 하여 본체(310)의 내부를 채울 수 있다. 그리고 다수의 원형 돌기(320)와 천공된 홀 사이에 밀크 그라우팅을 하여 천공된 홀과 주입관(300) 사이의 기밀성을 높일 수 있다. 또한, 다수의 원형 돌기(320)에 의해 밀크 그라우팅과 맞닿는 면적이 증가하여 주입관(300)의 고정력을 향상시킬 수 있다.The injection pipe 300 may be inserted into a hole drilled through a separate drilling device (not shown) and piped through the inside of the body 310 after being inserted. After piping, the interior of the body 310 may be filled by mortar grouting inside the body 310. In addition, by performing milk grouting between the plurality of circular protrusions 320 and the perforated hole, the airtightness between the perforated hole and the injection pipe 300 can be improved. In addition, an area in contact with the milk grouting may be increased by the plurality of circular protrusions 320, so that the fixing force of the injection pipe 300 may be improved.

이와 같이, 개착을 하지 않고 천공된 홀에 주입관(30)을 삽입하는 방식으로 시공이 이루어짐으로써 공사의 인허가를 용이하게 받을 수 있을 뿐만 아니라, 사면 또는 법면의 훼손을 최소화할 수 있다.In this way, the construction is performed by inserting the injection pipe 30 into the perforated hole without opening and closing, so that it is possible to easily obtain permission for construction and to minimize damage to the slope or slope.

이상에서는 본 발명의 일 실시 예에 따른 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 에 대해 설명하였으나, 본 발명의 사상은 본 명세서에 제시되는 실시 예에 제한되지 아니한다. 그리고, 본 발명의 사상을 이해하는 당업자는 동일한 사상의 범위 내에서 구성요소의 부가, 변경, 삭제, 추가 등에 의해서 다른 실시 예를 용이하게 제안할 수 있을 것이나, 이 또한 본 발명의 사상범위 내에 든다고 할 것이다.In the above, the method of crossing the river for an eco-friendly power pipe using a pipe protection PC culvert according to an embodiment of the present invention has been described, but the spirit of the present invention is not limited to the embodiments presented herein. And, those skilled in the art who understand the spirit of the present invention will be able to easily propose other embodiments by adding, changing, deleting, or adding components within the scope of the same idea, but this is also within the scope of the present invention. something to do.

100: PC암거 110: 전선관
120: 하부 암거 121: 바닥판
122: 옆판 123: 안착홀
130: 상부 암거 131: 상판
132: 옆판 140: 강연선
200: PC맨홀 210: 상부맨홀
211: 상판부 2111: 홀
212: 제1기둥부 220: 하부맨홀
221: 하판부 222: 제2기둥부
230: 결합부 240: 관로구
250: 노출철근 260: 관로구덮개
300: 주입관 310: 본체
320: 돌기
100: PC culvert 110: conduit
120: lower culvert 121: bottom plate
122: side plate 123: seating hole
130: upper culvert 131: upper plate
132: side plate 140: strand
200: PC manhole 210: upper manhole
211: upper plate 2111: hall
212: first pillar 220: lower manhole
221: lower plate portion 222: second pillar portion
230: coupling portion 240: pipeline
250: exposed reinforcement 260: conduit cover
300: injection tube 310: main body
320: protrusion

Claims (10)

삭제delete 기설 케이블의 증설을 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 있어서,
상기 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 PC암거 제작단계와, PC맨홀 제작단계와, 지장물 조사 및 협의 단계를 구비하는 사전 준비단계;
공사안내판 및 안전시설 설치단계와, 보행 및 자전거 도로 우회 가교 설치단계와, 오탁방지막 설치단계와, 공사용 가도 설치단계와, 가물막이 설치단계를 구비하는 사전 공사단계;
흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부맨홀 설치단계와, 접착체 도포단계와, 상부맨홀 설치단계와, 접합부 모르타르 방수단계와, 접지단계와, 조정용 부재 설치단계와, 맨홀 뚜껑 설치단계와, 관로구 몸체 설치단계와, 미사용 관로구에 관로구덮개 설치단계와, 되메우기 및 다짐 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC맨홀 설치단계;
가시설을 설치하는 단계와, 가이드관을 설치하는 단계와, 기존 맨홀에서 하천 방향으로 천공하는 단계와, 주입관을 설치하는 단계와, 배관후 내부를 몰탈 그라우팅하는 단계와, 상기 배관을 상기 PC맨홀에 연결하는 단계와, 가시설을 철거하는 단계를 구비하는 주입관 설치 단계;
흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부 암거 설치단계와, 강연선 인장단계와, 정착구 홈 모르타르 채움단계와, 전선관 부설단계와, 스페이서 설치단계와, 모래 포설 및 다짐 단계와, 스페이서 제거단계와, 상부 암거 설치단계와, 되메우기 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC암거 설치단계;
도통 시험단계와, 신설 케이블을 부설하는 단계를 구비하는 케이블 부설단계; 및 하천 원상 복구단계와, 장비 및 공구 반출단계를 구비하는 마무리단계; 를 구비하고,
상기 PC암거는 상기 전선관과, 상기 전선관의 하부에 구비되어 상기 전선관의 하부를 받치는 상기 하부 암거와, 상기 전선관의 상부에 구비되어 상기 전선관의 상부를 덮는 상기 상부 암거와, 상기 하부 암거의 내부에 구비되어 선형유지 및 부등침하를 방지하는 상기 강연선을 구비하고,
상기 하부 암거는 상기 강연선이 내장되는 바닥판과, 상기 바닥판의 너비방향 양단에서 상 방향으로 연장되어 상기 전선관의 측면을 덮는 한 쌍의 옆판과, 상기 바닥판과 한 쌍의 상기 옆판에 의해 둘러싸인 형태로 구비되어 상기 전선관이 안착하는 안착홀을 구비하고,
상기 상부 암거는 상판과, 상기 상판의 너비방향 양단에서 하 방향으로 연장되어 한 쌍의 상기 옆판을 덮는 한 쌍의 측판을 구비하고,
상기 주입관은 굴곡 된 원통 형상의 본체와, 상기 본체의 외면에서 돌출되도록 구비되는 다수의 원형 돌기를 구비하며, 사면 또는 법면을 개착하지 않고 사면 또는 법면에 천공된 홀에 삽입되는 방식을 통해 설치되어 사면 또는 법면의 훼손을 최소화하는 것을 특징으로 하는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법.
In the river crossing method for an eco-friendly open-ended power pipe using a PC culvert for pipe protection for the extension of existing cables,
The eco-friendly open-and-run power pipe crossing method using the pipe protection PC culvert includes a preliminary preparation step including a PC culvert manufacturing step, a PC manhole manufacturing step, and an obstacle investigation and consultation step;
A pre-construction step including a construction guide board and safety facility installation step, a pedestrian and bicycle road bypass bridge installation step, a pollution barrier installation step, a construction road installation step, and a temporary block installation step;
Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower manhole installation steps, adhesive application steps, upper manhole installation steps, joint mortar waterproofing steps, and grounding steps Wow, installation of a PC manhole including an adjustment member installation step, a manhole cover installation step, a conduit body installation step, a conduit cover installation step in an unused conduit, a backfilling and compaction step, a soil barrier temporary facility removal step, and a residual soil removal step step;
Installing a temporary facility, installing a guide pipe, drilling an existing manhole in the direction of a river, installing an injection pipe, mortar grouting the inside after the pipe, and connecting the pipe to the PC manhole. Injecting pipe installation step comprising the step of connecting to and removing the temporary facility;
Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower culvert installation steps, strand tensioning steps, fixing groove mortar filling steps, conduit laying steps, spacer installation steps And, a PC culvert installation step including a sand laying and compaction step, a spacer removal step, an upper culvert installation step, a backfilling step, a soil barrier temporary facility removal step, and a residual soil removal step;
A cable laying step including a conduction test step and a step of laying a new cable; And a finishing step including a restoration step of a river and a step of carrying out equipment and tools. And,
The PC culvert includes the conduit, the lower culvert provided under the conduit to support the lower part of the conduit, the upper culvert provided above the conduit to cover the upper part of the conduit, and inside the lower culvert It is provided with the stranded wire to prevent linear maintenance and differential settlement,
The lower culvert is surrounded by a bottom plate in which the strands are embedded, a pair of side plates extending upward from both ends in the width direction of the bottom plate to cover the side surfaces of the conduit, and the bottom plate and the pair of side plates. It is provided in a form and has a seating hole in which the conduit is seated,
The upper culvert includes an upper plate, and a pair of side plates extending downward from both ends of the upper plate in the width direction to cover the pair of side plates,
The injection tube has a curved cylindrical body and a plurality of circular protrusions provided to protrude from the outer surface of the body, and is installed through a method that is inserted into a hole drilled in the slope or slope without opening the slope or slope. It is an eco-friendly open-and-seat power pipe cross-river method using a pipe protection PC culvert, characterized in that it minimizes damage to the slope or slope.
기설 케이블의 보수를 위한 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법에 있어서,
상기 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법은 PC암거 제작단계와, PC맨홀 제작단계와, 지장물 조사 및 협의 단계를 구비하는 사전 준비단계;
공사안내판 및 안전시설 설치단계와, 보행 및 자전거 도로 우회 가교 설치단계와, 오탁방지막 설치단계와, 공사용 가도 설치단계와, 가물막이 설치단계를 구비하는 사전 공사단계;
흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부맨홀 설치단계와, 접착체 도포단계와, 상부맨홀 설치단계와, 접합부 모르타르 방수단계와, 접지단계와, 조정용 부재 설치단계와, 맨홀 뚜껑 설치단계와, 관로구 몸체 설치단계와, 미사용 관로구에 관로구덮개 설치단계와, 되메우기 및 다짐 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC맨홀 설치단계;
가시설을 설치하는 단계와, 가이드관을 설치하는 단계와, 기존 맨홀에서 하천 방향으로 천공하는 단계와, 주입관을 설치하는 단계와, 배관후 내부를 몰탈 그라우팅하는 단계와, 상기 배관을 상기 PC맨홀에 연결하는 단계와, 가시설을 철거하는 단계를 구비하는 주입관 설치 단계;
흙막이 가시설 조립 및 설치단계와, 터파기단계와, 바닥 고르기 단계와, 기초 모래 포설단계와, 하부 암거 설치단계와, 강연선 인장단계와, 정착구 홈 모르타르 채움단계와, 전선관 부설단계와, 스페이서 설치단계와, 모래 포설 및 다짐 단계와, 스페이서 제거단계와, 상부 암거 설치단계와, 되메우기 단계와, 흙막이 가시설 철거 단계와, 잔토반출 단계를 구비하는 PC암거 설치단계;
도통 시험단계와, 신설 케이블을 부설하는 단계와, 기설 케이블을 전환하는 단계와, 기설 전선관을 철거단계를 구비하는 케이블 부설단계; 및
하천 원상 복구단계와, 장비 및 공구 반출단계를 구비하는 마무리단계; 를 구비하고,
상기 PC암거는 상기 전선관과, 상기 전선관의 하부에 구비되어 상기 전선관의 하부를 받치는 상기 하부 암거와, 상기 전선관의 상부에 구비되어 상기 전선관의 상부를 덮는 상기 상부 암거와, 상기 하부 암거의 내부에 구비되어 선형유지 및 부등침하를 방지하는 상기 강연선을 구비하고,
상기 하부 암거는 상기 강연선이 내장되는 바닥판과, 상기 바닥판의 너비방향 양단에서 상 방향으로 연장되어 상기 전선관의 측면을 덮는 한 쌍의 옆판과, 상기 바닥판과 한 쌍의 상기 옆판에 의해 둘러싸인 형태로 구비되어 상기 전선관이 안착하는 안착홀을 구비하고,
상기 상부 암거는 상판과, 상기 상판의 너비방향 양단에서 하 방향으로 연장되어 한 쌍의 상기 옆판을 덮는 한 쌍의 측판을 구비하고,
상기 주입관은 굴곡 된 원통 형상의 본체와, 상기 본체의 외면에서 돌출되도록 구비되는 다수의 원형 돌기를 구비하며, 사면 또는 법면을 개착하지 않고 사면 또는 법면에 천공된 홀에 삽입되는 방식을 통해 설치되어 사면 또는 법면의 훼손을 최소화하는 것을 특징으로 하는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법.
In the river crossing method for eco-friendly open and close power pipes using PC culverts to protect pipes for repairing existing cables,
The eco-friendly open-and-run power pipe crossing method using the pipe protection PC culvert includes a preliminary preparation step including a PC culvert manufacturing step, a PC manhole manufacturing step, and an obstacle investigation and consultation step;
A pre-construction step including a construction guide board and safety facility installation step, a pedestrian and bicycle road bypass bridge installation step, a pollution barrier installation step, a construction road installation step, and a temporary block installation step;
Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower manhole installation steps, adhesive application steps, upper manhole installation steps, joint mortar waterproofing steps, and grounding steps Wow, installation of a PC manhole including an adjustment member installation step, a manhole cover installation step, a conduit body installation step, a conduit cover installation step in an unused conduit, a backfilling and compaction step, a soil barrier temporary facility removal step, and a residual soil removal step step;
Installing a temporary facility, installing a guide pipe, drilling an existing manhole in the direction of a river, installing an injection pipe, mortar grouting the inside after the pipe, and connecting the pipe to the PC manhole. Injecting pipe installation step comprising the step of connecting to and removing the temporary facility;
Assembling and installing temporary earth protection facilities, digging steps, floor selection steps, foundation sand laying steps, lower culvert installation steps, strand tensioning steps, fixing groove mortar filling steps, conduit laying steps, spacer installation steps And, a PC culvert installation step including a sand laying and compaction step, a spacer removal step, an upper culvert installation step, a backfilling step, a soil barrier temporary facility removal step, and a residual soil removal step;
A cable laying step including a continuity test step, a step of laying a new cable, a step of switching an existing cable, and a step of removing an existing conduit; And
A finishing step including a step of restoring the original stream and a step of carrying out equipment and tools; And,
The PC culvert includes the conduit, the lower culvert provided under the conduit to support the lower part of the conduit, the upper culvert provided above the conduit to cover the upper part of the conduit, and inside the lower culvert It is provided with the stranded wire to prevent linear maintenance and differential settlement,
The lower culvert is surrounded by a bottom plate in which the strands are embedded, a pair of side plates extending upward from both ends in the width direction of the bottom plate to cover the side surfaces of the conduit, and the bottom plate and the pair of side plates. It is provided in a form and has a seating hole in which the conduit is seated,
The upper culvert includes an upper plate, and a pair of side plates extending downward from both ends of the upper plate in the width direction to cover the pair of side plates,
The injection tube has a curved cylindrical body and a plurality of circular protrusions provided to protrude from the outer surface of the body, and is installed through a method that is inserted into a hole drilled in the slope or slope without opening the slope or slope. It is an eco-friendly open-and-seat power pipe cross-river method using a pipe protection PC culvert, characterized in that it minimizes damage to the slope or slope.
삭제delete 삭제delete 삭제delete 제2항 또는 제3항에 있어서,
상기 PC맨홀은 맨홀 뚜껑과 결합하는 홀을 구비하는 상판부와, 상기 상판부에서 하 방향으로 연장되어 상기 상판부를 지지하는 복수개의 제1기둥부를 구비하는 상기 상부맨홀;
상기 상부맨홀의 하부에 위치하는 하판부와, 상기 하판부에서 상 방향으로 연장되어 상기 제1기둥부와 결합하는 복수개의 제2기둥부를 구비하는 상기 하부맨홀; 및
상기 제1기둥부와 상기 제2기둥부에 구비되어 상기 상부맨홀과 상기 하부맨홀이 용이하게 결합하도록 하는 결합부; 를 구비하는 것을 특징으로 하는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법.
The method according to claim 2 or 3,
The PC manhole includes an upper manhole having an upper plate portion having a hole coupled with a manhole cover, and a plurality of first pillar portions extending downward from the upper plate portion to support the upper plate portion;
The lower manhole having a lower plate portion positioned below the upper manhole, and a plurality of second pillar portions extending upward from the lower plate portion and coupled to the first pillar portion; And
A coupling portion provided on the first and second pillars to facilitate coupling between the upper manhole and the lower manhole; An eco-friendly open-and-run electric power pipe crossing method using a pipe protection PC culvert, characterized in that it comprises a.
제 7항에 있어서,
결합 된 상기 상부맨홀과 상기 하부맨홀에는 관로구가 형성되고,
상기 상부맨홀과 상기 하부맨홀은 상기 관로구 측 상기 상판부, 상기 제1기둥부, 상기 하판부 및 상기 제2기둥부 일면에 노출되는 노출철근을 구비하는 것을 특징으로 하는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법.
The method of claim 7,
A pipe passage is formed in the combined upper manhole and the lower manhole,
The upper manhole and the lower manhole include exposed reinforcing bars exposed on one surface of the upper plate portion, the first pillar portion, the lower plate portion, and the second pillar portion on the pipe passage side. Type electric power pipe crossing river method.
제 8항에 있어서,
상기 관로구에는 상기 노출철근이 매설되도록 형성되어 미사용되는 상기 관로구를 덮는 관로구덮개가 구비되는 것을 특징으로 하는 관로보호 PC암거를 이용한 친환경 개착식 전력관로 하천횡단공법.
The method of claim 8,
The conduit port is formed so that the exposed reinforcement is buried, and a conduit cover for covering the unused conduit port is provided.
삭제delete
KR1020200032414A 2020-03-17 2020-03-17 Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert KR102170561B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200032414A KR102170561B1 (en) 2020-03-17 2020-03-17 Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200032414A KR102170561B1 (en) 2020-03-17 2020-03-17 Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert

Publications (1)

Publication Number Publication Date
KR102170561B1 true KR102170561B1 (en) 2020-10-27

Family

ID=73136149

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200032414A KR102170561B1 (en) 2020-03-17 2020-03-17 Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert

Country Status (1)

Country Link
KR (1) KR102170561B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113235657A (en) * 2021-04-30 2021-08-10 四川水建建设工程有限公司 Heavy-caliber immersed tube assembly and immersed tube method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000017967A (en) * 1999-12-31 2000-04-06 박병무 Cuvert And Production Method Therof
KR101052857B1 (en) * 2010-11-25 2011-07-29 산수산업 (주) The water-storage tank block and method for constructing thereof
JP2012031691A (en) * 2010-08-02 2012-02-16 Igarashi Daisuke Connection method of existing pipeline and new pipeline of manhole portion
KR20130043396A (en) * 2011-10-20 2013-04-30 주식회사 일성엔지니어링 Non excavation expansion repair method of flexible pipe for water and sewage
KR101585222B1 (en) * 2015-06-26 2016-01-13 정칠교 Protecting tube for distribution line in underground
KR101624518B1 (en) * 2015-12-29 2016-05-26 대실테크 주식회사 Live wire precast manhole and its construction method
KR101637507B1 (en) * 2015-12-11 2016-07-07 대실테크 주식회사 River crossing buried pipeline construction and pipeline laying method using the same
KR20190140313A (en) * 2018-06-11 2019-12-19 한국전력공사 Assembly type manhole

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000017967A (en) * 1999-12-31 2000-04-06 박병무 Cuvert And Production Method Therof
JP2012031691A (en) * 2010-08-02 2012-02-16 Igarashi Daisuke Connection method of existing pipeline and new pipeline of manhole portion
KR101052857B1 (en) * 2010-11-25 2011-07-29 산수산업 (주) The water-storage tank block and method for constructing thereof
KR20130043396A (en) * 2011-10-20 2013-04-30 주식회사 일성엔지니어링 Non excavation expansion repair method of flexible pipe for water and sewage
KR101585222B1 (en) * 2015-06-26 2016-01-13 정칠교 Protecting tube for distribution line in underground
KR101637507B1 (en) * 2015-12-11 2016-07-07 대실테크 주식회사 River crossing buried pipeline construction and pipeline laying method using the same
KR101624518B1 (en) * 2015-12-29 2016-05-26 대실테크 주식회사 Live wire precast manhole and its construction method
KR20190140313A (en) * 2018-06-11 2019-12-19 한국전력공사 Assembly type manhole

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113235657A (en) * 2021-04-30 2021-08-10 四川水建建设工程有限公司 Heavy-caliber immersed tube assembly and immersed tube method

Similar Documents

Publication Publication Date Title
CN113404062B (en) Waterproof and drainage construction method for backfilling laying of underground cable and PE (polyethylene) guide pipe
CN112064751A (en) Deep groove construction method for drainage pipeline
KR102170561B1 (en) Eco-friendly open-type electric power line river crossing method using pipeline protection PC culvert
KR100562158B1 (en) Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor
KR101682541B1 (en) Culvert crossing buried pipeline construction and pipeline laying method using the same
KR20210055980A (en) Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same
CN109797776B (en) Construction method for underground pipe gallery to meet cross pipeline based on open cut method
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
CN115710912A (en) Narrow roadway foundation pit supporting process
CN108951702A (en) A kind of construction method of pipe gallery
WO2013168879A1 (en) Construction of a structure using a trough and a process for constructing the structure
KR20210055981A (en) Underground roadway using steel continuous wall in the earth with minimum traffic control in constructing by top-down method and method for constructing the same
WO2010104234A1 (en) Structural steel casing, retaining wall, construction method thereof, and construction method for levee maintenance and road expansion
JP2002233019A (en) Pipe line for electric wire and the like
KR102118064B1 (en) Uninterruptible construction method of high and low pressure uninterruptible junction box using recycled composite resin
KR100538398B1 (en) The method of construction (KY-5 Pipejacking and propulsion method) and apparatus for propulsion based on soft and weak layer soil
CN217642641U (en) Pipe-penetrating direct-buried cable trench
JP4630215B2 (en) Relocation method for buried objects
WO2014069714A1 (en) Method for constructing earth retaining structure using iron plate
KR20050029332A (en) Basic bottom permanent drainage structure using trench and drainage member and it's construction method
JP2002021098A (en) Cut and cover tunneling method
CN115538448A (en) In-situ protection method for underground cable passing through excavation of subway foundation pit
JP3352951B2 (en) Installation method of invert and underground drainage in mountain tunnel
JP2008057188A (en) Earthquake resisting manhole structure and its manufacturing method
Maugain Basics on Construction and Installation Methods

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant