KR100685147B1 - Construction method for rc structured high rise building - Google Patents

Construction method for rc structured high rise building Download PDF

Info

Publication number
KR100685147B1
KR100685147B1 KR1020060037927A KR20060037927A KR100685147B1 KR 100685147 B1 KR100685147 B1 KR 100685147B1 KR 1020060037927 A KR1020060037927 A KR 1020060037927A KR 20060037927 A KR20060037927 A KR 20060037927A KR 100685147 B1 KR100685147 B1 KR 100685147B1
Authority
KR
South Korea
Prior art keywords
core
slab
concrete
column
construction
Prior art date
Application number
KR1020060037927A
Other languages
Korean (ko)
Inventor
한봉길
Original Assignee
한봉길
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한봉길 filed Critical 한봉길
Priority to KR1020060037927A priority Critical patent/KR100685147B1/en
Application granted granted Critical
Publication of KR100685147B1 publication Critical patent/KR100685147B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3505Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the in situ moulding of large parts of a structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/38Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for plane ceilings of concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A construction method for a reinforced concrete(RC)-structured high rise building is provided to improve quality of a column, a slab, a core, and a stairs structure and reducing the construction cost, while planning reduced construction term and safe work. A construction method for a reinforced concrete(RC)-structured high rise building comprises first through sixth steps. In the first step, a column and a slab(1) are divided into 2~4 sections, a reinforced rod column is arranged and a column system form(15) is installed in a first section, and column concrete is cured. The second step disjoints the column system form after curing the column concrete and transfers the column system form, and installs a slab system form. The third step arranges a slab reinforced rod in the slab system form, and installs electric pipes and facilities. The fourth step casts and cures the concrete in the slab system form. The first through the fourth steps are sequentially performed, thereby forming one layer of the column and slab. The fifth step constructs a core(5) from a lower layer of the slab. The sixth step constructs core stairs(17) from a lower layer of the core.

Description

철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법{Construction method for RC structured high rise building}Construction method for RC structured high rise building with reinforced concrete structure

도 1은 본 발명에 의한 철근콘크리트 구조를 갖는 고층 건축구조물의 구역 분할 및 시공 순서를 설명하기 위한 평면구성도이고,1 is a plan view for explaining the division and construction sequence of a high-rise building structure having a reinforced concrete structure according to the present invention,

도 2 내지 도 5는 본 발명에 의한 기둥 및 슬래브, 코어 및 계단의 시공 단계를 설명하는 단면구성도이며,2 to 5 is a cross-sectional view illustrating the construction step of the pillar and slab, core and stairs according to the present invention,

도 6은 본 발명을 이용하여 코어 벽체에 배근되는 수직 철근의 이음 개소 수를 절반으로 줄일 수 있는 철근 가이드 프레임을 설명하는 평면구성도이다.6 is a plan view illustrating a reinforcing bar guide frame capable of reducing the number of jointed points of a vertical reinforcing bar arranged to a core wall by using the present invention.

도 7은 본 발명에 의한 코어 및 코어 계단의 시공 단계를 보여주는 단면구성도이다.7 is a cross-sectional view showing the construction step of the core and the core step according to the present invention.

본 발명은 철근 콘크리트 구조를 이용하여 주거 공간 및 코어가 마련된 초고층 건축구조물을 축조하는 시공방법에 관한 것으로서, 특히 건축구조물을 이루는 기둥 1개층을 적어도 2 내지 4 구역 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량을 감안하여 적절히 분할하여 1차 선행 시공하고, 후속으로 슬래 브 1개 층을 적어도 2 내지 4 구역 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량을 감안하여 적절히 분할하여 2차 선행 시공하고, 이후 코어 골조를 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량에 맞춰 2 내지 3 구역으로 적절하게 분할하여 후행 시공하고 코어 골조가 완료된 하부 층에 최종으로 코어 계단을 순차 후행하여 시공함으로써, 작업의 적절한 분산을 유도하여 결과적으로 공사기간 단축, 원가 절감 및 안전 작업을 유도하면서도, 기둥, 보, 슬래브, 코어 및 계단 구조물의 품질을 향상시킬 수 있도록 한 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법에 관한 것이다.The present invention relates to a construction method for constructing a high-rise building structure provided with a residential space and a core using a reinforced concrete structure, and in particular, an appropriate amount of formwork and reinforcement work per day, such as at least 2 to 4 zones, for one floor of a column constituting the building structure. First preliminary construction by dividing properly in consideration of the appropriate amount of concrete placement per day, and subsequently, one layer of slab is appropriately divided in consideration of the daily mold and reinforcement work amount such as at least 2 to 4 zones and the appropriate amount of concrete placement per day. After the second preliminary construction, the core frame is appropriately divided into 2 to 3 zones according to the daily mold and reinforcement work amount and the concrete casting amount, followed by the subsequent construction, and finally the core stair is sequentially followed on the lower layer where the core frame is completed. By constructing, it induces proper distribution of work and consequently shortens construction time and costs And a method of constructing a high-rise building structure having a reinforced concrete structure capable of improving the quality of columns, beams, slabs, cores, and staircase structures while inducing safety work.

일반적으로 건축구조물은 철근 콘크리트구조(RC구조), 철골 구조(S구조) 및 철골·철근 콘크리트 복합구조(SRC구조)로 축조되며, 이 중 철근 콘크리트 구조는 고강도 콘크리트 제조 및 시공 기술의 발달과 함께 다른 구조에 비해 원가가 비교적 저렴하고 재료 특성상 화재에 유리하고 진동 및 소음 차단성이 유리하다는 이유로 초고층화 대형화되어가는 최근의 건축물에 자주 적용되고 있는 추세이다. 이러한 철근 콘크리트구조 초고층 건축구조물의 주요 구조부재는 일반적으로 엘리베이터, 전기시설, 설비시설 및 계단, 화장실 등 부속 시설이 집중되어있고 벽체로 구성되어 있는 코어와, 주거 공간을 구성하는 기둥 및 보, 슬래브로 요약되며,In general, building structures are constructed of reinforced concrete structures (RC structures), steel structures (S structures) and steel and reinforced concrete composite structures (SRC structures). Among these, reinforced concrete structures are developed with the development of high-strength concrete manufacturing and construction technology. Compared to other structures, the cost is relatively low, the material is favorable to fire, and the vibration and noise blocking property is advantageous, so it is frequently applied to the latest buildings which are becoming very large and large. The main structural members of such reinforced concrete structured high-rise building structures generally include cores composed of walls and pillars, beams, and slabs, which consist of walls, including elevators, electrical facilities, facilities, stairs, and toilets. Are summarized as

이러한 철근 콘크리트 구조를 갖는 건축구조물의 종래의 주된 시공 방법은 첫째, 코어를 선행 시공하고 기둥 및 슬래브를 후속으로 시공하는 코어 선행 시공방법과 둘째, 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법 등 두 가지가 있다.  Conventional main construction methods of building structures having such reinforced concrete structures include first, core prior construction methods for constructing cores in advance and subsequent construction of columns and slabs; and second, simultaneous construction methods for simultaneously constructing cores, columns, and slabs. There are two things.

이러한 철근 콘크리트 구조 시공방법들에 대하여 좀 더 자세히 설명하면, When explaining the reinforced concrete construction methods in more detail,

첫째, 전자의 철근 콘크리트구조를 갖는 건축구조물의 코어 선행 시공방법에서는 코어의 내측 공간 또는 코어의 외측 공간에 타워크레인, 호이스트(hoist), 콘크리트 디스트리뷰터(distributor) 등의 코어공사 전용 시설들을 가설한 다음, 상기 코어공사 전용 시설들을 이용하여 자재 및 인력을 운반하여 철근을 배근하고 후행 슬래브와의 결속을 위해, 상기 코어에 앵커부재를 함께 선 매립 설치하고 시스템 폼을 장착한 후 콘크리트를 타설하여 코어를 선행 축조하게 된다. 이후 기둥을 설치하고(기둥은 슬래브에 선행하여 콘크리트를 타설하는 경우도 있고 슬래브와 동시에 타설하는 경우가 있다.), 슬래브 형틀재 설치와 더불어 상기 코어에 매립된 앵커부재에 슬래브 철근을 연결 배근하고, 콘크리트 타설을 거쳐 슬래브를 축조 시공한다.First, in the core preliminary construction method of the building structure with the former reinforced concrete structure, the facilities for core construction such as tower crane, hoist and concrete distributor are installed in the inner space of the core or the outer space of the core. In order to reinforce the reinforcing bar by carrying materials and manpower by using the dedicated facilities for core construction and to bond with a trailing slab, the cores are installed by pre-installing anchor members on the cores, installing system foam, and then placing concrete cores. Pre-construction is done. Later, the column is installed (the column may be placed before the slab, and the concrete may be poured simultaneously with the slab), and the slab reinforcement is connected to the anchor member embedded in the core together with the slab frame member. The concrete slab is then constructed and poured.

상술한 코어 선행 공법은 작업량이 상대적으로 많은 코어 부위를 선행시킴으로써 독립적으로 운영하여 공사기간을 단축하고, 시스템 폼을 사용하여 양중 부하를 저감시킴으로써 초고층 건축물의 축조에 많이 이용되고 있다.The above-described core preceding method is used in the construction of high-rise buildings by operating independently by reducing the amount of load by using a system form to operate independently by preceding the core portion having a relatively high workload.

둘째, 후자의 철근 콘크리트구조를 갖는 건축구조물의 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법은 상기 첫 번째 공법과는 달리 코어와 기둥 및 슬래브를 동시에 시공함으로써 상기 코어 선행에 따른 코어공사 전용 시설 배치가 필요 없고 또한 코어 벽체에 앵커부재의 사전 매립도 필요 없고 적정 품질 유지 및 안전관리에 비교적 유리하고 원가 부담이 크지 않은 장점이 있고 가장 보편화된 공법이다.Second, in the simultaneous construction method for simultaneously constructing the core, the pillar, and the slab of the building structure having the latter reinforced concrete structure, unlike the first construction method, the core, pillar, and slab are constructed at the same time. It does not need to be laid out and also does not require the pre-embedding of anchor members in the core wall, it is relatively advantageous in maintaining proper quality and safety management, and it is the most cost-effective method.

상술한 종래의 두 가지 공법 중에서,Of the two conventional methods described above,

첫째, 전자의 철근 콘크리트구조를 갖는 건축구조물의 코어 선행 시공방법은 코어의 형틀 작업 및 철근 배근, 콘크리트 타설을 위한 타워크레인, 호이스트 및 콘크리트 디스트리뷰터 등의 코어공사 전용 시설을 가설해야 하고, 또한 코어가 먼저 선행하는 관계로 코어의 높이에 의해 타워크레인 운행 간섭현상에 의해 부득이 적정 대수 이상의 타워크레인을 배치해야하는 문제점이 발생하고, 후속으로 시공되는 슬래브 중 상기 코어공사 전용 시설로 인한 간섭구간은 철근 배근 및 콘크리트 타설을 보류하고 코어공사 전용 시설 철거 후 타설해야 하므로 작업 공정이 복잡하고 안전관리의 어려움 및 비용이 많이 드는 문제점이 있다.First, the core preliminary construction method of the building structure with the former reinforced concrete structure requires the construction of core formwork and reinforcement, core crane dedicated facilities such as tower crane for concrete placing, hoist and concrete distributor. First of all, there is a problem that tower cranes must be arranged more than the proper number due to the interference of tower crane operation due to the height of the core, and the interference section due to the core construction facility among the slabs that are subsequently constructed is reinforced with reinforcement bars and The concrete work process is complicated and the safety management is difficult and costly because it is necessary to withhold concrete pouring and dismantle the core construction facility.

또한 선행되는 코어는 후행하는 주거구간에 해당하는 슬래브보다 면적이 좁을 뿐 만 아니라 코어와 슬래브의 높이 차이에 의해 초고층 건축구조물의 핵심이라고 할 수 있는 엘리베이터 샤프트의 수직도 관리에 어려움이 많고, 코어와 슬래브의 콘크리트를 분리하여 타설해야 하므로 코어와 슬래브를 연결해주는 철근을 벽체에 사전 매립해야 함으로써 추가비용발생 및 분리 타설로 인한 접합부 품질이 저하되는 문제점이 있다.In addition, the preceding core is not only narrower than the slab corresponding to the following residential section, but also has difficulty in managing the verticality of the elevator shaft, which is the core of the high-rise building structure by the height difference between the core and the slab. Since the concrete of the slab must be separated and poured, the reinforcing bar connecting the core and the slab must be buried in the wall, causing additional cost and deterioration of the joint quality due to the separate casting.

또한 코어 선행을 위해서는 코어 벽체 형틀 공사용 시스템 폼을 장착하게 되는데 벽체 두께는 보통 높이 올라갈수록 벽체 두께가 얇아지는 것이 정상인데 반하여 코어 벽체 두께 변화에 따른 코어 벽체 형틀 공사용 시스템 폼을 수정하기가 어려워 코어 벽체를 저층부부터 고층부까지 일정한 두께를 유지하는 경향으로 인해 콘크리트 재료가 일반 공법에 비해 많이 들어가는 문제점이 있다. In addition, the core wall formwork system foam is installed to advance the core.While the wall thickness is usually higher, the wall thickness becomes thinner, whereas it is difficult to modify the core wall formwork system form due to the change of core wall thickness. Due to the tendency to maintain a constant thickness from the low floor to the high floor, there is a problem that a lot of concrete materials compared to the general method.

또한 코어와 슬래브 층의 작업이 상, 하간 떨어져 있어 안전 관리가 어렵고, 특히 선행하는 좁은 코어 공간 주위에서 다양한 공종이 동시에 작업이 이루어져야 하므로 혼잡하고, 작업 능률이 저하되며, 이로 인한 공정 관리의 어려움이 있다.In addition, the work of the core and slab layers is separated from the top and bottom, making it difficult to manage safety. In particular, various types of work must be performed simultaneously in the vicinity of the preceding narrow core space, resulting in congestion and reduced work efficiency. have.

둘째, 후자의 철근 콘크리트구조를 갖는 건축구조물의 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법은 첫 번째 공법과는 달리 코어와 기둥 및 슬래브를 동시에 시공함으로써 상기 코어 선행에 따른 코어공사 전용 시설 배치가 필요 없고 또한 코어 벽체에 앵커부재의 사전 매립도 필요 없고 적정 품질 유지 및 안전관리에 비교적 유리하고 원가 부담이 크지 않은 장점이 있는 가장 보편화된 공법이지만 코어와 기둥 및 슬래브가 동시에 작업이 집중 진행됨으로써 작업자들의 작업 공간 확보의 어려움이 발생하여 결과적으로 작업자들의 작업 공백 기간이 발생하여 공사기간 단축에는 한계가 있다는 것이 문제점이다.Second, in the simultaneous construction method for simultaneously constructing the core, column and slab of the building structure having the latter reinforced concrete structure, unlike the first construction method, the core, pillar and slab are constructed at the same time so that the core construction dedicated facility according to the core precedence is arranged. It is the most common method that does not need to be installed in the core wall, and does not need to pre-install anchor member in the core wall, and it is relatively advantageous in maintaining proper quality and safety management, and it does not have much cost burden, but the core, column, and slab work at the same time. The difficulty of securing the working space of the workers occurs as a result of the work gap of the workers occurs as a result there is a limit to shorten the construction period.

이와 같은 종래 기술의 문제점을 해결하기 위한 것으로서, 본 발명은 다른 구조에 비해 원가가 비교적 저렴하고 재료 특성상 화재에 유리하며 진동 및 소음 차단성이 좋은 철근콘크리트 구조를 이용하여 초고층 건축구조물을 시공하되, 건축구조물의 기둥을 적어도 2구역 내지 4개 구역 등 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량으로 적절히 분할하여 1차 선행하고, 후속으로 슬래브 1개 층을 적어도 2구역 내지 4개 구역 등 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량으로 적절히 분할하여 2차 선행하고, 이후 코어 골조를 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량에 맞춰 2 내지 3 구역으로 적절하게 분할하 여 후행 시공하고 코어 골조가 완료된 하부층에 최종으로 코어 계단을 순차 후행하여 시공함으로써, 작업의 적절한 분산을 유도하여 결과적으로 공사기간 단축 및 안전 작업을 유도하면서도, 기둥, 슬래브, 코어 및 계단 구조물의 품질을 더욱 향상시키고 원가절감을 도모함에 그 목적을 두고 있다.In order to solve the problems of the prior art, the present invention is a relatively low cost compared to other structures and advantageous to fire due to the characteristics of the material, the construction of ultra high-rise building structure using a reinforced concrete structure having good vibration and noise blocking properties, The pillars of the building structure are firstly divided into appropriate sections for at least 2 to 4 zones per day and appropriate for reinforcing work for steel and reinforcing concrete, followed by 1st slab layer for at least 2 to 4 zones. Secondly, the core frame is appropriately divided into the appropriate amount of mold and reinforcement work and concrete pouring, and then the core frame is appropriately divided into 2 to 3 zones according to the daily mold and reinforcement amount and concrete pouring amount. By laying the core staircase in order to finally complete the lower layer, It aims to further improve the quality of columns, slabs, cores and staircases and to reduce costs, while inducing proper dispersion and consequently shortening construction period and safety work.

이하, 본 발명의 바람직한 실시 형태를 첨부 도면에 의거하여 설명하기로 한다.EMBODIMENT OF THE INVENTION Hereinafter, preferred embodiment of this invention is described based on an accompanying drawing.

본 발명은 철근 콘크리트 구조를 이용하여 초고층 건축구조물을 시공하는 것을 기본으로 하고 있으며, 종래의 철근 콘크리트구조를 갖는 건축구조물의 코어 선행 시공방법 및 철근 콘크리트구조를 갖는 건축구조물의 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법과 달리, 기둥을 1차 선행하여 시공하고 슬래브를 2차 선행시키고, 이후로 코어 및 코어 계단의 순으로 순차 후행하여 건축구조물을 축조함을 특징으로 한다.The present invention is based on the construction of a high-rise building structure using a reinforced concrete structure, the core prior construction method of the building structure having a conventional reinforced concrete structure and the core, column and slab of the building structure having a reinforced concrete structure Unlike the simultaneous construction method of constructing at the same time, it is characterized by constructing the building structure by constructing the pillar first and the slab second, and then successively following the core and the core stairs in order.

도 1은 본 발명에 의한 철근콘크리트 구조를 갖는 고층 건축구조물의 구역 분할 및 시공 순서를 설명하기 위한 평면구성도로서,1 is a plan view for explaining the division and construction sequence of a high-rise building structure having a reinforced concrete structure according to the present invention,

도시한 바와 같이, 본 발명에서는 주거 구간의 기둥과 슬래브(1)의 1개 층을 시공이음(2)(4)를 이용하여 적어도 4구역 (가), (나), (다), (라) 또는 2구역 (가나), (다라) 등으로 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량에 맞춰 적절히 나누어 순연하면서 순차적으로 시공한다. 여기에서 시공이음이란 1일 콘크리트 타설량이 너무 많아 당일 안에 콘크리트를 타설 완료하기 불가하거나 공 사 현장의 예기치 못한 상황의 발생으로 인하여 부득이 콘크리트를 끊어쳐야 할 필요성이 있을 때 적정한 위치에 목재나 철재, 플라스틱 등의 재료를 이용하여 콘크리트 타설시 콘크리트가 새어나가지 않도록 구간을 분할, 구획하여 콘크리트를 타설토록 하는 임시 구획선을 의미한다. As shown, in the present invention, one floor of the pillar and the slab 1 of the residential section is constructed using at least four zones (A), (B), (C) and (D) using construction joints (2) and (4). ) Or 2 zones (Ghana), (Dara), etc., suitable for one-day mold and reinforcement work and one-day concrete placing appropriately, neatly divided and constructed sequentially. Here, construction joints are made of wood, steel, plastic in the right place when there is too much concrete to place in one day and it is impossible to finish the concrete within the same day or when it is necessary to break concrete due to the unexpected situation of the construction site. It refers to a temporary partition line that allows concrete to be poured by dividing and dividing sections so that concrete does not leak out when concrete is poured using materials such as concrete.

슬래브(1)의 각 구역은 공정별 1일 작업량을 감안하여 평면적으로 설정한 것이고, 구역을 분할하여 순차 시공하는 것은 융통성을 부여하고 연속적인 되풀이 작업을 유도하여 적정한 공기 단축을 실현하기 위한 것이다.Each zone of the slab 1 is set in plan in consideration of the daily work volume per process, and the division of the zones in order to construct them in order to provide flexibility and induce continuous repetitive work to realize proper air shortening.

이러한 슬래브(1)의 구역별 순차 시공 및 되풀이 작업을 실현하기 위해서는 기본적으로 기둥이나 슬래브가 가급적 단순한 구조로 설계되어야 하고 적절한 시스템 폼으로 계획되어야 한다. 기둥이나 슬래브의 시스템 폼은 잘 알려진 사항이므로 부연 설명을 생략하기로 한다.In order to realize the sequential construction and repetitive work of each section of the slab 1, the column or the slab should be basically designed as simple as possible and planned in a proper system form. The system form of the column or slab is well known and will be omitted.

구역별 시공 방법은 도 2 내지 도 5를 통하여 잘 표시되고 있다.The construction method for each zone is well represented through FIGS. 2 to 5.

여기서 슬래브(1)의 1개 층은 (가), (나), (다), (라) 구역으로 나눌 수 있으며, 코어(5)는 시공이음(2)(3)을 적절히 이용하여 CORE A, CORE B 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량에 맞춰 적절히 나누어 2 내지 3 개 구역으로 나눌 수 있으며 슬래브(1)의 한층 아래에서 후행되고, 코어 계단(17)은 더욱 한층 아래에서 후행한다. Here, one layer of slab (1) can be divided into (A), (B), (C) and (D) zones, and the core (5) can be divided into CORE A using the joint (2) (3) as appropriate. , CORE B, etc., can be divided into 2 to 3 zones according to the proper amount of work and reinforcement for the daily work and reinforcement of concrete, and the trailing of the slab 1 is followed by one step, and the core stair 17 is further down. Trailing in

도 2는 1일 차의 시공이다. 도면을 통하여 알 수 있는 바와 같이, (가) 구역에서는 기둥철근(6)을 배근하고 기둥 시스템 폼을 설치하며, 이어서 기둥 콘크리트(7)를 타설한다.2 shows the construction of the first day. As can be seen from the figure, in section (a), the column reinforcement 6 is reinforced, the column system foam is installed, and the column concrete 7 is then poured.

도 3은 2일 차의 시공 단계이다. 도면을 통하여 알 수 있는 바와 같이, (가) 구역에서는 기둥 시스템 폼을 해체하고, 이것을 (나) 구역으로 이동하며 상기 1일차 공정을 (나) 구역에 시공한다.3 is a construction step of the second day. As can be seen from the figure, in section (a), the column system foam is dismantled, moved to section (b) and the first day process is installed in section (b).

이때 (가) 구역에서는 슬래브 시스템 폼(13)을 인양, 설치한다.In this section (a), the slab system foam 13 is lifted and installed.

도 4는 3일 차의 시공 단계이다. 도면에서와 같이, (나) 구역의 기둥 시스템 폼은 다시 해체되어 (다) 구역으로 이동하며, 이어서 슬래브 시스템 폼(13)을 인양하여 (나) 구역에 설치하는 2일차의 공정이 이루어진다. (다) 구역에서는 상기 1일 차의 공정을 시공하게 된다.4 is a construction step of the third day. As shown in the figure, the column system foam of zone (B) is dismantled and moved to zone (C), followed by a second day process of lifting and installing the slab system form 13 in zone (B). In section (c), the first-day process will be constructed.

이때 (가) 구역에서는 슬래브철근(12)을 배근하고, 이와 동시에 전기나 설비 배관을 설치한다. At this time, in the area (A), the slab reinforcing bars 12 are disposed and at the same time, electricity or facility piping is installed.

도 5는 4일 차의 시공 단계이다. 도면에서와 같이, (다) 구역의 기둥 시스템폼은 다시 해체되어 (라) 구역으로 이동하며 여기에 상기 1일 차의 공정을 시공하게 된다.5 is a construction step of the fourth day. As shown in the drawing, the column system form of the (C) zone is dismantled and moved to the (D) zone, where the construction of the first day is performed.

또 (다) 구역에서는 슬래브 시스템 폼(13)을 인양하여 2일 차의 공정을 시공한다. (나) 구역에서는 슬래브철근(12)을 배근하고, 이와 동시에 전기나 설비 배관하여 3일 차의 공정을 설치한다.In section (c), the slab system foam 13 is lifted and the second day of construction is performed. In (B), slab reinforcing bars 12 are installed, and at the same time, a three-day process is installed by electricity or facility piping.

또한 (가) 구역에서는 슬래브 테이블 시스템 폼(13)에 슬래브 콘크리트(8)를 타설하여 양생 단계에 도달하여 슬래브(1) 1개 층을 완성하게 되며, 여기에 다시 1일 차의 공정을 반복하기 위하여 기둥, 벽 등의 먹매김 작업을 실시한다. In addition, in (A), slab concrete (8) is poured into the slab table system form (13) to reach the curing stage to complete one floor of the slab (1), where the process of day 1 is repeated again. In order to do this, it is necessary to fill the columns and walls.

이상에서 설명한 4일 차의 공정에 의해 본 발명에서는 1개 층의 슬래브(1)를 완성하게 되는 것이며, 이러한 공정은 작업량을 고려한 구역 분할과 각 공정의 연속된 순차 진행에 의해 이루어지며, 상기 공정의 반복에 의해 상부 층의 슬래브(1)를 축조하게 되는 것이다.In the present invention, the slab 1 of one layer is completed in the present invention by the above-described four-day process, and this process is performed by zoning in consideration of the workload and continuous sequential progress of each process. By repeating, the slab 1 of the upper layer is constructed.

한편, 본 발명에서는 기둥 및 슬래브를 구역별로 시공하는 다른 예로서, 기둥 및 슬래브 구간을 (가나), (다라) 등의 2 구역으로 분할하여 시공할 수 있으며, 각 구역별 시공 단계는 앞서 설명한 바와 동일하므로 부연 설명을 생략한다.Meanwhile, in the present invention, as another example of constructing the pillars and the slabs by zones, the pillars and the slab sections may be divided into two zones, such as (Ghana) and (Dara), and the construction steps for each zone are as described above. The description is omitted since it is the same.

이렇게 기둥 및 슬래브가 1차 선행 시공됨으로써 보다 복잡한 후속 코어 및 계단 공사를 수행하기 위한 비교적 넓은 바닥이 먼저 제공됨에 따라 코어 작업자들의 안전하고 다양한 현장 접근을 가능하게 하고, 슬래브와 코어와의 접속을 위한 앵커부재의 생략을 유도하고, 코어 수직도 확보를 위한 측량을 용이하게 하며 더욱이 콘크리트가 타설된 슬래브 층까지 호이스트를 운행시킴으로써 보다 빠른 인력 및 물류의 이동을 가능하게 하여 결과적으로 보다 안전하고도 공기 단축을 가능하게 하고 코어와 슬래브와의 접속부 품질을 높이면서도 원가 절감을 가능하게 하는 것이다.This preliminary pre-installation of the columns and slabs provides a relatively wide floor first for more complex subsequent core and stair constructions, enabling safe and versatile site access for the core workers and for the connection between the slabs and the cores. Induces omission of anchor members, facilitates surveying to ensure core verticality, and also enables hoists to move faster and manpower and logistics by running hoists up to the slab layer where concrete is poured, resulting in safer and shorter air. This enables cost reduction while improving the quality of the core-slab connection.

한편, 코어 및 코어 계단의 시공 단계에 대해 설명을 하면, On the other hand, when explaining the construction stage of the core and core stairs,

코어 및 코어 계단은 슬래브(1)에 후행하여 코어(5)를 시공하고 코어 계단(17)은 더욱 한층 아래에서 후행 시공하게 되는바, 이러한 공정은 앞서 설명한 바와 마찬가지로 시공이음(2)(3)을 적절히 이용하여 CORE A, CORE B 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량에 맞춰 2 내지 3 개 구역으로 분할하여 선행 시공되는 기둥 및 슬래브 구간의 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량과 중복이 되지 않도록 적절히 시차를 두어 결과적으로 골조공사 전체의 균형을 유지함으로써 1일 적정 작업 인원 및 투입 자재, 장비를 평준화하여 공정관리를 원활히 할 수 있도록 함이 핵심이라 할 수 있다.The core and the core stairs are followed by the slab 1 to construct the core 5 and the core stairs 17 to be further downstream from the bottom. This process is similar to the above-described construction joints (2) and (3). Proper amount of work on formwork and reinforcement for column and slab sections that are pre-constructed by dividing into 2 or 3 zones according to the proper amount of work on formwork and reinforcing steel and reinforcement of concrete, such as CORE A and CORE B The key is to equip the proper amount of concrete to avoid overlapping with the proper amount of daily concrete placement, and to maintain the balance of the overall frame construction. .

도 2 내지 도 5에 의거하여 코어 및 코어 계단의 시공 단계에 대해 설명을 하면, Referring to the construction step of the core and core stairs based on Figures 2 to 5,

도 2의 1일 차 시공 단계는, 선행하는 기둥 및 슬래브 구간의 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량과 중복이 되지 않도록 적절히 시차를 둔 바람직한 예로서, CORE A 구간에서는 CORE A 구간에 속한 슬래브 및 벽체에 콘크리트(9)를 타설하고, CORE B 구간에서는 벽체에 철근 가이드 프레임(10)을 이용하여 코어 수직 철근(11) 배근 및 각종 매입 작업을 함과 동시에 내부의 시스템 폼(14)을 인양, 고정하는 단계를 보여 주며 이때 CORE B 구간에 해당하는 슬래브 폼도 병행 설치한다.Day 1 construction step of Figure 2 is a preferred example of properly staggered so as not to overlap with the daily mold and reinforcement work amount and the daily concrete placing amount of the preceding column and slab section, CORE A section in the CORE A section Concrete (9) is poured into the slab and the wall belonging to it, and in the CORE B section, the core vertical reinforcing bar (11) is laid and various embedding work is performed by using the reinforcing bar guide frame (10) on the wall. ) Shows the steps of lifting and fixing, and install slab form corresponding to CORE B section at the same time.

도 3의 2일 차 시공 단계는, CORE A 구간에서는 벽체에 철근 가이드 프레임(10)을 이용하여 코어 수직 철근(11)을 배근함과 동시에 내부의 시스템 폼(14)을 인양, 고정하고 CORE A 구간에 해당하는 슬래브 폼도 병행 설치한다. CORE B 구간에서는 전일에 시행했던 CORE B 구간에 해당하는 슬래브 폼 잔여 작업 및 잔여 철근(11) 배근 및 각종 매입 작업을 진행하고, In the second day construction step of FIG. 3, in the CORE A section, the core vertical reinforcing bars 11 are reinforced using the reinforcing bar guide frame 10 on the wall, and at the same time, the internal system foam 14 is lifted and fixed, and the CORE A The slab foam corresponding to the section is also installed in parallel. In the CORE B section, the slab form remaining work, the remaining reinforcing bars (11), and the various purchases work corresponding to the CORE B section performed on the previous day,

도 4의 3일 차 시공 단계는, CORE A 구간에서는 전일에 시행했던 CORE A 구간에 해당하는 슬래브 폼 잔여 작업 및 잔여 철근(11) 배근 및 각종 매입 작업을 진행하고, CORE B 구간에서는 최종 철근(11) 배근 및 각종 매입 작업의 완료와 함께 건물 형상 및 구조에 맞도록 고안된 시스템 폼(15)을 설치하고 다른 한편에서는 작업자가 취급하기 용이하게 고안된 인력 설치 폼(16)을 설치하여 익일 콘크리트 타설을 위한 각종 검측 작업 및 콘크리트 타설 준비 작업이 이루어진다.In the third day construction step of FIG. 4, in the CORE A section, the slab foam remaining work and the remaining reinforcing bars 11 corresponding to the CORE A section performed on the previous day and the reinforcement and various purchase operations are performed, and in the CORE B section, the final rebar ( 11) With the completion of reinforcement and various purchases, the system form 15 designed for the shape and structure of the building is installed, and on the other hand, the manpower installation form 16 designed for easy handling by the worker is installed for concrete pouring the next day. Various inspection work and concrete preparation work are done for this purpose.

도 5의 4일 차 시공 단계는, CORE A 구간에서는 최종 철근(11) 배근 및 각종 매입 작업의 완료와 함께 건물 형상 및 구조에 맞도록 고안된 시스템 폼(15)을 설치하고 다른 한편에서는 작업자가 취급하기 용이하게 고안된 인력 설치 폼(16)을 설치하여 익일 콘크리트 타설을 위한 각종 검측 작업 및 콘크리트 타설 준비 작업이 이루어지고, CORE B 구간에서는 CORE B 구간에 속한 슬래브 및 벽체에 콘크리트(9)를 타설하게 된다.Day 4 construction step of FIG. 5, in the CORE A section, with the completion of the final reinforcement (11) reinforcement and various purchase operations, install the system form (15) designed to fit the building shape and structure and on the other hand the operator The installation of the manpower installation form 16 designed to facilitate the installation of various inspection work and concrete placement work for the next-day concrete placement, and in the CORE B section to the concrete (9) to the slab and wall belonging to the CORE B section do.

이상에서 설명한 4일 차의 공정에 의해 본 발명에서는 1개 층의 코어(5)를 완성하게 되는 것이며, 이러한 코어 공정은 선행 공정인 기둥 및 슬래브 작업량을 고려하여 구역 분할과 시차 조정을 통하여 각 공정의 연속된 순차 진행을 유도하여 순조로운 상기 공정의 반복에 의해 상부 층의 코어(5)를 축조하게 되는 것이다.In the present invention, the core 5 of one layer is completed in the present invention by the above-described four-day process, and each core process is performed through the division of the zone and the time difference adjustment in consideration of the pillar and slab workload, which are the preceding processes. This leads to successive sequential progression of the core 5 of the top layer by repeating the process smoothly.

한편, 코어 수직 철근(11)은 철근 가이드 프레임(10)을 코어 수직 철근 주위에 설치함으로써 2개 층의 길이로 된 것을 사용할 수 있으며 매 층마다 이음을 하는 것이 아니고 2개 층마다 철근을 지그재그로 절반의 개수만 이음으로써 이음부의 수를 절반으로 축소할 수 있고 구체적인 철근 이음 방법은 기 완성된 슬래브(1)위에서 1개 층 밑에서 후행하여 시공되는 코어(5) 벽체 하부로 내리꽂는 하향작업의 형태를 취하므로 작업자들이 손쉽게 철근 설치작업을 진행할 수 있다. On the other hand, the core vertical reinforcing bar (11) can be used in the length of two layers by installing the reinforcing bar guide frame 10 around the core vertical reinforcing bar, and not reinforcing every layer, but zigzag reinforcing bar every two layers By joining only half, the number of joints can be reduced to half, and the concrete reinforcing method is a type of downward work where the bottom of the core (5) wall is constructed by following one floor above the finished slab (1). This allows workers to easily install rebar.

이 철근 가이드 프레임(10)은 도 6에 도시한 바와 같이 바람직하게는 철재 파이프(20) 및 보강재(21), 인양용 고리(19)로 구성되며, 코어 벽체의 형태 및 코어의 작업 구역 분할에 따라 적절하게 분할, 구획되어 설치되며, 이 철근 가이드 프레임(10)의 운영은 최초 설치 후 공정 진행에 따라 타워크레인을 이용하여 철근 가이드 프레임에 장착되어 있는 인양용 고리(19)에 인양줄을 걸어 순차적으로 인양해주기만 하면 철근에 형성되어 있는 홈에 의해 철근 가이드 프레임(10)이 밑으로 흘러내리지 않으므로 별도로 고정해 줄 필요가 없고, 아울러 이 가이드 프레임의 보강을 위한 보강재(21)를 적절한 위치에 배치함으로써 코어 벽체 내, 외부의 시스템 폼 결합을 위한 긴결재의 위치에 철근이 배치되지 않도록 할 수 있으면서도 철근의 위치 및 수직도를 사전에 제어할 수 있으며, 이러한 일련의 작업을 통해 결과적으로 원가 및 공기를 단축할 수 있는 것이다.  This rebar guide frame 10 is preferably composed of a steel pipe 20, a reinforcing material 21, a lifting ring 19, as shown in Figure 6, to form the core wall and to divide the work zone of the core According to the progress of the process after the initial installation, the reinforcement hooks are mounted on the lifting hooks 19 mounted on the reinforcing bar guide frame using the tower crane according to the process after the initial installation. Since the rebar guide frame 10 does not flow down by the grooves formed in the reinforcing bars just by lifting sequentially, there is no need to fix them separately, and the reinforcing material 21 for reinforcing the guide frame is appropriately positioned. By placing them, the position and verticality of the reinforcing bars can be pre-set while preventing the reinforcing bars from being placed in the position of the binding material for joining the system foam in and out of the core wall. It can, and will, which can result in reduced costs and air through a series of these operations.

또한 도 7에서 도시한 것처럼, 코어(5)에 순차 후행하여 코어 계단(17)을 시공한다. 코어 계단(17)은 시스템 폼(14)(15)을 이용하여 벽체 구조가 이미 선행 시공 완료된 상태에서 재래식 폼을 이용하여 코어(5)의 1개 층 아래에서 후행하게 함으로써 수직 벽체와의 접합 등의 복잡한 형틀공사를 단순 작업으로 유도할 수 있다. 바람직하게는 계단 구조를 1방향 슬래브 구조로 단순화하여 계단을 코어 벽체와 일체화하기 위한 벽체 매립 철근을 최소화하여 벽체 매립 철근비용 절감 및 인력 절감을 유도한다.In addition, as shown in FIG. 7, the core staircase 17 is constructed by successively following the core 5. The core staircase 17 is connected to a vertical wall by using a system foam 14 and 15 to post the one below the one layer of the core 5 using a conventional foam while the wall structure has already been completed. Complex mold construction can be led to simple work. Preferably, the staircase structure is simplified to a one-way slab structure, thereby minimizing wall embedding reinforcing bars for integrating the staircase with the core wall, thereby inducing cost reduction and manpower reduction of the wall embedding reinforcement.

이때 1개 층 위쪽의 상기 시스템 폼(14)(15)에는 가설 계단(18)을 설치하여 작업자의 상, 하층 간의 이동을 원활히 하고 바람직하게는 콘크리트 타설이 완료된 슬래브(1)층에 호이스트를 근접 운행토록 하여 공사 관련자 및 자재 수송을 원활히 함으로써 본 발명의 효과를 더욱 높이 발휘할 수 있다.At this time, a temporary staircase 18 is installed on the system foams 14 and 15 above one floor to facilitate movement between the upper and lower floors of the worker, and preferably the hoist is close to the floor of the slab 1 where concrete casting is completed. By smoothly transporting the relevant personnel and materials to be operated, the effect of the present invention can be further exerted.

이상에서 설명한 실시 형태를 통하여 알 수 있는 바와 같이, 본 발명의 고층 건축구조물의 시공방법은 철근 콘크리트 구조를 이용하는 방법으로서, 종래의 코어 선행 공법과 달리, 주거 공간인 슬래브를 선행하여 시공하고 코어 및 코어 계단의 순으로 순차 후행함으로써, 초고층 건축구조물을 더욱 빠르고 안전하게 실현하는 효과를 얻을 수 있다. As can be seen through the embodiments described above, the construction method of the high-rise building structure of the present invention is a method using a reinforced concrete structure, unlike the prior art core construction method, prior to the construction of the slab which is a residential space and the core and By sequentially following the core staircase, the effect of realizing the high-rise building structure more quickly and safely can be obtained.

또한 본 발명에 의하면 슬래브 및 코어 구조물의 품질 및 안정성을 더욱 향상시킬 수 있다.In addition, according to the present invention can further improve the quality and stability of the slab and core structure.

Claims (4)

철근콘크리트 구조를 이용하여 코어 및 그 주변으로 주거 공간이 마련된 고층 건축구조물을 축조함에 있어서,In constructing a high-rise building structure in which a living space is provided around the core and its surroundings using reinforced concrete structures, 선 타설될 기둥 및 슬래브를 적어도 2-4 구역으로 분할하되, 상기 슬래브의 제 1 구역에 기둥철근을 배근하고 기둥 시스템 폼을 설치하여 기둥 콘크리트를 타설하는 제 1 단계;A first step of dividing the pillars and slabs to be pre-cast into at least 2-4 zones, placing the column reinforcement in the first zone of the slab and installing the pillar system foam to pour the pillar concrete; 콘크리트가 양생되면 기둥 시스템 폼을 해체하여 제 2 구역으로 보내고, 슬래브 시스템 폼을 설치하는 제 2 단계;A second step of dismantling the column system foam and sending it to the second zone when the concrete is cured, and installing the slab system foam; 슬래브 시스템 폼에 슬래브 철근 배근 및 전기, 설비 배관을 설치하는 제 3 단계;A third step of installing slab reinforcement and electrical, facility piping in the slab system foam; 슬래브 시스템 폼에 콘크리트를 타설하고 양생하는 제 4 단계;A fourth step of pouring and curing concrete into the slab system foam; 상기 제 1 단계 내지 제 4 단계는 각 구역을 따라 연속하여 순차 시공됨으로 써 기둥 및 슬래브 1개 층을 시공하는 것이고, 반복됨으로써 상부 층을 순차 시공하는 것이고;The first to fourth steps are to construct a single layer of columns and slabs by successive constructions along each zone, and by repeating, to construct the top layer sequentially; 상기 슬래브의 아래층에서 후행하여 코어를 시공하는 제 5 단계; 그리고 A fifth step of constructing the core by following the lower layer of the slab; And 상기 코어의 아래층에서 후행하여 코어 계단을 시공하는 제 6단계를 포함하여 이루어짐을 특징으로 하는 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법.A method of constructing a high-rise building structure having a reinforced concrete structure, characterized in that it comprises a sixth step of constructing a core staircase subsequent to the lower layer of the core. 제 1 항에 있어서, 상기 코어 철근은 2개 층의 높이로 된 것을 매 층마다 절반 수량만큼씩 결합하고, 이를 지지하기 위한 철근 가이드 프레임을 갖는 특징을 가진 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법.The construction of a high-rise building structure having a reinforced concrete structure according to claim 1, wherein the core reinforcing bar has a height of two floors, and a reinforcing bar guide frame for coupling the half quantity of each floor and supporting it. Way. 제 1 항에 있어서, 상기 코어를 시공함에 있어서,The method of claim 1, wherein in the construction of the core, 적어도 2-3의 구역으로 분할하되, 선 시공되는 기둥 및 슬래브 구역과 중복되지 않도록 시차를 조정하고 공정의 연속된 순차 진행을 통하여 코어를 축조함을 특징으로 하는 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법.A high-rise building structure with reinforced concrete, characterized in that it is divided into at least 2-3 zones, the parallaxes being adjusted so as not to overlap with the pre-installed column and slab zones, and the core is constructed through a continuous sequence of processes. Construction method. 제 1 항에 있어서, 상기 코어 계단을 시공함에 있어서,The method of claim 1, wherein in constructing the core stairs, 1방향 슬래브로 구성되고, 코어의 임의 위치에 작업자 이동용 가설계단이 설치되며, 콘크리트 타설이 완료된 슬래브층에 호이스트를 설치하여 운행함을 특징으로 하는 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법. A construction method for a high-rise building structure having a reinforced concrete structure, comprising a one-way slab, a temporary design stage for worker movement at an arbitrary position of the core, and a hoist installed on a slab layer in which concrete is placed.
KR1020060037927A 2006-04-27 2006-04-27 Construction method for rc structured high rise building KR100685147B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060037927A KR100685147B1 (en) 2006-04-27 2006-04-27 Construction method for rc structured high rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060037927A KR100685147B1 (en) 2006-04-27 2006-04-27 Construction method for rc structured high rise building

Publications (1)

Publication Number Publication Date
KR100685147B1 true KR100685147B1 (en) 2007-02-22

Family

ID=38104214

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060037927A KR100685147B1 (en) 2006-04-27 2006-04-27 Construction method for rc structured high rise building

Country Status (1)

Country Link
KR (1) KR100685147B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101632901B1 (en) 2015-02-24 2016-06-24 주식회사 정우비엔씨 transfer device reinforcing rod
KR20190038984A (en) * 2017-10-02 2019-04-10 한봉길 Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings
KR102643685B1 (en) * 2023-04-26 2024-03-05 주식회사 주산종합건설 Construction method of high-rise structure of reinforced concrete

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101632901B1 (en) 2015-02-24 2016-06-24 주식회사 정우비엔씨 transfer device reinforcing rod
KR20190038984A (en) * 2017-10-02 2019-04-10 한봉길 Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings
KR102619713B1 (en) * 2017-10-02 2023-12-29 한봉길 Structure construction method for multiple buildings with wall structure
KR102643685B1 (en) * 2023-04-26 2024-03-05 주식회사 주산종합건설 Construction method of high-rise structure of reinforced concrete

Similar Documents

Publication Publication Date Title
AU2020200977B2 (en) Methods, systems and components for multi-storey building construction
CN201217898Y (en) Concrete prefabricated stairs
CN105317137A (en) Prefabricated wall, prefabricated wallboard, construction method of prefabricated wall and production method of prefabricated wallboard
AU2022204051A1 (en) Method for constructing a concrete floor in a multistorey building
SG187296A1 (en) A multi-storey building with prefabricated members and a semi-prefabricating construction method thereof
KR102079703B1 (en) Modular staircase and method of constructing the same
CN107700648A (en) Prefabricated component and cast-in-place post assembled integral concrete frame structure construction
KR20060127632A (en) Wall structure using precast concrete panel with multi rib rows
KR100685147B1 (en) Construction method for rc structured high rise building
CN110924568A (en) Method for constructing stair partition wall by adopting precast concrete hollow wall board
KR20220049720A (en) Rapid Construction Structure of Core Part Using Multi-Story Precast Wall
KR102197994B1 (en) Construction method using beam-reinforced deck plate
CN214195056U (en) Prefabricated shear wall with assembling holes arranged in staggered mode reserved in assembling mode and assembling structure of prefabricated shear wall
KR20200075600A (en) Method for constructing transfer layer of building using precast concrete slab
AU2019203603B1 (en) Stair assembly and method
KR101315946B1 (en) Rc construction method for concrete lining in parallel
KR20100121865A (en) Method for constructing building using prc integrating method
KR20210141194A (en) Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure
KR20130035355A (en) Pc slab with spiral type shear reinforcement device
KR20120061423A (en) Concrete Construction Method For Slab And Core Wall Construction The Same Time Using Temporary Columns
TWI720486B (en) Method for constructing internal structure of building
KR20210068283A (en) Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing
CN204590360U (en) A kind of cavity plate continuously
CN221073222U (en) Heavy-duty decorative structural beam without independent support system
CN111962666B (en) Construction method of building internal structure

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130123

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140127

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141202

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160119

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170116

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180118

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190207

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20200108

Year of fee payment: 14