KR20190038984A - Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings - Google Patents

Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings Download PDF

Info

Publication number
KR20190038984A
KR20190038984A KR1020180041575A KR20180041575A KR20190038984A KR 20190038984 A KR20190038984 A KR 20190038984A KR 1020180041575 A KR1020180041575 A KR 1020180041575A KR 20180041575 A KR20180041575 A KR 20180041575A KR 20190038984 A KR20190038984 A KR 20190038984A
Authority
KR
South Korea
Prior art keywords
construction
day
zone
zones
frame
Prior art date
Application number
KR1020180041575A
Other languages
Korean (ko)
Other versions
KR102619713B1 (en
Inventor
한봉길
Original Assignee
한봉길
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한봉길 filed Critical 한봉길
Publication of KR20190038984A publication Critical patent/KR20190038984A/en
Priority to KR1020230191903A priority Critical patent/KR20240004188A/en
Application granted granted Critical
Publication of KR102619713B1 publication Critical patent/KR102619713B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The present invention relates to a construction method which reduces a construction scale by dividing a plane of a floor of a building to expedite framework construction to shorten construction time in construction having a wall structure such as an apartment building, a high-rise residential building, a studio building, and a knowledge industry center. Also, the present invention relates to finishing of a framework in a four-day cycle by dividing two buildings into four zones and performing construction by a difference of one day. According to the present invention, the construction method of a wall structure building such as an apartment building and a high-rise residential building comprises: a first step of plane division of dividing a plurality of households on a plane of a building into two or more zones (construction areas); a second step of wall construction of constructing a wall form, a wall reinforcing bar, and wall electric equipment for the first zone (area) of the first step; a third step of slab construction of pouring slab form, slab reinforcing bar, electric equipment, inspection and slab concrete after the second step; and a fourth step of performing the second step of wall construction and the third step of slab construction by a time difference with the first zone (area) for the second zone (area) of the first step. The second, the third, and the fourth step are repeated on an upper floor.

Description

아파트 주상복합 오피스텔 지식산업센터 등 벽식 구조 건축물의 시공방법 {Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a wall type building,

본 발명은 아파트 주상복합 오피스텔 지식산업센터 등 벽식 구조를 갖는 건설공사에서 기준층의 공기를 단축하기 위한 방법에 관한 것으로, 더욱 상세하게는 1개층의 평면을 2개 이상의 존(구역)으로 분할하여 공사규모를 작게 소형화하므로써 각 존(구역)의 공사가 빠르게 진행될 수 있도록 한다. The present invention relates to a method for shortening the air of a reference layer in a construction work having a wall structure such as an apartment complex, an office building, a knowledge industry center, and more particularly, to a method for shortening the air of a reference layer by dividing one plane into two or more zones By making the scale smaller and smaller, construction of each zone (zone) can be made faster.

또한 2개동을 4개 존으로 분할하고 존을 1일 차이로 진행하여 4일 싸이클에 1개층 골조를 완성하는 것이다.In addition, it divides two dongs into four zones, and advances zone one day difference, and completes one layer flooring in four days cycle.

한국은 세계에서 가장 많은 아파트를 보유하고 있고 현재에도 많이 시공하고 있다. 아파트 단지는 다수의 동으로 구성되고 아파트 1개동의 각 층의 평면은 다수의 세대가 거주한다.Korea has the largest number of apartments in the world and is still in construction. The apartment complex is made up of a number of buildings, and the planes of each floor of one apartment house are inhabited by many generations.

아파트 공사의 순서는 지하에서 터파기를 한 후 매트 기초를 타설하고 지하층 골조를 완성한다. 지상에서는 사람이 거주하는 세대의 골조를 만들고 실내 내부의 마감공사로 완성하여 완료된다. 주상복합 오피스텔도 아파트와 유사하게 진행된다.The order of the apartment construction is to construct the foundation of the mat after completing the terraces in the basement and complete the underground frame. On the ground, it is completed by making frame of the generation inhabited by the person and finishing the work inside the interior of the room. The residential and commercial office buildings are similar to the apartments.

골조공사는 전체 공기 및 공사비를 크게 차지하는 주요한 공종이다. 종래의 지상 골조 시공은 벽체와 바닥을 형성하기 위한 형틀을 설치하고, 벽체와 바닥을 지지하는 구조재로서 철근을 시공한 후 전기 설비 자재를 설치한 후 검측을 거쳐 콘크리트를 타설하는 과정으로 진행된다.Frame construction is a major type of construction that takes up a great deal of air and construction costs. Conventional groundframe construction is a process of installing a wall frame and a mold to form a floor, installing a reinforcing bar as a structural member for supporting the wall and the floor, installing the electrical equipment, and placing the concrete through the inspection.

예를 들어 아파트 1개동에 4개 세대가 배치된 경우, 형틀을 설치하고 철근을 배근한 후 콘크리트를 타설하여 1개 층을 완료하는데 통상 7일 내지 9일이 소요되고 있다.For example, if four generations are placed in one apartment building, it usually takes 7 to 9 days to complete a single layer by installing a mold, placing reinforcing bars, and pouring concrete.

도 1은 종래의 공법에 따라 아파트 1개 층을 시공하는 9일 사이클 공정을 나타낸 것이다. 9일 사이클 공정이란 아파트 1개 층을 시공하는데 9일이 소요된다는 것을 의미한다. 도 1에서 보는 바와 같이 종래에는 공간을 형성하는 벽과 바닥을 만들기 위해 형틀과 철근을 설치한 후 마지막 날에 1개층 전체에 대해 벽과 바닥의 콘크리트를 타설한다.FIG. 1 shows a 9-day cycle process for constructing a single apartment building according to a conventional method. The 9-day cycle means that it takes nine days to build one floor of an apartment. As shown in FIG. 1, conventionally, a mold and a reinforcing bar are installed to form a wall and a floor forming a space, and concrete and a floor are laid on the whole floor in the last day.

이러한 시공방식에 따르면 각층을 완성하는데 9일이 소요되는 9일 사이클을 나타낸다. 1일차에는 전일에 타설한 1개층의 콘크리트를 양생한다. According to this construction method, it represents a 9 day cycle which takes 9 days to complete each layer. On the first day, we cure one layer of concrete that we put on the day before.

2일차에는 양생 이후 바닥에 먹줄을 놓고 벽체 형틀과 계단 및 코어 형틀을 해체한다.On the second day, after the curing, place the food line on the floor and dismantle the wall mold, the stairs and the core mold.

3일차에는 벽체 철근을 조립하고 전기 설비는 벽체에 매립되는 자재를 부착한다. 여기서 중요한 구조재이며 많은 작업인원을 필요로 하는 공종인 벽체 철근은 1일이 소요되었다. 벽체철근은 각 실을 구획하는 칸막이 역할과 상부의 하중을 지지하는 수직 구조재의 역할을 한다.On the third day, the wall reinforcement is assembled, and the electric equipment attaches the material to be embedded in the wall. The wall reinforcement, which is an important structural material and requires a large number of workers, took one day. Wall reinforcement plays a role as a partition dividing each room and as a vertical structural member supporting the upper load.

공동주택 또는 주상복합은 벽체가 구조역할을 하는 내력벽식구조이다. 이에 따라 벽체에 철근과 콘크리트를 시공하여야 하므로 골조공사 시간이 크게 소요되는 특징이 있다.The apartment house or residential complex is the structure of the bearing wall which serves as the structure of the wall. As a result, reinforced concrete and concrete must be installed on the wall.

4일차에는 3일차에 완료된 벽체철근을 대해 콘크리트를 부어넣기 위한 벽체 형틀을 설치한다. 또한 계단 및 코어 형틀도 설치한다.On the 4th day, a wall frame for pouring concrete for the wall reinforced concrete completed on the 3rd day is installed. Stairs and core molds are also installed.

5일차에는 벽체 형틀이 마지막으로 설치 완료되고 계단 및 코어 형틀은 계속된다. 벽체가 완료되는 구간에 대해 슬라브 형틀 설치가 시작된다.On the fifth day, the wall mold is finally installed, and the stair and the core mold continue. The installation of the slab mold is started with respect to the section where the wall is completed.

6일차에는 슬라스(바닥) 형틀을 계속 설치하여 5일차에 이어 2일 만에 완료한다. 계단 및 코어 형틀도 3일 만에 완료한다.On the 6th day, the slat (bottom) frame will be installed and completed within two days following the 5th day. Stairs and core molds are completed in 3 days.

벽체와 슬라브 형틀은 설치하는 물량(수량)이 많아 작업자가 많이 투입되고 4일차부터 6일차까지 3일이 소요되었다.The wall and the slab mold were installed in large quantities (lots of workers) and took 3 days from 4th day to 6th day.

7일차에는 완성된 슬라브 형틀위에 슬라브 철근을 시공한다. 이때 전기 설비 자재도 함께 설치된다.On the 7th day, the slab reinforcement is constructed on the completed slab frame. At this time, electrical equipment is also installed.

이제 모든 작업이 완료되었으며, 8일차에는 청소 및 감리의 검측이 이루어진다. Now all work is done, and on the eighth day, cleaning and supervision are done.

9일차에는 콘크리트가 타설된다. 콘크리트는 벽체 및 슬라브, 계단 및 코어 등 1개층 전체가 하루 종일 타설된다.On the 9th day, concrete is poured. Concrete is laid throughout the entire floor, including walls, slabs, stairs and cores.

위와 같은 종래의 아파트 1개 층을 시공하는데 소요되는 9일 사이클의 문제점은 다음과 같다.The problems of the 9-day cycle required for constructing a conventional apartment as described above are as follows.

1개층 벽체와 슬라브의 콘크리트를 하루 종일 타설하는데 있어 낭비하는 시간이 크다. 1개층 전체를 타설하므로 콘크리트 타설은 10시간 이상 소요되어 오전 일찍부터 타설하면 저녁 무렵 타설이 끝난다. It takes a long time to put the concrete of 1 story wall and slab all day. Since all one floor is laid, it takes more than 10 hours to put concrete into it.

콘크리트를 타설하는 9일차에는 콘크리트 작업인부 몇 명 외에는 작업자가 들어갈 수 없어 철근 형틀 등 수많은 다른 공종은 작업을 할 수가 없다. 1개층의 한쪽 세대부터 콘크리트를 타설을 해오면, 나머지 세대는 오전에 아무런 할 일없이 자기 차례가 올 때인 오후까지 대기해야 한다. On the 9th day of pouring concrete, workers can not enter concrete workers except a few workers, so many other types of work such as reinforced concrete molds can not work. If you pour concrete from one generation on one floor, the next generation must wait until the afternoon, when your turn comes, with nothing to do in the morning.

예를 들면 101동에 4개 세대가 있고, 9층 슬라브 타설시 10월 1일 아침부터 1001호부터 콘크리트 타설을 시작한다. 레미콘 공급과 콘크리트를 위로 올리는 콘크리트 배관 파이프의 한계로 인하여, 4개 세대를 타설하지 않고 901호부터 904호 순으로 순차적으로 타설한다. 이때 901호부터 타설시 902호부터 904호는 아무런 작업을 하지 않고 콘크리트 차례가 올 때까지 대기해야 한다.For example, there are four generations in 101 dongs, and when you put slabs on the 9th floor, you start to put concrete from No. 1001 on the morning of October 1st. Due to the limit of concrete pipe piping that feeds concrete and concrete, it is installed sequentially from 901 to 904 without installing four generations. At this time, from 901 to 902, you have to wait until the concrete turn comes.

901호가 타설되면 902호로 이동한 후 901호는 다음날 콘크리트 양생이 될 때까지 작업이 없다. 따라서 901호는 10월 1일 오후부터 10월 2일 양생까지 2일간 타설 이외의 작업은 없다. When 901 is installed, it moves to 902 and there is no work until 901 is concrete curing the next day. Therefore, there is no work other than pouring 901 for two days from the afternoon of October 1 to the curing of October 2.

즉, 901호 또는 904호는 약 반나절의 휴무 대기시간이 발생하게 된다. In other words, 901 or 904 causes a waiting time of about half a day.

다음과 같은 가설을 통해 존(공구)의 규모가 커질수록 작업일수가 증가함을 알 수 있다. 아파트 101동이 층당 10개 세대로 많은 세대로 구성되면 콘크리트 타설물량도 증가한다. 9층 10개 세대 콘크리트 타설에 2일이 소요된다면 901호는 10월 1일 오전 몇 시간 타설 후 1.5일의 대기시간을 가지게 된다. 910호의 경우 10월 1일은 대기하고 10월 2일 두 번째 타설일 오후에 타설 시간을 갖게 되어 1.5일의 손실이 발생한다. The following hypothesis suggests that the number of work days increases as the size of the tool increases. If 101 apartment buildings are composed of 10 generations per floor, the amount of concrete pouring will increase. If it takes two days to put 10 generations of concrete on the 9th floor, the 901 will have a waiting time of 1.5 days after some hours of installation on October 1st. In the case of the 910, it will wait for October 1, and on the afternoon of October 2, it will have a casting time in the afternoon of the second casting, resulting in a loss of 1.5 days.

즉, 한 개층 상에 세대가 많아질수록 작업대기로 인한 손실은 증가함을 알 수 있다. In other words, it can be seen that as the number of households increases on one floor, the loss due to waiting for work increases.

골조공사는 대부분 작업자에 의해 진행되는 인력에 의한 노동집약적 작업이다. 철근과 형틀 작업자는 하루에 수십 명이 투입된다. 이들은 단체로 투입되고 이동하므로 자기 차례의 공정이 마무리 되지 않으면 다음 공정이 투입되지 않는다. 콘크리트 타설 공정이 완료되지 않으면 철근작업이 투입되지 않는다. 따라서 작업인원수의 규모가 커지므로 작업투입 철수의 움직임이 빠르지 않는 속성을 가지게 된다.The construction of the frame is a labor intensive work by the manpower carried out by most workers. Reinforcements and molders work for tens of people a day. These are put into groups and moved, so that if the process of their turn is not completed, the next process is not put into operation. If the concrete pouring process is not completed, no reinforcing work will be applied. Therefore, since the number of workers increases, the movement of work input withdrawal is not fast.

1일차 양생에서도 세대별로 대기시간이 발생하는 것은 앞서 기술한 바와 동일하다.In the first day of curing, the waiting time for each generation is the same as described above.

2일차 먹매김 작업에서는 소수인원이 투입된다. 콘크리트 타설과 마찬가지로 901호부터 먹줄놓기가 진행되므로 904호는 대기해야 한다. 먹줄 작업자가 여러명 투입되면 동시에 작업이 진행되고 완료될 수 있지만, 일반적으로 먹줄 작업자는 소수만 투입된다.In the 2nd day feeding work, a small number of people are put in. As with concrete pouring, it is necessary to wait for the 904 since the laying of the ladder will proceed from 901. When multiple feeders are fed, work can be done and completed at the same time, but only a few feeders are usually fed.

3일차 벽체철근 조립에서는 수십 명의 철근공이 작업을 한다. 그럼에도 불구하고 철근작업은 할 일이 많아 각 세대를 동시에 작업할 수가 없고 순차적으로 시공한다. 1개층을 반나절에 동시에 작업하려면 많은 수의 철근공이 하루에 출근해야 하는데 작업자를 구하기가 쉽지 않고 작업자 개인입장에서는 하루에 시공하는 물량이 줄어들어 수입이 줄어든다. In the 3rd day wall reinforcing assembly, dozens of barrels work. Nonetheless, since there is a lot of work to do for rebar works, each generation can not work at the same time. In order to work on one floor at the same time in half a day, a large number of steelworkers must go to work one day, but it is not easy to find a worker.

또한 철근작업자 다수가 있는 상태에서 다른 형틀 등의 공종이 투입되면 작업의 충돌과 혼재가 되기 때문에 철근 작업이 어느 정도 완성된 후 다음공정이 투입된다.In addition, when a large number of steel workers are employed and other types of molds are put in, the work will be mixed with the work.

또한 다음날에는 철근작업이 없으므로 102동 또는 다른 지역의 현장으로 이동해야 하므로 생산성이 저하된다. 이러한 원리로 철근 또는 형틀공은 하루 또는 이틀에 할 수 있는 적정한 인원이 투입된다.Also, the next day there will be no rebar work, so productivity will be reduced as it will have to move to site 102 or other area. With this principle, the rebar or the mold ball is put in the proper number of people to do in a day or two.

철근공이나 형틀공은 101동에서만 작업하는 것이 아니라 102동 103동 등으로 순환적으로 작업을 한다. 101동에서 매일 동일한 작업물량이 있는 것이 아니기 때문이다. 그러나 작업자 순환 사이클에 잘 돌아가면 매일 작업을 할 수가 있으나 동별 일정이 어긋나는 경우 또는 작업이 겹치는 경우 대기시간이 발생하게 된다. A steelworker or a mold ball does not work only in the 101st corridor but in the 102nd 103rd corridor. This is because there is not the same amount of work every day in the East. However, if worker circulation cycle is good, work can be done every day, but waiting time will occur when work schedule overlap or work overlap.

또한 비오는 날과 같은 기후의 영향과 토요일 일요일 명절 휴무일의 영향으로 1년중 약 75~85일 정도는 작업을 하지 않는 된다. 일반적으로 1년 365일중 75%인 273일 정도 작업한다. 일기예보상 오전에 비가 내리고 오후에 맑은 경우, 콘크리트 타설은 다음날로 연기된다. 이에 따라 금일 오후에는 작업이 없는 휴무시간이 발생하게 된다.In addition, due to the influence of the climate, such as rainy days, and the effect of holiday days on Saturdays and Sundays, about 75 to 85 days in a year do not work. Generally, I work about 273 days, 75% of 365 days a year. Reward Compensation If it rains in the morning and clear in the afternoon, the concrete pouring will be postponed to the next day. As a result, there will be no working hours in the afternoon.

이상과 같은 아파트 1개동의 9층 전체를 시공하는데 9일이 소요되는 것은 철근공과 형틀공을 100명이상 동시에 투입할 수 없기 때문에 적정인원이 순서대로 차근차근 901호부터 작업하기 때문이다. The reason why it takes 9 days to construct the entire 9 floors of one apartment building is because it is not possible to put more than 100 people at the same time.

몇 명이 투입되는 먹매김이나 콘크리트 타설이 있는 반면 수십 명이 투입되는 철근과 형틀공사로 복잡하게 진행된다. 이 과정에서 공종별로 대기시간이 발생하게 되고 세대수가 많을수록 철근 형틀 콘크리트 타설 같은 공종별 사이클이 길어지는 특징을 나타낸다. There are several people who put in earthenware and concrete, but it is complicated by rebar and mold work which dozens of people put in. In this process, waiting time is generated for each type of work, and as the number of households is increased, the cycle of each type of work such as reinforced concrete mold casting becomes longer.

건설공사의 최소단위는 하루이다. 공사는 작업자의 출근에 의해 이루어지고 작업자는 출퇴근에 많은 시간을 소비한다. 따라서 특정일에 오전에 철근 작업이 끝나는 경우에도 다음 공정인 형틀공은 오후에 투입되지 않고 다음날 출근한다. The minimum unit of construction work is one day. Construction work is done by worker's work, and workers spend a lot of time on commuting. Therefore, even if the rebar work ends in the morning on a certain day, the next process will not be put in the afternoon and will go to work the next day.

오후 작업 몇 시간을 위해 출퇴근을 할 수 없기 때문이다. 이러한 최소 1일 단위 작업의 특성으로 인하여 대기시간이나 버려지는 시간이 발생하고 아파트 골조 수십 개층을 모으면 그 양이 많다.This is because I can not commute for some hours in the afternoon. Due to the characteristics of the minimum daily work, waiting time or waste time occurs, and when dozens of apartment frames are collected, the amount is large.

위와 같은 문제점을 해결하기 위하여 본 발명에서는 아파트 주상복합 오피스텔 지식산업센터 등 벽식 구조를 갖는 건설공사에서 1개층의 공사 단위를 최소화하는 개념을 도입하여 작업 대기시간을 줄이고 공사를 빠르게 진행할 수 있도록 하여 전체 공사기간을 줄이는 공사방법을 제공하고자 한다.In order to solve the above problems, the present invention introduces the concept of minimizing the construction unit of one floor in the construction work having the wall structure such as apartment building, office building, office building, knowledge industrial center, etc., And to provide a construction method for reducing the construction period.

또한 본 발명은 철근과 형틀 등 작업자가 동일시간에 보다 많은 량의 작업을 할 수 있도록 작업량과 작업의 순서를 배분하여 생산성을 높이는 공사방법을 제공하고자 한다.In addition, the present invention provides a construction method for increasing productivity by allocating workload and order of work so that an operator such as a rebar and a mold can perform a larger amount of work at the same time.

또한 2개동을 4일 싸이클로 골조를 완성하는 것이다.In addition, it will complete the 4-day cycle frame of two buildings.

상술한 기술적 과제를 해결하기 위해 본 발명은 공동주택, 아파트, 주상복합, 오피스텔, 지식산업센터 등의 벽식 내력 구조를 갖는 골조공사에서, In order to solve the above-mentioned technical problems, in the present invention, in a frame construction having a wall strength structure such as a multi-house, an apartment, a residential complex, an office building,

1개동의 평면에서 다수 세대를 2개 또는 3개 이상의 존(zone), 공사구역으로 분할하는 평면분할의 제1단계 ;A first step of planarization in which a plurality of generations are divided into two or three or more zones and construction zones in one planar plane;

상기 제1단계의 첫번째 존(구역)에 대하여 벽체 형틀, 벽체 철근, 벽체 전기 설비 를 시공하는 벽체시공의 제2단계 ;A second step of wall construction for constructing a wall mold, a wall reinforcing bar, and a wall electric installation for the first zone (zone) of the first step;

제2단계에 이어 슬라브 형틀, 슬라브 철근, 전기 설비, 검측 및 슬라브 콘크리트를 타설하는 슬라브 시공의 제3단계 ;Following the second step, the third stage of slab construction, in which slabs, slab reinforcement, electrical equipment, inspection, and slab concrete are installed;

상기 제1단계의 두 번째의 존(구역)에 대하여 첫 번째 존(구역)과 시간차를 두고 벽체시공의 제2단계와 슬라브 시공의 제3단계를 시공하는 제4단계 ; 및A fourth step of constructing a second stage of wall construction and a third stage of slab construction with a time difference from the first zone (zone) for the second zone (zone) of the first stage; And

상기 제2, 3, 4단계를 위층에서 반복하여 시공하는 것을 특징으로 한다.And the second, third, and fourth steps are repeatedly performed on the upper layer.

또한 판상형 아파트에 있어서 2개동 짝으로 하여 1개동 2개존 2개동 4개의 존으로 분할하고 존별 1일 차이로 골조공사를 완성할 수 있도록 하되 1개층 골조를 4일 싸이클로 완성해가는 것을 특징으로 한다.It is also characterized in that it is divided into two zones, one zone, two zones, two zones, and four zones in a flat type apartment, and the frame construction can be completed by one day difference according to zones, but the one floor zone is completed with four days cycle.

그 방법은 아파트 공사단위를 소형화하여 공사방법 및 작업자 출역 및 이동의 융통성과 효율성을 높이는 것이다. 또한 평면분할과 순차적 시공의 소형화 및 연속화 방법을 통해 날씨 및 공휴일 등에 의한 영향을 최소화하고 자재 납품 회사의 상태 및 공사에 투입되는 작업자들의 근무시간 및 사회적 업무 인식 형태에 변화에 따른 적응성과 가변성을 크게 높이는 것이다.The method is to miniaturize the unit of the apartment building to increase the flexibility and efficiency of the construction method and worker moving and moving. In addition, through the miniaturization and sequencing method of planar division and sequential construction, it is possible to minimize the influence of weather and holidays, and to adapt to the change of the worker's working time and social work perception type It is the height.

구체적으로는 아파트 2개동을 짝으로 하여 평면을 2개존으로 분할하여 2개동 총 4개존을 구성한다. 4개존의 시공순서는 24가지가 발생하며 그 중 하나 또는 혼합으로 진행하며 존별 1일차이로 진행하는 공사방법을 포함한다.Specifically, the apartment is divided into two living quarters with two apartments in pairs, and a total of four living quarters are constructed. There are 24 kinds of construction orders of the four survivors, including one or a mixture of them.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

아파트 1개층의 콘크리트 타설 회수를 1회에서 2회 이상으로 나누어 소형화 타설한다. 9층에 4개 세대가 있는 경우, 901호와 902호를 묶어 A존, 903호와 904호를 묶어 B존이라고 명칭하기로 한다. 종래에는 901호부터 904호까지 4개 세대의 콘크리트를 하루에 다 같이 타설하였다. The number of concrete piling of one layer of apartment is divided into one or more than two times, and miniaturization is laid. If you have four generations on the 9th floor, you will group 901 and 902 together to name A zone, 903 and 904, and name it B zone. In the past, four generations of concrete from 901 to 904 were laid together one day.

그러나 본 발명에 따르면 9층 평면을 2개로 나누어 901호와 902호의 A존을 대상으로 콘크리트를 타설하므로 콘크리트 타설 물량이 절반으로 줄어들고 타설시간도 따라서 약 반으로 줄어든다. 나머지 903호와 904호의 B존의 콘크리트는 A존보다 하루 또는 이틀 후에 콘크리트를 타설한다. 종래에는 전체 타설에 12시간이 소요되었다면 A존이나 B존의 콘크리트 타설은 6시간이 소요되어 공사 사이클이 빨라진다.However, according to the present invention, since the 9-story plane is divided into two and the concrete is poured into the A zone of No. 901 and No. 902, the amount of poured concrete is reduced to half and the pouring time is also reduced to about half. Concrete in zone B of the remaining 903 and 904 cast concrete a day or two later than Zone A. Conventionally, if it takes 12 hours for the whole casting, it takes 6 hours to put the concrete in zone A or zone B, and the construction cycle is accelerated.

종래에는 비가 오전에 오는 경우, 오후에 타설을 하지 않고 다음날 종일 타설하였다. 또한 토요일 오전에 콘크리트 타설 전까지의 작업이 완료되는 경우, 일요일에는 레미콘이 공급되지 않으므로 토요일 오후를 건너뛰어 월요일 아침에 타설을 하였다. 그러나 본 발명에 따르면 존별 소형화로 인하여 반나절 콘크리트 타설이 되므로 오전에 비가 오는 경우, 토요일 오전에 타설 준비가 되는 경우 오후에 타설이 가능하여 종래에 비해 반나절의 시간을 단축하는 효과가 있다. In the past, when rain came in the morning, we poured all day without putting in the afternoon. Also, if work is completed before the concrete pouring on Saturday morning, no concrete is supplied on Sunday, so I skipped Saturday afternoon and put it on Monday morning. However, according to the present invention, due to the miniaturization of the zone, the half-day concrete is poured. Therefore, when it is raining in the morning, if it is ready to be installed on the morning of Saturday, it can be installed in the afternoon.

이에 따라 종래에는 901호의 A존 타설시 903호와 904호의 B존은 대기상태였으나 본 발명에 따르면 B존은 A존보다 2일이 늦은 공정이므로 철근이나 형틀작업자들이 B존에서 작업을 할 수 있어 작업대기가 발생하지 않아 시간낭비가 없다.Conventionally, according to the present invention, the B zone is two days late from the A zone, so that the rebar or the mold operator can work in the B zone There is no waste of time because no job waiting occurs.

철근공이나 형틀공은 같은 101동에서 A존과 B존을 번갈아 가며 연속적으로 작업을 할 수 있다. 콘크리트를 타설하는 날에도 타설 세대이외의 다른 세대에서 작업이 가능하거 이에 따라 1주일에 작업하는 생산량이 증가한다.A steelworker or a mold ball can work continuously with the A zone and the B zone in the same 101st turn alternately. On the day of pouring concrete, it is possible to work in other generations other than the piling generation, so the production amount to work in a week increases.

종래에는 작업의 최소단위가 하루단위이므로 착수나 완료시 남는 시간은 버려지게 된다. 오후 3시에 벽체 철근 작업이 끝나는 경우, 다른 아파트 동으로 이동하여 철근작업을 하기가 쉽지 않다. 이동과 세팅에 시간이 소요되고 벽체 철근 작업을 할 수 있는 상태의 아파트 동이 항상 있는 것은 아니기 때문이다.Conventionally, since the minimum unit of work is one unit, the remaining time at the start or completion is discarded. If the wall work finishes at 3:00 pm, it is not easy to move to another apartment building and work on the rebar. Moving and setting takes time, and there is not always the apartment which can work on the wall reinforcement.

그러나 본 발명에 따른 A존과 B존의 평면 분할은 아파트 1개에서 다른 세대로 이동하여 작업을 할 수 있는 경우의 수가 많고 이동시간도 단축되고 연속적으로 작업을 할 수 있게 된다.However, according to the present invention, the planar division of the A zone and the B zone is performed from one apartment to another, and the number of cases in which the work can be performed is shortened and the moving time is shortened, so that the work can be continuously performed.

종래에는 철근이나 형틀공이 101동에서 102동으로 이동하면서 작업 사이클을 맞추어가면서 작업을 해야 했다. 본 발명에 따라 평면분할로 공구가 분할되면 101동을 2개 이상의 동으로 분할하는 효과가 있어 101동 내에서의 이동 뿐만 아니라 102동의 A, B존으로 이동할 수 있어 이동의 폭과 대상이 많아진다. 이에 따라 대기시간 없이 연속적인 작업이 가능해진다.In the past, reinforcing bars and molds had to move from 101 to 102, while working along the cycle. According to the present invention, when the tool is divided into two planes, the tool 101 is divided into two or more dies. As a result, it is possible to move not only the dies 101 but also the 102 dies A and B zones, . Thus, continuous operation without waiting time becomes possible.

종래에는 하루단위로 공종이 착수되고 완료되었으나, 본 발명에 따라 존(구역)의 소형화의 경우 오전 오후의 반일 단위로 작업 착수 또는 완료가 가능해진다.In the past, work has been started and completed on a daily basis, but according to the present invention, in the case of miniaturization of a zone (zone), work can be started or completed in half a day in the afternoon.

이상과 같이 본 발명에 따라 평면분할로 A존이나 B존의 철근 형틀 콘크리트의 작업시간이 줄어들게 되므로, 작업대기 시간이 줄어들고 반일단위로 공사를 진행할 수 있어 1개층의 공사일수가 종래의 7일내지 9일에서 4일로 단축된다. As described above, according to the present invention, since the working time of the reinforced concrete frame of the A zone or the B zone is reduced by the planar division, the work waiting time is reduced and the work can be carried out in units of half a day, It is shortened from 9 days to 4 days.

골조공사의 층당 작업일수가 9일에서 4일로 단축되면, 골조공사 기간 단축뿐만 아니라 뒤따라오는 수십 개의 마감 및 인테리어 공사와 전기 설비공사의 생산성도 높아진다. If the number of working days per floor of the frame construction is shortened from 9 days to 4 days, not only the frame construction period is shortened but also the following dozens of finishes and the productivity of the interior construction and the electric installation work are improved.

공사순서대로 같은 속도로 연속적으로 올라가면서 시공하는 적층식 마감공사 택트 공정관리에 있어서, 택트 주기가 7~9일 사이클에서 4일 사이클로 단축되면 층당 작업일수가 짧은 도장공사, 방수공사, 타일공사, 가구설치 및 전기, 설비의 다수 공종의 공사중지, 철수 후 재출근 등 대기시간이 줄어들어 생산성이 향상된다.Laminar-type finishing work which is carried out while continuously climbing at the same speed in the order of construction. When the tact cycle is shortened from 7 to 9 days to 4 days in the tact process management, painting work, waterproofing work, The productivity is improved by reducing standby time such as installation of furniture, stoppage of construction of many kinds of facilities, and re-commissioning after withdrawal.

같은 아파트 동에서 9일 사이클에서 4일 사이클로 동일한 작업을 반복하면, 작업자의 학습효과 습숙효과로 공사 속도가 더욱 빨라진다. 또한 작업자는 안정적으로 높은 생산성을 나타내므로 타 현장으로 이동하거나 이탈이 발생하지 않아 동일한 공사속도를 유지할 수 있다. 생산성이 높지 않으면 작업자가 다른 현장으로 이탈하여 인원이 부족하거나 신규 작업자가 많은 경우, 공사일수가 증가하게 되는 현상을 제거한다.If the same operation is repeated in the same apartment building from the 9th cycle to the 4th cycle, the construction speed becomes faster due to the learning effect of the operator. Also, since the worker shows stable productivity, it can maintain the same construction speed because it does not move to another site or escape. If the productivity is not high, it will eliminate the phenomenon that the number of work days is increased when the worker moves to another site and there is a shortage of personnel or a lot of new workers.

생산성이 향상되면 동일한 인원이 같은 시간에 더 많은 작업을 할 수 있으므로 시공사는 보다 낮은 가격에 공사를 하도급 할 수 있어 골조 공사비가 절감된다. 또한 마감 및 전기 설비공사의 생산성도 일정부분 향상되므로 전체 공사비도 낮아진다.As the productivity improves, the same person can do more work at the same time, so the contractor can subcontract the construction at a lower price, thus reducing the construction cost of the frame. In addition, the productivity of the finishing and electrical equipment construction is improved to some extent, so the overall construction cost is also lowered.

아파트 공사는 공사금액이 크므로 금융비용이나 이자도 크다. 공사기간이 단축되면 공종별 단가, 관리비, 급여 및 이자 등 프로젝트 전체 비용이 낮아지는 효과를 갖는다.Because the construction cost of the apartment building is large, the financial cost and the interest rate are large. If the construction period is shortened, the overall cost of the project, such as unit price, management fee, salary and interest, will be lowered.

본 발명에 따르면 온도, 비(우수), 바람 등 기후적인 요소와 건설장비, 전력, 인력, 자재공급 등의 리스크를 최소화하고 운영 효율을 높임으로써 공기 및 원가를 크게 단축, 절감함으로써 작업자, 협력회사, 시공사, 발주자 등 공사관계자 모두의 이익을 극대화하여 적극적인 공사참여를 유도하게 된다.According to the present invention, by minimizing risks such as temperature, rain (excellent), wind, and construction equipment, power, manpower, and material supply, and by improving operational efficiency, the air and cost are greatly shortened and reduced, , Construction companies, contractors, and other stakeholders.

본 발명에 따르면 판상형 'ㄱ'자 형태 또는 'ㅡ'자 아파트 기준층 골조공사를 4일 싸이클로 완성한다. According to the present invention, a 4-day cycle is completed for the construction of a plate-shaped 'a' shaped or 'ㅡ' apartment base layer.

본 발명에 따른 효과는 골조공사를 작업일 기준 4일 싸이클로 완성하여 공기를 단축되며 작업자의 출역 손실이 최소화되며 소규모 공사의 빠른 반복으로 인한 학습효과 습숙효과를 통해 작업생산성을 크게 높아지며, 골조공사 공기를 단축하고 인력 장비 자재 관리비 금융비용 등의 제반 공사비가 낮아진다. 또한 안정되고 연속적이고 반복적인 작업에 따라 품질 및 안전성이 높아진다.The effect according to the present invention is to shorten the air by completing the frame construction with a cycle of 4 days as a work day, minimizing the worker's service loss and greatly improving work productivity through the effect of learning effect due to rapid repetition of small construction, And the construction cost of manpower equipment, material management costs, etc. will be lowered. In addition, the quality and safety are enhanced by stable, continuous and repetitive work.

도 1은 종래의 아파트 9일 사이클 골조공사 공정표이다.
도 2 내지 도 3은 본 발명에 의한 아파트 평면분할을 통한 골조공사 작업일수 단축의 업무 흐름도이다.
도 4 내지 도 5는 본 발명에 의한 아파트 평면을 A존과 B존으로 분할한 한 예이다.
도 6 내지 도 7은 본 발명에 의한 아파트 평면을 A존과 B존 그리고 버퍼존으로 분할한 한 예이다.
도 8은 본 발명에 의한 아파트 골조공사의 4일 사이클 공정표의 제 1 예이다.
도 9는 본 발명에 의한 아파트 골조공사의 4일 사이클 공정표의 제 2 예이다.
도 10 내지 도 11은 본 발명에 의한 아파트 골조공사의 4일 사이클 공정을 갖는 경우의 층별 존별 공사일정의 예이다.
도 12는 종래의 아파트 골조공사 층당 9일 사이클 골조공사의 전체 공기 도표의 일예이다.
도 13은 본 발명에 의한 아파트 골조공사 층당 5일 사이클 골조공사의 갖는 경우의 전체 공기 도표의 일예이다.
도 14는 본 발명에 의한 아파트 5일 사이클 골조공사와 종래의 9일 사이클 골조공사의 전체 공기의 차이를 비교한 도표이다.
도 15 내지 도 16은 본 발명에 의한 판상형 아파트 기준층 골조공사 4개존 분할에 따른 4일 싸이클 공사방법의 흐름도이다.
도 17 내지 도 19는 본 발명의 실시예 적용을 위한 판상형 아파트 공사의 예이다.
도 20 내지 21은 본 발명에 의한 판상형 아파트 1개동을 A와 B의 2개의 존으로 분할하고 각 존은 4일 싸이클, 존 간은 2일차 공정표이다.
도 22는 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 1일차의 공정표이다.
도 23은 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 3일차의 공정표이다.
도 24는 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 1일차의 공사방법 설명도이다.
도 25는 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 1일차의 9층과 10층의 일별 공사방법 설명도이다.
도 26은 본 발명에 의한 판상형 아파트 1개동의 평면을 2개존으로 분할한 예이다.
도 27은 본 발명에 의한 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할한 예이다.
도 28은 본 발명에 의한 또 다른 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할하고 4일 싸이클 시공의 예이다.
도 29는 본 발명에 의한 또 다른 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할하고 4일 싸이클 시공의 평면도 및 단면도의 예이다.
도 30내지 도 40은 본 발명에 의한 또 다른 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할한 후 24가지의 경우를 갖는 존별 공사순서 순열의 예이다.
FIG. 1 is a process chart of a conventional 9-day apartment cycle construction work.
FIGS. 2 to 3 are workflow diagrams for reducing the number of work days for frame construction work by dividing an apartment flat according to the present invention.
Figs. 4 to 5 show an example of dividing an apartment flat according to the present invention into A zone and B zone.
6 to 7 show an example of dividing the apartment plane according to the present invention into A zone, B zone and buffer zone.
Fig. 8 is a first example of a four-day cycle schedule of an apartment frame construction according to the present invention.
Fig. 9 is a second example of a four-day cycle schedule of an apartment frame construction according to the present invention.
Figs. 10 to 11 are examples of construction schedule for the floor according to the present invention when the apartment frame construction has a four-day cycle process.
FIG. 12 is an example of the entire air chart of a 9-day cycle frame construction per a conventional apartment frame construction work.
FIG. 13 is an example of the entire air chart in the case of the 5-day cycle frame construction per apartment framing construction layer according to the present invention.
FIG. 14 is a chart comparing the total air difference between the 5-day apartment cycle construction according to the present invention and the conventional 9-day cycle construction work.
15 to 16 are flowcharts of a four-day cycle construction method according to the present invention, in which the four-zone partitioning of a flat-plate-type apartment base layer frame construction is performed.
17 to 19 show an example of a plate-shaped apartment construction for application of the embodiment of the present invention.
Figs. 20 to 21 show one plate-shaped apartment block according to the present invention divided into two zones A and B, where each zone is a four-day cycle and zone is a two-step process table.
Fig. 22 is a process chart of the second day difference between the zone and the first day in the same house within the same town in the construction of the reference floor frame in the two flat-type apartments according to the present invention.
Fig. 23 is a process chart of the second day difference between the zone and the third day in the same house within the same building of the base layer frame construction in two planar type apartments according to the present invention.
Fig. 24 is an explanatory diagram of the construction method for the second day of the second day of stay and the first day of the same day in the same building in the same building construction of the base floor frame construction in two planar type apartments according to the present invention.
Fig. 25 is an explanatory view showing the daily construction work of the 9th and 10th floors in the same building within the same building in the two floor-type apartment buildings according to the present invention, in the same day of the second day of stay and the first day of the same day.
Fig. 26 is an example in which the plane of one flat plate-type apartment according to the present invention is divided into two rooms.
Fig. 27 shows an example in which two pairs of plate-shaped apartments according to the present invention are divided into four living quarters of ABCD.
Fig. 28 shows an example of four-day cycle construction in which two pairs of another flat type apartment according to the present invention are divided into four living quarters of ABCD.
29 is an example of a plan view and a cross-sectional view of a four-day cycle construction in which two pairs of planar type apartments according to the present invention are divided into four living quarters of ABCD.
FIGS. 30 to 40 are examples of the sorting work order permutations having twenty-four cases after dividing the two pairs of the different plate type apartments according to the present invention into four living quarters of ABCD.

이하, 본 발명에 따른 아파트 골조공사에 있어서 평면분할에 의한 소형화 골조공사를 통한 공기단축 방법을 첨부도면을 참조하여 상세히 설명한다.Hereinafter, an air shortening method through a miniaturized frame construction by plane division in an apartment frame construction according to the present invention will be described in detail with reference to the accompanying drawings.

도 2 내지 도 3은 본 발명의 일실시예에 따른 아파트 평면분할에 의한 소형화 골조공사의 업무 흐름도이다.FIGS. 2 to 3 are flowcharts of a miniaturized frame construction according to an embodiment of the present invention.

먼저 도 2를 참조하면, 먼저 아파트 단지공사의 여러 동의 아파트 중 1개동의 입면을 2개 이상으로 분할한다(S10). Referring to FIG. 2, first, the elevation of one of the apartment buildings of the apartment complex construction is divided into two or more sections (S10).

평면분할의 예로서 도 4를 참조하면, 아파트 또는 주상복합에서 1개동을 평면을A존과 B존으로 분할한다. 1개층이 2개의 타설 존으로 분할되고 콘크리트를 2회 시간차를 두고 타설한다. Referring to FIG. 4 as an example of the plane splitting, one plane is divided into A zone and B zone in an apartment or residential complex. One layer is divided into two casting zones and concrete is poured with a time difference of two times.

도 5를 참조하면 존별 타설구역을 나타낸 것이며, 상부는 A존 타설구역, 하부는 A존 타설구역을 나타낸 것이다. 존별 공사규모가 소형화되었으므로 철근 형틀 전기설비 및 콘크리트 공사는 하루 또는 이틀정도의 차이를 두고 A존과 B존을 번갈아가면 연속적으로 빠르게 진행되는 특징을 나타내게 된다.Referring to FIG. 5, there is shown a pit area by a zone, the upper part shows the A zone pitting area, and the lower part shows the A zone pitting area. As the scale of the construction by zone is miniaturized, the electric plant and the concrete construction of reinforced concrete molds are characterized by rapid progression in succession when the A zone and the B zone alternate with one or two days difference.

바람직하게는, 도 4처럼 본 공법에 적용되는 컨스트럭션 죠인트는 1일 타설 가능 콘크리트 물량 조건 등 콘크리트, 철근 , 형틀 등의 작업물량 밸런스를 최대한 충족시키면서도 건물 외장에 영향을 최소화 시킬 수 있는 부위에 수밀기능을 충족시키는 디테일을 적용하여 설치하는 것을 특징으로 하는 공사방법이다.Preferably, as shown in FIG. 4, the construction joint applied to the present method can be installed for 1 day. The watertightness function can be applied to the portion that minimizes the influence on the exterior of the building while satisfying the balance of work amounts of concrete, And a detail that satisfies the above-mentioned requirement is applied.

또 다른 평면분할의 예로서 도 6을 참조하면, 1개동 1개층에 5개 세대가 있는 경우, 중앙의 903호 세대는 버퍼존(Buffer Zone)으로 작용한다. 버퍼존이란 중앙의 903호 세대가 상황 및 여건에 따라 A존과 같이 콘크리트가 타설되거나 또는 B존과 같이 콘크리트를 타설하는 완충지대 역할을 한다. 이에 따라 버퍼존은 융통성과 유연성을 가져 공사의 리스크를 흡수하는 역할을 하게 된다. Referring to FIG. 6 as another example of the planar division, when there are five generations in one floor and one floor, the central 903 generation serves as a buffer zone. The buffer zone is a buffer zone where the central 903 generation is poured with concrete such as A zone or poured concrete like B zone according to the situation and circumstances. Accordingly, the buffer zone has flexibility and flexibility to absorb the risk of construction work.

도 7을 참조하면, 상부 도표는 버퍼존이 A존과 콘크리트가 타설되는 경우의 타설범위이다. 하부 도표는 버퍼존이 B존과 같이 콘크리트가 타설되는 범위를 나타내고 있다.Referring to FIG. 7, the upper chart is a range of a pit in the case where the buffer zone is paved with the A zone and concrete. The lower chart shows the range in which the concrete is poured like the buffer zone in the B zone.

도 6의 5세대 조합처럼 물량의 밸런스를 맞추기 어려운 경우에는 중앙세대를 버퍼존으로 하여 중앙세대의 좌우측에 컨스트럭션 죠인트를 형성시킴으로써 버퍼존을 포함한 좌측 2세대 또는 버퍼존을 포함한 우측 2세대를 묶어 타설 가능토록 융통성을 부여함으로써 공사 인력 및 장비의 효율을 극대화함으로써 더욱 더 공사 진행을 촉진시키는 것을 특징으로 한다.In the case where it is difficult to balance the quantity of water as in the case of the fifth generation combination shown in Fig. 6, the second generation including the buffer zone or the second generation including the buffer zone may be bundled by forming the construction joints on the left and right sides of the middle generation, It is characterized by maximizing the efficiency of construction manpower and equipment by giving flexibility so as to further promote construction progress.

다음으로 A존에 대하여 골조를 시공하는데 들어가는 건축재료의 수량의 범위를 설정한다(S20). 예를 들면 A존(2개 세대)에 들어가는 벽체 철근, 벽체 형틀, 슬라브 형틀, 슬라브 철근, 콘크리트에 대하여 수량의 범위를 설정한다. 예로 A존의 콘크리트 타설 물량은 300㎥은 이하, 300㎥를 초과하여서는 안된다.Next, a range of the quantity of building material entering the frame A is set for the zone A (S20). For example, the range of quantity for wall reinforcement, wall frame, slab frame, slab reinforcement, and concrete entering A zone (two generations) is set. For example, the amount of concrete pouring in Zone A should not exceed 300m3 and not exceed 300m3.

이후 A존에 대하여 실제 도면을 보고 수량 또는 물량을 산출한다(S30). 예를 들면 A존의 벽체 철근, 벽체 형틀, 슬라브 형틀, 슬라브 철근, 콘크리트에 대하여 도면상의 실제 수량을 산출한다. 이것을 적산 또는 수량산출이라고 하며 벽체철근은 100톤, 벽체 형틀은 300㎡, 콘크리트는 280㎥ 등이다.Thereafter, the actual drawing is viewed with respect to the A zone, and the quantity or quantity is calculated (S30). For example, the actual quantity on the drawing is calculated for wall reinforcement of A zone, wall frame, slab frame, slab reinforcement, and concrete. This is called integration or quantity calculation. The wall reinforcement is 100 tons, the wall frame is 300㎡, and the concrete is 280㎥.

위와 같이 물량이 산출되면, 이러한 재료를 설치하는데 필요한 작업자의 인원수를 산출한다(S40). 한명의 작업자가 하루에 설치할 수 있는 수량을 산출하여 철근이나 형틀의 수량을 나누면 필요한 작업자수가 산출된다.When the amount of water is calculated as above, the number of workers required to install such a material is calculated (S40). The number of workers required can be calculated by dividing the quantity of reinforcing bars or molds by calculating the quantity that one operator can install per day.

이상과 같이 A존을 시공하는데 필요한 철근 형틀 전기설비 콘크리트 수량과 인원이 산출되면, 상기 산출된 데이터가 4일만에 콘크리트 1개층을 시공할 수 있는지 종합 판단한다(S50). 만약 4일을 초과한다면 존을 더욱 작게 분할하여 층당 공사일수를 단축한다.As described above, when the quantity and the number of the concrete of the reinforcing frame electric equipment necessary for constructing the zone A are calculated, it is judged whether the calculated data can construct one layer of the concrete in four days (S50). If it exceeds 4 days, the zone is divided into smaller zones to shorten construction days per floor.

이하 공정표를 작성하는 과정을 설명한다. 골조공사의 작업목록을 작성한다. 주요한 작업목록은 먹매김, 벽체형틀 아래층에서 위층으로 올리기(인양), 벽체철근 조립, 전기 설비 부품 설치, 슬라브 형틀 조립, 슬라브 철근 조립, 검측, 콘크리트 타설, 자재 인양 등이다(S60).Hereinafter, the process of preparing the process chart will be described. Create a task list for framing work. (S60). The main task list is (S60). (S60) The main task list is to raise up (lift up) the floor from the lower layer of the wall formwork, to assemble the wall reinforcement, to install the electric equipment parts, to construct the slabs, to assemble the slabs.

상기 단계에서 작업목록이 작성되면 다음으로 작업의 순서를 결정한다. A존 골조를 시공하는 작업의 주요순서는 벽체 형틀 및 철근 조립, 슬라브 형틀 및 철근 조립, 콘크리트 타설로 진행된다(S70).When the task list is created in the above step, the order of the task is determined next. The main procedure for constructing the A zone frame is to proceed with wall mold and steel assembly, slab frame and steel assembly, and concrete pouring (S70).

상기 단계에서 작업목록이 작성되고 작업 순서가 결정되면, 각각의 작업에 소요되는 시간을 산출한다. 설치해야 하는 벽체철근의 소요시간은 철근의 수량을 작업자의 생산성과 투입인원수로부터 산출된다. 콘크리트 타설시간은 콘크리트 수량을 1시간에 타설할 수 있는 수량으로부터 결정된다(S80).When the task list is created and the task sequence is determined in the step, the time required for each task is calculated. The time required for the wall reinforcement to be installed is calculated from the productivity of the worker and the number of workers input. The concrete pouring time is determined from the quantity of concrete pouring that can be placed in one hour (S80).

이상과 같이 작업목록과 작업순서 그리고 작업시간이 산출되면, 아파트 1개동의 1개층의 A존 골조공사를 완성하는데 소요 작업일수를 산출한다. 1개층의 표준공정표인 사이클 공정을 작성한다. 본 발명에 따르면 A존의 층당 작업일수는 4일이내이다(S90).When the work list, the work order, and the work time are calculated as described above, the number of working days is calculated in order to complete the A zone frame construction of one floor of one apartment building. Create a cycle process that is one of the standard process charts. According to the present invention, the number of working days per A zone is within 4 days (S90).

이상으로 일반적으로 30개월이 소요되는 아파트 공사에서 전체공기의 많은 부분을 차지하는 지상층 세대 골조공사의 소형화 단위 공정이 작성되면 전체공사기간을 산출한다(S100).The total construction period is calculated (S100) when the miniaturization unit process of the ground-level generation frame construction, which occupies a large part of the total air, is completed.

아파트 공사는 터파기, 기초 타설, 지하층 골조공사, 지상층 골조공사, 마감 및 인테리어 공사 순서로 진행한다.The apartment construction will be carried out in the following order: terra cotta, foundation casting, underground framing, ground framing, finishing and interior construction.

공사기간이 적정하면, 존 단위 4일 사이클 공정을 확정한 후 예산을 산출하고 골조공사는 시공하는 시공사와 계약을 체결한 후 공사를 진행하는 과정으로 진행된다(S110).If the construction period is proper, a budget is calculated after the four-day cycle process of the zone unit is determined, and the frame construction is concluded with a construction contractor (S110).

도 8과 9는 본 발명에 따른 아파트 골조 평면분할의 존별 표준공정을 나타낸 것이다. 도 8과 9를 참조하면 아파트 골조 1개층을 4일에 완성하는 것이다. 하루는 오전, 오후, 저녁으로 세분화된다. 도 8은 하루가 아래로 내려가도록 작성한 공사일정이며, 도 9는 하루가 오른쪽으로 진행하도록 표기된 공사일정이다.8 and 9 illustrate a standard process for distinguishing an apartment frame plane division according to the present invention. Referring to FIGS. 8 and 9, one floor of an apartment frame is completed on the fourth day. The day is divided into morning, afternoon, and evening. FIG. 8 is a construction schedule written so that the day goes downward, and FIG. 9 is a construction schedule marked with the day progressing to the right.

먼저 0일차인 9월 30일에 8층의 바닥 콘크리트 타설이 이루어졌다. 그리고 1일차인 10월 1일에는 8층 바닥의 먹매김, 외부 벽체 형틀인 갱폼 인양, 벽체철근의 양중과 설치, 벽체에 설치되는 전기 설비 부품이 시공된다.On the first day of September 30th, 8 floor concrete was installed. On the first day of October 1, the earthen floor of the 8th floor, the gantry of the outside wall mold, the weight of the wall reinforcement and the installation of electrical equipment parts installed on the wall are constructed.

2일차인 10월 2일에는 슬라브 형틀을 설치하고 슬라브 철근을 야간에 양중해 놓는다. 슬라브 형틀은 작업량이 많아 하루 전체가 소요된다. On the second day, October 2, a slab frame is set up and slabs are placed at night. The slabs require a full day because of the heavy workload.

3일차인 10월 3일에는 어제 완료한 슬라브 형틀과 양중된 철근을 이용하여 슬라브 철근을 하루 전체 설치한다. 슬라브 철근이 설치되면 전기 설비 배관이나 부품이 슬라브에 설치된다. On the third day, Oct. 3, the slabs were completed by using the slabs and the reinforced bars that were completed yesterday. When the slab reinforcement is installed, the electrical equipment piping or parts are installed on the slab.

4일차에는 콘크리트를 타설하여 1개층 소형화 단위를 완성한다.On the 4th day, concrete is laid down to complete a one-story miniaturization unit.

아파트 101동 19층 소형화 단위 1과 2는 1일 내지 2일 차이로 진행된다. 이에 따라 철근, 형틀, 전기 설비, 콘크리트 작업자가 1과 2이로 이동하면서 연속적으로 쉬지 않고 작업을 하여 생산성을 높일 수 있게 된다.Apartment building 101, 19th floor Small-sized units 1 and 2 proceed by a difference of 1 day to 2 days. As a result, reinforcing bars, molds, electrical equipment, and concrete workers move to 1 and 2, so that they can work continuously without interruption to increase productivity.

도 10 내지 도 11은 본 발명에 의한 아파트 골조공사의 4일 사이클 공정을 갖는 경우의 층별 존별 공사일정의 예이다. 도 8을 참조하면, 10층에 4개 세대가 있는 경우로서, 평면을 2개 세대씩으로 2개 공사구역으로 분할한다. 첫 번째 공사구역인 A존에는 1001호와 1002호로 구성되며 19년 1월 1일부터 4일간 완성된다. 두번째 공사구역인 B존에는 1003호와 1004호로 구성되며 A존보다 2일차이로 늦게 진행된다. Figs. 10 to 11 are examples of construction schedule for the floor according to the present invention when the apartment frame construction has a four-day cycle process. Referring to Fig. 8, in the case where there are four generations on the 10th floor, the planes are divided into two construction zones by two generations. The first construction zone, A zone, consists of 1001 and 1002, and is completed for four days from January 1, 19. The B zone, which is the second construction zone, consists of 1003 and 1004, which is two days later than the A zone.

이에 따라 철근공사와 형틀공사, 전기 설비 공사와 콘크리트 공사가 겹치지 않고 A존과 B존이 번갈아 가며 시공된다. 이에 따라 작업자도 번갈아 가면서 작업을 수행하게 된다. 11층에서도 동일한 방식으로 진행되며 아파트 전체로 볼 때는 4일마다 한 층씩 공사가 진행된다. 아파트 1개층으로 2개 이상의 구역으로 분할하면 공사기간이 단축되는 것을 나타내고 있다. As a result, reinforced concrete construction, mold construction, electric installation construction and concrete construction do not overlap, and construction is carried out alternately between zone A and zone B. Accordingly, the worker performs work while alternately. The same goes for the 11th floor, and when you look at the apartment as a whole, construction is going on every four days. If one floor of an apartment is divided into two or more sections, the construction period is shortened.

도 12는 종래의 아파트 골조공사 방식으로서 층당 9일 사이클을 갖는 경우의 전체 공기를 나타낸 것이며 전체공기는 44개월 이다.Fig. 12 shows the total air in the case of a conventional apartment frame construction system having a cycle of 9 days per bed, and the total air is 44 months.

도 13은 본 발명에 의한 아파트 골조공사 휴무일 포함 층당 5일 사이클 골조공사의 갖는 경우의 전체 공기 도표의 일예이며 전체공기는 38.3개월이다. FIG. 13 is an example of the entire air chart in the case of the 5-day cycle frame construction per floor including the apartment frame construction work holiday according to the present invention, and the total air is 38.3 months.

도 14는 본 발명에 의한 아파트 평면분할의 존별 골조공사 방법과 종래의 골조공사의 방법과의 공사기간 차이를 비교한 도표이다. 49층 아파트 지상층 골조 공사에 있어서 종래의 층당 9일 공정과 본 발명에 따른 층당 5일 공정을 통해 전체 공사기간이 나타나 있다. FIG. 14 is a chart comparing the construction period difference between the method of constructing a zone frame of an apartment flat partition according to the present invention and the conventional frame construction method. The entire construction period is shown through the conventional 9-day process per floor and the 5-day process per floor according to the present invention in the construction of the 49-story apartment ground floor frame.

종래의 9일 사이클 공사방법에 따르면 전체 공사기간은 44개월이다. 본 발명에 따른 5일 사이클에 따르면 공사기간은 38.3개월로써 종래보다 골조공사 기간이 5.7개월 정도 단축된다. 본 발명의 공사방법에 따르면 전체공기의 15%의 단축되는 효과를 갖으며 이에 따라 프로젝트 비용 또한 절감된다. 시공사들은 같은 기간에 더 많은 프로젝트를 수행할 수 있어 생산성이 향상된다.According to the conventional 9-cycle construction method, the entire construction period is 44 months. According to the 5-day cycle according to the present invention, the construction period is 38.3 months, which is shorter than the conventional one by 5.7 months. According to the construction method of the present invention, the total air is reduced by 15%, thereby reducing the project cost. Contractors can be more productive during the same time period by performing more projects.

본 발명은 출원인이 기 출원한 철근콘크리트 구조를 갖는 고층 건축구조물의 시공방법(등록번호/일자 1006851470000 (2007.02.14))에서 정의한 존(구역), 공구분할 개념을 보다 명확히 발전시킨 것이다.The present invention is a clearer development of the concept of zone division and tool division defined in the construction method (registration number / date 1006851470000 (2007.02.14)) of a high-rise building having a reinforced concrete structure filed by the applicant.

다음은 본 발명에 의한 또 다른 실시예이다.The following is another embodiment according to the present invention.

아파트는 판상형과 타워형으로 구분된다. 판상형은 전면에 배치되는 공간이 많아 채광, 일조량이 우수하고 거실과 주방이 마주보는 형태로 맞통풍에 유리하다.The apartment is divided into a plate-type and a tower-type. Plate type has a lot of space to be placed on the front side, so it has excellent lighting and sunshine, and it is advantageous for ventilation in the form that the living room and the kitchen face each other.

통상 3베이 구조, 4베이 구조라고 이야기하는 평면은 판상형이다. 전면 배치 공간이 방-거실-방으로 3개면 3베이, 방-방-거실-방으로 4개면 4베이다. 주로 남향 위주로 배치되는 경우가 많아 자녀방, 거실, 안방 등에 빛이 잘 든다는 게 특징이다. 각 동이 'ㄱ'자 형태로 지어지는 경우가 많다. 아파트 동을 'ㅡ'자로 구성하는 것보다 'ㄱ'자로 구성할 때 가구수를 최대화 할 수 있기 때문에 대부분 아파트들이 'ㄱ'자로 설계된다.The planes that are usually referred to as a 3-bay structure and a 4-bay structure are plate-shaped. If the front layout space is 3 rooms in the room - living room - 3 rooms, 4 rooms in the room - room - living room - 4 rooms. In many cases, it is mainly oriented toward the south, and it is characterized by a good light in children's room, living room, and inner room. Each dong is often constructed in 'a' shape. Most apartments are designed as 'a' because they can maximize the number of households when they are composed of 'a' rather than 'ㅡ'.

