KR101152265B1 - Prestressed bored pile construction method and structures - Google Patents
Prestressed bored pile construction method and structures Download PDFInfo
- Publication number
- KR101152265B1 KR101152265B1 KR1020100032797A KR20100032797A KR101152265B1 KR 101152265 B1 KR101152265 B1 KR 101152265B1 KR 1020100032797 A KR1020100032797 A KR 1020100032797A KR 20100032797 A KR20100032797 A KR 20100032797A KR 101152265 B1 KR101152265 B1 KR 101152265B1
- Authority
- KR
- South Korea
- Prior art keywords
- fixing
- tension member
- cast
- wedge
- concrete pile
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/58—Prestressed concrete piles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/08—Members specially adapted to be used in prestressed constructions
- E04C5/12—Anchoring devices
- E04C5/122—Anchoring devices the tensile members are anchored by wedge-action
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/08—Members specially adapted to be used in prestressed constructions
- E04C5/12—Anchoring devices
- E04C5/125—Anchoring devices the tensile members are profiled to ensure the anchorage, e.g. when provided with screw-thread, bulges, corrugations
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The present invention relates to a method for constructing a cast-in-place concrete pile with prestress and its structure, and more particularly, to a tension member and a protective tube and a pile tip in the longitudinal direction of a pile when inserting a concrete reinforcing steel beam for a cast-in-place concrete pile construction. After inserting the fixing part in advance, and after the concrete placing and curing process, the tensile material is tensioned at the top of the pile to increase the tensile and flexural strength of the concrete pile structure by causing compressive stress over the entire length of the concrete pile. .
Description
The present invention relates to a method for constructing a cast-in-place concrete pile and a structure thereof, in which prestress is introduced, and more specifically, in the longitudinal direction of the pile when the concrete reinforcement mesh is inserted for the construction of the cast-in-place concrete pile, After inserting the fixing unit in advance, and after the concrete placing and curing process, by tensioning the tension at the top of the pile to increase the tensile strength and flexural strength of the concrete pile structure by causing a compressive stress over the entire length of the concrete pile.
In addition, when the reinforcing bar is used, the perforated diameter of the cast-in-place concrete pile is increased due to the increase of the reinforcing bar, but when the high-strength strand is used, the increase of the additional perforation diameter is minimized and significant construction savings are achieved.
In general, the pile foundation is used to transfer the load of the upper structure to the lower rigid layer when the upper layer is weak, in which case the compressive stress acts on the pile structure.
In addition, pile foundations are generally installed to resist lateral loads due to the bending stiffness of pile materials when lateral loads are applied to the structure. It will work at the same time.
Apart from the above cases, under special circumstances, i.e., when the ground is unstable, for example, when the expansion and contraction are repeated by changing the water content such as an expandable ground, or when swelling or hibbing occurs in the ground by excavation, When the structure is subjected to positive pressure due to the rise of the groundwater level, piles are sometimes installed to prevent the expected damage of the superstructure. In this case, the pile structure resists the swelling phenomenon of the ground or the upward force such as water pressure, and the tensile stress is increased. Will work.
On the other hand, the piles are divided into steel piles and concrete piles according to the material formed, and divided into ready-made piles and cast-in-place concrete piles according to the pile production method.
The disadvantage of steel piles in concrete piles is that they are relatively resistant to compression due to the characteristics of concrete, but they are only one tenth of their compressive strength.
Therefore, in the case of cast-in-place concrete piles, reinforcing reinforcing bars are generally installed before concrete in order to resist tensile stress or flexural stress in the structure.
On the other hand, in the case of ready-made concrete piles, a large amount of pile bodies are produced at the production site, not in the field, so when tensile stress or bending stress is expected to be applied to the structure, a prestressing is applied to the concrete piles to induce compressive stress. Thus, it is possible to use a method to increase the resistance to the bending stress expected to occur in the pile structure in the future (PC, PHC pile).
An example of a situation in which an existing cast-in-place concrete pile is subjected to tensile stress during the excavation of a temporary facility for constructing a superstructure foundation will be described with reference to FIG. 1.
As shown in FIG. 1, in the ground of the
As the above-mentioned soft ground in the lower excavated surface is displaced upward, frictional resistance is expressed in the direction to resist upward displacement in the contact surface between the pile and the ground, and the lower end of the pile is fixed to the rigid support layer. This is caused.
This upward force acts even more when the ground just below the excavation surface is a solid layer, when grouting is performed and when it is an existing structural slab.
The tensile stress during the excavation is a force acting on the pile temporarily, and the value of extinction due to the installation of the structure after completion of excavation and backfilling is prevented, or the unfavorable phenomenon of the pile such as excessive tensile stress during construction and the resulting concrete crack If additional rebar is used, the construction and material costs can increase significantly due to the use of materials that are not needed during public use.
The present invention has been made in consideration of the various problems as described above, and its purpose is to improve the tensile fracture and crack prevention and durability of the cast-in-place concrete piles, and to apply the pre-stressing to the cast-in-place concrete piles by using high-strength strands. The present invention provides a method and a structure for the construction of cast-in-place concrete piles using prestressing, which reduces material costs.
In order to achieve the above object, the present invention provides a temporary wall installation step of installing the temporary wall with the soft clay of the ground on which the structure is to be constructed; A drilling hole forming step of inserting a casing at the ground surface to drill the ground to form a drilling hole to the inside of the rock; Installing a plurality of reinforcing bar nets on the outer circumferential surface of the fixing plate formed in the upper side of the perforating hole, and inserting the reinforcing bar net and the tension member into the fixing plate through the fixing unit and inserting the reinforcing bar to the tip of the punching hole; A cast-in-place concrete pile forming step of pouring concrete into the perforated hole after inserting the reinforcing bar and the tension member to form a cast-in-place pile; A tension member tension step of installing a reaction force support on the ground surface after fixing the tension member, tensioning the hydraulic jet by the rear end of the tension member, and applying prestress to the cast-in-place concrete pile; After digging the tension member after the excavation of the ground to the top of the cast-in-place concrete pile after the excavation tensile force expression step to express the tensile force; consists of.
The present invention has various effects as follows.
First, it increases the tensile strength of cast-in-place concrete piles, and compressive stress is pre-applied to the concrete structure, thereby improving the tensile fracture and cracking of the concrete and improving durability.
Second, in the special case, that is, when the cast-in-place concrete pile receives both the pulling force and the bending stress at the same time, the concrete member can also resist the bending stress by prestressing, so that the resistance to the tensile stress of the cast-in-place concrete pile can be effectively increased. .
Thirdly, when a large tensile force is generated, the amount of reinforcing bars entering a large amount is increased to prevent tensile failure of the cast-in-place concrete pile and cracking of concrete materials. In this case, prestressing is performed using high-strength stranded wire, thereby reducing the construction cost and material cost.
1 is a cross-sectional view showing a state of use of the conventional cast-in-place pile
Figure 2 is a process chart showing the construction sequence of the cast-in-place concrete piles introduced the prestress of the present invention
3 is a cross-sectional view showing the overall configuration of the present invention.
4 is a cross-sectional view showing an installation state of the temporary wall of the present invention.
Figure 5 is a cross-sectional view showing the ground perforation state of the present invention
6a to 6b are sectional views showing the installation state of the reinforcing bar and the tension member of the present invention
7A to 7C are cross-sectional views illustrating a state where the stranded wire is coupled to the tip pressure plate of the present invention;
Figure 8 is a cross-sectional view showing a coupling state of the stranded wire connected to the loading body of the present invention
9 is a cross-sectional view showing that the inventor's body is formed in multiple stages
10 is a cross-sectional view showing the configuration of the fixing unit of the present invention.
11 to 12 are sectional views showing another configuration of the fixing unit of the present invention.
Figure 13 is a cross-sectional view showing the forming step of the cast-in-place concrete pile of the present invention
14a to 16b are sectional views showing the operating state of the present invention anchorage
17A to 17B are cross-sectional views showing a state in which the stranded wire of the present invention is removed.
Hereinafter, described in detail by the accompanying drawings for carrying out the present invention in detail.
2 is a flowchart illustrating a method of constructing a cast-in-place concrete pile incorporating the prestress of the present invention, and FIG. 3 is a cross-sectional view showing the overall configuration of the present invention.
The present invention comprises a temporary wall installation step, a hole forming step, the reinforcing bar and the tension member insertion step, the cast-in-place concrete pile forming step, the tension member tension step, the excavation of the tension material after the excavation step.
The temporary wall installation step,
As shown in FIG. 4, the temporary wall 10 is installed using a slurry wall, SCW, H pile pile or steel pipe sheet pile as soft clay ground of the site where the structure is to be constructed.
The drilling hole forming step,
After grouting the soft clay ground to improve the ground, as shown in FIG. 5, the casing 9 is mounted on the perforator, and the perforated ground is formed by rotating the casing 9 to form the
At this time, the tip of the
The temporary wall installation step and the drilling hole forming step may be executed in a different order depending on the work site and environment.
Inserting the reinforcing bar and the tension member,
As shown in FIG. 6A attached to the inside of the
At this time, the lower side of the
This is a way to ensure that the concrete is directly attached to the steel wire (61) when the concrete is poured into the drilling hole (30).
And the end of the reinforcing reinforcing
The
In addition, the attached strand as shown in Figure 6b is installed in one or more bundles, it can be used to install a variety of places, such as three to eight places.
In addition, as shown in Figure 6c of the accompanying drawings, the tip of the
At this time, the
In addition, as shown in FIG. 7C of the accompanying drawings, the
This method can be used not only in the excavation work of the ground but also in the existing slab floor.
As described above, another method of fixing the tip of the tension member is as shown in FIG. 8, instead of using a single large circular pressure plate as shown in FIG. 8. The stranded
The location of the
And attached to the drawing as shown in Figure 9 is used to fasten the
As described above, the lower ends of the reinforcing
And when fixing the
The fixing
The
The
Then, a plurality of protective
The
And the front end of the fixing
At this time, the watertight rubber O-
Another embodiment of the fixing
In addition, as shown in FIG. 12, the
A fixing
The cast-in-place concrete pile forming step,
13, the anchoring
At this time, the
The tension member tension step,
After the cast-in-place
At this time, since the entire strand (61) is covered with a
As a result, even in the external environment of the underground soft clay, the cast-in-place
In addition, the
This is because the
As such, when the stranded
Another embodiment of the
This is because the
As such, when the stranded
In addition, another embodiment of the fixing
At this time, the
As such, when the stranded
Tensile force expression step after the excavation,
After the tension is completed, the ground is excavated to the upper end of the cast-in-place concrete pile to apply the tensile force to the tensile material is expressed.
In the present invention as described above, when the load of the structure installed on the ground surface is large, a large compressive force may be applied to the pile after the completion of construction, so compressive fracture of the pile may occur, so that the strand removal step is required to remove the prestressing applied to the pile before the completion of the structure. Done.
The strand removal step is a
Then, the load introduced to the
Then, after cutting the
In addition, the present invention can be ground improvement work to increase the strength of the soft ground by applying and curing the grout liquid to the bottom of the final excavation surface after installing the temporary wall (10).
In this case, J.S.P (Jumbo Special Pattern), Jet grouting, LW (Labiles Water glass grouting), JCM (Just Selected Chemical Grouting Method), SGR (Space Grouting Rocket System), etc.
Referring to the configuration of the cast-in-place concrete pile of the present invention as follows.
As shown in FIG. 8, a plurality of rebar meshes 50 are installed on the outer circumferential surface of the
The load-
In addition, the
30: hole 40: bedrock
50: reinforcing steel bar 60: tensile material
61: strand 62: protective tube
70: fixed plate 85: tip acupressure plate
90,101: crimping grip 91,102: wet
93,103: U shape 100: Lower body
110: upper fixing plate 120: fixing hole
130: fixing head 140: fixing plate
150: elastic spring 160: hydraulic cylinder
170: concrete 180: reaction support
190: pedestal 200: cast-in-place concrete pile
Claims (13)
A drilling hole forming step of inserting a casing at the ground surface to drill the ground to form a drilling hole to the inside of the rock;
Installing a plurality of reinforcing bar nets on the outer circumferential surface of the fixing plate formed in the upper side of the perforating hole, and inserting the reinforcing bar net and the tension member into the fixing plate through the fixing unit and inserting the reinforcing bar to the tip of the punching hole;
A cast-in-place concrete pile forming step of pouring concrete into the perforated hole after inserting the reinforcing bar and the tension member to form a cast-in-place pile;
A tension member tension step of installing a reaction force support on the ground surface after fixing the tension member, tensioning the hydraulic jet by the rear end of the tension member, and applying prestress to the cast-in-place concrete pile;
Pre-stretching tensile strength step of excavation so that the tensile force is expressed after excavating the ground to the top of the site-cast concrete pile after tensioning the tension member;
Pre-stressed on-site concrete pile construction method comprising the use of installing a circular tip acupressure plate to the tip of the reinforcing bar and the tension member.
On-site casting with pre-stressing in which the protection pipe of the lower part of the tension member is inserted into the perforated hole so that the strand is inserted in the exposed state to the outside so that the concrete is directly attached to the strand when the concrete is poured into the perforated hole. Concrete pile construction method.
Pre-stressed cast-in-place concrete pile construction method comprising the installation in the form of a pressing grip or wedge and U-shaped to hold the tension member to the front of the tip plate.
The method of constructing concrete piles incorporating prestressing, comprising fastening a load bearing body to the tip of a tension member instead of the tip pressure plate, and fastening the load body and the tension member in a crimping grip, wedge or U-shape.
Pre-stressed cast-in-place concrete pile construction method comprising the step of distributing the load by installing the load-bearing body in multiple stages.
The fixing unit,
A fixing head which is formed to penetrate the wedge insertion hole in which a plurality of wedges are mounted, and a fixing tube fixing wedge is fastened to a lower side thereof, and a wedge fixing plate is fixed to a lower side by a fixing bolt;
A wedge inserted into the wedge insertion hole and having a strand connected to a protective tube on an outer circumferential surface thereof;
A fixing plate coupled to the upper surface of the fixing head and having a plurality of protection tube fixing wedges fastened thereon and fixing the wedge fixing plate to the upper surface and fixing the fixing head using the fixing bolts;
Precast stress-injected concrete pile construction method, characterized in that the fastening head and the fixing plate is in contact with the waterproof O-ring made by fastening.
Pre-stressed cast-in-place concrete pile construction method characterized in that the elastic spring is mounted between the upper surface of the wedge and the fixing tube fixed wedge of the fixing plate.
Method for constructing a site-in-place concrete pile introduced with prestress, characterized in that the use of the hydraulic cylinder is fastened instead of the elastic spring fastened between the wedge and the protective tube fixed wedge.
The removal hole is formed on the outer circumferential surface of the lower side of the anchorage, and the cylindrical pedestal having a hole into which the tension member is inserted in the upper surface is installed, and the strand wire removing step of removing the strand wire using an oxygen cutter as the elimination hole of the pedestal includes: Construction method of cast-in-place concrete piles using prestress.
After the installation of the temporary wall is applied to the grout liquid to the bottom of the final excavation surface curing step by introducing a pre-stress, characterized in that the ground improvement step to increase the strength of the soft ground.
Pre-stressed cast-in-place concrete pile structure characterized in that it comprises the fixing of the tension member by using a single pressure plate to the tip of the tension member.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100032797A KR101152265B1 (en) | 2010-04-09 | 2010-04-09 | Prestressed bored pile construction method and structures |
PCT/KR2010/002292 WO2011126170A1 (en) | 2010-04-09 | 2010-04-14 | Construction method of pre-stressed cast-in -place concrete pile and structure thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100032797A KR101152265B1 (en) | 2010-04-09 | 2010-04-09 | Prestressed bored pile construction method and structures |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20110113416A KR20110113416A (en) | 2011-10-17 |
KR101152265B1 true KR101152265B1 (en) | 2012-06-14 |
Family
ID=44763091
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100032797A KR101152265B1 (en) | 2010-04-09 | 2010-04-09 | Prestressed bored pile construction method and structures |
Country Status (2)
Country | Link |
---|---|
KR (1) | KR101152265B1 (en) |
WO (1) | WO2011126170A1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103410144A (en) * | 2013-08-20 | 2013-11-27 | 中交二航局第三工程有限公司 | Prestressed reinforcement rock-socketed cast-in-place pile and construction method thereof |
CN103526750A (en) * | 2013-10-11 | 2014-01-22 | 北京建材地质工程公司 | Partial-bonding tension-dispersing type prestress anti-uplift anti-floating pile and construction method |
CN104196021A (en) * | 2014-08-26 | 2014-12-10 | 深圳市工勘岩土集团有限公司 | Uplift pile structure and construction method thereof |
KR20230151142A (en) * | 2022-04-22 | 2023-11-01 | 주식회사 택한 | Pre-stressed composite pile for retaining wall in remodeling |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103195054A (en) * | 2013-04-03 | 2013-07-10 | 天津大学 | Prefabricated spiral pile head and auxiliary pile sinking construction method thereof |
CN105155516B (en) * | 2015-08-14 | 2016-11-30 | 江苏省华建建设股份有限公司 | The method of construction drill bored concrete pile before making an overall screening underground obstacle |
CN106759306A (en) * | 2016-12-29 | 2017-05-31 | 福建省大地管桩有限公司 | A kind of prestressed concrete prefabricated pile mechanical splice device |
CN107338793A (en) * | 2017-07-20 | 2017-11-10 | 重庆交通大学 | A kind of cast-in-place screw rod prestress pulling resistant stake and its construction method |
US10815665B2 (en) | 2018-02-05 | 2020-10-27 | Precision-Hayes International Inc. | Concrete anchor with retainer |
CN109778841B (en) * | 2018-12-05 | 2022-03-15 | 上海建工集团股份有限公司 | Recyclable prestressed reinforcement cast-in-place pile for foundation pit enclosure and construction method thereof |
KR102034760B1 (en) * | 2018-12-31 | 2019-10-22 | 지앤에스건설 주식회사 | Construction method of Sing column drilled pier foundation introduced the tension system and Pile structure-GNS Pile Method |
CN109764845B (en) * | 2019-03-12 | 2024-06-28 | 四川升拓检测技术股份有限公司 | Front end steel strand displacement detection device based on reverse pulling method |
CN109914406B (en) * | 2019-04-08 | 2024-02-13 | 重庆大学 | Novel anti-slip bearing pile capable of recycling vertical anchor prepressing |
CN113216446A (en) * | 2021-04-30 | 2021-08-06 | 丰和营造集团股份有限公司 | Local prestressing force connection structure of assembled concrete shear force wall |
CN113404040A (en) * | 2021-07-06 | 2021-09-17 | 中铁二十局集团第六工程有限公司 | Construction method of bored pile foundation |
CN114753361B (en) * | 2022-04-29 | 2024-04-30 | 深圳市交通公用设施建设中心 | Pile foundation steel pile casing capable of controlling stratum deformation and construction method thereof |
KR102623359B1 (en) | 2022-07-07 | 2024-01-10 | 나도진 | Ground support piles from recycled electrical poles and ground support pile construction method using the same |
US12054947B1 (en) * | 2024-01-08 | 2024-08-06 | King Faisal University | Multi-layer wedge anchorage for FRP plates and FRP tendons |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09111758A (en) * | 1995-10-17 | 1997-04-28 | Kajima Corp | Cast-in-place concrete pile and construction method thereof |
JP2005501190A (en) | 2001-08-29 | 2005-01-13 | ビョン−ク パク | Fixing device capable of removing tensile material and method of removing tensile material |
KR200389534Y1 (en) | 2005-04-07 | 2005-07-14 | 서병운 | Tension member removable anchoring apparatus |
KR100618597B1 (en) | 2004-11-16 | 2006-09-04 | 민경건설 주식회사 | Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200392122Y1 (en) * | 2005-05-02 | 2005-08-19 | 주식회사 삼성씨케이 | Structure of pretensioned spun high strength concrete piles |
-
2010
- 2010-04-09 KR KR1020100032797A patent/KR101152265B1/en active IP Right Grant
- 2010-04-14 WO PCT/KR2010/002292 patent/WO2011126170A1/en active Application Filing
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09111758A (en) * | 1995-10-17 | 1997-04-28 | Kajima Corp | Cast-in-place concrete pile and construction method thereof |
JP2005501190A (en) | 2001-08-29 | 2005-01-13 | ビョン−ク パク | Fixing device capable of removing tensile material and method of removing tensile material |
KR100618597B1 (en) | 2004-11-16 | 2006-09-04 | 민경건설 주식회사 | Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this |
KR200389534Y1 (en) | 2005-04-07 | 2005-07-14 | 서병운 | Tension member removable anchoring apparatus |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103410144A (en) * | 2013-08-20 | 2013-11-27 | 中交二航局第三工程有限公司 | Prestressed reinforcement rock-socketed cast-in-place pile and construction method thereof |
CN103410144B (en) * | 2013-08-20 | 2016-02-03 | 中交二航局第三工程有限公司 | Prestressed reinforcement piles set into rock and construction method |
CN103526750A (en) * | 2013-10-11 | 2014-01-22 | 北京建材地质工程公司 | Partial-bonding tension-dispersing type prestress anti-uplift anti-floating pile and construction method |
CN103526750B (en) * | 2013-10-11 | 2015-08-26 | 北京建材地质工程公司 | Part adhesive pulling force decentralized prestress pulling resistant anti-floating pile |
CN104196021A (en) * | 2014-08-26 | 2014-12-10 | 深圳市工勘岩土集团有限公司 | Uplift pile structure and construction method thereof |
KR20230151142A (en) * | 2022-04-22 | 2023-11-01 | 주식회사 택한 | Pre-stressed composite pile for retaining wall in remodeling |
KR102614988B1 (en) * | 2022-04-22 | 2023-12-18 | 주식회사 택한 | Pre-stressed composite pile for retaining wall in remodeling |
Also Published As
Publication number | Publication date |
---|---|
WO2011126170A1 (en) | 2011-10-13 |
KR20110113416A (en) | 2011-10-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101152265B1 (en) | Prestressed bored pile construction method and structures | |
US4832535A (en) | Process for compaction-reinforcement-grouting or for decompaction-drainage and for construction of linear works and plane works in the soils | |
KR100899372B1 (en) | Connection method of micropile cap to existing concrete footing structure, reinforced method using same and structure thereof | |
KR101241566B1 (en) | Method for Constructing Cap Beam Combined Wale For Retaining Wall | |
KR20090013528A (en) | The prestressed tunnel support structure | |
KR100918771B1 (en) | Micro pile setting apparatus and settling method using the same | |
JP7175725B2 (en) | Reinforcing structure of masonry building | |
CN109235490B (en) | Retaining wall and construction method thereof | |
CN105378222A (en) | Method for reinforcing pillar part of adjacently constructed parallel tunnels with reinforcing rods and excavation method | |
KR20170061061A (en) | Tunnel construction method by using pre-support and post-support, and suitable device therefor | |
KR20170061060A (en) | Tunnel construction method by using pre-support and post-support, and suitable device therefor | |
CN110616740A (en) | Structure for expanding subway section in subway mine method construction interval and construction method thereof | |
KR20140013497A (en) | Method for constructing block type reinforced retaining wall in cut site | |
KR20130095153A (en) | A removable prestressing steel pipe soil nailing structure | |
KR100726984B1 (en) | Temporary system for land-side protection wall | |
KR100779988B1 (en) | Method for constructing micropile | |
KR100933220B1 (en) | Repairing method for bulging of reinforced soil retaing wall and soil-nail structure used for it | |
KR101086643B1 (en) | Prestressed concrete girder with plural steel wires disposed at shear surface of tension port | |
KR102079563B1 (en) | Compression friction type anchor panel ground reinforcement system | |
KR101202845B1 (en) | Hybrid ground reinforcing method by earth anchor and soil nail | |
JPH11148231A (en) | Assembled and laid building reinforcing structure, its reinforcing method, and base isolating construction method | |
KR100862387B1 (en) | Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this | |
KR102647214B1 (en) | Prestressed pile for retaining wall with easy resource recovery and construction method thereof | |
KR20120122024A (en) | Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts. | |
KR20150050012A (en) | Retaining Wall and Construction Method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20150519 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20160517 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20170524 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20180525 Year of fee payment: 7 |