JPH09111758A - Cast-in-place concrete pile and construction method thereof - Google Patents

Cast-in-place concrete pile and construction method thereof

Info

Publication number
JPH09111758A
JPH09111758A JP26856095A JP26856095A JPH09111758A JP H09111758 A JPH09111758 A JP H09111758A JP 26856095 A JP26856095 A JP 26856095A JP 26856095 A JP26856095 A JP 26856095A JP H09111758 A JPH09111758 A JP H09111758A
Authority
JP
Japan
Prior art keywords
pile
hole
concrete
boring
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP26856095A
Other languages
Japanese (ja)
Other versions
JP3081905B2 (en
Inventor
Masahiko Hanamura
昌彦 花村
Akiyoshi Nojiri
明美 野尻
Yoshiya Kase
善弥 加瀬
Hideo Hayashi
英雄 林
Masataka Fukushima
正隆 福島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP07268560A priority Critical patent/JP3081905B2/en
Publication of JPH09111758A publication Critical patent/JPH09111758A/en
Application granted granted Critical
Publication of JP3081905B2 publication Critical patent/JP3081905B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To make it possible to construct a tension member easily and definitely by providing a dia-expanded area on a concrete pile whose head is exposed and excavating a boring hole and fixing a fixture grip at the tip of the tension member with the dia-expanded area. SOLUTION: A pile reinforcing bar 2 is placed into an excavation hole 1 where concrete 3 is cast only in an area which is the foundation of an underground skeleton. An evacuated area in the upper part is backfilled. After that, underground excavation is executed down to the foundation surface, thereby exposing the head of a pile 4 and constructing the pile 4. Then, a boring hole 5, which is opened in the upper end of the pile 4 and forms a dia-expanded area 5a at the lower part, is bored in the longitudinal direction of the pile 4. A tension member 6, on which a thick plate-like fixture grip 7 is mounted at the tip, is inserted into the boring hole 5 where a grout material is injected in the dia-expanded area and a primary grout filling work is executed. After the tension member 6 is strained, secondary grout filling work is further executed. At that time, the fixture rip 6 is fixed with the size expansion area so that it may act as a support member of tensile force, thereby introducing the tensile force to the pile 4 by way of the grout material.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、場所打ちコンクリ
ート杭およびその施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a cast-in-place concrete pile and its construction method.

【0002】[0002]

【従来の技術】場所打ちコンクリート杭は周知のよう
に、例えば掘削孔内に鉄筋カゴをセットし、コンクリー
トを打設して形成するものであるが、この場所打ちコン
クリート杭を引張り抵抗材として使用する場合や、地震
時等に作用する引張り力によるコンクリートのひび割れ
を防止するために、杭体中にPC鋼より線等の引張り材
を埋込みこれに引張り力を与えて、コンクリート杭に予
め圧縮力(プレストレス)を与えるようにすることがあ
る。
2. Description of the Related Art As is well known, cast-in-place concrete piles are formed by setting a reinforced basket in an excavation hole and placing concrete. The cast-in-place concrete piles are used as a tensile resistance material. In order to prevent cracking of concrete due to tensile force acting at the time of earthquake, etc., a tensile material such as PC steel stranded wire is embedded in the pile body and a tensile force is applied to this to pre-compress the concrete pile. (Prestress) may be given.

【0003】前記引張り材は通常PC鋼より線を1本ま
たは複数本束ねたもので、鉄筋のように簡単に接合する
ことはできないので、必要な長さのものを地上で組み立
て、コンクリート打設に先立ち、鉄筋カゴを掘削孔に挿
入する際に、鉄筋カゴに固定してシース管も挿入し、コ
ンクリート打設後にシース管内に引張り材を挿入し、こ
れを緊張させ、コンクリートに圧縮力(プレストレス)
を与える。
The above-mentioned tensile member is usually a bundle of one or a plurality of PC steel wires, which cannot be easily joined like a reinforcing bar. Therefore, one having a required length is assembled on the ground and placed in concrete. Before inserting the reinforced steel cage into the drill hole, fix it to the reinforced steel cage and insert the sheath tube.After placing concrete, insert a tension material into the sheath tube and tension it to compress the concrete (pre-press). stress)
give.

【0004】このように、鉄筋カゴ建込み時には、接合
が容易なシース管だけを地上から掘削した杭孔に埋め込
んでおき、コンクリート打設後にシース管内に引張り材
を挿入して、その後、モルタル等の固結材をシース管内
に注入して杭体コンクリートと引張り材を一体化してい
る。
As described above, at the time of reinforced cage construction, only the sheath tube which can be easily joined is embedded in the pile hole excavated from the ground, the tension material is inserted into the sheath tube after the concrete is placed, and then the mortar or the like is used. The solidification material is injected into the sheath pipe to integrate the pile concrete and the tension material.

【0005】[0005]

【発明が解決しようとする課題】地下室などの地下躯体
が構築される場合は、地上面よりも下方に基礎面が位置
し、杭は掘削孔の全長に対して基礎面から下方の部分だ
けが実長となり、コンクリートも掘削孔の内部の下方部
分の杭実長に相当する深さにのみ打設され、その上の部
分の掘削孔内部の空打ち部は砂等で埋め戻される。
When an underground skeleton such as a basement is constructed, the foundation surface is located below the ground surface, and the piles are located only below the foundation surface with respect to the entire length of the excavation hole. The actual length is reached, and the concrete is also driven only to a depth corresponding to the actual length of the pile in the lower part inside the drill hole, and the empty part inside the drill hole above that part is backfilled with sand or the like.

【0006】このため、従来のようにコンクリート打設
後に地上からシース管内に引張り材を挿入すると、引張
り材は空打ち部の部分にも配設され、杭の実長よりも上
方の部分の地上まで延びることになり、また、引張り材
の施工は地上からのものとなって施工性がよくなく、こ
れを解消するためにはシース管を地上まで延長すればよ
いが、これは前記した引張り材の場合と同様に空打ち部
の部分に配設することになる。そして、この引張り材の
施工は杭工事中の作業となり、工事が煩雑となる。
For this reason, when a tension member is inserted into the sheath pipe from the ground after placing concrete as in the conventional case, the tension member is also disposed in the blank driving portion, and the ground portion above the actual length of the pile is grounded. Moreover, the construction of the tension member is from the ground and the workability is not good, so in order to eliminate this, it is only necessary to extend the sheath tube to the ground. Similar to the above case, it will be arranged at the blanking portion. Then, the construction of this tensile member is a work during the pile construction, which makes the construction complicated.

【0007】本発明の目的は前記従来例の不都合を解消
し、地下室などの地下躯体が構築される場合に、引張り
材の施工が容易、かつ確実に行え、杭工事中の引張り材
の施工がなくなり工事の煩雑性をなくすことができ、施
工性のよい場所打ちコンクリート杭およびその施工法を
提供することにある。
The object of the present invention is to eliminate the disadvantages of the above-mentioned conventional example, and when the underground structure such as a basement is constructed, the tension members can be easily and surely constructed, and the tension members can be constructed during the pile construction. Another object is to provide a cast-in-place concrete pile and a construction method thereof that can eliminate the complexity of construction work and have good workability.

【0008】[0008]

【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、地下躯体が構築される場合で、地下
掘削で杭頭を露出させたコンクリート杭に長さ方向にボ
ーリング孔をその上端が杭上端に開口するように削孔
し、該ボーリング孔に引張り材を挿入したことを要旨と
するものである。
[Means for Solving the Problems] To achieve the above object, firstly, in the case where an underground skeleton is constructed, a boring hole is provided in a longitudinal direction in a concrete pile whose pile head is exposed by underground excavation. The gist is that a hole is drilled so that its upper end opens to the upper end of the pile, and a tensile member is inserted into the boring hole.

【0009】第2に、引張り材を挿入するボーリング孔
は下端部を拡径部に形成したこと、第3に、引張り材を
挿入するボーリング孔は下端部の孔壁に螺旋溝を形成し
たことを要旨とするものである。
Secondly, the boring hole for inserting the tensile member has a lower end portion formed with an enlarged diameter portion. Thirdly, the boring hole for inserting the tensile member has a spiral groove formed in the hole wall at the lower end portion. Is the gist.

【0010】第4に、引張り材は途中をU字状に折り返
し、この折り返し部を杭底に位置させて孔に挿入し、対
向して連結された一対の厚板状部材による支圧体の連結
部に前記折り返し部を掛着したことを要旨とするもので
ある。
Fourthly, the tension member is folded back in a U shape in the middle, and the folded back portion is positioned at the bottom of the pile and inserted into the hole. The gist is that the folded-back portion is hooked on the connecting portion.

【0011】第5に、地下躯体が構築される場合で、地
下掘削で杭頭が露出し、コンクリート杭に長さ方向に形
成したボーリング孔で下部を拡径部に形成した孔に、管
壁に螺旋溝を形成したシース管を挿入し、該シース管内
に先端に支圧体として厚板状の定着体を取り付けた引張
り材を挿入したことを要旨とするものである。
Fifth, in the case where an underground skeleton is constructed, a pile head is exposed by underground excavation and a lower part is formed in a diameter-expanded part by a boring hole formed in the concrete pile in the longitudinal direction. The gist of the invention is to insert a sheath tube having a spiral groove formed therein, and to insert a tension member having a thick plate-shaped fixing body as a pressure bearing body attached to the tip in the sheath tube.

【0012】第6に、地下躯体が構築される場合で、地
上から掘削した杭孔内の下方部で地下躯体の基礎部とな
る部分にのみコンクリートを打設した後、地下掘削を行
って杭頭を露出し、コンクリート杭にボーリング孔を形
成し、ここに引張り材を挿入することを要旨とするもの
である。
Sixth, in the case where an underground skeleton is constructed, concrete is placed only in the lower part of the pile hole excavated from the ground, which will be the foundation of the underground skeleton, and then underground excavation is performed. The purpose is to expose the head, form a boring hole in the concrete pile, and insert the tensile member there.

【0013】第7に、地下躯体が構築される場合で、地
上から掘削した杭孔内の下方部で地下躯体の基礎部とな
る部分にのみシース管を建て込んでコンクリートを打設
した後、地下掘削を行って杭頭を露出し、シース管の下
部にボーリングにより拡径部または螺旋溝のいずれかを
形成し、これらシース管内およびボーリングにより形成
した拡径部または螺旋溝に引張り材を挿入したことを要
旨とするものである。
Seventh, in the case where an underground skeleton is constructed, after a sheath pipe is built only in a portion which is a base of the underground skeleton in a lower portion in a pile hole excavated from the ground, concrete is poured, Underground excavation exposes the pile head, and either the expanded part or the spiral groove is formed by boring in the lower part of the sheath pipe, and the tensile material is inserted into the expanded part or spiral groove formed inside these sheath pipes and by the boring. What is done is the gist.

【0014】請求項1、請求項6記載の本発明によれ
ば、地下躯体が構築される場合、地上から掘削した杭孔
内の下方部で地下躯体の基礎部となる部分にのみコンク
リートを打設した後、地下掘削を行って杭頭を露出し、
その後にコンクリート杭にボーリング孔を形成し、ここ
に引張り材を挿入することで、杭工事が完了してから引
張り材の挿入作業ができ、杭工事中の作業がなくなって
施工性がよい。
According to the present invention as set forth in claims 1 and 6, when an underground skeleton is constructed, concrete is poured only into a portion which is a base portion of the underground skeleton in a lower portion in a pile hole excavated from the ground. After installation, underground excavation is performed to expose the pile head,
After that, by forming a boring hole in the concrete pile and inserting the tension member into this, the tension member can be inserted after the pile work is completed, and the work during the pile work is eliminated, and the workability is good.

【0015】請求項2、請求項3記載の本発明によれ
ば、前記作用に加えて、引張り材を挿入するボーリング
孔は下端部を拡径部、または、下端部の孔壁に螺旋溝を
形成したから、ボーリング孔を削孔する際にコンクリー
ト粉末等の塵が孔壁に付着しても、ボーリング孔に注入
するグラウト材との付着強度の低下を防止でき、コンク
リートとグラウト材との一体化を確保できる。
According to the second and third aspects of the present invention, in addition to the above action, the boring hole into which the tensile member is inserted has a lower end portion having a diameter-increasing portion, or a spiral groove in the hole wall at the lower end portion. Since it is formed, even if dust such as concrete powder adheres to the hole wall when boring the boring hole, it is possible to prevent the adhesion strength with the grout material injected into the boring hole from decreasing, and the concrete and grout material are integrated. Can be secured.

【0016】請求項4記載の本発明によれば、引張り材
はそのU字状の折り返し部が支圧体に掛着して杭底に定
着され、引張り材を緊張する際の引張力は支圧体の対向
して連結された一対の厚板状部材で支持されて分散され
る。よって、引張りの応力が杭底に集中せず、杭全体に
均等にプレストレスを導入できる。
According to the present invention as set forth in claim 4, the U-shaped folded portion of the tension member is attached to the bearing body and fixed to the bottom of the pile, and the tension force for tensioning the tension member is supported. The pressure body is supported and dispersed by a pair of thick plate-shaped members connected to face each other. Therefore, the tensile stress is not concentrated on the bottom of the pile, and the prestress can be uniformly introduced to the entire pile.

【0017】請求項5記載の本発明によれば、支圧体と
して厚板状の定着体を引張り材の先端に取り付けた場合
は、応力が定着体の付近に集中しやすいが、この引張り
材を挿入するシース管の管壁に螺旋溝を形成するととも
に、該シース管を建て込むボーリング孔の下部を拡径部
に形成したから、応力が分散してプレストレスが均等に
導入される。
According to the fifth aspect of the present invention, when a thick plate-shaped fixing member is attached to the tip of the tension member as a pressure bearing member, stress tends to concentrate near the fixing member. Since the spiral groove is formed on the tube wall of the sheath tube into which is inserted and the lower part of the boring hole for building the sheath tube is formed in the expanded diameter portion, the stress is dispersed and the prestress is uniformly introduced.

【0018】請求項7記載の本発明によれば、請求項6
記載の本発明による作用に加えて、杭孔内の地下躯体の
基礎部となる部分にはシース管を予め建て込んであるか
ら、コンクリート打設後に引張り材を挿入するための孔
を杭孔の全長にわたってボーリングする必要がなく、引
張り材の施工時には拡径部または螺旋溝のいずれかを形
成するたけでよく、施工性がさらに向上する。
According to the present invention of claim 7, claim 6 is provided.
In addition to the operation according to the present invention described, since the sheath pipe is built in advance in the portion that will be the foundation part of the underground structure in the pile hole, a hole for inserting a tensile member after placing concrete is provided in the pile hole. It is not necessary to perform boring over the entire length, and it suffices to form either the expanded diameter portion or the spiral groove when constructing the tensile member, which further improves the constructability.

【0019】[0019]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図1は本発明の場所打ちコン
クリート杭の施工方法の第1実施形態の第1工程を示す
縦断正面図、図2同上平面図で、地下室等の地下躯体を
構築する場合に実施されるものである。まず、掘削孔1
を地上から削孔し、ここに杭鉄筋2を建て込んで掘削孔
1内の下方部で地下躯体の基礎部となる部分にのみコン
クリート3を打設した後、掘削孔1内の上方部の空打ち
部は砂などで埋め戻し、その後、基礎面まで地下掘削を
行って杭頭を露出し、杭体4を施工する。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a vertical sectional front view showing a first step of the first embodiment of the method for constructing a cast-in-place concrete pile of the present invention, and FIG. 2 is a plan view of the same as above, which is carried out when constructing an underground skeleton such as a basement. is there. First, drill hole 1
After digging holes from the ground, building pile rebars 2 here, and placing concrete 3 only in the lower part of the excavation hole 1 that will be the foundation part of the underground structure, and then in the upper part of the excavation hole 1. The blank part is backfilled with sand or the like, and then underground excavation is performed to the foundation surface to expose the pile head, and the pile body 4 is constructed.

【0020】次に杭体4にその長さ方向にコンクリート
ボーリングを行い、ボーリング孔5を長さ方向に削孔す
る。このボーリング孔5の下部は、拡径部5aに形成
し、または図5に示すように第2実施形態として孔壁に
螺旋溝5bを形成する。この拡径部5aや螺旋溝5bの
形成は、機械的な拡径ピット、または水平噴射の高圧水
ジェットを利用する。一方、ボーリング孔5の上端は杭
体4の上端に開口する。
Next, concrete boring is performed on the pile body 4 in the lengthwise direction, and the boring hole 5 is drilled in the lengthwise direction. The lower portion of the boring hole 5 is formed in the expanded diameter portion 5a, or as shown in FIG. 5, a spiral groove 5b is formed in the hole wall as the second embodiment. The expanded diameter portion 5a and the spiral groove 5b are formed by using a mechanical expanded diameter pit or a horizontal jet of high-pressure water jet. On the other hand, the upper end of the boring hole 5 opens at the upper end of the pile body 4.

【0021】ボーリング孔5に図3に示すようにPC鋼
より線などによる引張り材6を挿入する。この引張り材
6の先端には厚板状の定着グリップ7を取り付けてお
き、図4に示すようにボーリング孔5内の先端の拡径部
5aにモルタル等のグラウト材8を注入して一次グラウ
トを行い、引張り材6を緊張した後、ボーリング孔5に
さらにグラウト材8を注入して二次グラウトを行う。
As shown in FIG. 3, a tension member 6 made of PC steel wire or the like is inserted into the boring hole 5. A thick plate-shaped fixing grip 7 is attached to the tip of the tension member 6, and the grouting material 8 such as mortar is injected into the expanded diameter portion 5a at the tip of the boring hole 5 as shown in FIG. After tensioning the tension member 6, the grout member 8 is further injected into the boring hole 5 to perform the secondary grout.

【0022】このとき、引張り材6の先端には定着グリ
ップ7が取り付けてあるから、これがグラウト材8を介
してボーリング孔5の先端に固定され、引張り力の支圧
体とて作用し、引張りの応力がグラウト材8を介して杭
体4に均等に導入される。
At this time, since the fixing grip 7 is attached to the tip of the tension member 6, it is fixed to the tip of the boring hole 5 via the grout material 8 and acts as a pressure bearing member for the tension force. Stress is uniformly introduced into the pile body 4 through the grout material 8.

【0023】また、ボーリングによる削孔の際に生じる
コンクリート粉末等の塵が孔壁に付着していることが多
いが、ボーリング孔6の下端部を拡径部5aに形成し、
またはここに螺旋溝5bを形成したから、グラウト材8
とコンクリート3との接触面積が大きくなり、一体性を
確保でき、これにより、プレストレスの導入も確実にな
る。
In addition, dust such as concrete powder produced during boring by boring often adheres to the hole wall, but the lower end of the boring hole 6 is formed in the expanded diameter portion 5a,
Or, since the spiral groove 5b is formed here, the grout material 8
The contact area between the concrete and the concrete 3 becomes large, and the integrity can be ensured, so that the introduction of pre-stress is also ensured.

【0024】なお、引張り材6の挿入とグラウト材8の
注入の施工順序は、前記と反対にグラウト材8を注入し
てから引張り材6の挿入を行うようにしてもよい。
The order of inserting the pulling material 6 and injecting the grout material 8 may be opposite to that described above such that the grout material 8 is injected and then the pulling material 6 is inserted.

【0025】前記した実施形態では杭体4のほぼ全長に
わたってボーリング孔5を削孔したが、第3実施形態と
して地上から掘削した掘削孔1内の下方部で地下躯体の
基礎部となる部分にのみ薄肉鋼管等によるシース管を予
め建て込んでおき、コンクリートを打設した後、地下掘
削を行って杭頭を露出し、シース管の下部にのみボーリ
ングにより拡径部または螺旋溝のいずれかを形成するこ
ともできる。
In the above-described embodiment, the boring hole 5 was drilled over substantially the entire length of the pile body 4, but in the third embodiment, the lower portion of the borehole 1 excavated from the ground is the lower end portion of the underground structure. Only after pre-building a sheath pipe made of thin-walled steel pipe, etc., after placing concrete, underground excavation is performed to expose the pile head, and only the lower part of the sheath pipe is bored so that either the expanded part or the spiral groove is formed. It can also be formed.

【0026】この場合は、杭体4のほぼ全長にわたって
ボーリング孔5を削孔する必要がなく、拡径または螺旋
溝の筋切りのみを引張り材6の施工時に行えばよいか
ら、施工性がよくなる。
In this case, it is not necessary to drill the boring hole 5 over substantially the entire length of the pile 4, and only the diameter expansion or the scoring of the spiral groove may be performed at the time of applying the tension member 6, so that the workability is improved. .

【0027】図6は第4実施形態を示し、支圧体として
定着グリップ7を使用する場合、これを取り付けた引張
り材6をボーリング孔5に直接挿入せずに、管壁に螺旋
溝9aを形成したシース管9を下部を拡径部5aに形成
したボーリング孔5に挿入し、このシース管9内に引張
り材6を挿入し、シース管9内とボーリング孔5内とに
グラウト材8を充填した。
FIG. 6 shows a fourth embodiment. When the fixing grip 7 is used as a bearing member, the tension member 6 to which the fixing grip 7 is attached is not directly inserted into the boring hole 5, but the spiral groove 9a is formed on the pipe wall. The formed sheath tube 9 is inserted into the boring hole 5 whose lower portion is formed in the expanded diameter portion 5a, the tension member 6 is inserted into the sheath tube 9, and the grout material 8 is inserted into the sheath tube 9 and the boring hole 5. Filled.

【0028】これにより、支圧体として定着グリップ7
を使用する場合はこの部分に引張りの応力が集中しやす
いが、この応力が螺旋溝9aを形成したシース管9と、
拡径部5aを形成したボーリング孔5とにより分散さ
れ、プレストレスが杭体4の全体に均等に導入できる。
As a result, the fixing grip 7 serves as a bearing member.
When using, the tensile stress is likely to concentrate in this portion, but this stress causes the sheath tube 9 in which the spiral groove 9a is formed,
The prestress can be evenly introduced into the entire pile body 4 by being dispersed by the boring hole 5 having the expanded diameter portion 5a.

【0029】図7、図8は支圧体の他の例を示し、引張
り材6は途中をU字状に折り返し、この折り返し部6a
を杭底に位置させて孔に挿入し、対向して連結部材10b
で連結される対向する一対の厚板状部材10aで支圧体10
を形成し、この連結部材10bに前記折り返し部6aを掛
着した。
7 and 8 show another example of the pressure bearing member, in which the tension member 6 is folded back in a U shape in the middle, and the folded back portion 6a is formed.
Position on the bottom of the pile and insert it into the hole, facing each other and connecting member 10b
The pressure-bearing body 10 is formed by a pair of thick plate-shaped members 10a facing each other connected by
And the folded-back portion 6a was hooked on the connecting member 10b.

【0030】これにより、引張り材6はそのU字状の折
り返し部6aが支圧体10に掛着して杭底に定着され、引
張り材6を緊張する際の引張力は支圧体10を構成する対
向して連結された一対の厚板状部材10bで支持されて分
散される。よって、引張りの応力が杭底に集中せず、杭
全体に均等にプレストレスを導入できる。
As a result, the tension member 6 has its U-shaped folded-back portion 6a hooked on the pressure bearing member 10 and fixed to the bottom of the pile, and the tension force when tensioning the tension member 6 causes the tension member 6 to be tightened. It is supported and dispersed by the pair of thick plate-shaped members 10b which are connected so as to face each other. Therefore, the tensile stress is not concentrated on the bottom of the pile, and the prestress can be uniformly introduced to the entire pile.

【0031】[0031]

【発明の効果】以上述べたように本発明の場所打ちコン
クリート杭およびその施工法は、地下室などの地下躯体
が構築される場合に、引張り材の施工が容易、かつ確実
に行え、杭工事中の引張り材の施工がなくなり工事の煩
雑性をなくすことができ、施工性がよく、しかも、杭体
の全体に均等にプレストレスを導入できるものである。
As described above, the cast-in-place concrete pile and the construction method thereof according to the present invention can easily and reliably perform the construction of the tensile member when the underground structure such as the basement is constructed, and the The construction of the tension material can be eliminated, the complexity of the construction can be eliminated, the workability is good, and the prestress can be evenly introduced into the entire pile body.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の場所打ちコンクリート杭の施工法の第
1実施形態を示す第1工程の縦断正面図である。
FIG. 1 is a vertical sectional front view of a first step showing a first embodiment of a method for constructing a cast-in-place concrete pile of the present invention.

【図2】本発明の場所打ちコンクリート杭の施工法の第
1実施形態を示す第1工程の平面図である。
FIG. 2 is a plan view of a first step showing the first embodiment of the method for constructing a cast-in-place concrete pile of the present invention.

【図3】本発明の場所打ちコンクリート杭の施工法の第
1実施形態を示す第2工程の縦断正面図である。
FIG. 3 is a vertical sectional front view of a second step showing the first embodiment of the method for constructing a cast-in-place concrete pile of the present invention.

【図4】本発明の場所打ちコンクリート杭の施工法の第
1実施形態を示す第3工程の縦断正面図である。
FIG. 4 is a vertical sectional front view of a third step showing the first embodiment of the method for constructing a cast-in-place concrete pile of the present invention.

【図5】本発明の場所打ちコンクリート杭の施工法の第
2実施形態を示す杭の要部の縦断正面図である。
FIG. 5 is a vertical sectional front view of a main portion of a pile showing a second embodiment of the method for constructing a cast-in-place concrete pile of the present invention.

【図6】本発明の場所打ちコンクリート杭の施工法の第
3実施形態による杭の要部の縦断正面図である。
FIG. 6 is a vertical sectional front view of a main portion of a pile according to a third embodiment of the method for constructing a cast-in-place concrete pile of the present invention.

【図7】本発明の場所打ちコンクリート杭の支圧体の一
例を示す縦断正面図である。
FIG. 7 is a vertical sectional front view showing an example of a pressure bearing body of a cast-in-place concrete pile of the present invention.

【図8】本発明の場所打ちコンクリート杭の支圧体の一
例を示す平面図である。
FIG. 8 is a plan view showing an example of a bearing member of a cast-in-place concrete pile of the present invention.

【符号の説明】[Explanation of symbols]

1…掘削孔 2…杭鉄筋 3…コンクリート 4…杭体 5…ボーリング孔 5a…拡径部 5b…螺旋溝 6…引張り材 6a…折り返し部 7…定着グリップ 8…グラウト材 9…シース管 9a…螺旋溝 10…支圧体 10a…厚板状部材 10b…連結部材 DESCRIPTION OF SYMBOLS 1 ... Excavation hole 2 ... Pile reinforcement 3 ... Concrete 4 ... Pile body 5 ... Boring hole 5a ... Expanded part 5b ... Spiral groove 6 ... Tensile material 6a ... Folding part 7 ... Fixing grip 8 ... Grout material 9 ... Sheath tube 9a ... Spiral groove 10 ... Bearing body 10a ... Thick plate member 10b ... Connecting member

───────────────────────────────────────────────────── フロントページの続き (72)発明者 林 英雄 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 福島 正隆 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Hideo Hayashi 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Within Kashima Construction Co., Ltd. (72) Masataka Fukushima 1-2-7 Moto-Akasaka, Minato-ku, Tokyo No. Kashima Construction Co., Ltd.