도 15 내지 도 16은 본 발명에 의한 'ㄱ'자 판상형 아파트 기준층 골조공사 4일 싸이클 공사방법의 흐름도이다. FIGS. 15 to 16 are flowcharts of a 4-day cycle construction method of the 'A' self-supporting flat base layer construction work according to the present invention.

도 15를 참조하면, 판상형 공동주택 101동의 4세대 및 2개 코어로 구성된 기준층 평면을 2개의 존(A,B) 분할한다(S10). 즉, A존에는 101호, 102호와 코어 1번이 속한다. B존에는 103호와 104호 그리고 이에 속하는 코어 2번이 포함된다.Referring to FIG. 15, two zones (A, B) are divided into a reference layer plane composed of four generations and two cores of the plate-shaped apartment house 101 (S10). That is, the A zone includes 101, 102 and 1 core. The B zone includes 103 and 104, and Core 2, which belongs to it.

101동과 작업자 이동의 짝을 이루는 102동 4세대 및 2개 코어로 구성된 평면을 2개의 존(C,D)분할한다(S20). 상기 짝을 이루는 것은 공사관리의 대상을 그룹핑하는 것으로서 공구 개념을 포함이다.101, 102 and 104, which correspond to the movement of the worker, are divided into two zones (C, D) (S20). The pairing is a grouping of objects of construction management and includes the concept of tools.

101동 기준층 A존 골조공사를 1일차 착수하여 4일 만에 완료(각 층 4일 싸이클)한다(S30). 첫 번째 동인 101동 A존 (101호, 102호, 코어 1번)을 맨 먼저인 1일차에 시작한다.The project will be completed on the first day after completion of the A zone frame construction of the 101 baselines and completed in 4 days (each floor 4 days cycle) (S30). The first driver 101 starts in the first day of the A zone (101, 102, core 1).

102동 기준층 C존 골조공사를 2일차에 착수하여 4일만에 완료한다(S40).102 C standard frame C zone frame construction is completed on the second day and completed within four days (S40).

101동 기준층 B존 골조공사를 3일차 착수하여 4일만에 완료한다(S50).101 Base layer B frame construction is completed on the third day and completed within four days (S50).

102동 기준층 D존 골조공사를 4일차에 착수하여 4일만에 완료한다(S60).102 D zone frame construction on the base layer is completed on the fourth day and completed within four days (S60).

이상으로 101동과 짝을 이루는 102동의 기준층 1개층 골조공사가 4일만에 완료되었다. 예를들면 101동 9층과 102동 9층을 4개의 존으로 분할하고 월요일에는 101동 9층 A존, 화요일에는 102동 9층 C존, 수요일에는 101동 9층 B존 마지막으로 목요일에는 102동 9층 D존을 완료한다.As a result, construction of one layer of 102 baselines with 101 blocks was completed in 4 days. For example, 101st to 9th floor, 102nd to 9th floor will be divided into 4 zones. On Monday, 101nd floor, 9th floor A zone, 102nd floor and 9th floor C zone on Tuesday, 101nd floor and 9th floor B zone on Wednesday. The D zone on the 9th floor is completed.

위와 같은 방식으로 한 개층 골조가 완료되면, 그 윗층의 골조를 완성한다. 아파트는 일반적으로 28층 내지 49층 범위이다. 초고층인 경우 70층까지 시공되는 경우가 있다. 상기 4일 싸이클은 비작업일을 제외한 순수 작업일로서 working day를 의미한다.When the one-storey framing is completed in the above manner, the upper framing is completed. Apartments generally range from 28 to 49 floors. In the case of ultra-high-rise buildings, construction may be made up to 70 stories. The 4-day cycle is a pure working day excluding working days, which means working days.

도 16을 참조하면, 판상형 'ㄱ'자 공동주택 아파트 N동 4세대 및 2개 코어로 구성된 기준층 평면을 2개의 존(A,B) 분할한다(V10).Referring to FIG. 16, a floor of a 'A' apartment house is divided into two zones (A and B) consisting of 4th generation and 2 cores.

상기 N동과 작업자 순환 짝을 갖는 N+1동 4세대 및 2개 코어로 구성된 평면을 2개의 존(C,D)분할한다(V20). The N + 1 and N + 1 planes composed of the fourth generation and the two cores having the N copper and the worker rotation pair are divided into two zones (C, D) (V20).

층별 세대수는 5세대 또는 6세대 일 수도 있다.The number of households by floor may be 5th generation or 6th generation.

N동 기준층 골조공사를 4일 싸이클로 하여 A존과 B존은 2일 차이로 진행한다(V30).The N zone and the B zone will proceed by two days difference (V30) with the 4-day cycle of the base layer construction work.

N+1동 기준층 골조공사를 4일 싸이클로 하여 C존과 D존은 2일 차이로 진행한다(V40).The C zone and D zone of the N + 1 baseline frame construction are carried out on a 4-day cycle (V40).

상기 N동과 N+1동 기준층 골조공사는 1일차 또는 3일 차이로 진행한다(V50).The construction of the N and N + 1 co-operating basement skyscrapers is carried out by a difference of 1 day or 3 days (V50).

각 층 골조공사를 진행하고 그 윗층을 완성하는 싸이클을 반복한다(V60~V70).Repeat the cycle of constructing each flooring and completing the upstairs (V60 ~ V70).

예를 들어 첫 번째 동인 N동(101동) A존 (101호, 102호, 코어 1번)을 맨 먼저인 1일차에 시작한다.For example, start the first driver, N (101), A zone (101, 102, core 1) on the first day.

N+1동(102동) 기준층 C존 골조공사를 2일차에 착수하여 4일만에 완료한다.N + 1 building (102 buildings) Construction of the C zone frame on the base layer is commenced on the 2nd day and completed in 4 days.

N동(101동) 기준층 B존(103호, 104호, 코어 2번) 골조공사를 3일차 착수하여 4일만에 완료한다.N Dong (101 Dong) Base layer B zone (No. 103, No. 104, Core No. 2) The frame construction will be completed on the 3rd day and completed in 4 days.

N+1동(102동) 기준층 D존 골조공사를 4일차에 착수하여 4일만에 완료한다.N + 1 Dong (102 Dong) Base layer D zone construction work will be completed on the 4th day and completed in 4 days.

이상으로 101동과 짝을 이루는 102동의 기준층 1개층 골조공사가 4일만에 완료되었다. 예를 들면 101동 9층과 102동 9층을 4개의 존으로 분할하고 월요일에는 101동 9층 A존, 수요일에는 101동 9층 B존, 목요일에는 102동 9층 C존, 마지막으로 토요일에는 102동 9층 D존을 완료한다.As a result, construction of one layer of 102 baselines with 101 blocks was completed in 4 days. For example, 101st to 9th floor, 102nd to 9th floor are divided into 4 zones. On Monday, 101nd floor, 9th floor A zone, 101th floor, 9th floor B zone, 102nd floor, 9th floor C zone, Complete the D zone on the 9th floor of building 102.

위와 같은 방식으로 한 개층 골조가 완료되면, 그 윗층의 골조를 시공하는 공사를 반복하여 최상층까지 완성한다. Once the one-storey framing is completed in the same manner as above, the construction of the upper framing is repeated to complete the uppermost floor.

도 17 내지 도 19는 본 발명의 실시예 적용을 위한 판상형 아파트 공사의 예이다.17 to 19 show an example of a plate-shaped apartment construction for application of the embodiment of the present invention.

도 17을 보면, 대단지 아파트이며, 판상형이며 'ㄱ'자 형태이며, 한 개동의 평면은 4개의 세대와 코어부 2개로 구성된다. 층수는 29층 규모이다. 도면 중앙의 121동부터 123동의 평면을 보면, 'ㄱ'자 형태의 평면이며 4개 세대와 코어 2개로 구성되어 있으며 모서로 부분은 왼쪽인 남쪽을 향하고 있다. 이는 세대가 햇빛을 받기 위함이고 코어는 북쪽에 배치하여 햇빛을 가리지 않도록 하고 있다. Referring to FIG. 17, it is a large-size apartment, a plate-like shape and an 'a' shape, and the planar surface of one building consists of four generations and two core portions. The number of floors is 29 floors. In the center of the drawing, from the 121st to the 123rd planes, 'A' shaped plane is composed of four generations and two cores. This is to ensure that the generation is to receive sunlight and the core is located in the north to keep away the sunlight.

도 18을 참조하면, 2017년 하반기에 분양을 실시한 대단지 아파트 공사현장이며 판상형으로서 'ㄱ'자 형태의 평면에 일부 'ㅡ'자 형태의 평면이 추가되어 있다.Referring to FIG. 18, a large-scale apartment construction site, which was sold in the second half of 2017, is a plate-like type, and a plane having a shape of '?'

도 19를 참조하면 2017년 하반기에 분양을 실시한 대단지 아파트 공사현장이며 판상형으로서 'ㄱ'자 형태의 평면이다. 그러나 일부 동의 경우 대칭이 아닌 한쪽의 길이가 긴 'ㄱ'자 세대 배치를 나타내고 있다.Referring to FIG. 19, it is a large-scale apartment construction site where a sale is carried out in the second half of 2017, and is a plate-like shape, and is a 'A' shaped plane. However, in some cases, it is not symmetric, but it shows a long 'A' generation.

도 20 내지 21은 본 발명에 의한 판상형 아파트 1개동을 2개의 존으로 분할하고 각 존을 4일 싸이클에 존간에 2일차이 공정표이다.Figs. 20 to 21 are diagrams showing a two-day difference table in which zones of one flat-type apartment according to the present invention are divided into two zones and each zone is divided into zones in a four-day cycle.

도 20을 참조하면, 101동 A존은 1일차부터 4일차까지 4일만에 완성되고, 잔여 B존은 2일차로 진행된다. 101동 A존을 보면 1일차에는 먹매김, 갱폼인상 및 설치, 벽체 철근양중 후 벽체 철근을 시공하며 전기 설비가 벽체에 매립된다. 2일차에는 형틀(알폼)을 설치하고 슬라브 철근을 인양하다. 3일차에는 슬라브 철근과 전기 설비 자재를 시공한 후 4일차에는 콘크리트를 타설하여 1개층을 완성한다.Referring to FIG. 20, the A zone 101 is completed in four days from the first day to the fourth day, and the remaining B zone proceeds on the second day. In the 101st A zone, on the first day, the euphemism, the gang raising and installation, and the reinforced concrete wall are installed, and the electric equipment is embedded in the wall. On the second day, we put mold (mold) and salvage the slab reinforcement. On the third day, after constructing slab reinforcement and electrical equipment, concrete is placed on the fourth day to complete one layer.

도 21을 참조하면 101동 N층은 A존은 1일차부터 4일차까지 4일만에 완성되고, 5일차에는 그 윗층인 N+1층 공사가 시작되는 것을 나타낸다. 즉, 본 발명에 의한 판상형 아파트 1개동을 2개의 존으로 분할하고 4일 싸이클로 골조공사가 연속적으로 진행되는 표준 공정표이다. Referring to FIG. 21, the N zone 101 is completed in four days from the first day to the fourth day in the A zone, and the N + 1 layer construction is started in the fifth day. That is, this is a standard process table in which one building of a flat type apartment according to the present invention is divided into two zones and a 4-day cycle frame construction is continuously performed.

여기서 공사형태 및 여건에 따라 작업들은 상기 공정표와 비교하여 몇 시간 또는 반나절의 차이를 나타낼 수도 있으나 전반적인 흐름은 도 20 및 도 21과 같은 내용을 포함한다.Here, according to the construction type and conditions, the work may show a difference of several hours or half days compared with the above schedule table, but the overall flow includes contents as shown in FIGS. 20 and 21. FIG.

도 22는 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 1일차의 공정표이다.Fig. 22 is a process chart of the second day difference between the zone and the first day in the same house within the same town in the construction of the reference floor frame in the two flat-type apartments according to the present invention.

도 22를 참조하면, 101동내에서 A존과 B존은 2일차, 102동도 C존과 D존은 2일차이지만, A존(101동)과 C존(102동)은 1일 차이로 진행하는 공정표이다.Referring to FIG. 22, zone A and zone B are in the second day, zone 102 is in the second day, while zones A and B (zone 101) and zone C (zone 102) It is a milestone.

A존(101동)과 C존(102동)은 1일 차이로 진행하는 목적은 목수(형틀)와 철근 작업자의 균등한 출역 및 원활한 이동을 위해서이다. 4일 싸이클의 경우, 형틀과 철근의 일별 작업내용이 매일 다르므로 1일차, 2일차, 3일차에 따른 작업자 및 공사관리의 효율성도 다르기 때문이다.The A zone (101) and the C zone (102) are aimed at a one-day difference in order to move the molder (mold) and the steel worker evenly and smoothly. In the case of the 4-day cycle, since the daily work contents of the mold and the rebar are different from each other, the efficiency of the worker and the construction management according to the 1st day, the 2nd day and the 3rd day are different.

도 23은 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 3일차의 공정표이다.Fig. 23 is a process chart of the second day difference between the zone and the third day in the same house within the same building of the base layer frame construction in two planar type apartments according to the present invention.

도 23을 참조하면, 101동내에서 A존과 B존은 2일차, 102동도 C존과 D존은 2일차이지만, A존(101동)과 C존(102동)은 3일 차이로 진행하는 공정표이다.Referring to FIG. 23, zone A and zone B are located on day 2, zone 102 is on day 2, while zones A and B (zone 101) and zone C (zone 102) It is a milestone.

A존(101동)과 C존(102동)은 3일 차이로 진행하는 목적은 도 22와 마찬가지로 목수(형틀)와 철근 작업자의 균등한 출역 및 원활한 이동을 위해서이다. 4일 싸이클의 경우, 형틀과 철근의 일별 작업내용이 매일 다르므로 1일차, 2일차, 3일차에 따른 작업자 및 공사관리의 효율성도 다르기 때문이다.The purpose of the A zone (101) and the C zone (102) is to provide a three-day difference in order to move the carpenter (mold) and the steel worker equally and smoothly. In the case of the 4-day cycle, since the daily work contents of the mold and the rebar are different from each other, the efficiency of the worker and the construction management according to the 1st day, the 2nd day and the 3rd day are different.

도 24는 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사 동일한 동내에서 존간 2일차, 동간 1일차의 공사방법 설명도이다.Fig. 24 is an explanatory diagram of the construction method for the second day of the second day of stay and the first day of the same day in the same building in the same building construction of the base floor frame construction in two planar type apartments according to the present invention.

도 24를 참조하면, 101동 10층과 102동 10층을 4일만에 번갈아 가면서 콘크리트를 타설하여 완성하는 공사방법의 설명도이다.Referring to Fig. 24, there is an explanatory view of a construction method in which concrete is laid alternately in 10th, 10th, 102nd and 10th floors alternately in 4 days.

첫 번째 동인 101동 A존(101호, 102호, 코어 1번)을 맨 먼저인 1일차에 콘크리트를 타설한다.The first driver 101, A zone (No. 101, No. 102, core No. 1) is poured concrete on the first day.

102동 기준층 C존 골조공사를 2일차에 완료한다.102 The basement layer C zone frame construction is completed on the second day.

101동 기준층 B존 골조공사를 3일차에 완료한다.101 The basement layer B zone frame construction is completed on the third day.

102동 기준층 D존 골조공사를 4일차에 완료한다.102 The base layer D zone frame construction is completed on the fourth day.

위와 같은 방법으로 도 23의 공정표도 도 24와 같이 나타낼 수 있으며 표시는 생략한다.23 can be represented as shown in Fig. 24, and the display thereof is omitted.

도 25는 본 발명에 의한 판상형 아파트 2개동에 있어서 기준층 골조공사에서 동일한 동내에서 존간 2일차, 동간 1일차의 9층과 10층의 일별 공사방법 설명도이다.Fig. 25 is an explanatory diagram showing daily construction methods for the 9th and 10th floors of the second floor of the same floor in the same floor in the base floor frame construction in the two flat-type apartments according to the present invention.

도 25를 참조하면, 101동 9층과 102동 9층을 4일만에 번갈아 가면서 콘크리트를 타설하여 완성한 후 5일차 부터는 그 윗층인 10층을 반복적으로 진행하는 공사방법의 설명도이다.Referring to FIG. 25, the concrete is laid alternately in the 9th floor, the 102th floor, and the 9th floor alternately in 4 days, and then the 10th floor is repeated from the 5th day onwards.

첫 번째 동인 101동 9층 A존(101호, 102호, 코어 1번)을 맨 먼저인 1일차에 콘크리트를 타설한다.The first driver 101, the 9th floor A zone (101, 102, core No. 1) is put on the first day of the first concrete.

102동 9층 C존 골조공사를 2일차에 완료한다.102 building 9 floor C zone frame construction on the second day.

101동 9층 B존 골조공사를 3일차에 완료한다.101 building 9 floor B zone frame construction is completed on the third day.

102동 9층 D존 골조공사를 4일차에 완료한다.102 building 9 floor D zone frame construction is completed on the fourth day.

101동 10층 A존을 5일차에 콘크리트를 타설한다.Concrete is poured on the 5th day of the 101st building 10th floor A zone.

102동 10층 C존 골조공사를 6일차에 완료한다.102-10th floor C zone frame construction is completed on the sixth day.

101동 10층 B존 골조공사를 7일차에 완료한다.101 building 10th floor B zone frame construction is completed on the seventh day.

도 26은 본 발명에 의한 도 25의 판상형 아파트 1개동의 평면을 2개존으로 분할한 예로서 세대번호와 코어부를 상세하게 분할한 도면이다.Fig. 26 is a diagram dividing the generation number and the core part in detail, as an example of dividing the plane of one planar apartment of Fig. 25 according to the present invention into two living quarters.

도 26을 참조하면 101동 9층으로서 평면을 보면 세대는 901호, 902호, 903호, 904호의 4개 세대로 구성되고, 901호와 902호 현관으로 연결되는 코어 1번(엘리베이터 및 계단실)이 있다. 여기서 901호, 902호, 코어 1번을 A존으로 하여 4일만에 1개층 골조공사를 완료한다. 나머지 반대쪽인 B존은 2일 늦은 공정으로 진행하며 마찬가지로 4일 싸이클로 진행한다. Referring to FIG. 26, the 9th floor of building 101 is a floor, and the households are composed of four generations 901, 902, 903 and 904, and core 1 (elevator and staircase) connected by door 901 and door 902, . Here, 901, 902, and core 1 are set as zone A, and one-storey frame construction is completed in four days. The other side, the B zone, goes to the late process on the 2nd and proceeds to the 4th cycle in the same way.

도 26은 판상형 대칭형 아파트로서 'ㄱ'형태이며, 평면 분할의 경계는 'ㄱ'의 모서리 부분의 902호와 903호의 경계 벽체 라인이다. 이때 902호를 먼저 타설하는 경우, 존 분할 경계 벽체를 먼저 타설한다. 분할라인은 경계면의 길이가 짧은 끊어치기 길이가 가장 짧은 부분으로 하는 것이 바람직하다. FIG. 26 is a plate-shaped symmetrical apartment having a shape of 'A', and a boundary of a plane division is a boundary wall line of the 902 and 903 corners of the 'A'. In this case, if you put 902 first, put the zone dividing boundary wall first. It is preferable that the dividing line is a portion having the shortest breaking length with a short boundary surface.

102동도 101동과 같은 방법으로 분할하며, 존의 명칭은 C존과 D존으로 하여 101동과 구분한다. 따라서 101동과 102동은 A, B, C, D의 총 4개의 존으로 분할하고 각 존에는 2개 세대와 코어 1개로 구성되며 각 존은 1일 차이로 진행하되 4일 싸이클로 1개층 골조를 시공한다.The name of the zone shall be divided into C zone and D zone and shall be distinguished from 101 zone. So 101 and 102 are divided into 4 zones of A, B, C, and D, each zone consists of 2 generations and 1 core, each zone is a day difference, Construction.

도 27은 본 발명에 의한 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할한 예이다.Fig. 27 shows an example in which two pairs of plate-shaped apartments according to the present invention are divided into four living quarters of ABCD.

도 27을 참조하면, 상단 101동과 102동은 짝을 이루며 A, B, C, D의 4개존으로 구성된다. 상기 4개존은 층당 4일 싸이클로 진행되며 존별 1일차이로 진행된다. Referring to FIG. 27, the top 101 and 102 corners are paired and consist of four entities, A, B, C, and D. The four living quarters are conducted in a 4-day cycle per floor and proceed with a 1-day difference in the zone.

하단은 다른 공사현장의 평면 분할의 예시이다. 101동은 1호와 4호가 A존으로 구분되고, 2호와 3호 그리고 가운데 코어부가 B존으로 구분된다. 101동과 동일한 형태인 102동도 101동과 동일하게 분할한다. 101동과 102동은 형태가 유사하여 짝을 이루도록 하고 작업자가 101동과 102동을 옮겨 가면서 작업하는 것이 인원관리의 효율성이 높다. The lower part is an example of a flat division of another construction site. In section 101, the first and fourth sections are divided into A zones, and the second and third sections are divided into B zones. The same shall apply to the case of 101, 102, 101 and 102 are similar in shape, so that they are paired and the worker moves to 101 and 102, which is highly effective in personnel management.

103동은 1호와 3호가 A존으로 분할되어 동시에 시공되고, 2호와 코어가 B존으로 하여 시공된다. A존과 B존은 2일 차이로 시공되는 것이 바람직하다. 104동은 103동과 동일하게 분할하고 C존과 D존으로 명칭하며 103동과 104동은 짝을 이룬다.No. 103 is divided into No. 1 and No. 3 A zones, and construction is carried out simultaneously. No. 2 and core are constructed as zone B. It is preferable that the A zone and the B zone are constructed by a difference of two days. 104 is divided in the same way as 103, and is named C zone and D zone, and 103 and 104 are paired.

105동은 1호와 2호 그리고 코어부가 A존으로 분할되고 나머지 3호와 4호 및 코어부가 B존으로 분할된 예시이다. 106동도 105동과 마찬가지이다.105 is an example in which the core 1 is divided into 1 and 2, the core is divided into A zones, and the remaining 3 and 4 and the core is divided into B zones. It is the same as 105 Dong 105.

한편 101동부터 104동을 보면 A존의 세대가 좌우로 분리되어 있고, 중앙부에 B존이 있으며 2개 세대 또는 1개 세대임이 다른 평면과의 특징으로 나타나고 있다. 본 발명에서는 'ㄱ'자의 모서리 부분에 코어가 배치되는 경우인 판상형과 타워형의 혼합형 평면에 있어서도, 4일 공정 및 작업의 효율성을 위하여 평면 분할 방법의 가변성과 다양성을 포함하는 평면분할 방법을 101동 내지 104동의 예시를 통해 나타내고 있다. On the other hand, from the 101st to the 104th, the generation of A zone is divided into left and right, there is B zone in the center, and two generations or one generation is characterized by the other planes. In the present invention, even in the case of a plate-like and a tower-type mixed-type plane in which cores are arranged at corner portions of the letter 'A', a plane dividing method including the variability and diversity of the plane- To 104 consent examples.

도 28은 본 발명에 의한 또 다른 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할하고 4일 싸이클 시공의 예이다.Fig. 28 shows an example of four-day cycle construction in which two pairs of another flat type apartment according to the present invention are divided into four living quarters of ABCD.

도 28을 참조하면, 1일차에 103동 A존 콘크리트를 타설하고 2일차에 102동 C존 콘크리트를 타설하고, 3일차에 103동 B존 콘크리트를 타설하고, 4일차에 102동 D존 콘크리트를 타설하여 4일만에 2개동 1개층을 시공하는 싸이클 공사방법을 나타낸 것이다. 2개동의 1개층을 4일 싸이클로 시공하는 경우에서, 동을 번갈아 가면서 A C B D 순서로 시공하는 예시를 나타내고 있다.Referring to FIG. 28, 103-zone A-zone concrete was installed on the 1st day, 102-zone C zone concrete was installed on the 2nd day, 103-zone B zone concrete was installed on the 3rd day, 102-zone D zone concrete was installed on the 4th day It shows the construction method of constructing two buildings and one layer in four days after casting. In the case where one floor of two buildings is installed in a cycle of four days, an example is shown in which the buildings are alternately arranged in the order of A C D D.

도 29는 본 발명에 의한 또 다른 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할하고 4일 싸이클 시공의 평면도 및 단면도의 예로서 도 28 공사방법을 평면과 단면도에 동시에 나타낸 것이다.FIG. 29 is a plan view and a cross-sectional view showing the construction method of FIG. 28 as an example of a plan view and a sectional view of a four-day cycle construction, in which two pairs of another plate-shaped apartments according to the present invention are divided into four living quarters of ABCD.

도 30내지 도 40은 본 발명에 의한 판상형 아파트 2개동 짝을 ABCD의 4개존으로 분할한 후 24가지의 경우를 갖는 존별 공사순서 순열의 예이다.FIGS. 30 to 40 show an example of a construction work order sequence with 24 cases after dividing two pairs of the plate type apartments according to the present invention into four rooms of ABCD.

본 발명의 특징에 따르면 판상형 아파트 골조공사에 있어서, 'ㄱ'자 형태 또는 'ㅡ'자 형태의 아파트 평면을 갖는 경우, 2개동을 하나의 짝으로 하여 공사를 진행한다. 이때 2개동을 4개존의 존으로 분할하여 A존 B존 C존 D존을 1일 차이로 시공하는 경우, 존의 순서를 결정해야 한다. 존의 순서는 형틀 철근 콘크리트 등의 자재 수량(물량)과 이를 시공해야 하는 형틀(목수) 및 철근 전기 설비 콘크리트 작업자의 출역인원이 가장 합리적인 경우를 선택하는 것이 바람직하다. According to a feature of the present invention, in the case of a flat-type apartment building construction, if the apartment plan has an 'A' shape or a '-' shape, the construction is carried out with two pairs of buildings as one pair. In this case, when the two zones are divided into four zones, and zone A zone B zone C zone D zone is constructed by one day difference, the order of zone should be determined. It is preferable to select the case where the number of materials (quantity) of the molds, the reinforced concrete and the like, and the number of the workers who are to carry out the molds and the workers of the reinforced concrete equipment concrete worker are the most reasonable.

건설현장은 다른 산업과 달리 지역, 동수, 평면, 층수, 작업자, 재료 수량 등의 변수에 따라 각기 다른 특징을 갖는다. 따라서 존의 순서는 해당현장의 특성을 분석하여 결정하는 것이 바람직하다.Unlike other industries, construction sites have different characteristics depending on variables such as area, number of people, number of floors, number of workers, and quantity of materials. Therefore, it is desirable to determine the order of zones by analyzing characteristics of the site.

본 발명에서는 상기 2개동의 4개존을 1일 차이로 시공하는 순서를 분석하였다. 그 결과 4개존을 시공하는 경우의 수는 24가지이다. 기준층에서 한 번 존의 시공순서가 결정되는 계속해서 상층에서도 동일하게 반복될 것이므로 가장 합리적인 존의순서를 분석하고 결정하는 것이 성공적인 골조공사의 주요한 사항임을 본 발명의 특징에 따라 알 수 있다.In the present invention, the order of constructing the four entrances of the two buildings by one day difference was analyzed. As a result, there are 24 cases of construction of four survivors. It can be understood according to the characteristics of the present invention that it is important to analyze and determine the most reasonable sequence of zones since the construction sequence of the zone is determined once in the reference layer and the same process will be repeated in the upper layer.

먼저 도 30을 참조하면, 본 발명의 실시예에 따라 그림 하단에는 101동 A존과 B존, 102동에는 C존과 D존으로 분할되어 있다.Referring to FIG. 30, according to an embodiment of the present invention, the lower part of the figure is divided into A zone A and B zone 101, and C zone and D zone 102.

상기 4개 존의 1일차이로 시공하는 경우의 수는 순열로서 4가지 중 4개를 순서대로 선택하는 확률이며 총 24가지이다.The number of cases in which the construction is performed with the difference of 1 day in the above four zones is a probability of selecting 4 out of 4 in order as a permutation.

먼저 1번부터 6번까지는 18년 3월 12일 월요일에 101동 특정 기준층 A존 공사의 시작 또는 콘크리트를 타설하는 경우이다.First, from the 1st to the 6th, it is the start of the construction of the 101st building of the specific standard class A zone on Monday, March 12, 18, or the concrete is laid.

7번부터 12번까지는 18년 3월 12일 월요일에 101동 B존이 앞서가는 경우이다.From 7th to 12th, the 101st B zone leads the way on Monday, March 12th, 18th.

13번부터 18번까지는 18년 3월 12일 월요일에 102동 C존이 앞서가는 경우이다.From 13th to 18th, it is the case that 102nd C zone leads on Monday, March 12th, 18th.

19번부터 24번까지는 18년 3월 12일 월요일에 102동 D존이 앞서 시공해가는 경우이다.From 19th to 24th, it is the case that 102nd D zone is constructed earlier on Monday, March 12th, 18th.

18년 3월 14일 화요일 두 번째 날에는 1번부터 6번까지의 경우 101동 A존을 제외한 나머지 B C D존중 하나가 시공되는 경우이다.On the second day of Tuesday, March 14, 18, in the case of the 1st to 6th cases, one of the remaining B C D residence except for the A zone of 101 is applied.

위와 같은 방식으로 24가지 경우의 수에 대한 내용을 본 발명의 실시예로서 알 수 있다.As to the number of 24 cases in the above-described manner, it can be understood as an embodiment of the present invention.

도 31은 본 발명의 실시예에 따른 동과 존의 명칭 전체를 표기한 실시예이다.FIG. 31 is an embodiment showing the entire names of the zones and zones according to the embodiment of the present invention.

도 32는 본 발명의 실시예에 따른 존을 기준으로 시공 요일을 표기한 실시예이다.FIG. 32 is an embodiment showing a construction day on the basis of a zone according to an embodiment of the present invention.

도 33은 본 발명의 실시예에 따른 101동 A존의 시공일정을 표기한 실시예이다. 하단을 보면 요일별로 총 6가지 경우를 나타내고 있다.FIG. 33 is an embodiment showing the construction schedule of the 101st A zone according to the embodiment of the present invention. In the lower part, 6 cases are shown by day.

도 34는 본 발명의 실시예에 따른 101동 B존의 시공일정을 표기한 실시예이다. 하단을 보면 요일별로 총 6가지 경우를 나타내고 있다.FIG. 34 is an embodiment showing the construction schedule of the 101st B zone according to the embodiment of the present invention. In the lower part, 6 cases are shown by day.

도 35는 본 발명의 실시예에 따른 102동 C존의 시공일정을 표기한 실시예이다. FIG. 35 is an embodiment showing the construction schedule of the 102nd C zone according to the embodiment of the present invention.

도 36은 본 발명의 실시예에 따른 102동 D존의 시공일정을 표기한 실시예이다. FIG. 36 is an embodiment showing the construction schedule of the 102nd D zone according to the embodiment of the present invention.

도 37은 본 발명의 실시예에 따른 층별 존별 4일 싸이클의 공사일정을 표기한 실시예이다. 경우의 수 1 내지 4가 표시되어 있다. 경우의 수 1번 101동 A존이 12일에 5층을 착수하여 계속 4일 싸이클로 윗층으로 진행하고 있다. 여기서 일요일, 명절, 날씨 등의 비작업일을 제외한 순수작업일(working day, 워킹데이)만을 기준으로 나타낸 예시이다.FIG. 37 is a view showing a construction schedule of a 4-day cycle according to an embodiment of the present invention. The number of cases 1 to 4 is shown. Number of occasions No. 1, No. 101 A zone started on the 5th floor on the 12th and continues to the upper floor of the 4th cycle continuously. Here, it is an example showing only pure working days excluding working days such as Sunday, holidays, and weather.

다음으로 경우 1에서 두 번째 존인 101동 B존은 두 번째 날인 13일(화)에 5층을 시작한다. C존읜 14일(수)에 5층을 시작하고 D존은 15일(목)에 5층을 시작한다. 따라서 ABCD 4개존은 1일차이로 진행하는 것이 경우 1이다.Next, the second zone 101, which is the second zone in case 1, starts on the 5th floor on the second day (Tuesday). C Zone On the 14th (Wed), the 5th floor starts and the D zone starts on the 15th (Thur) on the 5th floor. Therefore, ABCD 4 is a case 1 where the difference is 1 day difference.

경우 2는 ABDC, 경우 3은 ACBD로 진행하는 것을 나타내고 있다.Case 2 indicates progression to ABDC, Case 3 progresses to ACBD.

도 38은 본 발명의 실시예에 따른 도 37의 경우에서 4일차인 콘크리트 타설만을 표기한 것이다.FIG. 38 is a view showing only a concrete installation of four days in the case of FIG. 37 according to the embodiment of the present invention.

도 39는 본 발명의 실시예에 따른 층별 존별 4일 싸이클의 공사일정을 표기한 실시예이다. 경우의 수 18 내지 21이 표시되어 있다. 경우 18은 C존이 앞서가고, 경우 19부터는 D존이 가장 앞서가는 경우이다.FIG. 39 is a view showing a construction schedule of a four-day cycle according to an embodiment of the present invention. The number of cases 18 to 21 is shown. In case 18, the C zone goes ahead, and in case 19, the D zone leads the most.

도 40은 본 발명의 실시예에 따른 도 39의 경우에서 4일차인 콘크리트 타설만을 표기한 것이다.FIG. 40 is a view showing only a concrete installation of four days in the case of FIG. 39 according to the embodiment of the present invention.

이상과 같이 본 발명에서는 판상형 아파트 골조공사에 있어서, 'ㄱ'자 형태 또는 'ㅡ'자 형태를 갖는 경우, 2개층을 짝으로 하여 4개의 존으로 분할하고 24가지 ABCD존 시공순서와 4일 싸이클 공정과 일별 세부 공정을 나타내었다. As described above, according to the present invention, in the case of the 'A' shape or the '-' shape in the case of the plate-shaped apartment frame construction, the two layers are mated into four zones and the 24 ABCD zone construction sequence and the 4 day cycle Process and day-by-day detailed process.

본 발명의 목적은 판상형 'ㄱ'자 형태 또는 'ㅡ'자 아파트 기준층 골조공사를 4일 싸이클로 완성하는 것이다. 그 방법은 아파트 공사단위를 소형화하여 공사방법 및 작업자 출역 및 이동의 융통성과 효율성을 높이는 것이다. 또한 평면분할과 순차적 시공의 소형화 및 연속화 방법을 통해 날씨 및 공휴일 등에 의한 영향을 최소화하고 자재 납품 회사의 상태 및 공사에 투입되는 작업자들의 근무시간 및 사회적 업무 인식 형태에 변화에 따른 적응성과 가변성을 크게 높이는 것이다. The object of the present invention is to complete a 4-day cycle of a floor-type 'a' shaped or 'ㅡ' apartment base layer structure construction. The method is to miniaturize the unit of the apartment building to increase the flexibility and efficiency of the construction method and worker moving and moving. In addition, through the miniaturization and sequencing method of planar division and sequential construction, it is possible to minimize the influence of weather and holidays, and to adapt to the change of the worker's working time and social work perception type It is the height.

구체적으로는 아파트 2개동을 짝으로 하여 평면을 2개존으로 분할하여 2개동 총 4개존을 구성한다. 4개존의 시공순서는 24가지가 발생하며 그 중 하나 또는 혼합으로 진행하며 존별 1일차이로 진행하는 공사방법을 포함한다.Specifically, the apartment is divided into two living quarters with two apartments in pairs, and a total of four living quarters are constructed. There are 24 kinds of construction orders of the four survivors, including one or a mixture of them.

본 발명에 따른 효과는 골조공사를 작업일 기준 4일 싸이클로 완성하여 공기를 단축되며 작업자의 출역 손실이 최소화되며 소규모 공사의 빠른 반복으로 인한 학습효과 습숙효과를 통해 작업생산성을 크게 높아지며, 골조공사 공기를 단축하고 인력 장비 자재 관리비 금융비용 등의 제반 공사비가 낮아진다. 또한 안정되고 연속적이고 반복적인 작업에 따라 품질 및 안전성이 높아진다.The effect according to the present invention is to shorten the air by completing the frame construction with a cycle of 4 days as a work day, minimizing the worker's service loss and greatly improving work productivity through the effect of learning effect due to rapid repetition of small construction, And the construction cost of manpower equipment, material management costs, etc. will be lowered. In addition, the quality and safety are enhanced by stable, continuous and repetitive work.

아파트 골조공사를 업으로 하는 건설기술자들은 본 발명의 목적 및 사상을 기반으로 일부 변형 등을 통해서도 목적과 효과를 달성할 수 있음을 명백히 알 수 있을 것이다.It will be apparent to those skilled in the art that the construction of an apartment framework can achieve the objects and effects of the present invention based on the object and spirit of the present invention.

Claims (13)

아파트, 주상복합, 오피스텔, 지식산업센터의 내력 벽식 구조를 갖는 골조공사에 있어서,
1개동의 평면을 2개 또는 3개의 공사구역으로 분할하여 콘크리트 타설 구역을 소형화하는 제1단계 ;
분할된 공사구역에 대하여 1개층의 시공 수량을 산출하는 제2단계 ;
상기 시공 수량의 설치에 필요한 작업인원을 산출하는 제 3단계 ;
상기 공사구역의 구역의 골조를 완성하는데 소요되는 작업시간을 산출하는 제4단계 ; 및
상기 층당 작업시간이 4일 이내인지를 검증하는 제5단계 ;
로 이루어져 평면을 분할하고 공사구역을 소형화하여 공사속도를 빠르게 하는 것을 특징으로 하는 내력벽식 골조공사의 공사방법
In the frame construction with the proof wall structure of apartment, apartment complex, office tower, and knowledge industry center,
A first step of dividing a flat plane into two or three construction zones to reduce the size of the concrete slab zone;
A second step of calculating a construction quantity of one layer with respect to the divided construction area;
A third step of calculating a number of workers required for installing the construction water;
A fourth step of calculating a working time required to complete the frame of the space of the work space; And
A fifth step of verifying whether the working time per layer is within 4 days;
, And the construction speed is increased by miniaturizing the construction area by dividing the flat surface.
아파트, 주상복합, 오피스텔, 지식산업센터의 내력 벽식 구조를 갖는 골조공사에 있어서,
1개동의 평면을 2개 또는 3개의 존(구역)으로 분할하여 콘크리트 타설 구역을 소형화하는 제1단계 ;
첫번째 존(구역)에 있어서 1일차에 먹매김, 벽체형틀 설치, 벽체 철근 설치, 벽체 전기 설비 부품 설치에 대하여 주요작업을 시공하는 제2단계 ;
2일차에 슬라브 형틀 설치하는 제3단계 ;
3일차에 슬라브 철근 설치 및 전기 설비 부품을 설치하는 제4단계 ; 및
4일차에 콘크리트를 타설하는 제5단계 ;
로 이루어져 평면분할을 통한 공사구역의 소형화로 공사속도를 빠르게 하는 것을 특징으로 하는 내력벽식 골조공사의 공사방법
In the frame construction with the proof wall structure of apartment, apartment complex, office tower, and knowledge industry center,
A first step of dividing the plane of one operation into two or three zones (zones) so as to miniaturize the concrete installation area;
The second stage is the construction of the main works on the 1st zone in the first zone (installation), installation of the wall frame, installation of the wall reinforcement, and installation of wall electric parts;
A third step of installing a slab mold on the second day;
A fourth step of installing the slab reinforcement on the third day and installing the electric equipment parts; And
A fifth step of pouring concrete on the fourth day;
And the construction speed is increased by miniaturization of the construction area through the planar division.
아파트, 주상복합, 오피스텔, 지식산업센터의 내력 벽식 구조를 갖는 골조공사에 있어서,
평면을 2개 내지 4개의 공사구역으로 분할하여 공사물량을 소형화하는 제1단계 ;
첫번째 공사구역에 있어서, 골조공사를 4일에 시공하는 과정으로 진행하는 제2단계 ;
두번째 공사구역은 첫 번째 공사구역과 1일 또는 2일의 차이로 진행하는 제3단계 ; 및
작업자가 첫번째 공사구역과 두번째 공사구역을 번갈아가며 이동하면서 작업하거고 콘크리트를 타설하는 제 4단계 ;
로 이루어져 작업 대기시간을 발생을 방지하고 작업자의 연속적인 작업으로 공사를 빠르게 진행하는 것을 특징으로 하는 내력벽식 골조공사의 공기단축 방법
In the frame construction with the proof wall structure of apartment, apartment complex, office tower, and knowledge industry center,
A first step of dividing a plane into two to four construction zones to reduce the amount of construction work;
A second step of constructing the frame construction on the fourth day in the first construction site;
The second construction zone is the third stage, which is a difference of 1 day or 2 days from the first construction zone; And
A fourth step of the worker moving alternately between the first construction site and the second construction site while working and pouring the concrete;
To prevent the occurrence of waiting time for work and to promptly carry out the construction work by the continuous work of the worker.
아파트, 주상복합, 오피스텔, 지식산업센터의 내력 벽식 구조를 갖는 골조공사에 있어서,
평면을 2개 내지 4개의 공사구역으로 분할하고 철근설치 형틀설치 콘크리트를 타설함에 있어서 컨스트럭션 죠인트는 1일 타설 가능 콘크리트 물량 조건 등 콘크리트, 철근, 형틀 등의 작업물량 밸런스를 최대한 충족시키면서도 건물 외장에 영향을 최소화 시킬 수 있는 부위에 수밀기능을 충족시키는 디테일을 적용하여 설치하는 것을 특징으로 하는 공사방법
In the frame construction with the proof wall structure of apartment, apartment complex, office tower, and knowledge industry center,
Plane is divided into 2 to 4 construction areas, and reinforced concrete frame is installed. Concrete joint can be installed for 1 day. Concrete water condition conditions It is possible to meet the balance of work such as concrete, steel bar, And a detail that satisfies the watertight function is applied to the portion where the watertightness function can be minimized.
아파트, 주상복합, 오피스텔, 지식산업센터의 내력 벽식 구조를 갖는 골조공사에 있어서,
평면을 2개 또는 3개의 공사구역으로 분할하여 철근 및 형틀을 시공하고 콘크리트를 타설함에 있어서 다수의 세대 조합에서 콘크리트의 물량의 밸런스를 맞추기 어려운 경우에는 중앙세대를 버퍼존으로 하여 중앙세대의 좌우측에 컨스트럭션 조인트를 형성시킴으로써 버퍼존을 포함한 좌측 2세대 또는 버퍼존을 포함한 우측 2세대를 묶어 콘크리트를 타설 가능토록 융통성을 부여함으로써 공사 인력 및 장비의 효율을 극대화함으로써 더욱 더 공사 진행을 촉진시키는 것을 특징으로 하는 내력 벽식 구조 공사방법
In the frame construction with the proof wall structure of apartment, apartment complex, office tower, and knowledge industry center,
In the case where it is difficult to balance the amount of concrete in a plurality of generation assemblies in the construction of reinforcing bars and molds by dividing the planes into two or three construction zones, it is difficult to balance the amount of concrete in the plurality of generation assemblies, By forming a construction joint, it is possible to tie two generations on the left, including the buffer zone, or the second generation, including the buffer zone, to allow concrete to be laid so as to maximize the efficiency of construction manpower and equipment. Construction method of wall structure
내력 벽식 구조를 갖는 공동주택, 주상복합, 오피스텔 동(건물)의 평면이 'ㄱ'자 또는 'ㅡ' 일자 형태의 판상형 구조를 포함하는 2개 이상의 동(건물)의 건설공사의 골조공사에 있어서,
2개 동을 짝(한 벌, 한 쌍)으로 설정하고 상기 첫 번째 동과 두 번째 동의 평면을 2개의 존(Zone, 구역)으로 각각 분할(존닝)하여 총 4개의 존으로 분할하는 제1단계 ;
상기 4개 존의 시공순서를 순열로서 분석하여 순서를 결정하고 각 존은 4일 싸이클로 시공하며, 각 존간의 일정차이는 적어도 1일 이상으로 진행하는 경우를 포함하는 제2단계 ;
1개층이 시공되면 그 상향층을 제3단계의 4일 싸이클로 시공하는 과정을 되풀이하여 골조를 상향으로 완성해가는 과정을 포함하는 제3단계 ;
로 이루어져 2개동을 4개존으로 분할하고 4일 싸이클 공정을 포함하여 공사속도를 빠르게 하는 것을 특징으로 하는 벽식 구조를 갖는 복수동의 골조공사 방법
In the construction of two or more buildings (construction) of a building with a proof wall structure, a residential complex, an office building, and a flat structure of a flat type having a flat shape of 'ㄱ' or 'ㅡ' ,
A first step of dividing the first copper and the second copper plane into two zones (zones) by dividing the copper and the copper into two zones (one pair and one pair), and dividing the first copper and the second copper plane into two zones ;
A second step of analyzing the construction sequence of the four zones as a permutation sequence to determine a sequence, each zone being constructed in a cycle of four days, and a predetermined difference between the zones progressing to at least one day;
A third step of repeating the process of constructing the upper layer by a cycle of 4 days in the third step when the one layer is constructed, and completing the frame upwards;
, And dividing the two buildings into four living quarters and accelerating the construction speed including the four-day cycle process.
제 6항에 있어서,
상기 2개 동을 짝으로 설정하고 상기 첫 번째 동과 두 번째 동의 평면을 2개의 존으로 각각 분할하는 단계는,
상기 건물(동)의 평면이 'ㄱ'자 형태의 경우, 'ㄱ'자의 모서리 부분의 세대 경계 또는 대칭평면이 중간지점을 존의 경계로 분할하는 단계와,
상기 건물(동)의 평면이 'ㅡ' 일자 형태의 경우, 동 중간 부분의 세대 경계 또는 중간지점 부근을 존으로 분할하는 단계를 더 포함하는 것을 특징으로 하는 벽식 구조를 갖는 복수동의 골조공사 방법.
The method according to claim 6,
Wherein the step of dividing the first copper and the second copper plane into two zones, respectively,
If the plane of the building is in the 'a' shape, dividing the intermediate point into the boundaries of the zone of the generation border or symmetry plane of the corner portion of the 'a'
Further comprising the step of dividing the generation boundary or the vicinity of the intermediate point of the intermediate portion into zones when the plane of the building is in the form of a dash.
제 6항에 있어서,
상기 2개 동을 짝으로 설정하고 상기 첫 번째 동과 두 번째 동의 평면을 2개의 존으로 각각 분할하는 단계는,
각 동이 4개의 세대와 2개의 코어부로 구성되는 경우,
각 동에 있어서 2개 세대와 코어부 1개를 첫 번째 존으로 하고 나머지 잔여 2개 세대와 코어부 1개를 두 번째 존으로 분할하는 단계를 더 포함하는 것을 특징으로 하는 벽식 구조를 갖는 복수동의 골조공사 방법
The method according to claim 6,
Wherein the step of dividing the first copper and the second copper plane into two zones, respectively,
When each copper is composed of four generations and two core portions,
And dividing the remaining two generations and one core section into a second zone with two generations and one core section as a first zone in each copper, and dividing the remaining two generations and one core section into a second zone. Construction method of frame
제 6항에 있어서,
상기 4개 존의 시공순서를 순열로서 분석하여 순서를 결정하고 단계는,
상기 2개동의 4개존에 공사순서에 있어서 4개존의 순열인 24개 경우 중 적어도 하나 이상의 순서로 시공하는 단계를 더 포함하는 것을 특징으로 하는 벽식 구조를 갖는 복수동의 골조공사 방법
The method according to claim 6,
Determining a sequence by analyzing the construction sequence of the four zones as a permutation,
Further comprising a step of constructing at least one of the 24 cases of four quadrants in the order of construction in the four quadrants of the two quadrants,
제 6항에 있어서,
각 존을 4일 싸이클로 시공하며, 각 존간의 일정차이는 적어도 1일 이상으로 진행하는 단계는,
2개동의 1개층 4개존을 4일 싸이클로 시공하는 경우로써
첫 번째 존은
1일차에 벽체 철근과 형틀을 설치하는 단계 ;
2일차에 슬라브 형틀을 설치하는 단계 ;
3일차에 슬라브 철근을 시공하는 단계 ;
4일차에 콘크리트를 타설하는 단계
두 번째 존은
2일차에 벽체 철근과 형틀을 설치하는 단계 ;
3일차에 슬라브 형틀을 설치하는 단계 ;
4일차에 슬라브 철근을 시공하는 단계 ;
5일차에 콘크리트를 타설하는 단계
세 번째 존은
3일차에 벽체 철근과 형틀을 설치하는 단계 ;
4일차에 슬라브 형틀을 설치하는 단계 ;
5일차에 슬라브 철근을 시공하는 단계 ;
6일차에 콘크리트를 타설하는 단계
네 번째 존은
4일차에 벽체 철근과 형틀을 설치하는 단계 ;
5일차에 슬라브 형틀을 설치하는 단계 ;
6일차에 슬라브 철근을 시공하는 단계 ;
7일차에 콘크리트를 타설하는 단계를 포함하되 상기 일별 단계는 공휴일, 날씨에 따른 비 작업일을 포함하지 않은 순수작업일(working day)을 포함하며, 또한 상기 일별 시공단계는 벽체 및 슬라브에 있어서 형틀, 철근의 주요한 물량을 시공하는 단계를 더 포함하는 것을 특징으로 하는 벽식 구조를 갖는 복수동의 골조공사 방법
The method according to claim 6,
Each zone is constructed with a 4-day cycle, and the difference between the zones is at least one day,
It is a case where one floor of 4 buildings and 4 buildings of 2 buildings are installed in 4 days cycle.
The first zone
Installing a wall reinforcing bar and a mold frame on the first day;
Installing a slab mold on the second day;
Constructing the slab reinforcement on the third day;
Steps to cast concrete on day 4
The second zone
Installing a wall reinforcing bar and a mold frame on the second day;
Installing a slab mold on the third day;
Constructing the slab reinforcement on the fourth day;
Steps to cast concrete on the 5th day
The third zone
Installing a wall reinforcing bar and a mold frame on the third day;
Installing a slab frame on the fourth day;
Constructing a slab reinforcement on the fifth day;
Steps to cast concrete on the 6th day
The fourth John
Installing a wall reinforcing bar and a mold frame on the fourth day;
Installing a slab mold on the 5th day;
Constructing the slab reinforcement on the 6th day;
Wherein the daily step includes a pure working day that does not include holidays and non-working days according to the weather, and wherein the daily construction step includes the steps of: The method of claim 1, further comprising the step of:
제 6항에 있어서,
1개층이 시공되면 그 상향층을 제3단계의 4일 싸이클로 시공하는 과정을 되풀이하여 골조를 상향으로 완성해가는 단계는,
기준층에 대상으로 공휴일, 날씨에 따른 비 작업일을 포함하지 않은 순수작업일(working day)이며 일부 층 또는 존은 공사 여건에 따라 5일 싸이클로 진행하는 단계를 더 포함하는 것을 특징으로 하는 벽식 구조를 갖는 복수동의 골조공사 방법
The method according to claim 6,
When one layer is applied, the step of constructing the upward layer by repeating the process of constructing the upper layer by the 4-day cycle of the third step is repeated,
The method according to any one of claims 1 to 6, further comprising the step of: operating the base layer on a working day that does not include holidays and weather days, A method of constructing multiple frames
내력 벽식 구조를 갖는 공동주택, 주상복합, 오피스텔 공사에서 동의 평면이 'ㄱ'자 또는 'ㅡ' 일자 형태의 판상형 구조를 포함하는 2개 이상의 동(건물)의 골조공사에 있어서,
상기 복수동에 있어서 2개동을 한 개의 짝으로 설정하고 첫 번째 동과 두 번째 동의 평면을 2개의 존(구역)으로 각각 분할하여 총 4개의 존으로 분할하는 제1단계 ;
기준층의 1개층에 있어서
첫 번째 동의 첫 번째 존과 두 번째 존을 2일 차이로 시공하는 제2단계 ;
두 번째 동의 첫 번째 존과 두 번째 존을 2일 차이로 시공하는 제3단계 ;
첫 번째 동과 두 번째동을 1일 차이 또는 3일 차이로 시공하는 제4단계 ;
상기 2 내지 4단계는 각 존을 순수 작업일 기준 4일 싸이클 공정으로 시공하고 완료후에는 윗층에서 시공하는 과정을 되풀이하여 골조를 완성해가는 제5단계 ;
로 이루어져 하고 복수 동의 골조공사를 신속하게 완성하는 것을 특징으로 하는 복수 동의 골조공사 방법.
In the frame construction of two or more buildings (buildings) including a plate-like structure with a plane of 'A' or 'ㅡ' in the apartment house, residential complex, or office building having a proof wall structure,
A first step of dividing the first copper and the second copper plane into two zones (zones) and dividing the two copper lines into a total of four zones;
In one layer of the reference layer
A second step of constructing the first zone and the second zone by two days difference;
A third step of constructing the first zone and the second zone of the second agreement with a difference of two days;
A fourth step of constructing the first and second phases by a difference of 1 day or 3 days;
In the steps 2 to 4, each zone is constructed by a 4-day cycle process based on a pure working day, and after completion, the process of constructing the upper zone is repeated to complete the frame.
And a plurality of bridge frames are quickly completed.
내력 벽식 구조를 갖는 공동주택, 주상복합, 오피스텔 공사에서 동의 평면이 'ㄱ'자 또는 'ㅡ' 일자 형태의 판상형 구조를 포함하는 2개 이상의 동(건물)의 골조공사에 있어서,
상기 복수동에 있어서 2개동을 한 개의 짝으로 설정하고 첫 번째 동과 두 번째 동의 평면을 2개의 존(구역)으로 각각 분할하여 총 4개의 존으로 분할하는 제1단계 ;
상기 4개의 존의 순서를 순열의 경우의 수로서 분석하는 제2단계 ;
상기 순열중 적어도 하나의 경우를 선택하는 제3단계 ;
상기 선택된 순열 경우에서 첫 번째 존을 시공하는 제4단계 ;
두 번째부터 네 번째 존은 각각 적어도 1일 차이 이상으로 진행하는 제5단계 ;
상기 제4단계 내지 5단계는 순수 작업일 기준 4일 싸이클 공정의 범위에서 시공하고 해당 층 완료후에는 윗층에서 시공하는 과정을 되풀이하여 골조를 완성해가는 제5단계 ;
로 이루어져 하고 복수 동의 골조공사를 분할하여 신속하게 완성하는 것을 특징으로 하는 복수 동의 골조공사 방법.
In the frame construction of two or more buildings (buildings) including a plate-like structure with a plane of 'A' or 'ㅡ' in the apartment house, residential complex, or office building having a proof wall structure,
A first step of dividing the first copper and the second copper plane into two zones (zones) and dividing the two copper lines into a total of four zones;
A second step of analyzing the order of the four zones as the number of permutations;
A third step of selecting at least one of the permutations;
A fourth step of constructing a first zone in the selected permutation case;
A fifth step of proceeding from the second zone to the fourth zone by at least one day difference;
The fourth step to the fifth step are performed in the range of the 4-day cycle process based on the pure water working day, and the step of constructing the upper layer after completion of the layer is completed to complete the frame;
And a plurality of bridge frame construction is divided and completed promptly.
KR1020180041575A 2017-10-02 2018-04-10 Structure construction method for multiple buildings with wall structure KR102619713B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020230191903A KR20240004188A (en) 2017-10-02 2023-12-26 Structure construction method for multiple buildings with wall structure

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR20170128482 2017-10-02
KR1020170128482 2017-10-02

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020230191903A Division KR20240004188A (en) 2017-10-02 2023-12-26 Structure construction method for multiple buildings with wall structure

Publications (2)

Publication Number Publication Date
KR20190038984A true KR20190038984A (en) 2019-04-10
KR102619713B1 KR102619713B1 (en) 2023-12-29

Family

ID=66163960

Family Applications (4)

Application Number Title Priority Date Filing Date
KR1020180041575A KR102619713B1 (en) 2017-10-02 2018-04-10 Structure construction method for multiple buildings with wall structure
KR1020180117335A KR20190039011A (en) 2017-10-02 2018-10-02 Construction method for wall and slab type structured building
KR1020180117336A KR20190039012A (en) 2017-10-02 2018-10-02 Analysis device for constructing frame of building for calculating number of worker and method for the same
KR1020230191903A KR20240004188A (en) 2017-10-02 2023-12-26 Structure construction method for multiple buildings with wall structure

Family Applications After (3)

Application Number Title Priority Date Filing Date
KR1020180117335A KR20190039011A (en) 2017-10-02 2018-10-02 Construction method for wall and slab type structured building
KR1020180117336A KR20190039012A (en) 2017-10-02 2018-10-02 Analysis device for constructing frame of building for calculating number of worker and method for the same
KR1020230191903A KR20240004188A (en) 2017-10-02 2023-12-26 Structure construction method for multiple buildings with wall structure

Country Status (1)

Country Link
KR (4) KR102619713B1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847593A (en) * 2019-11-14 2020-02-28 南通大学 Construction process of gradient curved surface bare concrete wall based on BIM technology
KR102263190B1 (en) 2020-11-09 2021-06-09 파인건설(주) Method for frame construction
KR102263191B1 (en) 2020-11-09 2021-06-09 파인건설(주) Method for frame construction
KR20230150089A (en) * 2022-04-21 2023-10-30 쿠팡 주식회사 Operating method for electronic apparatus for providing information and electronic apparatus supporting thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100685147B1 (en) * 2006-04-27 2007-02-22 한봉길 Construction method for rc structured high rise building
KR101315946B1 (en) * 2012-05-08 2013-10-08 삼성물산 주식회사 Rc construction method for concrete lining in parallel

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100685147B1 (en) * 2006-04-27 2007-02-22 한봉길 Construction method for rc structured high rise building
KR101315946B1 (en) * 2012-05-08 2013-10-08 삼성물산 주식회사 Rc construction method for concrete lining in parallel

Also Published As

Publication number Publication date
KR20240004188A (en) 2024-01-11
KR20190039012A (en) 2019-04-10
KR20190039011A (en) 2019-04-10
KR102619713B1 (en) 2023-12-29

Similar Documents

Publication Publication Date Title
Wakisaka et al. Automated construction system for high-rise reinforced concrete buildings
US7665250B2 (en) System for construction of a compression structure with corner blocks, key blocks, and corner block supports
KR20190038984A (en) Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings
Bari et al. Environmental awareness and benefits of industrialized building systems (IBS)
O’Brien VPM scheduling for high-rise buildings
Tam et al. Use of prefabrication to minimize construction waste-a case study approach
EP1971727B1 (en) Construction of buildings
CN110869568B (en) Improvements in reinforced concrete wall modules for building ventilation in general and special industrial building systems
Safa et al. A decision-making method for choosing concrete forming systems
CN105839784B (en) Assembled jacking type construction techniques
CN112431416A (en) Workshop building method capable of effectively shortening construction period and workshop built by same
Ikeda et al. Application of the automated building construction system using the conventional construction method together
KR20230169923A (en) An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
Chaudhary Study of tunnel formwork system & comparative analysis with conventional formwork
Bari et al. Industrialised Building Systems (IBS): It's attribute towards enhancing sustainability in construction
Saeedi et al. Study the Effects of Constructions New Techniques and Technologies on Time, Cost and Quality of Construction Projects from the Perspective of Construction Management
Oleinik et al. Optimization of parameters for the construction of prefabricated residential buildings
Heineck et al. Transparency in building construction: a case study
Shalgar et al. Introduction to advanced tunnel formwork system: case study of ‘Rohan-Abhilasha’
KR20190038985A (en) Method of structural work zoning and construction sequence for minimizing of daily labour attendance
Hamada et al. Development of automated construction system for high-rise reinforced concrete buildings
RU2336399C1 (en) Method for rebuilding of large-panel apartment house
Wright Industrialized Building in the Soviet Union:(a Report of the US Delegation to the USSR)
Marfella et al. The Logic of Rapid Extrusion Produces the “Jumping” Phoenix
Latorre Zaplana Study and Constructive Analysis of Deinze’s New City Hall

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant