KR100959947B1 - Roof structure and constructing method thereof giving tension on the ground - Google Patents
Roof structure and constructing method thereof giving tension on the ground Download PDFInfo
- Publication number
- KR100959947B1 KR100959947B1 KR1020100012344A KR20100012344A KR100959947B1 KR 100959947 B1 KR100959947 B1 KR 100959947B1 KR 1020100012344 A KR1020100012344 A KR 1020100012344A KR 20100012344 A KR20100012344 A KR 20100012344A KR 100959947 B1 KR100959947 B1 KR 100959947B1
- Authority
- KR
- South Korea
- Prior art keywords
- tension
- loop
- assembly
- girder
- tension member
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims description 21
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 60
- 239000010959 steel Substances 0.000 claims abstract description 60
- 238000010276 construction Methods 0.000 claims abstract description 31
- 239000004567 concrete Substances 0.000 claims description 20
- 239000002689 soil Substances 0.000 claims description 5
- 230000000149 penetrating effect Effects 0.000 claims 1
- 230000035515 penetration Effects 0.000 claims 1
- 239000011178 precast concrete Substances 0.000 abstract description 2
- 230000015572 biosynthetic process Effects 0.000 abstract 1
- 239000000463 material Substances 0.000 description 20
- 238000009434 installation Methods 0.000 description 8
- 238000009412 basement excavation Methods 0.000 description 6
- 238000009415 formwork Methods 0.000 description 4
- 230000003014 reinforcing effect Effects 0.000 description 4
- 239000000853 adhesive Substances 0.000 description 3
- 230000001070 adhesive effect Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000004891 communication Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/04—Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/005—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Civil Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
본 발명은 루프 구조체에 관한 것으로, 더욱 상세하게는 루프 구조체에 종방향 강성을 확보하여 작은 단면으로도 견실한 영구 구조체를 시공할 수 있고, 인장재를 루프 구조체의 양측 단부에 설치하여 인장재의 설치 및 인장 작업이 용이하도록 한 지상에서 인장력을 부여하는 루프 구조체 및 이 시공 방법에 관한 것이다.
The present invention relates to a loop structure, and more particularly, it is possible to construct a permanent structure secured even in a small cross section by securing longitudinal rigidity in the loop structure, and installing a tension member by installing a tension member at both ends of the loop structure. The present invention relates to a loop structure and a construction method for imparting a tensile force on the ground to facilitate a tensioning operation.
일반적으로, 지중에 구조물을 축조하는 방식으로 개착 및 비개착에 의한 구조물 축조방식이 있다.In general, there is a structure construction method by the attachment and non-attachment in a way to build the structure in the ground.
기존 도로 및 철도 하부를 횡단해서 하수암거나 지하차도, 터널구조물 등을 설치해야 하는 경우 공사에 따른 지장물의 이전이 곤란하거나, 지장물 저촉, 차량 소통 장애 등으로 개착이 불가능하여 비개착공법이 요구되는데, 비개착에 의한 구조물 축조 공법에는 횡단하는 도로나 저장물의 양측으로 작업구 개념의 전진기지와 도달기지가 필수적이며, 대표적인 비개착식 지중구조물 축조공법으로는 함체견인공법과 강관루프공법 등을 들 수 있다.If it is necessary to install sewage rocks, underground roadways, tunnel structures, etc. across existing roads and railroads, it is difficult to transfer obstacles due to construction, or it is impossible to fix them due to obstacles and obstacles in vehicle communication. In the non-adhesive structure construction method, the forward base and the arrival base of the working tool concept are essential on both sides of the crossing road and the stored object, and the representative non-adhesive underground structure construction method includes the pull dog artificial method and the steel pipe loop method. Can be mentioned.
함체견인공법은 함체가 통과할 지중에 미리 600mm내외의 함체지지용 가설용 강관을 전진기지에서 도달기지 방향으로 수평으로 압입 관통시킨 후, 견인할 함체의 반대 측 도달기지로부터 지중을 횡단하여 이어진 다수의 P.C 강선을 현장에서 제작된 함체와 결속한 후, 견인하여 함체내의 내부토사를 제거하고, 이와 같은 견인과 굴착작업을 반복하여 지중에 구조물을 설치하는 공법이다.In the case of the ship prosthesis method, the steel pipes for supporting the housing of about 600mm in advance are horizontally press-fitted in the direction of the reach base from the forward base, and then cross the ground from the reach base on the opposite side of the ship to be towed. After binding the PC steel wire to the ship manufactured in the field, it is towed to remove the internal soil in the box, and the same towing and excavation work is repeated to install the structure in the ground.
그러나, 이러한 공법은 함체 추진시 함체의 추진하중이나 추진함체와 이미 지중에 설치된 가설강관과의 틈에 의해 함체 상부의 도로나 지장물에 침하가 발생할 우려가 있으며, 또한 함체가 미리 제작되어 견인 설치되므로 함체의 규모가 커지게 되면 견인에 제약이 따르게 되고 작업장의 규모가 큰 편이므로 심도가 깊은 지하공간에서의 작업이 곤란한 문제점이 있었다.However, this method may cause settlement of the road or obstacles on the upper part of the enclosure due to the propulsion load of the enclosure or the gap between the propulsion vessel and the temporary steel pipe installed in the underground. Therefore, when the size of the enclosure increases, the traction is restricted and the size of the workplace is large, so it is difficult to work in a deep underground space.
또한, 함체간의 연결부의 처리가 미흡하게 되면 누수 등이 발생할 우려가 있었는 바, 이러한 함체견인공법의 단점 등에 의하여 비개착식 지중구조물 축조공법으로는 강관루프 공법이 많이 적용되고 있는 실정이다.In addition, if the connection between the enclosures is insufficient treatment, there was a risk of leakage, etc. Due to the drawbacks of the hull prosthesis method, the steel pipe loop method is applied as a non-removable underground structure construction method.
종래의 강관루프 공법은 구조물이 형성될 지중에 미리 강관을 순차적으로 압입, 연결하여 강관 루프를 형성하고, 강관루프 안쪽의 내부 토사를 전부 제거하고 구조물을 축조하게 되는데, 굴착 시 발생하는 상부나 측면하중은 횡방향 지지보 및 가설기둥 등의 가설재로 지지된다.In the conventional steel pipe loop method, steel pipe loops are formed by sequentially indenting and connecting steel pipes to the ground where the structure is to be formed, removing all the internal soil inside the steel pipe loop, and constructing the structure. The load is supported by temporary materials such as lateral support beams and temporary columns.
강관루프의 축조과정을 간단히 설명하면, 먼저 전진기지에서 조성할 구체의 크기를 고려하여 구체 외곽면에 600~800mm정도의 가설용 강관을 수평 압입하고 강관 내에 콘크리트를 타설하여 강관 루프를 형성한다.Briefly describing the construction process of the steel pipe loop, considering the size of the sphere to be constructed at the forward base, horizontally press-fit the temporary steel pipe of about 600 ~ 800mm to the outer surface of the sphere and cast the concrete in the steel pipe to form the steel pipe loop.
전진기지로부터 구조물이 축조될 강관루프의 안쪽을 굴착하게 되는데 굴착은 상부하중과 측압에 대한 안전성을 고려하여 강관루프의 상층부위로부터 하향으로 단계별로 굴착이 이루어지게 된다.From the forward base, the inside of the steel pipe loop will be excavated, and the excavation is carried out step by step from the upper part of the steel pipe loop in consideration of the safety of the upper load and the side pressure.
이때, 굴착은 1차로 강관 루프 하면을 3m 내외의 심도로 굴착하게 되는데, 강관루프에 사용된 강관과 강관은 고리형태로 연결되어 있으므로, 강관루프 하면과 측면에 강관과 직각방향으로 H형 강재로 횡방향 지지보를 설치하고 다수의 가설기둥으로 받쳐, 전 구간에 걸쳐 하중을 지지시켜야 한다.At this time, the excavation is primarily to excavate the bottom of the steel pipe loop with a depth of about 3m, since the steel pipe and the steel pipe used in the steel pipe loop are connected in a ring shape, so as to H-shaped steel in the direction perpendicular to the steel pipe on the bottom and side of the steel pipe loop. Transverse support beams should be installed and supported by a number of temporary columns to support the load over the entire section.
다시 말하면, 기존의 강관루프는 강관 측면 중앙부에 한 쌍의 ㄱ자형 고리와 T자형 걸쇠가 부착된 요철의 연결구조로 기 압입된 강관들을 상호 고리형태로 연결하여 시공함으로써 하중에 견디는 역할보다는 강관의 위치 이탈을 방지하기 위한 개념에 불과한 것이다.In other words, the existing steel pipe loop is constructed by connecting the pre-indented steel pipes in an annular connection structure with a pair of L-shaped rings and T-shaped clasps attached to the central part of the steel pipe to bear the load, rather than bearing the load. It is just a concept to prevent deviations.
따라서, 상기 강관루프의 연결부간에 횡방향 강성을 확보할 수 없는 문제점이 있었다. 이에 횡방향 지지보와 보다 많은 개수의 가설기둥이 설치되어야 하며, 지지보만큼 이격되어 구조물이 설치되어야 하므로 가시설의 규모가 커지는 문제점이 있었다.Therefore, there is a problem that can not secure the lateral rigidity between the connecting portion of the steel pipe loop. The lateral support beam and a larger number of temporary columns have to be installed, and the structure has to be installed to be spaced apart as much as the support beam.
이후 2차, 3차로 굴진하면서 이미 설치된 가설기둥을 조심스럽게 하향으로 연장하여 구조물의 설치심도까지 내부의 토사 굴착을 완료한 후, 최종적으로 상부슬래브, 벽체, 및 하부슬래브 등을 위한 철근과 거푸집을 설치하고 콘크리트를 타설하여 지중 축조물의 구조체를 완성한다.After digging into the 2nd and 3rd phases, the installation pillars are carefully extended downward to complete the excavation of the earth and sand to the installation depth of the structure. Finally, the reinforcing bars and formwork for the upper slabs, walls, and lower slabs are finished. Install and pour concrete to complete the structure of underground construction.
이와 같이 축조된 종래의 강관루프 공법은 굴착한 후, 이미 설치된 가설기둥을 설치심도까지 하향으로 연장 설치해야 하는 문제점으로 인해 시공 중 침하의 우려가 높고, 기존에 설치된 가설재와의 저촉문제로 공기가 늦어짐은 물론 공사비가 많이 소요되는 문제점이 있었다.The conventional steel pipe loop method constructed as above is highly susceptible to settlement during construction due to the problem of installing the installed temporary pillar downwardly to the installation depth after excavation, and the air is inferior to the existing installed temporary material. Of course, there was a problem that it takes a lot of construction costs.
이러한 문제점을 해결하기 위하여 별도의 콘크리트 구조체를 시공하지 않고 루프만을 통해 구조체화할 수 있는 기술이 제안되고 있으나, 루프의 크기가 커지고철근과 콘크리트의 사용량이 많아지는 문제점이 있다.In order to solve this problem, a technique that can be structured only through the loop without constructing a separate concrete structure has been proposed, but there is a problem in that the size of the loop is increased and the amount of rebar and concrete is increased.
또한, 강관을 사용하는 비개착 공법은 강관의 종방향 강성은 계산하지 않고 횡방향 강성만 계산하여 구조물의 규격을 정하는데 문제가 있다. 따라서 횡방향 강성을 확보하기 위해서는 강관의 크기를 크게 하거나 시공방법을 가설재로 사용하고 별도의 구조체를 만들어야 하는 문제가 있다. 즉, 현재까지 지중 구조물을 축조하는데 모든 계산은 횡방향만 고려하여 계산하였다.
In addition, the non-adhesive method using the steel pipe has a problem in determining the size of the structure by calculating only the transverse stiffness without calculating the longitudinal stiffness of the steel pipe. Therefore, in order to secure the lateral rigidity, there is a problem in that the size of the steel pipe is increased or the construction method is used as a temporary material and a separate structure must be made. That is, to date, underground structures have been constructed. All calculations have been made considering only the transverse direction.
본 발명은 전술한 바와 같은 문제점을 해결하기 위한 것으로, 강관 조립체의 양측을 인장을 통해 종방향 강성을 확보하여 별도의 콘크리트 구조물을 시공하지 않고 가시설이 아닌 영구적인 루프 구조체를 시공할 수 있는 지상에서 인장력을 부여하는 루프 구조체 및 이 시공 방법를 제공하려는데 목적이 있다.The present invention is to solve the problems as described above, by securing the longitudinal stiffness of both sides of the steel pipe assembly through the ground to the construction of a permanent loop structure rather than the construction of a separate concrete structure without a separate concrete structure It is an object of the present invention to provide a loop structure and a construction method for imparting tensile force.
전술한 바와 같은 목적을 달성하기 위한 본 발명에 따른 지상에서 인장력을 부여하는 루프 구조체는, 다수의 강관이 연쇄적으로 연결되거나 다수의 강관과 연결부재가 연쇄적으로 연결되거나 다수의 콘크리트 박스가 연쇄적으로 연결되어 지중에 일정 형상으로 삽입 설치되는 루프 조립체와; 상기 루프 조립체에 폭방향으로 설치되며 인장력에 의해 상기 루프 조립체를 지지하는 하나 이상의 인장재를 포함하여, 상기 루프 조립체의 안쪽에 콘크리트 구조물없이 도로를 포함하는 시설물을 형성하는 루프 구조체로서, 상기 루프 조립체의 길이방향 양측 중 일측 이상이 지중에서 외부로 돌출되어 돌출부가 형성되고, 상기 루프 조립체의 돌출부에 상기 인장재가 상기 루프 조립체의 폭방향을 따라 설치되는 것을 특징으로 한다.The loop structure for imparting tension in the ground according to the present invention for achieving the object as described above, a plurality of steel pipes are connected in series, or a plurality of steel pipes and connecting members are connected in series or a plurality of concrete boxes are chained A loop assembly which is electrically connected to and inserted into a predetermined shape in the ground; A roof structure installed in the roof assembly in a width direction and including a one or more tension members supporting the loop assembly by a tensile force, the roof structure forming a facility including a road without a concrete structure inside the roof assembly, At least one of both sides in the longitudinal direction protrudes from the ground to the outside to form a protrusion, the tension member is characterized in that the tension member is installed along the width direction of the loop assembly.
본 발명에 의한 지상에서 인장력을 부여하는 루프 구조체 시공 방법은, 다수의 관을 이용하여 지중에 일정 형상의 루프 조립체를 시공하는 제1단계와; 상기 제1단계를 통해 시공된 루프 조립체에 인장재를 설치하여 상기 인장재의 일측 이상에 인장단을 배치하는 제2단계와; 상기 제2단계에서 설치된 상기 인장재의 인장단을 인장하는 제3단계와; 상기 제3단계 이후 상기 루프 조립체 안쪽에 있는 흙을 굴착하고, 굴착된 공간의 바닥부에 기초부를 시공하는 제4단계를 포함하고, 상기 제1단계에서는 상기 루프 조립체의 길이방향 양측 중 일측 이상을 지상으로 돌출시키고, 상기 제2단계에서는 상기 인장재를 상기 루프 조립체의 돌출부에 설치하여 지중의 외부에서 상기 인장재를 인장하도록 하는 것을 특징으로 한다.
According to the present invention, there is provided a loop structure construction method for imparting tensile force on a ground, comprising: a first step of constructing a loop assembly having a predetermined shape in the ground using a plurality of tubes; A second step of disposing a tension member on at least one side of the tension member by installing a tension member in the loop assembly constructed through the first step; A third step of tensioning the tension end of the tension member installed in the second step; And a fourth step of digging soil inside the roof assembly after the third step, and constructing a foundation at the bottom of the excavated space, and in the first step, at least one side of both sides in the longitudinal direction of the roof assembly is provided. Protruding to the ground, the second step is characterized in that the tension member is installed on the protrusion of the loop assembly to tension the tension member from the ground.
본 발명에 의한 지상에서 인장력을 부여하는 루프 구조체 및 이 시공 방법에 의하면, 강관 조립체의 양측 단부에 각각 인장재를 통해 프리스트레스를 부여하여 종방향에 대한 강성을 확보함으로써 강관 조립체의 안에 별도의 콘크리트 구조물을 시공하지 않고 노면만 정리함으로써 도로 등을 구축할 수 있는 영구적인 루프 구조체를 시공할 수 있으므로 시공비용을 절감하고 공기를 단축할 수 있다.According to the roof structure and the construction method for imparting tensile force on the ground according to the present invention, pre-stress is applied to both ends of the steel pipe assembly through tension members to secure rigidity in the longitudinal direction, thereby providing a separate concrete structure in the steel pipe assembly. By arranging only the road surface without construction, it is possible to construct a permanent roof structure that can be used to build roads, thereby reducing construction costs and reducing air.
그리고, 강관 조립체의 양측 단부를 지상으로 돌출시켜 지상에서 인장재를 설치 및 인장재의 인장을 수행하므로 인장재의 설치와 조작이 매우 용이한 효과가 있다.
In addition, since both ends of the steel pipe assembly protrude to the ground, the tension member is installed on the ground, and the tension member is tensioned. Therefore, the tension member may be easily installed and manipulated.
도 1 내지 도 4는 본 발명의 실시예 1에 의한 지상에서 인장력을 부여하는 루프 구조체의 사시도, 정면도, 측면도 및 평면도.
도 5는 본 발명의 실시예 1에 의한 지상에서 인장력을 부여하는 루프 구조체의 변형 예시도.
도 6은 본 발명의 실시예 2에 의한 지상에서 인장력을 부여하는 루프 구조체의 사시도.
도 7과 도 8은 본 발명의 실시예 2에 의한 지상에서 인장력을 부여하는 루프 구조체의 변형 예시도.
도 9는 본 발명의 실시예 3에 의한 지상에서 인장력을 부여하는 루프 구조체의 정면도.1 to 4 are a perspective view, a front view, a side view and a plan view of a loop structure for imparting a tensile force on the ground according to the first embodiment of the present invention.
5 is an exemplary view of a modification of the loop structure to impart a tensile force in the ground according to the first embodiment of the present invention.
Figure 6 is a perspective view of a loop structure for imparting tensile force in the ground according to the second embodiment of the present invention.
7 and 8 are views illustrating a modification of the loop structure for imparting tensile force in the ground according to the second embodiment of the present invention.
Figure 9 is a front view of the loop structure to impart the tensile force in the ground according to the third embodiment of the present invention.
<실시예 1>≪ Example 1 >
도 1 내지 도 4에서 보이는 바와 같이, 본 실시예에 의한 지상에서 인장력을 부여하는 루프 구조체 시공 방법은 다음과 같다.As shown in Figures 1 to 4, the loop structure construction method for imparting a tensile force on the ground according to the present embodiment is as follows.
(S10) 루프 조립체 및 거더 설치.(S10) roof assembly and girder installation.
본 발명에 의한 루프 구조체(100)는 루프 조립체(10)(중공형의 강관(1)들이 서로 연쇄적으로 결합되거나 강관(1)들이 연결부재(2)를 통해 연결되어 이루어지며, 천정부와 좌우 측벽부를 형성하는 구조 또는 아치형 구조로 이루어진 것을 말함)에 종방향 강성을 확보하기 위해 인장재를 적용한 것으로, 루프 조립체(10)를 구성하는 중공형의 강관(1)은 원형, 사각형 등 다양한 형태로 형성될 수 있고, 강관(1) 대신 프리캐스트 콘크리트 박스가 사용될 수도 있으며, 연결부재(2)는 도면에 도시된 것으로 한정되지 않는다.
도면에 도시되지는 않았지만, 강관(1)과 연결부재(2)의 내부에 철근을 종횡방향으로 배근한다.Although not shown in the drawings, the reinforcing bars in the longitudinal direction of the steel pipe (1) and the connecting member (2).
인장재(20,30)는 루프 조립체(10)의 천정부와 양 측벽부에 각각 설치될 수 있으며, 인장재(20,30)를 지상에 설치할 수 있도록 루프 조립체(10)의 양측 단부가 지중에서 외부로 돌출되어 돌출부(10a)가 형성된다. 루프 조립체(10)의 돌출부(10a)의 길이는 인장재(20,30)를 설치할 수 있는 만큼의 길이인 것이므로 구체적인 수치로 한정하지는 않는다.The
루프 조립체(10)의 돌출부(10a)를 지지함과 아울러 인장재(20,30)를 설치하기 위하여 루프 조립체(10)의 안쪽에는 거더(40)가 시공될 수 있다. 거더(40)는 필수적으로 시공되는 것이 아니라 선택적으로 시공될 수 있다. 거더(40)가 선택되는 경우 거더(40)는 루프 조립체(10)의 전구간에 걸쳐 시공되지 않고 루프 조립체(10)의 돌출부(10a)에만 형성된다. 거더(40)는 철근 콘크리트 구조물이거나 강재 구조물일 수 있다. 즉, 루프 조립체(10)의 시공 후 또는 시공 전에 거푸집을 설치하고 상기 거푸집 내부에 철근을 배근한 후 상기 거푸집 내부에 콘크리트를 타설하거나 강재 구조물을 설치함으로써 거더(40)를 시공한다.A
인장재(20,30)의 설치를 위하여 거더(40)(또는 거더(40)와 루프 조립체(10))의 시공시 쉬스관(21,31)을 미리 설치할 수 있다.
In order to install the
(S20) 인장재 설치.(S20) Tension material installation.
인장재(20,30)의 이해를 돕기 위하여 천정부의 인장재를 제1인장재(20), 양 측벽부의 인장재를 제2인장재(30)라 한다.In order to help the understanding of the
제1,2인장재(20,30)는 쉬스관(21,31)의 내부에 인장이 가능하도록 설치될 수 있으며, 거더(40)에 폭방향을 따라 설치되고, 도면에는 1개로 도시되었으나 다수개가 설치될 수도 있고, 강봉, 강선 등이 사용 가능하다.The first and
구체적으로 설명하면, 거더(40)의 시공시 쉬스관(21,31)을 설치하고, 제1,2인장재(20,30)가 거더(40)와 루프 조립체(10)를 통과하는 경우 거더(40)와 루프 조립체(10)의 내부에 쉬스관(21,31)을 설치한다.In detail, when the
쉬스관(21,31)은 다수개가 연쇄적으로 관이음되어 제1,2인장재(20,30)를 설치할 수 있는 공간을 제공한다.Sheath pipe (21, 31) is a plurality of pipes are connected in series to provide a space for installing the first and second tensile material (20, 30).
쉬스관(21,31)의 설치가 완료되면 쉬스관(21,31)의 내부에 제1,2인장재(20,30)를 삽입한다. 제1,2인장재(20,30)는 일직선형으로 설치되거나 루프 조립체(10)의 내부(도로 측)를 향해 볼록하게 설치될 수 있고, 양측 단부 중 일측 이상은 인장단으로 구성되고 나머지는 고정단으로 구성된다(본 발명에서는 일측에는 고정단이 타측에는 인장단이 설치된 것을 예로 들어 설명한다)When the
도면에서는 제1,2인장재(20,30)가 루프 조립체(10)의 내부(도로 측)를 향해 볼록하게 설치되는 것으로 도시되고, 또한, 도면에서는 중앙부가 거더(40)를 관통하고 양측 단부의 고정단과 인장단이 루프 조립체(10)의 강관(1) 또는 연결부재(2)에 설치된 것으로 도시하였으나, 제1,2인장재(20,30)는 거더(40)를 관통하고 양측 단부의 고정단과 인장단이 거더(40)에 설치될 수도 있다.
In the figure, the first and
(S30) 루프 조립체 콘크리트 타설.(S30) roof assembly concrete pour.
루프 조립체(10)를 구성하는 강관(1)과 연결부재(2)의 중공부에 콘크리트(C)를 타설한다. Concrete (C) is poured into the hollow part of the steel pipe (1) and the connecting member (2) constituting the roof assembly (10).
제1,2인장재(20,30)와 무관한 부분의 루프 조립체(10)는 기존과 동일하므로 구체적인 구조와 시공 방법은 생략한다.Since the
(S40) 인장재 인장.(S40) tensile material tension.
(S30) 공정에서 타설한 콘크리트(C)가 양생되면 제1,2인장재(20,30)를 각각 인장한다.When the concrete (C) poured in step (S30) is cured, the first and second
제1,2인장재(20,30)의 인장단은 루프 조립체(10)의 외부 즉 지중이 아니라 외부에 배치되어 있기 때문에 작업자가 루프 조립체(10)의 양측 돌출부(10a)나 지면에서 제1,2인장재(20,30)의 인장단을 인장할 수 있다.Since the tension ends of the first and
제1,2인장재(20,30)가 인장되면 루프 조립체(10)의 천정부와 양 측벽부는 각각 제1,2인장재(20,30)의 설치 형태에 따라 일직선형태인 경우 서로 모이는 방향으로 힘을 받고 곡선형태인 경우 루프 구조체(10)의 외부에 대항하는 버팀력을 발생한다.When the first and
제1,2인장재(20,30)의 인장이 완료되면 인장단을 고정한다. 제1,2인장재(20,30)의 인장과 고정은 공지된 것이므로 구체적인 설명을 생략하여도 당업자라면 충분하게 실시할 수 있다.When the tension of the first and
이러한 방법을 통해 루프 조립체(10)의 천정부와 양 측벽부에 제1,2인장재(20,30)를 설치한다.
In this way, the first and
(S50) 굴착 및 기초부 시공.(S50) excavation and foundation construction.
이상의 공정을 통해 천정부와 양 측벽부를 갖는 루프 조립체(10)와 제1,2인장재(20,30)의 시공이 완료되며, 이하에서는 루프 조립체(10) 내부에 도로 등을 시공하기 위한 작업을 한다.Through the above process, the construction of the
먼저 루프 조립체(10)의 내부에 있는 흙을 굴착하고, 굴착된 공간의 바닥부에 콘크리트를 타설하여 기초부를 시공한다. First, the soil inside the
본 실시예에 의한 루프 구조체(100)는 자체적인 강도가 발현되어 내부에 별도의 콘크리트 박스 구조물이 설치되지 않으며, 지지보 등도 사용되지 않는다.
The
한편, 제1,2인장재(20,30)는 루프 구조체(100)의 종방향 강성을 확보하기 위한 것이며, 본 실시예에서는 루프 구조체(100)의 횡방향 강성도 확보하기 위하여 제3인장재(50)가 적용될 수 있다.Meanwhile, the first and
제3인장재(50)는 제1,2인장재(20,30)와 동일한 제품이며, 루프 조립체(10)를 구성하는 강관(1) 또는 연결부재(2) 또는 미도시된 콘크리트 박스의 내부에 배선되고 양측 단부 즉 고정단과 인장단이 루프 조립체(10)의 외부에 배치된다.The third
제3인장재(50)는 일직선 형태 또는 하부를 향해 볼록하게 설치될 수 있고 쉬스관을 통해 설치될 수 있다.The third
제3인장재(50)는 루프 조립체(10)를 구성하는 모든 강관(1)과 연결부재(2)(또는 콘크리트 박스)의 내부에 적용되거나 다수개가 일정 간격을 두고 설치될 수도 있다.The third
이와 같이 구성된 제1,2인장재(20,30)에 따르면 루프 조립체(10)의 천정부와 양 측벽부에 외력에 대항하는 힘을 발생하여 구조적으로 안정된 루프 구조체(100)가 시공된다.
According to the first and
도 5는 본 실시예에 의한 지상에서 인장력을 부여하는 루프 구조체 시공 방법의 변형 예로서, 도로의 차선이 많은 경우 즉 루프 구조체(100)의 폭이 넓고 높은 연속경간의 경우 효과적인 것이다.5 is a modified example of the construction method of the roof structure for imparting tensile force on the ground according to the present embodiment, and is effective when there are many lanes of the road, that is, when the width of the
즉, 루프 구조체(100)의 폭이 좁은 경우에는 거더(40)에 수직의 지지벽이 필요없지만 차선의 수가 많아 폭이 넓은 경우에는 구조검토를 통해 거더(40)에 하나 이상의 지지벽(41)이 형성된다.That is, when the width of the
이때, 제1인장재(20)는 직선 형태, 하부를 향해 볼록한 형태, 파형으로 설치될 수 있고, 파형으로 설치되는 경우 상부를 향해 볼록한 부분은 거더(40)의 지지벽(41)과 대응된다.
In this case, the
<실시예 2><Example 2>
도 6에서 보이는 바와 같이, 본 실시예에 의한 지상에서 인장력을 부여하는 루프 구조체 시공 방법은, 실시예 1과 비교할 때 거더(40)를 강관(1)과 연결부재(2)의 조립체의 외부에 배치하고 루프 조립체(10)를 제1,2인장재(20,30)에 의해 매달기식으로 지지하는 것이다.As shown in Figure 6, the loop structure construction method for imparting a tensile force on the ground according to the present embodiment, compared to the first embodiment, the
루프 조립체(10)를 시공한 후 또는 시공 전에 거더(40)를 시공하며, 이때, 제1,2인장재(20,30)의 설치를 위하여 쉬스관을 설치하는 것은 실시예 1과 동일하다.After the
제1,2인장재(20,30)는 일직선형이나 루프 조립체(10)의 내부(도로 측)를 향해 볼록하게 설치될 수 있다.The first and
도면에 도시되지는 않았지만, 본 실시예에서도 횡방향 강성의 확보를 위한 제3인장재가 적용될 수 있다.Although not shown in the drawings, the third tensile material for securing the lateral rigidity may also be applied in this embodiment.
실시예 1은 거더(40)가 강관(1)과 연결부재(2)의 내부에 배치되어 루프 조립체(10)의 양측 입출구측의 단면을 점유하게 되므로 그만큼(점유면적만큼) 루프 조립체(10)의 크기를 크게 하여야 하지만, 본 실시예는 거더(40)가 강관(1)과 연결부재(2)의 외부에 배치되어 루프 조립체(10)의 양측 입출구측의 단면을 점유하지 않으므로 루프 조립체(10)의 크기에 변화를 주지 않는다.In the first embodiment, since the
그리고, 제1,2인장재(20.30)가 루프 조립체(10)의 외부에서 이들(1,2)에 외부로 당기는 방향의 힘을 부여함으로써 외력에 대한 버팀력을 확보한다.
In addition, the first and second tension members 20.30 secure the support force against the external force by applying a force in the direction in which the first and second tension members 20.30 are pulled outwardly from the outside of the
도 7은 본 실시예의 변형 예로서, 도로의 차선이 많은 경우 즉 루프 구조체(100)의 폭이 넓고 높은 연속경간의 예를 보인 것이다.FIG. 7 illustrates an example of the case where there are many lanes of a road, that is, a wide and high continuous span of the
폭이 넓은 루프 구조체(100)는 내부에 하나 이상의 지지벽(41)이 시공되고, 제1인장재(20)는 다수개가 설치된다.The
예를 들어 다수의 제1인장재(20)는 중앙부가 거더(40)와 하나 이상의 강관(1)이나 연결부재(2)를 관통하도록 루프 조립체(10)의 내부를 향해 볼록하게 설치되면서 고정단과 인장단이 거더(40)의 외부에 배치된다.For example, the plurality of
다수의 제1인장재(20)는 정면에서 볼 때 일부분이 겹쳐지도록 설치됨으로써 루프 구조체(100)의 천정부의 모든 영역에 종방향 강성을 부여한다.The plurality of
제2인장재(30)는 루프 구조체(100)의 양 측벽부에 상기 양 측벽부의 높이에 맞는 수량이 선택되고, 제1인장재(20)와 동일한 형식으로 설치되며 고정단과 인장단이 거더(40)의 외부에 배치된다.The
도 8은 도 7의 변형예로서, 제1인장재(20)를 하나만 사용한 것이다.FIG. 8 is a modification of FIG. 7, in which only one first
즉, 루프 구조체(100)의 폭이 넓은 경우 다수의 제1인장재(20)를 사용하는 것에 한정되지 않고, 하나의 제1인장재(20)를 파형으로 설치할 수 있다. 이때, 제1인장재(20)의 상부를 향해 볼록한 부분은 지지벽(41)에 대응되는 위치일 수 있다.
That is, when the width of the
<실시예 3><Example 3>
도 9에서 보이는 바와 같이, 본 실시예는, 거더(40)가 루프 조립체(10)를 감싸는 형태이다. 즉, 루프 조립체(10)는 거더(40)의 내부에 배치되는 것이다.As shown in FIG. 9, in this embodiment, the
제1,2인장재(20,30)는 일직선형, 하부를 향해 볼록한 형태 등 다양하게 설치될 수 있고, 또한, 수량도 하나 이상이 적용될 수 있다. 즉, 예를 들어 제1인장재(20)는 도면에서처럼 하나가 파형으로 설치될 수 있고, 다르게는 실시예 2처럼 다수개가 설치될 수도 있는 것이다.The first and
1 : 강관, 2 : 연결부재
10 : 루프 조립체, 20,30,50 : 제1 내지 제3인장재
40 : 거더, 41 : 지지벽1: steel pipe, 2: connecting member
10: loop assembly, 20, 30, 50: first to third tensile material
40: girder, 41: support wall
Claims (11)
상기 루프 조립체에 폭방향으로 설치되며 인장력에 의해 상기 루프 조립체를 지지하는 하나 이상의 인장재(20)와;
상기 루프 조립체의 돌출부의 둘레부에 시공되며 상기 루프 조립체를 지지하는 거더(40)를 포함하여, 상기 루프 조립체의 안쪽에 콘크리트 구조물없이 도로를 포함하는 시설물을 형성하는 루프 구조체로서,
상기 루프 조립체의 길이방향 양측 중 일측 이상에 지중에서 외부로 돌출되는 돌출부(10a)가 형성되고, 상기 인장재(20)는 상기 루프 조립체와 상기 거더에 걸쳐 설치되어 상기 거더를 통해 상기 루프 조립체를 하부에서 받치거나 상기 루프 조립체를 상부에서 매달아 지지하면서 인장하는 것을 특징으로 하는 지상에서 인장력을 부여하는 루프 구조체.A loop assembly 10 in which a plurality of steel pipes are connected in series, a plurality of steel pipes and a connecting member are connected in series, or a plurality of concrete boxes are connected in series, and inserted into a predetermined shape in the ground;
At least one tension member (20) installed in the loop assembly in a width direction and supporting the loop assembly by a tension force;
A roof structure including a girder 40 installed at a periphery of a protrusion of the roof assembly and supporting the roof assembly, the facility including a road without a concrete structure inside the roof assembly,
A protrusion 10a protruding from the ground to the outside is formed on at least one of both sides of the roof assembly in the longitudinal direction, and the tension member 20 is installed across the loop assembly and the girder to lower the loop assembly through the girder. Tensile force on the ground, characterized in that the tensioning or supporting the loop assembly suspended from the top.
상기 제1단계를 통해 시공된 루프 조립체에 인장재를 설치하여 상기 인장재의 일측 단부 이상에 인장단을 배치하는 제2단계와;
상기 제2단계에서 설치된 상기 인장재의 인장단을 인장하는 제3단계와;
상기 제3단계에 의해 인장재의 인장이 완료되면 상기 루프 조립체 안쪽에 있는 흙을 굴착하고, 굴착된 공간의 바닥부에 기초부를 시공하는 제4단계를 포함하고,
상기 제1단계에서는 상기 루프 조립체의 길이방향 양측 중 일측 이상의 단부를 지상으로 돌출시켜 돌출부(10a)를 형성하고,
상기 제2단계에서는 상기 인장재를 상기 루프 조립의 돌출부에 설치하여 지상에서 상기 인장재를 인장하는 것을 특징으로 하는 지상에서 인장력을 부여하는 루프 구조체 시공 방법.A first step in which a plurality of steel pipes are connected in series, a plurality of steel pipes and a connecting member are connected in series, or a plurality of concrete boxes are connected in series to construct a loop assembly having a predetermined shape;
A second step of disposing a tensile end in at least one end of the tension member by installing a tension member in the loop assembly constructed through the first step;
A third step of tensioning the tension end of the tension member installed in the second step;
Comprising a fourth step of excavating the soil in the inside of the loop assembly when the tension of the tension member is completed by the third step, and constructing the foundation on the bottom of the excavated space,
In the first step, the protrusion 10a is formed by protruding one or more end portions of both sides of the roof assembly in the longitudinal direction to the ground.
In the second step, the construction of the loop structure to impart a tensile force on the ground, characterized in that the tension member is installed on the protrusion of the loop assembly to tension the tension member on the ground.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100012344A KR100959947B1 (en) | 2010-02-10 | 2010-02-10 | Roof structure and constructing method thereof giving tension on the ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100012344A KR100959947B1 (en) | 2010-02-10 | 2010-02-10 | Roof structure and constructing method thereof giving tension on the ground |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100959947B1 true KR100959947B1 (en) | 2010-05-26 |
Family
ID=42282113
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100012344A KR100959947B1 (en) | 2010-02-10 | 2010-02-10 | Roof structure and constructing method thereof giving tension on the ground |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100959947B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101792135B1 (en) | 2017-05-10 | 2017-11-07 | 김동수 | Bridge span expansion method of non-excavation type |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57100231A (en) | 1980-12-11 | 1982-06-22 | Nippon Keemoo Koji Kk | Construction of underground concrete structure |
JPH08270375A (en) * | 1995-03-31 | 1996-10-15 | East Japan Railway Co | Drilling method under railway line |
KR100904857B1 (en) | 2007-12-20 | 2009-06-25 | 유필수 | A constructing method of underground structure using steel pipe and segment |
KR20090092990A (en) * | 2008-02-28 | 2009-09-02 | 연세대학교 산학협력단 | Construction method for underground structure using prestressed beam and development structure, saddle used in the same |
-
2010
- 2010-02-10 KR KR1020100012344A patent/KR100959947B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57100231A (en) | 1980-12-11 | 1982-06-22 | Nippon Keemoo Koji Kk | Construction of underground concrete structure |
JPH08270375A (en) * | 1995-03-31 | 1996-10-15 | East Japan Railway Co | Drilling method under railway line |
KR100904857B1 (en) | 2007-12-20 | 2009-06-25 | 유필수 | A constructing method of underground structure using steel pipe and segment |
KR20090092990A (en) * | 2008-02-28 | 2009-09-02 | 연세대학교 산학협력단 | Construction method for underground structure using prestressed beam and development structure, saddle used in the same |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101792135B1 (en) | 2017-05-10 | 2017-11-07 | 김동수 | Bridge span expansion method of non-excavation type |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102337785B1 (en) | Wire structure for staggered lapping in slurry wall and construction method using the same | |
JP2017089104A (en) | Structure and method for constructing tunnel lining body | |
KR100712593B1 (en) | Construction method of pipe roof structures | |
KR100562158B1 (en) | Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor | |
KR100569703B1 (en) | Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof | |
KR20060097891A (en) | Pipe roof structures and construction method of pipe roof structures | |
KR101329443B1 (en) | Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning | |
CN110777802A (en) | Deep foundation pit high-low span supporting structure and construction method thereof | |
KR102149473B1 (en) | Prestressing using PC steel wire apply Construction method of underground non-adhesive steel composite concrete tunnel | |
KR100986312B1 (en) | Apparatus for guiding the driving force of steel pipe loop structure | |
KR100987948B1 (en) | Construction method for underground structure using prestressed beam and development structure, saddle used in the same | |
KR100806867B1 (en) | Steel pipe roof assembly and the construction method for Tunnel using thereof | |
KR100784201B1 (en) | Method for construction of tunnel | |
KR100959947B1 (en) | Roof structure and constructing method thereof giving tension on the ground | |
KR100959946B1 (en) | Constructing method of loop structure by tension force and loop structure constructed by this | |
KR200385542Y1 (en) | Pipe roof structures | |
KR100813910B1 (en) | Pipe roof structure | |
KR101057003B1 (en) | Post Tension Tunnel Method | |
KR200354467Y1 (en) | Steel pipe roof structure for building underground structure | |
KR102310091B1 (en) | Underground structure installation method that does not require the installation of temporary pillars | |
KR101249660B1 (en) | Earth pressure supporting method of walls trench applying construction of none- excavation underground structure | |
KR101297679B1 (en) | Self-supporting Temporary Structure Using Steel Wire And Method Of The Same | |
KR101627658B1 (en) | Pile beam with shear-keys and Construction method of mixed bridge using Piled beams with shear-key | |
JP2005002671A (en) | Underpinning method and viaduct | |
KR101106799B1 (en) | Construction method of Top-down concrete slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130516 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20140516 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20150513 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20160503 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20170502 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20180419 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20190429 Year of fee payment: 10 |