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 地下躯体が構築される場合で、地下掘削
で杭頭を露出させたコンクリート杭に長さ方向にボーリ
ング孔をその上端が杭上端に開口するように削孔し、該
ボーリング孔に引張り材を挿入したことを特徴とする場
所打ちコンクリート杭。
1. When an underground skeleton is constructed, a boring hole is drilled in a length direction in a concrete pile whose pile head is exposed by underground excavation so that its upper end opens at the upper end of the pile. A cast-in-place concrete pile characterized by having a tensile member inserted in it.
【請求項2】 引張り材を挿入するボーリング孔は下端
部を拡径部に形成した請求項1記載のコンクリート杭。
2. The concrete pile according to claim 1, wherein the boring hole into which the tensile member is inserted has a lower end portion formed in a diameter-expanded portion.
【請求項3】 引張り材を挿入するボーリング孔は下端
部の孔壁に螺旋溝を形成した請求項1記載のコンクリー
ト杭。
3. The concrete pile according to claim 1, wherein the boring hole into which the tensile member is inserted has a spiral groove formed in the hole wall at the lower end.
【請求項4】 引張り材は途中をU字状に折り返し、こ
の折り返し部を杭底に位置させて孔に挿入し、対向して
連結された一対の厚板状部材による支圧体の連結部に前
記折り返し部を掛着した請求項1記載の場所打ちコンク
リート杭。
4. The tension member is folded back in a U shape in the middle, and the folded portion is positioned at the bottom of the pile and inserted into the hole. The cast-in-place concrete pile according to claim 1, wherein the folded-back portion is hooked on.
【請求項5】 地下躯体が構築される場合で、地下掘削
で杭頭が露出し、コンクリート杭に長さ方向に形成した
ボーリング孔で下部を拡径部に形成した孔に、管壁に螺
旋溝を形成したシース管を挿入し、該シース管内に先端
に支圧体として厚板状の定着体を取り付けた引張り材を
挿入したことを特徴とする場所打ちコンクリート杭。
5. When an underground skeleton is constructed, the pile head is exposed by underground excavation, and the lower part of the concrete pile is formed in the lengthwise direction by boring holes formed in the expanded part, and the pipe wall is spiraled. A cast-in-place concrete pile in which a sheath tube having a groove is inserted, and a tensile member having a thick plate-shaped fixing body as a pressure bearing body attached to the tip is inserted into the sheath tube.
【請求項6】 地下躯体が構築される場合で、地上から
掘削した杭孔内の下方部で地下躯体の基礎部となる部分
にのみコンクリートを打設した後、地下掘削を行って杭
頭を露出し、コンクリート杭にボーリング孔を形成し、
ここに引張り材を挿入することを特徴とする場所打ちコ
ンクリート杭の施工法。
6. In the case where an underground skeleton is constructed, concrete is placed only in the lower portion of the pile hole excavated from the ground, which will be the foundation of the underground skeleton, and then underground excavation is performed to remove the pile head. Exposed, forming a boring hole in the concrete pile,
A method of constructing cast-in-place concrete piles, characterized by inserting a tensile member here.
【請求項7】 地下躯体が構築される場合で、地上から
掘削した杭孔内の下方部で地下躯体の基礎部となる部分
にのみシース管を建て込んでコンクリートを打設した
後、地下掘削を行って杭頭を露出し、シース管の下部に
ボーリングにより拡径部または螺旋溝のいずれかを形成
し、これらシース管内およびボーリングにより形成した
拡径部または螺旋溝に引張り材を挿入したことを特徴と
する場所打ちコンクリート杭の施工法。
7. In the case where an underground skeleton is constructed, a sheath pipe is laid only in a portion which will be a foundation of the underground skeleton in a lower portion of a pile hole excavated from the ground, and concrete is then poured, followed by underground excavation. To expose the pile head and form either an expanded diameter part or a spiral groove by boring in the lower part of the sheath tube, and insert a tension material inside these sheath tubes and in the expanded diameter part or spiral groove formed by boring. Construction method for cast-in-place concrete piles.
JP07268560A 1995-10-17 1995-10-17 Cast-in-place concrete pile and its construction method Expired - Fee Related JP3081905B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP07268560A JP3081905B2 (en) 1995-10-17 1995-10-17 Cast-in-place concrete pile and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP07268560A JP3081905B2 (en) 1995-10-17 1995-10-17 Cast-in-place concrete pile and its construction method

Publications (2)

Publication Number Publication Date
JPH09111758A true JPH09111758A (en) 1997-04-28
JP3081905B2 JP3081905B2 (en) 2000-08-28

Family

ID=17460231

Family Applications (1)

Application Number Title Priority Date Filing Date
JP07268560A Expired - Fee Related JP3081905B2 (en) 1995-10-17 1995-10-17 Cast-in-place concrete pile and its construction method

Country Status (1)

Country Link
JP (1) JP3081905B2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100680286B1 (en) * 2006-09-05 2007-02-08 주식회사 삼풍엔지니어링건축사 사무소 Pile structure for building
WO2011126170A1 (en) * 2010-04-09 2011-10-13 Kim Sung-Kyu Construction method of pre-stressed cast-in -place concrete pile and structure thereof
CN102345292A (en) * 2011-07-21 2012-02-08 从卫民 Composite prestressed uplift pile with expansion heads
CN102644279A (en) * 2012-04-28 2012-08-22 从卫民 Uplift pile with prestress reinforced plastic rods
JP2014227729A (en) * 2013-05-23 2014-12-08 東日本旅客鉄道株式会社 Banking reinforcement structure and banking reinforcement method
CN107806086A (en) * 2017-10-31 2018-03-16 西南石油大学 Soil pressure cell fixing device after a kind of manually digging hole filling pile stake
CN113281407A (en) * 2021-04-30 2021-08-20 中国一冶集团有限公司 Device and method for improving compactness of cast-in-situ bored pile
CN114016498A (en) * 2021-11-15 2022-02-08 中国建筑第四工程局有限公司 Construction method for preventing hole string of overlength hollow cast-in-place pile in sea-filling area

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05134125A (en) * 1991-11-14 1993-05-28 Tatsuta Electric Wire & Cable Co Ltd Gas dam part of optical coated fiber

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100680286B1 (en) * 2006-09-05 2007-02-08 주식회사 삼풍엔지니어링건축사 사무소 Pile structure for building
WO2011126170A1 (en) * 2010-04-09 2011-10-13 Kim Sung-Kyu Construction method of pre-stressed cast-in -place concrete pile and structure thereof
KR101152265B1 (en) * 2010-04-09 2012-06-14 김성규 Prestressed bored pile construction method and structures
CN102345292A (en) * 2011-07-21 2012-02-08 从卫民 Composite prestressed uplift pile with expansion heads
CN102644279A (en) * 2012-04-28 2012-08-22 从卫民 Uplift pile with prestress reinforced plastic rods
JP2014227729A (en) * 2013-05-23 2014-12-08 東日本旅客鉄道株式会社 Banking reinforcement structure and banking reinforcement method
CN107806086A (en) * 2017-10-31 2018-03-16 西南石油大学 Soil pressure cell fixing device after a kind of manually digging hole filling pile stake
CN113281407A (en) * 2021-04-30 2021-08-20 中国一冶集团有限公司 Device and method for improving compactness of cast-in-situ bored pile
CN113281407B (en) * 2021-04-30 2024-01-12 中国一冶集团有限公司 Device and method for improving compactness of bored pile
CN114016498A (en) * 2021-11-15 2022-02-08 中国建筑第四工程局有限公司 Construction method for preventing hole string of overlength hollow cast-in-place pile in sea-filling area
CN114016498B (en) * 2021-11-15 2023-11-03 中国建筑第四工程局有限公司 Construction method for preventing filling pile from being in series holes in ultra-long hollow holes in sea-filling area

Also Published As

Publication number Publication date
JP3081905B2 (en) 2000-08-28

Similar Documents

Publication Publication Date Title
JP4010383B2 (en) Pile method
EP0070659A1 (en) Retaining wall and in situ method of construction
JPH09111758A (en) Cast-in-place concrete pile and construction method thereof
JP3754506B2 (en) Prestressed concrete pile construction method
US20060177279A1 (en) Reinforcing wall in a deep excavation site
KR20030028518A (en) apparatus and method for retaining wall using ground anchor
KR102171787B1 (en) Soil retaining wall using phc pile
JP2984728B2 (en) Construction method of cast-in-place concrete pile
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
JP3331110B2 (en) Construction method and retaining wall structure of retaining wall using deep mixed consolidated pile
JP3586839B2 (en) In-situ formed concrete pile and its forming method
JPH073777A (en) Method for constructing self-supporting land slide protection wall
KR102264595B1 (en) Self supporting type phc pile and construction method for the same
KR102614988B1 (en) Pre-stressed composite pile for retaining wall in remodeling
JPH0468407B2 (en)
KR100450444B1 (en) Construction Method of Complex Pile Consisting Prestressed spun High strength Concrete Pile and Anchor
JPS6138015A (en) Sheathing work
JPH08199565A (en) Pile head joint construction of cast-in-place concrete pile
JPH10298976A (en) Foundation structure for building bound with soil cement column row earth retaining wall to skeleton
JPH04185816A (en) Construction of beam in underground wall
JP2893422B2 (en) Construction method of underground structure
KR20000021523A (en) Prestress soil nailing method for stabilizing slant face using steel reinforcing
KR20200123347A (en) Phc pile for soil retaining wall
JPH025205B2 (en)
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees