CN110616740A - Structure for expanding subway section in subway mine method construction interval and construction method thereof - Google Patents

Structure for expanding subway section in subway mine method construction interval and construction method thereof Download PDF

Info

Publication number
CN110616740A
CN110616740A CN201910871792.2A CN201910871792A CN110616740A CN 110616740 A CN110616740 A CN 110616740A CN 201910871792 A CN201910871792 A CN 201910871792A CN 110616740 A CN110616740 A CN 110616740A
Authority
CN
China
Prior art keywords
fender
pile
foundation pit
piles
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910871792.2A
Other languages
Chinese (zh)
Inventor
孔恒
彭明玉
史磊磊
梁静宇
王渭
张仲宇
贾硕
戴建伟
鲍宇
王胜奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Beijing No 4 Municipal Construction Engineering Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Beijing No 4 Municipal Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd, Beijing No 4 Municipal Construction Engineering Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201910871792.2A priority Critical patent/CN110616740A/en
Publication of CN110616740A publication Critical patent/CN110616740A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Abstract

A structure for expanding a metro section in a metro mine construction interval and a construction method thereof. The structure comprises a newly-built interval structure (6) built between an existing left line interval structure (4) and an existing right line interval structure (5) built by a mine method, wherein the newly-built interval structure (6) is a variable-section rectangular structure, a main structure of the newly-built interval structure comprises a structure bottom plate, a side wall and a top plate structure, and the newly-built interval structure (6) is in a gradual change form along the direction of a subway line; the newly-built interval structure (6) is supported by an irregular foundation pit enclosure system, the foundation pit is formed by expanding by an open cut method, and the irregular foundation pit enclosure system adopts a combination mode of double-row enclosure piles (7) + prestressed anchoring cables (10) and single-row enclosure piles (8) + steel supports (9). The invention provides a reasonable and feasible design scheme, and realizes the reconstruction of the established subway interval of the mine method through an open cut method and the extension of an interval structure with a transition line segment.

Description

Structure for expanding subway section in subway mine method construction interval and construction method thereof
Technical Field
The invention belongs to the field of underground structures, and particularly relates to a structure for expanding a metro section in a metro mine method construction interval and a key technical construction method thereof, which are beneficial to solving the metro operation problem and bring better social benefits to the society.
Background
In recent years, the problem of traffic jam in large and medium-sized cities is particularly prominent, so that the development of public traffic is promoted, and more cities begin to build urban rail transit to meet the urban traffic demand. However, subway lines are generally long, and some stations may not be completely communicated due to the reason of a certain station because of the limitation of conditions such as occupied area removal, integrated development or restriction factors encountered during construction. Aiming at the situation, a mode of additionally arranging a single crossover line in front of a station of a checkpoint can be adopted to meet the requirement of operation organization and achieve the purpose of full-line segmented operation. However, the design is usually improved immediately, the reserved crossover condition is not considered during the design, and the construction of the section is completed, so that the vehicle cannot turn back in the section, and only the crossover at the previous section can turn back, and the station between the checkpoint station and the crossover at the previous section cannot be opened for operation. Therefore, it is necessary to provide a structure and a method for opening the station in this area.
Disclosure of Invention
In order to solve the problems, the invention provides a structure for expanding a metro section in a metro mine method construction interval into a transition line section and a key technical construction method thereof. The invention provides a reasonable and feasible design scheme, and realizes the reconstruction of the established subway interval of the mine method through an open cut method and the extension of an interval structure with a transition line segment.
The technical scheme adopted by the invention for solving the technical problems is that a structure for expanding a subway construction interval into a transition line section by a subway mine method comprises a newly-built interval structure between an existing left line interval structure and an existing right line interval structure which are built by the mine method, wherein the newly-built interval structure is a variable-section rectangular structure, the main structure of the newly-built interval structure comprises a structure bottom plate, a side wall and a top plate structure, and the newly-built interval structure is in a gradual change form along the subway line;
the newly-built interval structure is supported by an irregular foundation pit enclosure system, the foundation pit is formed by expanding by an open cut method, the irregular foundation pit enclosure system adopts a combination mode of double-row enclosure piles, prestressed anchoring cables and single-row enclosure piles and steel supports, the concrete structure comprises that the left side and the right side of the foundation pit along the trend of the subway line are supported by the single-row enclosure piles, the single-row enclosure piles on the left side and the right side are connected by the steel supports, the soil bodies at two ends of the foundation pit along the trend of the subway line are provided with the double-row enclosure piles and the prestressed anchoring cables for reinforcement, the lower parts of the double-row enclosure piles are reinforced by a soil nailing wall reinforcing embedded structure, and the upper parts of the double-row enclosure piles are provided with crown beams;
the number of the single row of fender piles is multiple, a crown beam is arranged above each single row of fender piles, and the top ends of the multiple single row of fender piles are fixedly connected with the crown beam into a whole; the steel supports are arranged in parallel from top to bottom, the uppermost group of steel supports is connected with the crown beam, and the rest groups of steel supports are connected with the single row of fender posts through the waist beam; each group of steel supports is provided with a plurality of steel supports which are arranged in parallel from front to back and are uniformly distributed on the same horizontal plane, and two ends of each steel support are respectively fixed on the inner side wall of the waist beam on the same horizontal plane; the steel support is supported by a plurality of temporary stand columns, and the temporary stand columns are fixed on a base of the foundation pit; a retaining wall is arranged at the upper edge of the foundation pit, and a water intercepting ditch is arranged on the outer side of the retaining wall; and arranging an L-shaped crown beam on the soil slope 3-5m away from the pile bottom of the double-row fender pile at two ends of the foundation pit, and arranging a soil nail wall reinforcing and embedding structure at the lower part of the L-shaped crown beam.
Preferably, the pile bodies of the single-row fender pile and the double-row fender pile are both made of slurry and pile body reinforcements, each pile body reinforcement is a prefabricated steel member and is provided with a connecting end, each connecting end consists of a high-strength connecting steel rod and a plug, and the joints of the connecting ends are sealed by epoxy resin; and a crown beam is arranged at the top of the pile body reinforcing piece.
In any of the above solutions, preferably, the slurry is cement mortar formed by pouring and mixing the undisturbed soil of the pile position of the fender pile with a curing agent through a drill hole, so as to form an independent pile body with a cylindrical or rectangular cross section.
In any of the above schemes, preferably, between adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the single row of fender piles and the double row of fender piles, and on the surface of the fender piles facing the inner side of the foundation pit, fender structures with the same height as the fender piles are arranged, the fender structures are made of concrete, reinforcing mesh is arranged in the concrete, and the reinforcing mesh is connected with the fender piles through a plurality of connectors; the connecting piece is a reinforcing steel bar with the diameter of 12-15mm, and the reinforcing mesh is of a reticular structure made of phi 8 round steel with the size of 150mm multiplied by 150 mm.
The invention adopts another technical scheme to solve the technical problems, and the key technical construction method for expanding a metro section into a transition line section structure by a metro mine method construction interval comprises the following steps:
a. constructing a plurality of dewatering wells on the stratum of the designed foundation pit excavation construction area by adopting the dewatering wells, and performing dewatering construction on the stratum by adopting a water suction pump;
b. side lines are excavated along the periphery of a designed foundation pit area, double rows of fender piles and single rows of fender piles are sequentially constructed at related design positions of the foundation pit, and cement mortar is formed on the pile positions of the fender piles by adopting a drilling and pouring method to form independent pile bodies with cylindrical or rectangular sections; hoisting the pile body reinforcement to a pile position, overcoming resistance through a high-frequency vibration hammer and implanting the pile body reinforcement into the formed slurry, splicing the pile body reinforcement through a connecting end, continuously and repeatedly hoisting after splicing, splicing to the bottom of the slurry, and adjusting the plane position and elevation of the pile body reinforcement through a pile top positioning adjusting bolt; then constructing a crown beam at the pile top of the fender pile, and sequentially constructing a retaining wall and a catch basin around the designed excavation position of the foundation pit;
c. sequentially and downwards excavating, and arranging the steel supports among the single row of fender piles; then, arranging a prestressed anchoring cable at the position where the double-row fender post is constructed on the excavated foundation pit wall; excavating a soil body to a position 3-5m away from the pile bottom of the double-row fender pile, reserving a part of soil slope, constructing an L-shaped crown beam on the soil slope, and immediately arranging a prestressed anchoring cable after the design strength is reached; and a fence structure is constructed above the L-shaped crown beam and between the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double rows of fender piles;
d. continuously excavating a soil body downwards, spraying concrete to the soil slope construction hanging net, immediately drilling 2 anchor rods, and forming a soil nailing wall reinforced embedding structure after the design strength is reached;
e. continuously excavating the soil body downwards to the designed height position of the newly-built interval structure, and dismantling the existing structure; constructing a fence structure between adjacent single fender piles of the single row of fender piles;
f. and finally, sequentially completing construction of a structural bottom plate, a side wall and a top plate structure for the main structure of the newly-built interval structure according to a sequential construction method, and effectively connecting the main structure with the existing interval structure to ensure the communication of the whole interval.
Preferably, the step c of arranging the steel supports among the single row of fender piles comprises the following construction steps: excavating a first layer of soil body of the excavated foundation pit until the first layer of soil body is excavated to the bottom elevation of the uppermost layer of the steel supports; then connecting the group of steel supports on the uppermost layer with the crown beams of the single row of fender piles; excavating a second layer of soil body of the excavated foundation pit until the second layer of soil body is excavated to the bottom elevation of the group of steel supports with the second height; then connecting the steel support with the single row of fender posts through the wale; and repeating the construction sequence until a group of steel supports at the lowermost layer are connected with the single-row fender piles through the wales.
In any of the above schemes, preferably, the construction steps of the enclosure structure are as follows: manually cleaning soil on the surface of the fender pile and soil between any two adjacent fender piles; preparing a plurality of connecting pieces, drilling holes in the cleaned fender post, and placing one end of each connecting piece into the fender post; manufacturing a steel bar mesh with a mesh structure by using a plurality of steel bars, and penetrating the other end of the connector through the steel bar mesh; and laying templates on two sides of the reinforcing mesh, pouring concrete between the templates and the fender post, and removing the templates after the concrete is solidified.
In any scheme, preferably, in the step d, soil bodies are continuously excavated downwards, the slope of the soil slope is 1:0.2, and double layers are hung@150X150 reinforcing mesh, spraying C25 concrete with the thickness of 150mm, and immediately drilling 2 anchor rods; and e, removing the existing structure by adopting a static force removing method.
The invention is obtained according to years of practical application practice and experience, adopts the best technical means and measures to carry out combined optimization, obtains the optimal technical effect, is not simple superposition and splicing of technical characteristics, and has obvious significance.
The invention has the beneficial effects that:
1. under the condition that a subway section is built, the structure of the subway section is improved by adopting an open cut method, the section structure of a cross section is completed, and conditions are provided for turning back of subway vehicles; the construction method of the invention provides a safe solution for the pile body with insufficient embedding depth, and the fender post is constructed above the existing interval structure, and the embedding depth of the pile body can not be met due to the existence of the lower structure, even under the condition that the base is positioned below the pile end, the soil body at the pile end is reinforced by adopting a mode of reinforcing the embedding structure by the soil nailing wall, so as to prevent the pile end from generating displacement to cause instability of the foundation pit, and the method can be used for solving the problems similar to the foundation pit.
2. The method has the advantages of simple steps, reasonable design, convenient construction, faster construction progress, good construction effect and lower input construction cost. The foundation pit support structure is optimized, combined measures such as construction pipe well dewatering, prestressed anchoring cables, fender piles, steel supports and soil nailing wall reinforcing embedment are fully utilized for supporting, and safety and reliability of the foundation pit support structure are guaranteed. The invention has high practical value, remarkable social benefit and economic benefit and great popularization and application value.
3. The invention inserts the vertically assembled body reinforcement into the slurry pre-formed into a pile on site, and forms the integral fender pile through the crown beam arranged at the top, thereby replacing the existing fender pile structure. The invention has strong field construction operability and high operation efficiency, can ensure the integrity and construction quality of the structure, reduces the construction cost and has good construction implementation effect.
4. By adopting the technical scheme provided by the invention, the enclosure piles, the reinforcing mesh and the concrete are connected into an integral structure, the poured concrete layer is smoother, the thickness of the concrete layer is easier to control, the enclosure piles are well sealed, the waterproof effect of the whole supporting system is ensured, and meanwhile, the reinforcing mesh is arranged between the enclosure piles and the inner wall of the foundation pit, so that the strength of the supporting structure is enhanced.
Drawings
FIG. 1 is a schematic structural plane view of a transition line segment expanded in a subway mine method construction interval according to the present invention;
FIG. 2 is a cross-sectional view of a foundation pit enclosure system of a structure for expanding a transition line section between metro and mine construction intervals according to the present invention;
fig. 3 is a side view of a foundation pit enclosure system of a structure for expanding a transition line section in a subway mine method construction interval.
Wherein, 1-existing left line interval structure central line, 2-existing right line interval structure central line and 3-crossover line central line.
Detailed Description
The invention is further described with reference to the following figures and specific examples, but the scope of the claims is not limited thereto.
Example 1
Referring to fig. 1-3, a structure for expanding a subway mine-method-built interval into a transition line section comprises a newly-built interval structure 6 built between an existing left line interval structure 4 and an existing right line interval structure 5 built by a mine method, wherein the newly-built interval structure 6 is a variable-section rectangular structure, the main structure of the newly-built interval structure comprises a structure bottom plate, a side wall and a top plate structure, and the newly-built interval structure 6 is in a gradual change form along the subway line;
the newly-built interval structure 6 is supported by an irregular foundation pit enclosure system, the foundation pit is formed by expanding by an open cut method, the irregular foundation pit enclosure system adopts a combination mode of double-row enclosure piles 7+ prestressed anchoring cables 10 and single-row enclosure piles 8+ steel supports 9, specifically, the foundation pit is supported by the single-row enclosure piles 8 along the left side and the right side of the subway line trend, the single-row enclosure piles 8 on the left side and the right side are connected by the steel supports 9, the double-row enclosure piles 7 and the prestressed anchoring cables 10 are arranged on soil bodies at two ends of the foundation pit along the subway line trend for reinforcement, the lower parts of the double-row enclosure piles 7 are reinforced by soil nail wall reinforcing embedded structures 16, and the upper parts of the double-row enclosure piles 7 are provided with crown beams 13;
the number of the single row of fender piles 8 is multiple, a crown beam 13 is arranged above each single row of fender piles 8, and the top ends of the multiple single row of fender piles 8 are fixedly connected with the crown beam 13 into a whole; the steel supports 9 are arranged in parallel from top to bottom, the uppermost steel support 9 is connected with the crown beam 13, and the rest steel supports 9 are connected with the single-row fender post 8 through the waist beam; each group of steel supports 9 is provided with a plurality of steel supports 9 which are arranged in parallel from front to back and are uniformly distributed on the same horizontal plane, and two ends of each steel support 9 are respectively fixed on the inner side wall of the waist beam on the same horizontal plane; the steel support 9 is supported by a plurality of temporary upright columns 11, and the temporary upright columns 11 are fixed on a base 12 of a foundation pit; a retaining wall 15 is arranged at the upper edge of the foundation pit, and a catch basin 14 is arranged on the outer side of the retaining wall 15; an L-shaped crown beam 17 is arranged on a soil slope 3-5m away from the pile bottom of the double-row fender pile 7 at two ends of the foundation pit, and a soil nailing wall reinforcing and embedding structure 16 is arranged at the lower part of the L-shaped crown beam 17.
The pile bodies of the single-row fender post 8 and the double-row fender post 7 are both made of slurry and pile body reinforcing parts, the pile body reinforcing parts are prefabricated steel members and are provided with connecting ends, each connecting end consists of a high-strength connecting steel rod and a plug, and joints of the connecting ends are sealed by epoxy resin; and a crown beam 13 is arranged at the top of the pile body reinforcing part.
The slurry is cement mortar formed by pouring pile position undisturbed soil of the fender post into a drilled hole and mixing with a curing agent, so that an independent pile body is formed, and the section of the pile body is cylindrical or rectangular.
A fence structure with the same height as the fender pile is arranged between the single row of fender piles 8 and the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double rows of fender piles 7 and on the surface of the fender piles facing the inner side of the foundation pit, the fence structure is made of concrete, a steel bar net is arranged in the concrete, and the steel bar net is connected with the fender piles through a plurality of connectors; the connecting piece is a reinforcing steel bar with the diameter of 12-15mm, and the reinforcing mesh is of a reticular structure made of phi 8 round steel with the size of 150mm multiplied by 150 mm.
In addition, a key technical construction method for expanding a metro section into a transition line section structure in a metro mine method construction interval comprises the following steps:
a. constructing a plurality of dewatering wells on the stratum of the designed foundation pit excavation construction area by adopting the dewatering wells, and performing dewatering construction on the stratum by adopting a water suction pump;
b. side lines are excavated along the periphery of a designed foundation pit area, double rows of fender piles 7 and single rows of fender piles 8 are sequentially constructed at related design positions of the foundation pit, and cement mortar is formed on the pile positions of the fender piles by adopting a drilling and pouring method to form an independent pile body with a cylindrical or rectangular cross section; hoisting the pile body reinforcement to a pile position, overcoming resistance through a high-frequency vibration hammer and implanting the pile body reinforcement into the formed slurry, splicing the pile body reinforcement through a connecting end, continuously and repeatedly hoisting after splicing, splicing to the bottom of the slurry, and adjusting the plane position and elevation of the pile body reinforcement through a pile top positioning adjusting bolt; then constructing a crown beam 13 on the pile top of the fender pile, and sequentially constructing a retaining wall 15 and a catch basin 14 around the designed excavation position of the foundation pit;
c. sequentially and downwards excavating, and arranging the steel supports 9 among the single row of fender piles 8; then, arranging a prestressed anchoring cable 10 at the position where the double-row fender post 7 is constructed on the excavated foundation pit wall; excavating a soil body to a position 3-5m away from the pile bottom of the double-row fender post 7, reserving a part of soil slope, constructing an L-shaped crown beam 17 on the soil slope, and immediately arranging a prestressed anchoring cable 10 after the design strength is reached; and a fence structure is constructed above the L-shaped crown beam 17 and between the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double-row fender piles 7;
d. continuously excavating the soil body downwards, spraying concrete 18 to the soil slope construction hanging net, immediately drilling 2 anchor rods 19, and forming a soil nailing wall reinforcing embedded structure 16 after the design strength is reached;
e. continuously excavating the soil body downwards to the designed height position of the newly-built interval structure 6, and dismantling the existing structure 20 at the designed height position; then constructing a fence structure between the adjacent single fender piles of the single row of fender piles 8;
f. and finally, sequentially completing construction of a structure bottom plate, a side wall and a top plate structure for the main structure of the newly-built interval structure 6 according to a sequential construction method, and effectively connecting the main structure with the existing interval structure to ensure the communication of the whole interval.
In the step c, the construction steps for arranging the steel supports 9 among the single row of fender piles 8 are as follows: excavating a first layer of soil body of the excavated foundation pit until the first layer of soil body is excavated to the bottom elevation of the uppermost group of steel supports 9; then connecting the group of steel supports 9 at the uppermost layer with the crown beams 13 of the single row of fender piles 8; excavating a second layer of soil body of the excavated foundation pit until the second layer of soil body is excavated to the bottom elevation of the group of steel supports 9 with the second height; then connecting the steel support 9 with the single row of fender posts 8 through the wale; and repeating the construction sequence until the group of the steel supports 9 at the lowest layer is connected with the single-row fender piles 8 through the wales.
The construction steps of the enclosure structure are as follows: manually cleaning soil on the surface of the fender pile and soil between any two adjacent fender piles; preparing a plurality of connecting pieces, drilling holes in the cleaned fender post, and placing one end of each connecting piece into the fender post; manufacturing a steel bar mesh with a mesh structure by using a plurality of steel bars, and penetrating the other end of the connector through the steel bar mesh; and laying templates on two sides of the reinforcing mesh, pouring concrete between the templates and the fender post, and removing the templates after the concrete is solidified.
In the step d, soil is continuously excavated downwards, the slope of the soil slope is 1:0.2, and double layers are hung@150X150 reinforcing mesh, spraying C25 concrete 18 with the thickness of 150mm, and immediately drilling 2 anchor rods 19; and e, removing the existing structure 20 by adopting a static force breaking method.
Example 2
Referring to fig. 1-3, a structure for expanding a subway mine-method-built interval into a transition line section comprises a newly-built interval structure 6 built between an existing left line interval structure 4 and an existing right line interval structure 5 built by a mine method, wherein the newly-built interval structure 6 is a variable-section rectangular structure, the main structure of the newly-built interval structure comprises a structure bottom plate, a side wall and a top plate structure, and the newly-built interval structure 6 is in a gradual change form along the subway line;
the newly-built interval structure 6 is supported by an irregular foundation pit enclosure system, the foundation pit is formed by expanding by an open cut method, the irregular foundation pit enclosure system adopts a combination mode of double-row enclosure piles 7+ prestressed anchoring cables 10 and single-row enclosure piles 8+ steel supports 9, specifically, the foundation pit is supported by the single-row enclosure piles 8 along the left side and the right side of the subway line trend, the single-row enclosure piles 8 on the left side and the right side are connected by the steel supports 9, the double-row enclosure piles 7 and the prestressed anchoring cables 10 are arranged on soil bodies at two ends of the foundation pit along the subway line trend for reinforcement, the lower parts of the double-row enclosure piles 7 are reinforced by soil nail wall reinforcing embedded structures 16, and the upper parts of the double-row enclosure piles 7 are provided with crown beams 13;
the number of the single row of fender piles 8 is multiple, a crown beam 13 is arranged above each single row of fender piles 8, and the top ends of the multiple single row of fender piles 8 are fixedly connected with the crown beam 13 into a whole; the steel supports 9 are arranged in parallel from top to bottom, the uppermost steel support 9 is connected with the crown beam 13, and the rest steel supports 9 are connected with the single-row fender post 8 through the waist beam; each group of steel supports 9 is provided with a plurality of steel supports 9 which are arranged in parallel from front to back and are uniformly distributed on the same horizontal plane, and two ends of each steel support 9 are respectively fixed on the inner side wall of the waist beam on the same horizontal plane; the steel support 9 is supported by a plurality of temporary upright columns 11, and the temporary upright columns 11 are fixed on a base 12 of a foundation pit; a retaining wall 15 is arranged at the upper edge of the foundation pit, and a catch basin 14 is arranged on the outer side of the retaining wall 15; an L-shaped crown beam 17 is arranged on a soil slope 3-5m away from the pile bottom of the double-row fender pile 7 at two ends of the foundation pit, and a soil nailing wall reinforcing and embedding structure 16 is arranged at the lower part of the L-shaped crown beam 17.
The pile bodies of the single-row fender post 8 and the double-row fender post 7 are both made of slurry and pile body reinforcing parts, the pile body reinforcing parts are prefabricated steel members and are provided with connecting ends, each connecting end consists of a high-strength connecting steel rod and a plug, and joints of the connecting ends are sealed by epoxy resin; and a crown beam 13 is arranged at the top of the pile body reinforcing part.
The slurry is cement mortar formed by pouring pile position undisturbed soil of the fender post into a drilled hole and mixing with a curing agent, so that an independent pile body is formed, and the section of the pile body is cylindrical or rectangular.
A fence structure with the same height as the fender pile is arranged between the single row of fender piles 8 and the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double rows of fender piles 7 and on the surface of the fender piles facing the inner side of the foundation pit, the fence structure is made of concrete, a steel bar net is arranged in the concrete, and the steel bar net is connected with the fender piles through a plurality of connectors; the connecting piece is a reinforcing steel bar with the diameter of 12-15mm, and the reinforcing mesh is of a reticular structure made of phi 8 round steel with the size of 150mm multiplied by 150 mm.
In addition, a key technical construction method for expanding a metro section into a transition line section structure in a metro mine method construction interval comprises the following steps:
a. constructing a plurality of dewatering wells on the stratum of the designed foundation pit excavation construction area by adopting the dewatering wells, and performing dewatering construction on the stratum by adopting a water suction pump;
b. side lines are excavated along the periphery of a designed foundation pit area, double rows of fender piles 7 and single rows of fender piles 8 are sequentially constructed at related design positions of the foundation pit, and cement mortar is formed on the pile positions of the fender piles by adopting a drilling and pouring method to form an independent pile body with a cylindrical or rectangular cross section; hoisting the pile body reinforcement to a pile position, overcoming resistance through a high-frequency vibration hammer and implanting the pile body reinforcement into the formed slurry, splicing the pile body reinforcement through a connecting end, continuously and repeatedly hoisting after splicing, splicing to the bottom of the slurry, and adjusting the plane position and elevation of the pile body reinforcement through a pile top positioning adjusting bolt; then constructing a crown beam 13 on the pile top of the fender pile, and sequentially constructing a retaining wall 15 and a catch basin 14 around the designed excavation position of the foundation pit;
c. sequentially and downwards excavating, and arranging the steel supports 9 among the single row of fender piles 8; then, arranging a prestressed anchoring cable 10 at the position where the double-row fender post 7 is constructed on the excavated foundation pit wall; excavating a soil body to a position 3-5m away from the pile bottom of the double-row fender post 7, reserving a part of soil slope, constructing an L-shaped crown beam 17 on the soil slope, and immediately arranging a prestressed anchoring cable 10 after the design strength is reached; and a fence structure is constructed above the L-shaped crown beam 17 and between the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double-row fender piles 7;
d. continuously excavating the soil body downwards, spraying concrete 18 to the soil slope construction hanging net, immediately drilling 2 anchor rods 19, and forming a soil nailing wall reinforcing embedded structure 16 after the design strength is reached;
e. continuously excavating the soil body downwards to the designed height position of the newly-built interval structure 6, and dismantling the existing structure 20 at the designed height position; then constructing a fence structure between the adjacent single fender piles of the single row of fender piles 8;
f. and finally, sequentially completing construction of a structure bottom plate, a side wall and a top plate structure for the main structure of the newly-built interval structure 6 according to a sequential construction method, and effectively connecting the main structure with the existing interval structure to ensure the communication of the whole interval.
In the step c, the construction steps for arranging the steel supports 9 among the single row of fender piles 8 are as follows: excavating a first layer of soil body of the excavated foundation pit until the first layer of soil body is excavated to the bottom elevation of the uppermost group of steel supports 9; then connecting the group of steel supports 9 at the uppermost layer with the crown beams 13 of the single row of fender piles 8; excavating a second layer of soil body of the excavated foundation pit until the second layer of soil body is excavated to the bottom elevation of the group of steel supports 9 with the second height; then connecting the steel support 9 with the single row of fender posts 8 through the wale; and repeating the construction sequence until the group of the steel supports 9 at the lowest layer is connected with the single-row fender piles 8 through the wales.
The construction steps of the enclosure structure are as follows: manually cleaning soil on the surface of the fender pile and soil between any two adjacent fender piles; preparing a plurality of connecting pieces, drilling holes in the cleaned fender post, and placing one end of each connecting piece into the fender post; manufacturing a steel bar mesh with a mesh structure by using a plurality of steel bars, and penetrating the other end of the connector through the steel bar mesh; and laying templates on two sides of the reinforcing mesh, pouring concrete between the templates and the fender post, and removing the templates after the concrete is solidified.
In the step d, soil is continuously excavated downwards, the slope of the soil slope is 1:0.2, and double layers are hung@150X150 reinforcing mesh, spraying C25 concrete 18 with the thickness of 150mm, and immediately drilling 2 anchor rods 19; and e, removing the existing structure 20 by adopting a static force breaking method.
Further, in order to guarantee the construction effect, the soil nailing wall reinforcing and embedding structure 16 is further provided with soil nails, the soil nails and the anchor rods 19 are distributed in an inserting mode, and the soil nails and the anchor rods are inclined. Each stock 19 is locked on the foundation ditch lateral wall through the U shaped steel that sets up along foundation ditch lateral wall level, and stock 19 passes the diapire entering soil body of U shaped steel, fills up between the bottom of rod end and U shaped steel and is equipped with the cushion, and the tip of stock 19 compresses tightly to the bottom of U shaped steel through the cushion, and the outer bottom surface of rethread U shaped steel compresses tightly to the foundation ditch lateral wall on.
In order to prevent the end part or the outer bottom surface of the U-shaped steel from crushing the side wall of the foundation pit when the anchor rod 19 is anchored, and ensure that the anchoring force of the anchor rod 19 can be effectively transmitted to the fender pile, a plurality of hollow steel rods are arranged between the outer bottom surface of the U-shaped steel and the fender pile on the slope-releasing section of the side wall of the foundation pit, and the fender pile is uniformly supported by the hollow steel rods. Meanwhile, concrete is poured into the hollow steel bar, and after the concrete is finally set, the soil nailing wall reinforcing embedded structure 16 is organically combined with the fender post, so that the effect of transmission force between the concrete and the fender post is enhanced, and the supporting effect is enhanced.
One end of the hollow steel bar close to the fender pile is provided with an adaptive end, and the shape of the adaptive end is matched with that of the outer wall of the fender pile, so that the anchor rod 19 can be effectively stressed.
The foundation pit supporting structure adopting the soil nailing wall reinforced embedded structure 16 has low construction difficulty, short construction period and easy control of construction quality; the self-stability of the soil body is utilized, the material is saved, and the cost is reduced; in addition, the construction noise is low, the vibration is small, and the method can be used for projects with higher requirements on construction influence. And the density of the fender pile in the pile anchor support is reduced, and the foundation pit support is carried out according to the advanced support concept.
Example 3
Referring to fig. 1-3, a structure for expanding a subway mine-method-built interval into a transition line section comprises a newly-built interval structure 6 built between an existing left line interval structure 4 and an existing right line interval structure 5 built by a mine method, wherein the newly-built interval structure 6 is a variable-section rectangular structure, the main structure of the newly-built interval structure comprises a structure bottom plate, a side wall and a top plate structure, and the newly-built interval structure 6 is in a gradual change form along the subway line;
the newly-built interval structure 6 is supported by an irregular foundation pit enclosure system, the foundation pit is formed by expanding by an open cut method, the irregular foundation pit enclosure system adopts a combination mode of double-row enclosure piles 7+ prestressed anchoring cables 10 and single-row enclosure piles 8+ steel supports 9, specifically, the foundation pit is supported by the single-row enclosure piles 8 along the left side and the right side of the subway line trend, the single-row enclosure piles 8 on the left side and the right side are connected by the steel supports 9, the double-row enclosure piles 7 and the prestressed anchoring cables 10 are arranged on soil bodies at two ends of the foundation pit along the subway line trend for reinforcement, the lower parts of the double-row enclosure piles 7 are reinforced by soil nail wall reinforcing embedded structures 16, and the upper parts of the double-row enclosure piles 7 are provided with crown beams 13;
the number of the single row of fender piles 8 is multiple, a crown beam 13 is arranged above each single row of fender piles 8, and the top ends of the multiple single row of fender piles 8 are fixedly connected with the crown beam 13 into a whole; the steel supports 9 are arranged in parallel from top to bottom, the uppermost steel support 9 is connected with the crown beam 13, and the rest steel supports 9 are connected with the single-row fender post 8 through the waist beam; each group of steel supports 9 is provided with a plurality of steel supports 9 which are arranged in parallel from front to back and are uniformly distributed on the same horizontal plane, and two ends of each steel support 9 are respectively fixed on the inner side wall of the waist beam on the same horizontal plane; the steel support 9 is supported by a plurality of temporary upright columns 11, and the temporary upright columns 11 are fixed on a base 12 of a foundation pit; a retaining wall 15 is arranged at the upper edge of the foundation pit, and a catch basin 14 is arranged on the outer side of the retaining wall 15; an L-shaped crown beam 17 is arranged on a soil slope 3-5m away from the pile bottom of the double-row fender pile 7 at two ends of the foundation pit, and a soil nailing wall reinforcing and embedding structure 16 is arranged at the lower part of the L-shaped crown beam 17.
The pile bodies of the single-row fender post 8 and the double-row fender post 7 are both made of slurry and pile body reinforcing parts, the pile body reinforcing parts are prefabricated steel members and are provided with connecting ends, each connecting end consists of a high-strength connecting steel rod and a plug, and joints of the connecting ends are sealed by epoxy resin; and a crown beam 13 is arranged at the top of the pile body reinforcing part.
The slurry is cement mortar formed by pouring pile position undisturbed soil of the fender post into a drilled hole and mixing with a curing agent, so that an independent pile body is formed, and the section of the pile body is cylindrical or rectangular.
A fence structure with the same height as the fender pile is arranged between the single row of fender piles 8 and the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double rows of fender piles 7 and on the surface of the fender piles facing the inner side of the foundation pit, the fence structure is made of concrete, a steel bar net is arranged in the concrete, and the steel bar net is connected with the fender piles through a plurality of connectors; the connecting piece is a reinforcing steel bar with the diameter of 12-15mm, and the reinforcing mesh is of a reticular structure made of phi 8 round steel with the size of 150mm multiplied by 150 mm.
In addition, a key technical construction method for expanding a metro section into a transition line section structure in a metro mine method construction interval comprises the following steps:
a. constructing a plurality of dewatering wells on the stratum of the designed foundation pit excavation construction area by adopting the dewatering wells, and performing dewatering construction on the stratum by adopting a water suction pump;
b. side lines are excavated along the periphery of a designed foundation pit area, double rows of fender piles 7 and single rows of fender piles 8 are sequentially constructed at related design positions of the foundation pit, and cement mortar is formed on the pile positions of the fender piles by adopting a drilling and pouring method to form an independent pile body with a cylindrical or rectangular cross section; hoisting the pile body reinforcement to a pile position, overcoming resistance through a high-frequency vibration hammer and implanting the pile body reinforcement into the formed slurry, splicing the pile body reinforcement through a connecting end, continuously and repeatedly hoisting after splicing, splicing to the bottom of the slurry, and adjusting the plane position and elevation of the pile body reinforcement through a pile top positioning adjusting bolt; then constructing a crown beam 13 on the pile top of the fender pile, and sequentially constructing a retaining wall 15 and a catch basin 14 around the designed excavation position of the foundation pit;
c. sequentially and downwards excavating, and arranging the steel supports 9 among the single row of fender piles 8; then, arranging a prestressed anchoring cable 10 at the position where the double-row fender post 7 is constructed on the excavated foundation pit wall; excavating a soil body to a position 3-5m away from the pile bottom of the double-row fender post 7, reserving a part of soil slope, constructing an L-shaped crown beam 17 on the soil slope, and immediately arranging a prestressed anchoring cable 10 after the design strength is reached; and a fence structure is constructed above the L-shaped crown beam 17 and between the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double-row fender piles 7;
d. continuously excavating the soil body downwards, spraying concrete 18 to the soil slope construction hanging net, immediately drilling 2 anchor rods 19, and forming a soil nailing wall reinforcing embedded structure 16 after the design strength is reached;
e. continuously excavating the soil body downwards to the designed height position of the newly-built interval structure 6, and dismantling the existing structure 20 at the designed height position; then constructing a fence structure between the adjacent single fender piles of the single row of fender piles 8;
f. and finally, sequentially completing construction of a structure bottom plate, a side wall and a top plate structure for the main structure of the newly-built interval structure 6 according to a sequential construction method, and effectively connecting the main structure with the existing interval structure to ensure the communication of the whole interval.
In the step c, the construction steps for arranging the steel supports 9 among the single row of fender piles 8 are as follows: excavating a first layer of soil body of the excavated foundation pit until the first layer of soil body is excavated to the bottom elevation of the uppermost group of steel supports 9; then connecting the group of steel supports 9 at the uppermost layer with the crown beams 13 of the single row of fender piles 8; excavating a second layer of soil body of the excavated foundation pit until the second layer of soil body is excavated to the bottom elevation of the group of steel supports 9 with the second height; then connecting the steel support 9 with the single row of fender posts 8 through the wale; and repeating the construction sequence until the group of the steel supports 9 at the lowest layer is connected with the single-row fender piles 8 through the wales.
The construction steps of the enclosure structure are as follows: manually cleaning soil on the surface of the fender pile and soil between any two adjacent fender piles; preparing a plurality of connecting pieces, drilling holes in the cleaned fender post, and placing one end of each connecting piece into the fender post; manufacturing a steel bar mesh with a mesh structure by using a plurality of steel bars, and penetrating the other end of the connector through the steel bar mesh; and laying templates on two sides of the reinforcing mesh, pouring concrete between the templates and the fender post, and removing the templates after the concrete is solidified.
In the step d, soil is continuously excavated downwards, the slope of the soil slope is 1:0.2, and double layers are hung@150X150 reinforcing mesh, spraying C25 concrete 18 with the thickness of 150mm, and immediately drilling 2 anchor rods 19; and e, removing the existing structure 20 by adopting a static force breaking method.
Further, in order to ensure the construction effect, the prestressed anchoring cable 10 comprises an anchoring main body arranged inside the soil layer, an anchoring cable is embedded inside the anchoring main body, and the tail part of the anchoring cable extends out of the soil layer and is connected to a waist beam on the surface of the soil layer; the anchor body is made of cement paste. The anchoring cable is sequentially divided into a tensioning section, a free section and an anchoring section from the tail part to the front end; the free section and the anchoring section are embedded in the anchoring main body; the anchoring cable is a plurality of steel strands, and corrugated pipes wrap the side faces of the steel strands in the free section interval. A plurality of supporting bodies used for supporting the steel strands are arranged in the interval of the anchoring section at intervals, a plurality of notches are formed in the edges of the supporting bodies, and the steel strands are fixed in the notches of the supporting bodies. The support body can prevent the steel strands forming the anchoring cable from being wound together, so that the anchoring cable can keep the shape during installation. The steel strands between any two adjacent support bodies are crossed with each other. The steel strands are mutually crossed, so that the anchoring cable and the anchoring main body are combined more tightly, and the strength of the prestressed anchoring cable is enhanced. The tensioning section sequentially penetrates through the waist beam and the anchor block attached to the surface of the waist beam, the anchoring cable is tensioned through prestress, the tensioning section is fixedly connected with an anchorage device, and the anchorage device is supported on the surface of the anchor block.
The construction method of the prestressed anchoring cable comprises the following steps:
1) providing an anchor cable and a drilling rig;
2) installing the anchor cable inside a hollow drill stem of a drilling rig;
3) using the drilling machine to jet and drill holes in a rotary manner into the soil layer to form anchoring cable holes, injecting cement slurry into the anchoring cable holes through the hollow drill rods in the drilling process of the drilling machine, and enabling the anchoring cables to enter the anchoring cable holes along with the hollow drill rods;
4) after the drilling machine drills to a target depth, the hollow drill rod is drawn out of the anchoring cable hole, and the anchoring cable is left in the anchoring cable hole in the process of drawing out the hollow drill rod;
5) grouting the inside of the anchoring cable hole;
6) tensioning and locking the hawser after the grout in the hawser hole reaches a predetermined strength.
The construction method can be used for simultaneously performing punching, anchor cable installation and grouting. The construction technology of the prestressed anchoring cable can avoid the problem of easy hole collapse caused by the installation of the anchoring cable after the hole is punched, and meanwhile, the construction steps can be reduced, and the time is saved.
The pre-stressed anchoring cable 10 is further provided with an anchoring force real-time monitoring system which comprises a force transducer and a signal transmission system, wherein the force transducer is arranged between the anchor block and the anchorage device, and the force transducer is connected with the signal transmission system. The signal transmission system comprises a main processor, a signal data transmission module and a remote server, wherein the output of the force measuring sensor is connected with the main processor, the main processor is connected with the input of the signal data transmission module, and the output of the signal data transmission module is connected with the remote server. The signal data transmission module is a GPRS wireless data transmission module.
The sensor and the wireless transmission technology are applied to the field of anchor cable anchoring force monitoring, and the real-time monitoring system for the anchoring force of the prestressed anchor cable, which can be remotely monitored, has good safety performance and high measurement precision, is provided.
In addition, in order to achieve better technical effects, the technical solutions in the above embodiments may be combined arbitrarily to meet various requirements of practical applications.
According to the embodiment, under the condition that the subway section is built, the structure of the subway section is improved by adopting an open cut method, the section structure of the transition line section is completed, and conditions are provided for turning back of the subway vehicles; the construction method of the invention provides a safe solution for the pile body with insufficient embedding depth, and the fender post is constructed above the existing interval structure, and the embedding depth of the pile body can not be met due to the existence of the lower structure, even under the condition that the base is positioned below the pile end, the soil body at the pile end is reinforced by adopting a mode of reinforcing the embedding structure by the soil nailing wall, so as to prevent the pile end from generating displacement to cause instability of the foundation pit, and the method can be used for solving the problems similar to the foundation pit.
2. The method has the advantages of simple steps, reasonable design, convenient construction, faster construction progress, good construction effect and lower input construction cost. The foundation pit support structure is optimized, combined measures such as construction pipe well dewatering, prestressed anchoring cables, fender piles, steel supports and soil nailing wall reinforcing embedment are fully utilized for supporting, and safety and reliability of the foundation pit support structure are guaranteed. The invention has high practical value, remarkable social benefit and economic benefit and great popularization and application value.
3. The invention inserts the vertically assembled body reinforcement into the slurry pre-formed into a pile on site, and forms the integral fender pile through the crown beam arranged at the top, thereby replacing the existing fender pile structure. The invention has strong field construction operability and high operation efficiency, can ensure the integrity and construction quality of the structure, reduces the construction cost and has good construction implementation effect.
4. By adopting the technical scheme provided by the invention, the enclosure piles, the reinforcing mesh and the concrete are connected into an integral structure, the poured concrete layer is smoother, the thickness of the concrete layer is easier to control, the enclosure piles are well sealed, the waterproof effect of the whole supporting system is ensured, and meanwhile, the reinforcing mesh is arranged between the enclosure piles and the inner wall of the foundation pit, so that the strength of the supporting structure is enhanced.
The foregoing is directed to preferred embodiments of the present invention, other and further embodiments of the invention may be devised without departing from the basic scope thereof, and the scope thereof is determined by the claims that follow. However, any simple modification, equivalent change and modification of the above embodiments according to the technical essence of the present invention are within the protection scope of the technical solution of the present invention.

Claims (8)

1. A structure for expanding a subway section between a subway mine method-built section is characterized by comprising a newly-built section structure (6) built between an existing left line section structure (4) and an existing right line section structure (5) built by a mine method, wherein the newly-built section structure (6) is a variable-section rectangular structure, the main structure of the newly-built section structure comprises a structure bottom plate, a side wall and a top plate structure, and the newly-built section structure (6) is in a gradual change form along the subway line;
the newly-built interval structure (6) is supported by an irregular foundation pit enclosure system, the foundation pit is expanded by an open cut method, the irregular foundation pit bracing system adopts a combination mode of double rows of fender piles (7), prestressed anchoring cables (10), single rows of fender piles (8) and steel supports (9), and specifically comprises the steps that the left side and the right side of the foundation pit along the subway line trend are respectively braced by the single rows of fender piles (8), the single row of fender posts (8) at the left side and the right side are connected by steel supports (9), two rows of fender posts (7) and prestressed anchoring cables (10) are arranged on the soil body at two ends of the foundation pit along the trend of the subway line for reinforcement, the lower parts of the double rows of fender piles (7) are reinforced by adopting a soil nailing wall reinforcing embedded structure (16), and the upper parts of the double rows of fender piles (7) are provided with crown beams (13);
the number of the single row of fender piles (8) is multiple, a crown beam (13) is arranged above each single row of fender piles (8), and the top ends of the multiple single row of fender piles (8) are fixedly connected with the crown beam (13) into a whole; the steel supports (9) are arranged in parallel from top to bottom, the uppermost steel support (9) is connected with the crown beam (13), and the rest steel supports (9) are connected with the single-row fender post (8) through the waist beam; each group of steel supports (9) is provided with a plurality of steel supports (9) which are arranged in parallel from front to back and are uniformly distributed on the same horizontal plane, and two ends of each steel support (9) are respectively fixed on the inner side wall of the waist beam on the same horizontal plane; the steel support (9) is supported by a plurality of temporary upright columns (11), and the temporary upright columns (11) are fixed on a base (12) of the foundation pit; a retaining wall (15) is arranged at the upper edge of the foundation pit, and a catch drain (14) is arranged on the outer side of the retaining wall (15); an L-shaped crown beam (17) is arranged on a soil slope 3-5m away from the pile bottom of the double-row fender pile (7) at two ends of the foundation pit, and a soil nailing wall reinforcing and embedding structure (16) is arranged at the lower part of the L-shaped crown beam (17).
2. The structure for expanding a section into a transition line section according to a subway mine method built section, which is characterized in that pile bodies of the single-row fender pile (8) and the double-row fender pile (7) are both made of slurry and pile body reinforcing members, the pile body reinforcing members are prefabricated steel members and are provided with connecting ends, the connecting ends are composed of high-strength connecting steel rods and plug-in connectors, and joints of the connecting ends are sealed by epoxy resin; and a crown beam (13) is arranged at the top of the pile body reinforcing piece.
3. A structure of a metro mine construction interval expanded into a transition line section according to claims 1-2, wherein the slurry is cement mortar formed by mixing and mixing pile position undisturbed soil of the fender pile through drilling and pouring and mixing with a curing agent, so as to form an independent pile body with a cylindrical or rectangular cross section.
4. A structure for extension of a metro section according to the subway mine method, as claimed in claim 3, wherein a retaining structure having the same height as the fender is arranged between the single row of fender posts (8) and the adjacent single fender posts of the row of fender posts close to the inner side of the foundation pit in the double row of fender posts (7) and on the surface of the fender posts facing the inner side of the foundation pit, the retaining structure is made of concrete, a reinforcing mesh is arranged in the concrete, and the reinforcing mesh is connected with the fender posts through a plurality of connectors; the connecting piece is a reinforcing steel bar with the diameter of 12-15mm, and the reinforcing mesh is of a reticular structure made of phi 8 round steel with the size of 150mm multiplied by 150 mm.
5. A key technical construction method for expanding a transition line segment structure in a subway mine construction interval according to claims 1-4, characterized by comprising the following steps:
a. constructing a plurality of dewatering wells on the stratum of the designed foundation pit excavation construction area by adopting the dewatering wells, and performing dewatering construction on the stratum by adopting a water suction pump;
b. side lines are excavated along the periphery of a designed foundation pit area, double rows of fender piles (7) and single rows of fender piles (8) are successively constructed at related design positions of the foundation pit, and cement mortar is formed on the pile positions of the fender piles by adopting a drilling and pouring method to form an independent pile body with a cylindrical or rectangular cross section; hoisting the pile body reinforcement to a pile position, overcoming resistance through a high-frequency vibration hammer and implanting the pile body reinforcement into the formed slurry, splicing the pile body reinforcement through a connecting end, continuously and repeatedly hoisting after splicing, splicing to the bottom of the slurry, and adjusting the plane position and elevation of the pile body reinforcement through a pile top positioning adjusting bolt; then constructing a crown beam (13) at the pile top of the fender pile, and sequentially constructing a retaining wall (15) and a catch basin (14) around the designed excavation position of the foundation pit;
c. excavating downwards in sequence, and arranging the steel supports (9) among the single row of fender piles (8); then, arranging a prestressed anchoring cable (10) at the position where the double-row fender post (7) is arranged on the excavated foundation pit wall; excavating a soil body to a position 3-5m away from the pile bottom of the double-row fender pile (7), reserving a part of soil slope, constructing an L-shaped crown beam (17) on the soil slope, and immediately arranging a prestressed anchoring cable 10 after the design strength is reached; and a fence structure is constructed above the L-shaped crown beam (17) and between the adjacent single fender piles of the row of piles close to the inner side of the foundation pit in the double rows of fender piles (7);
d. continuously excavating the soil body downwards, spraying concrete (18) to the soil slope construction hanging net, immediately drilling 2 anchor rods (19), and forming a soil nailing wall reinforcing embedded structure (16) after the design strength is reached;
e. continuously excavating the soil body downwards to the position of the design height of the newly-built interval structure (6), and dismantling the existing structure (20) at the position; then constructing a fence structure between the adjacent single fender piles of the single row of fender piles (8);
f. and finally, sequentially completing construction of the structure bottom plate, the side wall and the top plate structure of the main structure of the newly-built interval structure (6) according to a sequential construction method, and effectively connecting the main structure with the existing interval structure to ensure the communication of the whole interval.
6. The method according to claim 5, characterized in that the step c of arranging the steel struts (9) between the single row of fender posts (8) is carried out by the steps of: excavating a first layer of soil body of the excavated foundation pit until the first layer of soil body is excavated to the bottom elevation of the group of steel supports (9) on the uppermost layer; then connecting the group of steel supports (9) at the uppermost layer with the crown beams (13) of the single row of fender piles (8); excavating a second layer of soil body of the excavated foundation pit until the second layer of soil body is excavated to the bottom elevation of a group of steel supports (9) with the second height; then connecting the steel support (9) with the single row of fender posts (8) through the wale; and repeating the construction sequence until a group of steel supports (9) at the lowest layer are connected with the single-row fender piles (8) through the wale.
7. The method as claimed in claims 5 to 6, wherein the construction steps of the enclosure structure are as follows: manually cleaning soil on the surface of the fender pile and soil between any two adjacent fender piles; preparing a plurality of connecting pieces, drilling holes in the cleaned fender post, and placing one end of each connecting piece into the fender post; manufacturing a steel bar mesh with a mesh structure by using a plurality of steel bars, and penetrating the other end of the connector through the steel bar mesh; and laying templates on two sides of the reinforcing mesh, pouring concrete between the templates and the fender post, and removing the templates after the concrete is solidified.
8. The method of claim 7, wherein in step d, the soil is excavated downwards continuously, the slope of the soil is 1:0.2, and double layers are hung@150X150 reinforcing mesh, spraying C25 concrete (18) with the thickness of 150mm, and then drilling 2 anchor rods (19); and e, removing the existing structure (20) by adopting a static force breaking method.
CN201910871792.2A 2019-09-16 2019-09-16 Structure for expanding subway section in subway mine method construction interval and construction method thereof Pending CN110616740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910871792.2A CN110616740A (en) 2019-09-16 2019-09-16 Structure for expanding subway section in subway mine method construction interval and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910871792.2A CN110616740A (en) 2019-09-16 2019-09-16 Structure for expanding subway section in subway mine method construction interval and construction method thereof

Publications (1)

Publication Number Publication Date
CN110616740A true CN110616740A (en) 2019-12-27

Family

ID=68923369

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910871792.2A Pending CN110616740A (en) 2019-09-16 2019-09-16 Structure for expanding subway section in subway mine method construction interval and construction method thereof

Country Status (1)

Country Link
CN (1) CN110616740A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719563A (en) * 2020-06-24 2020-09-29 中铁第五勘察设计院集团有限公司 Foundation pit supporting structure
CN113006079A (en) * 2021-02-22 2021-06-22 河南省远基岩土工程有限公司 Foundation pit extension support body and foundation pit extension support method
CN114737575A (en) * 2022-05-23 2022-07-12 福州闽龙铁路工程有限公司 Foundation pit extension support body and foundation pit extension support method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612162A (en) * 2014-12-15 2015-05-13 中铁二十局集团第三工程有限公司 Subway station deep foundation pit excavation construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612162A (en) * 2014-12-15 2015-05-13 中铁二十局集团第三工程有限公司 Subway station deep foundation pit excavation construction method

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
何升等: "《地质灾害治理工程施工技术》", 30 September 2018, 成都:西南交通大学出版社 *
孔清华: "《建筑桩基的绿色创新技术》", 30 April 2017, 上海:同济大学出版社 *
李昂等: "已建成地铁区间改成成渡线区间的设计方案研究", 《中国勘察设计》 *
李继业等: "《建设工程施工实用手册》", 30 April 2007, 北京:中国建材工业出版社 *
殷跃平等: "《滑坡防治技术指南》", 30 October 2018, 北京:地质出版社 *
葛世荣: "《卓越采矿工程师教程》", 30 March 2017, 北京:煤炭工业出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719563A (en) * 2020-06-24 2020-09-29 中铁第五勘察设计院集团有限公司 Foundation pit supporting structure
CN113006079A (en) * 2021-02-22 2021-06-22 河南省远基岩土工程有限公司 Foundation pit extension support body and foundation pit extension support method
CN114737575A (en) * 2022-05-23 2022-07-12 福州闽龙铁路工程有限公司 Foundation pit extension support body and foundation pit extension support method

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN105350584B (en) A kind of construction method of anti-float anchor rod
CN202969392U (en) Complex geology deep excavation pit combined support
CN110616740A (en) Structure for expanding subway section in subway mine method construction interval and construction method thereof
CN110924433A (en) Design method of subway foundation pit foot-hanging pile enclosure structure in upper-soft lower-hard rock stratum
CN103306289A (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN106522236A (en) Structure for shoring of foundation trench and construction method
CN111877366A (en) Combined type foundation pit supporting structure and construction method thereof
CN112095656A (en) Tension-compression combined type prestressed anchor cable retaining wall structure
CN113417300B (en) Slope support system and construction method thereof
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN112813984B (en) Deep foundation pit construction method under complex geological condition
CN212506313U (en) Combined foundation pit supporting structure
CN108149691A (en) Face the method for excavation of deep foundation pit of inner city under complicated geological
CN107542094A (en) With the insertion hidden nail Construction method that outer wall of basement structure is combined
CN113202110A (en) Construction method for supporting and protecting finite space railway bridge and culvert prefabricated foundation pit
KR20130073336A (en) Pile structure and construction methods
CN216973441U (en) Circular pile anchor retaining structure
CN206233244U (en) The supporting construction of foundation ditch
CN215562584U (en) Pre-tensioning method prestress anti-floating anchor rod construction node
CN116517595B (en) Soft broken rock mass chamber reinforcing structure and method
CN204000837U (en) A kind of prefabricated diaphragm wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191227

RJ01 Rejection of invention patent application after publication