KR100685147B1 - Construction method for rc structured high rise building - Google Patents
Construction method for rc structured high rise building Download PDFInfo
- Publication number
- KR100685147B1 KR100685147B1 KR1020060037927A KR20060037927A KR100685147B1 KR 100685147 B1 KR100685147 B1 KR 100685147B1 KR 1020060037927 A KR1020060037927 A KR 1020060037927A KR 20060037927 A KR20060037927 A KR 20060037927A KR 100685147 B1 KR100685147 B1 KR 100685147B1
- Authority
- KR
- South Korea
- Prior art keywords
- core
- slab
- concrete
- column
- construction
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B1/3505—Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the in situ moulding of large parts of a structure
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/38—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for plane ceilings of concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/02—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
도 1은 본 발명에 의한 철근콘크리트 구조를 갖는 고층 건축구조물의 구역 분할 및 시공 순서를 설명하기 위한 평면구성도이고,1 is a plan view for explaining the division and construction sequence of a high-rise building structure having a reinforced concrete structure according to the present invention,
도 2 내지 도 5는 본 발명에 의한 기둥 및 슬래브, 코어 및 계단의 시공 단계를 설명하는 단면구성도이며,2 to 5 is a cross-sectional view illustrating the construction step of the pillar and slab, core and stairs according to the present invention,
도 6은 본 발명을 이용하여 코어 벽체에 배근되는 수직 철근의 이음 개소 수를 절반으로 줄일 수 있는 철근 가이드 프레임을 설명하는 평면구성도이다.6 is a plan view illustrating a reinforcing bar guide frame capable of reducing the number of jointed points of a vertical reinforcing bar arranged to a core wall by using the present invention.
도 7은 본 발명에 의한 코어 및 코어 계단의 시공 단계를 보여주는 단면구성도이다.7 is a cross-sectional view showing the construction step of the core and the core step according to the present invention.
본 발명은 철근 콘크리트 구조를 이용하여 주거 공간 및 코어가 마련된 초고층 건축구조물을 축조하는 시공방법에 관한 것으로서, 특히 건축구조물을 이루는 기둥 1개층을 적어도 2 내지 4 구역 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량을 감안하여 적절히 분할하여 1차 선행 시공하고, 후속으로 슬래 브 1개 층을 적어도 2 내지 4 구역 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량을 감안하여 적절히 분할하여 2차 선행 시공하고, 이후 코어 골조를 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량에 맞춰 2 내지 3 구역으로 적절하게 분할하여 후행 시공하고 코어 골조가 완료된 하부 층에 최종으로 코어 계단을 순차 후행하여 시공함으로써, 작업의 적절한 분산을 유도하여 결과적으로 공사기간 단축, 원가 절감 및 안전 작업을 유도하면서도, 기둥, 보, 슬래브, 코어 및 계단 구조물의 품질을 향상시킬 수 있도록 한 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법에 관한 것이다.The present invention relates to a construction method for constructing a high-rise building structure provided with a residential space and a core using a reinforced concrete structure, and in particular, an appropriate amount of formwork and reinforcement work per day, such as at least 2 to 4 zones, for one floor of a column constituting the building structure. First preliminary construction by dividing properly in consideration of the appropriate amount of concrete placement per day, and subsequently, one layer of slab is appropriately divided in consideration of the daily mold and reinforcement work amount such as at least 2 to 4 zones and the appropriate amount of concrete placement per day. After the second preliminary construction, the core frame is appropriately divided into 2 to 3 zones according to the daily mold and reinforcement work amount and the concrete casting amount, followed by the subsequent construction, and finally the core stair is sequentially followed on the lower layer where the core frame is completed. By constructing, it induces proper distribution of work and consequently shortens construction time and costs And a method of constructing a high-rise building structure having a reinforced concrete structure capable of improving the quality of columns, beams, slabs, cores, and staircase structures while inducing safety work.
일반적으로 건축구조물은 철근 콘크리트구조(RC구조), 철골 구조(S구조) 및 철골·철근 콘크리트 복합구조(SRC구조)로 축조되며, 이 중 철근 콘크리트 구조는 고강도 콘크리트 제조 및 시공 기술의 발달과 함께 다른 구조에 비해 원가가 비교적 저렴하고 재료 특성상 화재에 유리하고 진동 및 소음 차단성이 유리하다는 이유로 초고층화 대형화되어가는 최근의 건축물에 자주 적용되고 있는 추세이다. 이러한 철근 콘크리트구조 초고층 건축구조물의 주요 구조부재는 일반적으로 엘리베이터, 전기시설, 설비시설 및 계단, 화장실 등 부속 시설이 집중되어있고 벽체로 구성되어 있는 코어와, 주거 공간을 구성하는 기둥 및 보, 슬래브로 요약되며,In general, building structures are constructed of reinforced concrete structures (RC structures), steel structures (S structures) and steel and reinforced concrete composite structures (SRC structures). Among these, reinforced concrete structures are developed with the development of high-strength concrete manufacturing and construction technology. Compared to other structures, the cost is relatively low, the material is favorable to fire, and the vibration and noise blocking property is advantageous, so it is frequently applied to the latest buildings which are becoming very large and large. The main structural members of such reinforced concrete structured high-rise building structures generally include cores composed of walls and pillars, beams, and slabs, which consist of walls, including elevators, electrical facilities, facilities, stairs, and toilets. Are summarized as
이러한 철근 콘크리트 구조를 갖는 건축구조물의 종래의 주된 시공 방법은 첫째, 코어를 선행 시공하고 기둥 및 슬래브를 후속으로 시공하는 코어 선행 시공방법과 둘째, 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법 등 두 가지가 있다. Conventional main construction methods of building structures having such reinforced concrete structures include first, core prior construction methods for constructing cores in advance and subsequent construction of columns and slabs; and second, simultaneous construction methods for simultaneously constructing cores, columns, and slabs. There are two things.
이러한 철근 콘크리트 구조 시공방법들에 대하여 좀 더 자세히 설명하면, When explaining the reinforced concrete construction methods in more detail,
첫째, 전자의 철근 콘크리트구조를 갖는 건축구조물의 코어 선행 시공방법에서는 코어의 내측 공간 또는 코어의 외측 공간에 타워크레인, 호이스트(hoist), 콘크리트 디스트리뷰터(distributor) 등의 코어공사 전용 시설들을 가설한 다음, 상기 코어공사 전용 시설들을 이용하여 자재 및 인력을 운반하여 철근을 배근하고 후행 슬래브와의 결속을 위해, 상기 코어에 앵커부재를 함께 선 매립 설치하고 시스템 폼을 장착한 후 콘크리트를 타설하여 코어를 선행 축조하게 된다. 이후 기둥을 설치하고(기둥은 슬래브에 선행하여 콘크리트를 타설하는 경우도 있고 슬래브와 동시에 타설하는 경우가 있다.), 슬래브 형틀재 설치와 더불어 상기 코어에 매립된 앵커부재에 슬래브 철근을 연결 배근하고, 콘크리트 타설을 거쳐 슬래브를 축조 시공한다.First, in the core preliminary construction method of the building structure with the former reinforced concrete structure, the facilities for core construction such as tower crane, hoist and concrete distributor are installed in the inner space of the core or the outer space of the core. In order to reinforce the reinforcing bar by carrying materials and manpower by using the dedicated facilities for core construction and to bond with a trailing slab, the cores are installed by pre-installing anchor members on the cores, installing system foam, and then placing concrete cores. Pre-construction is done. Later, the column is installed (the column may be placed before the slab, and the concrete may be poured simultaneously with the slab), and the slab reinforcement is connected to the anchor member embedded in the core together with the slab frame member. The concrete slab is then constructed and poured.
상술한 코어 선행 공법은 작업량이 상대적으로 많은 코어 부위를 선행시킴으로써 독립적으로 운영하여 공사기간을 단축하고, 시스템 폼을 사용하여 양중 부하를 저감시킴으로써 초고층 건축물의 축조에 많이 이용되고 있다.The above-described core preceding method is used in the construction of high-rise buildings by operating independently by reducing the amount of load by using a system form to operate independently by preceding the core portion having a relatively high workload.
둘째, 후자의 철근 콘크리트구조를 갖는 건축구조물의 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법은 상기 첫 번째 공법과는 달리 코어와 기둥 및 슬래브를 동시에 시공함으로써 상기 코어 선행에 따른 코어공사 전용 시설 배치가 필요 없고 또한 코어 벽체에 앵커부재의 사전 매립도 필요 없고 적정 품질 유지 및 안전관리에 비교적 유리하고 원가 부담이 크지 않은 장점이 있고 가장 보편화된 공법이다.Second, in the simultaneous construction method for simultaneously constructing the core, the pillar, and the slab of the building structure having the latter reinforced concrete structure, unlike the first construction method, the core, pillar, and slab are constructed at the same time. It does not need to be laid out and also does not require the pre-embedding of anchor members in the core wall, it is relatively advantageous in maintaining proper quality and safety management, and it is the most cost-effective method.
상술한 종래의 두 가지 공법 중에서,Of the two conventional methods described above,
첫째, 전자의 철근 콘크리트구조를 갖는 건축구조물의 코어 선행 시공방법은 코어의 형틀 작업 및 철근 배근, 콘크리트 타설을 위한 타워크레인, 호이스트 및 콘크리트 디스트리뷰터 등의 코어공사 전용 시설을 가설해야 하고, 또한 코어가 먼저 선행하는 관계로 코어의 높이에 의해 타워크레인 운행 간섭현상에 의해 부득이 적정 대수 이상의 타워크레인을 배치해야하는 문제점이 발생하고, 후속으로 시공되는 슬래브 중 상기 코어공사 전용 시설로 인한 간섭구간은 철근 배근 및 콘크리트 타설을 보류하고 코어공사 전용 시설 철거 후 타설해야 하므로 작업 공정이 복잡하고 안전관리의 어려움 및 비용이 많이 드는 문제점이 있다.First, the core preliminary construction method of the building structure with the former reinforced concrete structure requires the construction of core formwork and reinforcement, core crane dedicated facilities such as tower crane for concrete placing, hoist and concrete distributor. First of all, there is a problem that tower cranes must be arranged more than the proper number due to the interference of tower crane operation due to the height of the core, and the interference section due to the core construction facility among the slabs that are subsequently constructed is reinforced with reinforcement bars and The concrete work process is complicated and the safety management is difficult and costly because it is necessary to withhold concrete pouring and dismantle the core construction facility.
또한 선행되는 코어는 후행하는 주거구간에 해당하는 슬래브보다 면적이 좁을 뿐 만 아니라 코어와 슬래브의 높이 차이에 의해 초고층 건축구조물의 핵심이라고 할 수 있는 엘리베이터 샤프트의 수직도 관리에 어려움이 많고, 코어와 슬래브의 콘크리트를 분리하여 타설해야 하므로 코어와 슬래브를 연결해주는 철근을 벽체에 사전 매립해야 함으로써 추가비용발생 및 분리 타설로 인한 접합부 품질이 저하되는 문제점이 있다.In addition, the preceding core is not only narrower than the slab corresponding to the following residential section, but also has difficulty in managing the verticality of the elevator shaft, which is the core of the high-rise building structure by the height difference between the core and the slab. Since the concrete of the slab must be separated and poured, the reinforcing bar connecting the core and the slab must be buried in the wall, causing additional cost and deterioration of the joint quality due to the separate casting.
또한 코어 선행을 위해서는 코어 벽체 형틀 공사용 시스템 폼을 장착하게 되는데 벽체 두께는 보통 높이 올라갈수록 벽체 두께가 얇아지는 것이 정상인데 반하여 코어 벽체 두께 변화에 따른 코어 벽체 형틀 공사용 시스템 폼을 수정하기가 어려워 코어 벽체를 저층부부터 고층부까지 일정한 두께를 유지하는 경향으로 인해 콘크리트 재료가 일반 공법에 비해 많이 들어가는 문제점이 있다. In addition, the core wall formwork system foam is installed to advance the core.While the wall thickness is usually higher, the wall thickness becomes thinner, whereas it is difficult to modify the core wall formwork system form due to the change of core wall thickness. Due to the tendency to maintain a constant thickness from the low floor to the high floor, there is a problem that a lot of concrete materials compared to the general method.
또한 코어와 슬래브 층의 작업이 상, 하간 떨어져 있어 안전 관리가 어렵고, 특히 선행하는 좁은 코어 공간 주위에서 다양한 공종이 동시에 작업이 이루어져야 하므로 혼잡하고, 작업 능률이 저하되며, 이로 인한 공정 관리의 어려움이 있다.In addition, the work of the core and slab layers is separated from the top and bottom, making it difficult to manage safety. In particular, various types of work must be performed simultaneously in the vicinity of the preceding narrow core space, resulting in congestion and reduced work efficiency. have.
둘째, 후자의 철근 콘크리트구조를 갖는 건축구조물의 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법은 첫 번째 공법과는 달리 코어와 기둥 및 슬래브를 동시에 시공함으로써 상기 코어 선행에 따른 코어공사 전용 시설 배치가 필요 없고 또한 코어 벽체에 앵커부재의 사전 매립도 필요 없고 적정 품질 유지 및 안전관리에 비교적 유리하고 원가 부담이 크지 않은 장점이 있는 가장 보편화된 공법이지만 코어와 기둥 및 슬래브가 동시에 작업이 집중 진행됨으로써 작업자들의 작업 공간 확보의 어려움이 발생하여 결과적으로 작업자들의 작업 공백 기간이 발생하여 공사기간 단축에는 한계가 있다는 것이 문제점이다.Second, in the simultaneous construction method for simultaneously constructing the core, column and slab of the building structure having the latter reinforced concrete structure, unlike the first construction method, the core, pillar and slab are constructed at the same time so that the core construction dedicated facility according to the core precedence is arranged. It is the most common method that does not need to be installed in the core wall, and does not need to pre-install anchor member in the core wall, and it is relatively advantageous in maintaining proper quality and safety management, and it does not have much cost burden, but the core, column, and slab work at the same time. The difficulty of securing the working space of the workers occurs as a result of the work gap of the workers occurs as a result there is a limit to shorten the construction period.
이와 같은 종래 기술의 문제점을 해결하기 위한 것으로서, 본 발명은 다른 구조에 비해 원가가 비교적 저렴하고 재료 특성상 화재에 유리하며 진동 및 소음 차단성이 좋은 철근콘크리트 구조를 이용하여 초고층 건축구조물을 시공하되, 건축구조물의 기둥을 적어도 2구역 내지 4개 구역 등 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량으로 적절히 분할하여 1차 선행하고, 후속으로 슬래브 1개 층을 적어도 2구역 내지 4개 구역 등 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량으로 적절히 분할하여 2차 선행하고, 이후 코어 골조를 1일 형틀 및 철근 작업 적정량 및 콘크리트 타설 적정량에 맞춰 2 내지 3 구역으로 적절하게 분할하 여 후행 시공하고 코어 골조가 완료된 하부층에 최종으로 코어 계단을 순차 후행하여 시공함으로써, 작업의 적절한 분산을 유도하여 결과적으로 공사기간 단축 및 안전 작업을 유도하면서도, 기둥, 슬래브, 코어 및 계단 구조물의 품질을 더욱 향상시키고 원가절감을 도모함에 그 목적을 두고 있다.In order to solve the problems of the prior art, the present invention is a relatively low cost compared to other structures and advantageous to fire due to the characteristics of the material, the construction of ultra high-rise building structure using a reinforced concrete structure having good vibration and noise blocking properties, The pillars of the building structure are firstly divided into appropriate sections for at least 2 to 4 zones per day and appropriate for reinforcing work for steel and reinforcing concrete, followed by 1st slab layer for at least 2 to 4 zones. Secondly, the core frame is appropriately divided into the appropriate amount of mold and reinforcement work and concrete pouring, and then the core frame is appropriately divided into 2 to 3 zones according to the daily mold and reinforcement amount and concrete pouring amount. By laying the core staircase in order to finally complete the lower layer, It aims to further improve the quality of columns, slabs, cores and staircases and to reduce costs, while inducing proper dispersion and consequently shortening construction period and safety work.
이하, 본 발명의 바람직한 실시 형태를 첨부 도면에 의거하여 설명하기로 한다.EMBODIMENT OF THE INVENTION Hereinafter, preferred embodiment of this invention is described based on an accompanying drawing.
본 발명은 철근 콘크리트 구조를 이용하여 초고층 건축구조물을 시공하는 것을 기본으로 하고 있으며, 종래의 철근 콘크리트구조를 갖는 건축구조물의 코어 선행 시공방법 및 철근 콘크리트구조를 갖는 건축구조물의 코어와 기둥 및 슬래브를 동시에 시공하는 동시 시공방법과 달리, 기둥을 1차 선행하여 시공하고 슬래브를 2차 선행시키고, 이후로 코어 및 코어 계단의 순으로 순차 후행하여 건축구조물을 축조함을 특징으로 한다.The present invention is based on the construction of a high-rise building structure using a reinforced concrete structure, the core prior construction method of the building structure having a conventional reinforced concrete structure and the core, column and slab of the building structure having a reinforced concrete structure Unlike the simultaneous construction method of constructing at the same time, it is characterized by constructing the building structure by constructing the pillar first and the slab second, and then successively following the core and the core stairs in order.
도 1은 본 발명에 의한 철근콘크리트 구조를 갖는 고층 건축구조물의 구역 분할 및 시공 순서를 설명하기 위한 평면구성도로서,1 is a plan view for explaining the division and construction sequence of a high-rise building structure having a reinforced concrete structure according to the present invention,
도시한 바와 같이, 본 발명에서는 주거 구간의 기둥과 슬래브(1)의 1개 층을 시공이음(2)(4)를 이용하여 적어도 4구역 (가), (나), (다), (라) 또는 2구역 (가나), (다라) 등으로 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량에 맞춰 적절히 나누어 순연하면서 순차적으로 시공한다. 여기에서 시공이음이란 1일 콘크리트 타설량이 너무 많아 당일 안에 콘크리트를 타설 완료하기 불가하거나 공 사 현장의 예기치 못한 상황의 발생으로 인하여 부득이 콘크리트를 끊어쳐야 할 필요성이 있을 때 적정한 위치에 목재나 철재, 플라스틱 등의 재료를 이용하여 콘크리트 타설시 콘크리트가 새어나가지 않도록 구간을 분할, 구획하여 콘크리트를 타설토록 하는 임시 구획선을 의미한다. As shown, in the present invention, one floor of the pillar and the
슬래브(1)의 각 구역은 공정별 1일 작업량을 감안하여 평면적으로 설정한 것이고, 구역을 분할하여 순차 시공하는 것은 융통성을 부여하고 연속적인 되풀이 작업을 유도하여 적정한 공기 단축을 실현하기 위한 것이다.Each zone of the
이러한 슬래브(1)의 구역별 순차 시공 및 되풀이 작업을 실현하기 위해서는 기본적으로 기둥이나 슬래브가 가급적 단순한 구조로 설계되어야 하고 적절한 시스템 폼으로 계획되어야 한다. 기둥이나 슬래브의 시스템 폼은 잘 알려진 사항이므로 부연 설명을 생략하기로 한다.In order to realize the sequential construction and repetitive work of each section of the
구역별 시공 방법은 도 2 내지 도 5를 통하여 잘 표시되고 있다.The construction method for each zone is well represented through FIGS. 2 to 5.
여기서 슬래브(1)의 1개 층은 (가), (나), (다), (라) 구역으로 나눌 수 있으며, 코어(5)는 시공이음(2)(3)을 적절히 이용하여 CORE A, CORE B 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량에 맞춰 적절히 나누어 2 내지 3 개 구역으로 나눌 수 있으며 슬래브(1)의 한층 아래에서 후행되고, 코어 계단(17)은 더욱 한층 아래에서 후행한다. Here, one layer of slab (1) can be divided into (A), (B), (C) and (D) zones, and the core (5) can be divided into CORE A using the joint (2) (3) as appropriate. , CORE B, etc., can be divided into 2 to 3 zones according to the proper amount of work and reinforcement for the daily work and reinforcement of concrete, and the trailing of the
도 2는 1일 차의 시공이다. 도면을 통하여 알 수 있는 바와 같이, (가) 구역에서는 기둥철근(6)을 배근하고 기둥 시스템 폼을 설치하며, 이어서 기둥 콘크리트(7)를 타설한다.2 shows the construction of the first day. As can be seen from the figure, in section (a), the
도 3은 2일 차의 시공 단계이다. 도면을 통하여 알 수 있는 바와 같이, (가) 구역에서는 기둥 시스템 폼을 해체하고, 이것을 (나) 구역으로 이동하며 상기 1일차 공정을 (나) 구역에 시공한다.3 is a construction step of the second day. As can be seen from the figure, in section (a), the column system foam is dismantled, moved to section (b) and the first day process is installed in section (b).
이때 (가) 구역에서는 슬래브 시스템 폼(13)을 인양, 설치한다.In this section (a), the
도 4는 3일 차의 시공 단계이다. 도면에서와 같이, (나) 구역의 기둥 시스템 폼은 다시 해체되어 (다) 구역으로 이동하며, 이어서 슬래브 시스템 폼(13)을 인양하여 (나) 구역에 설치하는 2일차의 공정이 이루어진다. (다) 구역에서는 상기 1일 차의 공정을 시공하게 된다.4 is a construction step of the third day. As shown in the figure, the column system foam of zone (B) is dismantled and moved to zone (C), followed by a second day process of lifting and installing the
이때 (가) 구역에서는 슬래브철근(12)을 배근하고, 이와 동시에 전기나 설비 배관을 설치한다. At this time, in the area (A), the
도 5는 4일 차의 시공 단계이다. 도면에서와 같이, (다) 구역의 기둥 시스템폼은 다시 해체되어 (라) 구역으로 이동하며 여기에 상기 1일 차의 공정을 시공하게 된다.5 is a construction step of the fourth day. As shown in the drawing, the column system form of the (C) zone is dismantled and moved to the (D) zone, where the construction of the first day is performed.
또 (다) 구역에서는 슬래브 시스템 폼(13)을 인양하여 2일 차의 공정을 시공한다. (나) 구역에서는 슬래브철근(12)을 배근하고, 이와 동시에 전기나 설비 배관하여 3일 차의 공정을 설치한다.In section (c), the
또한 (가) 구역에서는 슬래브 테이블 시스템 폼(13)에 슬래브 콘크리트(8)를 타설하여 양생 단계에 도달하여 슬래브(1) 1개 층을 완성하게 되며, 여기에 다시 1일 차의 공정을 반복하기 위하여 기둥, 벽 등의 먹매김 작업을 실시한다. In addition, in (A), slab concrete (8) is poured into the slab table system form (13) to reach the curing stage to complete one floor of the slab (1), where the process of
이상에서 설명한 4일 차의 공정에 의해 본 발명에서는 1개 층의 슬래브(1)를 완성하게 되는 것이며, 이러한 공정은 작업량을 고려한 구역 분할과 각 공정의 연속된 순차 진행에 의해 이루어지며, 상기 공정의 반복에 의해 상부 층의 슬래브(1)를 축조하게 되는 것이다.In the present invention, the
한편, 본 발명에서는 기둥 및 슬래브를 구역별로 시공하는 다른 예로서, 기둥 및 슬래브 구간을 (가나), (다라) 등의 2 구역으로 분할하여 시공할 수 있으며, 각 구역별 시공 단계는 앞서 설명한 바와 동일하므로 부연 설명을 생략한다.Meanwhile, in the present invention, as another example of constructing the pillars and the slabs by zones, the pillars and the slab sections may be divided into two zones, such as (Ghana) and (Dara), and the construction steps for each zone are as described above. The description is omitted since it is the same.
이렇게 기둥 및 슬래브가 1차 선행 시공됨으로써 보다 복잡한 후속 코어 및 계단 공사를 수행하기 위한 비교적 넓은 바닥이 먼저 제공됨에 따라 코어 작업자들의 안전하고 다양한 현장 접근을 가능하게 하고, 슬래브와 코어와의 접속을 위한 앵커부재의 생략을 유도하고, 코어 수직도 확보를 위한 측량을 용이하게 하며 더욱이 콘크리트가 타설된 슬래브 층까지 호이스트를 운행시킴으로써 보다 빠른 인력 및 물류의 이동을 가능하게 하여 결과적으로 보다 안전하고도 공기 단축을 가능하게 하고 코어와 슬래브와의 접속부 품질을 높이면서도 원가 절감을 가능하게 하는 것이다.This preliminary pre-installation of the columns and slabs provides a relatively wide floor first for more complex subsequent core and stair constructions, enabling safe and versatile site access for the core workers and for the connection between the slabs and the cores. Induces omission of anchor members, facilitates surveying to ensure core verticality, and also enables hoists to move faster and manpower and logistics by running hoists up to the slab layer where concrete is poured, resulting in safer and shorter air. This enables cost reduction while improving the quality of the core-slab connection.
한편, 코어 및 코어 계단의 시공 단계에 대해 설명을 하면, On the other hand, when explaining the construction stage of the core and core stairs,
코어 및 코어 계단은 슬래브(1)에 후행하여 코어(5)를 시공하고 코어 계단(17)은 더욱 한층 아래에서 후행 시공하게 되는바, 이러한 공정은 앞서 설명한 바와 마찬가지로 시공이음(2)(3)을 적절히 이용하여 CORE A, CORE B 등 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량에 맞춰 2 내지 3 개 구역으로 분할하여 선행 시공되는 기둥 및 슬래브 구간의 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량과 중복이 되지 않도록 적절히 시차를 두어 결과적으로 골조공사 전체의 균형을 유지함으로써 1일 적정 작업 인원 및 투입 자재, 장비를 평준화하여 공정관리를 원활히 할 수 있도록 함이 핵심이라 할 수 있다.The core and the core stairs are followed by the
도 2 내지 도 5에 의거하여 코어 및 코어 계단의 시공 단계에 대해 설명을 하면, Referring to the construction step of the core and core stairs based on Figures 2 to 5,
도 2의 1일 차 시공 단계는, 선행하는 기둥 및 슬래브 구간의 1일 형틀 및 철근 작업 적정량 및 1일 콘크리트 타설 적정량과 중복이 되지 않도록 적절히 시차를 둔 바람직한 예로서, CORE A 구간에서는 CORE A 구간에 속한 슬래브 및 벽체에 콘크리트(9)를 타설하고, CORE B 구간에서는 벽체에 철근 가이드 프레임(10)을 이용하여 코어 수직 철근(11) 배근 및 각종 매입 작업을 함과 동시에 내부의 시스템 폼(14)을 인양, 고정하는 단계를 보여 주며 이때 CORE B 구간에 해당하는 슬래브 폼도 병행 설치한다.
도 3의 2일 차 시공 단계는, CORE A 구간에서는 벽체에 철근 가이드 프레임(10)을 이용하여 코어 수직 철근(11)을 배근함과 동시에 내부의 시스템 폼(14)을 인양, 고정하고 CORE A 구간에 해당하는 슬래브 폼도 병행 설치한다. CORE B 구간에서는 전일에 시행했던 CORE B 구간에 해당하는 슬래브 폼 잔여 작업 및 잔여 철근(11) 배근 및 각종 매입 작업을 진행하고, In the second day construction step of FIG. 3, in the CORE A section, the core vertical reinforcing
도 4의 3일 차 시공 단계는, CORE A 구간에서는 전일에 시행했던 CORE A 구간에 해당하는 슬래브 폼 잔여 작업 및 잔여 철근(11) 배근 및 각종 매입 작업을 진행하고, CORE B 구간에서는 최종 철근(11) 배근 및 각종 매입 작업의 완료와 함께 건물 형상 및 구조에 맞도록 고안된 시스템 폼(15)을 설치하고 다른 한편에서는 작업자가 취급하기 용이하게 고안된 인력 설치 폼(16)을 설치하여 익일 콘크리트 타설을 위한 각종 검측 작업 및 콘크리트 타설 준비 작업이 이루어진다.In the third day construction step of FIG. 4, in the CORE A section, the slab foam remaining work and the remaining reinforcing
도 5의 4일 차 시공 단계는, CORE A 구간에서는 최종 철근(11) 배근 및 각종 매입 작업의 완료와 함께 건물 형상 및 구조에 맞도록 고안된 시스템 폼(15)을 설치하고 다른 한편에서는 작업자가 취급하기 용이하게 고안된 인력 설치 폼(16)을 설치하여 익일 콘크리트 타설을 위한 각종 검측 작업 및 콘크리트 타설 준비 작업이 이루어지고, CORE B 구간에서는 CORE B 구간에 속한 슬래브 및 벽체에 콘크리트(9)를 타설하게 된다.
이상에서 설명한 4일 차의 공정에 의해 본 발명에서는 1개 층의 코어(5)를 완성하게 되는 것이며, 이러한 코어 공정은 선행 공정인 기둥 및 슬래브 작업량을 고려하여 구역 분할과 시차 조정을 통하여 각 공정의 연속된 순차 진행을 유도하여 순조로운 상기 공정의 반복에 의해 상부 층의 코어(5)를 축조하게 되는 것이다.In the present invention, the
한편, 코어 수직 철근(11)은 철근 가이드 프레임(10)을 코어 수직 철근 주위에 설치함으로써 2개 층의 길이로 된 것을 사용할 수 있으며 매 층마다 이음을 하는 것이 아니고 2개 층마다 철근을 지그재그로 절반의 개수만 이음으로써 이음부의 수를 절반으로 축소할 수 있고 구체적인 철근 이음 방법은 기 완성된 슬래브(1)위에서 1개 층 밑에서 후행하여 시공되는 코어(5) 벽체 하부로 내리꽂는 하향작업의 형태를 취하므로 작업자들이 손쉽게 철근 설치작업을 진행할 수 있다. On the other hand, the core vertical reinforcing bar (11) can be used in the length of two layers by installing the reinforcing
이 철근 가이드 프레임(10)은 도 6에 도시한 바와 같이 바람직하게는 철재 파이프(20) 및 보강재(21), 인양용 고리(19)로 구성되며, 코어 벽체의 형태 및 코어의 작업 구역 분할에 따라 적절하게 분할, 구획되어 설치되며, 이 철근 가이드 프레임(10)의 운영은 최초 설치 후 공정 진행에 따라 타워크레인을 이용하여 철근 가이드 프레임에 장착되어 있는 인양용 고리(19)에 인양줄을 걸어 순차적으로 인양해주기만 하면 철근에 형성되어 있는 홈에 의해 철근 가이드 프레임(10)이 밑으로 흘러내리지 않으므로 별도로 고정해 줄 필요가 없고, 아울러 이 가이드 프레임의 보강을 위한 보강재(21)를 적절한 위치에 배치함으로써 코어 벽체 내, 외부의 시스템 폼 결합을 위한 긴결재의 위치에 철근이 배치되지 않도록 할 수 있으면서도 철근의 위치 및 수직도를 사전에 제어할 수 있으며, 이러한 일련의 작업을 통해 결과적으로 원가 및 공기를 단축할 수 있는 것이다. This
또한 도 7에서 도시한 것처럼, 코어(5)에 순차 후행하여 코어 계단(17)을 시공한다. 코어 계단(17)은 시스템 폼(14)(15)을 이용하여 벽체 구조가 이미 선행 시공 완료된 상태에서 재래식 폼을 이용하여 코어(5)의 1개 층 아래에서 후행하게 함으로써 수직 벽체와의 접합 등의 복잡한 형틀공사를 단순 작업으로 유도할 수 있다. 바람직하게는 계단 구조를 1방향 슬래브 구조로 단순화하여 계단을 코어 벽체와 일체화하기 위한 벽체 매립 철근을 최소화하여 벽체 매립 철근비용 절감 및 인력 절감을 유도한다.In addition, as shown in FIG. 7, the
이때 1개 층 위쪽의 상기 시스템 폼(14)(15)에는 가설 계단(18)을 설치하여 작업자의 상, 하층 간의 이동을 원활히 하고 바람직하게는 콘크리트 타설이 완료된 슬래브(1)층에 호이스트를 근접 운행토록 하여 공사 관련자 및 자재 수송을 원활히 함으로써 본 발명의 효과를 더욱 높이 발휘할 수 있다.At this time, a
이상에서 설명한 실시 형태를 통하여 알 수 있는 바와 같이, 본 발명의 고층 건축구조물의 시공방법은 철근 콘크리트 구조를 이용하는 방법으로서, 종래의 코어 선행 공법과 달리, 주거 공간인 슬래브를 선행하여 시공하고 코어 및 코어 계단의 순으로 순차 후행함으로써, 초고층 건축구조물을 더욱 빠르고 안전하게 실현하는 효과를 얻을 수 있다. As can be seen through the embodiments described above, the construction method of the high-rise building structure of the present invention is a method using a reinforced concrete structure, unlike the prior art core construction method, prior to the construction of the slab which is a residential space and the core and By sequentially following the core staircase, the effect of realizing the high-rise building structure more quickly and safely can be obtained.
또한 본 발명에 의하면 슬래브 및 코어 구조물의 품질 및 안정성을 더욱 향상시킬 수 있다.In addition, according to the present invention can further improve the quality and stability of the slab and core structure.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060037927A KR100685147B1 (en) | 2006-04-27 | 2006-04-27 | Construction method for rc structured high rise building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060037927A KR100685147B1 (en) | 2006-04-27 | 2006-04-27 | Construction method for rc structured high rise building |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100685147B1 true KR100685147B1 (en) | 2007-02-22 |
Family
ID=38104214
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020060037927A KR100685147B1 (en) | 2006-04-27 | 2006-04-27 | Construction method for rc structured high rise building |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100685147B1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101632901B1 (en) | 2015-02-24 | 2016-06-24 | 주식회사 정우비엔씨 | transfer device reinforcing rod |
KR20190038984A (en) * | 2017-10-02 | 2019-04-10 | 한봉길 | Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings |
KR102643685B1 (en) * | 2023-04-26 | 2024-03-05 | 주식회사 주산종합건설 | Construction method of high-rise structure of reinforced concrete |
-
2006
- 2006-04-27 KR KR1020060037927A patent/KR100685147B1/en active IP Right Grant
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101632901B1 (en) | 2015-02-24 | 2016-06-24 | 주식회사 정우비엔씨 | transfer device reinforcing rod |
KR20190038984A (en) * | 2017-10-02 | 2019-04-10 | 한봉길 | Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings |
KR102619713B1 (en) * | 2017-10-02 | 2023-12-29 | 한봉길 | Structure construction method for multiple buildings with wall structure |
KR102643685B1 (en) * | 2023-04-26 | 2024-03-05 | 주식회사 주산종합건설 | Construction method of high-rise structure of reinforced concrete |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2020200977B2 (en) | Methods, systems and components for multi-storey building construction | |
CN201217898Y (en) | Concrete prefabricated stairs | |
CN105317137A (en) | Prefabricated wall, prefabricated wallboard, construction method of prefabricated wall and production method of prefabricated wallboard | |
AU2022204051A1 (en) | Method for constructing a concrete floor in a multistorey building | |
SG187296A1 (en) | A multi-storey building with prefabricated members and a semi-prefabricating construction method thereof | |
KR102079703B1 (en) | Modular staircase and method of constructing the same | |
CN107700648A (en) | Prefabricated component and cast-in-place post assembled integral concrete frame structure construction | |
KR20060127632A (en) | Wall structure using precast concrete panel with multi rib rows | |
KR100685147B1 (en) | Construction method for rc structured high rise building | |
CN110924568A (en) | Method for constructing stair partition wall by adopting precast concrete hollow wall board | |
KR20220049720A (en) | Rapid Construction Structure of Core Part Using Multi-Story Precast Wall | |
KR102197994B1 (en) | Construction method using beam-reinforced deck plate | |
CN214195056U (en) | Prefabricated shear wall with assembling holes arranged in staggered mode reserved in assembling mode and assembling structure of prefabricated shear wall | |
KR20200075600A (en) | Method for constructing transfer layer of building using precast concrete slab | |
AU2019203603B1 (en) | Stair assembly and method | |
KR101315946B1 (en) | Rc construction method for concrete lining in parallel | |
KR20100121865A (en) | Method for constructing building using prc integrating method | |
KR20210141194A (en) | Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure | |
KR20130035355A (en) | Pc slab with spiral type shear reinforcement device | |
KR20120061423A (en) | Concrete Construction Method For Slab And Core Wall Construction The Same Time Using Temporary Columns | |
TWI720486B (en) | Method for constructing internal structure of building | |
KR20210068283A (en) | Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing | |
CN204590360U (en) | A kind of cavity plate continuously | |
CN221073222U (en) | Heavy-duty decorative structural beam without independent support system | |
CN111962666B (en) | Construction method of building internal structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130123 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20140127 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20141202 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20160119 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20170116 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20180118 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20190207 Year of fee payment: 13 |
|
FPAY | Annual fee payment |
Payment date: 20200108 Year of fee payment: 14 |