KR101578205B1 - Method for constructing wall embeded insulating metals in concrete walls - Google Patents

Method for constructing wall embeded insulating metals in concrete walls Download PDF

Info

Publication number
KR101578205B1
KR101578205B1 KR1020150014488A KR20150014488A KR101578205B1 KR 101578205 B1 KR101578205 B1 KR 101578205B1 KR 1020150014488 A KR1020150014488 A KR 1020150014488A KR 20150014488 A KR20150014488 A KR 20150014488A KR 101578205 B1 KR101578205 B1 KR 101578205B1
Authority
KR
South Korea
Prior art keywords
wall
formwork
heat insulating
insulating material
die
Prior art date
Application number
KR1020150014488A
Other languages
Korean (ko)
Inventor
김대자
Original Assignee
김대자
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김대자 filed Critical 김대자
Priority to KR1020150014488A priority Critical patent/KR101578205B1/en
Application granted granted Critical
Publication of KR101578205B1 publication Critical patent/KR101578205B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/7604Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only fillings for cavity walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/64Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete
    • E04B2/68Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete made by filling-up wall cavities

Abstract

The present invention relates to a method to construct a wall of a building in order to prevent heat loss in the building by embedding an adiabatic material in the wall of the building formed with concrete. In order to achieve this, the method of the present invention comprises: a step of arranging separately a first cast and a second cast on a position to form a concrete wall, and fixing the first cast to a first fastening hole formed on one end of a flat tie, and fixing the second cast to a third fastening hole formed on a center of the flat tie under a state where an adiabatic material adheres to an inner side of the second cast using the flat tie where the third fastening hole is formed on the center to install the adiabatic material in accordance as the first fastening hole, the second fastening hole, and a cutting groove formed on both ends of a position for an inner wall and an outer wall to be formed; a step of curing a first wall by inserting a concrete mortar between the first case and the adiabatic material, and then moving the second cast to a position of the second fastening hole formed on an other end of the flat tie, and then curing a second wall by inserting the concrete mortar between the second cast and the adiabatic material; and a step of removing both ends of the flat tie exposed to the outside of the first and the second wall formed by the cured concrete mortar by cutting both ends of the flat tie in accordance to the cutting groove formed on both ends of the flat tie after taking out the first cast and the second cast.

Description

콘크리트벽체 내에 단열재가 매립된 건축물의 벽체 시공방법{METHOD FOR CONSTRUCTING WALL EMBEDED INSULATING METALS IN CONCRETE WALLS}TECHNICAL FIELD [0001] The present invention relates to a method for constructing a wall of a building in which a heat insulating material is embedded in a concrete wall,

본 발명은 콘크리트로 이루어지는 건축물의 벽체에 단열재를 설치하여 건축물 내의 열손실을 방지할 수 있도록 하는 건축물의 벽체 시공방법에 관한 것으로, 더욱 상세하게는 콘크리트 벽체 내에 하나 이상의 단열재를 매립시켜 단열효율을 향상시키도록 하는, 콘크리트벽체 내에 단열재가 매립된 건축물의 벽체 시공방법에 관한 것이다.
The present invention relates to a method of constructing a wall of a building to prevent heat loss in the building by providing a heat insulating material on a wall of a building made of concrete. More particularly, the present invention relates to a method of inserting one or more heat insulating materials in a concrete wall To a method of constructing a wall of a building in which a heat insulating material is embedded in a concrete wall.

근래에 들어 지구온난화 방지 및 환경보호를 목적으로 단열과 친환경 건설 방법에 대한 연구가 늘고 있다.In recent years, researches on insulation and eco-friendly construction methods have been increasing for the purpose of preventing global warming and protecting the environment.

일반적으로 건축물의 벽체를 시공할 때에는 벽체를 형성할 부위에 철근을 수직 및 수평으로 배근하고, 배근된 철근들의 양측으로 거푸집을 평행하게 설치한 후, 평행하게 배치되어 있는 거푸집 사이로 콘크리트를 타설하여 소정시간 양생하게 되며, 이후 양생된 콘크리트 벽면의 내측면 및/또는 외측면에 단열재를 설치하고 마감재로 마감처리하여 벽체를 완성하게 된다.Generally, when a wall of a building is to be installed, reinforcing bars are vertically and horizontally arranged at a portion where a wall is to be formed, and the formwork is installed parallel to both sides of the reinforced bars, and then concrete is placed between parallel- And then the insulating material is installed on the inner side and / or the outer side of the cured concrete wall surface and finished with the finishing material to complete the wall.

도 1 및 도 2는 종래 콘크리트 건축물의 시공예를 나타내는 것으로, 도 1에 도시된 바와 같이 배근된 철근(12)을 중심으로 실외측과 실내측에 거푸집(14)이 평행하게 설치되는데, 평행한 거푸집(14)이 소정간격을 일정하게 유지할 수 있도록 평행한 거푸집들은 플랫 타이에 의해 고정된 상태에서 거푸집(14) 사이에 콘크리트(20)가 타설되어 벽체가 형성되어 있다. 그리고 도 2의 확대단면도에 도시된 바와 같이 양생된 콘크리트(20)의 외면에 단열재(30)가 부착된 상태에서 단열재 외면에 마감재(40)로 마무리되어 벽체를 형성하고 있다.1 and 2 illustrate an example of construction of a conventional concrete building. As shown in FIG. 1, a formwork 14 is installed parallel to an outdoor side and an indoor side with respect to a reinforced concrete reinforcement 12, The parallel molds are fixed by the flat tie so that the molds 14 can be maintained at a predetermined interval, and the concrete is placed between the molds 14 to form a wall. As shown in an enlarged cross-sectional view of FIG. 2, the heat insulating material 30 is attached to the outer surface of the cured concrete 20, and the outer surface of the heat insulating material is finished with a finishing material 40 to form a wall.

그러나 이와 같은 종래 콘크리트벽체의 단열재는 건물벽체의 외벽 또는 내벽에 단열재를 부착하도록 이루어져 있기 때문에 화재나 충격에 취약하고, 유지보수에 많은 비용이 소요될 수 있으며, 특히 단열재는 단열과 화재에 강한 석면 등을 주로 사용하는 관계로 단열재가 파손되면 인체에 유해한 물질에 쉽게 노출될 수 있는 문제점이 있었다.
However, since the conventional heat insulating material of the concrete wall is constructed to adhere the heat insulating material to the outer wall or the inner wall of the building wall, it is vulnerable to fire or shock, and it may take a lot of maintenance and repairing cost. Especially, And thus, when the heat insulating material is broken, it is easily exposed to harmful substances to the human body.

국내공개특허공보 10-2013-0075109(2013년7월5일 공개)Korean Patent Publication No. 10-2013-0075109 (published on July 5, 2013)

본 발명은 상기 사정을 감안하여 발명한 것으로, 콘크리트 벽체의 시공시 그 벽체 내에 하나 이상의 단열재를 매립하는 다중 복합 구조의 벽체를 일체로 형성하도록 함으로써, 단열재의 양면으로 콘크리트벽체가 배치되어 외부로부터 열이나 충격을 받더라도 손상되지 않고 방음, 방수, 단열성능이 우수함과 아울러, 화재시 고열로 인하여 내부의 단열재가 녹아내리더라도 유독가스를 배출하지 않으면서 그 자리에 공기층이 형성되면서 단열층 역할을 하게 되므로 인명피해를 최대한 줄일 수 있도록 된 콘크리트벽체 내에 단열재가 매립된 건축물의 벽체 시공방법을 제공하고자 함에 그 목적이 있다.
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a composite wall structure in which one or more heat insulating materials are embedded in a wall of a concrete wall when the concrete wall is constructed, And it is excellent in soundproofing, waterproofing and insulation performance even when it is impacted. In addition, even when the heat insulating material melts due to high heat in the fire, the air layer is formed on the place without discharging toxic gas, It is an object of the present invention to provide a method of constructing a wall of a building in which a heat insulating material is embedded in a concrete wall which can minimize damage.

상기 목적을 달성하기 위한 본 발명의 제1 실시예에 따른 시공방법은,In order to accomplish the above object, according to a first aspect of the present invention,

건축물의 벽체를 형성하기 위해 제1 거푸집과 제2거푸집을 폭 방향으로 대향시켜 소정 간격 이격되게 배치하고 상기 제1 거푸집과 제2 거푸집 사이에 콘크리트를 타설한 후 양생하여 콘크리트벽체를 형성하는 건축물의 벽체 시공방법에 있어서,A structure for constructing a concrete wall by placing concrete between a first formwork and a second formwork and then curing the first formwork and the second formwork so as to face the first formwork and the second formwork in a width direction to form a wall of the building, In the wall construction method,

콘크리트벽체를 형성할 위치에 제1 거푸집과 제2 거푸집을 소정 간격 이격되게 배치하는 단계;Disposing a first formwork and a second formwork so as to be spaced apart from each other by a predetermined distance at a position where the concrete wall is to be formed;

내벽과 외벽이 형성될 위치의 양단에 제1, 제2 체결구멍과 절단홈이 각각 형성됨과 아울러 단열재가 설치될 위치의 중앙에 제3 체결구멍이 형성되어 있는 플랫타이를 사용하여 상기 제1 거푸집을 상기 플랫타이의 일측 끝단에 형성되어 있는 제1 체결구멍에 체결핀으로 고정하는 단계;The first and second fastening holes and the cut grooves are formed at both ends of the position where the inner wall and the outer wall are to be formed, and the third fastening hole is formed at the center of the position where the heat insulating material is to be installed, Securing the first fastening hole to the first fastening hole formed at one end of the flat tie with the fastening pin;

상기 제2 거푸집을 플랫타이의 중앙에 형성되어 있는 제3 체결구멍에 체결핀으로 고정하되, 제2 거푸집의 내측면에 단열재가 밀착된 상태로 고정하는 단계;Fixing the second die in a state where the heat insulating material is adhered to the inner surface of the second die by fixing the third die with the fastening pin in the third fastening hole formed at the center of the flat tie;

상기 제1 거푸집과 단열재 사이에 콘크리트몰탈을 투입하여 제1 벽체를 양생하는 단계;Curing the first wall by injecting concrete mortar between the first formwork and the heat insulating material;

상기 제2 거푸집을 플랫타이의 타측 끝단에 형성되어 있는 제2 체결구멍 위치로 이동하여 체결핀으로 고정하는 단계;Moving the second die to a second fastening hole position formed at the other end of the flat tie and fixing the second die with a fastening pin;

상기 제2 거푸집과 단열재 사이에 콘크리트몰탈을 투입하여 제2 벽체를 양생하는 단계;Curing the second wall by injecting concrete mortar between the second formwork and the heat insulating material;

상기 제1 및 제2 거푸집을 떼어낸 후 상기 플랫타이의 양단에 형성된 절단홈을 기준으로 플랫타이의 양단을 잘라내어 양생된 콘크리트몰탈에 의해 형성되는 제1, 제2 벽체 외측으로 노출되는 플랫타이의 양단을 제거하는 단계;The first and second molds are removed, and both ends of the flat tie are cut off with reference to a cutting groove formed at both ends of the flat tie. The flat tie is exposed to the outside of the first and second walls formed by the cured concrete mortar Removing both ends;

를 포함하여 이루어져, 단열재가 벽체 내에 매립되는 콘크리트벽체를 시공하도록 되어 있다.
So as to construct a concrete wall in which the heat insulating material is embedded in the wall.

또한 본 발명의 제2 실시예에 따른 시공방법은, According to a second aspect of the present invention,

건축물의 벽체를 형성하기 위해 제1 거푸집과 제2거푸집을 폭 방향으로 대향시켜 소정 간격 이격되게 배치하고 상기 제1 거푸집과 제2 거푸집 사이에 콘크리트를 타설한 후 양생하여 콘크리트벽체를 형성하는 건축물의 벽체 시공방법에 있어서,A structure for constructing a concrete wall by placing concrete between a first formwork and a second formwork and then curing the first formwork and the second formwork so as to face the first formwork and the second formwork in a width direction to form a wall of the building, In the wall construction method,

콘크리트벽체를 형성할 위치에 제1 거푸집과 제2 거푸집을 소정 간격 이격되게 배치하는 단계;Disposing a first formwork and a second formwork so as to be spaced apart from each other by a predetermined distance at a position where the concrete wall is to be formed;

내벽과 외벽이 형성될 위치의 양단에 제1, 제2 체결구멍과 절단홈이 각각 형성됨과 아울러 단열재가 설치될 위치의 중간에 제3 체결구멍과 제4 체결구멍이 형성되어 있는 플랫타이를 사용하여 상기 제1 거푸집을 상기 플랫타이의 중간 일측에 형성되어 있는 제3 체결구멍에 체결핀으로 고정하되, 제1 거푸집의 내측면에 단열재가 밀착된 상태로 고정하는 단계;The first and second fastening holes and the cut grooves are formed at both ends of the position where the inner wall and the outer wall are to be formed, and the flat tie having the third fastening hole and the fourth fastening hole formed in the middle of the position where the heat insulating material is to be installed Fixing the first die in a state in which the heat insulating material is adhered to the inner surface of the first die by fixing pins to the third fastening hole formed at the intermediate side of the flat tie;

상기 제2 거푸집을 플랫타이의 중간 타측에 형성되어 있는 제4 체결구멍에 체결핀으로 고정하되, 제2 거푸집의 내측면에 단열재가 밀착된 상태로 고정하는 단계;Fixing the second die in a state where the heat insulating material is adhered to the inner surface of the second die by fixing the fourth die with the fastening pin in the fourth fastening hole formed on the other side of the flat tie;

상기 제1 거푸집의 단열재와 제2 거푸집의 단열재 사이에 콘크리트몰탈을 투입하여 제1 벽체를 양생하는 단계;Curing the first wall by injecting concrete mortar between the heat insulating material of the first formwork and the heat insulating material of the second formwork;

상기 제1, 제2 거푸집을 각각 플랫타이의 타측 끝단에 형성되어 있는 제1, 제2 체결구멍 위치로 이동하여 체결핀으로 고정하는 단계;Moving the first and second molds to the first and second fastening hole positions formed at the other end of the flat tie, respectively, and fixing the first and second molds with the fastening pin;

상기 제1, 제2 거푸집과 각각의 거푸집에 대향하고 있는 단열재 사이에 콘크리트몰탈을 투입하여 제2, 제3 벽체를 양생하는 단계;Curing the second and third walls by injecting the concrete mortar between the first and second molds and the heat insulating material opposed to the respective molds;

상기 제1 및 제2 거푸집을 떼어낸 후 상기 플랫타이의 양단에 형성된 절단홈을 기준으로 플랫타이의 양단을 각각 잘라내어 양생된 콘크리트몰탈에 의해 형성되는 제2, 제3 벽체 외측으로 노출되는 플랫타이의 양단을 제거하는 단계;The first and second molds are removed, and both ends of the flat tie are cut off based on the cut grooves formed at both ends of the flat tie. The flat tie is exposed to the outside of the second and third walls formed by the cured concrete mortar. Removing both ends of the support;

를 포함하여 이루어져, 단열재가 2중으로 매립되는 콘크리트벽체를 시공하도록 되어 있다.
So as to construct a concrete wall in which a heat insulating material is doubly embedded.

이어, 본 발명의 제3 실시예에 따른 시공방법은, Next, a construction method according to a third embodiment of the present invention,

건축물의 벽체를 형성하기 위해 제1 거푸집과 제2거푸집을 폭 방향으로 대향시켜 소정 간격 이격되게 배치하고 상기 제1 거푸집과 제2 거푸집 사이에 콘크리트를 타설한 후 양생하여 콘크리트벽체를 형성하는 건축물의 벽체 시공방법에 있어서,A structure for constructing a concrete wall by placing concrete between a first formwork and a second formwork and then curing the first formwork and the second formwork so as to face the first formwork and the second formwork in a width direction to form a wall of the building, In the wall construction method,

콘크리트벽체를 형성할 위치에 제1 거푸집과 제2 거푸집을 소정 간격 이격되게 배치하는 단계;Disposing a first formwork and a second formwork so as to be spaced apart from each other by a predetermined distance at a position where the concrete wall is to be formed;

내벽과 외벽이 형성될 위치의 양단에 제1, 제2 체결구멍과 절단홈이 각각 형성됨과 아울러 단열재가 설치될 위치의 중앙에 제3 체결구멍이 형성되어 있는 플랫타이를 사용하여 상기 제1 거푸집을 상기 플랫타이의 일측 끝단에 형성되어 있는 제1 체결구멍에 체결핀으로 고정하는 단계;The first and second fastening holes and the cut grooves are formed at both ends of the position where the inner wall and the outer wall are to be formed, and the third fastening hole is formed at the center of the position where the heat insulating material is to be installed, Securing the first fastening hole to the first fastening hole formed at one end of the flat tie with the fastening pin;

상기 제2 거푸집을 플랫타이의 중앙에 형성되어 있는 제3 체결구멍에 체결핀으로 고정하되, 제2 거푸집의 내측면에 제1 단열재가 밀착된 상태로 고정하는 단계;Fixing the second die in a state in which the first heat insulating material is in close contact with the inner surface of the second die by fixing the third die with the fastening pin in the third fastening hole formed at the center of the flat tie;

상기 제1 거푸집과 제1 단열재 사이에 콘크리트몰탈을 투입하여 제1 벽체를 양생하는 단계;Curing the first wall by injecting concrete mortar between the first mold and the first heat insulating material;

상기 제2 거푸집을 플랫타이의 타측 끝단에 형성되어 있는 제2 체결구멍 위치로 이동하여 체결핀으로 고정하는 단계;Moving the second die to a second fastening hole position formed at the other end of the flat tie and fixing the second die with a fastening pin;

상기 제2 거푸집과 제1 단열재 사이에 콘크리트몰탈을 투입하여 제2 벽체를 양생하는 단계;Curing the second wall by injecting concrete mortar between the second mold and the first heat insulating material;

상기 제1 거푸집을 해체하고 제1 벽체의 외벽에 제2 단열재를 부착시공하는 단계;Disassembling the first formwork and attaching a second heat insulator to an outer wall of the first wall;

상기 제2 단열재 외측으로 소정 거리 이격시겨 제3 거푸집을 설치하되, 상기 제1 벽체 외면으로 노출되는 플랫타이의 제1 체결구멍에 고리볼트의 걸고리를 끼우고 고리볼트의 타단인 나사산이 형성되어 있는 부분을 제3 거푸집을 관통시킨 후 반대편에서 너트를 체결하여 고정하는 단계;A third die is provided to be spaced apart from the second heat insulating member by a predetermined distance, and a hook of the hook bolt is inserted into the first fastening hole of the flat tie exposed to the outer surface of the first wall, And then fixing and fixing the nut on the opposite side after passing through the third die;

상기 제2 단열재와 제3 거푸집 사이에 콘크리트몰탈을 투입하여 제3 벽체를 양생하는 단계;Curing the third wall by injecting concrete mortar between the second insulation and the third die;

상기 제2 및 제3 거푸집을 해체한 후 제2 벽체 외측으로 노출되는 플랫타이의 끝단을 제거하는 단계;Removing the ends of the flat ties exposed to the outside of the second wall after disassembling the second and third dies;

를 포함하여 이루어져, 단열재가 다중으로 매립되는 콘크리트벽체를 시공하도록 되어 있다.
So as to construct a concrete wall in which the heat insulating material is embedded in multiple.

상기한 바와 같은 본 발명은 단열재가 콘크리트벽체 내에 매립된 상태로 시공되므로 단열재가 열이나 충격에 보호된다. 또한, 매립된 단열재가 고열로 인하여 내부에서 녹아 소멸되더라도 단열재가 있던 자리에 형성되는 공기층이 단열층 역할을 함으로써 난방효율이 높아 저렴한 비용으로 난방효율을 극대화할 수 있다. 아울러, 방음 및 방수효과에 의해 사행활 노출 등에 의한 피해를 줄일 수 있는 효과가 있다.
In the present invention as described above, since the heat insulating material is embedded in the concrete wall, the heat insulating material is protected from heat or impact. In addition, even if the insulated material is melted due to the high temperature, the air layer formed at the place where the heat insulating material is disposed serves as a heat insulating layer, so that the heating efficiency is high and the heating efficiency can be maximized at low cost. In addition, there is an effect that the damage due to the exposure of the meandering bow by the soundproofing and the waterproof effect can be reduced.

도 1은 종래 콘크리트벽체의 시공과정을 설명하기 위한 도면
도 2는 도 1에 의거 시공된 단열벽체의 구조를 설명하기 위한 도면,
도 3 내지 도 5는 본 발명에 따른 시공방법의 제1 실시예를 설명하기 위한 도면,
도 6은 본 발명에 따른 플랫타이의 구성도,
도 7의 (a) 및 (b)는 본 발명에 따른 시공방법의 제2 실시예를 설명하기 위한 도면,
도 8은 본 발명에 따른 시공방법의 제3 실시예를 설명하기 위한 도면.
1 is a view for explaining a construction process of a conventional concrete wall;
FIG. 2 is a view for explaining a structure of a heat insulating wall constructed according to FIG. 1,
3 to 5 are views for explaining a first embodiment of a construction method according to the present invention,
6 is a configuration diagram of a flat tie according to the present invention,
7 (a) and 7 (b) are views for explaining a second embodiment of the construction method according to the present invention,
8 is a view for explaining a third embodiment of a construction method according to the present invention.

이하, 본 발명의 바람직한 실시예를 예시도면에 의거하여 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 3 내지 도 5는 본 발명에 따른 시공방법의 제1 실시예를 설명하기 위한 도면이다.3 to 5 are views for explaining a first embodiment of a construction method according to the present invention.

먼저, 도 3에 도시된 바와 같이 콘크리트벽체를 형성할 위치에 콘크리트벽체의 두께를 고려하여 제1 거푸집(112)과 제2 거푸집(114)을 소정 간격 이격되게 배치한 후 플랫타이(120A)를 사용하여 이격상태를 유지할 수 있도록 고정하게 된다.3, the first dies 112 and the second dies 114 are spaced apart from each other by a predetermined distance in consideration of the thickness of the concrete wall at the position where the concrete wall is to be formed, and then the flat tie 120A So as to be able to maintain the spacing.

이때 사용되는 플랫타이(120A)는 도 6의 (a)에 도시된 바와 같이 전체적인 형상은 장방형의 철편으로 이루어지고, 양단에 제1 체결구멍(121)과 제2 체결구멍(122)이 형성됨과 아울러 중앙에 제3 체결구멍(123)이 형성되어 있으며, 제1 체결구멍(121)과 제2 체결구멍(122) 직전 가장자리에는 예컨대 V형의 절단홈(125)이 각각 형성된 것이다. 상기 제1 내지 제3 체결구멍(121~123)은 공지된 바와 같이 거푸집에 형성되어 있는 체결구멍과 일치시킨 후 체결핀을 관통시켜 거푸집을 고정하는데 사용되는 것이고, 절단홈(125)은 거푸집 사이에 콘크리트몰탈을 타설하여 콘크리트벽체를 축조하였을 때 콘크리트벽체 외부로 노출되는 플랫타이 끝단을 용이하게 잘라내는데 사용되는 것이다. 특히 플랫타이(120A)의 양단에 형성되는 제1 체결구멍(121)과 제2 체결구멍(122)은 축조될 콘크리트벽체의 두께에 대응되어 형성되며, 중앙에 형성되는 제3 체결구멍(123)은 축조될 콘크리트벽체 내에 단열재가 매립될 위치를 고려하여 형성되는 것이다.As shown in FIG. 6A, the flat tie 120A used in this case has a rectangular shape as a whole, a first fastening hole 121 and a second fastening hole 122 are formed at both ends thereof, A third fastening hole 123 is formed at the center and a V-shaped cutting groove 125 is formed at the edge just before the first fastening hole 121 and the second fastening hole 122, respectively. The first to third fastening holes 121 to 123 are used to fasten the mold by passing the fastening pin through the fastening holes formed in the mold as well known in the art, And the concrete mortar is laid to construct the concrete wall, the flat tie end exposed to the outside of the concrete wall is easily cut. Particularly, the first fastening hole 121 and the second fastening hole 122 formed at both ends of the flat tie 120A are formed corresponding to the thickness of the concrete wall to be constructed, and the third fastening hole 123, Is formed in consideration of the position where the heat insulating material is to be embedded in the concrete wall to be built.

즉, 도 3에 도시된 바와 같이 제1 거푸집(112)은 플랫타이(120A)의 일측 끝단에 형성된 제1 체결구멍(121)에 맞춰 체결핀(도시되지 않음)으로 고정하고 제2 거푸집(114)은 플랫타이(120A)의 중앙에 형성된 제3 체결구멍(123)에 맞춰 체결핀(도시되지 않음)으로 고정한다. 3, the first die 112 is fixed with a fastening pin (not shown) in alignment with the first fastening hole 121 formed at one end of the flat tie 120A, and the second die 114 Is fastened with a fastening pin (not shown) in conformity with the third fastening hole 123 formed at the center of the flat tie 120A.

이때 제2 거푸집(114)의 내측면에는 단열재(130)를 먼저 밀착된 상태로 고정하는데, 단열재(130)를 원활하게 설치할 수 있도록 단열재(130)에서 플랫타이(120A)가 관통될 위치에는 관통되는 플랫타이(120A)의 크기에 대응되는 관통홈(도시되지 않음)이 미리 형성됨이 바람직하며, 이러한 단열재(130)의 플랫타이(120A) 관통홈은 단열재(130)의 제조과정에서 미리 형성함이 바람직하다.At this time, the heat insulating material 130 is first fixed to the inner surface of the second die 114 in a state in which the heat insulating material 130 is closely adhered. In order to smoothly install the heat insulating material 130, (Not shown) corresponding to the size of the flat tie 120A is formed in advance in the process of manufacturing the heat insulating material 130. Preferably, the through trench 120A of the heat insulating material 130 is formed in advance in the process of manufacturing the heat insulating material 130 .

상기와 같이 대향하고 있는 제1 거푸집(112)과 제2 거푸집(114) 사이 특히 제1 거푸집(112)과 단열재(130) 사이에 콘크리트몰탈을 투입하여 제1 벽체(141)를 양생한다.The first wall 141 is cured by injecting the concrete mortar between the first die 112 and the second die 114 facing each other as described above, particularly between the first die 112 and the heat insulating material 130.

이후, 제2 거푸집(114)과 플랫타이(120A)를 결속하고 있는 체결핀을 빼내면 제2 거푸집(114)이 단열재(130)로부터 분리되며, 분리되는 제2 거푸집(110)을 플랫타이(120A)의 타측 끝단에 형성되어 있는 제2 체결구멍(122) 위치로 이동시켜 제2 거푸집(114)의 프레임에 형성되어 있는 체결구멍과 플랫타이(120A)의 제2 체결구멍(122)을 일치시킨 후 체결핀을 사용하여 고정한다.The second die 114 is separated from the heat insulating material 130 and the second die 110 is separated from the flat tie 120 by pulling out the fastening pin binding the second die 114 and the flat tie 120A. The first fastening hole 122 formed at the other end of the flat tie 120A is moved to the position of the second fastening hole 122 formed at the other end of the flat tie 120A so that the fastening hole formed in the frame of the second die 114 matches the second fastening hole 122 of the flat tie 120A And then fix it with a fastening pin.

이에 따라 제2 거푸집(114)과 단열재(130) 사이에는 제2 체결구멍(122)과 제3 체결구멍(123) 간의 거리만큼 소정 공간이 형성되며, 이 공간에 콘크리트몰탈을 타설 및 양생하여 제2 벽체(142)를 형성한다.A predetermined space is formed between the second die 114 and the heat insulating material 130 by a distance between the second fastening hole 122 and the third fastening hole 123 and the concrete mortar is placed and cured 2 wall 142 is formed.

상기와 같이 제2 벽체(142)를 양생한 후 제1 거푸집(112) 및 제2 거푸집(114)을 제거하면 제1 벽체(141)와 제2 벽체(142) 사이에 단열재(130)가 매립된 상태의 콘크리트벽체가 형성된다.When the first and second molds 112 and 114 are removed after the second wall 142 is cured as described above, the heat insulating material 130 is buried between the first wall 141 and the second wall 142 The concrete wall is formed.

이때 제1 벽체(141)와 제2 벽체(142) 외측면으로는 플랫타이(120A)에서 제1 거푸집(112) 및 제2 거푸집(114)과 체결되었던 끝단이 노출되는데, 플랫타이(120A)의 각 양단에 형성된 절단홈(125)이 제1 벽체(141)와 제2 벽체(142)의 외측면과 동일 평면에 위치하게 되므로, 플랫타이(120A)의 절단홈(125) 외측으로 타격을 가하여 절단홈(125)을 기준으로 플랫타이(120A)의 양 끝단을 잘라내어 도 5에 도시된 바와 같이 제1 벽체(141)와 제2 벽체(142)의 외측면으로 플랫타이(120A)의 끝단이 노출되지 않은 콘크리트벽체를 형성한다.At this time, the end of the flat tie 120A which is fastened to the first and second dies 112 and 114 is exposed to the outer surface of the first wall 141 and the second wall 142. The flat tie 120A, The cutting grooves 125 formed at both ends of the flat tie 120A are positioned on the same plane as the outer surfaces of the first wall 141 and the second wall 142 so that the strike of the flat tie 120A outside the cut groove 125 The both ends of the flat tie 120A are cut off with reference to the cut groove 125 to form the outer edges of the first wall 141 and the second wall 142 as shown in FIG. Thereby forming an unexposed concrete wall.

이후, 제1 벽체(141)와 제2 벽체(142) 외측으로 마감재(도시되지 않음)를 시공함으로써 콘크리트벽체의 중앙에 단열재를 매립한 콘크리트벽체를 완성한다.
Thereafter, a finishing material (not shown) is installed outside the first wall 141 and the second wall 142 to complete a concrete wall in which a heat insulating material is embedded in the center of the concrete wall.

도 7의 (a) 및 (b)는 본 발명에 따른 시공방법의 제2 실시예를 설명하기 위한 도면이다. 7 (a) and 7 (b) are views for explaining a second embodiment of the construction method according to the present invention.

도 7에 도시된 실시예의 기본 시공방법은 상기 제1 실시예와 유사한 것으로, 제1 실시예가 콘크리트벽체 내에 단일의 단열재를 매립하는 시공방법임과 달리 제2 실시예는 콘크리트벽체 내에 2중의 단열재를 매립하는 시공방법이다.The basic construction method of the embodiment shown in FIG. 7 is similar to that of the first embodiment, except that the first embodiment embeds a single heat insulator in the concrete wall, It is a construction method to be buried.

도 7의 (a)에 도시된 바와 같이 본 발명의 제2 실시예에 따른 시공방법을 수행하기 위해서는 도 6의 (b)에 도시된 바와 같은 플랫타이(120B)를 사용할 수 있다.As shown in FIG. 7 (a), a flat tie 120B as shown in FIG. 6 (b) can be used to perform the construction method according to the second embodiment of the present invention.

상기 플랫타이(120B)는 플랫타이(120A)와 달리 제1 체결구멍(121)과 제2 체결구멍(122) 사이에 2개의 체결구멍(123)(124)이 형성되어 있으며, 각 체결구멍(123)(124) 위치에 단열재(130a)(130b)를 배치하여 매립하기 위한 것이다.Unlike the flat tie 120A, the flat tie 120B has two fastening holes 123 and 124 formed between the first fastening hole 121 and the second fastening hole 122, 123) 124 by inserting the heat insulating materials 130a, 130b.

즉, 플랫타이(120B)의 양단에 제1 체결구멍(121)과 제2 체결구멍(122)이 형성됨과 아울러 중간에 제3 체결구멍(123)과 제4 체결구멍(124)이 형성되어 있으며, 제1 체결구멍(121)과 제2 체결구멍(122) 직전 가장자리에는 예컨대 V형의 절단홈(125)이 각각 형성된 것이다. That is, the first fastening hole 121 and the second fastening hole 122 are formed at both ends of the flat tie 120B, and the third fastening hole 123 and the fourth fastening hole 124 are formed in the middle And a V-shaped cutting groove 125 is formed at the edge just before the first fastening hole 121 and the second fastening hole 122, respectively.

다음에는 제2 실시예의 시공방법에 대하여 설명한다.Next, the construction method of the second embodiment will be described.

도 7의 (a)에 도시된 바와 같이 제1 거푸집(112)은 플랫타이(120B)의 중간에 형성된 제3 체결구멍(123)에 맞춰 체결핀(도시되지 않음)으로 고정하고 제2 거푸집(114)은 플랫타이(120B)의 중간에서 제3 체결구멍(123)과 소정 간격 이격도어 형성된 제4 체결구멍(124)에 맞춰 체결핀(도시되지 않음)으로 고정한다. 7A, the first die 112 is fixed with a fastening pin (not shown) in conformity with the third fastening hole 123 formed in the middle of the flat tie 120B, and the second die 114 are fastened with a fastening pin (not shown) in the middle of the flat tie 120B in conformity with the fourth fastening hole 124 formed at a predetermined distance from the third fastening hole 123.

이때 제1 거푸집(112)와 제2 거푸집(114)의 내측면에는 단열재(130a)(130b)를 제1 실시예와 같은 방법으로 각각 먼저 밀착된 상태로 고정한다.At this time, the heat insulating materials 130a and 130b are fixed to the inner surfaces of the first die 112 and the second die 114 in a state in which they are tightly adhered in the same manner as in the first embodiment.

상기와 같이 대향하고 있는 제1 거푸집(112)과 제2 거푸집(114) 사이 특히 단열재(130a)와 단열재(130b) 사이에 콘크리트몰탈을 투입하여 제1 벽체(141)를 양생한다.The first wall 141 is cured by injecting concrete mortar between the first die 112 and the second die 114 facing each other as described above, particularly between the heat insulating material 130a and the heat insulating material 130b.

이후, 제3 체결구멍(123)에 결속되어 있는 제1 거푸집(112)을 분리하여 끝단의 제1 체결구멍(121)으로 이동하여 결속함과 아울러 제4 체결구멍(124)에 결속되어 있는 제2 거푸집(114)을 분리하여 끝단의 제2 체결구멍(122)으로 이동하여 결속한다.Thereafter, the first die 112 bound to the third fastening hole 123 is separated and moved to the first fastening hole 121 at the end, and the first die 112 is coupled to the fourth fastening hole 124, 2 molds 114 are separated and moved to the second fastening holes 122 at the ends to bind.

이에 따라 제1 거푸집(112)과 단열재(130a) 사이에는 제1 체결구멍(121)과 제3 체결구멍(123) 간의 거리만큼 소정 공간이 형성되고 또한 제2 거푸집(114)과 단열재(130b) 사이에도 제2 체결구멍(122)과 제4 체결구멍(124) 간의 거리만큼 소정 공간이 형성되며, 이 공간들에 콘크리트몰탈을 타설 및 양생하여 제2 벽체(142)와 제3 벽체(143)를 형성한다.A predetermined space is formed between the first die 112 and the heat insulating material 130a by the distance between the first fastening hole 121 and the third fastening hole 123 and the space between the second die 114 and the heat insulating material 130b, A predetermined space is formed by a distance between the second fastening holes 122 and the fourth fastening holes 124. The concrete mortar is poured and cured in these spaces to form the second wall 142 and the third wall 143, .

상기와 같이 제2 벽체(142)와 제3 벽체(143)를 양생한 후 제1 거푸집(112) 및 제2 거푸집(114)을 제거하면 제2 벽체(142)와 제3 벽체(143) 사이에 단열재(130a)(130b)가 매립된 상태의 콘크리트벽체가 형성된다.After the second wall 142 and the third wall 143 are cured as described above, the first and second molds 112 and 114 are removed to form a gap between the second wall 142 and the third wall 143 A concrete wall in which the heat insulating materials 130a and 130b are embedded is formed.

이때 제2 벽체(142)와 제3 벽체(143) 외측면으로는 플랫타이(120B)에서 제1 거푸집(112) 및 제2 거푸집(114)과 체결되었던 끝단이 노출되는데, 플랫타이(120B)의 각 양단에 형성된 절단홈(125)이 제2 벽체(142)와 제3 벽체(143)의 외측면과 동일 평면에 위치하게 되므로, 플랫타이(120b)의 절단홈(125) 외측으로 타격을 가하여 절단홈(125)을 기준으로 플랫타이(120b)의 양 끝단을 잘라내면 외벽이 매끝한 형태의 콘크리트벽체를 형성할 수 있다.At this time, the end of the flat tie 120B, which is fastened to the first and second dies 112 and 114, is exposed to the outside of the second wall 142 and the third wall 143. The flat tie 120B, The cutting grooves 125 formed at both ends of the flat tie 120b are positioned on the same plane as the outer surfaces of the second wall 142 and the third wall 143 so that the strike of the flat tie 120b And the both ends of the flat tie 120b are cut off with respect to the cut grooves 125, thereby forming a concrete wall having a shape in which the outer wall is staggered.

이후, 제2 벽체(142)와 제3 벽체(143) 외측으로 마감재(도시되지 않음)를 시공함으로써 콘크리트벽체의 중간에 단열재가 이중으로 매립된 콘크리트벽체를 완성하게 된다.Thereafter, a finishing material (not shown) is installed outside the second wall body 142 and the third wall body 143 to complete a concrete wall in which a heat insulating material is embedded in the middle of the concrete wall.

상기 제2 실시예와 유사한 방법으로 콘크리트벽체 내에 단열재를 3중, 4중 또는 그 이상의 다중으로 매립한 콘크리트벽체를 시공할 수 있다.A concrete wall in which a heat insulating material is embedded in a plurality of triple, quadruple or more multiples in a concrete wall can be constructed in a similar manner to the second embodiment.

도 8은 본 발명에 따른 시공방법의 제3 실시예를 설명하기 위한 도면이다. 8 is a view for explaining a third embodiment of the construction method according to the present invention.

도 8에 도시된 실시예의 기본 시공방법은 상기 제2 실시예와 같이 콘크리트벽체 내에 2중의 단열재를 매립하는 시공방법으로서, 제2 실시예가 매립할 단열재의 수만큼 중간에 체결구멍이 형성된 플랫타이를 이용하는 것과 달리, 플랫타이의 끝단에 타이연결볼트를 체결하여 거푸집을 설치할 수 있도록 함으로써 추가적으로 단열재를 매립하는 콘크리트벽체를 시공할 수 있도록 하는 방법이다.The basic construction method of the embodiment shown in FIG. 8 is a construction method for embedding a double insulation material in a concrete wall as in the case of the second embodiment. In the second embodiment, a flat tie having a fastening hole formed in the middle by the number of insulation materials to be embedded The tie-connecting bolt is fastened to the end of the flat tie so that the formwork can be installed so that the concrete wall to be filled with the heat-insulating material can be additionally installed.

도 8에 도시된 바와 같은 본 발명의 제3 실시예에 따른 시공방법을 수행하기 위해서는 도 6의 (c)에 도시된 바와 같은 타이연결구(150)를 사용할 수 있다. 상기 타이연결구(150)는 일단에 U자 형의 걸고리(151)가 형성되고 타단에 나사산(152)이 형성되어 있는 고리볼트(153)와 상기 고리볼트(153)의 나사산(152)에 체결될 수 있는 너트(154)로 이루어진다.In order to perform the construction method according to the third embodiment of the present invention as shown in FIG. 8, a tie connector 150 as shown in FIG. 6 (c) can be used. The tie connector 150 includes a ring bolt 153 having a U-shaped hook 151 formed at one end thereof and a thread 152 formed at the other end thereof, and a tie bolt 153 fastened to the thread 152 of the ring bolt 153 And a nut 154,

다음에는 제3 실시예의 시공방법에 대하여 설명한다.Next, the construction method of the third embodiment will be described.

제3 실시예는 도 4 또는 도 7의 (b)에 도시된 바와 같이 플랫타이(120A) 또는 플랫타이(120B)의 양 끝단에 형성된 체결구멍(121)(122) 인접부위까지 콘크리트벽체를 형성한 이후에 추가로 단열재가 매립된 벽체를 시공하는 방법으로서, 도 8은 도 4에 도시된 실시예에서 제1 벽체(141) 외측으로 추가적으로 단열재와 콘크리트벽체를 시공하는 방법을 도시한 예를 나타낸다. The third embodiment forms a concrete wall up to the vicinity of the fastening holes 121 and 122 formed at both ends of the flat tie 120A or the flat tie 120B as shown in FIG. 4 or FIG. 7B. 8 shows an example of a method of additionally inserting a heat insulating material and a concrete wall outside the first wall 141 in the embodiment shown in FIG. 4 .

즉, 도 8의 (a)에 도시된 바와 같이 플랫타이(120A)의 끝단이 제1벽체(141)의 외측으로 노출된 상태에서 도 8의 (b)에 도시된 바와 같이 제1 벽체(141)의 외측면에 단열재(130c)를 부착시공한다.8 (a), when the end of the flat tie 120A is exposed to the outside of the first wall 141, as shown in FIG. 8 (b), the first wall 141 The heat insulating member 130c is attached to the outer surface of the heat insulating member 130c.

이어, 플랫타이(120A)의 끝단에 인접하게 가는 철근(160)을 배근하면서 와이어(161)로 제1 체결구멍(121)에 묶어 고정한다. 상기 철근(160)은 제1 벽체(141) 외측으로 추가로 설치될 제4 벽체가 마감용 벽체로서 두께가 두껍지 않은 경우 단열재(130c)에 의거 분리될 수 있기 때문에 철근(160)으로 결속력을 높이기 위함이다. 이를 목적으로 설치되는 철근(160)은 제1벽체(141)의 외측으로 노출되는 플랫타이(120A)의 끝단들에 대하여 수직방향과 수평방향으로 적절히 혼용하여 체결할 수 있다.Next, a reinforcing bar 160 adjacent to the end of the flat tie 120A is stuck to the first fastening hole 121 with the wire 161 while being laid. Since the reinforcing bar 160 can be separated by the heat insulating material 130c when the fourth wall to be additionally installed outside the first wall 141 is not a thick wall as the finishing wall, It is for this reason. The reinforcing bars 160 installed for the purpose can be properly combined with each other in the vertical direction and the horizontal direction with respect to the ends of the flat tie 120A exposed to the outside of the first wall 141.

이후, 고리볼트(153)의 걸고리(151)를 플랫타이의 끝단에 형성되어 있는 체결구멍(121)에 끼우고 고리볼트(153)의 타단인 나사산(152)이 형성되어 있는 부분을 제3 거푸집(116)을 관통시킨 후 반대편에서 너트(154)를 체결하여 고정한다. 상기 제3 거푸집(116)은 제3 거푸집(116)의 제조당시에 상기 타이연결구(150)의 나사산(152)을 관통시켜 체결할 수 있는 관통홈을 형성함이 바람직하다.Thereafter, the hook 151 of the bolt 153 is inserted into the fastening hole 121 formed at the end of the flat tie, and the portion of the bolt 153 where the thread 152 is formed is inserted into the third die And then the nut 154 is fastened and fixed on the opposite side. The third die 116 is preferably formed with a through-hole through which the thread 152 of the tie connector 150 passes when the third die 116 is manufactured.

이에 따라 제1 벽체(141)에 부착된 단열재(130c)와 제3 거푸집(116) 사이에는 소정 공간이 형성되며, 이 공간에 콘크리트몰탈을 타설하여 양생한 후 제3 거푸집(116)을 해체함으로써 제4 벽체(144)를 형성할 수 있다.A predetermined space is formed between the heat insulating material 130c and the third mold 116 adhered to the first wall 141. The concrete moldant is cured by being placed in the space and the third mold 116 is disassembled The fourth wall 144 can be formed.

제3 거푸집(116)을 해체하게 되면 고리볼트(153)에서 나사산(152)이 형성되어 있는 끝부분이 제4 벽체(144) 외측으로 돌출되게 되는바, 망치나 해머등을 이용하여 측면을 타격하면 표면에 나사산이 형성되어 있어서 도 8의 (c)에 도시된 바와 같이 제4 벽체(144)의 표면부위에서 쉽게 절단되어 돌출부분이 거의 없게 된다.When the third formwork 116 is disassembled, the end portion of the bolt 153 where the thread 152 is formed is protruded to the outside of the fourth wall body 144, and the side face is hammered by using a hammer or a hammer, A thread is formed on the lower surface of the fourth wall 144 to be easily cut off from the surface portion of the fourth wall 144 as shown in FIG. 8 (c), so that there is almost no protruding portion.

상기와 같은 벽체 시공과정에서 최외측면에 사용하는 거푸집을 표면이 고른 거푸집으로 사용하는 경우 양생된 콘크리트 표면에 바로 드리이비트를 시공하여 마감처리할 수 있다.In the case of using the mold used for the outermost side in the wall construction process as a uniform form of the surface, the drill bit can be applied to the surface of the cured concrete and finished.

아울러, 본 발명에 따른 콘크리트벽체의 시공과정에서 타설되는 콘크리트는 본 출원인에 의하여 선출원되어 등록된 특허 제10-1418635호에 개시되어 있는 바와 같이, 시멘트 15 내지 25부피%, 마사토 15 내지 25부피%, 입도가 6 내지 8mm인 자갈 50 내지 70부피%를 포함하는 조성물로 이루어진 고강도 세라 콘크리트를 사용함으로써 강도 높고 경제적인 콘크리트벽체를 시공할 수 있다.
In addition, as disclosed in Korean Patent No. 10-1418635 filed by the applicant of the present invention, the concrete to be installed in the concrete wall construction according to the present invention may be prepared by mixing 15 to 25% by volume of cement, 15 to 25% , And 50 to 70% by volume of gravel having a particle size of 6 to 8 mm is used as the cementitious concrete, it is possible to construct a concrete wall with high strength and economy.

위와 같이 본 발명에 따른 단열재가 매립된 콘크리트벽체 시공방법에 대한 기술사상을 예시도면에 의거하여 설명했지만, 이는 본 발명의 가장 양호한 실시예를 예시적으로 설명한 것이지 본 발명의 특허청구범위를 한정하는 것은 아니다.Although the description of the method for constructing a concrete wall with a heat insulating material according to the present invention as described above has been described with reference to the drawings, it is to be understood that the present invention is not limited to the above- It is not.

본 발명은 이 기술분야의 통상 지식을 가진 자라면 누구나 본 발명의 기술사상의 범주를 이탈하지 않는 범위 내에서 다양한 변형 및 모방이 가능함은 명백한 사실이다.
It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the scope of the present invention.

112 -- 제1 거푸집, 114 -- 제2 거푸집,
116 -- 제3 거푸집, 120A,120B -- 플랫타이,
121~124 -- 체결구멍, 125 -- 절단홈,
130,130a,130b -- 단열재, 141~143 -- 제1 벽체,
150 -- 타이연결구, 151 -- 걸고리,
152 -- 나사산, 153 -- 고리볼트,
154 -- 너트.
112 - a first die, 114 - a second die,
116 - Third die, 120A, 120B - Flat tie,
121 - 124 - fastening holes, 125 - cutting grooves,
130, 130a, 130b - insulation, 141 - 143 - first wall,
150 - Tie Connector, 151 - Hook,
152 - threads, 153 - collar bolts,
154 - Nuts.

Claims (3)

건축물의 벽체를 형성하기 위해 제1 거푸집과 제2거푸집을 폭 방향으로 대향시켜 소정 간격 이격되게 배치하고 상기 제1 거푸집과 제2 거푸집 사이에 콘크리트를 타설한 후 양생하여 콘크리트벽체를 형성하는 건축물의 벽체 시공방법에 있어서,
콘크리트벽체를 형성할 위치에 제1 거푸집과 제2 거푸집을 소정 간격 이격되게 배치하는 단계;
내벽과 외벽이 형성될 위치의 양단에 제1, 제2 체결구멍과 절단홈이 각각 형성됨과 아울러 단열재가 설치될 위치의 중앙에 제3 체결구멍이 형성되어 있는 플랫타이를 사용하여 상기 제1 거푸집을 상기 플랫타이의 일측 끝단에 형성되어 있는 제1 체결구멍에 체결핀으로 고정하는 단계;
상기 제2 거푸집을 플랫타이의 중앙에 형성되어 있는 제3 체결구멍에 체결핀으로 고정하되, 제2 거푸집의 내측면에 단열재가 밀착된 상태로 고정하는 단계;
상기 제1 거푸집과 단열재 사이에 콘크리트몰탈을 투입하여 제1 벽체를 양생하는 단계;
상기 제2 거푸집을 플랫타이의 타측 끝단에 형성되어 있는 제2 체결구멍 위치로 이동하여 체결핀으로 고정하는 단계;
상기 제2 거푸집과 단열재 사이에 콘크리트몰탈을 투입하여 제2 벽체를 양생하는 단계;
상기 제1 및 제2 거푸집을 떼어낸 후 상기 플랫타이의 양단에 형성된 절단홈을 기준으로 플랫타이의 양단을 잘라내어 양생된 콘크리트몰탈에 의해 형성되는 제1, 제2 벽체 외측으로 노출되는 플랫타이의 양단을 제거하는 단계;
를 포함하여 이루어지는, 콘크리트벽체 내에 단열재가 매립된 건축물의 벽체 시공방법.
A structure for constructing a concrete wall by placing concrete between a first formwork and a second formwork and then curing the first formwork and the second formwork so as to face the first formwork and the second formwork in a width direction to form a wall of the building, In the wall construction method,
Disposing a first formwork and a second formwork so as to be spaced apart from each other by a predetermined distance at a position where the concrete wall is to be formed;
The first and second fastening holes and the cut grooves are formed at both ends of the position where the inner wall and the outer wall are to be formed, and the third fastening hole is formed at the center of the position where the heat insulating material is to be installed, Securing the first fastening hole to the first fastening hole formed at one end of the flat tie with the fastening pin;
Fixing the second die in a state where the heat insulating material is adhered to the inner surface of the second die by fixing the third die with the fastening pin in the third fastening hole formed at the center of the flat tie;
Curing the first wall by injecting concrete mortar between the first formwork and the heat insulating material;
Moving the second die to a second fastening hole position formed at the other end of the flat tie and fixing the second die with a fastening pin;
Curing the second wall by injecting concrete mortar between the second formwork and the heat insulating material;
The first and second molds are removed, and both ends of the flat tie are cut off with reference to a cutting groove formed at both ends of the flat tie. The flat tie is exposed to the outside of the first and second walls formed by the cured concrete mortar Removing both ends;
And inserting the heat insulating material into the concrete wall.
건축물의 벽체를 형성하기 위해 제1 거푸집과 제2거푸집을 폭 방향으로 대향시켜 소정 간격 이격되게 배치하고 상기 제1 거푸집과 제2 거푸집 사이에 콘크리트를 타설한 후 양생하여 콘크리트벽체를 형성하는 건축물의 벽체 시공방법에 있어서,
콘크리트벽체를 형성할 위치에 제1 거푸집과 제2 거푸집을 소정 간격 이격되게 배치하는 단계;
내벽과 외벽이 형성될 위치의 양단에 제1, 제2 체결구멍과 절단홈이 각각 형성됨과 아울러 단열재가 설치될 위치의 중간에 제3 체결구멍과 제4 체결구멍이 형성되어 있는 플랫타이를 사용하여 상기 제1 거푸집을 상기 플랫타이의 중간 일측에 형성되어 있는 제3 체결구멍에 체결핀으로 고정하되, 제1 거푸집의 내측면에 단열재가 밀착된 상태로 고정하는 단계;
상기 제2 거푸집을 플랫타이의 중간 타측에 형성되어 있는 제4 체결구멍에 체결핀으로 고정하되, 제2 거푸집의 내측면에 단열재가 밀착된 상태로 고정하는 단계;
상기 제1 거푸집의 단열재와 제2 거푸집의 단열재 사이에 콘크리트몰탈을 투입하여 제1 벽체를 양생하는 단계;
상기 제1, 제2 거푸집을 각각 플랫타이의 타측 끝단에 형성되어 있는 제1, 제2 체결구멍 위치로 이동하여 체결핀으로 고정하는 단계;
상기 제1, 제2 거푸집과 각각의 거푸집에 대향하고 있는 단열재 사이에 콘크리트몰탈을 투입하여 제2, 제3 벽체를 양생하는 단계;
상기 제1 및 제2 거푸집을 떼어낸 후 상기 플랫타이의 양단에 형성된 절단홈을 기준으로 플랫타이의 양단을 각각 잘라내어 양생된 콘크리트몰탈에 의해 형성되는 제2, 제3 벽체 외측으로 노출되는 플랫타이의 양단을 제거하는 단계;
를 포함하여 이루어져, 단열재가 2중으로 매립되는 콘크리트벽체를 시공하도록 하는 콘크리트벽체 내에 단열재가 매립된 건축물의 벽체 시공방법.
A structure for constructing a concrete wall by placing concrete between a first formwork and a second formwork and then curing the first formwork and the second formwork so as to face the first formwork and the second formwork in a width direction to form a wall of the building, In the wall construction method,
Disposing a first formwork and a second formwork so as to be spaced apart from each other by a predetermined distance at a position where the concrete wall is to be formed;
The first and second fastening holes and the cut grooves are formed at both ends of the position where the inner wall and the outer wall are to be formed, and the flat tie having the third fastening hole and the fourth fastening hole formed in the middle of the position where the heat insulating material is to be installed Fixing the first die in a state in which the heat insulating material is adhered to the inner surface of the first die by fixing pins to the third fastening hole formed at the intermediate side of the flat tie;
Fixing the second die in a state where the heat insulating material is adhered to the inner surface of the second die by fixing the fourth die with the fastening pin in the fourth fastening hole formed on the other side of the flat tie;
Curing the first wall by injecting concrete mortar between the heat insulating material of the first formwork and the heat insulating material of the second formwork;
Moving the first and second molds to the first and second fastening hole positions formed at the other end of the flat tie, respectively, and fixing the first and second molds with the fastening pin;
Curing the second and third walls by injecting the concrete mortar between the first and second molds and the heat insulating material opposed to the respective molds;
The first and second molds are removed, and both ends of the flat tie are cut off based on the cut grooves formed at both ends of the flat tie. The flat tie is exposed to the outside of the second and third walls formed by the cured concrete mortar. Removing both ends of the support;
And inserting a heat insulating material into the concrete wall for allowing a concrete wall to be filled with the heat insulating material to be buried therein.
건축물의 벽체를 형성하기 위해 제1 거푸집과 제2거푸집을 폭 방향으로 대향시켜 소정 간격 이격되게 배치하고 상기 제1 거푸집과 제2 거푸집 사이에 콘크리트를 타설한 후 양생하여 콘크리트벽체를 형성하는 건축물의 벽체 시공방법에 있어서,
콘크리트벽체를 형성할 위치에 제1 거푸집과 제2 거푸집을 소정 간격 이격되게 배치하는 단계;
내벽과 외벽이 형성될 위치의 양단에 제1, 제2 체결구멍과 절단홈이 각각 형성됨과 아울러 단열재가 설치될 위치의 중앙에 제3 체결구멍이 형성되어 있는 플랫타이를 사용하여 상기 제1 거푸집을 상기 플랫타이의 일측 끝단에 형성되어 있는 제1 체결구멍에 체결핀으로 고정하는 단계;
상기 제2 거푸집을 플랫타이의 중앙에 형성되어 있는 제3 체결구멍에 체결핀으로 고정하되, 제2 거푸집의 내측면에 제1 단열재가 밀착된 상태로 고정하는 단계;
상기 제1 거푸집과 제1 단열재 사이에 콘크리트몰탈을 투입하여 제1 벽체를 양생하는 단계;
상기 제2 거푸집을 플랫타이의 타측 끝단에 형성되어 있는 제2 체결구멍 위치로 이동하여 체결핀으로 고정하는 단계;
상기 제2 거푸집과 제1 단열재 사이에 콘크리트몰탈을 투입하여 제2 벽체를 양생하는 단계;
상기 제1 거푸집을 해체하고 제1 벽체의 외벽에 제2 단열재를 부착시공하는 단계;
상기 제2 단열재 외측으로 소정 거리 이격시겨 제3 거푸집을 설치하되, 상기 제1 벽체 외면으로 노출되는 플랫타이의 끝단에 가는 철근을 배근하고 와이어로 제1 체결구멍에 묶어 고정함과 아울러 제1 체결구멍에 고리볼트의 걸고리를 끼우고 고리볼트의 타단인 나사산이 형성되어 있는 부분을 제3 거푸집을 관통시킨 후 반대편에서 너트를 체결하여 고정하는 단계;
상기 제2 단열재와 제3 거푸집 사이에 콘크리트몰탈을 투입하여 제3 벽체를 양생하는 단계;
상기 제2 및 제3 거푸집을 해체한 후 제2 벽체 외측으로 노출되는 플랫타이의 끝단과 제3 벽체 외측으로 노출되는 고리볼트의 끝단을 제거하는 단계;
를 포함하여 이루어져, 단열재가 다중으로 매립되는 콘크리트벽체를 시공하도록 하는 콘크리트벽체 내에 단열재가 매립된 건축물의 벽체 시공방법.
A structure for constructing a concrete wall by placing concrete between a first formwork and a second formwork and then curing the first formwork and the second formwork so as to face the first formwork and the second formwork in a width direction to form a wall of the building, In the wall construction method,
Disposing a first formwork and a second formwork so as to be spaced apart from each other by a predetermined distance at a position where the concrete wall is to be formed;
The first and second fastening holes and the cut grooves are formed at both ends of the position where the inner wall and the outer wall are to be formed, and the third fastening hole is formed at the center of the position where the heat insulating material is to be installed, Securing the first fastening hole to the first fastening hole formed at one end of the flat tie with the fastening pin;
Fixing the second die in a state in which the first heat insulating material is in close contact with the inner surface of the second die by fixing the third die with the fastening pin in the third fastening hole formed at the center of the flat tie;
Curing the first wall by injecting concrete mortar between the first mold and the first heat insulating material;
Moving the second die to a second fastening hole position formed at the other end of the flat tie and fixing the second die with a fastening pin;
Curing the second wall by injecting concrete mortar between the second mold and the first heat insulating material;
Disassembling the first formwork and attaching a second heat insulator to an outer wall of the first wall;
And a third die formed at a predetermined distance apart from the second heat insulator, wherein a thin reinforcing bar is disposed at the end of the flat tie exposed to the outer surface of the first wall, and is fastened and fixed to the first fastening hole with a wire, A step of inserting a hook bolt of a collar bolt into the fastening hole, passing a part of the bolt through which the thread is formed, through the third die, and fastening the nut at the opposite side;
Curing the third wall by injecting concrete mortar between the second insulation and the third die;
Removing the end of the flat tie exposed to the outside of the second wall and the end of the bolt exposed to the outside of the third wall after disassembling the second and third dies;
And inserting a heat insulating material into the concrete wall to allow the concrete wall to be embedded with the heat insulating material in multiple.
KR1020150014488A 2015-01-29 2015-01-29 Method for constructing wall embeded insulating metals in concrete walls KR101578205B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150014488A KR101578205B1 (en) 2015-01-29 2015-01-29 Method for constructing wall embeded insulating metals in concrete walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150014488A KR101578205B1 (en) 2015-01-29 2015-01-29 Method for constructing wall embeded insulating metals in concrete walls

Publications (1)

Publication Number Publication Date
KR101578205B1 true KR101578205B1 (en) 2015-12-21

Family

ID=55083881

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150014488A KR101578205B1 (en) 2015-01-29 2015-01-29 Method for constructing wall embeded insulating metals in concrete walls

Country Status (1)

Country Link
KR (1) KR101578205B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170142250A (en) * 2016-06-17 2017-12-28 주식회사 대미 One unified body construction method of the building concrete wall together with complex boards which has the insulation materials and the finishing materials
KR20220090598A (en) 2020-12-22 2022-06-30 오유상 Method for constructing wall for building

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331302A (en) * 1997-06-04 1998-12-15 Yoshiyuki Hayakawa Molding method for heat insulating double concrete wall
KR20130075109A (en) 2011-12-27 2013-07-05 코오롱글로벌 주식회사 Method for construction of wall structure and wall constructed by thereof
KR20140078801A (en) * 2012-12-17 2014-06-26 신영산업개발 주식회사 Outdoor wall finishing structure and construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331302A (en) * 1997-06-04 1998-12-15 Yoshiyuki Hayakawa Molding method for heat insulating double concrete wall
KR20130075109A (en) 2011-12-27 2013-07-05 코오롱글로벌 주식회사 Method for construction of wall structure and wall constructed by thereof
KR20140078801A (en) * 2012-12-17 2014-06-26 신영산업개발 주식회사 Outdoor wall finishing structure and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170142250A (en) * 2016-06-17 2017-12-28 주식회사 대미 One unified body construction method of the building concrete wall together with complex boards which has the insulation materials and the finishing materials
KR20220090598A (en) 2020-12-22 2022-06-30 오유상 Method for constructing wall for building

Similar Documents

Publication Publication Date Title
US7627997B2 (en) Concrete foundation wall with a low density core and carbon fiber and steel reinforcement
KR101954652B1 (en) Fire-proofing Concrete airduct slab panel using two wet condition material And Manufacturing method thereof
KR101413089B1 (en) Outdoor wall finishing structure and construction method
KR101578205B1 (en) Method for constructing wall embeded insulating metals in concrete walls
KR101731493B1 (en) Insulation and bearing panel and its manufacturing and installation method
KR101253253B1 (en) Concrete composite wall construction method with gangform and precast wall
KR20140120481A (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
RU2519314C1 (en) Leave-in-place form
KR101312992B1 (en) Concrete composite wall construction method with soft gangform and form-tie
RU2335604C2 (en) Process of sandwich wall formation
KR101549418B1 (en) Wedge shaped water stop and embeded concrete expansion joint form using the same
WO2017035674A1 (en) Structural wall made of reinforced concrete with thermal insulation and associated production method
KR101292523B1 (en) Concrete composite wall construction method with inner insulation, composite shear connector and composite form-tie
CN105714943B (en) Exterior-wall heat insulation reinforcement composite plate, heat-preserving wall integral structure and construction method
KR20150131904A (en) Tension for both steel and precast concrete structures and its production and construction methods
US11225792B2 (en) Insulating construction panels, systems and methods
KR101196343B1 (en) Concrete arch-slab bridge of stone facing
JP5281919B2 (en) Outside heat insulation foundation structure and its construction method
KR101366503B1 (en) Concrete composite wall for improving concrete pouring pressure resistance ability and the construction method therefor
KR101733127B1 (en) Method for constructing concrete walls reinforced water-proof
KR101312990B1 (en) Wire-mesh with lateral bending parts for concrete composite wall, concrete composite and concrete composite wall construction method wall using the same
KR101156568B1 (en) Method of Constructing Wall
AR077560A1 (en) A thin shell composite panel that has a concrete slab and reinforcement of laminated metal and methods to manufacture a thin shell composite panel that has two concrete slabs spaced apart in parallel plans and uplift units.
KR101650856B1 (en) Partial slab integrated I-shaped girder and bridge construction method using the same
KR20150018366A (en) Composite structure of concrete flange and web and method thereof

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20171211

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20191121

Year of fee payment: 5